This project schedule outlines the repair of exhaust stacks at the Alaoji Gas Turbine facility over 18 tasks across 12 weeks. The project will involve erecting scaffolding around each of the 4 gas turbine exhaust stacks (GT-1 through GT-4), preparing the surface, painting, and then dismantling the scaffolding for each stack individually. Key dates include mobilizing on September 19th, completing scaffold dismantling and demobilization by November 11th, and a total project duration of 45 weeks.
This project schedule outlines the repair of exhaust stacks at the Alaoji Gas Turbine facility over 18 tasks across 12 weeks. The project will involve erecting scaffolding around each of the 4 gas turbine exhaust stacks (GT-1 through GT-4), preparing the surface, painting, and then dismantling the scaffolding for each stack individually. Key dates include mobilizing on September 19th, completing scaffold dismantling and demobilization by November 11th, and a total project duration of 45 weeks.
This project schedule outlines the repair of exhaust stacks at the Alaoji Gas Turbine facility over 18 tasks across 12 weeks. The project will involve erecting scaffolding around each of the 4 gas turbine exhaust stacks (GT-1 through GT-4), preparing the surface, painting, and then dismantling the scaffolding for each stack individually. Key dates include mobilizing on September 19th, completing scaffold dismantling and demobilization by November 11th, and a total project duration of 45 weeks.
PROJECT TITLE NDPHC Alaoji - Exhaust stack repair COMPANY NAME Trifecta Integrated Services
PROJECT MANAGER Ikechukwu Onyejekwe DATE 9/7/22
ALAOJI GAS TURBINE EXHAUST STACKS CORROSION CONTROL
WBS NUMBER TASK TITLE START DATE DUE DATE DURATION WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5 WEEK 6 WEEK 7 WEEK 8 WEEK 9 WEEK 10 WEEK 11 WEEK 12 M T W T F M T W T F M T W T F M T W T F M T W T F M T W T F M T W T F M T W T F M T W T F M T W T F M T W T F M T W T F