Project: Unit Renovation - Tuscany 14C

Date: 3/7/2022
Today is 7-Mar-22
Item Incharge Scope Duraton Start Finish
Mar. '22 Apr. '22 May '22
Admin Mobilization 3 21-Mar-22 23-Mar-22
Admin Haulout of Scrap/Debris (1st) 1 28-Mar-22 28-Mar-22
Admin Haulout of Scap/Debris (2nd) 1 2-May-22 2-May-22
1 GROUND FLOOR 61 21-Mar-22 20-May-22
Foyer
Admin Installation of Tiles 2 24-Mar-22 25-Mar-22
Admin/Machuca Delivery of Tiles (Machuca) 1 1-Apr-22 1-Apr-22
Admin/Machuca Installation of Tiles (Machuca) 2 2-Apr-22 3-Apr-22
Admin Installation of Structural Support 5 30-Mar-22 3-Apr-22
Admin Installation of Ceiling (Framing/Gyp Board) 3 6-Apr-22 8-Apr-22
Admin EE works (Rough-ins and wirings Ins) 2 30-Mar-22 31-Mar-22
Admin Painting Works (Prep to Final Coat) 3 9-Apr-22 11-Apr-22
Admin Installation of Lighting Fixtures 1 20-Apr-22 20-Apr-22
Admin Delivery of FF&E 5 2-May-22 6-May-22
Powder Room
Admin Masonry Works/ Surface Prep 2 24-Mar-22 25-Mar-22
Admin Installation of Lavatory Counter 3 24-Mar-22 26-Mar-22
Plumbing and Electrical Works (Roughing-Ins and
Admin Inst. of Wiring)
5 21-Mar-22 25-Mar-22

Admin Waterproofing Works 2 25-Mar-22 26-Mar-22


Admin Installation of all Tiles 5 28-Mar-22 1-Apr-22
Admin Installation of Ceiling (Framing/Gyp Board) 5 28-Mar-22 1-Apr-22
Admin Installation of all Plumbing Fixtures 2 4-Apr-22 5-Apr-22
Admin Painting Works (Prep to Final Coat) 3 4-Apr-22 6-Apr-22
Admin Installation of Lighting Fixtures 1 6-Apr-22 6-Apr-22
Dining Area
Admin Delivery of Structural Support 1 30-Mar-22 30-Mar-22
Installation of Structural Support w Primer
Admin Coating
4 31-Mar-22 3-Apr-22

Admin Installation of all Tiles 3 4-Apr-22 6-Apr-22


AC Mechanical and Electrical Works (Roughing-
Contractor/Admin Ins and Wiring
3 7-Apr-22 9-Apr-22

