1377769905nitrogen Generator
Barrel Division
Vill. Piyala, Post. Asaoti
FARIDABAD – 121 102 (Haryana)
Tel. : 0129-2205073/2205322
Fax. : 0129-2215090
Address for Courier Correspondance :
Balmer Lawrie & Co,Ltd
C/O DTDC Courier & Cargo Services
GF-4, Rama Palace, Near Ajouranda Chowk,
Faridabad-haryana-121001
Contract No.- 9999976099,9813193623
M/s. __________________________
______________________________
Dear Sirs,
Balmer Lawrie & Co. Ltd., a Government of India Enterprises under Ministry of Petroleum & Natural
Gas is a multi-activity, multi technology, multi-location conglomerate with global footprints – along with
its joint Ventures, encompassing diverse interests in Manufacturing Sector via, Industrial Packaging,
Grease & Lubricants, Performance Chemicals and Tours & Travels, Logistics Infrastructure & Services
and Engineering & Technology Services.
Our Asaoti unit of SBU – Industrial Packaging is engaged in manufacturing of MS Drums & Barrels
which are supplied to M/s. India Oil Corporation, M/s. Bharat Petroleum Corporation, Ministry of
Defence and also various exporters in Food, Pharmaceuticals & Chemical Industries etc.
Tenders are invited from the reputed and experienced parties for “Supply, erection and
commissioning of Nigtrogen Generator”, as per Specifications & Scope of Work, given below
:
The sealed offers, alongwith a Demand Draft of Rs. 10,000/- (Rupees Ten Thousand) only in favour of
BALMER LAWRIE & CO. LTD. payable at FARIDABAD towards Earnest Money Deposit ( EMD ),
have to be submitted at our Faridabad Works address.
NOTE : All the bidders should quote their Excise Registrtion No./details,
VAT No./TIN No., CST No., PAN No., Service Tax Registration No.etc.,
PSA Nitrogen Gas generator of 100NM³/HR. capacity with 99.50% purity along with 20 M³
Nitrogen gas storage tank and purging device for drums with online O2 Gas Analyzer(without Air
Compressor) - 1 set.
has to quote for suitable purging device to match production capacity of 400 drums per hour. Drums will
be moving on a conveyor line while purging operation. The purpose of Nitrogen purging in the drums is
to avoid rusting of drum surface as drums are manufactured from Mild Steel CR steel sheets hence its
highly rust prone.
Scope of Supply:
1. One no. air receiver with auto drain trap, safety valve, low pressure switch, and pressure gauge.
2. One no. first stage activated carbon filter.
3. One set of 2nd and third stage Macro and Micro Oil removal and fine filters.
4. Twin tower PSA unit filled with first charge of imported carbon molecular sieves, activated
alumina, ceramic balls and coconut mesh, interconnected with 8nos. of PSA quick automatic
changeover valves operated with solenoid valves, pressure gauges and orifice plates.
5. One no. of Nitrogen gas surge vessel.
6. One no. of Nitrogen Gas Rotameter.
7. One no. of back pressure controller.
8. One no. of 3-Way vent valve.
9. Nitrogen gas storage tank of 20 M³ volume.
10. On-line percentage Oxygen gas analyzer.
11. Electronic controller for entire operation sequence.
12. Pressure indicators, pressure switches, safety valves and flow switches.
13. Centralized Electrical Control Unit.
14. All interconnected piping and fittings.
15. Erecting, Commissioning and operational training to plant people.
16. Suitable Purging Devices.
17. Any other accessories.
18. Adequate safety built ups in the system.
1. Air Receiver:
Operating Pressure : 7 Bar
Design Pressure : 12 Bar
Plate Thickness : 6mm
Design Code : IS-2825
Material of construction : IS-2062 Gr. II
4
General Conditions :
5
To ascertain the exact nature of job, the interested parties are advised to visit our Asaoti (Faridabad)
Plant and quote as per Annexure attached.
The offer should be valid for acceptance for a period of 60 days from the date of opening of tender with a
provision to extend the validity by another 30 days if required by the Company.
The successful tenderer has to provide all necessary lifting tools & tackles, consumables, safety gears
including skilled personnel at their own cost. The successful tenderer shall provide all costs towards
conveyance, food & lodging to their personnel.
