Rohan Builders (i) Pvt.Ltd.

Job Safety Analysis

DSM Engineering - MIDC Ranjangaon

TASK : - Dressing, Levelling, PCC, CONTRACTOR: Rohan Builders JOB No.:

SUPERVISOR : Mr. Himanshu, Mr. Vijay LOCATION :Cooling Tower [Utility] Date: 02-10-07

JOB STEP HAZARDS Control Measure ACTION


Break the job into steps. List the hazard or type of harm List the necessary control measures to be followed to Person who will ensure
Listing work which may be hazardous. identified with each step eliminate the identified hazards this happens

Dressing/Levelling By Manually Cut Hazard/Hit Hazard Inspected Tools & Tackles to be provided.

Tool box talk to be given and recorded before


start the work Deepak Nimbalkar

Continuous supervision to be provided.

PCC work
Entry to be restricted inside the Batching Plant
operator room other than the operator and the
Mini Batching Plant Electrocution electrician.

Only authorised operator is allowed to operate.

Proper ear thing to be given and all the


connections to be provided through ELCB only.

This document is current at -2007/10


Rohan Builders (i) Pvt.Ltd.

Job Safety Analysis

Electrician have to use rubber hand gloves


(tested & trade mark) while working/testing on
charged equipments.

Identification boards to be displayed.

Moving parts/Trip hazard All the moving parts to be guarded and no


loose clothing allowed near the
machinery/conveyors.

Un authorised entry to be restricted.

CO2 fire extinguisher to be provided.


Fire Hazard

Nose Mask provided for those who engaged on


Dust Hazard cement work.

Eye Hazard Safety Goggles to be provided for all those who


are engaged on the work.

Transit Mixer

Placing of Transit Mixer Mobile Plants/Hit Hazard Documents of the vehicle to be checked and
certified.

Valid licence for the driver.

This document is current at -2007/10


Rohan Builders (i) Pvt.Ltd.

Job Safety Analysis

Head light, Tail light, Reverse horn to be


checked.

Proper access to be provided by clearing all


unwanted materials or traffic to enter the work
Vehicle movement/Cut hazard space.

Helper to be provided for controlling the traffic


by signal.

Vehicle to be placed with the help of the helper.

Daily check for the equipment and the check


list to be fulfilled.

Continuous supervision to be provided.

For Shifting of concrete to the area proper


access to be given to avoid trip hazard
PCC work by manually Trip hazard
Concrete to be poured on concrete tray and
those who are doing the filling work & those
Person Injury who are standing on the concrete will be
provided with gumboots and rubber hand
gloves other than mandatory PPE’s.

This document is current at -2007/10


Rohan Builders (i) Pvt.Ltd.

Job Safety Analysis

Proper House keeping will be provided to


avoid cut injury/ Trip Hazard

House keeping Trip hazard/Cut hazard Daily tool box talks to be followed & recorded.

Work area should kept neat & clean after the


completion of work.

All the scraps to be to shifted to the specified


scrap area.

Remove all the materials used for shuttering


from the work area and shifted to the yard as
soon as the de-shuttering work ends or
properly stacked at the work place for reuse.

Proper illumination to be provided at the work


area as per required or depends on the work.

Working at night Inadequate illumination

This document is current at -2007/10


Rohan Builders (i) Pvt.Ltd.

Job Safety Analysis

Job Safety analysis attendees D. Nimbalkar, Mr.Himanshu. Mr. Vijay Date


02-10-07
Written by T.Haque

This document is current at -2007/10