Admin Installation of Ceiling (Framing/Gyp Board) 15 4-Apr-22 18-Apr-22


Cabinetry/Woodworks - Site
Others (2) inspection/preparation
1 11-Apr-22 11-Apr-22
Others (2) Cabinetry/Woodworks - Ins of support 3 18-Apr-22 20-Apr-22
Others (2) Cabinetry/Woodworks - Fabrication 25 12-Apr-22 6-May-22
Others (2) Cabinetry/Woodworks - Installation 5 7-May-22 11-May-22
Admin Painting Works (Prep to Final Coat) 4 19-Apr-22 22-Apr-22
Admin Installation of Lighting Fixtures 2 25-Apr-22 26-Apr-22
AC Contractor Installation of AC Unit 2 25-Apr-22 26-Apr-22
Admin Delivery of FF&E 5 2-May-22 6-May-22
Living Area
Admin Cleaning/preparation of area 1 21-Mar-22 21-Mar-22
Admin Installation of Floor Tiles 2 22-Mar-22 23-Mar-22
Admin Installation of Ceiling (Framing/Gyp Board) 3 23-Mar-22 25-Mar-22
Mechanical and Electrical Works (Roughing-
Admin Ins and Wiring
10 23-Mar-22 1-Apr-22
Admin Painting Works (Prep to Final Coat) 5 25-Apr-22 29-Apr-22
Others (1) Glass/Mirrors/Windows - Site Insp/Prep 1 25-Apr-22 25-Apr-22
Others (1) Glass/Mirrors/Alum Windows - Fabrication 5 26-Apr-22 30-Apr-22
Others (1) Glass/Mirrors/Alum Windows - Delivery 1 2-May-22 2-May-22
Others (1) Glass/Mirrors/Alum Windows - Installation 4 3-May-22 6-May-22
AC Contractor Installation of AC Unit 2 25-Apr-22 26-Apr-22
Admin Delivery of FF&E 5 25-Apr-22 29-Apr-22
Kitchen
Admin Cleaning/Preparation of area 2 28-Mar-22 29-Mar-22
Admin Installation of Floor Tiles 7 30-Mar-22 5-Apr-22
Admin/Machuca Installation of Wall Tiles (inc Machuca) 8 5-Apr-22 12-Apr-22
Mechanical/Plumbing/Electrical Works (Roughing-
Admin Ins and Inst. of Wiring) 10 30-Mar-22 8-Apr-22
Admin Installation of Ceiling (Framing/Gyp Board) 4 30-Mar-22 2-Apr-22
Admin Painting Works (Prep to Final Coat) 4 4-Apr-22 7-Apr-22
Admin Installation of Counter-Top support (Initial) 3 28-Mar-22 30-Mar-22
Modello Kitchen - Site Inspection/Preparation 1 30-Mar-22 30-Mar-22
Modello Kitchen - Fabrication 10 31-Mar-22 9-Apr-22
Modello Kitchen - Delivery of materials at site 2 10-Apr-22 11-Apr-22
Modello Kitchen - Installation 5 18-Apr-22 22-Apr-22
Felport/Ar2 Countertop - Site Inspection/Preparation 1 22-Apr-22 22-Apr-22
Felport/Ar2 Countertop - Fabrication 7 23-Apr-22 29-Apr-22
Felport/Ar2 Countertop - Installation 3 2-May-22 4-May-22
Others (1) Glass/Mirrors/Windows - Site Insp/Prep 1 25-Apr-22 25-Apr-22
Others (1) Glass/Mirrors/Alum Windows - Fabrication 5 26-Apr-22 30-Apr-22
Others (1) Glass/Mirrors/Alum Windows - Delivery 1 2-May-22 2-May-22
Others (1) Glass/Mirrors/Alum Windows - Installation 4 3-May-22 6-May-22
Admin Installation of Lighting Fixtures 2 24-Apr-22 25-Apr-22
AC Contractor Installation of AC Unit 2 25-Apr-22 26-Apr-22
Admin Delivery of FF&E 5 25-Apr-22 29-Apr-22
Master's Bedroom
Admin Delivery of Structural Support 1 30-Mar-22 30-Mar-22
Project: Unit Renovation - Tuscany 14C
Date: 3/7/2022
Today is 7-Mar-22
Item Incharge Scope Duraton Start Finish
Mar. '22 Apr. '22 May '22
Installation of Structural Support w Primer
Admin Coating
4 31-Mar-22 3-Apr-22
AC Mechanical and Electrical Works (Roughing-Ins
Contractor/Admin and Inst. of Wiring)
4 31-Mar-22 3-Apr-22

Matimco Delivery of Wood Flooring and Doors 1 13-May-22 13-May-22


Matimco Installation of Wood Flooring and Doors 5 16-May-22 20-May-22
Admin Installation of Ceiling (Framing/Gyp Board) 5 6-Apr-22 10-Apr-22
Cabinetry/Woodworks - Site
Others (2) inspection/preparation (Inc WIC)
1 11-Apr-22 11-Apr-22
Cabinetry/Woodworks - Ins of support (Incl
Others (2) WIC)
3 18-Apr-22 20-Apr-22

