Download as pdf or txt
Download as pdf or txt
You are on page 1of 93

eni spa

COMPANY STANDARD

ELECTRICAL SYSTEM DESIGN

20208.ENG.ELE.PRG
Rev. 13 July 2021

This COMPANY Specification defines the minimum electrical design,


engineering and installation criteria to be used and the minimum
ABSTRACT
technical requirements for electrical equipment and materials to be
installed in both Eni onshore and offshore Oil & Gas facilities.

Digitally Signed by
SORIN RUGAN
02/08/2021
08:56:48

Firmato digitalmente da: Fabien Dominique Duclocher


Organizzazione: ENI SPA/00484960588
Unità organizzativa: UPSTREAM DOT
Motivo: Approved
Luogo: Milano
Data: 16/08/2021 16:21:49

Sorin Rugan
Paolo De
13 July 2021 Final Issue Giuseppe De Vincolis Fabien Duclocher
Bartolomeis
Massimo Gorlini
REV. DATE Reason for issue Prepared Verified Approved

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 2 of 93

REVISION TRACKING

Rev. 0: 28 pages - Date December 1995

Rev. 1: 34 pages - Date July 2003

Rev. 2: 40 pages - Date October 2006

Rev. 3: 48 pages - Date February 2009

Rev. 4: 49 pages - Date October 2016

Rev. 5: 48 pages - Date May2017

Rev. 6: 51 pages - Date May 2018

Rev. 7: 59 pages - Date December 2018

Rev. 8: 64 pages - Date June 2019

Rev. 9: 63 pages - Date December 2019

Rev. 10: 64 pages - Date July 2020

Rev. 11: current revision is of 78 pages


• Modified par. 1.1: “Scope”
• Modified par. 1.2.3: “Internal standardization references”
• Modified par. 2.1.1: “General definition”
• Modified par. 2.1.2: “Specific definition”
• Modified par. 2.2: “Symbols and abbreviations”
• Modified par. 2.4: “Operative environment”
• Modified par. 2.6.1: “Project technical review and assessment”
• Modified par. 2.6.4: “Certificates, declarations and test reports”
• Modified par. 2.6.5: “Energy efficiency”
• Modified par. 2.7.1: “General”
• Modified Table 1: “Loads Classification”
• Modified par. 2.7.2.2: “Load balance”
• Modified Table 2: “Rated Voltage and maximum voltage levels for the equipment”
• Modified Table 3: “Criteria for voltage levels selection”
• Modified par. 2.7.2.6: “Voltage and frequency variation”
• Modified par. 2.7.2.7: “Maximum value of rated current on switchgears bus-bars”
• Modified Table 4: “Maximum current and rated power on switchgears bus-bars”
• Modified par. 2.7.3: “Harmonic distortion”
• Modified par. 2.7.5: “Neutral earthing”
• Modified par. 2.7.7: “Electrical protection”
• Modified par. 2.7.7.1: “Short circuits protections”
• Modified par. 2.7.7.2: “Overloads protections”
• Modified par. 2.7.8: “Intertripping and interlocking”
• Modified par. 2.7.9.2: “Protection against lightning”
• Modified par. 2.7.10: “Emergency electrical system”
• Modified par. 2.7.11: “Black start requirements”
• Modified par. 2.7.12: “Motor starting system selection”
• Modified par. 2.7.15: “Safe shut down of machinery”
• Modified par. 2.8.1: “Insulation classes and temperature rises”
• Modified Table 7: “Electric machines: classes of insulation and over-
temperatures”

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 3 of 93

Modified par. 2.8.2: “Protection against explosion and fire hazards”



Modified par. 2.8.3.1: “External network connection”

Modified Table 8: “Selection criteria for RICE Diesel/Gas Generator”

Modified par. 2.8.4: “Switchgears” and subparagraphs

Modified par. 2.8.5: “Power transformers “ and subparagraphs

Modified par. 2.8.6: “Inductive shunt reactors”

Added par. 2.8.6.1: “Dry type reactors”

Added par. 2.8.6.2: “Oil immersed reactors”

Modified par. 2.8.7.1: “AC Uninterruptible Power Supply System”

Modified par. 2.8.7.2: “Selection of UPS scheme”

Modified par. 2.8.7.6: “Cut off battery box”

Modified par. 2.8.8: “Storage batteries”

Modified par. 2.8.9.3: “Motors supplied by power converters”

Modified par. 2.8.11: “Cables, wires and accessories”

Modified par. 2.8.11.3: “Battery cables”

Modified par. 2.8.11.4: “Cable system categories”

Modified par. 2.8.11.7: “Mechanical protection of cables”

Modified par. 2.8.11.8: “Cables screen”

Modified par. 2.8.11.9: “Minimum and maximum conductor section”

Modified par. 2.9.1: “Lighting system”

Modified par. 2.9.1.3: “Emergency escape lighting (EEL)”

Modified par. 2.9.2: “Motor Control Station”

Modified par. 2.9.3: “Power and convenience sockets”

Modified par. 2.9.4: “Conduits”

Modified par. 2.9.5: “Cable trays”

Modified par. 2.9.7: “Multi-cable Transit (MCT)”

Modified par. 2.10.1: “Electrical rooms”

Modified par. 2.10.1.2: “Transformer bay”

Modified par. 2.10.1.3: “Battery room”

Modified par. 2.10.2: “Cabling and wiring”

Modified par. 2.10.4: “Earthing system”

Modified par. 2.10.4.1: “HV substations”

Modified par. 2.10.4.2: “MV and LV substations”

Modified par. 2.10.4.4: “Metal structures, equipment and interconnecting”

Modified par. 3.1: “General”

Modified par. 3.2: “Neutral earthing”

Modified par. 3.3: “Protection against explosion and fire hazard”

Modified par. 3.4: “Protective device”

Modified par. 3.5: “Essential power generation system”

Deleted par. 3.6: “LV switchgear”

Modified par. 3.8.2: “IEC 61892-4 “Cables”

Modified par. 3.11: “Lighting”

Modified par. 3.12: “Navigation & aeronautical aids system for offshore platforms

and floaters”
Date December 2020

Rev. 12: current revision is of 85 pages


• Modified par. 1.1: “Scope”
• Modified par. 1.2.3: “Internal standardization references”
• Modified par. 2.1.2: “Specific definition”
• Modified par. 2.2: “Symbols and abbreviations”
• Modified par. 2.6.1: “Project technical review and assessment”
• Modified TABLE 4: “Maximum current and rated power on switchgears bus-bars”
• Modified par. 2.7.5.1: “Medium voltage systems”
• Modified par. 2.8.5.1: “General”
• Modified par. 2.8.5.2: “Dry type power transformers”

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 4 of 93

Modified par. 2.8.5.3: “Oil immersed power transformers”



Modified par. 2.8.7.7: “Selection of UPS autonomy”

Deleted Table 11 “UPS autonomy”

Modified par. 2.8.9.1: “Asynchronous motors”

Modified par. 2.8.11.1: “General requirements”

Added par. 2.8.11.10: “General requirements for CPR cables (applicable for EU

projects)”
• Modified par. 2.8.12: “Overhead transmission lines”
• Added par. 2.8.14: “Neutral earthing resistors”
• Added par. 2.8.15: “Electric process heaters”
• Added par. 2.8.16: “CAS levels”
• Modified par. 2.9.8: “Electrical resistance trace heating”
• Added par. 2.9.8.1: “Electrical resistance trace heating following IEC/IEEE
60079-30-1 and IEC/IEEE 60079-30-2”
• Added par. 2.9.8.2: “Electrical resistance trace heating following IEC 62395-1
and IEC 62395-2”
• Modified par. 2.9.9: “Junction boxes”
• Modified par. 2.10.1.2: “Transformer bay”
• Modified par. 3.3: “Protection against explosion and fire hazard”
• Modified par. 3.4: “Protective device”
• Modified par. 3.7.2: IEC 61892-4 “Cables”
• Added par. 3.7.5: “CPR Cables”
• Added par. 3.13: “Submarine cables”
Date February 2021

Rev. 13: current revision is of 93 pages


General revision
Date July 2021

INFORMATION REQUEST FOR COMPANY STANDARDS

Eni personnel can access COMPANY standard repository at:


http://wwweandp.eni.it/TSServices/TAE/company-documents-standards

External user shall refer to the Project Engineer Manager.

For information about the content of this standard, please refer to persons mentioned on first
page or to COMPANY Standard Team (mbxc&st@eni.com).

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 5 of 93

INDEX

1 GENERAL.............................................................................................. 9
SCOPE ................................................................................................. 9
NORMATIVE REFERENCES ................................................................... 9
1.2.1 International, IOGP and European standards 9
1.2.2 Laws, Decrees, Directives 20
1.2.3 Internal standardization references 20
2 FUNCTIONAL REQUIREMENT.............................................................. 24
DEFINITIONS.................................................................................... 24
2.1.1 General definition 24
2.1.2 Specific definition 24
SYMBOLS AND ABBREVIATIONS ....................................................... 26
GRAPHIC, SYMBOLS, CODES AND IDENTIFICATIONS TAG ................ 27
OPERATIVE ENVIRONMENT .............................................................. 27
MEASUREMENT UNITS ...................................................................... 27
DESIGN AND ENGINEERING PRINCIPLES ......................................... 27
2.6.1 Protection against explosion and fire hazard 27
2.6.2 Standardisation of equipment and materials 28
2.6.3 Certificates, declarations and test reports 28
2.6.4 Energy efficiency 28
ELECTRICAL SYSTEM DESIGN ........................................................... 28
2.7.1 General 28
2.7.2 Electrical loads classification and load balance 28
2.7.2.1 Loads Classification ....................................................................................... 28
2.7.2.2 Load balance ................................................................................................. 31
2.7.2.3 Rated voltage levels and maximum voltage for the equipment ..................... 31
2.7.2.4 Selection criteria of voltage levels ................................................................ 33
2.7.2.5 Voltage drops ................................................................................................ 34
2.7.2.6 Voltage and frequency variation ................................................................... 34
2.7.2.7 Maximum value of rated current on switchgears bus-bars ............................ 35
2.7.3 Power factor 35
2.7.4 Harmonics distortion 36
2.7.5 Neutral earthing 36
2.7.5.1 Medium Voltage systems ............................................................................... 36
2.7.5.2 LV systems .................................................................................................... 37
2.7.5.3 AC UPS systems ............................................................................................ 39
2.7.6 Power distribution configuration 39
2.7.7 Electrical protection 40
2.7.7.1 Short circuits protections .............................................................................. 40
2.7.7.2 Overloads protections ................................................................................... 41
2.7.8 Intertripping and interlocking 41
2.7.9 Earthing and lightning system 42
2.7.9.1 Earthing system ............................................................................................ 42
2.7.9.2 Protection against lightning .......................................................................... 42
2.7.10 Emergency electrical system 43
2.7.11 Black start requirements 43
2.7.12 Motor starting system selection 44
2.7.13 Electrical Management System (EMS) 44

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 6 of 93

2.7.14 Electrical studies and reports 44


2.7.15 Transformer impedances 44
ELECTRICAL EQUIPMENT DESIGN AND SELECTION CRITERIA .......... 44
2.8.1 Selection of insulation classes and temperature rise limits 44
2.8.2 Selection of protection methods against explosion and fire hazards 45
2.8.3 Power generation systems 45
2.8.3.1 External network connection......................................................................... 45
2.8.3.2 Generation system ........................................................................................ 46
2.8.3.3 Additional requirements for RICE Gas / Diesel Generator ............................. 46
2.8.3.4 Additional requirements for emergency diesel generator .............................. 47
2.8.4 Switchgears 47
2.8.4.1 MV Switchgears ............................................................................................. 47
2.8.4.2 LV Switchgears ............................................................................................. 49
2.8.5 Power transformers 53
2.8.5.1 General ......................................................................................................... 53
2.8.5.2 Dry type power transformers ........................................................................ 55
2.8.5.3 Oil immersed power transformers ................................................................. 56
2.8.5.4 Selection criteria of power transformers ....................................................... 56
2.8.6 Inductive shunt reactors 57
2.8.6.1 Dry type reactors .......................................................................................... 57
2.8.6.2 Oil immersed reactors ................................................................................... 58
2.8.7 UPS equipment and batteries 58
2.8.7.1 AC Uninterruptible Power Supply System ...................................................... 58
2.8.7.2 Selection of AC UPS scheme .......................................................................... 60
2.8.7.3 DC Uninterruptible Power Supply System...................................................... 61
2.8.7.4 Battery isolator box (AC and DC UPS) ........................................................... 62
2.8.7.5 Selection of UPS autonomy (AC and DC UPS) ................................................ 63
2.8.8 Storage batteries 63
2.8.9 Electric motors 64
2.8.9.1 MV asynchronous motors .............................................................................. 64
2.8.9.2 LV asynchronous motors ............................................................................... 65
2.8.9.3 Synchronous motors ..................................................................................... 65
2.8.10 Electrical Management System (EMS) 65
2.8.11 Cables, wires and accessories 65
2.8.11.1 General requirements ................................................................................ 66
2.8.11.2 Cable sizing criteria ................................................................................... 66
2.8.11.3 Battery cables ............................................................................................ 67
2.8.11.4 Cable system categories ............................................................................ 67
2.8.11.5 Cables in parallel........................................................................................ 68
2.8.11.6 Control/command cables ........................................................................... 68
2.8.11.7 Mechanical protection of cables ................................................................. 68
2.8.11.8 Cables screen ............................................................................................. 68
2.8.11.9 Minimum and maximum conductor section ................................................ 68
2.8.11.10 General requirements for CPR cables (applicable for EU projects) ............. 69
2.8.12 Overhead transmission lines 70
2.8.13 Decorative colours for electrical equipment 70
2.8.14 Neutral earthing resistors 70
2.8.15 Electric process heaters 71
2.8.16 CAS levels 71
2.8.17 Safe shutdown of machinery 72
2.8.18 Adjustable Speed Electrical Power Drive Systems 72
BULK MATERIALS .............................................................................. 72
2.9.1 Lighting system 72
2.9.1.1 Normal lighting (NL) ..................................................................................... 73

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 7 of 93
2.9.1.2 Emergency lighting (EL) ................................................................................ 73
2.9.1.3 Emergency escape lighting (EEL) .................................................................. 74
2.9.1.4 Additional requirements for lighting inside the buildings .............................. 75
2.9.1.5 Illumination level .......................................................................................... 75
2.9.2 Motor Control Station 75
2.9.3 Power and convenience sockets 76
2.9.4 Conduits 76
2.9.5 Cable trays 76
2.9.6 Cable glands 77
2.9.7 Multi-cable Transit (MCT) 77
2.9.8 Electrical resistance trace heating 77
2.9.8.1 Electrical resistance trace heating following IEC/IEEE 60079-30-1 and
IEC/IEEE 60079-30-2 ................................................................................................... 78
2.9.8.2 Electrical resistance trace heating following IEC 62395-1 and IEC 62395-2 . 78
2.9.9 Junction boxes 79
INSTALLATION REQUIREMENTS ....................................................... 79
2.10.1 Electrical rooms 79
2.10.1.1 Generator room.......................................................................................... 80
2.10.1.2 Transformer bay ........................................................................................ 80
2.10.1.3 Battery room .............................................................................................. 81
2.10.2 Cabling and wiring 81
2.10.3 Lighting system 82
2.10.4 Earthing system 82
2.10.4.1 HV substations ........................................................................................... 82
2.10.4.2 MV and LV substations ............................................................................... 83
2.10.4.3 Electric equipment ..................................................................................... 83
2.10.4.4 Metal structures, equipment and interconnecting ...................................... 83
2.10.4.5 Buildings .................................................................................................... 84
2.10.4.6 Metal fences ............................................................................................... 84
2.10.4.7 Tankers - mobile containers of flammable materials .................................. 85
2.10.4.8 Pipeline valve control rooms ...................................................................... 85
2.10.5 Lightning system 85
2.10.6 Aviation warning lighting 85
2.10.7 Power and convenience sockets 85
3 ADDITIONAL REQUIREMENTS FOR OFFSHORE PLANTS ......................87
GENERAL........................................................................................... 87
NEUTRAL EARTHING ......................................................................... 87
PROTECTION AGAINST EXPLOSION AND FIRE HAZARD .................... 88
PROTECTIVE DEVICE......................................................................... 88
ESSENTIAL POWER GENERATION SYSTEM ........................................ 89
CABLES ............................................................................................. 89
3.6.1 IEC 61892-2 “System design” 89
3.6.2 IEC 61892-4 “Cables” 90
3.6.3 IEC 61892-6 “Installation” 90
3.6.4 Other requirements 90
3.6.5 CPR cables 91
EARTHING AND BONDING ................................................................ 91
LIGHTNING PROTECTION SYSTEM .................................................... 91
LIGHTING ......................................................................................... 91

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 8 of 93

NAVIGATION & AERONAUTICAL AIDS SYSTEM FOR OFFSHORE


PLATFORMS AND FLOATERS ............................................................. 91
SWIVEL AND TURRET ........................................................................ 91
SUBMARINE CABLES ......................................................................... 92

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 9 of 93

1 GENERAL

SCOPE

This COMPANY Specification defines the minimum electrical design, engineering and installation
criteria to be used and the minimum technical requirements for electrical equipment and
materials to be installed in both Eni onshore and offshore Oil & Gas facilities.

This standard does not cover the following:


• Power generation plant exclusively connected to an external grid;
• HV substations;
• Cable transmission lines with Um>52 kV;
• Subsea systems;
• Downstream plants;
• Renewable power plants;
• Accommodation camps;
• Drilling rigs and associated users;
• Jetties;
• Transformer for Submersible pump;
• Submersible pump motors;
• Electric firefighting pumps;
• Erection, commissioning and start-up.

NORMATIVE REFERENCES

Materials and equipment shall fully comply with all requirements defined by the international/
European rules, laws, decrees, directives and internal standardization documents.

