Professional Documents
Culture Documents
L3 Project Planning
L3 Project Planning
Project Planning
LESSON 3
Content
• Project Initiation
• Overview of Project Planning
• Weighted Decision Matrix
• Financial Considerations
• Scope Planning
• Project Requirements
• Scope Inputs
• Work Breakdown Structure
Project Initiation
• The project initiation phase is the first phase within the project management life cycle, as
it involves starting up a new project.
• Within the initiation phase, the business problem or opportunity is identified, a solution is
defined, a project is formed, and a project team is appointed to build and deliver the
solution to the customer.
• A business case is created to define the problem or opportunity in detail and identify a
preferred solution for implementation.
Project Initiation
• The business case includes:
• A summarized plan for implementation that includes a schedule and financial analysis
Project Initiation
• The need for establishing clear project objectives cannot be overstated.
• Ideally, if an objective is clear, you can show it to five people who, after reviewing it, hold
a single view about its meaning. The best way to make an objective clear is to state it in
such a way that it can be verified.
• Realism is introduced because the people who will do the work have a good sense of
what it takes to accomplish a particular task.
• In addition, this process assures some level of commitment on all sides: management
expresses its commitment to support the work effort and workers demonstrate their
willingness to do the work.
• Imagine an office manager has contracted a painter to paint his office. His goal or
objective is to have the office painted a pleasing blue colour. Consider the conversation
that occurs after the job was finished.
Project Initiation
Overview of Project Planning
• The project planning phase is a challenging phase for a project manager, as you need to
make an educated guess about the staff, resources, and equipment needed to complete
your project.
• You may also need to plan your communications and procurement activities, as well as
contract any third-party suppliers.
• Scope Planning – specifying the in-scope requirements for the project to facilitate
creating the work breakdown structure
• Preparation of the Work Breakdown Structure – spelling out the breakdown of the
project into tasks and sub-tasks
• Project Schedule Development – listing the entire schedule of the activities and
detailing their sequence of implementation
• Resource Planning – indicating who will do what work, at which time, and if any
special skills are needed to accomplish the project tasks
Overview of Project Planning
• Risk Management – planning for possible risks and considering optional contingency
plans and mitigation strategies
• Users will often begin describing their objectives in qualitative language. The project
manager must work with the user to provide quantifiable definitions to those qualitative
terms.
Example 2
• Let’s say that your company is going to produce a holiday batch of eggnog. Your
objective statement might be stated this way: Christmas Cheer, Inc. will produce two
million cases of holiday eggnog, to be shipped to our distributors by October 30, at a
total cost of $1.5 million or less.
• The objective criteria in this statement are clearly stated and successful fulfillment can
easily be measured. Stakeholders will know that the objectives are met when the two
million cases are produced and shipped by the due date within the budget stated.
Overview of Project Planning
When articulating the project objectives you should follow the SMART rule:
• Specific – get into the details. Objectives should be specific and written in clear,
concise, and understandable terms.
• Measurable – use quantitative language. You need to know when you have successfully
completed the task.
• Time-based – deadlines not durations. Objectives should have a time frame with an end
date assigned to them.
If you follow these principles, you’ll be certain that your objectives meet the quantifiable
criteria needed to measure success.
Overview of Project Planning
When articulating the project objectives you should follow the SMART rule:
• Specific – get into the details. Objectives should be specific and written in clear,
concise, and understandable terms.
• Measurable – use quantitative language. You need to know when you have successfully
completed the task.
• Time-based – deadlines not durations. Objectives should have a time frame with an end
date assigned to them.
If you follow these principles, you’ll be certain that your objectives meet the quantifiable
criteria needed to measure success.
Weighted Decision Matrix
• To select the best option, we can use tools such as a Weighted Decision Matrix.
Weighted Decision Matrix is more advanced than Basic Decision Matrix.
• A Basic Decision Matrix consists of establishing a set of criteria for options that are
scored and summed to gain a total score that can then be ranked. Importantly, it is
not weighted to allow a quick selection process.
