0.IM 15 Plant and Equipment Procedure
0.IM 15 Plant and Equipment Procedure
Document:
Reference: IM 15
IMS PROCEDURE
IC- EHS
Prepared by G Divakar 13.01.2021
Compliance Head
Michael William
Reviewed by IC-EHS Head 13.01.2021
Sanderson
Revision History:
INDEX
1 Introduction
2 Purpose
3 Scope
4 Definitions
5 Responsibilities
6 Procedure
---------------------------------------------------------------------------------------------------------------------------
A Attachments/Appendices
Nil
B Abbreviations
As L&T Heavy Civil Infrastructure IC moves towards a zero harm vision through the
L&T L.I.F.E. program, there requires a management game changing shift and a
complete gradual overhaul of what was done in the past so as to meet the current
business model.
L&T Heavy Civil & Infrastructure IC, engage Plant & Equipment in-house and
outsourced from contractors for the project execution works across HCI-IC. This
procedure is designed to ensure all Cranes, Vehicles & Earth Moving
Equipment(including own, hired and sub-contractor’s) and comply with L&T HCI-IC
IM Procedures, CHESS, Client’s and Legal requirements during project execution.
2. PURPOSE
This procedure is intended to define the EHS requirements and expectations that
shall be attained and implemented by our L&T and Sub-Contractor’s Plant &
Equipment and Electrical Installations, the main objectives are:
• To engage suitable L&T and Sub-contractors P&M Vehicles on the projects.
• Monitor & Evaluate equipment fitness of L&T & Sub-Contractor’s regularly.
• Allow and Reject those equipment which is fit and unfit respectively.
3. SCOPE
This procedure shall be applicable to L&T Heavy Civil & Infra IC Project Site’s all
Cranes, Vehicles & Earth Moving Equipment (including Own, hired and sub-
contractor’s) and all Electrical Installations at site.
Electrical Installations:
An electrical installation is a combination of electrical equipment installed from a
common electrical supply to fulfill a particular purpose. Electrical Installation cover a diverse
Green Card:
Green Card is a sticker type card / tag. Such card shall be displayed over the vehicles or
equipment which is declared “FIT FOR USE”. It is advisable to be made in such a manner that
it can be stuck to the vehicle from inside the wind screen. “Green Card” should have Vehicle
or equipment ID no, date of inspection and validity and signed jointly by P&M and EHS I/c.
Red Card:
Red Card is a sticker type card / tag. Such card shall be displayed over the vehicles or
equipment which is declared “UNFIT FOR USE”
“Hazardous Wastes”
It means any waste which by reason of any of its physical, chemical, reactive, toxic,
flammable, explosive or corrosive characteristics causes danger or is likely to cause danger to
health or environment, whether alone or when in contact with other wastes or substances.
IC Head Shall:
Ensure sound, competent Sub-contractors and Hired Plant & Machinery are only
IC Head
engaged on the projects.
Empower the Project Manger to remove the Sub-contractors and Hired Plant &
Machinery from site if he found “Unfit”.
IC EHS Head shall:
IC EHS
HEAD
Develop Plant & Machinery procedure in consistent with EHS Policy and legal
requirements.
Communicate to HCI-IC and all BUs, Clusters and Projects for implementation.
Procurement Head Shall (As per Approval limit):
Communicate EHS pre-qualification requirements to the sub-contractors.
(Annexure -1 of IM 30 Procedure).
IC-Procurement Head
They shall be responsible to engage only those Plant and Machinery, Equipment and
Construction
In-charge
Vehicles which are certified fit by both P&M and EHS I/c and have valid “Green card”
display.
In addition they shall be also responsible for identifying any unsafe condition of
Plant and Machinery, Equipment and Vehicles and to declare such items as “Not
Fit”. They should inform the P &M & EHS I/c also about such P&M Equipment.
Project Head shall:
Project Head
Ensure that sub-contractor’s employees/plant and equipment meet all the EHS
requirements prior to mobilization on project.
Discuss sub-contractor performance during monthly EHS coordination meeting and
suggest areas for improvement.
Project P&M In charge shall:
Project P&M
Shall be responsible for joint EHS inspection of all the Plant and Machinery,
Equipment and Vehicles. After ascertaining their performance worthiness, “Green
Card” shall be issued.