1.2.1 International, IOGP and European standards

This specification is primarily based on the publications of the International Electrotechnical


Commission (IEC) and on the relevant documents issued by the European Committee for
Electrotechnical Standardisation (CENELEC).
National standards of the country in which the installation will be located may be used in lieu of
IEC standards for the design and engineering of the electrical installation, provided they are not
less stringent in their total requirement. Equipment to be installed in the European Union Member
States shall have the appropriate ‘CE’ marking.
The latest edition of each publication shall be used, together with any
amendments/supplements/revisions. New revisions/updates during an activity or project may
not be considered, unless there are associated safety/environmental impacts.
The design of the electrical system shall comply with the standards listed in TABLE 1. National
standards are not included in this list. If the application of national standards is required in the
country of installation, these shall be added to the list.
If a standard number is followed by the words “all parts”, it shall include all parts of the standard,
including Technical Specifications (TS) and Technical Reports (TR).
If a standard included in the following list has been withdrawn, it shall be substituted by the
standard that has replaced it. If a standard has been withdrawn without replacement, it shall
not be applied and an agreement shall be reached between COMPANY and CONTRACTOR
regarding the technical requirements to be used instead of it.
If a standard refers to an agreement between parties, such agreement shall be subject to
COMPANY approval.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 10 of 93

For standards and specifications mentioned in the present document, if a requirement is


preceded or followed by expressions such as “unless defined otherwise in the data sheets”, the
possibility to change the requirement in the data sheet shall require the specific authorization of
COMPANY, unless the requirement adopted is more restrictive than the requirement of the
standard or specification.
The international or national standards referred in other international or national standards, or
in IOGP documents, or COMPANY standards, shall be considered mandatory at the same level of
the standard (or IOGP document) that refers to them, even if not explicitly mentioned in the
present specification.
The IOGP specifications mentioned in the present standard shall be considered integral part of
it.
TABLE 1: List of international and IOGP standards

Ref. Code Title


1 IEC 60034 (all parts) Rotating electrical machines
2 IEC 60038 IEC standard voltages
Direct acting indicating analogue electrical measuring
3 IEC 60051 (all parts)
instruments and their accessories
4 IEC 60060 (all parts) High-voltage test techniques
5 IEC 60068 (all parts) Environmental testing
Insulation co-ordination – Part 1: Definitions, principles
6 IEC 60071-1
and rules
7 IEC 60071-2 Insulation co-ordination – Part 2: Application guidelines
Dimensions and output series for rotating electrical
8 IEC 60072 (all parts)
machines
Basic and safety principles for man-machine interface,
9 IEC 60073 marking and identification – Coding principles for
indicators and actuators
10 IEC 60076 (all parts) Power transformers
11 IEC 60079 (all parts) Explosive atmospheres
Explosive atmospheres – Part 30-1: Electrical resistance
12 IEC/IEEE 60079-30-1
trace heating – General and testing requirements
Explosive atmospheres – Part 30-2: Electrical resistance
13 IEC/IEEE 60079-30-2 trace heating – Application guide for design,
installation and maintenance
14 IEC 60085 Electrical insulation – Thermal evaluation and designation
Electrical installations in ships – Part 350: General
construction and test methods of power, control and
15 IEC 60092-350
instrumentation cables for shipboard and offshore
applications
Electrical installations in ships – Part 353: Power cables
16 IEC 60092-353
for rated voltages 1 kV and 3 kV
Electrical installations in ships – Part 354: Single- and
three-core power cables with extruded solid insulation for
17 IEC 60092-354
rated voltages 6 kV (Um = 7,2 kV) up to 30 kV (Um = 36
kV)
Electrical installations in ships – Part 360: Insulating and
sheathing materials for shipboard and offshore units,
18 IEC 60092-360
power, control, instrumentation and telecommunication
cables
Electrical installations in ships – Part 376: Cables for
19 IEC 60092-376
control and instrumentation circuits 150/250 V (300 V)
20 IEC 60099 (all parts) Surge arresters
21 IEC 60146 (all parts) Semiconductor Converters

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 11 of 93

Safety of machinery – Electrical equipment of machines –


22 IEC 60204-1
Part 1: General requirements
Safety of machinery – Electrical equipment of machines –
23 IEC 60204-11 Part 11: Requirements for equipment for voltages above
1 000 V AC or 1 500 V DC and not exceeding 36 kV
Tap-changers – Part 1: Performance requirements and
24 IEC 60214-1
test methods
25 IEC/IEEE 60214-2 TAP-changers – Part 2: Application guidelines
26 IEC 60228 Conductors of insulated cables
27 IEC 60255 (all parts) Measuring relays and protection equipment
Secondary cells and batteries containing alkaline or other
28 IEC 62259 non-acid electrolytes – Nickel-cadmium prismatic
secondary single cells with partial gas recombination
Carbon brushes, brush holders, commutators and slip-
29 IEC 60276
rings – Definitions and nomenclature
30 IEC 60282-1 High-voltage fuses – Part 1: Current-limiting fuses
Low-voltage fuses – Part 4: Supplementary requirements
31 IEC 60269-4
for fuse-links for the protection of semiconductor devices
Low-voltage fuses - Part 6: Supplementary requirements
32 IEC 60269-6 for fuse-links for the protection of solar photovoltaic
energy systems
High-voltage test techniques – Partial discharge
33 IEC 60270
measurements
Electric cables – Calculation of the current rating – Part 1-
34 IEC 60287-1-1 1: Current rating equations (100 % load factor) and
calculation of losses – General
Standard Colours for Insulation for Low Frequency Cables
35 IEC 60304
and Wires
36 IEC 60364 (all parts) Low-voltage electrical installations
37 IEC 60529 Degrees of protection provided by enclosures (IP Code)
38 IEC 60721 (all parts) Classification of environmental conditions
Electric and optical fibre cables – Test methods for non-
39 IEC 60811 (all parts)
metallic materials
Stationary lead-acid batteries – Part 11: Vented types –
40 IEC 60896-11
General requirements and methods of tests
Stationary lead-acid batteries – Part 21: Valve regulated
41 IEC 60896-21
types – Methods of test
Stationary lead-acid batteries – Part 22: Valve regulated
42 IEC 60896-22
types – Requirements
43 IEC 60909 (all parts) Short-circuit currents in three-phase a.c. systems
Tests for electric cables under fire conditions – Circuit
44 IEC 60331 (all parts)
integrity
Tests on electric and optical fibre cables under fire
45 IEC 60332 (all parts)
conditions
Basic and safety principles for man-machine interface,
46 IEC 60445 marking and identification – Identification of equipment
terminals, conductor terminations and conductors
Power cables with extruded insulation and their
accessories for rated voltages from 1 kV (Um = 1,2 kV)
47 IEC 60502-1
up to 30 kV (Um = 36 kV) – Part 1: Cables for rated
voltages of 1 kV (Um = 1,2 kV) and 3 kV (Um = 3,6 kV)
Power cables with extruded insulation and their
48 IEC 60502-2 accessories for rated voltages from 1 kV (Um = 1,2 kV)
up to 30 kV (Um = 36 kV) – Part 2: Cables for rated

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 12 of 93

voltages from 6 kV (Um = 7,2 kV) up to 30 kV (Um = 36


kV)
Power cables with extruded insulation and their
accessories for rated voltages from 1 kV (Um = 1,2 kV)
49 IEC 60502-4 up to 30 kV (Um = 36 kV) – Part 4: Test requirements on
accessories for cables with rated voltages from 6 kV (Um
= 7,2 kV) up to 30 kV (Um = 36 kV)
Safety in installations for electroheating and
50 IEC 60519-1 electromagnetic processing – Part 1: General
requirements
Safety in electroheating installations – Part 10: Particular
51 IEC 60519-10 requirements for electrical resistance trace heating
systems for industrial and commercial applications
Electrical and electronic installations in ships –
52 IEC 60533 Electromagnetic compatibility (EMC) – Ships with a
metallic hull
53 IEC 60617 DATABASE Graphical symbols for diagrams
Secondary cells and batteries containing alkaline or other
54 IEC 60622 non-acid electrolytes – Sealed nickel-cadmium prismatic
rechargeable single cells
Secondary cells and batteries containing alkaline or other
55 IEC 60623 non-acid electrolytes – Vented nickel-cadmium prismatic
rechargeable single cells
Specification for high-voltage fuse-links for motor circuit
56 IEC 60644
applications
Insulation coordination for equipment within low-voltage
57 IEC 60664-1
systems – Part 1: Principles, requirements and tests
58 IEC 60684 (all parts) Flexible insulating sleeving
Fire hazard testing – Part 11-10: Test flames – 50 W
59 IEC 60695-11-10
horizontal and vertical flame test methods
Fire hazard testing – Part 11-20: Test flames – 500 W
60 IEC 60695-11-20
flame test method
Test on gases evolved during combustion of materials
61 IEC 60754-1 from cables – Part 1: Determination of the halogen acid
gas content
Test on gases evolved during combustion of materials
62 IEC 60754-2 from cables – Part 2: Determination of acidity (by pH
measurement) and conductivity
Selection and dimensioning of high-voltage insulators
63 IEC/TS 60815-1 intended for use in polluted conditions – Part 1:
Definitions, information and general principles
Power cables with extruded insulation and their
accessories for rated voltages above 30 kV (Um = 36 kV)
64 IEC 60840
up to 150 kV (Um = 170 kV) – Test methods and
requirements
Electrical test methods for electric cables. Part 2: Partial
65 IEC 60885-2
discharge tests
Electrical test methods for electric cables - Part 3: Test
66 IEC 60885-3 methods for partial discharge measurements on lengths of
extruded power cables
Photovoltaic devices – Procedures for temperature and
67 IEC 60891
irradiance corrections to measured I-V characteristics
68 IEC 60904 (all parts) Photovoltaic devices
69 IEC 60947 (all parts) Low-voltage switchgear and controlgear

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 13 of 93

Short-circuit temperature limits of electric cables with


70 IEC 60986 rated voltages from 6 kV (Um = 7,2 kV) up to 30 kV (Um
= 36 kV)
71 IEC 61000 (all parts) Electromagnetic compatibility (EMC)
Measurement of smoke density of cables burning under
72 IEC 61034-1
defined conditions – Part 1: Test apparatus
Measurement of smoke density of cables burning under
73 IEC 61034-2 defined conditions – Part 2: Test procedure and
requirements
74 IEC 61131 (all parts) Programmable controllers
75 IEC 61310 (all parts) Safety of machinery – Indication, marking and actuation
Electrical installations of ships and mobile and fixed
76 IEC 61363-1 offshore units – Part 1: Procedures for calculating short-
circuit currents in three-phase a.c.
Low-voltage power supply devices, d.c. output –
77 IEC 61204 (all parts)
Performance characteristics
Terrestrial photovoltaic (PV) modules – design
78 IEC 61215 (all parts)
qualification and type approval
Converter transformers – Part 1: Transformers for
79 IEC 61378-1
industrial applications
80 IEC 61378-3 Converter transformers – Part 3: Application guide
81 IEC 61400 (all parts) Wind energy generation systems
Secondary cells and batteries for renewable energy
82 IEC 61427-1 storage - General requirements and methods of test - Part
1: Photovoltaic off-grid application
83 IEC 61439 (all parts) Low-voltage switchgear and controlgear assemblies
Test methods for accessories for power cables
84 IEC 61442 with rated voltages from 6 kV (Um = 7,2 kV) up to 30 kV
(Um = 36 kV)
Functional safety of electrical/electronic/programmable
85 IEC 61508 (all parts)
electronic safety-related systems
Functional safety – Safety instrumented systems for the
process industry sector – Part 1: Framework, definitions,
86 IEC 61511-1
system, hardware and application programming
requirements
Cable management – Cable tray systems and cable ladder
87 IEC 61537
systems
Safety of transformers, reactors, power supply units and
88 IEC 61558 (all parts)
combinations thereof
Enclosed low-voltage switchgear and controlgear
89 IEC TR 61641 assemblies – Guide for testing under conditions of arcing
due to internal fault
90 IEC 61643 (all parts) Low-voltage surge protective devices
Short-circuit currents in d.c. auxiliary installations in
91 IEC 61660 (all parts)
power plants and substations
Electrical measuring transducers for converting A.C. and
92 IEC 60688
D.C. electrical quantities to analogue or digital signals
93 IEC 61701 Photovoltaic (PV) module – Salt mist corrosion testing
94 IEC 61730 (all parts) Photovoltaic (PV) module safety qualification
Industrial platinum resistance thermometers and platinum
95 IEC 60751
temperature sensors
96 IEC 61800 (all parts) Adjustable speed electrical power drive systems
97 IEC 61810 (all parts) Electromechanical elementary relays
Solar photovoltaic energy systems – Terms, definitions
98 IEC TS 61836
and symbols

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 14 of 93

Communication networks and systems for power utility


99 IEC 61850 (all parts)
automation
Photovoltaic (PV) module performance testing and energy
100 IEC 61853 (all parts)
rating
101 IEC 61869 (all parts) Instrument transformers
102 IEC 61892 (all parts) Mobile and fixed offshore units – Electrical installations
Low-voltage switchgear and controlgear – Overcurrent
103 IEC/TR 61912-1 and 2
protective devices
Power installations exceeding 1 kV a.c. – Part 1: Common
104 IEC 61936-1
rules
105 IEC 62040 (all parts) Uninterruptible power systems (UPS)
Transformers, power supplies, reactors and similar
106 IEC 62041
products – EMC requirements
Concentrator photovoltaic (CPV) modules and assemblies
107 IEC 62108
– Design qualification and type approval
Safety of power converters for use in photovoltaic power
108 IEC 62109 (all parts)
systems
Photovoltaic (PV) stand-alone systems - Design
109 IEC 62124
verification
Composite station post insulators for substations with a.c.
110 IEC 62231 voltages greater than 1 000 V up to 245 kV – Definitions,
test methods and acceptance criteria
Degrees of protection provided by enclosures for electrical
111 IEC 62262
equipment against external mechanical impacts (IK code)
112 IEC 62271 (all parts) High-voltage switchgear and controlgear
Electrical resistance trace heating systems for industrial
113 IEC 62395-1 and commercial applications – Part 1: General and testing
requirements
Electrical resistance trace heating systems for industrial
114 IEC 62395-2 and commercial applications – Part 2: Application guide
for system design, installation and maintenance
Safety requirements for power electronic converter
115 IEC 62477-1
systems and equipment – Part 1: General
Concentrator photovoltaic (CPV) modules and assemblies
116 IEC 62688
– Safety qualification

117 IEC/TS 62727 Photovoltaic systems – Specification for solar trackers

Application of IEC 62471 for the assessment of blue light


118 IEC TR 62778:2014
hazard to light sources and luminaires
Photovoltaic systems – Design qualification of solar
119 IEC 62817
trackers
120 IEC 62305 (all parts) Protection against lightning
Industrial communication networks - High availability
121 IEC 62439 (all parts)
automation networks
Industrial communication networks – Network and system
122 IEC 62443 (all parts)
security
123 IEC 62444 Cable glands for electrical installations
124 IEC 62471 Photobiological safety of lamps and lamp systems
Safety requirements for secondary batteries and battery
125 IEC 62485-1
installations – Part 1: General safety information
Safety requirements for secondary batteries and battery
126 IEC 62485-2
installations – Part 2: Stationary batteries
Battery charge controllers for photovoltaic systems –
127 IEC 62509
Performance and functioning

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 15 of 93

128 IEC 62548 Photovoltaic (PV) arrays – Design requirements


Junction boxes for photovoltaic modules – Safety
129 IEC 62790
requirements and tests
130 IEC 62894 Photovoltaic inverters – Data sheet and name plate
Photovoltaic power generating systems - EMC
131 IEC 62920 requirements and test methods for power conversion
equipment
Electrical cables for photovoltaic systems with a voltage
132 IEC 62930
rating of 1,5 kV DC
Photovoltaic modules – Bypass diode – Thermal runaway
133 IEC 62979
test
Submarine power cables with extruded insulation and
their accessories for rated voltages from 6 kV (Um = 7,2
134 IEC 63026
kV) up to 60 kV (Um = 72,5 kV) – Test methods and
requirements
Lightning and surge voltage protection for photovoltaic
135 IEC TR 63227
(PV) power supply systems
Measurement protocols for photovoltaic devices based on
136 IEC TR 63228
organic, dye-sensitized or perovskite materials
137 IEC 80000-6 Quantities and units – Part 6: Electromagnetism
138 EN 1838 Lighting applications - Emergency lighting
Light and lighting — Lighting of work places
139 EN 12464-1
Part 1: Indoor work places
Light and lighting — Lighting of work places
140 EN 12464-2
Part 2: Outdoor work places
Overhead electrical lines exceeding AC 1 kV
141 EN 50341-1
Part 1: General requirements - Common specifications
142 EN 50522 Earthing of power installations exceeding 1 kV a.c.
Industrial, scientific and medical equipment - Radio-
143 EN 55011 frequency disturbance characteristics - Limits and
methods of measurement
144 ISO 80000 (all parts) Quantities and units
Reciprocating internal combustion engine driven
145 ISO 8528-1 alternating current generating sets — Part 1: Application,
ratings and performance
IEEE Standard for Electrical Power System Device Function
146 IEEE Std C37.2™
Numbers, Acronyms, and Contact Designations
IEEE Recommended Practice and Requirements for
147 IEEE Std 519™
Harmonic Control in Electric Power Systems
148 CAP 437 Standards for offshore helicopter landing areas
149 IALA O-139 The Marking of Man-Made Offshore Structures
Supplementary Specification to IEC 62271-200 High-
150 IOGP S-620
voltage switchgear and controlgear
Supplementary Requirements to IEC 61439-1 & 2 LV
151 IOGP S-560
Switchgear & Controlgear
Supplementary Specification to IEC 62040-3 AC
152 IOGP S-701
Uninterruptible Power Systems (UPS)
Supplementary Specification to IEC 62040-5-3 DC
153 IOGP S-702
Uninterruptible Power Systems (UPS)
Supplementary Specification to IEC 60034-1 Low Voltage
154 IOGP S-703
Three Phase Cage Induction Motors
Supplementary Specification to IEC 60034-1 High Voltage
155 IOGP S-704
Three Phase Cage Induction Motors
156 IOGP S-720 Supplementary Specification to IEC 60076-1 Transformers
157 IOGP S-723 Specification for Electric Process Heaters

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 16 of 93

158 IOGP S-740 Specification for Batteries

For facilities in Italy, the international and IOGP standards of the TABLE 1 shall be applied, with
the following amendments:
• If there is a “CEI EN” standard with the same number as the corresponding IEC standard,
the “CEI EN” standard shall be applied in lieu of the IEC one (e.g. CEI EN 61439 in lieu
of IEC 61439).
• If there is a “CEI” standard that replaces an IEC standard, identical or with modifications,
the CEI standard shall be applied (e.g. CEI 64-8 in lieu of IEC 60364).
• The standards indicated in TABLE 2 shall be applied in addition to those of TABLE 1.
• The cables shall be as indicated in 2.8.11.10.
• IEC 60502 series shall not be used.
• IEC 60092 series shall not be used for cables.

TABLE 2: Additional standards for facilities in Italy

Ref. Code Title


Guida per la definizione della documentazione di progetto
159 CEI 0-2
degli impianti elettrici
Dichiarazione CE di conformità - Guida all’applicazione
160 CEI 0-5 delle Direttive Nuovo Approccio e della Direttiva Bassa
Tensione (Memorandum CENELEC N 3)
Guida all'applicazione del DPR 462/01 relativo alla
semplificazione del procedimento per la denuncia di
161 CEI 0-14 installazioni e dispositivi di protezione contro le scariche
atmosferiche, di dispositivi di messa a terra degli impianti
elettrici e di impianti elettrici pericolosi
Regola tecnica di riferimento per la connessione di Utenti
162 CEI 0-16 attivi e passivi alle reti AT e MT delle imprese distributrici
di energia elettrica
Regola tecnica di riferimento per la connessione di Utenti
163 CEI 0-21 attivi e passivi alle reti BT delle imprese distributrici di
energia elettrica
CEI 14-4/8 (instead of IEC
164 Powers transformers - Application guide
60076-8)
CEI 14-15 (instead of IEC Power transformers Part 7: Loading guide for oil-
165
60076-7) immersed power transformers
CEI 14-41 (instead of IEC
166 Tap-changers – Part 2: Application guide
60214-2)
167 CEI 16-6 Codice di designazione dei colori
Elementi per identificare i morsetti e la terminazione dei
168 CEI 16-7
cavi
Low-voltage switchgear and controlgear - Overcurrent
CEI 17-97/1 (instead of
169 protective devices
IEC/TR 61912-1)
Part 1: Application of short-circuit ratings
Electrical installations of ships and mobile
CEI 18-57 (instead of IEC
170 and fixed offshore units – Part 1: Procedures for
61363-1)
calculating short-circuit currents in three-phase a.c.
CEI 18-58, 18-59, 18-60,
171 18-61, 18-62, 18-63, 18-64 Mobile and fixed offshore units – Electrical installations
(instead of IEC 61892)
Cavi con isolamento estruso in gomma per tensioni
172 CEI 20-13
nominali da 1 kV a 30 kV

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 17 of 93

Electric cables – Calculation of the current rating – Part 1-


CEI 20-21/1-1 (instead of
173 1: Current rating equations (100 % load factor) and
IEC 60287-1-1)
calculation of losses – General
Cavi senza alogeni isolate in gomma, non propaganti
174 CEI 20-38 l’incendio, per tensioni nominali U0/U non superiori a 0,6/1
kV
Cavi per energia isolati in gomma elastomerica ad alto
modulo di qualità G18, sotto guaina termoplastica o
elastomerica, con particolari caratteristiche di reazione al
175 CEI 20-45 fuoco rispondenti al Regolamento Prodotti da Costruzione
(CPR)
Cavi con caratteristiche aggiuntive di resistenza al fuoco.
Tensione nominale U0/U: 0,6/1 kV
Cavi elettrici isolati con materiale elastomerico,
termoplastico e isolante minerale per tensioni nominali
non superiori a 1000 V in corrente alternata e 1500 V in
176 CEI 20-65
corrente continua
Metodi di verifica termica (portata) per cavi raggruppati in
fascio contenente conduttori di sezione differente
Power cables with extruded insulation and their
CEI 20-66 (instead of IEC
177 accessories for rated voltages above 36 kV (Um = 42 kV)
60840)
up to 150 kV (Um = 170 kV)
178 CEI 20-67 Guida per l’uso dei cavi 0,6/1 kV
Limitatori di sovratensioni di bassa tensione
CEI 37-11 (instead of IEC
179 Parte 12: Limitatori di sovratensioni connessi a sistemi di
61643-12)
bassa tensione – Scelta e principi di applicazione
Impianti elettrici utilizzatori a tensione nominale non
CEI 64-8 (all parts, instead
180 superiore a 1 000 V in corrente alternata e a 1 500 V in
of IEC 60364)
corrente continua
Guida d'applicazione all'utilizzo di limitatori di
181 CEI 81-27 sovratensioni all'arrivo della linea di alimentazione degli
impianti elettrici utilizzatori di bassa tensione
Guida alla protezione contro i fulmini degli impianti
182 CEI 81-28
fotovoltaici
Guida per l’esecuzione di cabine elettriche MT/BT del
183 CEI 99-4
cliente/utente finale
Guida per l’esecuzione degli impianti di terra delle utenze
184 CEI 99-5 attive e passive connesse ai sistemi di distribuzione con
tensione superiore a 1 kV in c.a.
185 CEI 301-1 Azionamenti elettrici - Dizionario
Guida per la caratterizzazione ed identificazione degli
186 CEI 301-3 azionamenti elettrici a velocità variabile per mezzo della
targa
Method of test for resistance to fire of unprotected small
187 CEI EN 50200
cables for use in emergency circuits
Test of insulation of bars and coils of high-voltage
188 CEI EN 50209
machines
189 CEI EN 50216 (all parts) Power transformers and reactor fittings
Bushings for transformers and reactor cable boxes not
190 CEI EN 50336
exceeding 36 kV
Linee elettriche aeree con tensione superiore a 1 kV in c.a.
191 CEI EN 50341-2-13 Parte 2-13: Aspetti Normativi Nazionali (NNA) per l'Italia
(basati sulla EN 50341-1:2012)
Overhead electrical lines exceeding AC 45 kV Part 3: Set
192 CEI EN 50341-3
of National Normative Aspects

