Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 23

15-Nov-22 Tuesday

Personnel
Category no.
Day Night Total
Project Manager 1 0 1
Project Engineer 0 0 0
Project Supervisor 3 1 4
Safety/ Evir. Staff 1 1 2
Maintenance supervisor 0 0 0
Survey Crew 3 0 3
QC/QA Crew 3 1 4
Operators 17 11 28
Maintenance Crew 0 0 0
Security 0 0 0
Spotters 2 2 4
Unskilled Labourer 0 0 0
Clerk of works/HR 1 0 1
Chainsaw operator 0 0 0
Total 31 16 47
Weather
Today Week todate Mth todate
Rainfall / mm
Delay (hour) 0
Activity Quantity
Today Week todate Mth todate
Cleared area (m2) 0 65120 65120
Rockfill (m3) 10152.5 72929.5 72929.5
Topsoil stripped area m3 0 7536 7536
spent ore m3 0
Unsuitable material(M3) 2040 3375 3375
Today Week todate Mth todate
Manhours (Hour) 564 4704 4704
Subcontractor (Hours) 0 0 0
No of Visitor
Day Activities
1 Excavation and zone A fill at the-north box cut

2 placing and spreading of waste rocks at west buttress

3 Removal and haulage of unsuitable material to unsuitable dump

Night Activities

1 placing and spreading of waste rocks at west buttress

2 Removal and haulage of unsuitable material to unsuitable dump

3 Excavation and zone A fill at the-north box cut

Prj. Todate

Prj. Todate
65120
72929.5
7536

3375
Prj. Todate
4704
0
Equipment
Used Down Stand by On Site
Type Day Night Day Night
Dozer CAT 1 1
Excavator 3 2
Loader CAT 0 0
ADT Truck 7 7
Grader 1 1
16t Compactor 0 0
Sheepfoot Compactor CAT 0 0
Water Bowser 0
Fuel Bowser 0
Backhoe CAT
Tyre handler
Forklift CAT
Lighting Plant 0 3
Gen Set
Staff Bus
Water Pump
Man deisel Truck
Light Vehicle 6 2
29-Aug-21 Sunday
Personnel
Category no.
Day Night Total
Project Manager 0 0 0
Project Engineer 0 0 0
Project Supervisor 1 1 2
Safety/ Evir. Staff 1 1 2
Maintenance supervisor 0 0 0
Survey Crew 1 0 1
QC/QA Crew 1 1 2
Operators 5 5 10
Maintenance Crew 0 0 0
Security 0 0 0
Spotters 1 1 2
Unskilled Labourer 4 0 4
Pump attendant 0 0 0
Chainsaw operator 0 0 0
Total 14 9 23
Weather
Today Week todate Mth todate
Rainfall / mm
Delay (hour) 0
Activity Quantity
Today Week todate Mth todate
Cleared area (m2)
Rockfill (m3)
Topsoil stripped area m3 0
spent ore m3 0
Zone F Material(M3) 864 864 864
Today Week todate Mth todate
Manhours (Hour) 276 276 276
Subcontractor (Hours) 36 36 36
No of Visitor

30-Aug-21 Monday
Personnel
Category no.
Day Night Total
Project Manager 0 0 0
Project Engineer 0 0 0
Project Supervisor 1 1 2
Safety/ Evir. Staff 1 1 2
Maintenance supervisor 0 0 0
Survey Crew 1 0 1
QC/QA Crew 1 1 2
Operators 5 5 10
Maintenance Crew 0 0 0
Security 0 0 0
Spotters 1 1 2
Unskilled Labourer 4 0 4
Pump attendant 0 0 0
Chainsaw operator 0 0 0
Total 14 9 23
Weather
Today Week todate Mth todate
Rainfall / mm
Delay (hour) 0
Activity Quantity
Today Week todate Mth todate
Cleared area (m2)
Rockfill (m3)
Topsoil stripped area m3 0
spent ore m3 600 600 600
Zone F Material(M3) 1032 1896 1896
Today Week todate Mth todate
Manhours (Hour) 276 552 552
Subcontractor (Hours) 36 72 72
No of Visitor