Others (2) Cabinetry/Woodworks - Fabrication (Inc WIC) 25 12-Apr-22 6-May-22

Others (2) Cabinetry/Woodworks - Installation (Inc WIC) 5 9-May-22 13-May-22

Admin Painting Works (Prep to Final Coat) 10 12-Apr-22 21-Apr-22


Admin Installation of Lighting Fixtures 1 27-Apr-22 27-Apr-22
AC Contractor Installation of AC Unit 2 25-Apr-22 26-Apr-22
Admin Delivery of FF&E 2 25-Apr-22 26-Apr-22
Master's Bedroom - WIC and T&B
Admin Cleaning/Preparation of area 1 21-Mar-22 21-Mar-22
Masonry Works/Surface
Admin Preparation/Rectification of Existing Tiles
3 23-Mar-22 25-Mar-22
Plumbing and Electrical Works (Roughing-Ins
Admin and Ins of Wirings)
3 23-Mar-22 25-Mar-22
Admin Installation of Bathtub Housing 5 28-Mar-22 1-Apr-22
Admin Installation of Lavatory Counter 5 28-Mar-22 1-Apr-22
Admin Waterproofing Works 2 1-Apr-22 2-Apr-22
Admin Installation of all Tiles 5 4-Apr-22 8-Apr-22
Admin Installation of Ceiling (Framing/Gyp Board) 6 7-Apr-22 12-Apr-22
Installation of all Plumbing Fixtures inc
Admin Bathtub
2 18-Apr-22 19-Apr-22
Others 3 Shower Enlclosure - Site Inspection 1 19-Apr-22 19-Apr-22
Others 3 Shower Enlclosure - Fabrication 5 20-Apr-22 24-Apr-22
Others 3 Shower Enlclosure - Installation 2 25-Apr-22 26-Apr-22
Admin Painting Works (Prep to Final Coat) 3 18-Apr-22 20-Apr-22
Admin Installation of Lighting Fixtures 2 21-Apr-22 22-Apr-22
AC Contractor Installation of AC Unit 2 25-Apr-22 26-Apr-22
Admin Delivery of FF&E 5 25-Apr-22 29-Apr-22
Office
Admin Cleaning/preparation of area 1 28-Mar-22 28-Mar-22
Admin Installation of Floor Tiles 5 1-Apr-22 5-Apr-22
Admin Installation of Ceiling (Framing/Gyp Board) 5 6-Apr-22 10-Apr-22
AC Mechanical and Electrical Works (Roughing-
Contractor/Admin Ins and Wiring
5 28-Mar-22 1-Apr-22
Admin Painting Works (Prep to Final Coat) 5 18-Apr-22 22-Apr-22
Others (1) Glass/Mirrors/Windows - Site Insp/Prep 1 25-Apr-22 25-Apr-22
Others (1) Glass/Mirrors/Alum Windows - Fabrication 5 26-Apr-22 30-Apr-22
Others (1) Glass/Mirrors/Alum Windows - Delivery 1 2-May-22 2-May-22
Others (1) Glass/Mirrors/Alum Windows - Installation 4 3-May-22 6-May-22
AC Contractor Installation of AC Unit 2 25-Apr-22 26-Apr-22
Admin Delivery of FF&E 5 25-Apr-22 29-Apr-22
Stairs
Electrical Works (Roughing-Ins and Inst. of
Admin Wiring)
3 21-Mar-22 23-Mar-22
Admin Masonry Works/Surface Preparation 5 21-Mar-22 25-Mar-22
Admin Instalation/Fixing of Stringer 5 21-Mar-22 25-Mar-22
Admin Fabrication/Installation of Thread Cleats 5 28-Mar-22 1-Apr-22
Admin Installation of Tiles (Landing Area) 5 28-Mar-22 1-Apr-22
Matimco Stair Thread - Delivery 1 4-Apr-22 4-Apr-22
Matimco Stair Thead - Installation 5 5-Apr-22 9-Apr-22
Others (1) Glass/Mirrors/Windows - Site Insp/Prep 1 25-Apr-22 25-Apr-22
Others (1) Glass/Mirrors/Alum Windows - Fabrication 4 26-Apr-22 29-Apr-22
Others (1) Glass/Mirrors/Alum Windows - Delivery 1 29-Apr-22 29-Apr-22
Others (1) Glass/Mirrors/Alum Windows - Installation 5 1-May-22 5-May-22
Balcony 1 and 2
Admin Cleaning/preparation of area 1 18-Apr-22 18-Apr-22
AC Mechanical and Electrical Works (Roughing-
Contractor/Admin Ins and Wiring
4 19-Apr-22 22-Apr-22