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 18 of 93

General purpose three-phase induction motors having


193 CEI EN 50347 standard dimensions and outputs
Frame numbers 56 to 315 and flange numbers 65 to 740
Marking and documentation requirements for Photovoltaic
194 CEI EN 50380
Modules
Common test methods for cables under fire conditions -
Heat release and smoke production measurement on
195 CEI EN 50399
cables during flame spread test – Test apparatus,
procedures, results
Solar cells - Datasheet information and product data for
196 CEI EN 50461
crystalline silicon solar cells
197 CEI EN 50524 Data sheet and name plate for photovoltaic inverters
Medium power transformers 50 Hz, with highest voltage
198 CEI EN 50588 (all parts)
for equipment not exceeding 36 kV
Power, control and communication cables - Cables for
199 CEI EN 50575 general applications in construction works subject to
reaction to fire requirements
200 CEI EN 50708 (all parts) Power transformers - Additional European requirements
Characteristic parameters of stand-alone photovoltaic
201 CEI EN 61194
(PV) systems
202 CEI-UNEL 00721 Colori di guaina dei cavi elettrici
203 CEI-UNEL 00722 Identificazione delle anime dei cavi
Cavi per energia e segnalamento
204 CEI-UNEL 35011
Sigle di designazione
Classe di Reazione al fuoco dei cavi in relazione al
205 CEI-UNEL 35016
Regolamento EU "Prodotti da Costruzione" (305/2011)
Cavi elettrici isolati con materiale elastomerico o
termoplastico per tensioni nominali non superiori a 1000
206 CEI-UNEL 35024
V in corrente alternata e a 1500 V in corrente continua
Portate di corrente in regime permanente per posa in aria
Cavi elettrici isolati con materiale elastomerico o
termoplastico per tensioni nominali di 1000 V in corrente
207 CEI-UNEL 35026 alternata e 1500 V in corrente continua
Portate di corrente in regime permanente per posa
interrata
Cavi per energia isolati in gomma elastomerica di qualità
G18, sotto guaina termoplastica o elastomerica, con
particolari caratteristiche di reazione al fuoco e rispondenti
208 CEI-UNEL 35312 al Regolamento Prodotti da Costruzione (CPR)
Cavi con conduttori flessibili per posa fissa - Tensione
nominale Uo/U 0,6/1kV - Classe di reazione al fuoco:
B2ca-s1a,d1,a1
Cavi per energia isolati in gomma etilenpropilenica, ad alto
modulo di qualità G16 sotto guaina termoplastica di
qualità M16, con particolari caratteristiche di reazione al
fuoco e rispondenti al Regolamento Prodotti da
209 CEI-UNEL 35324 Costruzione (CPR)
Cavi unipolari e multipolari con conduttori flessibili per
posa fissa con o senza schermo (treccia o nastro) -
Tensione nominale Uo/U 0,6/1kV - Classe di reazione al
fuoco: Cca-s1b,d1,a1
Fire classification of construction products and building
210 UNI EN 13501-6 elements - Part 6: Classification using data from reaction
to fire tests on power, control and communication cables

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 19 of 93

For facilities in countries that are members of CENELEC, the international and IOGP standard of
the TABLE 1 shall be applied, with the following amendments:
• If there is a “EN” or “HD” standard with the same number as the corresponding IEC
standard, it shall be applied in lieu of the IEC one (e.g. EN 61439 in lieu of IEC 61439).
• If there is a “EN” standard that replaces an IEC standard, identical or with modifications,
the EN standard shall be applied.
• The standards indicated in TABLE 3 shall be applied in addition to those of TABLE 1.
• The cables shall be as indicated in 2.8.11.10, for facilities in countries of the European
Union.
• IEC 60502 series shall not be used for facilities in countries of the European Union.
• IEC 60092 series shall not be used for cables in facilities in countries of the European
Union.
• Application of national standards shall be evaluated on project basis.

TABLE 3: Additional standards for facilities in countries members of CENELEC

Ref. Code Title


Fire classification of construction products and building
211 EN 13501-6 elements - Part 6: Classification using data from reaction
to fire tests on power, control and communication cables
Method of test for resistance to fire of unprotected small
212 EN 50200
cables for use in emergency circuits
Test of insulation of bars and coils of high-voltage
213 EN 50209
machines
214 EN 50216 (all parts) Power transformers and reactor fittings
Bushings for transformers and reactor cable boxes not
215 EN 50336
exceeding 36 kV
Overhead electrical lines exceeding AC 1 kV
216 EN 50341-2 (all parts)
National Normative Aspects (NNA)
Overhead electrical lines exceeding AC 45 kV Part 3: Set
217 EN 50341-3
of National Normative Aspects
General purpose three-phase induction motors having
218 EN 50347 standard dimensions and outputs
Frame numbers 56 to 315 and flange numbers 65 to 740
Marking and documentation requirements for Photovoltaic
219 EN 50380
Modules
Common test methods for cables under fire conditions -
Heat release and smoke production measurement on
220 EN 50399
cables during flame spread test – Test apparatus,
procedures, results
Solar cells - Datasheet information and product data for
221 EN 50461
crystalline silicon solar cells
222 EN 50524 Data sheet and name plate for photovoltaic inverters
Medium power transformers 50 Hz, with highest voltage
223 EN 50588 (all parts)
for equipment not exceeding 36 kV
Power, control and communication cables - Cables for
224 EN 50575 general applications in construction works subject to
reaction to fire requirements
225 EN 50708 (all parts) Power transformers - Additional European requirements
Characteristic parameters of stand-alone photovoltaic
226 EN 61194
(PV) systems

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 20 of 93

1.2.2 Laws, Decrees, Directives

In any case, all Laws, Decrees and Directives, issued by local Entities and Authorities under
which equipment shall be installed, shall be applied.
The Regulation 305/2011 of the European Parliament and of the Council (“REGULATION (EU) No
305/2011 OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 9 March 2011 laying down
harmonised conditions for the marketing of construction products and repealing Council Directive
89/106/EEC”) and its interpretation through National Laws and Committee shall be complied
with for cables installed in EU.
The Directive 2013/35/EU of the European Parliament and of the Council (“DIRECTIVE
2013/35/EU OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL of 26 June 2013 on the
minimum health and safety requirements regarding the exposure of workers to the risks arising
from physical agents (electromagnetic fields) (20th individual Directive within the meaning of
Article 16(1) of Directive 89/391/EEC) and repealing Directive 2004/40/EC”) shall also be
applicable outside EU, in the cases indicated in the present document.

1.2.3 Internal standardization references

All systems, equipment, materials and engineering philosophies relevant to this specification,
shall comply with the COMPANY Standards listed here below:
• 20056.ENG.ELE.STD “Explosion-proof connection box with contactor for shedding”
• 02947.ENG.ELE.STD “Measurement of earth electrical resistivity”
• 03778.ENG.ELE.STD “Electric generator driven by gas turbine”
• 20213.ENG.ELE.STD “Diesel\gas driven engine generator set”
• 20231.ENG.ELE.PRG “Minimum technical content of documents for each project
development phase”
• 20168.ENG.ELE.STD “Synchronous electric machines”
• 28881.ENG.ELE.STD “M.V. switchgear and controlgear (over 1000V a.c. and up 52kV
a.c.) - typical incoming / outgoing feeders”
• 28880.ENG.ELE.STD “L.V. switchgear and controlgear assemblies (up to 1000 V a.c 1500
V d.c) – typical incoming / outgoing feeders”
• 20174.ENG.ELE.STD “Aids to navigation & helideck lighting system for offshore platforms
and floaters
• 28882.ENG.ELE.STD “AC uninterruptible power supply system - typical configurations”
• 28914.ENG.ELE.STD “Luminaires”
• 28915.ENG.ELE.STD “Electrical bulk material”
• 28916.ENG.ELE.STD “Cable ladders and cable trays”
• 28917.ENG.ELE.STD “Floodlight high masts”
• 20172.ENG.ELE.STD “High voltage substation with sulphur hexafluoride (SF6) insulated
metal-enclosed switchgear from 72.5 kV to 245 kV”
• 20173.ENG.ELE.STD “Air insulated high voltage substation from 52 kV to 245 kV”
• 20180.ENG.ELE.STD “Electrical Management System (EMS)”
The following COMPANY documents shall be complied with where referenced in the present
document:
• 20183.VAR.GEN.STD “Units of measurement”
• 20198.VAR.LCI.STD “Item numbering”
• 20452.ENG.MEC.PRG “Guideline for HVAC systems for offshore / FPSO production
installations”
• 20453.ENG.MEC.PRG “Guideline for HVAC systems for onshore production installations”
• 20456.ENG.STA.STD “Instrumentation & automation plants included In HVAC package”
• 20531.ENG.STA.STD “Measure, control, data processing and similar associated electronic
system protection subject to indirect lightning”
• 20532.ENG.STA.STD “Earthing systems for instrumentation plants”
• 21000.ENG.PRC.STD “Plant graphic symbology”

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 21 of 93

• 28045.ENG.STA.PRG “Minimum design requirements for instrumentation and control


systems”
• 29000.ENG.CPI.STD “Paintings and coatings for offshore and coastal structures”
• 29001.ENG.CPI.STD “Paintings and coatings for onshore facilities”
• opi hse 023 eni spa “Safety & Environmental Minimum Design Requirements”
The following COMPANY forms shall be utilized:

• MOD.ELE.RMA.022 “Data sheet for low voltage three phase cage induction motors (IOGP
S-703D)(TDS)”
• MOD.ELE.RMA.023 “Quality requirements for low voltage three phase cage induction
motors (IOGP S-703Q) (IDS)”
• MOD.ELE.RMA.024 “Information requirements for low voltage three phase cage induction
motors (IOGP S-703L) (DDS)”
• MOD.ELE.NAV.001 “Aids to navigation & helideck lighting system for offshore platforms
and floaters (TDS)”
• MOD.ELE.NAV.002 “Aids to navigation & helideck lighting system for offshore platforms
and floaters (IDS)”
• MOD.ELE.NAV.003 “Aids to navigation & helideck lighting system for offshore platforms
and floaters (DDS)”
• MOD.ELE.NAV.009 “Temporary navigation aids system (TDS)”
• MOD.ELE.NAV.010 “Temporary navigation aids system (IDS)”
• MOD.ELE.NAV.011 “Temporary navigation aids system (DDS)”
• MOD.ELE.MVS.001 “Data sheet for high voltage switchgear and controlgear (including
IOGP S-620D) (TDS)”
• MOD.ELE.MVS.002 “Quality requirements for high voltage switchgear and controlgear
(IOGP S-620Q) (IDS)”
• MOD.ELE.MVS.003 “Information requirements for high-voltage switchgear and
controlgear (IOGP S-620L) (DDS)”
• MOD.ELE.LVS.001 “Data sheets for IEC 61439 LV switchgear and controlgear assemblies
(including IOGP S-560D) (TDS)”
• MOD.ELE.LVS.002 “Purchaser order quality requirements (POQR) for IEC 61439 LV
switchgear and controlgear assemblies IOGP S-560Q) (IDS)”
• MOD.ELE.LVS.003 “Supplier deliverable requirements list (SDRL) for IEC 61439 LV
switchgear and controlgear assemblies (IOGP S-560L) (DDS)”
• MOD.ELE.LVS.008 “Electrical Power Unit - data sheet”
• MOD.ELE.GEN.005 “Electrical documentation and data books check list (DDS)”
• MOD.ELE.GEN.006 “Electrical production check list (DDS)”
• MOD.ELE.ACB.001 “Data Sheet for Batteries (IEC) (IOGP S-740D) (TDS)”
• MOD.ELE.ACB.002 “Quality Requirements for Batteries (IEC) (IOGP S-740Q) (IDS)”
• MOD.ELE.ACB.003 “Information Requirements for Batteries (IEC) (IOGP S-740L) (DDS)”
• MOD.ELE.UPS.001 “Data Sheet for AC Uninterruptible Power Systems (UPS) (IEC 62040-
3) (IOGP S-701D) (TDS)”
• MOD.ELE.UPS.002 “Quality Requirements for AC Uninterruptible Power Systems (UPS)
(IEC 62040-3) (IOGP S-701Q) (IDS)”
• MOD.ELE.UPS.003 “Information Requirements for AC Uninterruptible Power Systems
(UPS) (IEC 62040-3) (IOGP S-701L) (DDS)”
• MOD.ELE.UPS.005 “Data Sheet for DC Uninterruptible Power Systems (UPS) (IEC 62040-
5-3) (IOGP S-702D) (TDS)”
• MOD.ELE.UPS.006 “Quality Requirements for DC Uninterruptible Power Systems (UPS)
(IEC 62040-5-3) (IOGP S-702Q) (IDS)”
• MOD.ELE.UPS.007 “Information Requirements for DC Uninterruptible Power Systems
(UPS) (IEC 62040-5-3) (IOGP S-702L) (DDS)”
• MOD.ELE.ESH.001 “High voltage substation - technical data sheet (TDS)”
• MOD.ELE.ESH.002 “High voltage substation - inspection data sheet (IDS)”
• MOD.ELE.ESH.003 “High voltage substations - required documentation data sheet (DDS)”
• MOD.ELE.TRA.001 “Data sheet for transformers (IOGP S-720D) (TDS)”

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 22 of 93

• MOD.ELE.TRA.002 “Quality requirements for transformers (IOGP S-720Q) (IDS)”


• MOD.ELE.TRA.004 “Information requirements for transformers (IOGP S-720L) (DDS)”
• MOD.ELE.RMA.002 “Data Sheet for High Voltage Three-phase Cage Induction Motors
(IEC) (IOGP S-704D) (TDS)”
• MOD.ELE.RMA.003 “Quality Requirements for High Voltage Three-phase Cage Induction
Motors (IEC) (IOGP S-704Q) (IDS)”
• MOD.ELE.RMA.005 “Information Requirements for High Voltage Three-phase Cage
Induction Motors (IEC) (IOGP S-704L) (DDS)”
• MOD.ELE.RMA.007 “Synchronous motors - technical data sheet (TDS)”
• MOD.ELE.RMA.011 “Synchronous generators (TDS)”
• MOD.ELE.RMA.012 “Synchronous generators (IDS)”
• MOD.ELE.RMA.013 “Synchronous generators (DDS)”
• MOD.ELE.RMA.015 “Variable speed drives of medium and large power (TDS)”
• MOD.ELE.RMA.016 “Variable speed drives of medium and large power (IDS)”
• MOD.ELE.RMA.017 “Variable speed drives of medium and large power (DDS)”
• MOD.ELE.RMA.019 “Variable speed drives supplied with low voltage (TDS)”
• MOD.ELE.RMA.020 “Variable speed drives supplied with low voltage (IDS)”
• MOD.ELE.RMA.021 “Variable speed drives supplied with low voltage (DDS)”
• MOD.ELE.ETG.001 “Earthing resistors - technical data sheet (TDS)”
• MOD.ELE.ETG.002 “Resistors for earthing the neutral of electric systems - inspection data
sheet (IDS)”
• MOD.ELE.ETG.003 “Earthing resistors - required documentation data sheet (DDS)”
• MOD.ELE.ESY.006 “Overhead transmission line from 11kV up to 66kV - technical data
sheet (TDS)”
• MOD.ELE.ESY.007 “Overhead transmission line from 11kV up to 66kV - inspection data
sheet (IDS)”
• MOD.ELE.ESY.008 “Overhead transmission line from 11kV up to 66kV - required
documentation data sheet (DDS)”
• MOD.ELE.ESY.019 “Overhead transmission from 11 kV up to 45 kV - civil work (TDS)”
• MOD.ELE.ESY.021 “Overhead transmission from 11 kV up to 45 kV - material data sheet
(TDS)”
• MOD.ELE.PKG.001 “Diesel generating set - technical data sheet (TDS)”
• MOD.ELE.PKG.002 “Internal combustion generation set - inspection data sheet (IDS)”
• MOD.ELE.PKG.003 “Internal combustion generation set - inspection data sheet (IDS)”
• MOD.ELE.PKG.201 “Diesel/gas generating set - required documentation data sheet
(DDS)”
• MOD.ELE.ELN.001 “List analog and digital signals to system of supervision/monitoring,
control and protection of the electrical network (EMS) - I/O list”
• MOD.ELE.ESY.001 “Electrical load list - general data sheet (GDS)”
• MOD.ELE.EAM.001 “Electrical material list - list (LST)”
• MOD.ELE.EAM.002 “Electrical equipment list”
• MOD.ELE.CBL.001 “Electric cables - technical data sheet (TDS)”
• MOD.ELE.CBL.003 “Electric cables - required documentation data sheet (DDS)”
• MOD.ELE CBL.010 “Submarine electric cable (TDS)”
• MOD.ELE.CBL.012 “Competence submarine electrical cable - general data sheet (GDS)”
• MOD.ELE.CBL.013 “Submarine electric cable (DDS)”
• MOD.ELE.CBL.020 “Electrical cable list - list (LST)”
• MOD.ELE.CBL.030 “Electrical interconnecting list (LST)”
• MOD.ELE.CBL.040 “Electrical system-summary of power circuits and protection
verification”
• MOD.ELE.GEN.002 “Data sheet for measurement of soil electric resistivity”
• MOD.ELE.BLK.010 “EEx-d connection box shedding battery (TDS)”
• MOD.ELE.ESY.020 “Electrical load balance”
• MOD.ELE.FMX.007 “Data Sheet for Electric Process Heaters (IOGP S-723D) (TDS)”
• MOD.ELE.FMX.008 “Quality Requirements for Electric Process Heaters (IOGP S-723Q)
(IDS)”

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 23 of 93

• MOD.ELE.FMX.009 “Information Requirements for Electric Process Heaters (IOGP S-


723L) (DDS)”

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 24 of 93

2 FUNCTIONAL REQUIREMENT

DEFINITIONS

Normative References from paragraph 1.2 shall be used for the following definitions and
terminology.

2.1.1 General definition

COMPANY:
The party that initiates the project and ultimately pays for its design and construction. The
COMPANY will generally specify technical requirements. The term “COMPANY” may also include
agents or consultants authorised to act for, and on behalf of, the COMPANY.

CONTRACTOR:
Party that performs the design, procurement, supply, manufacturing, construction, testing and
commissioning activities (or some of them).

SUBCONTRACTOR:
Any supplier, distributor, vendor, or firm that furnishes supplies or services to or for a prime
contractor or another subcontractor.

SUPPLIER:
Organisation or person that provides a product.

VENDOR:
A supplier of material or services offered from a catalogue or price list and purchased by issue
of a purchase order.
The word shall is used to indicate that a provision is mandatory.
The word should is used to indicate that a provision is not mandatory, but recommended as
good practice.