31-Aug-21 Tuesday
Personnel
Category no.
Day Night Total
Project Manager 0 0 0
Project Engineer 0 0 0
Project Supervisor 1 1 2
Safety/ Evir. Staff 1 1 2
Maintenance supervisor 0 0 0
Survey Crew 1 0 1
QC/QA Crew 1 1 2
Operators 5 5 10
Maintenance Crew 0 0 0
Security 0 0 0
Spotters 1 1 2
Unskilled Labourer 4 0 4
Pump attendant 0 0 0
Chainsaw operator 0 0 0
Total 14 9 23
Weather
Today Week todate Mth todate
Rainfall / mm
Delay (hour) 0
Activity Quantity
Today Week todate Mth todate
Cleared area (m2)
Rockfill (m3)
Topsoil stripped area m3 0
spent ore m3 1021 1621 1621
Zone F Material(M3) 0 1896 1896
Today Week todate Mth todate
Manhours (Hour) 276 828 828
Subcontractor (Hours) 36 108 108

1-Sep-21 Wednesday
Personnel
Category no.
Day Night Total
Project Manager 0 0 0
Project Engineer 0 0 0
Project Supervisor 1 1 2
Safety/ Evir. Staff 1 1 2
Maintenance supervisor 0 0 0
Survey Crew 1 0 1
QC/QA Crew 1 1 2
Operators 5 5 10
Maintenance Crew 0 0 0
Security 0 0 0
Spotters 1 1 2
Unskilled Labourer 4 0 4
Pump attendant 0 0 0
Chainsaw operator 0 0 0
Total 14 9 23
Weather
Today Week todate Mth todate
Rainfall / mm
Delay (hour) 0
Activity Quantity
Today Week todate Mth todate
Cleared area (m2)
Rockfill (m3)
Topsoil stripped area m3 0
spent ore m3 1021 2642 2642
Zone F Material(M3) 0 1896 1896
Today Week todate Mth todate
Manhours (Hour) 276 1104 1104
Subcontractor (Hours) 36 144 144

2-Sep-21 Thursday
Personnel
Category no.
Day Night Total
Project Manager 0 0 0
Project Engineer 0 0 0
Project Supervisor 1 1 2
Safety/ Evir. Staff 1 1 2
Maintenance supervisor 0 0 0
Survey Crew 1 0 1
QC/QA Crew 1 1 2
Operators 5 5 10
Maintenance Crew 0 0 0
Security 0 0 0
Spotters 1 1 2
Unskilled Labourer 4 0 4
Pump attendant 0 0 0
Chainsaw operator 0 0 0
Total 14 9 23
Weather
Today Week todate Mth todate
Rainfall / mm
Delay (hour) 0
Activity Quantity
Today Week todate Mth todate
Cleared area (m2)
Rockfill (m3)
Topsoil stripped area m3 0
spent ore m3 1021 3663 3663
Zone F Material(M3) 0 1896 1896
Today Week todate Mth todate
Manhours (Hour) 276 1380 1380
Subcontractor (Hours) 36 180 180

3-Sep-21 Friday
Personnel
Category no.
Day Night Total
Project Manager 0 0 0
Project Engineer 0 0 0
Project Supervisor 1 1 2
Safety/ Evir. Staff 1 1 2
Maintenance supervisor 0 0 0
Survey Crew 1 0 1
QC/QA Crew 1 1 2
Operators 5 5 10
Maintenance Crew 0 0 0
Security 0 0 0
Spotters 1 1 2
Unskilled Labourer 4 0 4
Pump attendant 0 0 0
Chainsaw operator 0 0 0
Total 14 9 23
Weather
Today Week todate Mth todate
Rainfall / mm
Delay (hour) 0
Activity Quantity
Today Week todate Mth todate
Cleared area (m2)
Rockfill (m3)
Topsoil stripped area m3 0
spent ore m3 986 4649 4649
Zone F Material(M3) 0 1896 1896
Today Week todate Mth todate
Manhours (Hour) 276 1656 1656
Subcontractor (Hours) 36 216 216
Day Activities
1

Night Activities

Prj. Todate

Prj. Todate
296208
1207298
11014.33

864
Prj. Todate
109548
3216

Day Activities
1

2
3

Night Activities

Prj. Todate

Prj. Todate
296208
1207298
11014.33
600
1896
Prj. Todate
109824
3252

Day Activities
1

Night Activities
1

Prj. Todate

Prj. Todate
296208
1207298
11014.33
1621
1896
Prj. Todate
110100
3288

Day Activities
1

Night Activities

4
Prj. Todate

Prj. Todate
296208
1207298
11014.33
2642
1896
Prj. Todate
110376
3324

Day Activities
1

Night Activities

Prj. Todate

Prj. Todate
296208
1207298
11014.33
3663
1896
Prj. Todate
110652
3360

Day Activities
1

Night Activities

Prj. Todate

Prj. Todate
296208
1207298
11014.33
4649
1896
Prj. Todate
110928
3396
Day Activities
Placing of Zone F material at the South Embankment

preparation of south embarkment to receive zone c material(Spent ore)

