Professional Documents
Culture Documents
RR Contract Costing
RR Contract Costing
Topic
Contract Costing
1
Topic 9 Contract Costing
the increased prices. As per this clause, the contractor increases the contract price if
the cost of materials, employees and other expenses increase beyond a certain limit.
Inclusion of such a clause in a contract deed is called an “Escalation Clause”.
2
Topic 9 Contract Costing
If in question actual data is given as well as estimated data is also given. For e.g.
contract started on 1/4/2020. Actual data for year 20-21 is given. Contract is likely
to be completed on 31/12/2021. And estimated data from 1/4/2021 to 31/12/2021
is given. To calculate notional profit we will use actual data of 20-21. But to calculate
estimated profit we will use data from 1/4/2020 to 31/12/2021 (i.e. actual plus
estimated). Hence, we will prepare contract account for entire life of contract in our
example 21 months. Following adjustments are important:
1. We will never consider material at site and plant at site as on 31/03/2021.
2. Material returned or plant returned will be considered for both the period.
3. Material sold, plant sold will be considered for both the period.
4. Outstanding expenses, prepaid expenses at the end of actual period i.e.
31/03/2021 will not be considered
5. Outstanding expenses at the end of estimated period i.e. 31/12/2021 will be
considered.
3
Topic 9 Contract Costing
Total Total
4
Topic 9 Contract Costing
1. HKC commenced a commenced a contract on April 1, 2011. The total contract was for `
49,21,875. It was decided to estimate the total profit. Actual expenditure in 2011-12
and estimated expenditure in 2012-13 are given below:
The plant is subject to annual depreciation at 25% on WDV cost. The contract is likely
to be completed on 30 Sept 2012. Required: Prepare the contract account for the year
2011-2012. Estimate the profit on the contract for the year 2011-2012.