2.1.2 Specific definition

This document refers also to the following definitions:

Bulk material Items that can be purchased from a standard catalogue


description. Examples are:
• lighting system material;
• earthing system material;
• motor control station;
• power sockets;
• conduits;
• cable trays;
• cable glands.
Control/command cable It is used for transmission of information and command with a
voltage level more than 125 V AC/DC.
Electrical room It is a room or space in a building or prefabricated cabin
dedicated to electrical equipment. It typically houses the
following:
• Switchgears;
• Transformers;

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 25 of 93

• UPS;
• Batteries.
It is normally divided in:
• Switchroom;
• Transformer room;
• Battery room;
• Cable cellar;
• Multiservice room.
Instrument/automation cable It is used for transmission of information and command with a
voltage level less than 125 V AC/DC.
Small power Motors<1kW, lighting fixtures, power sockets, space heaters,
etc.
Site conditions The external factors, e.g. altitude, air temperature, wind
velocity, vibrations, relative humidity, etc., which may
influence the operation of an equipment.
Soft Starter It is a device that limits the initial inrush of current associated
with motor start-up. It provides a gentle ramp up to full speed
and is used only for start-up. Ramping up the voltage applied
to the motor produces this gradual start up.
Temporary installation It is defined as a time-constrained installation (e.g. facilities
for construction/commissioning activities).
Voltage Levels The following definitions regarding Low, Medium, High Voltage
levels are applied. Even if international IEC/EN standard
defines LV for levels up to 1 kV AC and HV for levels over 1kV
AC, for compatibility within Eni documents the following
definitions are maintained:
- LV for voltages up to 1 kV in AC (Low Voltage) ;
- MV for voltages over 1 kV in AC and up to 52 kV in AC
(Medium Voltage) ;
- HV for voltages over 52 kV in AC (High Voltage).

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 26 of 93

SYMBOLS AND ABBREVIATIONS

For symbols and abbreviations reference is made to the Normative References listed in 1.2.
Moreover the following are defined:
- AC Alternating Current;
- ACB Air Circuit Breaker;
- AFWF Air Forced Water Forced
- AGM Absorbed Glass Mat;
- AIS Air Insulated Switchgear;
- ASP Auxiliary Service Panel;
- CENELEC Comité Européen de Normalisation en Electronique et en
Electrotechnique;
- CE Conformité Européenne;
- COP continuous power;
- CT Current Transformer;
- DC Direct Current;
- DOL Direct-on-Line;
- DCS Distributed Control System;
- D.D.S. Document Data Sheet;
- EMS Electrical Management System;
- EPL Equipment Protection Level (see IEC 60079-0);
- ESP emergency standby power
- EU European Union;
- FCL Fault Current limiter
- FEED Front End Engineering Design;
- F&G Fire and Gas System;
- FLNG Floating Liquefied Natural Gas;
- FPSO Floating Production Storage and Offloading;
- GIS Gas Insulated Switchgear;
- GRP Glass Reinforced Polyester;
- HSE Health, Safety and Environment;
- HV High Voltage;
- HVAC Heating, Ventilation, & Air Conditioning;
- Ic capacitive current;
- ICSS Integrated Control and Safety System;
- Icw Rated short-time withstand current;
- I.D.S. Inspection Data Sheet;
- IEC International Electrotechnical Commission;
- In Rated Current;
- IOGP International Association of Oil & Gas Producers;
- IP Ingress Protection degree
- Ip arc permissible short-circuit current under arcing conditions
- Ips arc permissible short-circuit current under self-extinguishing arcing
conditions
- Ir resistive current;
- ISO International Standards Organisation;
- IT See IEC 60364-1 (onshore) and IEC 61892-2 (offshore)
- LCCA Life Cycle Cost Analysis
- LP Lighting distribution Panel;
- LPL Lightning Protection Level (see IEC 62305-1)
- LSS Load Shedding System;
- LV Low Voltage;
- MCB Miniature Circuit Breaker;
- MCC Motor Control Centre;
- MCT Multi-Cable Transits;
- MV Medium Voltage;

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 27 of 93

- NER Neutral Earthing Resistors;


- PC Power Centre;
- PMCC Power Motor Control Centre;
- PTC Positive Temperature Coefficient;
- PSC Power Switchgear and Controlgear (see IEC 61439-2)
- PVC Poly Vinyl Chloride;
- RCD Residual Current Device;
- RICE Reciprocating Internal Combustion Engine
- RTD Resistance Temperature Detector;
- S.I. International System;
- SIS Safety Instrumented System;
- SPD Surge Protective Device;
- T.D.S. Technical Data Sheet;
- THD Total Harmonic Distortion;
- TN See IEC 60364-1 (onshore) and IEC 61892-2 (offshore);
- TN-S See IEC 60364-1 (onshore) and IEC 61892-2 (offshore);
- TT See IEC 60364-1;
- UCP Unit Control Panel;
- UL Underwriters Laboratories;
- UPS Uninterruptible Power Supply;
- VRLA Valve Regulated Lead Acid;
- VT Voltage Transformer;
- Zg Earth Fault Impedance.

GRAPHIC, SYMBOLS, CODES AND IDENTIFICATIONS TAG

For graphic symbols, codes and identification tags reference shall be made to COMPANY standards
21000.ENG.PRC.STD and IEC 60617. Additional requirements shall be indicated in the Project
Documentation.

OPERATIVE ENVIRONMENT

Rating of equipment and systems shall comply with the range of ambient conditions (e.g.
temperature, humidity) indicated in relevant project documentation (e.g. Basis of Design).
Equipment that have to remain operational in case of partial or total shut down of HVAC shall
also be rated for the ambient conditions that can occur with such partial or total shutdown of the
HVAC.

MEASUREMENT UNITS

The measurement units adopted shall conform to the International System (S.I.) and COMPANY
Standard 20183.VAR.GEN.STD.
By exception, for cable conduits diameters and fittings in general the measurement in "inch"
may be used.

DESIGN AND ENGINEERING PRINCIPLES

2.6.1 Protection against explosion and fire hazard

If electrical equipment has to be installed in hazardous areas, appropriate equipment protection


to allow operation of that equipment shall be specified, selected and certified in accordance with
relevant rules (e.g. IECEx, ATEX).

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 28 of 93

2.6.2 Standardisation of equipment and materials

Equipment of similar nature, incorporating similar or identical components and of similar or


identical construction should be supplied by the same VENDOR (e.g. power and convenience
sockets, luminaries, junction boxes, switches etc.).

2.6.3 Certificates, declarations and test reports

For all equipment (e.g. for generators, motors, adjustable speed electrical power drive systems,
MV and LV switchgear, UPS equipment and transformers), the CONTRACTOR shall provide as a
minimum the VENDOR's test reports in accordance with the equipment Inspection data sheet
(I.D.S.).
Certificate and test for equipment and materials for use in hazardous areas shall comply with
IECEx System Directives or with European ATEX Directive 2014/34/EU.

2.6.4 Energy efficiency

Overall design shall consider the reduction in energy consumption through the selection and
utilization of efficient electrical equipment. The use of high efficiency/power factor electric drives,
the use of adjustable speed electrical power drive systems for speed, flow or power control, the
selection of transformers with reduced losses, etc. shall be evaluated in terms of LCCA.

ELECTRICAL SYSTEM DESIGN

2.7.1 General

The electrical system design (generation and distribution philosophy, voltage levels selection,
equipment sizing, selection of type and characteristics for each component) shall be determined
by a technical and economic analysis considering the following factors:
• People Safety;
• Plant safe operation;
• Energy efficiency opportunities;
• Plant power demand;
• Single loads absorbed power and location;
• Availability and quality of power from external network, if available;
• Reliability of supply related to load classification;
• Reduction of equipment footprint and weight (especially in offshore installations);
• Environmental site conditions;
• Easy access for operation and maintenance;
• Flexibility for future expansions;
• Standardisation and availability of components;
• Integration with existing plant and uniformity with previous system design.

2.7.2 Electrical loads classification and load balance

2.7.2.1 Loads Classification

Loads shall be classified based on their required level of availability and reliability and
consequently the appropriate power supply shall be selected. Loads classification is shown in
TABLE 4.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 29 of 93

TABLE 4: Loads Classification

TYPE SUPPLIED BY DESCRIPTION

Users the lack of which does not cause hazard


to people or damage to equipment.
Normal Loads Main Power supply system
Users that are not classified as preferential or
safety loads.

These users need a power supply to guarantee


the continuity of service in case of loss of main
source of power.
Essential/Emergency power source shall
guarantee the restart of the main generation,
prevent any damage to the plant equipment,
guarantee the control of the whole plant,
Main electrical system and, in case provide a fast restoration of normal operating
Preferential
of failure, by the emergency and, if conditions, maintain the manned areas in
Loads (1) (2)
present, by the essential system. habitable conditions. The following loads should
be considered as preferential loads:
pressurisation systems, air instrumentation
compressors, heaters, lubrication pumps and
cooling systems, firefighting pumps, control
and shutdown systems, main generators start-
up systems, auxiliaries of switchgears and
machinery and maintenance devices for the
plant.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 30 of 93

Users needed for life safeguarding, safety and


security throughout the plant and for the proper
functioning of services.
The following loads shall be considered as
safety loads:
• telecommunication plants,
• control systems including ICSS and
EMS,
Main electrical system and, in case • SIS,
of failure, by the emergency
electrical system. For transient • F&G,
Safety Loads period and in case of lack of main • public address and alarm systems,
and emergency electrical system,
UPS system by accumulator • auxiliary circuits for controls and
battery banks protections in electrical switchgears,
• emergency escape lighting,
• helideck lights,
• aeronautical obstruction lights,
• boat landing lights,
• navigation aids.

Note: other loads may be classified as Safety


Loads during each project development phase

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 31 of 93

Notes:
(1) Power supply of these users is required for technical reasons and therefore for reasons different from
those of providing personnel safety.
(2) Essential generation is normally required for floaters or for large manned offshore installations.

2.7.2.2 Load balance

A schedule of the foreseen electrical loads, split by relevant supplying switchgear shall be
prepared. The load balance shall provide the demand load and peak load expressed in kilowatts
and kilovars, under the specified operating conditions identified during the project development.
The definitions are the following:
Demand Load Continuous Load + Intermittent Load
Peak Load Demand Load + % Stand-by Load

% Stand-By Load the greatest between the following values:


- 10% of total stand-by loads;
- the biggest stand-by load;
- the sum of all stand-by loads of the greatest unit
power wise (e.g. compressor trains), for which a
make–before-break load transfer is foreseen between
a running unit and its associated stand-by unit.
In case of multiple users fed by one feeder, a conventional load shall be applied, calculated as
the sum of the rated powers of the users, multiplied by a load factor not lower than below:
• Lighting fixtures: 1;
• Continuous Use Equipment: 0,8;
• Sockets (n= number of socket): 1/n+0,1;
• HVAC: 1;
• Various centralized services (water, thermal, etc.): 0,8.
An engineering margin shall be included to the final total demand load to account for an increase
in the power demand due to uncertainties.
Apart from the already planned future plant expansion, the following margins shall be applied to
the peak load, during the various project development phases:
• For evaluation and selection phases (pre-feasibility and feasibility), a margin of 30% shall
be applied.
• For definition phase (Basic design and FEED), a margin of 20% shall be applied.
• For execution phase, a margin of 10% shall be applied at the end of detailed design.
Such margins shall be verified in the whole range of environmental operating conditions and in
each operating scenario.

2.7.2.3 Rated voltage levels and maximum voltage for the equipment

Rated voltage and maximum voltage levels for the equipment shall be as per TABLE 5.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 32 of 93

TABLE 5: Rated Voltage and maximum voltage levels for the equipment

RATED VOLTAGE of electrical MAXIMUM VOLTAGES


system [kV]
[kV]
50 Hz 60 Hz
0,4 / 0,44 (*)
0,4 1
/0,48
0,69 0,69 (*) 1
50 Hz or 60 Hz 60 Hz
6 / 6,6 - 7,2
10 / 11 - 12
- 13,8 14,52
20 / 22 - 24
30 / 33 - 36
35 - 40,5
(*) Offshore only

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 33 of 93

2.7.2.4 Selection criteria of voltage levels

The levels of generation and supply voltage for equipment and final users shall be selected
according to the criteria indicated in TABLE 6.

TABLE 6: Criteria for voltage levels selection

NOMINAL AC SYSTEM VOLTAGE


APPLICATION
(kV)
Power generation (Main, Essential, Emergency),
50 Hz 60 Hz
Power Transformer and Switchgears (1)(2)
Up to maximum switchgear current ratings indicated in
0,4 0,4 / 0,44 /0,48
TABLE 7
Up to maximum switchgear current ratings indicated in
0,69 0,69
TABLE 7
Power generation (Main, Essential), Power
50 Hz or 60 Hz 60 Hz
Transformer and Switchgears
Up to maximum switchgear current ratings indicated in
6 / 6,6 -
TABLE 7
Up to maximum switchgear current ratings indicated in
10 / 11 -
TABLE 7
Up to maximum switchgear current ratings indicated in
- 13,8
TABLE 7
Up to maximum switchgear current ratings indicated in
20 (1)
/ 22 (1)
-
TABLE 7
Up to maximum switchgear current ratings indicated in
30 / 33 -
TABLE 7
Up to maximum switchgear current ratings indicated in
35 -
TABLE 7
50 Hz 60 Hz Motors
0,4 0,4/ 0,44 / 0,48 Up to 75 kW (MCC)
0,69 0,69 Up to 132 kW (MCC)
0,4 0,4/ 0,44 / 0,48 Up to 200 kW (PC)
0,69 0,69 Up to 315 kW (PC)
50 Hz or 60 Hz 60 Hz Motors
6 / 6,6 - Above 200 kW up to 5 MW
10 / 11 - Above 5 MW
- 13,8 Above 5 MW
50 Hz 60 Hz Auxiliaries and small power
0,11 0,11 VT Secondary
Switchgears auxiliary control and protection circuits
0,23 0,23 / 0,24
(phase to phase)
0,23 0,23 Single phase loads in TN systems
0,23 0,23 / 0,24 Phase to phase loads in IT systems

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 34 of 93

NOMINAL DC SYSTEM VOLTAGE


APPLICATION
(V)
Power supply and auxiliaries
Photovoltaic system or other alternative power source and
24 / 48 /110
electrical distribution in small installation
Switchgears auxiliary control and protection circuits and
110 (2)
packages (VENDOR standard)
Notes:
(1) Used for power transmission systems only
(2) 110 Vdc power supply from DC UPS may be used after COMPANY approval only

2.7.2.5 Voltage drops

Electric system components shall be sized in such a way that maximum voltage drops, in steady
state operating conditions, never exceed the following values:
From main generator/transformer to MV
or LV switchgear 2% at rated current of generator;
From MV switchgear to MV switchgear 1% at rated current of downstream
switchgear;
MV overhead and buried transmission lines 5% at rated power;
MV motor feeder cables 3% for normal running at motor rated
current;
From transformer to LV switchgear 2% at rated current of transformer;
From LV switchgear to LV switchgear 1% at rated current of switchgear;
LV motor feeder cables 5% for normal running at motor rated
current;
Lighting circuits/small power users 3% from distribution board to last end user;
AC UPS circuits 5% at rated load (at the end user).

Between batteries and UPS 2%, with maximum between boost charge
current and the maximum direct current that
the inverter can absorb, increased of 25%

In steady state conditions, the sum of voltage drops of the various sections of a circuit, from the
power source / transformer to the terminals of the final load, shall be less or equal to 5 % of the
rated voltage of the circuit itself.
The voltage drop at MV switchgear shall not exceed 10% during motor starting.
The voltage drop at LV switchgear shall not exceed 15% during motor starting.

2.7.2.6 Voltage and frequency variation

Under steady-state conditions, the voltage at generator and users terminals shall not deviate
from the rated equipment voltage by more than 5 % and the system frequency shall not deviate
from the rated frequency by more than 2 %. The combined voltage and frequency deviations
shall lie within Zone A as described in IEC 60034-1.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 35 of 93

All loads shall be balanced so that the negative phase sequence components of voltage and
current at any point in the system shall not exceed the values quoted in IEC 60034-1.
Transient voltage deviations occurring at switchgear busbars during motor or group motor
starting/reacceleration shall be such as to maintain a minimum of 85% voltage on switchgear
busbars, and at least 80 %, but not more than 110 %, of rated equipment voltage on all other
users.
During motor or group motor starting/reacceleration, the voltage at the motor terminals shall
not deviate by more than +10 % or –20 % from rated equipment voltage.
Notwithstanding the above requirements, the limits set by the external power SUPPLIER
regarding the maximum voltage deviations that a consumer is permitted to cause at the point
of common coupling, e.g. due to the starting of electric motors, shall be adhered to.

2.7.2.7 Maximum value of rated current on switchgears bus-bars

The maximum current values (rated and short circuit currents) of the switchgear (main bus-
bars) shall be as per recommended values in TABLE 7.
The values are relevant to switchgears with single bus bar configuration.
TABLE 7: Maximum current and rated power on switchgears bus-bars
MAIN BUS-BAR
SHORT
RATED CURRENT
SWITCHGEAR CIRCUIT
RATED VOLTAGE [In]
TYPE CURRENT [Icw]

(1)
MV switchgear From 6 kV to 13,8 kV 4000 A 50 kA
MV switchgear From 20 kV to 35 kV 2500 A 31.5 kA
MV MCC 6 kV / 6,6 kV 1250 A 31.5 kA
Power Centre 0,4 kV/0,44 kV/0,48 kV 4000 A 100 kA
Power Centre 0,69 kV 4000 A 75 kA
LV MCC 0,4 kV/0,44 kV/0,48 kV 1250 A 75 kA
LV MCC 0,69 kV 1250 A 50 kA
ASP 0,4 kV/0,44 kV/0,48 kV 800 A 20 kA
Notes:
1) Site condition

2.7.3 Power factor

In case of connection to an external network (except for more stringent requirements by the
external power SUPPLIER itself), the overall system power factor in steady state operating
conditions, inclusive of reactive power losses in transformers and other distribution system
equipment, shall not be less than 0,92 lagging.
In case of self-generation the power factor shall remain over 0,8 lagging, otherwise a power
factor correction system shall be provided.
Power factor correction shall be achieved by one or more of the following methods stated in
order of preference. The method selected depends on reliability and economic considerations:
1) permanently energised static capacitor banks connected to MV switchgears;
2) variation of the excitation of synchronous generators;
3) variation of the excitation of synchronous motors;
4) permanently energised static capacitor banks connected to distribution switchgears
(Power Centre).

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 36 of 93

2.7.4 Harmonics distortion

The individual harmonic voltage distortions at any point of the system shall not exceed the levels
as defined in IEC/TR 61000-3-6 table 1. The Total Harmonic Distortion (THD) shall not exceed
8%. At MV switchgear incomers, the planning levels indicated in IEC/TR 61000-3-6, table 2 shall
not be exceeded, and the Total Harmonic Distortion (THD) shall not exceed 6,5%.
Such requirements shall be satisfied with the main power sources designated as spares in shut
down. In case of connection to an external grid in parallel with local main power generation, the
requirements shall be satisfied also when all the main power generators are in shut down. On
emergency distribution, such requirements shall be satisfied also when fed by the emergency
power source.
In case of connection to external grid, the requirements of the energy SUPPLIER shall be
respected if more stringent.
The electronic devices shall be suitable for electromagnetic environment class 2 according to IEC
61000-2-4.
Equipment shall be capable to operate continuously in the conditions present on the network at
point of installation, considering also emergency conditions such as operation with emergency
power source.

2.7.5 Neutral earthing

The neutral system configurations shall be as indicated below.

2.7.5.1 Medium Voltage systems

MV system neutrals shall be earthed by means of neutral earthing resistors.


The rating of the neutral earthing resistors shall be designed to limit he maximum earth fault
current to a value less than the maximum current permitted by equipment (generator or power
transformer) during earth fault considering also the total capacitive current of the system, for
the time necessary for the intervention of the protections.
The resistive current of the NER shall be determined by the following formula: Ir≥1,1 Ic where
Ic is the capacitive earth current of the system during an earth fault.
In case the earth fault (considering both the resistive and capacitive contribute) cannot be
sustained by the equipment (transformers or generators), alternative solutions shall be proposed
for COMPANY approval.
If two or more generators can operate in parallel, connected to the same switchgear without
step up transformers, one of the following solutions shall be adopted:
a) Each generator shall have its own neutral earthing resistor, connected to the star point
and provided with a contactor or circuit breaker or switch by means of which it can be
connected and disconnected, commanded by a control logic, based on the status of
generator circuit breakers and of bus ties.
b) Each busbar of the switchgear to which the generators are connected shall be provided
with a neutral earthing transformer (such as zigzag transformer or star/delta transformer
with open delta) with its own neutral earthing resistor. The neutral earthing transformers
shall be connected and disconnected by a control logic, based on the status of the
switchgear bus ties.
For each electrically separated system, only one neutral earthing resistor shall be connected at
a time. For short time parallel operations, such as the closing of a bus tie and the opening of an
incomer, more than one resistor may be connected at the same time, providing that the condition
of only one neutral earthing resistor for each electrically separated system is restored
automatically.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 37 of 93

Connection of two or more neutral earthing resistors in the same electrically separated system
(e.g. with bus tie closed) shall be prohibited by means of an interlock that shall be active even
in case the control logic is not operational.
In case the generators are connected to the switchgear by means of step up transformers, each
generator shall be provided with its own neutral earthing resistor, that shall always be connected
during operation. The neutral earthing on switchgear side, if the switchgear is in MV, shall be as
per point b) above.
If a switchgear can be fed simultaneously by transformers and generators, solution b) above
shall be adopted.
Control logics used to manage the connection of the neutral earthing resistors, or of the neutral
earthing transformers, shall be hardwired and shall have the following functions:
• They shall be operational even in case of fault of the single generators.
• Opening or closing of circuit breakers, contactors or switches shall not leave each
electrically separated system without earthing resistors connected. The logic shall
automatically execute the commands to bring the system in an acceptable configuration.
• It shall be possible for the operator to disable the control logic, but in such a case an
alarm shall be raised to the EMS. An alarm to the EMS shall be raised also in all the cases
in which, for any reason, the neutral is isolated.
The status of the connection of neutral earthing resistors and neutral earthing transformers shall
be visible in the EMS graphic pages.
In case solution b) is adopted, control logics used to manage the connection of the neutral
earthing resistors shall be implemented in the switchgear to which generators are connected.
A back-up protection sensible to voltage unbalance (such as 59N) shall be provided in order to
cover possible faults while the neutral is isolated, for example if the logic malfunctions.
For parts of the network connected to an external electrical energy SUPPLIER without interposed
transformers, the neutral earthing philosophy of the external network shall be adopted.