• The advantage of the Weighted Decision Matrix is that subjective opinions about one
alternative versus another can be made more objective. Another advantage of this
method is that sensitivity studies can be performed.
Weighted Decision Matrix
• A Weighted Decision Matrix allows decision makers to structure and solve their
problem by:
• The sample in the next page shows a Weighted Decision Matrix that compared three
options for a web development project (SJS Enterprises).
• This method is especially useful when choosing purchase alternatives and comparing
them against specific desirable system requirements.
Weighted Decision Matrix
Weighted Decision Matrix
Financial Considerations
• In many new project endeavors, we need to find out if our project is financially feasible.
We do that by using Net Present Value (NPV), Rate of return (ROI), and payback
analysis.
Financial Considerations
NPV
• A dollar earned today is worth more than a dollar earned one or more years from now.
The NPV of a time series of cash flows, both incoming and outgoing, is defined as the
sum of the present values (PVs) of the individual cash flows of the same entity.
• In the case when all future cash flows are incoming and the only outflow of cash is the
purchase price, the NPV is simply the PV of future cash flows minus the purchase
price (which is its own PV). NPV is a standard method for using the time value of
money to appraise long-term projects.
• Used for capital budgeting and widely used throughout economics, finance, and
accounting, it measures the excess or shortfall of cash flows, in present value terms,
once financing charges are met.
Financial Considerations
• NPV can be described as the “difference amount” between the sums of discounted
cash inflows and cash outflows.
• It compares the present value of money today to the present value of money in the
future, taking inflation and returns into account.
• The NPV of a sequence of cash flows takes as input the cash flows and a discount
rate or discount curve and outputs a price.
• Each cash inflow/outflow is discounted back to its present value (PV). Then they are
summed. Therefore, NPV is the sum of all terms.
Financial Considerations
Where:
• i is the discount rate (the rate of return that could be earned on an investment in
the financial markets with similar risk; the opportunity cost of capital)
• Rt is the net cash flow (i.e., cash inflow − cash outflow, at time t)
Video
Insert Text Here Insert Text Here Insert Text Here Insert Text Here
https://www.youtube.com/watch?v=cSAfp6D28RM
Financial Considerations
• NPV is an indicator of how much value an investment or project adds to the firm. With
a particular project, if NPV is a positive value, the project is in the status of positive
cash inflow in the time t.
• If NPV is a negative value, the project is in the status of discounted cash outflow in the
time t. Sometimes risky projects with a positive NPV could be accepted.
• This does not necessarily mean that they should be undertaken since NPV at the cost
of capital may not account for opportunity cost (i.e., comparison with other available
investments).
• In financial theory, if there is a choice between two mutually exclusive alternatives, the
one yielding the higher NPV should be selected.
Financial Considerations
Present Value Table (Take note of the decreasing value of money as the period increases from 1 to 10 years.)
Financial Considerations
NPV Example
• The following example is calculating the NPV of a project at a discount rate of 12%. The
project takes five years to complete with given benefits and costs for each year.
• In Year 0, there is no benefit to the organization, just an initial cost of $75,000 with no
discount rate.
• In Year 1, the discount rate is 89%. This means that at 12% assumed interest, the time
value of money says that the $1 today is worth $0.89 in one year, $0.80 in two years, etc.
• By calculating the NPV for the benefits and the costs, you subtract the NPV of all costs
from the NPV of all benefits. The final result is a positive value of $105,175.
Table of NPV of costs and benefits
Financial Considerations
ROI
• This is calculated by subtracting the project’s costs from the benefits and then dividing by
the costs. For example, if you invest $100 and your investment is worth $110 next year,
the ROI is (110 − 100) ÷ 100 = 0.1 or a 10% return.
• Payback analysis is important in determining the amount of time it will take for a project
to recoup its investments.
• This is the point at which the benefits start to outweigh the costs. The best way to see
that is by charting the cumulative benefits and costs.
• In the next diagram, the cumulative benefits outweigh the cumulative costs in the second
year.