Night Activities

Placing of Zone F material at the South Embankment

preparation of south embarkment to receive zone c material(Spent ore)

Day Activities
Placing ,Spreading and compaction of zone c material at the South Embankment

placing ,Spreading of zone F material at the South Embankment


Night Activities

Placing ,Spreading and compaction of zone c material at the South Embankment

placing ,Spreading of zone F material at the South Embankment

Day Activities
Placing ,Spreading and compaction of zone c material at the South Embankment

placing ,Spreading of zone F material at the South Embankment

Night Activities
Placing ,Spreading and compaction of zone c material at the South Embankment

placing ,Spreading of zone F material at the South Embankment

Day Activities
Placing ,Spreading and compaction of zone c material at the South Embankment

Night Activities

Placing ,Spreading and compaction of zone c material at the South Embankment


Day Activities
Placing ,Spreading and compaction of zone c material at the South Embankment

Night Activities

Placing ,Spreading and compaction of zone c material at the South Embankment


Day Activities
Placing ,Spreading and compaction of zone c material at the South Embankment

Night Activities

Placing ,Spreading and compaction of zone c material at the South Embankment


Equipment
Used Down Stand by On Site
Type Day Night Day Night
Dozer CAT 1 1
Excavator 1 1
Loader CAT 1 1
ADT Truck 4 4
Grader 1 1
16t Compactor 3 3
Sheepfoot Compactor CAT 1 1
Water Bowser 1
Fuel Bowser 1
Backhoe CAT
Tyre handler
Forklift CAT
Lighting Plant 0 2
Gen Set
Staff Bus
Water Pump
Man deisel Truck
Light Vehicle 2 2

Equipment
Used Down Stand by On Site
Type Day Night Day Night
Dozer CAT 1 1
Excavator 1 1
Loader CAT 1 1
ADT Truck 4 4
Grader 1 1
16t Compactor 3 3
Sheepfoot Compactor CAT 1 1
Water Bowser 1
Fuel Bowser 1
Backhoe CAT
Tyre handler
Forklift CAT
Lighting Plant 0 2
Gen Set
Staff Bus
Water Pump
Man deisel Truck
Light Vehicle 2 2

Equipment
Used Down Stand by On Site
Type Day Night Day Night
Dozer CAT 1 1
Excavator 1 1
Loader CAT 1 1
ADT Truck 4 4
Grader 1 1
16t Compactor 3 3
Sheepfoot Compactor CAT 1 1
Water Bowser 1
Fuel Bowser 1
Backhoe CAT
Tyre handler
Forklift CAT
Lighting Plant 0 2
Gen Set
Staff Bus
Water Pump
Man deisel Truck
Light Vehicle 2 2

Equipment
Used Down Stand by On Site
Type Day Night Day Night
Dozer CAT 1 1
Excavator 1 1
Loader CAT 1 1
ADT Truck 4 4
Grader 1 1
16t Compactor 3 3
Sheepfoot Compactor CAT 1 1
Water Bowser 1
Fuel Bowser 1
Backhoe CAT
Tyre handler
Forklift CAT
Lighting Plant 0 2
Gen Set
Staff Bus
Water Pump
Man deisel Truck
Light Vehicle 2 2

Equipment
Used Down Stand by On Site
Type Day Night Day Night
Dozer CAT 1 1
Excavator 1 1
Loader CAT 1 1
ADT Truck 4 4
Grader 1 1
16t Compactor 3 3
Sheepfoot Compactor CAT 1 1
Water Bowser 1
Fuel Bowser 1
Backhoe CAT
Tyre handler
Forklift CAT
Lighting Plant 0 2
Gen Set
Staff Bus
Water Pump
Man deisel Truck
Light Vehicle 2 2
Equipment
Used Down Stand by On Site
Type Day Night Day Night
Dozer CAT 1 1
Excavator 1 1
Loader CAT 1 1
ADT Truck 4 4
Grader 1 1
16t Compactor 3 3
Sheepfoot Compactor CAT 1 1
Water Bowser 1
Fuel Bowser 1
Backhoe CAT
Tyre handler
Forklift CAT
Lighting Plant 0 2
Gen Set
Staff Bus
Water Pump
Man deisel Truck
Light Vehicle 2 2

You might also like