2.7.5.2 LV systems

The neutral of LV electrical systems shall be solidly earthed at each source of supply by means
of dedicated earth electrodes that have a direct, low impedance connection to the plant main
earth grid. The system of earthing shall be designated “TN-S”, in accordance with IEC 60364.
TABLE 8 shows the typical connection among generators / transformer / switchgear / users:
TABLE 8: System earthing selection guide

FROM TO SYSTEM EARTHING CORES

LV Generator PC TN 4 (R-S-T-PEN)
MV/LV Power
PC TN 4 (R-S-T-PEN)
transformer
PC MCC TN-S 4 (R-S-T-PE)
PC PMCC TN-S 5 (R-S-T-N-PE)
LV/LV
ASP TN 4 (R-S-T-PEN)
Power Transformer
MCC Users TN-S 4 (R-S-T-PE)
PMCC-ASP Users TN-S 5 (R-S-T-N-PE)

Note: According to IEC 60079-14, the TN-C system earthing is not permitted in hazardous area.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 38 of 93

2.7.5.2.1 Typical interconnecting between LV Generator and Main Switchboard

2.7.5.2.2 Typical interconnecting between MV/LV Power Transformer and Main Switchboard

2.7.5.2.3 Typical interconnecting between LV/LV Power Transformer and Main Switchboard

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 39 of 93

2.7.5.2.4 Typical LV distribution

Further references concerning low voltage typical incoming / outgoing feeders are in paragraph
2.8.4.3.

2.7.5.3 AC UPS systems

AC UPS systems shall have neutral isolated not distributed (IT system), provided with an
insulation monitoring device. Such device shall raise an alarm to the EMS in case of earth fault.
The faulty feeder shall be identified by visual indication on the front of the UPS distribution
section or distribution board.
This shall apply both to phase to phase and to three phase systems.

2.7.6 Power distribution configuration

Double radial distribution shall be applied for all power distribution systems inside plants,
according to TABLE 9, with exception for local panels within packages, skids and buildings.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 40 of 93

TABLE 9: Single and double radial configuration selection

SYSTEM CONFIGURATION

Distribution in medium voltage Double Radial

Distribution in low voltage, up to Power Centre (PC) Double Radial

Distribution to LV Motor Control Centre (MCC) Single or Double Radial(1)

Distribution in low voltage, up to Power Motor Control Double Radial


Centre (PMCC)

Distribution to Auxiliary Services Panel (ASP) Double Radial(1)

Lighting Panel Single or Double Radial(1)

Local Panel Single Radial

Note: (1) With single busbar even if fed with two incomers

2.7.7 Electrical protection

The coordination and selectivity among protections devices shall be guaranteed in order to avoid
unnecessary trips in case of fault. The coordination and selectivity study shall be implemented
considering that the failure downstream of any protection device in a switchgear shall not
compromise the power supply to other feeders.
The protection relays shall be equipped with a separate lock out relay (K86) with local manual
reset.
Electrical protections shall be provided with a separate power supply from UPS 230V AC.
Incomers and feeders of LV and MV switchgears shall be equipped with hardwired trip contacts
activated by a dedicated SIS signal in order to open the involved circuit breaker or contactor.
This signal shall be permanent type and resettable only by SIS system. If the circuit breaker or
contactor is already open, the trip signal shall inhibit its closure.
For ASP and UPS distribution boards, hardwired trip contacts activated by dedicated SIS signals
shall be foreseen, in order to disconnect single users or groups of users. These signals shall be
permanent type and resettable only by SIS system. If the circuit breaker or contactor is already
open, the trip signal shall inhibit its closure.
For all electrical equipment that use cooling with water (e.g. large MV motors or generators in
offshore, AFWF transformers) alarm against water leakage shall be provided.

2.7.7.1 Short circuits protections

All equipment shall be capable to withstand the effects of short circuits as a minimum for the
time necessary for the intervention of the protections.
For the calculation of the maximum short circuit current, the maximum values of the voltage
factor c shall not be lower than recommended in IEC 60909-0. Maximum short circuit currents
shall be calculated with all main power generators including spares connected, and external grid
if any, plus emergency power generators working in parallel.
Short circuit currents momentarily exceeding the design rating of the installation are permitted
only for make-before-break switching operation between incomers and bus tie circuit breakers

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 41 of 93

of a switchgear. In such a case, the configuration of the circuit breakers shall be in the conditions
in which the short circuit current rating is exceeded only for the period necessary for the
switching operation.
All circuits shall be protected against short circuits, with the exception of the connection of
starting batteries to engine for emergency machinery, such as emergency generators or fire-
fighting pumps.
The use of protective device with a short-circuit breaking or making capacity lower than
maximum prospective short-circuit at the point where it is installed (Backup Protection) shall not
be permitted.
A destructive fault current limited (FCL) in new installation (“green field”) shall not be permitted;
in case of revamping (“brown field”), the use of FCL may be permitted upon COMPANY approval.
In LV, TN and TT systems, switches with associated residual current relays shall be used for the
protection against indirect contacts of the final users.
In LV IT system, in case the protection against indirect contact is performed by means of
magneto-thermic switches, the impedance Zg of fault loop shall be verified.
The protections shall intervene also in case of minimum short circuit at the end of the line.
In TN systems, all incomers directly fed from generators or transformers and all feeders shall be
provided with protections against earth fault.
Motors rated 3 MW and over shall be provided with motor differential protection (87M), phase
shifting type.

2.7.7.2 Overloads protections

Overloads protections shall be provided for all the circuits with the exclusion of:
• rotating machines excitation circuits;
• lifting electromagnets supply circuits;
• current transformers secondary circuits;
• connection of batteries to UPS or to engine starting systems;
• equipment that for safety reasons have to operate even in case of overload, such as fire-
fighting pumps and emergency diesel generators. However, such equipment shall be
protected against overload when operated for testing purposes.

2.7.8 Intertripping and interlocking

As per relevant COMPANY standards (see par. 2.8.4.1 for MV switchgear and 2.8.4.2.3 for LV
switchgear) inter-tripping function between upstream and downstream circuit breakers (i.e.
power transformer outgoing feeder on MV switchgear and power transformer incomer on LV
Power Centre) shall be foreseen.
A key interlock shall be provided in MV switchgear between each earthing switch installed on the
front and the removable cover or door on the rear corresponding to the same functional unit, in
such a way that it shall be impossible to remove the cover or door unless the earthing switch is
in earthed position.
A key interlock shall be provided between earthing switch on MV switchgear feeder and
removable cover or door related to potentially live parts of the functional unit of the
corresponding LV incomer, in such a way that it shall be impossible to remove the cover or door
unless the earthing switch is in earthed position.
For LV switchgear located in different rooms, a key interlock shall be provided between LV feeder
and removable cover or door related to potentially live parts of the functional unit of the
corresponding LV incomer, in such a way that it shall be impossible to remove the cover or door
unless the upstream feeder is open, and withdrawn if applicable.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 42 of 93

An interlock shall be foreseen between earthing switch on an incomer and corresponding feeder
on upstream switchgear, in order to avoid the risk of energization of an earthed circuit.
An interlock shall inhibit the starting, crank and slow roll of a generator if the switchgear incomer
to which it is connected has the earthing switch in earthed position.
A key interlock between the generator and the earthing switch of the corresponding switchgear
generator incomer shall inhibit the closure of the earthing switch when the generator is not
completely stopped, in order to avoid the risk of energization of an earthed circuit.
Electrical interlocks and intertrips shall be hardwired. The use of IEC 61850 for the purpose shall
be subject to the COMPANY approval and to the demonstration of its functionality during the
integrated factory acceptance test among EMS and related switchgear.
Electrical interlocks shall be fail safe.

2.7.9 Earthing and lightning system

2.7.9.1 Earthing system

The earthing system shall be in accordance with:


• IEC 60364 for low voltage installation;
• IEC 61936-1 and EN 50522 for power installation exceeding 1 kV a.c.
In order to design the earthing systems, the soil characteristic shall be evaluated, according to
COMPANY standard 02947.ENG.ELE.STD, before the execution of the project.
The earthing system in the plant shall be realized with horizontal buried bare conductors
combined with vertical rods. The total length of earth conductors, the cross-section, the ground
grid, the number of vertical rods and their depth shall be determined by a grounding calculation
report, according to reference rules.
The ground system materials shall be chosen according to the degree of soil corrosivity and shall
not create galvanic coupling with other buried metallic structures.
In case these structures are cathodically protected, the grounding system material shall be
galvanized steel instead of copper. In any case the compatibility of earthing system and cathodic
protection system shall be evaluated during the first stage of the project.
In case of electrical system connected to external network, the earthing system shall be sized
considering the maximum earth fault currents and the fault clearance time of protective device
as per external power SUPPLIER requirements.
The design of earthing system shall consider the lightning protection report, according to the
project and reference rules. (See par 2.7.9.2)
The instrumentation earthing system shall be connected to the electrical earthing system
according to COMPANY standard 20532.ENG.STA.STD.

2.7.9.2 Protection against lightning

The protection against lightning shall be in accordance with IEC 62305.


Class I LPL shall be used for all manned plants, while at least class II LPL shall be used for
unmanned installations.
The use of early streamer emitters or dissipation array systems is prohibited.
In the evaluation of potential risks according to the criteria of IEC 62305, it shall be considered
that the damage to UPS, emergency generator and emergency switchgear can endanger human
life. The same is applicable for any instrumentation or system necessary for safe plant shut down
or evacuation.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 43 of 93

Earthing and equipotential bonding requirements and recommendations of IEC 62305-3 and IEC
62305-4 shall be applied.
For the provision of SPD, the requirements and the recommendations of IEC 62305-4, including
Annexes C and D, shall be followed.
The lightning protection system for electronic devices is described in the COMPANY standard
20531.ENG.STA.STD.

2.7.10 Emergency electrical system

The emergency electrical system shall be able to feed all the users classified as preferential and
safety.
The emergency power generation system shall be physically separated from the main power
generation source and shall be able to provide energy (including connection to switchgear) to
the system without relying on external auxiliary systems. Cooling by means of a source external
to the package, such as process water or sea water, shall not be permitted.
The emergency electrical distribution shall be derived from the main distribution system and
shall be supplied by an additional back-up power supply, consisting in an automatically started
emergency diesel engine generator.
The number of emergency diesel generators may be more than one in a facility.
Emergency power generation shall be in low voltage, with each generator with a maximum power
rating of 3150 kVA at a power factor of 0,8 lagging, according to the definition of ISO 8528-1.
Emergency power distribution shall be realized according to LVS 906 or LVS 905 of
28880.ENG.ELE.STD.
In case of main supply failure, the power supply to all emergency users shall be guaranteed
within 3 minutes.
To guarantee a stable and reliable emergency system, an automatic time sequence to energize
the loads shall be foreseen.
Distance between emergency diesel generator and relevant substation shall not be higher than
30m.
If different stand-alone emergency systems are foreseen, each emergency diesel generator shall
be located close to the relevant substation.
If the emergency absorbed power is limited, the emergency generation system may be powered
by a UPS with back-up batteries.
After main power generation restart, parallel between the emergency generator and the main
one shall allow the transfer of the load without any supply interruption.
The supply of safety users shall be guaranteed by a UPS with back-up batteries.
The apparent power of the emergency generator shall not be less than twice the sum of the
rated apparent output powers of all the UPSs. Only one out of two redundant UPS units shall be
counted for this purpose.

2.7.11 Black start requirements

Black start facilities shall be provided. Black start philosophy shall be developed by focusing on
relevant equipment selection, location criteria and black start sequence.
The override of the SIS trip signals which are necessary for the plant black start shall be achieved
with an auto-reset logic circuit, commanded with a local device. The SIS trip signals override
shall be auto-reset upon SIS reactivation.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 44 of 93

If the SIS signal override is active, an alarm shall be raised to the EMS and to the SIS, with
indication of the involved device, and in front of the involved equipment.

2.7.12 Motor starting system selection

The permitted systems are:


• Direct DOL (Direct On-Line);
• Soft-starters (Voltage control);
• Adjustable speed electrical power drive systems.
Selection among the above mentioned alternative shall consider the impact on power generation
during motor starting, the process requirements (e.g. flow regulation) and the space constraints.

2.7.13 Electrical Management System (EMS)

EMS shall be provided. For functional requirements, see 20180.ENG.ELE.STD.

2.7.14 Electrical studies and reports

For electrical system calculation reports and studies during each phase of the project refer to
COMPANY Standard 20231.ENG.ELE.PRG.

2.7.15 Transformer impedances

Transformers with the same rated power that feed the same switchgear shall have the same
short circuit impedance, within tolerance limits.

ELECTRICAL EQUIPMENT DESIGN AND SELECTION CRITERIA

2.8.1 Selection of insulation classes and temperature rise limits

Insulation class and maximum temperature rise for machines shall be according to Table 10.
TABLE 10: Insulation classes and temperature rise limits

CLASS OF TEMPERATURE RISE


MACHINES
INSULATION
(IEC 60085)
Asynchronous motors and
synchronous machines
• up to 1000 V As per IOGP S-703 As per IOGP S-703
• higher than 1000 V As per IOGP S-704 As per IOGP S-704
Oil transformers As per IEC 60076-2 As per IEC 60076-2 (2)

Resin transformers: (IEC 60076-11) (1) (2)


• MV coils F Limited to 80 K
• LV coils F Limited to 80 K

Note 1: For LV/LV transformers, class of insulation H with temperature rise limited to 125 K is
also acceptable.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 45 of 93

Note 2: maximum limits of absolute temperature indicated for each class shall consider the
corrections indicated in referenced standards, in particular regarding ambient temperatures
exceeding standard operating conditions.

2.8.2 Selection of protection methods against explosion and fire hazards

In case of installation in hazardous area, the electrical equipment shall be selected and installed
in accordance with IEC 60079 series.
The following criteria shall be used:
a) LV motors, for both Zone 1 and Zone 2, shall have level of protection “db” “eb” or “eb”.
b) For both Zone 1 and Zone 2, MV motors shall have type of protection “eb” or “db” “eb”.
If such type of protection is not available, level of protection “pxb” or “pxb” “eb” shall be
used. In such a case, in the conditions when the IEC 60079-14 foresees alarm only in
case of loss of pressurization, the equipment shall also be switched off. Type of protection
“p” shall be however avoided for preferential users.
c) For luminaires, the requirements of 28914.ENG.ELE.STD shall be complied with. In
addition, lighting fixtures with integrated battery shall always be certified EPL “Gb” as a
minimum, including local accessories and junction boxes. Outdoors, emergency escape
lighting shall always be certified EPL “Gc” as a minimum, including local accessories and
junction boxes.
d) For junction boxes, socket outlets and plugs, motor control stations and cable glands, the
requirements of 28915.ENG.ELE.STD shall be complied with.
e) For bulk materials not comprised in 28914.ENG.ELE.STD or 28915.ENG.ELE.STD, the
minimum protection degree shall be IP55 for outdoor and IP44 for indoor.
f) Battery isolator box shall have level of protection “db” “eb”, in all installation locations.
g) Other equipment not listed above (such as switchgear and panels) shall have level of
protection “eb” or “db” “eb” for Zone 1 and Zone 2.
h) if level of protection “db” is used, the terminal boxes shall be protected “eb” (e.g. indirect
cable entry protection “db” “eb”).
In case of presence of dust or possibility of sand storms, outdoor equipment and bulk materials
shall be rated for IP65 or IP66, with exception of oil transformers.
If installed in non-hazardous areas, electrical bulk materials shall be industrial type as a
minimum.

2.8.3 Power generation systems

The main electric system shall be able to supply all the users installed in the plant.
Its sizing shall consider:
• Total absorbed power calculated considering the total installed power with the use of
coefficients to consider actual utilization factor for each load, kind of service and the
operating contemporaneity;
• Presence of particular users such as large motors or other critical users;
• Availability of spares and allowance for future extensions.
The connection to external network in parallel with a self-generation system is permitted.

2.8.3.1 External network connection

External network incomer, if required to operate in parallel with own plant generation, shall be
provided with:
• manual synchronising facilities;
• check synchronising relay;

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 46 of 93

• dead-bar override;
• bidirectional measurement (e.g. active and reactive power and energy)
• directional protection.
The above synchronising controls shall be located where control of the frequency and voltage of
the generators is exercised.
An islanding system shall be incorporated in the design. Provision shall be made to allow re-
synchronisation of islanded system with external network.
CONTRACTOR shall comply with the requirements imposed by the external power SUPPLIER (e.g.
power factor, sectioning and measuring equipment, protections, fiscal metering)

2.8.3.2 Generation system

The generators selection (number and rating) shall consider the spare philosophy and, in case
of offshore plants, the space and weight constrains.
Configurations shall be with N+1 generators (with N ≥ 2), with N generators capable to cover
the load balance in worst conditions, with the margins defined at par. 2.7.2.2.
The solution with two generators only (1+1) may be accepted in particular cases after an
assessment to be approved by COMPANY against the above typical configurations in terms of at
least:
• performances of electrical system in term of reliability and functionality;
• generator utilization in different load scenarios.
The power rating of the generating sets shall be sized for continuous service in the whole range
of operating site conditions.
The rating, type and characteristics of the generating set shall fulfil the functional requirements,
as example operating in island mode, in parallel with other generating sets, in parallel with an
external power SUPPLIER or any combination of these.
The kW rating of the alternator in continuous service shall be higher than the output of the prime
mover, in the whole range of operating site conditions.
The generator rated power factor shall be 0,8 lagging unless otherwise specified in the project
documents.
During normal operation, the utilization coefficient of single generators shall never exceed 0,9
and never go below 0,5 for gas engine and 0.3 for turbo-generators, if not otherwise indicated
by VENDOR.
For further information on gas turbine generators, reference shall be made to the COMPANY
Standard 03778.ENG.ELE.STD.

2.8.3.3 Additional requirements for RICE Gas / Diesel Generator

The RICE Diesel/generator set shall be in accordance with TABLE 11:


TABLE 11 – Selection criteria for RICE Diesel/Gas Generator

TERM ITEM REFERENCE


Mode of operation: Continuous operation at varying load ISO 8528-1 Par 7.1.3
Power rating classification: Continuous power (COP) ISO 8528-1 Par 14.3.2
Performance class: G2 ISO 8528-1 Par 8

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 47 of 93

2.8.3.4 Additional requirements for emergency diesel generator

The emergency diesel generator shall be sized considering the emergency loads.
No sparing philosophy is required.
Facilities shall be provided for periodic offload and on-load test.
According to ISO 8528 series, the RICE Emergency Diesel generator set shall be in accordance
with TABLE 12:

TABLE 12 – Selection criteria for RICE Emergency Diesel Generator

TERM ITEM REFERENCE


Mode of operation: Limited time operation at varying load ISO 8528-1 Par 7.1.5
Power rating classification: Emergency Standby Power (ESP)* ISO 8528-1 Par 14.3.5
Performance class: G2 ISO 8528-1 Par 8
(*) Valid only up to 200 h/y of operation. Over 200 h/y and up to 500 h/y of operation use LTP
type (par 14.3.4). Over 500 h/y of operation use PRP type (par 14.3.3)
For further information reference shall be made to the COMPANY Standard 20213.ENG.ELE.STD.

