TH 07 004

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

Construction dewatering for underground station in urban

environment
Raja Rajan K, Nagarajan D, Vijayakumar T
CMPC division, EDRC, Heavy Civil Infra, L&T Construction, Chennai, Tamil Nadu, India

ABSTRACT
Metro is seen as the only solution for mass rapid transit system in urban areas. For underground metro station, deep
excavations in densely populated areas impose specific challenges to the contractor. Based on type of soil or rock,
excavation procedure, method and time shall be adopted. The control of groundwater is one of the most common
and complicated problems encountered on a deep excavation. The contractor selects the dewatering method and
contractor is sole responsible for its design and operation. Many dewatering techniques like multiple wells, sump
pumps, vacuum pumps, deep wells are available to control ground water. In this paper, author explains the usage of
MODFLOW software for dewatering analysis in underground metro station and also about the dewatering system
which has been adopted in site. Pump out test is an accurate method of determining the safe yield of the well and
also for assessing the actual site condition.

1 INTRODUCTION awarded to Larsen & Toubro and STEC Joint Venture


(L&T STEC JV) Contractor to design and build.
Urban transportation infrastructure in India needs big
investment and a massive upgradation. Metro is seen
as the only solution for mass rapid transit system. After 3 GENERALIZED SUB SOIL PROFILE
the success of Delhi Metro, lots of Indian cities are
exploring the option to implement metro rail project Geotechnical Strata for each station been classified to
across the country. different units which is tabulated in Table 1. Predefined
For underground metro station, deep excavations soil parameters provided in Geotechnical Interceptive
in densely populated urban areas impose specific report.
challenges, especially to the safety and impact on
adjacent structures. Effective risk management in the
design and construction of deep excavations in the Table 1. Sub-soil classification with description
urban environment must consider a range of issues
such as the design of excavation support, ground water Soil Type Description
control system, pre-construction surveys of adjacent
properties and utilities and the implementation of Unit 1-Filled Reddish brown dry clayey sand with gravel
effective monitoring systems. For constructing metro up material / clayey gravelly sand
station which may be on an average of 20m deep Silty sand, sandy silty, sandy clay, clayey
Unit 2a: Soil
excavation to be carried out below ground. In order to sand
perform excavation in dry zone, dewatering system to
be well planned and executed. The contractor selects Unit 2b: Very dense dark brownish yellow moist
Residual Soils sand with gravel, boulders
the dewatering method and contractor is sole
responsible for its design and operation. The authors of Unit 3a: Basalt
this paper had taken the role for designing the Weak to very weak completely weathered
-WG V
dewatering system for all 4 stations of Mumbai Metro
Line 3 package 1 based on the site geologic condition. Strong highly weathered to moderately
Unit 3b: Basalt
weathered grey basalt with very closely
-WG IV
spaced horizontal fractures
2 LOCATION & SITE DETAILS Unit 3c: Basalt Strong moderately weathered grey basalt
-WG III with closely spaced horizontal fractures
Mumbai Metro Line 3 (MML3) Project is proposed from
Colaba in South Mumbai to SEEPZ via Bandra Kurla Very strong moderately to slightly
Unit 3d: Basalt
Complex. Package UGC-01 is one of the 7 packages of weathered basalt with widely spaced
-WG I & II
MML3 and it consists of 4 stations (Cuffe Parade, horizontal fractures.
Vidhan Bhavan, Church gate and Hutatma Chowk Unit 4a1:
Station) and associated tunnels. MML3 UGC-01 was Weak to moderately strong moderately
Shale/Breccia
weathered light brownish grey shale
- WG V