Financial Considerations
Financial Considerations
Project Charter
• Provide an understanding of the project, the reason it is being conducted, and its
justification
• Establish the project manager and his or her authority level. A note of who will review and
approve the project charter must be included.
• They describe the required functionality that the final deliverable must have or specific
conditions the final deliverable must meet in order to satisfy the objectives of the project.
Project Requirements
Functional Requirements
• They should be understandable to the customers, and the customers should play a direct
role in their development. Functional requirements are what you want the deliverable to
do.
Example:
• If you were buying vehicles for a business, your functional requirement might be:
“The vehicles should be able to take up to a one-tonne load from a warehouse to a
shop.”
• For a computer system you may define what the system is to do: “The system should
store all details of a customer’s order.”
Project Requirements
Non-Functional Requirements
• Non-functional requirements specify criteria that can be used to judge the final product or
service that your project delivers. They are restrictions or constraints to be placed on the
deliverable and how to build it.
• Their purpose is to restrict the number of solutions that will meet a set of requirements.
Using the vehicle example, the functional requirement is for a vehicle to take a load from
a warehouse to a shop.
• Without any constraints, the solutions being offered might result in anything from a small
to a large truck. Non-functional requirements can be split into two types: performance
and development.
Project Requirements
To restrict the types of solutions, you might include these performance constraints:
Similarly, for the computer system example, you might specify values for the generic types
of performance constraints:
• The response time for information is displayed on the screen for the user.
• The number of hours a system should be available.
• The number of records a system should be able to hold.
• The capacity for growth of the system should be built in.
• The length of time a record should be held for auditing purposes.
Project Requirements
Similarly, for the computer system example, you might specify values for the generic types
of performance constraints:
• The response time for information is displayed on the screen for the user.
• The number of hours a system should be available.
• The number of records a system should be able to hold.
• The capacity for growth of the system should be built in.
• The length of time a record should be held for auditing purposes.
Business Requirements
• Business requirements are the needs of the sponsoring organization, always from a
management perspective.
• They are usually expressed in broad outcomes, satisfying the business needs, rather
than specific functions the system must perform. These requirements grow out of the
vision for the product that, in turn, is driven by mission (or business) goals and
objectives.
Project Requirements
User Requirements
• User requirements describe what the users need to do with the system or product. The
focus is on the user experience with the system under all scenarios.
• These requirements are the input for the next development phases: user-interface
design and system test cases design.
Regulatory Requirements
• They are the restrictions, licenses, and laws applicable to a product or business that are
imposed by the government.
Scope Inputs
The project manager gathers initial project facts from the project charter. In addition,
background information on the stakeholder’s workplace, existing business model and rules,
etc. assist in creating the vision of the final product/service, and consequently, the project
scope.
Scope Inputs
Techniques
Gathering requirements is part of scope definition, and it can be done using one or more of
following techniques:
• Interviews
• Focus groups
• Facilitated groups such as JAD (joint application development)
• Group creativity techniques: brainstorming, nominal groups, delphi, mind map, affinity
diagnostics
• Prototyping
• Observation
• Questions and surveys
• Group decision-making techniques: unanimity, majority, plurality, dictatorship
Scope Inputs
• The requirements traceability matrix is a table that links requirements to their origin and
traces them throughout the project life cycle.
• It provides a means to track requirements throughout the project life cycle, helping to
ensure that requirements approved in the requirements documentation are delivered at
the end of the project.
Scope Inputs
Finally, it provides a structure for managing changes to the product scope. This process
includes, but is not limited to, tracking:
• In a project or contract, the WBS is developed by starting with the end objective and
successively subdividing it into manageable components in terms of size, duration, and
responsibility (e.g., systems, subsystems, components, tasks, subtasks, and work
packages), which include all steps necessary to achieve the objective.
Work Breakdown Structure
• Listing all the project outputs (deliverables and other direct results)
• Identifying all the activities required to deliver the outputs
• Subdividing these activities into subactivities and tasks
• Identifying the deliverable and milestone(s) of each task
• Identifying the time usage of all the resources (personnel and material) required to
complete each task
Work Breakdown Structure