2.8.4 Switchgears

The use of switching devices in parallel to achieve the required rating is not permitted.
Nameplates and labels for switchgear to be installed indoors shall be in plastic with embossed
letters.
Nameplates and labels for switchgear to be installed outdoors shall be in AISI 316L with engraved
letters.
Base frame, accessories for switchgear and controlgear clamping, lift pad eyes or equivalent
devices, shall be provided.
If the motor starters are equipped with circuit breaker only (no contactor), an undervoltage coil
shall be foreseen.
Switchgear auxiliary power supply for space heaters, sockets and maintenance lighting shall be
provided from ASP.
Auxiliary power supply for control, logic, opening and closing circuits, protections, digital
instruments, signalling lights and spring charging motors of switchgears shall be fed by 230V AC
UPS, with the only possible exception of contactors for LV switchgears.
If switchgears are installed outdoors, the minimum protection degree shall be IP 55.

2.8.4.1 MV Switchgears

The use of GIS (Gas Insulated Switchgear) is permitted only for rated voltages of the system of
20 kV and over.
MV switchgears shall comply with IOGP S-620 “Supplementary Specification to IEC 62271-200
High-voltage switchgear and controlgear”.
The “circuit schedule” mentioned in IOGP S-620 shall be included in COMPANY form
MOD.ELE.MVS.001.
AIS assemblies shall comply with 28881.ENG.ELE.STD.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 48 of 93

28881.ENG.ELE.STD shall be used as “user diagrams”, as mentioned in IOGP S-620.


For GIS assemblies, the content of 28881.ENG.ELE.STD shall be updated by CONTRACTOR and
submitted for COMPANY approval.
Protection 87BB shall be implemented in switchgear for rated system voltages of 30 kV and over.
Protection 87BB may also be installed in switchgear for rated system voltages lower than 30 kV.
Protection 87BB shall be of low impedance type for system voltages of 30 kV and over, otherwise
it shall be of high impedance type.
The acronym “ECMS” used in IOGP S-620 shall be considered equivalent to the acronym “EMS”
used in the present document.
The words “electrical control and management system” used in IOGP S-620 shall be considered
equivalent to the words “electrical management system” used in the present document.
Where expressions such as “unless defined otherwise by the user in the data sheets” or “unless
defined otherwise by the user in the circuit schedule” are used in IOGP S-620, the possibility to
specify a different requirement in the Data Sheets shall be subject to COMPANY approval, unless
such requirement is more stringent.
Busbars bolts and terminals shall be provided with self-locking systems.
Low voltage fuses are not permitted for the protection of power and auxiliary circuits.
The communication of protection relays and multimeters shall comply with 20180.ENG.ELE.STD.
Indicator light colour coding shall be in accordance with 28881.ENG.ELE.STD.
Quantity of volt-free contacts of high-voltage switching devices, if not defined in IOGP S-620,
shall be established in project documentation.
Low-voltage compartments for auxiliary and control components and air insulated high-voltage
connection (cable) compartments shall be provided with space heaters for the prevention of
condensation.
Motor starter functional units shall be fitted with auxiliary circuits to feed motor space heaters.
Auxiliary and control circuit insulation shall be low smoke, zero halogen content.
Protective treatments and surface finish colours shall be in accordance with the requirements
of the COMPANY specifications 29000.ENG.CPI.STD (offshore and coastal areas) or
29001.ENG.CPI.STD (onshore).
With reference to IEC 62271-102:2018, subclauses 5.6, 5.7, 5.8, earthing switches shall not be
assigned a different rating than the one of the main circuit.
In addition to the provisions already foreseen for future development phases, for each busbar at
the extremity of the switchgear, at least one fully equipped spare feeder shall be provided. The
spares shall be feeders to MV/MV or MV/LV oil transformers (MVS 610 of 28881.ENG.ELE.STD).
The rating shall be equal to the maximum already installed of the same typology, or 630A if the
same typology is not present.
Circuit breakers of the main circuit shall be withdrawable for air insulated switchgear and
controlgear, and shall be provided with service, test and disconnected positions.
Circuit breakers in SF6 shall be provided with low pressure alarm and lockout contacts.
The contactor and fuse insert shall be withdrawable for air insulated switchgear and controlgear,
and shall be provided with service, test and disconnected positions.
Contactors in SF6 shall be provided with low pressure alarm and lockout contacts.
The control voltage of contactors shall be derived from 230 V AC UPS.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 49 of 93

VTs shall be withdrawable for all air insulated switchgear and controlgear.
The accuracy class of CTs used for differential protection shall be indicated in project
documentation.
As a minimum, 10% unused spare terminals for control and auxiliaries shall be provided.
Terminals of amperometric circuits between CT, protection devices, control devices, and all
amperometric terminals of strips for external connections, shall be short-circuitable,
disconnectable and with a socket for portable instrument prods.
Unused CT secondary circuits and additional connection sockets shall be connected to the exit
terminal blocks. Unused amperometric terminals shall be short circuited.
Terminals of voltmetric circuits between VT, protection devices, control devices, and all terminal
blocks for external connections, shall be sectionable.
Simulation test to validate the interfaces with the EMS shall be performed, as described in IOGP
S-620.

2.8.4.2 LV Switchgears

Low voltage switchgears shall comply with IOGP S-560 “Supplementary Requirements to IEC
61439-1 & 2 LV Switchgear & Controlgear”, with the additional requirements indicated in
2.8.4.2.1 (all LV switchgears), 2.8.4.2.2 (all LV switchgears), 2.8.4.2.3 (all LV switchgears with
exception of HVAC switchgears), 2.8.4.2.4 (HVAC switchgears).
IOGP S-560 shall also be used for lighting and small power distribution boards rated less than
250A, with the indications included in 2.8.4.2.3.

2.8.4.2.1 Definitions for all PSC-Assemblies


The following terms, definitions and requirements shall be adopted, in addition to those of IEC
61439-1, IEC 61439-2 and IOGP S-560.

Power Centre (PC)


The Power Centre switchgear shall be used to feed MCC and ASP and users with maximum rating
as indicated in TABLE 6. The maximum rating of bus bar shall be as indicated in the TABLE 7.

Motor Control Centre (MCC)


The Motor Control Centre (MCC) shall be used to feed the motors and heaters with maximum
rating as indicated in TABLE 6. The maximum rating of bus bar shall be as indicated in TABLE 7.

Power Motor Control Centre (PMCC)


The functions of Power Centre and Motor Control Centre may be unified in one single switchgear
denominated Power Motor Control Centre (PMCC). If the maximum calculated short circuit
current is less than 20 kA, also the functions of Auxiliary Service Panel may be integrated in the
PMCC.

Auxiliary Services Panel (ASP) and Lighting distribution Panel (LP)


Switchgear used for electrical power distribution to auxiliary services or electrical lighting,
including:
• Local distribution panels;
• Local panels relevant to packages;
• Other users (e.g. electrical tracing system, package user, etc.);
• Lighting system;
• Socket circuits.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 50 of 93

• Auxiliary services of switchgear that are not fed by UPS, such as sockets, internal lighting,
space heater circuits.
The lighting distribution panels shall be used to feed the lighting system.
The maximum rating of panels shall be as indicated in TABLE 7.
If the maximum calculated short circuit current on the ASP is higher that the relevant maximum
short circuit current included in TABLE 7, insulation transformers shall be provided in order to
reduce the ASP short circuit current rating and to use modular switches with a short circuit
withstanding current up to the value indicated in the TABLE 7.

Local distribution panel


Panel used to feed locally lights and power (e.g. groups of motor valves, electric tracing circuits,
power sockets, etc.). Their execution shall comply with the requirements due to the installation
location (i.e. hazardous areas). In case of separated supplies, the local distribution panels shall
be executed with two or more segregated sections. Local distribution panels do not include UPS
distribution boards or UPS distribution sections.

UPS distribution board, UPS distribution section


Panel directly fed from one or more UPS units, either if in the same enclosure as the UPS (UPS
distribution section) or in a separate enclosure (UPS distribution board).

HVAC switchgear
Switchgear dedicated to HVAC loads and provided by HVAC SUPPLIER. The present document
refers only to power distribution part, for control section of HVAC refer to 20456.ENG.STA.STD.

2.8.4.2.2 Requirements for all PSC-Assemblies


The “circuit schedule” mentioned in IOGP S-560 shall be included in COMPANY form
MOD.ELE.LVS.001.
The acronym “ECMS” used in IOGP S-560 shall be considered equivalent to the acronym “EMS”
used in the present document.
The words “electrical control and management system” used in IOGP S-620 shall be considered
equivalent to the words “electrical management system” used in the present document.
When expressions such as “unless defined otherwise in the Data Sheets” or “unless defined
otherwise in the Circuit Schedule” are used in IOGP S-560, the possibility to specify a different
requirement in the Data Sheets shall be subject to COMPANY approval, unless such requirement
is more stringent.
Protective treatments and surface finish colours shall be in accordance with the requirements
of the COMPANY specifications 29000.ENG.CPI.STD (offshore and coastal areas) or
29001.ENG.CPI.STD (onshore).
PSC-Assemblies shall be provided with anti-condensation heaters for the prevention of
condensation in each section.
Motor starter functional units shall have the provision to feed motor space heaters.
Fuses are not permitted for the protection of power and auxiliary circuits.
The control voltage of contactors shall be as indicated in IOGP S-560, subclause 8.5.3.105, or
derived from 230 V AC UPS.
Over temperature protection using PTC thermistor / RTD shall be provided as a minimum for the
motors for which it is foreseen in IOGP S-703.
Fixed door locking devices with key shall be used when required in 2.7.8 of 20208.ENG.ELE.PRG,
in amendment to IOGP S-560, subclause 8.5.5.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 51 of 93

Terminals of amperometric circuits between CTs, protection d e v i c e s , control devices,


and all amperometric terminals of strips for external connections, shall have shunt and
disconnection facility. Socket for connection of portable instrument is also required.
Unused CT secondary circuits and additional connection sockets shall be connected to the exit
terminal blocks. Unused amperometric terminals shall be shunted.
Terminals of voltmetric circuits between VT, protection devices, control devices, and all terminal
blocks for external connections, shall be sectionable.
Simulation test to validate the interfaces with the EMS shall be performed, as described in IOGP
S-560.
For lighting, small power and heat tracing, the intervention of the protections in case of fault
shall be guaranteed up to the end of the circuit, also in the minimum short circuit conditions. If
necessary for the purpose, dedicated field distribution panels shall be foreseen.
For lighting and heat tracing circuits, the curve of intervention of the circuit breaker shall be
verified against the relevant inrush current, which shall be sustained without tripping.
In IOGP S-560, subclause 8.5.3.102, IEC 60947-3 Table 4 is referred. Reference shall be made
to Table 5 of IEC 60947-3 instead.
For switchgear of PC, PMCC and MCC type, plus other switchgear with form of internal separation
3 or 4, the PSC-Assembly shall be designed, constructed and verification tested (as a special
test) for “Internal Arc Containment” in accordance with the requirements of IEC TR 61641.
The minimum requirement is for Arcing Class C for emergency switchgear, and for Arcing Class
B for all other switchgear. The PSC-Assembly shall withstand internal arcing for 0,3 s. Ip arc and
Ips arc shall be defined in the Data Sheets. The requirements shall be satisfied with the maximum
calculated prospective short circuit current at the incoming terminals of the PSC-Assembly,
including increments for future expansions of the plant.
For switchgear with form of internal separation 2, excluding lighting and small power distribution
boards rated less than 250A, the requirements of IOGP S-560, subclause 9.3.1 shall be complied
with. The requirements shall be satisfied with the maximum calculated prospective short circuit
current at the incoming terminals of the PSC-Assembly, including increments for future
expansions of the plant.

2.8.4.2.3 Requirements for PSC-Assemblies other than HVAC switchgear


PSC-Assemblies other than UPS distribution sections and UPS distribution boards shall comply
with 28880.ENG.ELE.STD.
AC UPS distribution sections and AC UPS distribution boards shall comply with
28882.ENG.ELE.STD.
28880.ENG.ELE.STD shall be used as “user diagrams”, as mentioned in IOGP S-560, for PSC-
Assemblies different than UPS distribution boards and UPS distribution sections.
28882.ENG.ELE.STD shall be used as “user diagrams”, as mentioned in IOGP S-560, for AC UPS
distribution boards and AC UPS distribution sections.
In ASP and LP, incomers shall be disconnectable and feeders shall be of the fixed type.
In UPS distribution boards and UPS distribution sections, and in local distribution panels,
incomers and feeders shall be of the fixed type.
For PC, MCC, PMCC, functional units shall be withdrawable.
For functional units with ACB, only the circuit breaker shall be withdrawable.
For feeders of the MCC type, the whole functional unit shall be withdrawable.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 52 of 93

For feeders of the PC type and for PC, MCC, PMCC incomers without ACBs, the following solutions
are permitted:
• Only the circuit breaker is withdrawable; or
• The whole functional unit is withdrawable.
For functional units with ACB, for feeders of the PC type and for switchgear incomers the term
“withdrawable” in the Data Sheets shall refer to the circuit breaker only, unless otherwise
indicated in the “Additional notes” column.
For each LV switchgear of PMCC and MCC type, in addition to the provisions already foreseen for
future development phases, for each busbar, at least 10% fully equipped spare MCC drawers
shall be provided, with a minimum of two spare drawers and of rating equal to the maximum
already present. In case the switchgear has more than one busbar, spares shall be distributed
in such a way that drawers of the same size are as evenly distributed as possible between
busbars.
For each LV switchgear of PC and PMCC type, in addition to the provisions already foreseen for
future development phases, for each busbar, at least one fully equipped spare feeder shall be
provided. The spares shall be feeders to ASP (LVS 530/535 of 28880.ENG.ELE.STD). The rating
shall be equal to the maximum already installed of the same typology, or 630A if the same
typology is not present.
For each ASP and low voltage distribution boards, including UPS distribution sections and
distribution boards, 20% fully equipped spare feeders shall be provided, with at least one for
each rating.
For ratings of 800A and over, ACBs shall be used.
The communication of protection relays and multimeters shall comply with 20180.ENG.ELE.STD.
Switching devices shall switch all phases or poles, with the exceptions indicated in
28880.ENG.ELE.STD.
MCBs that feed external circuits, with the exception of motor space heaters, shall be operable
from the front of the PSC-Assembly without need of opening the door. Covers may be used over
MCBs providing that after the removal of these the degree of protection is not lower than IP2X.
For local distribution panels in IT systems not directly fed from transformers, it is not mandatory
to have an insulation monitoring and earth fault detection system as described in subclause
8.5.3.111 of IOGP S-560, providing that automatic location of earth faults for individual outgoing
circuits is available in the upstream PSC-Assembly.
Indicator light colour coding shall be in accordance with 28880.ENG.ELE.STD for PSC-Assemblies
other than UPS distribution boards and UPS distribution sections.
Indicator light colour coding shall be in accordance with 28882.ENG.ELE.STD for AC UPS
distribution boards and AC UPS distribution sections.
Form of internal separation for ACB functional units shall be 4b.
Form of internal separation for PC, PMCC, MCC functional units other than ACBs shall be 3b as a
minimum.
For ASP and LP, for UPS distribution boards and UPS distribution sections, and for local
distribution panels, the minimum form of internal separation shall be 2b, with exception of local
distribution panels rated less than 250A, for which also 2a is permitted.
The distances indicated in mm in subclause 8.8 of IOGP S-560 are not mandatory for local
distribution panels rated less than 250A.

2.8.4.2.4 Requirements for HVAC switchgear


User Diagrams shall be developed by CONTRACTOR and subject to COMPANY approval.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 53 of 93

If normal and emergency HVAC loads are fed by the same switchgear (permitted only onshore),
means to disconnect and to inhibit starting of non-emergency loads shall be foreseen upon
unavailability of main power source.
Devices for operation, such as stop buttons, shall be placed on the front of the switchgear
(without necessity to open doors or covers).
For PSC-Assemblies with more than one incomer, protections to avoid the connection of
unsynchronized circuits shall be foreseen.
For motor and heater feeders, there shall always be the possibility to stop them from the front
of the switchgear.
Stop command shall be different than protection hand reset device.
For incomers, bus couplers and for feeders to subdistribution panels, possibility to open and
close from front of the switchgear shall be foreseen. In case remote operation is foreseen, it
shall be possible only by means of a local/remote selector located in front of the switchgear.
Possibility of opening the circuit shall be available regardless of the position of the local/remote
selector.
Incomers and bus ties shall be with circuit breakers.
PSC-Assemblies incomer functional units and bus coupler functional units (if any) shall be
withdrawable. Other functional units shall be as defined in the Data Sheet.
The term “withdrawable” in the Data Sheet shall be intended as follows:
• For all incomers and bus couplers and for feeders of the PC type, shall refer to the circuit
breaker only, unless otherwise indicated in the “Additional notes” column.
• For feeders of the MCC type, shall refer to the whole functional unit.
The minimum signaling mounted on front of the switchgears shall be as follows:
• Red lamp (trip) for each incomer / feeder;
• Green lamp (available) for each incomer /feeder;
• White lamp:
 (closed) feeder;
 (running) motor feeder.
If there is no visible evidence of the test or withdrawn position of a withdrawable part, such
condition (cumulative of test or withdrawn) shall be shown by means of blue lamp.
As a minimum, three phase voltage and current measurement shall be made available for each
incomer from the front of the PSC-Assembly.
Form of internal separation shall be 4b for ACBs.
Interface with EMS shall be as described in 20180.ENG.ELE.STD.

2.8.5 Power transformers

2.8.5.1 General

Power transformers, including LV/LV transformers, shall comply with IEC 60076 series.
In addition, they shall comply with IOGP S-720 “Supplementary Specification to IEC 60076-1
Transformers “.
The paint system applied to the transformer and its accessories shall provide protection against
the specific climatic conditions for the location of installation, in compliance with COMPANY
standard 29000.ENG.CPI.STD (offshore and coastal areas) or 29001.ENG.CPI.STD (onshore).

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 54 of 93

Anticondensation heaters, if provided (e.g. in cable box), shall be protected against direct contact
(IP2X) and in order to avoid burning if accidentally touched.
Winding temperature detectors shall be of platinum of 100 Ω at 0°C (PT100).
Space heater controlled with thermostat shall be provided in main cable boxes.
If cable connecting boxes are foreseen, these shall be separated for:
• High voltage side of the transformer
• Low voltage side of the transformer
• The auxiliary circuits of the transformers, such as CT secondaries and alarm/trip
measuring devices
• Forced cooling equipment terminals
• On load tap changer
• Neutral connection of transformers with secondary voltage > 1kV
Contacts shall be NC for alarm and NO for trip circuits.
All the power transformers (including LV/LV ones) shall be capable to sustain the thermal and
dynamic effects of short circuit, as specified in IEC 60076-5. The values of apparent short circuit
power of the network shall be used for the calculations. The ability to withstand the dynamic
effects of short circuit shall be demonstrated by calculations and design and manufacturer
considerations.
Rating plates shall be provided and made of stainless steel AISI 316L.
Junction boxes and control panels for auxiliary devices shall be rated IP44 if installed indoors (in
room enclosed on all sides), otherwise IP55. These shall be provided with space heaters
controlled with thermostat and protected with MCBs or with switch-disconnector-fuses. In case
motor starters are included, these shall be provided at least with protection with thermomagnetic
circuit breakers. Space heater terminals shall be provided with a warning label.
Transformers shall be provided with de-energized tap changer, with a tapping range of ±5% in
steps of 2,5%, unless on load tap changer is requested by COMPANY. In case on load tap changer
is foreseen, it shall be motorized and provided with remote control panel.
The protection degree of the remote control panel for on-load tap changer shall be IP 31 or
higher for indoor installation in room enclosed on all sides and IP 55 or higher in other cases.
The installation of power transformers inside switchboards is not permitted, including those used
to feed ASP or lighting and small power sections, with the exception of auxiliary transformers,
such as those used for UPS, that are treated as a component of the switchboard itself.
Two winding transformers with star connection both at primary and secondary windings shall be
rejected.
Power transformers connected to overhead lines or air insulated substations shall be protected
with surge arresters.
Transformers in series shall be accepted only for the following cases:
• If there is a preferential power generation in MV, for the transformers feeding preferential
loads;
• LV/LV transformer;
• If the LV loads are less than 20% of MV loads.
Autotransformers shall be permitted only if explicitly indicated in COMPANY standards.
For LV/LV transformers, the voltage ratio for the tappings other than the principal one may
exceed the tolerances of IEC 60076-1; in such a case, the voltage ratio of the tappings shall be
subject to agreement with COMPANY.
LV/LV transformers feeding ASP or lighting board shall not be rated more than 500 kVA.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 55 of 93

2.8.5.2 Dry type power transformers

Dry type power transformer shall be in resin.