1
4.1.2 Top Down Method
Unit 4a2: Moderately strong slightly weathered dark
Shale /Breccia grey shale with closely to very closely This method is applicable only when the traffic diversion
- WG IV spaced horizontal fractures
is possible. In some places decking panel used for
traffic movement over the excavated portion as shown
in Figure 2. Earth retaining system is constructed and
4 RETAINING SYSTEM & METHOD OF excavation shall be done up to top slab level. Once the
CONSTRUCTION top construction is completed, filling is done above the
top slab and then open to traffic. Through the openings
For deep excavation, the earth has to be retained by in the top slab further excavation and construction
suitable structural member in order to avoid disturbance proceeds. As construction moves from top to down,
to the adjacent structures. Since the excavation depth there is no requirement of temporary strut. Intermediate
is very deep and location of the station at urban area, slabs itself act as strut member. Comparatively this
open cut excavation is not feasible. Earth retaining method has less working space and vehicle movement
systems like Diaphragm walls, secant piles, soldier inside the excavated area.
piles, contiguous piles and sheet piles were available
for retaining system. Suitable structure shall be chosen
based on client’s requirement, site geology,
construction methods, ground water and soil/rock
properties.

4.1 Method of Construction

For constructing underground metro station many


methods been widely followed by the contractors. Top
down method and Bottom up method were the
conventional methods adopted by global contractors.

4.1.1 Bottom up Method

This method is applicable only when the traffic diversion Figure 2. Typical top down construction method
is not possible. The principle of bottom up method is to
isolate the excavation area by proper earth retaining
system and then to proceed with stages of excavation. 5 DEWATERING
After each stage of excavation temporary strut shall be
installed and activated before advancing to the next Dewatering means “the separation of water from the
stage of excavation. Similar procedure is adopted till soil”, This leads to concepts like pre-drainage of soil,
excavation reaches the final excavation level as shown control of ground water, and even the improvement of
in Figure 1. Upon reaching the toe level, base slab is physical properties of soil. The purpose of construction
constructed along with side walls. Gap between walls dewatering is to control the surface and subsurface
and excavated profile shall be filled with suitable hydrologic environment in such a way as to permit the
material. As side wall construction proceeds, bottom structure to be constructed “in the dry state.”
most strut is deactivated and removed. Intermediate Construction dewatering has existed as a specialty
slabs shall be constructed as per levels and industry for a long time. Consequently, a number of
specification. Similarly, the procedure is followed till top well-established techniques have been developed to
slab construction and remaining portion is filled with soil lower the ground water table during excavation. The
and road laid for public traffic. geology, ground water conditions, and type of
excavation all influence the selection of dewatering
technology.

Retaining
System

Figure 1. Typical Bottom up construction method


Figure 3. Typical underground metro station
construction

2
Generally, two major groups of underground facilitating easy discharge of water through robust solid
water techniques controls are existing: Exclusion handling pumps.
techniques and dewatering techniques.

5.1 Exclusion Techniques

This technique is to exclude water from the excavation.


The aim of groundwater control by exclusion techniques
is to prevent groundwater from entering the working
area. Region which has a very low permeability wall like
sheet pile or diaphragm walls were physically
constructed or inserted in the ground.

5.2 Dewatering Techniques

Those that deal with groundwater by pumping. In the


second group, underground water flow is pumped so
the underground water table is lowered below the
deepest excavation formation level. For safe and stable Figure 5. Sump pump system – dewatering technique
excavation, it necessary to remind these two important
points: In the excavation period, do not hold back the Since the bottom of the sump is situated at a level lower
water table to its first condition. This may cause a than that of the excavation bottom, it will abridge the
buildup of pore water pressures that will eventually seepage way along which groundwater from outside
cause catastrophic movement of soil and groundwater. seeps into the excavation zone and as a result the exit
Ensure those fine grain soil particles are not gradient of the sump bottom will be larger than that on
continuously migrated around the drainage well. Proper the excavation surface. Typical sump system shown in
filter design avoids any buildup of pore water pressures Figure 5.
and prevents transportation of fines.
5.2.3 Deep Well Method
5.2.1 Well Point Method
A deep well system consists of an array of bored wells
A series of wells of required depth are created in the pumped by submersible pumps. Pumping from each
vicinity of the excavated area from where the water has well lowers the groundwater level and creates a cone of
to be pumped out as shown in Figure 4. Riser pipes or depression or drawdown around itself as shown in
dewatering pipes are then installed into those closely Figure 6. Several wells acting in combination can lower
spaced wells which on the surface are connected to a groundwater level over a wide area beneath an
flexible swing pipe which is ultimately appended to a excavation. Because the technique does not operate on
common header pipe that is responsible for discharging a suction principle, large drawdowns can be achieved,
the water away from the site. One end of the header limited only by the depth of the wells, and the
pipe is connected to a vacuum pump which draws water hydrogeological conditions. The wells are generally
through notches in the well point. The drawdown using sited just outside the area of proposed excavation and
this method is restricted to around five to six meters are pumped by electric submersible pumps near the
below the well point pump level. If a deeper drawdown base of each well. Water collection pipes, power supply
is required, multiple stages of well points must be used. generators, electrical controls and monitoring systems
are located at the surface.

