ID Task Task Name Duration Start 09 OctFinish

'22 16 Oct '22 23 Oct '22


Mode T F S S M T W T F S S M T W
1 Data poliklinik 7 days Fri 14/10/22 Mon 24/10/22
2 Id_poliklinik 6 days Fri 14/10/22 Fri 21/10/22
3 Nama_poliklinik 5 days Fri 14/10/22 Thu 20/10/22
4 Huruf 4 days Fri 14/10/22 Wed 19/10/22
5 Cara bayar 3 days Fri 14/10/22 Tue 18/10/22
6 Status_perkawinan 2 days Fri 14/10/22 Mon 17/10/22
7 Golongan_darah 1 day Fri 14/10/22 Fri 14/10/22
8 Alamat 7 days Fri 14/10/22 Mon 24/10/22
9 Pekerjaan 6 days Fri 14/10/22 Fri 21/10/22
10 Agama 5 days Fri 14/10/22 Thu 20/10/22
11 Umur 4 days Fri 14/10/22 Wed 19/10/22
12 Tgl_lahir 3 days Fri 14/10/22 Tue 18/10/22
13 Nama_pasien 2 days Fri 14/10/22 Mon 17/10/22
14 No_rm 1 day Fri 14/10/22 Fri 14/10/22
15 Data_pasien 7 days Fri 14/10/22 Mon 24/10/22
16 Data_petugas 6 days Fri 14/10/22 Fri 21/10/22
17 Id_petugas 5 days Fri 14/10/22 Thu 20/10/22
18 Username 4 days Fri 14/10/22 Wed 19/10/22
19 Password 3 days Fri 14/10/22 Tue 18/10/22
20 Data_dokter 2 days Fri 14/10/22 Mon 17/10/22
21 Spesialis 1 day Fri 14/10/22 Fri 14/10/22
22 Jadwal_praktek 7 days Fri 14/10/22 Mon 24/10/22
23 Jam_praktek 6 days Fri 14/10/22 Fri 21/10/22
24 Data_daftar 5 days Fri 14/10/22 Thu 20/10/22
25 No_antrian 4 days Fri 14/10/22 Wed 19/10/22
26 Waktu 3 days Fri 14/10/22 Tue 18/10/22

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: Nia Fahmiati_20.0.A.1480 Milestone Inactive Milestone Start-only


Date: Fri 14/10/22 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 1
ID Task Task Name Duration Start 09 OctFinish
'22 16 Oct '22 23 Oct '22
Mode T F S S M T W T F S S M T W
27 Hari 2 days Fri 14/10/22 Mon 17/10/22
28 Jenis_kelamin 1 day Fri 14/10/22 Fri 14/10/22
29 Data_admin 7 days Fri 14/10/22 Mon 24/10/22
30 Id_admin 6 days Fri 14/10/22 Fri 21/10/22
31 Username 5 days Fri 14/10/22 Thu 20/10/22
32 Password 4 days Fri 14/10/22 Wed 19/10/22

Task External Milestone Manual Summary Rollup


Split Inactive Task Manual Summary

Project: Nia Fahmiati_20.0.A.1480 Milestone Inactive Milestone Start-only


Date: Fri 14/10/22 Summary Inactive Summary Finish-only
Project Summary Manual Task Deadline
External Tasks Duration-only Progress

Page 2

You might also like