CONSTRUCTION OF ADMIN BLOCK AT ITUMELENG PRIMARY SCHOOL IN GABORONE, FOR THE 2019-20 CONSTITUENCY PROJECTS

ID Task Task Name Duration


Mode Week -2 Week -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18
1 GCC/63/2020 - ADMIN BLOCK 14 wks
2 PRELIMINARIES & GENERAL ITEMS 0.2 wks
3 Complying with all the initial general 1 day
conditions of the project
4 Mobilize on site 0.6 wks
5 Set up the site office 3 days General management,project management
6 Mobilize equipment and personnel 3 days
7 SECTION NO. 1: ADMIN BLOCK 11.2 wks
STRUCTURE
8 BILL NO. 1: DEMOLITIONS, 2 days
SUBSTRUCTURES (PROVISIONAL)
9 BILL NO. 2: CONCRETE, FORMWORK 7 days
& REINFORCEMENT
10 BILL NO. 3: PRECAST CONCRETE 10 days concrete mixer,concreting equipments,Front End Loader,project management,project workforce
11 BILL NO. 4: MASONRY 15 days
12 BILL NO. 5: WATERPROOFING 4 days bricklayers,project management
13 BILL NO. 6: ROOF CONSTRUCTION, 7 days
COVERINGS, ETC
14 BILL NO. 7: CARPENTRY & JOINERY 10 days carpenter,project management,project workforce
15 BILL NO. 8: CEILINGS, PARTITIONS & 7 days carpenter,project management,project workforce
ACCESS FLOORING
16 BILL NO. 9: IRONMONGERY 3 days carpenter
17 BILL NO. 10: METALWORK 7 days carpenter
18 BILL NO. 11: PLASTERING 10 days
19 BILL NO. 12: TILING 10 days project management,project workforce,Tiler
20 BILL NO. 13 PLUMBING & DRAINAGE 7 days project management,project workforce,plumber
21 BILL NO. 14: GLAZING 4 days project workforce
22 BILL NO. 15: PAINTING 15 days
23 SECTION NO. 2: ADMIN BLOCK 5.6 wks
ELECTRICAL & MECHANICAL
24 BILL NO. 1: ELECTRICAL INSTALLATION7 days project management,electrician

25 BILL NO. 2: AIRCONDITIONING 3 days Technician,project management


26 SECTION NO. 3: EXTERNAL WORKS 1.2 wks
27 BILL NO. 1: SITE PREPARATIONS 1 day
28 BILL NO. 2: WATER RETICULATION 5 days General management,plumber
29 BILL NO. 3: SEWER RETICULATION 5 days
30 SITE CLEANING AND FINAL 0.8 wks
INSPECTIONS
31 SNAGGING 1 day
32 HANDING OVER 1 day
33 DEMOBILIZATION 2 days
Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: STATE LINK GROUP INC Split External Tasks Inactive Summary Manual Summary Critical
Date: Sat 09/01/21 Milestone External Milestone Manual Task Start-only Critical Split
Summary Inactive Task Duration-only Finish-only Progress