Figure 4. Multiple Well system – Dewatering technique

5.2.2 Open Sump Pumping Method Figure 6. Deep well system – Dewatering technique

This is the most common and economical method of


dewatering as gravity is the main playing force. Sump 6 MODFLOW
is created in the excavated area into which the
surrounding water converges and accumulates Due to complex nature of hydraulic boundary conditions
(flow barriers), caused by secant piles at this site,

3
dewatering analysis using theoretical approach is not 7 DEWATERING FOR CUFFE PARADE STATION
adequate and requiring numerical simulations.
Dewatering analysis using Visual MODFLOW v.2010.1 Contractor is sole responsible for adopting suitable
is employed to design the deep well design in dewatering system to enhance the dry excavation in
underground metro stations. MODFLOW is a modular station. Many dewatering techniques are readily
3D finite difference ground water flow model where available, but as a pioneered contractor the most
similar program functions are grouped together, and efficient and most economical system to be selected.
scientific computational and hydrologic options are This paper explains the dewatering design adopted for
constructed in such a manner that each option is cuffe parade station using MODFLOW software.
independent of other options. It has provision for barrier In contract document, Client has provided some
flow conditions to be modelled. contract requirement to be fulfilled while designing the
The model is applicable for transient as well as dewatering system.
steady state model. The interface is divided into three • The groundwater within the excavations shall be
separate modules, the Input Module, the Run Module, maintained at a level that permits achievement of
and the Output Module. When you open or create a file, undisturbed, stable and dry subgrade to permit
you will be able to seamlessly switch between these construction and backfilling of the permanent
modules to build or modify the model input parameters, works and avoids heave, piping or base failure of
run the simulations, calibrate the model, and display the excavation
results (in plan view or cross section). Workflow of • The Groundwater drawdown (a drop of water table
MODFLOW software is explained in the below Figure7 during dewatering/construction) outside the
as flowchart. Software works from importing the model excavation/adjacent to works, shall be controlled
from drawing or picture, providing adequate inputs, such that the water table doesn’t get lowered by
selecting the proper engine for analysis and then the more than one metre below the lowest recorded
output is displayed. groundwater table. For ensuring this the
The Input Module allows the user to graphically recharging well system shall be provided, if
assign all of the necessary input parameters building a required.
three-dimensional groundwater flow and contaminant • Where ever water bearing seams, fissures or
transport model. The input menus represent the basic broken ground yielding undesirably large
"model building blocks" for assembling a data set for quantities of water is encountered, it shall be
MODFLOW. These menus are displayed in the logical grouted
order to guide the modeler through the steps necessary Cuffe parade station extends to a length of about 407m
to design a groundwater flow and contaminant transport with cross width of 37m. Station details been tabulated
model. in below table 2 with other details.

Table 2. Cuffe parade station details

Base Total
Length Width of Ground slab depth of
of station station level Bottom station
+3.84 m, -21.24 m,
407m 37m CD CD 25m

Design consultant has predefined each excavation


stages till bottom of excavation which has been
tabulated in Table 3. Excavation has to reach the depth
of about 24m below existing ground level.

