Cost Estimating

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-1
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Capital Cost Estimating
Seminar Outline

n Project Stages/Use of Cost Estimates


n Elements & Techniques of a Cost Estimate
n Cost Indexes/Escalation
n Contingency
n Cost Study Example Using Aspen Icarus
Process Evaluator
n Estimating Tools

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-2
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Project Stages

Market Study

Feasibility Study

Engineering

Construction

Startup

CE-R00-01
2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-3
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Market Study

Abandon
Project

Supply and Demand


Proceed to
Price Forecasts Decision Next Step

Economic Indicators

Consider
Alternatives

CE-R00-02
2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-4
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Feasibility Study

Abandon
Project
Raw Materials
Processing
Operations Proceed to
Decision Next Step
Cost Estimates
- Fixed Capital
- Utilities, catalyst
Economic Analysis
Consider
Alternatives

CE-R00-03
2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-5
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Engineering Stage

Abandon
Equipment Specifications Project
Plant Layout
- Piping
- Foundations
- Structures Proceed to
Decision Next Step
Utility Specifications
Cost Estimates
- Fixed Capital
- Operating
Consider
Economic Analysis Alternatives

CE-R00-04
2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-6
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Project Stages and Cost Estimates
Scope Definition Estimate Accuracy

Order of Magnitude (+/- 50%)

Project Milestones
1. Planning and Analysis
2. Design Basis Selected
3. Process Design Complete
4. Detailed Design Complete
5. Mechanical Erection Complete
6. Startup
Uncertainty

Preliminary Budget (+/- 30%)


- Curve
- Factored

Detailed (+/- 10%)

Definitive (+/- 5%)

1 2 3 4 5 6
Project Milestones
CE-R00-05
2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-7
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Cost Estimate Types

n Order-of-Magnitude
n Preliminary Budget
n Detailed Cost Estimate

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-8
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Order-of-Magnitude Cost Estimate

n Purpose
– Project Screening
– Preliminary Feasibility Studies
n Methods
– Periodicals/Trade Journals
– Capacity Ratio ($/bbl)
– Nelson Complexity
n Accuracy
– +/- 50% or Greater
n Minimum Engineering Required
– None
2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-9
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Preliminary Budget Cost Estimate
n Purpose
– Refined Feasibility Studies
– Preliminary and Refined Economic Studies
– Licensor Selection
– Preliminary Project Budget
n Methods
– Capacity Curve Type
– Factored Type
n Accuracy
– +/- 25-40%
n Minimum Engineering Required
– Yield Estimates
– Preliminary Equipment Sizing
2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-10
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Detailed Cost Estimate

n Purpose
– Refined Economic Study
– Establish Project Budget
– Contractor Selection
n Methods
– Detail
n Accuracy
– +/- 5-10%
n Minimum Engineering Required
– Schedule A
– Detailed Design

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-11
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Elements & Techniques
of a Cost Estimate

n Basic Elements
n Detailed Elements
n Standard Basis
n Local Basis

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-12
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Basic Elements

Capital Cost

Project Battery Limits

Special Requirements

Contingencies

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-13
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Project Battery Limits

n Direct Field Costs


– Major Equipment
– Bulk Materials
– Installation Labor

— Permanent Installation of Physical


Components

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-14
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Project Battery Limits

n Indirect Field Costs


– Construction Equipment
– Temporary Construction
– Field Expenses and Services
– Construction Insurance
– Labor Benefits and Burdens

— Nonpermanent Facilities and Services


Required to Execute the Project

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-15
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Project Battery Limits

n Home Office Expense


– Engineering
– Procurement
– Construction Services
– Construction Supervision
– Bonding
– Contractor’s Fee

— Services and Management for the Project

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-16
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Special Requirements

n Property Costs
n Taxes and Duties
n Project Development Costs
n Royalties/Know-How Fees
n Catalyst and Chemicals
n Start-up Costs
n Operations and Maintenance