Admin Waterproofing Works 2 25-Apr-22 26-Apr-22


Admin Installation of Grass Turf 3 26-Apr-22 28-Apr-22
Admin Delivery of FF&E 1 29-Apr-22 29-Apr-22
Admin Laundry Area (To be used for Temp Storage and CR)
NA TBD TBD
Admin Maids Room (To be used as Temporary Storage and CR)

NA TBD TBD

2 2ND FLOOR 61 21-Mar-22 20-May-22


Hallway and Entertainment Area
Admin Masonry Works/ Surface Prep 5 21-Mar-22 25-Mar-22
AC Mechanical and Electrical Works (Roughing-
Contractor/Admin Ins and Wiring
5 21-Mar-22 25-Mar-22
Cabinetry/Woodworks - Site
Others (2) inspection/preparation
1 11-Apr-22 11-Apr-22
Project: Unit Renovation - Tuscany 14C
Date: 3/7/2022
Today is 7-Mar-22
Item Incharge Scope Duraton Start Finish
Mar. '22 Apr. '22 May '22
Others (2) Cabinetry/Woodworks - Ins of support 3 18-Apr-22 20-Apr-22
Others (2) Cabinetry/Woodworks - Fabrication 25 21-Apr-22 15-May-22
Others (2) Cabinetry/Woodworks - Installation 5 16-May-22 20-May-22
Others (1) Glass/Mirrors/Windows - Site Insp/Prep 1 25-Apr-22 25-Apr-22
Others (1) Glass/Mirrors/Alum Windows - Fabrication 4 26-Apr-22 29-Apr-22
Others (1) Glass/Mirrors/Alum Windows - Delivery 1 30-Apr-22 30-Apr-22
Others (1) Glass/Mirrors/Alum Windows - Installation 5 1-May-22 5-May-22
Matimco Delivery of Wood Flooring and Doors 1 13-May-22 13-May-22
Matimco Installation of Wood Flooring and Doors 5 16-May-22 20-May-22
Admin Installation of Ceiling (Framing/Gyp Board) 5 4-Apr-22 8-Apr-22
Admin Painting Works (Prep to Final Coat) 5 4-Apr-22 8-Apr-22
Admin Installation of Lighting Fixtures 2 9-Apr-22 10-Apr-22
AC Contractor Installation of AC Unit 2 25-Apr-22 26-Apr-22
Admin Delivery of FF&E 5 25-Apr-22 29-Apr-22
Boys and Girls Bedroom
AC Mechanical and Electrical Works (Roughing-Ins
Contractor/Admin and Inst. of Wiring)
5 4-Apr-22 8-Apr-22

Matimco Delivery of Wood Flooring and Doors 1 13-May-22 13-May-22


Matimco Installation of Wood Flooring and Doors 5 16-May-22 20-May-22
Admin Installation of Ceiling (Framing/Gyp Board) 5 4-Apr-22 8-Apr-22
Cabinetry/Woodworks - Site
Others (2) inspection/preparation
1 11-Apr-22 11-Apr-22

Others (2) Cabinetry/Woodworks - Ins of support 3 18-Apr-22 20-Apr-22


Others (2) Cabinetry/Woodworks - Fabrication 25 21-Apr-22 15-May-22
Others (2) Cabinetry/Woodworks - Installation 5 16-May-22 20-May-22
Admin Painting Works (Prep to Final Coat) 3 10-Apr-22 12-Apr-22
Admin Installation of Lighting Fixtures 2 18-Apr-22 19-Apr-22
AC Contractor Installation of AC Unit 2 25-Apr-22 26-Apr-22
Admin Delivery of FF&E 5 25-Apr-22 29-Apr-22
Girls T&B
Admin Installation of Lavatory Counter 3 21-Mar-22 23-Mar-22
Plumbing and Electrical Works (Roughing-Ins
Admin and Ins of Wirings)
5 21-Mar-22 25-Mar-22