Table 3. Excavation stages of Cuffe parade station

Description Reduced Depth below


Level GL

Natural ground level +3.84 0.0m


Figure 7. Flowchart of MODFLOW workflow
Initial Ground Water Level +2.84 1.0m
The Run Module allows the user to modify the
various MODFLOW parameters and options which are First Excavation Level +0.59 3.25m
run-specific. These include selecting initial head
estimates, setting solver parameters, activating the re- Second Excavation Level -3.41 7.25m
wetting package, specifying the output controls, etc.
The Output Module allows the user to display all of the Third Excavation Level -7.41 11.25m
modelling and calibration results for MODFLOW. The Max. Toe level of Secant
-3.87 7.71m
output menus allow you to select, customize, and Pile wall (3a)
overlay the various display options for presenting the Max. Toe level of Secant
-12.66 16.5m
modelling results. Pile wall (3b)
Fourth Excavation Level -12.65 16.49m

Final Excavation Level -20.245 24.08m

4
As per client requirement, dewatering to be done 1m instance, if user desired to view dewatering stage 10m
below each excavation stages i.e. if first excavation below ground level, simply 10th layer shall be viewed so
stage is +0.59m, then level of water by dewatering to be that corresponding drawdown can be witnessed in the
at -0.59m. Similarly, for each stage, dewatering to be corresponding layers which is an effective tool for
done at least 1m below the proposed excavation level monitoring the dewatering analysis.
as shown in Figure 8. Setting the above criteria as
benchmark, suitable dewatering design been adopted.
Secant piles proposed as temporary retaining system.
Soft pile and hard piles form the combination of secant
pile design. Reinforcement is provided in hard pile
whereas soft pile is filled only with concrete. The toe of
secant pile is determined based on encountering of rock
level. Based on type of rock grade, pile embedment is
predefined by consultant. During execution for each
pile, geologist confirms the grade of rock and execute
the proposed embedment of pile in rock. Below fig.9
shows a typical cross section of cuffe parade station
with secant piles as retaining system and pile
termination on either side based on rock grade with
excavation sequence till base slab level. Among the
available dewatering system deep well system is found
to be efficient and more suitable for the ground
condition.
In rocky strata, open sump pumping is the only
available dewatering system. Modflow software works
based on certain assumption. Faults or fissures present Figure 9. Plan of cuffe parade station imported for
in the rocks is completely ignored in analysis, if analysis from PDF file
encountered in execution, same to be closed by
grouting. 7.1 Input Data for Analysis

In this analysis, the aquifer is considered as unconfined.


Ground water table is considered at ground water itself
as per client requirement. Secant piles which act as
retaining system been modelled as dead cells which
means no water from outside station area is allowed to
pass through the secant piles. Layout of the secant
piles and depth of secant pile also modelled as per
consultant drawings. In this model the effect of secant
pile is considered in design, so it is assumed that
secant pile will be in position before the start of
dewatering works. In Modflow software, water source
like sea, river, well, pond etc., shall be modelled which
will act as source of water to ground water which will be
influenced in dewatering analysis inside the station
area. In this station, sea is present 250m away from
station area which has been included in the model.
Geotechnical details taken from approved Geological
Interceptive Report of cuffe parade station area and
Figure 8. Excavation & Strut Level details of Cuffe modelled it as shown in below table3 in Modflow
parade station software.

Geotechnical inputs like soil strata, permeability of


each strata (both vertical and horizontal), retaining Table 4. Sub soil data profile for Cuffe parade station
system layout and depth etc., to be defined as input
parameters. In order to start the analysis, plan layout of Layer Max Depth (m)
the station to be imported. Import files shall be PDF Subsoil Profile
No. From To
format, JPEG format, or it can be directly imported from
google maps. Below figure shows the imported plan of 1 Fill (Top Layer) 0.0 3 - 4.9
cuffe parade station in Modflow software.
After importing the plan, grids to be defined for 2 Residual Soil 4.9 3.0- 6.0
ease of bifurcation of station for analysis. Grids to be Completely weathered 3.0-
defined in both vertical and horizontal direction which 3 6 -12
Basalt 6.0
will help to cut the section anywhere in grid location as Highly weathered to
per user requirement. In this grid spacing is taken as 12-
4 Moderately weathered 15.0
1m interval in both directions as shown in Figure 9. 13.5
Shale/Basalt
Apart from grid, layers also can be defined so that Fresh to slightly
output can be viewed as per desired layer. For 5 weathered Below 15.0
Amygdaloidal Basalt