The successful tenderer & their labourers will be allowed to work inside our premises at Asaoti
(Faridabad) any time between 9.30 A.M to 6 P.M on all working days of the week. The successful
tenderer has to submit written request to the Company providing detail of their persons e.g Name, Father's
name, age, address, category ( skilled/semi skilled/ un skilled) to obtain permission to work inside our
premises.
Please note that in case of any shutdown of the production line is required to complete the job, that
would be planned in consultation with Manager (Manufacturing).
The tenderer shall submit an Earnest Money Deposit [EMD] of Rs.10,000.00 (Rupees Ten thousand
only) along with the tender in the form of Demand Draft (DD)/Pay order drawn in favour of Balmer
Lawrie & Co. Ltd, issued by a scheduled bank payable at Faridabad, Cheque / Cash or any other
form of payment are not acceptable towards EMD.
Linking with earlier transactions/adjustments with pending bills of any other amount payable by the
company is not allowed.
EMD IS LIABLE TO FORFEITURE IN THE EVENT OF :
Withdrawal of offers during validity period of the offer.
Non acceptance of orders.
Non-confirmation of acceptance of orders within the stipulated time.
Any unilateral revision made by the tenderer during the validity period of the offer.
Non-executing of the documents after acceptance of the contract due to any dispute of the
tenderer or any reason whatsoever.
AWARD OF CONTRACT :
Only the Lowest Quoted (L1) party shall be considered for award of the contract. The company reserves
the right to reject the offers submitted by the tenderer s either in part or full without assigning any reasons
what so ever. The decision of the company is final in this regard.
SECURITY DEPOSIT :
The successful party shall be required to deposit 10% of the total order value towards Security
Deposit within 10 days from the date of receipt of confirmed order.
6
COMPLETION PERIOD :
The successful party should complete the job within 30 days after receipt of our Work Order.
The tenderer must ensure that their workmen abide by all the statutory safety norms and wears
safety gears as stipulated for working in factory premises and working at a height of 10 metres from
the floor during the work at site and also behave in a responsible and disciplined manner while at
work.
The successful tenderer shall be responsible for fulfilling all statutory obligations in respect of PF,
ESI, Laws and Injuries Act, etc., for their labour force working in company's premises. Necessary
contributions to above for their workmen shall be deposited by the successful tenderer. They shall
also provide complete information and furnish all records to the company whenever asked for. In
the event of any additional levies or penalties being imposed on this account ,the same,to be
remitted by the tenderer within the due dates with intimation to the company. In all respects,
tenderer will be responsible for employment, welfare, conduct, etc. of his employees.
iii] The contractor shall hold the company harmless and indemnified from and against all claims,
charges and costs for which the company may be held liable under the Workmen’s Compensation
Act 1923.
Employees Liability Act 1930 and amendments thereof and expenses which the company may be
made to bear by them in respect of personnel injuries to the servants and employees of the
company, arising out or occasion through the acts of commissions/omissions whether due to
negligence or not of the contractor or his agents or his employees in carrying out the job of the
contractor, will be the liability of the contractor.
iv] The contractor shall hold the company harmless and indemnified from all claims, costs and charges
for which the company may be held liable in respect of any loss of injury exchanged to any third
party through servants/employees/agents. This indemnity shall be in addition to, and not in lieu of
any indemnity towards the company may be entitled by law.
v] ARBITRATION
In case of any dispute, the COO (IP) or any person nominated by him will act as an Arbitrator.
The place of arbitration will be Delhi and language to be used for the arbitration proceeding will
be English.
The award of Arbitrator so appointed shall be final and conclusive and binding all parties to the
agreement subject to the Provisions of the Indian Arbitration and Conciliation Act, 1996, and the
rules there under and any statutory modification or re-enactment’s thereof deemed to apply to the
Arbitration proceedings under this clause.
7
It shall be understood that every Endeavour has been made to avoid error which may materially
affect the basis of the tender and the successful tenderer will take upon himself to provide for risk
of any error which may subsequently be discovered and shall make no subsequent claim on
account thereof.
AUTHORISED SIGNATORY
ANNEXURE – 1
Excise Duty
2.
8
3. CST /VAT
4. Packing & Forwarding
8. Guarantee
9. Warranty
Note : Please note that 5% of the order value shall be retained by us for a
period of six months from the date of commissioning of the equipment against
Performance Guarantee and will bear no interest.