Admin Waterproofing Works 2 25-Mar-22 26-Mar-22


Admin Instalation of all Tiles 5 28-Mar-22 1-Apr-22
Admin Installation of Ceiling (Framing/Gyp Board) 3 4-Apr-22 6-Apr-22
Admin Instalation of all Tiles 5 4-Apr-22 8-Apr-22
Admin Installation of Plumbing Fixtures 2 18-Apr-22 19-Apr-22
Admin Painting Works (Prep to Final Coat) 5 18-Apr-22 22-Apr-22
Admin Installation of Lighting Fixtures 3 18-Apr-22 20-Apr-22
Boy's T&B
Admin Installation of Lavatory Counter 3 21-Mar-22 23-Mar-22
Plumbing and Electrical Works (Roughing-Ins
Admin and Ins of Wirings)
5 21-Mar-22 25-Mar-22

Admin Waterproofing Works 2 25-Mar-22 26-Mar-22


Admin Instalation of all Tiles 5 28-Mar-22 1-Apr-22
Admin Installation of Ceiling (Framing/Gyp Board) 3 4-Apr-22 6-Apr-22
Admin Instalation of all Tiles 5 4-Apr-22 8-Apr-22
Admin Installation of Plumbing Fixtures 2 18-Apr-22 19-Apr-22
Admin Painting Works (Prep to Final Coat) 5 18-Apr-22 22-Apr-22
Admin Installation of Lighting Fixtures 2 18-Apr-22 19-Apr-22
Storage Room
Electrical Works (Roughing-Ins and Inst. of
Admin Wiring)
3 4-Apr-22 6-Apr-22

Admin Installation of Ceiling (Framing/Gyp Board) 5 4-Apr-22 8-Apr-22


Admin Installation of Lighting Fixtures 2 18-Apr-22 19-Apr-22
Cabinetry/Woodworks - Site
Others (2) inspection/preparation
1 11-Apr-22 11-Apr-22
Others (2) Cabinetry/Woodworks - Ins of support 3 18-Apr-22 20-Apr-22
Others (2) Cabinetry/Woodworks - Fabrication 25 21-Apr-22 15-May-22
Others (2) Cabinetry/Woodworks - Installation 5 16-May-22 20-May-22
Admin Painting Works (Prep to Final Coat) 5 27-Apr-22 1-May-22

3 Others
AC Contractor ME - AC Roughing-ins and Ins of wiring/copper tube 10 14-Mar-22 23-Mar-22
Admin FP - Instalation of Fire Protection (Sprikler System) 10 14-Mar-22 23-Mar-22
Admin FF&E - Delivery/Hauling NA TBD TBD
Client/Admin Punchlisting 5 23-May-22 27-May-22
Client/Admin Testing and Commisioning 3 27-May-22 29-May-22
Client/Admin Cleaning and Demobilization 2 30-May-22 31-May-22

4 Long-Lead Items
Structural Support (Tubular) - Offsite Fabrication Inc
Admin Delivery at Site
14 14-Mar-22 27-Mar-22

Machuca Supply of Cement Tiles/Accent Tiles at various areas 17 14-Mar-22 31-Mar-22


AC contractor AC (Supply and Installation) 30 14-Mar-22 12-Apr-22

Matimco Solid Wood Flooring and Doors(Supply and Installation) 20 20-Apr-22 10-May-22
Others (2) Cabinetry and Woodworks 25 14-Mar-22 13-May-22
Others 3 Shower Enlclosure - Supply and Delivery 15 28-Mar-22 11-Apr-22
Project: Unit Renovation - Tuscany 14C
Date: 3/7/2022
Today is 7-Mar-22
Item Incharge Scope Duraton Start Finish
Mar. '22 Apr. '22 May '22
FF&E
Client All Furnitures, Fixtures and Equipment 14 14-Mar-22 27-Mar-22