5
The permeability of each strata taken from GIR recharge wells which is positioned outside the station
as primary input for Modflow analysis. To be on area. In order to know the exact ground permeability, it
conservative side, vertical permeability is taken as half is recommended to conduct a pump out test in the
of horizontal permeability. Permeability in rock strata is station.
very low and considered as impervious layer.
Permeability of soil is considered much on conservative 7.2 Pump Out Test
side in order to design the system for adverse condition. Pumping test is an accurate method of determining the
As a prudent contractor L&T wants to design safe safe yield of the well. A pumping test is a field
dewatering system in order to meet any unpredictable experiment in which a well is pumped at a controlled
situation like high ingress of water during excavation rate and water-level response (drawdown) is measured
which may affect the excavation work to proceed in one or more surrounding observation wells and
further. optionally in the pumped well (control well) itself;
response data from pumping tests are used to estimate
the hydraulic properties of ground. The rate of pumping,
Table 5: Soil permeability for Cuffe parade station per hour, under this equilibrium condition, gives the
yield per hour (Q) of the well at a particular drawdown
Horizontal (s).
Vertical
Layer Depth (m) conductivity
Conductivity kz Pumping test is conducted to evaluate an
No. kx or ky
From To (m/sec) aquifer by "stimulating" the aquifer through constant
(m/sec)
1 0.0 4.5 5E-04 2.50E-04 pumping and observing the aquifer's "response"
2 4.5 12.0 1.13E-05 5.65E-06
(drawdown) in observation wells on the well in the area
is only method for computing the aquifer parameters. A
4 Below 12.0 4.12E-06 2.06E-06 long duration pump test for 2160 minutes was
conducted to observe the effect of pumping in pumping
well and nearby observation wells. The Pumping well
Pumping wells used to pump out water from and observation wells were of identical design.
excavation area. Diameter of wells vary from 200 to
300mm in diameter. Perforated PVC pipe of 150mm From the long duration pump test conducted in the
diameter is inserted in the well and remaining area is study area, following parameters have been computed
filled with filter material which used to allow water inside • Transmissivity (T)
the well without any clot at perforations. In this station
• Field Permeability/Hydraulic Conductivity (k)
total of 19 pumping wells been planned with total depth
• Specific yield (Sy)
of 20m from ground level. Recharge wells which used
to pump water in the ground in order to maintain the • Specific Capacity (C)
ground water table outside the station area. As per Though different methods are available for estimating
contract condition, ground water table outside the the above parameters, most suitable methods chosen
station area shall not be lowered more than 1m from for computation.
existing level. In order to maintain, constant recharge
shall be done using recharge wells.

Figure 11. Pump out test at cuffe parade station area


The Pumping test data was analyzed by
Theis’s Recovery Method & Jacob’s Method in order to
determine the above said parameters. The
Transmissivity ‘T’ value 1.44 m2/day and 0.81 m2 /day
respectively. Permeability ‘k’ value in the pumping well
(MW) is derived to be 0.93 x 10-5 cm/sec and 5.20 x
10-5 cm/sec respectively. Specific yield (sy) in the
pumping well MW is derived to be 0.13% and 0.05%
respectively. This indicates lack of very fine
Figure 10. Co-ordinates input for pumping and recharge interconnecting zones among fracture zones that are
wells weak, and due to which groundwater movement is very
The pumping capacity of pumping well to be slow in the station area.
defined as input in order to calculate the number of 7.3 Engine Selection for Analysis
days required to achieve the desired drawdown. In the
present analysis 600 cum/day given as pumping After providing the required inputs, engine selection
capacity and 80 cum/day as recharge quantity for shall be made in order to analyze the dewatering

6
design. Various engines been enlisted in software for
different usage.

