Professional Documents
Culture Documents
Blowing Procedure
Blowing Procedure
Blowing Procedure
PROJECT NO.
CRYOGENIC NITROGEN UNIT,
HPCL, VIZAG, ANDHRA PRADESH 47000189
BLOWING PROCEDURE
Table of Contents
4. Safety -------------------------------------------------------------------------------------------------------- 5
01 47000189 1 of 7
Doc. No. Issue Date Project Number Page of pages
COMPRESSED AIR AND CRYOGENIC
PROJECT NO.
NITROGEN UNIT, HPCL, VIZAG, 47000189
ANDHRA PRADESH
The selection criteria can be described as defining the characteristics required in the current
situation. Each solution represents a compromise with advantages and disadvantages.
Before a decision is made about which cleaning method has to be used, the need for cleaning
must be considered and established. It might be possible to reduce cleaning operations by mak-
ing changes in the production process.
According to EIGA Typical methods for cleaning of components, vessels and pipe work sys-
tems used in oxygen service are summarized in the following section and include:
• Mechanical cleaning
• Chemical cleaning
• Detergent cleaning
• Hot water (steam) cleaning
• Emulsion cleaning
01 10/01/2022 47000189 2 of 7
Doc. No. Issue Date Project Number & Code Page of pages
COMPRESSED AIR AND CRYOGENIC
PROJECT NO.
NITROGEN UNIT, HPCL, VIZAG, 47000189
ANDHRA PRADESH
3.Blowing of Pipelines:
Linde uses pressurized air of Main air compressor for blowing the product lines. The quality of
air after Pre purification is as follows:
• This air is free from Oil
• Free from Hydrocarbons
• Free from moisture.
Standard document of LINDE for blowing is used as given in Blowing and section be used.
Temporary connection for blowing of product lines after PPU is generally made; flow through a
pipeline can be controlled either by manual valve or sometimes control valve whatever is avail-
able in the direction of flow.
01 10/01/2022 47000189 3 of 7
Doc. No. Issue Date Project Number & Code Page of pages
COMPRESSED AIR AND CRYOGENIC
PROJECT NO.
NITROGEN UNIT, HPCL, VIZAG, 47000189
ANDHRA PRADESH
P&ID checks to be performed before blowing of the pipelines, once after blowing modifications
are very difficult to do in the plant.
3.2 Blowing protocol and authorizations
Engineered air blowing is an efficient way to remove construction debris, loose rust, liquids, and
other contaminants from process piping. Every air blow procedure is specifically engineered for
the individual system being cleaned. This approach provides numerous benefits for our clients,
including time effective execution by efficiently sequencing the blows, thorough cleaning guar-
anteed by achieving an optimal cleaning force and safe field execution through following the
best industry practices.
For safety, protocol is used here to ensure that proper planning and preparation have been tak-
en prior to beginning of blowing, which presents hazards to personnel and equipment not ordi-
narily encountered in blowing and blasting operations. Compressed air is used for blowing in a
variety of applications within air separation industries. Applications include air blowing for the
cleaning and commissioning of new facilities or build systems, drying pipelines and systems
following hydro tests, pressure and leak testing, and heating and cooling of systems.
01 10/01/2022 47000189 4 of 7
Doc. No. Issue Date Project Number & Code Page of pages
COMPRESSED AIR AND CRYOGENIC
PROJECT NO.
NITROGEN UNIT, HPCL, VIZAG, 47000189
ANDHRA PRADESH
Once after last mentioned blowing is done, put a temporary orifice at PPU inlet T-Point accord-
ing to the plant specification for the back pressure in DCAC and Start Precooling unit. Continue
the blowing in a sequence as follows:
• PPU Skid
• Up to Cold Box Inlet.
• Cold Box Inlet to Main heat exchanger.
• Cold box outlet lines, Like GAN, Waste GAN.
3.6 Criteria:
Blowing of free dry air through the piping system shall be continued until the air coming out at
the end is free from any noticeable solid particles. To achieve high speeds, blowing should be
performed at low pressure, i.e., pressure reduction should occur at the start point of the system
being blown out. The air speed should be significantly greater than the speed encountered as
per process design. The speed of gas in the pipes is normally around 10-20 m/sec. For better
cleaning the speed should be in range of 40-50 m/sec.
Required flow for getting the speed in the pipeline shall be mentioned below considered based
on the velocity of 50 m/sec at free end: -
For 18” Pipe: - (3.14×0.4572×0.4572×50) ×3600 / 4 = 29536.2 m3/hr
For 16” Pipe:- (3.14×0.4064×0.4064×50) ×3600 / 4 = 23337.24 m3/hr
For 12” Pipe :- (3.14×0.3048×0.3048×50) ×3600 / 4 = 13127.2 m3/hr
For 10” Pipe :- (3.14×0.254×0.254×50) ×3600 / 4 = 9116.11 m3/hr
For 8” Pipe :- (3.14×0.2032×0.2032×50) ×3600 / 4 = 5834.31 m3/hr
For 6” Pipe :- (3.14×0.1524×0.1524×50) ×3600 / 4 = 3281.8 m3/hr
4.Safety
During blowing care must be taken to ensure the output pressure of the blowing. The piping
system being blown out should be isolated from the neighbouring system by closing valves. The
areas where compressed air leaves the system should be cordoned off against unauthorized
access. The local rules and regulations concerning safety, health environmental protection (dis-
posal) to be followed.
5.Responsibilities, Procedure
The local rules and regulations concerning safety, helath and environmental protection (dispos-
al) are to be followed.
The construction manager is responsible for cleaning pipes mechanically and verification of the
desired operational status in the following manner:
01 10/01/2022 47000189 5 of 7
Doc. No. Issue Date Project Number & Code Page of pages
COMPRESSED AIR AND CRYOGENIC
PROJECT NO.
NITROGEN UNIT, HPCL, VIZAG, 47000189
ANDHRA PRADESH
6.Documentation, QSE-Records
Protocol needs to be made & the same shall be signed by LINDE, EIL & HPCL representatives
before starting of the work. After completion of the individual application, relevant documents
required to be signed before processing of the next stage. After completion of the total process,
all signed documents shall be kept by LINDE, EIL & HPCL representatives & same shall be
handed over to the commissioning team and the pipelines shall be considered ready for charg-
ing.
The pipe cleaning performed is confirmed in the ready for operation report. One copy of the re-
port goes to the customer/consultant and one to the construction manager of LINDE.
Once the system has been approved and accepted, the report is administered and archived by
the department responsible for commissioning from client/consultant.
Note: Sequence may vary plant to plant due to different process flow designs. Blowing of
the cold box and product lines can be done but once after blowing is done thawing with
the dry air (once after readiness of Pre purification unit) should be performed.
01 10/01/2022 47000189 6 of 7
Doc. No. Issue Date Project Number & Code Page of pages
COMPRESSED AIR AND CRYOGENIC
PROJECT NO.
NITROGEN UNIT, HPCL, VIZAG, 47000189
ANDHRA PRADESH
01 10/01/2022 47000189 7 of 7
Doc. No. Issue Date Project Number & Code Page of pages