Inspection & Test Plan for Owner : TUWAIQ CASTING & FORGING COMPANY Plan No.

:
Below Ground Water Proofing Works
Contractor : Doosan Heavy Industries & Construction Page No. :

Inspection Activity
Item Project Phase &
Inspection Process Applied Code Remarks
No. Activity Code
Sub-Con Contractor Owner

1.0 Material

Tech. Spec. &


1.1 Material Approval C H S/W
submittals

1.2 Material Delivery Inspection

2.0 Coating System

Tech. Spec &


2.1 Surface Preparation of Concrete C W S/W IC.1.1
Standard Drawing

2.2 Application of 1st Coat of Bitumen Coating Tech. Spec. C W S/W IC.1.2

2.3 Application of Final Coat of Bitumen Coating Tech. Spec. C W S/W IC.1.2

3.0 Tanking system

Tech. Spec &


3.1 Surface Preparation of Concrete C W S/W IC.1.3
Standard Drawing
Tech. Spec &
3.2 Application of Primer at concrete surface C W S/W IC.1.3
Standard Drawing
Tech. Spec &
3.3 Application of 1st layer of water proofing membrane C W S/W IC.1.3
Standard Drawing
Tech. Spec &
3.4 Installation of Protection board C W S/W IC.1.3
Standard Drawing
Tech. Spec &
3.5 Installation of Aluminium Falshing and sealant C W S/W IC.1.3
Standard Drawing

Note:

H : Hold Point for QC Inspection/ Test C : Control by Subcontractor

W : Witness Inspection/Test
Concrete Surface Preparation Checklist

Project Name : TUWAIQ CASTING AND FORGING FACILITY Contract No. :

Date : Reference No. :

Location : Subcon Name :

Status
S. No. Check Items Date
Accepted Rejected

A1 Confirm concrete is accepted.

A2 Confirm the surfaces cleaned of all contaminants.

Confirm the surfaces are free of dust, traces of curing compound, oil and
A3
grease.

A4 Confirm the surface imperfections, nail head protrusions are repaired.

Confirm unsound and friable concrete removed and repaired with a


A5
suitable

A6 Confirm all chamfers and fillets required for concrete are compeleted.

A7 Confirm the surface is dry.

REMARKS :

Submittd by Checked by Inspected by


Witnessed by
Sub-con. Contractor Contractor
Owner / PMC
Inspector Sign / Date Construction Sign / Date QC Inspector Sign / Date Sign / Date
Bitumen Coat Application Checklist

Project Name : TUWAIQ CASTING AND FORGING FACILITY Contract No. :

Date : Reference No. :

Location : Subcon Name :

Status
S. No. Check Items Date
Accepted Rejected

A1 Confirm approved material is available.

A2 Confirm the surfaces cleaned of all contaminants.

A3 Confirm surface inspection has been done and released for coating.

A4 Confirm the surface is dry.

A5 Check the Application of 1st coat of Bitumen is done.

A6 Check the Application of 2nd coat of Bitumen is done.

A7 Check both coats are completed and accepted.

REMARKS :

Submittd by Checked by Inspected by


Witnessed by
Sub-con. Contractor Contractor
Owner / PMC
Inspector Sign / Date Construction Sign / Date QC Inspector Sign / Date Sign / Date
Water Proofing system Application Checklist

Project Name : TUWAIQ CASTING AND FORGING FACILITY Contract No. :

Date : Reference No. :

Location : Subcon Name :

Status
S. No. Check Items Date
Accepted Rejected

A1 Checked and confirm material approval.

A2 Checked concrete surface preparation inspection completed.

A3 Checked primer coat application.

A4 Checked the layer water proofing membrane.

A5 Confirm that the member is not overheated.

Confirm the overlaps are heated and tipped trowel to seal the overlap
A6
and lap splice is provided as per manufacturer recommendation.

A7 Checked and confirm protection layer/protection Board

A8 Checked and inspect the insallation of flashing.

A7 Checked and inspect application of approved sealant.

REMARKS :

Submittd by Checked by Inspected by


Witnessed by
Sub-con. Contractor Contractor
Owner / PMC
Inspector Sign / Date Construction Sign / Date QC Inspector Sign / Date Sign / Date