Figure 14. Plan showing drawdown of cuffe parade


station
Figure 12. Engine selection for Modflow analysis For the plan shown above, two cross section
been chosen in order to view the drawdown for cross
section and longitudinal section of the station.

Figure 13. Analysis in Modflow software for the selected


engines
Modflow user manual provide a clear idea for Figure 15. Cross section showing drawdown of cuffe
selection of appropriate engine based on type of design. parade station
Once the engine is selected, analysis starts for
computing drawdown, water flow path, influence area of
well, time taken to achieve dewatering etc., and output
window is used to view the desired output.
7.4 Output Window of Modflow Analysis

Many trials to be carried out by adjusting number of


days of dewatering, location of pump wells, depth of
pump wells in order to achieve more economical
desired output. Software has a unique feature to make
cross section at any grid and also to view drawdown at
any depth. Some of the output window images shown
below for better understanding. Typical drawdown
achieved all along the length of station in plan view is Figure 16. Longitudinal section showing drawdown of
shown below. Based on drawdown depth, different cuffe parade station
color legends assigned.
Apart from drawdown, water flow path shall be
seen in plan view which gives a clear direction of water
movement path. The maximum drawdown achieved in
this station is 14m below ground level i.e. till top of the
rock strata.

7.4 Sump Pump System

If excavation reaches the rocky strata, then deep well is


inefficient and for dewatering sump pump system to be

7
adopted. Total 6 nos of sump system been deployed 9 CONCLUSIONS
for this station. Sump size is of 1.5m X 1m X 1m which
will be taken down as excavation proceeds. Sump is Some of the key points to be noted while designing the
positioned 3m inside secant pile such that it will not dewatering techniques for underground metro station
affect berm of secant pile. The water collected in the
sump shall be pumped out periodically using • Many dewatering techniques like multiple wells, sump
submersible pump. Apart from this, sump requirement pump, vacuum well, deep wells are available to control
for monsoon is also calculated by analytical method and the ground water. Contractor has to choose the suitable
recommendation is provided to use of extra sump in technique based on sub surface, permeability of strata,
monsoon period. Maximum recorded rain water is depth of excavation and excavation area.
taken and compared with area of excavation to arrive at •Pumping wells used to pump water from excavated
sum pump requirements. 2 nos of extra pump kept in zone, Recharge wells present outside the station used
reserve for monsoon period. for pump in water to maintain the ground level outside
station area and Observation well used to monitor the
7.5 Dewatering Layout ground water during the entire process.

