Professional Documents
Culture Documents
CP&M - Lec 7 Scheduling & Bar Chart
CP&M - Lec 7 Scheduling & Bar Chart
CP&M - Lec 7 Scheduling & Bar Chart
Non-Network Network
Techniques Techniques
AON
Network Diagrams
Scheduling Techniques
Activity
A task or a work component of the project which has some
time period and consumes the resources for its completion.
Event
• It is a Milestone of any activity.
• Starting point or Ending point of an activity.
Gantt Chart
• A GANTT chart is a type of bar chart that illustrates
a project schedule.
• After the PERT/CPM analysis is completed, the
following phase is to construct the GANTT chart
and then to re-allocate resources and re-schedule if
necessary.
• GANTT charts have become a common technique
for representing the phases and activities of a
project work breakdown structure.
• It was introduced by Henry Gantt around 1910 –
1915.
7
Building a Gantt Chart
• List all tasks and milestones from the
project along the vertical axis
• List time frame along the horizontal axis
Activity 1
Activity 2
Milestone
2-Aug-22
Building a Gantt Chart
• Activities: Create box the length of each activity time
duration
– E.g., activity one is scheduled from day1-day3
Activity 1
Activity 2
2-Aug-22
Building a Gantt Chart
• Dependencies: Show dependencies between
activities with arrows
– E.g., activity 2 cannot start until activity 1 is complete
Activity 1
Activity 2
2-Aug-22
GANTT CHART
• Planned program is shown by thick line
• Actual progress is shown by thin line
• The float is shown by dotted lines
• The dependencies of one work on another is represented by dotted
vertical lines
Sequence of Activities of The Project -
House Building
Number Activity Predecessor Duration
1 Design house and obtain -- 3 months
financing
2 Lay foundation 1 2 months
2-Aug-22
Gantt Chart for House Building Project using QM for Windows
Activity A has no predecessor activity. i.e., It is the first activity. Let us suppose that
activity A takes the project from event 1 to event 2.
For activity B, the predecessor activity is A. Let us suppose that B joins nodes 2 and 3.
Bar Charts
Immediate Predecessor activity
22
Gantt Chart
Advantages
Simple
Good visual communication to others
Task durations can be compared easily
Good for scheduling resources
Easy to create and comprehend
Easy to understand
Activities can be easily handled
Coding can make more explanatory charts
Suitable for small works
Disadvantages
Dependencies are more difficult to visualise
Minor changes in data can cause major changes in the chart
Difficult for long project
Dependencies are difficult to analyse
Critical path cannot be identified easily
Different alternate paths are difficult
23 to choose
DHA, OVERHEAD WATER TANK SCHEDULING
Equipment Schedule
Labour Schedule
Materials Schedule
Financial Schedule
TASK
• Prepare bar chart for different construction projects i.e. Building,
roadwork, dams, tunnel structure, bridges etc.
• Prepare equipment schedule for 4 different commercial buildings,
started at same time. The total project duration is 6 months. Assume
necessary equipment resources yourself.