– Any Requirement Considered Part of Capital


Cost

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-17
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Contingency

n Scope Definition
n Economic Changes
n Basis Definition
n Process Experience
n Estimating Methods
n Undefined Occurrences

– Anticipating and Preventing Losses

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-18
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Basic Elements

n Project Battery Limits


n Special Requirements
n Contingencies
– All capital projects have these basic elements
– Cost estimates should be expressed in terms of
what is included and what is excluded

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-19
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Detailed Elements

n Examples of the Next Level of Capital Cost


Estimating:
– Major Equipment
– Instrumentation
– Electrical
– Piping
– Bulks

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-20
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Standard Basis

n What is a Standard Basis Cost Estimate?


n U.S.A. Gulf Coast?
n How is Standard Basis Used?

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-21
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Standard Basis

n What is a Standard Basis Cost Estimate?


– Project Battery Limits
– Provides Essential Costs
– A Common Reference

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-22
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Standard Basis

n U.S.A. Gulf Coast


– Two thirds of U. S. refining/petrochemical
industry located on Gulf Coast
– Very high construction experience
– A common reference basis for owners and
contractors

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-23
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Standard Basis

n How is Standard Basis Used?


– A comparable reference point to past projects
– A consistent basis for data collection
– A common basis for conversion to other locations
– An accepted industry wide reference

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-24
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Local Basis

n What is a Local Basis Cost Estimate?


– Levels of influence
– Comprehensiveness of a local basis cost estimate

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-25
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Local Basis

n What is a Local Basis Cost Estimate?


– A comprehensive evaluation of specific
conditions and requirements for a project such
as local labor, imported equipment, taxes and
duties, contract type
– A total installed (budget) cost for a specific scope

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-26
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Local Basis
Levels of Influence

International National Local Project Contractor

Political X X X X X

Financial X X X X X

Legal X X X X X

Social X X X X X

Geographical X X X X

Industrial X X X

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-27
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Local Basis
Comprehensiveness

n Procurement Plan for Equipment and Materials


n Field Labor Plan
n Field Labor Cost Basis
n Subcontracting Plan
n Site Sub-Soil Conditions
n Plot Plan for New and Existing Facilities

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-28
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Local Basis
Comprehensiveness

n Equipment and Material Transportation Plan


n Field Supervision Plan
n Philosophy of Detailed Design
n Contractor’s Work Methods
n Type of Project Contract
n Project Schedule

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-29
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Local Basis
Comprehensiveness

n Construction Equipment Plan


n Temporary Construction Facilities Plan
n Construction Services Including Utilities Supply
n Bonding and Insurance
n Construction Safety

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-30
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Local Basis
Comprehensiveness

n Labor Mobilization/Demobilization
n Labor Camp and Catering Requirements
n Spare Parts
n Escalation

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-31
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Cost Indexes/Escalation

n Use of Cost Indexes


n Escalation

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-32
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Use of Cost Indexes

n Update Past Cost Estimates

Example:
Year Index
1991 361
2001 395

Escalation Factor from 1991 to 2001 is:


395/361 = 1.09

Applying Factor to 1991 Cost Estimate gives:


$1,000,000 (1991) x 1.09 = $1,090,000 (2001)

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-33
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Source of Cost Indexes

n Major U.S. Cost Indexes


– Nelson (Oil and Gas Journal)
– ENR (Engineering News Record)
– Chemical Engineering (McGraw-Hill)
– Marshall and Swift
– BLS (U.S. Bureau of Labor Statistics)

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-34
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Major Index Comparison

ENR NELSON CHEMICAL MARSHALL &


Construction R e finery Index ENGINEERING SWIFT Index
Index Index
Index for Complete NO YES YES YES
Chemical Plants (Excluding
Buildings)
Index for General NO YES YES NO
Process Equipment
Specific Classes of NO YES YES NO
Equipment
Separate Index for YES NO YES YES
Buildings
Index for Large Civil YES NO NO NO
Projects
Correction for Labor NO NO YES YES
Productivity
Correction for Technical NO NO NO NO
Improvement