Dry type power transformers shall comply with IEC 60076-11.
The partial discharge measurement for transformers operated under a single phase line-to-earth
fault condition, that is a special test mentioned in IEC 60076-11, shall be performed for all
transformers that operate in systems for which automatic disconnection is not foreseen in case
of first earth fault.
Cooling method shall be AN, according to IEC 60076-2.
The following shall be provided, in addition to IOGP S-720 requirements:
• In addition to temperature detectors in the windings foreseen in IOGP S-720 (see § 9.6.8
and subclauses), two (one as spare) PT100 temperature detectors in the core;
• Temperature control relay, digital type, to be installed in the switchgear, with alarm and
trip thresholds;
• Removable wheel assembly, with wheels orientable at 90°;
• Lifting lugs;
• Two AISI 316L stainless steel plates as grounding terminals, placed at the bottom on the
sides of incoming cables or diagonally at two opposite sides;
• Additional equipment necessary for installation and maintenance, such as jacking plates
and pulling hooks for towing the transformers in both perpendicular directions;
• Junction box for auxiliary circuits.
The minimum Environment, Climate and Fire classification shall be in compliance with the project
climatic conditions and as a minimum as follows (with reference to IEC 60076-11):
• E1-C1-F1 for indoor installation, in room enclosed on all sides (without openings such as
louvres or grates);
• E4-C1-F1 in all other cases.
Transformers shall be placed in protective metal enclosures, rated as follows:
• IP31 if located inside rooms enclosed on all sides
• IP44 if located in rooms with one wall opened to the outside, by means of grates or
louvers
• IP54 if placed outdoor under canopy. Canopy shall be sloped to avoid the stagnation of
water.
Only one transformer shall be housed in a single enclosure.
Outdoor installation shall be with canopy.
The enclosures shall be in AISI 316L for offshore installations and for onshore installations in
aggressive environment (e.g. marine). In other onshore locations the enclosures shall be made
of galvanized steel. Passages of single core cables shall not be surrounded by magnetic
materials.
Opening of the enclosure shall be possible only if the transformer is de-energized, by means of
interlock. For MV/MV and MV/LV transformers, the interlock shall require the upstream earthing
switch to be in the earthed position before it is possible to open the enclosure.
In case the transformers are placed each in a dedicated room or bay, in rooms enclosed on all
sides without open walls to the outside, the enclosure is not necessary. Protection barriers,
grating and clearances shall be in compliance with IEC 61936-1 (to be complied with also in
offshore from this respect). Access to the room or bay shall be possible only if the transformer
is de-energized, by means of key interlock. For MV/MV and MV/LV transformers, the interlock
shall require the upstream earthing switch to be in the earthed position before it is possible to
access the room or bay. In the room or bay, only equipment related to the transformers shall
be installed (e.g.: auxiliaries, neutral earthing resistor).

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 56 of 93

2.8.5.3 Oil immersed power transformers

The following shall be provided, in addition to IOGP S-720 requirements:


• Conservator (except for sealed type transformers) with silica gel breather.
• Additional temperature detectors, besides those foreseen in IOGP S-720 (see § 9.6.8 and
subclauses), according to Manufacturer recommendations;
• Temperature control relay, digital type, to be installed in the switchgear, with alarm and
trip thresholds;
• Removable wheel assembly, with wheels orientable at 90°;
• Lifting lugs;
• Two AISI 316L stainless steel plates as grounding terminals, placed at the bottom on the
sides of incoming cables, or diagonally at two opposite sides.
• Connections for vacuum pump, excluding sealed transformers
• Dial type pressure vacuum gauge (only for sealed transformers), including a NC contact
for low pressure and a NO contact for high pressure
• Additional equipment necessary for installation and maintenance, such as jacking plates
and pulling hooks for towing the transformers in both perpendicular directions
• Junction box for auxiliary circuits
Alarm contact for diaphragm failure shall be provided for transformers with diaphragm in
conservator.
Pressure relief device for transformer and reactor tanks shall be provided.
Facility for directing emissions of liquid from the relief device in the direction specified shall be
provided.
Liquid level indicator of the conservator shall be provided with an alarm contact.
The diverter switch oil compartment shall be provided with Buchholz relay.
According to definitions of IEC 60076-2, cooling shall be ONAN, with the possible addition of the
following cooling methods:
• ONAF
• OFAN
• OFAF
• ODAF
Transformers that have to remain energized in emergency conditions shall be ONAN only.
Other types of cooling based on water, such as OFWF, ONWF, ODWF, shall be subject to
COMPANY approval. The water system necessary for cooling shall be available and operational
without need of prior energization of the transformer.
Oil immersed transformers shall not be installed inside switchgear or panels, or indoors in rooms
without a wall opened to the outside by means of grates or louvers. These shall be installed in
rooms with one wall opened to the outside, by means of grates or louvers, or outdoors (see
2.10.1.2). Oil immersed transformers shall always be suitable for outdoor operation.
Main cable connecting boxes shall be rated IP55 or higher.
The use of sealed transformers shall be limited to power ratings lower than 3150 kVA and shall
be subject to COMPANY approval.

2.8.5.4 Selection criteria of power transformers

Power transformers shall be dry type in resin, unless these have at least one winding rated more
than 36 kV, or power rating higher than 15 MVA. Over 15 MVA and up to 25 MVA, these may be
in oil or dry type in resin, providing that there are no windings rated more than 36 kV. Over 25
MVA, or if there are windings rated more than 36 kV, oil type shall be used.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 57 of 93

In desert locations and wherever sand or dust storms are expected, dry type transformers in
resin may be used only up to 3,15 MVA. These shall be installed only indoors, in rooms
surrounded on all sides, with forced ambient ventilation. For sizes over 3,15 MVA, the
transformers shall be oil type. In such ambient conditions, oil type transformers may be used
also for power ratings of 3,15 MVA and below.
Power ratings indicated in this paragraph are referred to natural ventilation.

2.8.6 Inductive shunt reactors

Inductive shunt reactors shall comply with IEC 60076-6.


In addition, these shall comply with IOGP S-720 “Supplementary Specification to IEC 60076-1
Transformers “.
All choices made inside the Data Sheets shall not be in contrast with the present document,
IOGP S-720 or project specifications.
The paint system applied to the reactor and its accessories shall provide protection against the
specific climatic conditions for the location of installation, in compliance with COMPANY standard
29000.ENG.CPI.STD (offshore and coastal areas) or 29001.ENG.CPI.STD (onshore).
Winding temperature detectors shall be of platinum of 100 Ω at 0°C (PT100).
Space heater controlled with thermostat shall be provided in main cable boxes, unless
CONTRACTOR is able to demonstrate that this is not required to avoid condensation.
If cable connecting boxes are foreseen, these shall be separated for:
• Main power connection
• The auxiliary circuits of the reactor, such as CT secondaries and alarm/trip measuring
devices
• Forced cooling equipment terminals
• On load tap changer
The protection degree of the remote control panel for on-load tap changer shall be IP 31 or
higher for indoor installation in room enclosed on all sides and IP 55 in other cases.
Requirements for testing shall be as indicated in IEC 60076-6 for shunt reactors.
Rating plates shall be provided and made of stainless steel AISI 316L.
Anticondensation heaters, if provided (e.g. in cable box), shall be protected against contact
(IP2X) and to avoid burning if accidentally touched.
Contacts shall be NC for alarm and NO for trip circuits.
Junction boxes and control panels for auxiliary devices shall be rated IP44 if installed indoors (in
room enclosed on all sides), otherwise IP55. These shall be provided with space heaters
controlled with thermostat and protected with MCBs or with switch-disconnector-fuses. In case
motor starters are included, these shall be provided at least with protection with thermomagnetic
circuit breakers. Space heater terminals shall be provided with a warning label.
Reactors connected to overhead lines or air insulated substations shall be protected with surge
arresters.

2.8.6.1 Dry type reactors

CONTRACTOR shall include in the project specification for the dry type reactors as indicated in
IEC 60076-6, the pollution conditions on the installation site. Lacking information, very heavy
pollution severity shall be assumed, according to the definitions of IEC TS 60815-1.
Magnetic clearance and protection from atmospheric effects shall be verified by CONTRACTOR
and VENDOR in relation to the conditions of installation. Demonstration that heating and reaction

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 58 of 93

forces induced in nearby metallic objects are negligible shall be provided. Verification shall also
consider the overheating of concrete rebars due to the interaction with electromagnetic fields
generated by reactors.
Dry type reactors shall be installed in a fenced area which shall be accessible, by means of
interlock, only when the equipment installed inside it are de-energized. Such fenced area shall
contain only the reactors and associated auxiliary equipment, if any. Reactors that are redundant
to each other shall not be installed in the same fenced area.

2.8.6.2 Oil immersed reactors

Oil immersed reactors shall be installed with the same requirements described in 2.10.1.2 and
3.1 for oil immersed transformers.
These shall comply with the same requirements indicated for oil immersed transformers in
2.8.5.3.

2.8.7 UPS equipment and batteries

2.8.7.1 AC Uninterruptible Power Supply System

AC UPS shall be used to feed safety loads.


For details of loads classified as safety, reference shall be made to TABLE 4.
UPS shall guarantee the supply of the connected loads in case of power loss of power generation
(main and emergency). In case emergency power systems are not available, the UPS shall
remain in operation to guarantee the minimum conditions of occupancy, safety and survival and
to allow remedy actions, activities of communication, immediate relief, evacuation of people,
etc.
Unless otherwise specified in the project documents, at least two independent UPS shall be
provided:
1. to supply electrical loads (e.g. switchgear’s auxiliaries for control and protections, safety
lighting, lighting escape routes etc.);
2. to supply instrumentation system (e.g. telecommunication plants, DCS, SIS, F&G, etc.).
For the design of the HVAC system, it shall be considered that the UPS generates heat also when
fed from the batteries only.
AC UPS shall comply with IOGP S-701 “Supplementary Specification to IEC 62040-3 AC
Uninterruptible Power Systems (UPS)”.
AC UPS shall comply with 28882.ENG.ELE.STD.
AC UPS shall be suitable for ambient with pollution degree 3 as per IEC 62477-1.
UPS topology shall be double conversion with bypass.
Static switch shall be in both inverter and bypass path.
AC UPS shall comply with the requirements of Category C3 as per IEC 62040-2.
The maximum harmonic current distortion shall comply with Table 2 of IEEE Std 519™.
Acoustic noise at 1 m shall not exceed 75 dBA.
Maximum output frequency variation in unsynchronized conditions shall be ±0,1%.
Output voltage and frequency tolerances in all operating modes (normal energy mode, storage
energy mode and operation from bypass) shall be selected in order to match the requirements
of the loads to be fed.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 59 of 93

UPS performance classification shall be VFI SS 111.


DC earth condition shall be floating.

DC earth leakage monitoring shall be provided, with alarm on the UPS and on the EMS.

The UPS shall be interfaced with the EMS for monitoring purposes, as indicated in
20180.ENG.ELE.STD. The information to be shown in the EMS shall be as a minimum those listed
in IOGP S-701, § 8.4.2.5, § 8.4.3, § 8.4.4.2.
UPS distribution boards, if not integrated in the UPS, shall be interfaced with the EMS as ASP,
as indicated in 20180.ENG.ELE.STD.
UPS distribution board, if integrated in the UPS, shall as a minimum provide a common alarm
(cumulative of fault) to the EMS, plus the status and trip indication of the circuit breakers
upstream of the distribution bus bars.
UPS distribution board shall comply with IOGP S-560 and with 2.8.4.2 and subparagraphs of the
present document, both if integral to the UPS or separated from it.
If the UPS distribution board is not integral to the UPS, it shall be positioned in the same room
and as close as possible to it.
For the UPS distribution section, or distribution board, the COMPANY form MOD.ELE.LVS.001
shall be used.
The UPS shall respect the accessibility requirements indicated in subclause 8.5.5 of IEC 61439-
1.
Maximum height of the UPS shall be 2,5 m.
Protective treatments and surface finish colours shall be in accordance with the requirements
of the COMPANY specifications 29000.ENG.CPI.STD (offshore and coastal areas) or
29001.ENG.CPI.STD (onshore).

If redundant UPS configuration is used (i.e. UPS of type “B” or “C” according to
28882.ENG.ELE.STD), it shall be possible to replace components of a UPS unit keeping the other
UPS unit part of the redundant UPS configuration in service, without risk of accidental contact
with live parts.
Live parts of a redundant UPS that remain in service when one UPS unit is de-energized shall be
protected with barriers of at least IP2X with respect to an operator that is working on the de-
energized UPS unit.
The maintenance bypass switch and isolation transformer shall be mounted separately in an
adjacent compartment.
Cooling fans shall be replaceable while the UPS remains in service.
Battery isolator box shall be in AISI 316L or GRP.
Push buttons and manipulators shall comply with IEC 60073.
Fuses shall be used only when shown in 28882, or for protection of semiconductor devices if
strictly required by the Manufacturer.
On-line battery capacity testing shall be provided, to discharge the battery into the load.
With batteries at the discharge minimum voltage, the UPS shall allow the recharge of the battery
to at least 80% capacity in a period of maximum 10 hours.
The UPS shall allow a black start, delivering power to the users at the rated output with only the
batteries as power source.
The inverter section of the UPS shall deliver the short circuit current necessary to operate the
downstream protections in case of fault on an outgoing circuit.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 60 of 93

If the UPS has two or more inverters to be operated in parallel, alarm of inverters not
synchronized shall be shown on the UPS front by means of HMI or LED signaling lights, and an
alarm shall be raised to the EMS.
If remote manual reset of trip functions is foreseen, this shall be performed from the EMS.
Each inverter shall be able to operate even if the batteries are disconnected and the power is
fed only by the relevant rectifier.
If there are motors among the loads of the UPS, the UPS motor starting capability shall be
verified in all possible operating configurations. In case the UPS is not capable of starting a
motor, adjustable speed electrical power drive system shall be provided for starting and
integrated in the UPS distribution board or UPS distribution section.
Temporized disconnection of loads with different autonomy times shall be as shown in
28882.ENG.ELE.STD.
For earth fault detection and alarm, refer to 2.7.5.3.
Coordination and selectivity of protections shall be guaranteed in such a way that a fault on a
single outgoing circuit does not compromise the power supply to other feeders.
Baseframe, lift pad eyes and accessories for UPS installation shall be provided.
For AC UPS rated more than 5 kVA, the incomer shall be three phase.
For AC UPS rated more than 120 kVA, the output shall be three phase.

2.8.7.2 Selection of AC UPS scheme

The configuration of AC UPS shall be one of the following:


Type A: single rectifier/inverter unit (1x100%), non-redundant batteries (1x100%) and
bypass system (ref. doc. 28882.ENG.ELE.STD – UPS 001);
Type B: parallel redundant rectifier/inverter units (2x100%), redundant batteries (2x100%)
and bypass system (ref. doc. 28882.ENG.ELE.STD – UPS 002);
Type C: dual configuration rectifier/inverter units (2x100%), redundant batteries (2x100%)
and bypass system (ref. doc. 28882.ENG.ELE.STD – UPS 003).
UPS units and bypass paths shall be fed from emergency busbars.
If two UPS of type A are used, the two converter paths shall be fed from two different emergency
busbars.
If two UPS of type A are used, the two bypass paths shall be fed from two different emergency
busbars.
If UPS of type B or C is used, the two converter paths shall be fed from two different emergency
busbars.
The criteria for the choice of the type of AC UPS shall be as follows:

Type A
The configuration with one UPS of type A is permitted only in case the loads to be fed are not
related to people safety or equipment integrity, and following specific COMPANY approval.
The configuration with two UPS of type A, may be used if it is required to have two fully
independent units in different locations. If the two UPS of type A are used also for loads that are
not fed through redundant AC/DC converters, the outputs of the two UPS shall be synchronized.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 61 of 93

If there are loads with single power supply, these shall be fed from both UPS distribution boards.
An intermediate panel shall be provided with a break-before-make automatic transfer switch.
The inrush current of the loads shall be verified against the capacity of the inverter.
Type B
This configuration may be used for all electrical loads.
This configuration may be used for the instrumentation and telecom loads which do not require
redundant power supplies.
This configuration may be used if the electrical and instrumentation UPS are merged in one.
The inverter outputs shall be synchronized.
Type C
This configuration may be used only for instrument and telecom loads (such as DCS, SIS, F&G
etc.) which require redundant power supplies.

2.8.7.3 DC Uninterruptible Power Supply System

DC UPS may be used only after COMPANY approval.


DC UPS shall not be used for instrumentation and telecom loads.
DC UPS shall comply with IOGP S-702 “Supplementary Specification to IEC 62040-5-3 DC
Uninterruptible Power Systems (UPS)”.
DC UPS shall be suitable for ambient with pollution degree 3 as per IEC 62477-1.
Battery configuration shall be 2x100%.
The configuration of the DC UPS shall be parallel redundant.
DC UPS configuration shall be the following: simplified dual DC UPS with common output bus
(Figure A.3 of IOGP S-702).
DC UPS topology shall be series converter connect.
DC UPS shall comply with the requirements of Category C3 as per IEC 62040-2.
Acoustic noise at 1 m shall not exceed 75 dBA.
The maximum harmonic current distortion shall comply with Table 2 of IEEE 519.
For DC UPS rated more than 5 kVA, the incomer shall be three phase.
UPS performance classification shall be NN.
Output voltage in all operating modes (normal energy mode, storage energy mode) shall be
selected in order to match the requirements of the loads to be fed.
DC earth condition shall be floating.
DC earth leakage monitoring shall be provided, with alarm on the UPS and on the EMS.
Battery isolator box shall be provided, with same characteristics as described in 2.8.7.4.
Black start override shall be provided for the battery isolator box only in case the DC UPS is used
for black start.
The UPS shall be interfaced with the EMS for monitoring purposes, as indicated in
20180.ENG.ELE.STD. The information to be shown in the EMS shall be as a minimum those listed
in IOGP S-702, § 8.2.2.5, § 8.2.3, § 8.2.4.2.
UPS distribution boards, if not integrated in the UPS, shall be interfaced with the EMS as ASP,
as indicated in 20180.ENG.ELE.STD.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 62 of 93

UPS distribution board, if integrated in the UPS, shall as a minimum provide a common alarm
(cumulative of fault) to the EMS, plus the status and trip indication of the circuit breakers
upstream of the distribution bus bars.
UPS distribution board shall comply with IOGP S-560 and with 2.8.4.2 and subparagraphs of the
present document, both if integral to the UPS or separated from it.
If the UPS distribution board is not integral to the UPS, it shall be positioned in the same room
and as close as possible to it.
For the UPS distribution section, or distribution board, the COMPANY form MOD.ELE.LVS.001
shall be used.
Protective treatments and surface finish colours shall be in accordance with the requirements
of the COMPANY specifications 29000.ENG.CPI.STD (offshore and coastal areas) or
29001.ENG.CPI.STD (onshore).
It shall be possible to replace components of a UPS unit keeping the other UPS unit part of the
parallel redundant DC UPS configuration in service, without risk of accidental contact with live
parts.
Live parts of a parallel redundant DC UPS that remain in service when one UPS unit is de-
energized shall be protected with barriers of at least IP2X with respect to an operator that is
working on the de-energized UPS unit.
Cooling fans shall be replaceable while the UPS remains in service.
Battery isolator box shall be in AISI 316L or GRP.
The UPS shall respect the accessibility requirements indicated in subclause 8.5.5 of IEC 61439-
1.
Maximum height of the UPS shall be 2,5 m.
Push buttons and manipulators shall comply with IEC 60073.
Fuses shall be used only for protection of semiconductor devices, if strictly required by the
Manufacturer.
On-line battery capacity testing shall be provided, to discharge the battery into the load.
With batteries at the discharge minimum voltage, the UPS shall allow the recharge of the battery
to at least 80% capacity in a period of maximum 10 hours.
Unless it is dedicated to feeding auxiliaries of non-emergency packages, the UPS shall allow a
black start, delivering power to the users at the rated output with only the batteries as power
source.
If remote manual reset of trip functions is foreseen, this shall be performed from the EMS.
The short circuit capability of the DC UPS shall be sufficient to operate the downstream
protections in case of fault on an outgoing circuit.
The UPS shall be able to operate even if the batteries are disconnected and the power is fed only
by the relevant rectifier.
Coordination and selectivity of protections shall be guaranteed in such a way that a fault on a
single outgoing circuit does not compromise the power supply to other feeders.
Temporized disconnection of loads with different autonomy times shall be foreseen.
Baseframe, lift pad eyes and accessories for UPS installation shall be provided.