Shall also be responsible for periodical inspection for identifying EHS deficiencies
related to P&M.
Carry out necessary rectification/Periodic Maintenance to the Plant and Equipment.
Ensure this LOTO procedure is implemented across the project.
Ensure their employees wear appropriate PPE according to the nature of the
hazards.
Report any incidents and near misses to project EHS in-charge.
Ensure their plant and equipment are inspected/certified prior to use and
maintained periodically.
Participate in Risk assessment and incident investigation process whenever project
requires.
Ensure competent operators, drivers and riggers are engaged for the job.
6. PROCEDURE
OK
During the day to day operation ‘daily checklist’ procedure has to be followed for the
safe and productive operation of the following mentioned equipment and vehicle:-
Cranes (moveable or stationery), Lift and Reach Equipment.
Vehicles
Winches
Passenger hoist / cage /lift
Material hoisting equipment
DG set
Rolling Cutting and Bending m/c
Compressor & Air receiver
Plants – Batching Plant/ Crushing Plant etc.
The vehicle or equipment has to be checked daily (at the beginning of each shift / shift
change) as per the check list by the respective operator / driver and then only it is to be
engaged for productive activity. If the operator was unable to read the English
language, then the checklist to be made in the local language as known to the
driver/operator. In case any malfunctioning of any Plant & Equipment, the
operator/driver has to consult with concerned in charge. The mal-function shall be
removed immediately by suitable repairs or maintenance works.
The checklist has to be signed by the driver / operator and the same has to be kept in a
plastic folder inside the cabin so that on demand it can be verified.
The immediate supervisor has to have periodic supervisory review (at least once a
week) on this checklist and he/she has to countersign on the Checklist. The entire
process has to be monitored by P&M or EHS I/C or regular basis.
The P&M In charge, should ensure that contractors engaged at site should undertake
maintenance are managed as per the requirements. The frequency of the maintenance
program will depend on:
• Legislative requirements;
• Manufacturer recommendations and requirements;
• Results of the Plant and Equipment inspection record;
• Plant and equipment breakdown/failure rates.
All the Electrical and Mechanical Services and Maintenance shall be carried out with
the Lock out and Tag out System. Lockout/ Tag out procedures must be documented
and made available to authorized employees for their use. E.g., Batching plant Mixing
Chamber cleaning activities. Activities that take place during normal operation are
exempt unless the employee is required to bypass a guard or place part of their body in
harm’s way.
The Plant and Equipment shall comply with HCI-IC IMS procedure, CEHSS, Project EHS
policy & plans, Client’s requirements and Legal requirements all the times.
Licensing Requirements requires the operator of certain items of plant and equipment
to hold a relevant license. P&M should ensure that all operators of plant and equipment
required to be licensed are identified as per the Induction and Training Procedure. A
photocopy of the current licence must be collected by the P&M dept. /EHS dept. and
retained with the training records.
Certain Plant and Equipment to be registered under legislation. Examples of plant which
must be registered include:
• Air receivers
• Pressure vessels
• Boilers
• Tower cranes/ Other cranes
• Ice Plant
• Batching Plant for CTO/CTE from Pollution Board.
For more information refer to the Register of Regulations, IM 07- Legal and Other
Requirements.
A. Attachments/Appendices:
Nil
____________________ _____________________
(P&M Engineer) (EHS Engineer)
IM-15-Plant & Equipment Rev.02, Dt: 13.01.2021 Page 1 of 1
Environment, Health and Safety
Integrated Management System Manual
IM Format No. : 15 B
Sl.
Check Points Observation Remarks
No.
1 Engine condition
2 Clutch / brake
3 Hydraulic System
4 Guards / Covers / Doors
5 Fastener lock pins / Keys.
6 Horn / Reverse horn / Lights/
7 Indicators / Wiper Blades
8 Operators fitness
9 Tyre pressure
10 Condition of Battery and Lamps
11 Operating levers / steering
12 Gauges & warning devices
13 Fire extinguisher Provided
14 First Aid Box
15 Swing Alarm Provided
16 Validity of PUC Certificate
17 Validity of Fitness Certificate
18 Delay Start Mechanism
This Vehicle/ Earth Moving Equipment has been checked for the above points and
__________________ ___________________
(P&M Engineer) (EHS Engineer)