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-35
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Cost Index Comparison
ENR Nelson CE M&S UOP

140

130

120
Index

110

100

90
1991 1992 1993 1994 1995 1996 1997 1998 1999 2000

Year

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-36
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Escalation

n Adjust Cost Estimate for Increasing Costs Over


Time
Example:
Inflation Rate from 1997 to 2001:

5%/Year

Right Way:
$1,000,000 x (1.05)4 = $1,215,500

Wrong Way:
$1,000,000 x (1 + (0.05 x 4)) = $1,200,000

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-37
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Contingency

n Contingency Definition
n How Is It Used
n Project Definition
n Project Evaluation

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-38
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Contingency Definition

n An amount added to an estimate to allow for


changes that experience shows will likely be
required. AACE

n An amount added to an estimate to allow for


probable, undefined occurrence and for
unforeseen occurrence.

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-39
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Contingency
How Is It Used?

n Cover Inadequacies in Scope Definition

n Anticipate Escalation and Currency Changes

n Improve Confidence in Estimate Basis Such as


Labor Productivity, or Sub-Soil Information

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-40
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Contingency
How Is It Used?

n Improve Confidence in (New) Process Experience

n Cover Unforeseen Occurrences Such as Labor


Disruptions or Epidemic Illness

n (Political) Decrease Chances Project Budget Will


Be Over Run

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-41
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Contingency
Project Definition

n General Project Basis (1 to 5 Factor)


n Process Design Basis
n Site Information
n Engineering Design Basis
n Detailed Design
n Field Performance

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-42
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Contingency
Project Evaluation

n Effectiveness of Management
n Effectiveness of Control Systems
n Allowance for Additional Escalation
n Addition Work/Rework
n Extended Project Schedule
n Engineering Status at Time of Estimate
n Variations in Estimating Methods

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-43
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Contingency
Project Evaluation

n Premiums for Availability and/or Delivery


n Fluctuation in Currency Exchange Rate
n Outbreak of Epidemic Illness
n Unforeseen Subsurface Conditions
n Changes in Taxes and/or Duties
n Repeat Takeover and Performance Tests
n Default by Contractor
n Variations in Labor Productivity

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-44
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Cost Study Example

n Design Influence and Timing


n Costing Method Used By UOP

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-45
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Design Influence on Project
versus Time
Project
100 Expenditures
High
90
80 Design
70 Influence
on Cost
60
50
40
30
20
Low10
0
Conceptual Detailed Engineering Start Up Operations
Definition & Procurement
Basic Design and Construction

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-46
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Estimating Resources and Tools

n Professional Organizations
n Published Materials
n Tools

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-47
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Estimating Resources and Tools
Professional Organizations

n AACE International
209 Prairie Ave., Suite 100
Morgantown, WV 26501 USA
800-858-COST or 304-296-8444
www.aacei.org

n Project Management Institute


Four Campus Boulevard
Newton Square, PA 19073-3299 USA
610-356-4600
e-mail: pmihq@pmi.org
2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-48
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Estimating Resources and Tools
Published Materials

n Richardson Engineering Services


P.O. Box 9103
Mesa, AZ 85214-9103
480-497-2062

n Thomas Register of American Manufacturers


Five Penn Plaza
New York, NY 10001
212-695-0500

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-49
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.
Estimating Resources and Tools
Tools

n Aspen Technology, Inc.


Icarus Office
600 Jefferson Plaza
Rockville, MD 20852-1150
301-795-6800

– Aspen Icarus Decision Analyzer


– Aspen Icarus Process Evaluator (IPE)
– Aspen Icarus 2000
– Aspen Icarus Project Manager

2003 ENGINEERING DESIGN SEMINAR – LIMITED DISTRIBUTION: This material is UOP LLC technical information of a confidential
nature for use only by personnel within your organization requiring the information. The material shall not be reproduced in any manner or
EDS 2003/CE-50
distributed for any purpose whatsoever except by written permission of UOP LLC and except as authorized under agreements with UOP LLC.