Apart from the deep well arrangement and sump •MODFLOW software works from importing the layout,
system, dewatering layout to be provided for the entire providing required geotechnical inputs, choosing the
station. The capacity of pumps is decided based on rate engine to analyze and output for the desired drawdown
of pumping, required vertical lift, amount and type of is obtained.
suspended solids. Suitable electrical submersible •Using MODFLOW software, well spacing, well depth
pumps shall be installed within each deep well. The and influence of retaining structure shall be clearly
pumps shall be connected to discharge pipes, cables pictured
and ropes prior to lowering. The system can be fitted
with an external control to automatically start and stop •Pump out test reveals the yield capacity of well and the
pumping at predetermined levels. actual permeability of the ground stratum. Pumping test
The units shall be lowered with the pipe and conducted for 72 hours continuously in order to
cable strapped to the lifting rope into the PVC screen determine transmissivity and permeability by Theis’s
casing. The lifting rope shall be secured at the top of Recovery Method & Jacob’s Method
well for removal of pump in case of repair and
•Total of 19 pumping wells, 6 recharge wells and 2
maintenance. Discharge from pumping wells shall be
observations wells were provided to dewater the entire
measured and recorded at least twice in a day during
cuffe parade station area
dewatering. Discharge from both deep wells and sump
pumps to be connected a common discharge pipeline •Pumping well diameter is 200mm with perforated pipe
which shall be provided along the periphery of the of 150mm to encase the submersible pump with 50mm
station. Water discharge is collected in sedimentation of filter layer all around the perforation
tank before discharging into drainage. Water is allowed
to stagnate in sedimentation tank so that sediments •Perforations to the well to be provided as per the
carried along water shall get settled in sedimentation specifications. Improper filter criteria shall affect the
tank and after some time water is allowed to discharge specific yield of well which ultimately reduce the
in drainage pipelines. Sedimentation tank is frequently efficiency of the well
cleaned in order to remove the settled sediments from •Depth of pumping well terminated based on rock depth,
the tank. bottom of well is provided 2m below the rock surface
without any perforations in order to provide sufficient
head for efficiency of pump
8 PROTECTION OF ADJACENT STRUCRUTRES
•Deep wells found to be inefficient in rock strata,
dewatering in rocky layer depends only on sump
Due to lowering of groundwater, there may be impact
pumping system
on the adjacent structures. The condition of the existing
buildings is taken from the Mumbai Metro Line 3 Tender •Sump shall be provided 3m away from the secant pile
Documents - Building Condition Survey. The surveyed wall in order to protect the berm of the wall
buildings are located within a band width of about 60m
along the corridor defined as the “influence zone. •Surface water control due to monsoon been calculated
Category of building given as per contract separately by analytical method for which 4 nos of 5HP
recommendation and suitable instrumentation been pumps were provided in order to dewater the
planned all around buildings located near the station. accumulated water due to rain
Building settlement and cracks been monitored •Flood protection wall of 1m height been provided all
continuously during the time of excavation and along the periphery of the station in order to stop the in-
dewatering. If cracks exceed and settlement exceeds flow of water to the excavated area from the
the permissible level, then excavation to be stopped. surroundings.
Observation wells located outside the station helps to
monitor the ground water table outside the station area. •Shotcrete been provided along the surface of the
excavated rock in order to stop the seepage of water
from the sides of the rock.
•If any local faults or fissures encountered during rock
excavation, same has to be grouted completely

8
•In cuffe parade station, rock encountered Visual MODFLOW, version 2010.1, Waterloo Hydro
approximately 12 m below ground level, if no rock geologic, Ontario, Canada
surface encounters, then depth of pumping well has to
go below base slab level.
•Observation wells to be monitored continuously for the
depth of ground water table outside the station area.
Fluctuation of ground water shall be allowed maximum
for 1 meter.
•All discharges from deep wells and sump system shall
be connected to the common discharge pipeline which
flows to the sedimentation tank and followed to
drainage outlet.
•Sedimentation tank used to remove the sludge which is
mixed in the water which is helpful to avoid clot in the
drainage system.
•Instrumentation to be fixed in the adjacent buildings in
order to monitor the cracks of the building during the
time of dewatering and excavation of station building.
Prior to dewatering, category of existing building
condition to be identified and labelled.
• Inclinometer fixed on secant piles in order to monitor
the pile deflection due to earth pressure during the
process of excavation.

10 ACKNOWLEDGEMENTS

I would like to convey my thanks to the management for


allowing me to present this paper and my heartful
regards to my colleagues and site team for their
valuable contribution.

11 REFERENCES

Bureau of Indian Standards IS 9759 (1981, reaffirmed


2003): Guidelines for Dewatering during
Construction

CIRIA C515 (2000), Groundwater Control: Design and


Practice. Prepared by Preene M, Roberts T O L,
Powrie W, and Dyer M. CIRIA London

Mumbai Metro – Package 1 - Project contract &


technical documents

P.M. Cashman, M. Preene, (2001), Ground water


lowering in Construction – A Practical Guide

Paul, Khursheed, and Rohit singh (2017) Comparative


study of construction technologies for underground
metro station, Vol.6 Issue 3, International Journal
of research in Engineering and Technology

Sadhegpour, Ghanbari and Fadee (2008) Groundwater


lowering in deep excavation, International
conference on case histories in Geotechnical
engineering.

Ground Water Information Greater Mumbai District


Maharashtra - Govt. of India Ministry of Water
Resources Central Ground Water Board

You might also like