Evershine Shop Drawing and Material Submittal Status_Revised 3-Aug-2022

Item RFI No. Description Level Shop Drawing Status Action By Target Date Material Submittal Status Action By Target Date
of Submission of Submission
Basement
1 BP03-RFI-A-06297 Vehicle Purlin B1-B5 Re-submit based on Teck Siong To submit submittal documents Teck Siong Vehicle purlin sample
commented RFI-06297 (CD- submitted. Document
112) 25-Aug-2022 to submit 6-Aug-
2022.

2 Bicycle Rack B1 Re-submit - Izzat to provide Izzat Mock Up Redo after MEP Grille Teck Siong Mock up installed.
Pending MEP grille
MEP Grille detail Installation Pending MEP grille
sample
by SUJV
3 BP03-RFI-A-05825-01 MS Grating Scupper Drain at Basement B1-B5 Pending submission based on Teck Siong Pending submission Teck Siong B4 Ms grating
1-Sep-2022
Carpark_design based on vehicle load B4 grating details approved.
4 BP03-RFI-A-04667-02 Steel Trellis / Louver at B1 Entrance B1 Pending submission Teck Siong 12-Aug-2022 Pending submission Teck Siong 7-Sep-2022
BP03-RFI-S-05913-02 Pump Room Access Opening Removeable Cover at B1 Pending submission Teck Siong Pending submission Teck Siong
5 9-Sep-2022 -
Plot 3 (Vehicle Load)

Podium Foyer
West Podium Cut-Off drain Grating WP Submit layout and follow BP03 Teck Siong Advise by Haris Haris BP03 sample grating
6 18-Aug-2022
details submitted.
7 BP03-RFI-A-06126 Bulk Waste Room Railing & Swing Gate L1 Pending submission Teck Siong 8-Aug-2022 Advise by Haris Haris -
BP03-RFI-A-03513-04 E-Waste & Management Room Scupper drain Advise by Haris
8 L1 Pending submission Teck Siong 11-Aug-2022 Haris -
Grating
Balcony Stair Railing Teck Siong Advise by Haris
Re-submit - Details for
9 L1 4-Aug-2022 Haris 11-Aug-2022
additional connection support
BP03-RFI-A-04970 Advise by Haris Cat ladder sample
10 Cat Ladder at Reception Desk L4 Re-submit Teck Siong 15-Aug-2022 Haris
submitted.
11 Mail box L1 Approved NIL To re-submit due to size not Teck Siong
Letterbox sample
- same as approved shop
submitted.
drawing
12 HDGI L Angle at Waste Management Room L1 Check with design team for Teck Siong To submit sample and submittal Teck Siong
shop drawing submission documents (4mm thk change
- 25-Aug-2022
to 5mm with no cost
implication)

Kindly furnish all relevant softcopy drawing for Item


Note from Evershine 3, 5, 6, 7, 8 & 10. We do not have detail information
Design on tht except RFI information from contract team.
Need AUTOCAD softcopy to proceed with drawing.

Except item 2 is in our contract, other items are V.O


Note from Evershine to us. Pricing for all the V.O items are not confirm.
Management We do not receive any MCI/MCD for some of the V.O
items as well. Kindly expedite on this.

Dwg & Material List/1/1