2.8.7.4 Battery isolator box (AC and DC UPS)

Batteries shall be connected to UPS though battery isolator box.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 63 of 93

The battery isolator shall be a MCCB.


Battery isolator box shall be certified EPL “Gb”.
Battery isolator box shall comply with 20056.ENG.ELE.STD.
In case of offshore installation, the circuit breaker shall be provided with undervoltage coil
controlled by SIS to open the circuit breaker.
In case of onshore installation, the circuit breaker shall not be controlled by SIS, unless otherwise
specified in the project documents.

2.8.7.5 Selection of UPS autonomy (AC and DC UPS)

Refer to opi hse 023 eni spa “Safety & Environmental Minimum Design Requirements”.

2.8.8 Storage batteries

Batteries shall comply with IOGP S-740 “Specification for batteries (IEC)”.
Battery technology shall be one of the following:
• nickel-cadmium partial gas recombination, in accordance with IEC 62259
• valve-regulated lead-acid – AGM, in accordance with IEC 60896-22
• valve-regulated lead-acid – gel, in accordance with IEC 60896-22
Other battery technologies shall be subject to COMPANY approval.
Service life of batteries that are regularly under floating charge conditions, at the design ambient
temperature of the room in which they are installed, shall not be less than the following:
• 20 years for Ni-Cd batteries;
• 12 years for VRLA AGM batteries;
• 15 years for VRLA gel batteries;
Cells shall not require refilling during their service life.
The number of cells for UPS application shall be chosen in such a way that at the end of autonomy
time with the required load profile the DC voltage at UPS terminals is such as to guarantee that
the output of the UPS is within required limits.
For the single cells, values of rated voltage, gassing voltage and minimum voltage at the end of
discharge at 20°C shall be provided.
The elements cell containers of a battery shall be in totally or partially transparent material and
in a self-extinguishing material as per UL 94 (Standard for tests for flammability of plastic
materials for parts in devices and appliance).
The selection criteria of type of material cell (opaque or transparent) enclosure are the following:
• UL 94 class V0 (opaque) for offshore and floaters installation;
• UL 94 class HB (opaque or transparent) for onshore installation.
The batteries shall be installed into dedicated battery rooms. Exception is made for starting
battery sets installed on/close to generation set skid.
Other exceptions shall be subject to COMPANY approval (e.g. small offshore platform, etc.).
The required autonomy time shall be verified in the whole range of ambient temperatures,
including the case in which HVAC is not operational due to shutdown of main and emergency
power systems.
The containers shall bear the two polarity signs clearly visible near the respective poles.
The container of valve regulated batteries shall be provided with outlet valve, normally closed
to avoid oxygen entrance from external ambient.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 64 of 93

Connecting bolts with anti-loosening device shall be used for inter-cell connections. Welded
connections shall not be accepted.
Battery terminals and electrical connections between cells, tiers and racks shall be insulated or
protected with covers in order to realize a protection against accidental contact with live parts
of at least IP 2X.
Tools required in IOGP S-740, subclause 9.2.1 shall be provided.
Commissioning charge, as per battery manufacturer recommendations, shall be possible with
one of the following solutions:
• With the UPS (for UPS batteries) or with the battery charger of the generator package
(for generator starting batteries)
• With a portable external battery charger, to be provided to COMPANY by CONTRACTOR
or VENDOR
If the weight of a single cell exceeds 25 kg, a battery lift or battery removal tool shall be provided.
Batteries for the UPS shall be on battery rack.
Battery rack shall be solidly fixed to the floor to avoid the falling of batteries.
Battery rack shall have a maximum of three tiers.
Maximum height of the rack, measured from the top of battery on the top tier to the floor, shall
be 1800 mm.
Material for battery rack shall be electrical insulation coated steel.
Material for battery rack shall be chemical resistant.
Battery rack shall be isolated from the ground.
Surface treatment of the rack shall comply with the requirements of the COMPANY specifications
29000.ENG.CPI.STD (offshore and coastal areas) or 29001.ENG.CPI.STD (onshore).
In FPSO and floaters, the batteries shall not spill electrolyte in the conditions indicated in IEC
61892-5 as the limits of inclination in which emergency machinery are required to operate.
For FPSO and floaters, the rack shall be anti-seismic.
For FPSO and floaters, the batteries and the rack shall not fall in the conditions indicated in IEC
61892-5 as the limits of inclination in which emergency machinery are required to operate.
Close to each battery rack a sectioning device (switch-disconnector or circuit breaker) shall be
provided, to isolate the rack for maintenance purposes.

2.8.9 Electric motors

2.8.9.1 MV asynchronous motors

MV asynchronous motors shall comply with IOGP S-704 “Supplementary Specification to IEC
60034-1 High Voltage Three-phase Cage Induction Motors”.
For interior locations, the degree of protection shall not be lower than IP 44.
If report from test on identical motor is not available, the test of noise level at no load shall be
performed.
Lateral analysis shall be performed for motors rated over 400 kW and for converter-fed motors.
Torsional analysis shall be performed for motors rated over 400 kW and for converter-fed
motors.
The sensors indicated in 28906.ENG.MEC.STD shall be provided.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 65 of 93

Space heaters shall be provided for motor windings and for line conductor terminal box.
Motors shall have at least two ISO metric thread earthing terminals fitted externally on the
frame.
Components necessary for lifting and installation at site shall be provided (e.g. lifting lugs).
The use of magnetic bearings shall be subject to COMPANY approval.
Auxiliary fans and pumps driven by independent motor shall have a N+1 sparing philosophy and
in case of trip an alarm shall be raised to a manned location.
With reference to IOGP S-704, subclause 15.2, type test certification for use with converter shall
always be required for motors with type of protection “e”, according to IEC 60079-14.
Protective treatments and surface finish colours shall be in accordance with the requirements
of the COMPANY specifications 29000.ENG.CPI.STD (offshore and coastal areas) or
29001.ENG.CPI.STD (onshore).
Cooling methods based on water shall be acceptable for ratings of 2 MW and over in offshore,
and in other cases only following COMPANY approval.

2.8.9.2 LV asynchronous motors

LV asynchronous motors shall comply with IOGP S-703 “Supplementary Specification to IEC
60034-1 Low Voltage Three Phase Cage Induction Motors”.
Space heaters shall be provided.
For interior locations, the degree of protection shall not be lower than IP 44.
With reference to IOGP S-703, subclause 15.3, type test certification for use with converter shall
always be required for motors with type of protection “e”, according to IEC 60079-14.
Protective treatments and surface finish colours shall be in accordance with the requirements
of the COMPANY specifications 29000.ENG.CPI.STD (offshore and coastal areas) or
29001.ENG.CPI.STD (onshore).

2.8.9.3 Synchronous motors

Synchronous motors shall comply with 20168.ENG.ELE.STD.

2.8.10 Electrical Management System (EMS)

For technical requirements of the EMS, see 20180.ENG.ELE.STD.

2.8.11 Cables, wires and accessories

Connections between equipment shall be realized by means of cables. The use of bus ducts and
cable bus may be considered on a case by case basis according to project requirements and
after COMPANY approval.
For outdoor installation the cables shall be mechanically protected over whole length by armour.
Cables shall be continuous; joints are not permitted, unless for particular cases to be specifically
approved by COMPANY. Junction boxes are permitted for lighting and small power circuits.
Single core Cables and multicore cables installed in ladder shall be fixed to ladder rungs with
cable cleats certified for the upstream calculated short circuit current. Single core cable shall be
fixed with trefoil cable cleats; in case of more than one core per phase each trefoil cleats shall
accommodate one core per phase.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 66 of 93

2.8.11.1 General requirements

All cables for onshore application (included internal wiring of switchgear and other enclosure for
electrical equipment) shall be in accordance with IEC 60502-1, IEC 60502-2, IEC 60840 and
shall be low smoke, halogen free and flame retardant, according to IEC 61034-2, IEC 60754-1,
IEC 60754-2 and IEC 60332-3-22.
Cables to be routed where there is risk of deposits or dripping of liquid hydrocarbons shall also
be hydrocarbon resistant, according to IEC 60811 series.
The following emergency/safety circuits shall be realized with low smoke, halogen free and fire
resistant cables, according to IEC 61034-2, IEC 60754-1, IEC 60754-2 and IEC 60331 series:
• Power and control of firefighting system
• Fire and gas detection system (1)
• Emergency escape lighting
• Interconnecting cables from battery to UPS
• Obstruction light
• Radio communication (1)
• Other emergency and critical loads defined in the project specification
Note (1): See also COMPANY Standard 28045.ENG.STA.PRG.
Even if indicated in The IEC 60502-1 and IEC 60502-2, the insulating compound “PVC/A” and
“PVC/B” listed in Table 2 is not permitted.
For lighting, small power and convenience sockets in indoor distribution, (e.g. Living quarter,
electrical rooms) according to IEC 60228, cables class 5 (flexible cables) or class 6 (more flexible
cable) shall be used.
The colors of cores of electrical cables shall be in accordance with IEC 60445. For cables with
one or two cores, the choice of colors of the cores shall be uniform within the facility.
The colors of outer sheath shall be:
• Black or gray for low voltage cables (up to 0.6/1 kV). However only one color shall be
used per facility.
• Black for electrical control cables
• Red, white or violet for Medium voltage cable (over 0.6/1 kV). For each voltage level
within a facility, only one color shall be used. For different voltage levels, different colors
shall be used.
• Yellow/green for earthing and protective cables
Fire resistant cables shall have specific color of outer sheath, different from the outer sheath of
power, control and earthing cables (e.g. orange).
Routine tests, sample tests, type tests, tests after installation shall be performed as per
indications of reference standards IEC 60502-1, IEC 60502-2, IEC 60840. Reports of the tests
shall be provided. Type tests already performed do not need to be repeated, if deemed
acceptable in referenced standards.
DC voltage test of the insulation shall be avoided.
In addition, reports of type tests as per IEC 60332-3-22, IEC 61034-2, IEC 60754-1, IEC 60754-
2 and, if corresponding characteristics are required, also IEC 60331 series and IEC 60811 series,
shall be provided.
Accessories for cables shall have been qualified as per IEC 60502-4, for the voltage range therein
indicated.

2.8.11.2 Cable sizing criteria

Cables sizing is performed to fulfill the following conditions:

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 67 of 93

• containment of voltage drops within fixed values (steady-state and during transient), as
shown in 2.7.2.5.
• containment of temperatures within the limits allowed by the cable insulation at normal
operating current, at overload current and at short circuit current under actual installation
conditions, considering the fault clearance time of protective device. (Note 1)
• correct activation of upstream protections in function of the minimum impedance of the
fault circuit

Note 1:
Short circuit current is equal to calculated short circuit current plus 20%
In absence of project data, the fault clearance time of protective device is assumed equal
to:
• 0,5 sec. for Low Voltage system
• 1 sec. for Medium Voltage system

Sizing based on normal operation currents is executed considering the following criteria:
• cables connecting single equipment (such as generators, transformers, motors, heaters)
to the power switchgear shall be sized for the rated current of the equipment.
• cables connecting a switchgear to a sub-board (e.g. from PC to MCC) shall be sized for
the rated current of the sub-board busbar rated current.
• The power cables for socket circuits shall be sized as follows:
 The main cable from the switchboard to each socket junction box shall be sized
according to its length, the number of sockets in the circuit taking in consideration
the diversity factor and considering at least n ° 1 socket (the farthest one) running
at full load (In).
 The cable from JB to socket shall be sized according to socket rated current.

LV cable sizing shall comply with IEC 60364-5-52.

2.8.11.3 Battery cables

The power cables between battery accumulators and switchboard (AC or DC UPS) shall be sized
for the maximum between boost charge current (or maximum charging current, if boost charging
is not applicable to the battery) and the UPS rating on DC side considering the overload
capability, increased of 25%.
Moreover, the battery cables shall have the following characteristics:
• Single core cables
• Non-armoured type if the cable routing is within the same building (i.e. without outdoor
routing)
• Fire resistant in compliance with IEC 60331. Resistance to fire shall be 30 minutes or
more.
• External sheath with the requirement of “Resistance to chemicals and acids”

2.8.11.4 Cable system categories

The system category of cables shall be “B” according to IEC 60502-1, IEC 60502-2.
The “C” system category shall be chosen in case the operating philosophy requires the continuity
of the electrical user with one phase earthed, or in case the system is not designed to open the
circuit on first earth fault.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 68 of 93

2.8.11.5 Cables in parallel

Single core or multicore cables in parallel shall be used to avoid the use of cables with sections
higher than those indicated in paragraph 2.8.11.9.
The cables in parallel shall have the same impedance, the same length and the same section so
that the current is equally distributed on each cable.
Single core buried cables shall be fixed together with metal clamps.

2.8.11.6 Control/command cables

For command cables, in case of cable routes of considerable length, the capacitance of cable and
voltage drop shall be considered to avoid relay malfunction.
All control/command multi-cables shall be selected by using VENDOR standard production with
number of cores greater than the number of cores actually needed, i.e. with the provision of
spare cores.

2.8.11.7 Mechanical protection of cables

Cables in hazardous areas shall be armoured, for exceptions refer to paragraph 2.8.11.3.
All power and control cables installed outdoor shall be armoured-type; alternatively, the main
distribution cables of medium and low voltage, wholly installed in non-classified area, may be
non-armoured-type but shall be installed with appropriate mechanical protection and be
equivalent to the armour (i.e. cable tray with cover or conduit) for all extension up to equipment
terminal box entry.
If a cable route has a section in classified areas, precautions shall be taken to avoid the spread
of hazardous substances in a safe area; for example, cable trench with cover shall be filled with
sand or in the case of cableway in duct, they shall be properly sealed.
Cable armour shall be in tape, wire or sleeve, the choice depending on the section and the type
of flexibility required. In case of single core cables the armour material shall be non-magnetic
type.

2.8.11.8 Cables screen

Medium voltage cables, as well as control cables, shall be provided with screen.

2.8.11.9 Minimum and maximum conductor section

The following tables show the recommended cross sections of cable conductors.
The choice of the maximum section shall consider the bending radius of cables in respect to the
available cable installation space.

Table 13: Medium voltage ONSHORE systems

MINIMUM SECTION MAXIMUM SECTION


TYPE
mm2 mm2
Three-core 25 240

Single core 240 630

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 69 of 93

Table 14: Medium voltage OFFSHORE systems

MINIMUM SECTION MAXIMUM SECTION


TYPE
mm2 mm2
Three-core 25 120

Single core 120 300

Table 15: Low Voltage ONSHORE and OFFSHORE systems

MINIMUM SECTION MAXIMUM SECTION


USE TYPE
mm2 mm2
Power
Distribution/Motor Four-core 4 240
power supply
Power Distribution Five-core 4 185
Power
Distribution/Motor Single core 240 300/630(1)
power supply
Lighting Multi-core 2,5 95
Logical wiring among
Multi-core 1,5(2) -
boards in cabin
Wiring connections
analog and digital
signals among panels in Multi-core 1,5 -
cabin and the control
system
Control and command
Multi-core 2,5 -
towards the field
Power between
Single core 25 300
batteries and UPS

Notes:
1) 300 mm2 is referred to offshore installation, 630 mm2 is referred to onshore installation
2) Ethernet cable excluded

2.8.11.10 General requirements for CPR cables (applicable for EU projects)

• Projects for facilities in the European Union


All cables shall be specified according to the Regulation 305/2011 of the European
Parliament and of the Council and its interpretation through National Laws and
Committee. In any case, the technical characteristics of cables shall not be lower than
the following:
 low smoke, halogen free and flame retardant (Cca-s1b, d1, a1)
 for emergency and safety circuits, also fire resistant (B2ca – s1a, d1, a1 and in
compliance with EN 50200 and EN IEC 60331-1)

• Projects for facilities in Italy

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 70 of 93

All cables shall be specified according to Dlgs 106/17, as follows:


 low smoke, halogen free and flame retardant, according to UNI EN 13501-6 and CEI
UNEL 35016 (Cca-s1b, d1, a1)
 for emergency and safety circuits, halogen free and fire resistant, according to UNI
EN 13501-6 and CEI UNEL 35016 (B2ca – s1a, d1, a1).
For CPR cables, tests and inspections shall be according to EN 50399, EN 60332-1-2, EN 61034-
2, EN 60754-2.
For fire resistant cables, tests and inspections shall be according to CEI EN 50200 and CEI EN
IEC 60331-1, CEI 20-45 and CEI 20-45 V2.

2.8.12 Overhead transmission lines

Overhead transmission lines may be used to connect the plant with remote areas, outside of its
boundaries.
The requirements and recommendations of EN 50341-1 shall be followed.
Limits of exposure to electric and magnetic fields shall be as per national normatives and
regulations. If such limits are not defined in national normatives or regulations, the limits and
recommendations indicated in the Directive 2013/35/EU of the European Parliament and of the
Council shall be applicable.
To provide protection against atmospheric discharge on the overhead lines, surge arresters shall
be foreseen after the gantry structure (e.g. primary side of plant incoming transformer).
The OHTL shall be protected against lightning by means of earth wires that shall be sized in line
with the result of calculations that take in to account the value of expected lightning current.
Shielding of the line by means of earth wires shall be demonstrated by means of calculations.
The use of wooden supports for overhead lines is prohibited.

2.8.13 Decorative colours for electrical equipment

External painting of electrical equipment shall be in compliance with the COMPANY standard
29000.ENG.CPI.STD Appendix “A”, Table “A-2” (offshore and coastal areas) or
29001.ENG.CPI.STD Appendix “A”, Table ”A-2” (onshore).

2.8.14 Neutral earthing resistors

Neutral earthing resistors and related testing activities shall comply with IEEE C37.52, including
the amendment issued in 2020. However, insulation levels and test voltages for applied voltage
tests shall be chosen according to highest voltages for equipment and standard rated short
duration power-frequency withstand voltages indicated in IEC 60071-1.
Reports of the test activities shall be provided.
Rated time of the resistors shall be 10 seconds.
The resistors shall be made of stainless steel.
The resistors shall be provided with removable links.
A contactor, circuit breaker or switch inside an enclosure (same enclosure ratings and access
protections as for NER, if different from it) shall be provided if it is necessary to have the
possibility to disconnect the resistor, in the cases indicated in 2.7.5.1. The switching device shall
be capable to be controlled (open/close and status monitoring) by a remote logic as per 2.7.5.1.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 71 of 93

The earthing resistors shall be housed in a metallic enclosure providing a protection degree of a
minimum as follows:
• IP 23 for indoor installations in rooms enclosed on all sides
• IP 44 for installation in a room opened on one side to the outdoors, by means of grating
or louvers
• IP 55 in other cases
For offshore installations, and for onshore installations in aggressive environment (e.g. marine)
the enclosure shall be made of AISI 316L. In other onshore locations the enclosures shall be
made of galvanized steel.
Cable entrances shall be made of non-magnetic material.
External parts that can be touched by an operator shall not develop surface temperatures that
can result in burn hazards, both in normal operating conditions and in case of earth faults.
A mechanical interlock shall permit access to potentially live parts (i.e. when accessing to the
internal of the enclosure) only in case the resistor is de-energized, as well as the generator or
transformer to which it is connected.
An anti-condensation heater controlled by a thermostat or a self-regulating anti-condensation
heater shall be provided and protected on the feeding line by MCBs or with switch-disconnector-
fuses located in the junction box. Anticondensation heaters shall be protected against contact
(IP2X) and to avoid burning if accidentally touched.
Nameplates shall be engraved with writing on plates made of AISI 316L stainless steel. Related
accessories shall be made of the same material.
Junction boxes shall be provided for the connection of auxiliary circuits, such as space heaters
and amperometric circuits. These shall have protection degree minimum IP44 if installed indoors
in rooms enclosed on all sides, otherwise minimum IP55. Terminals remaining live when the
neutral earthing resistor is de-energized shall be provided with warning labels.
Current transformers for protection functions shall be provided inside the enclosure of the neutral
earthing resistor. Current transformers shall be installed upstream of the resistor. Current
transformer secondary neutral points shall be earthed via a disconnecting link. Current
transformer wiring connected to external circuits shall have shorting links located at the outgoing
terminals.
The resistors shall be provided with lifting eyebolts and accessories necessaries for installation
and maintenance.

2.8.15 Electric process heaters

Electrical requirements for electric process heaters shall be as per IOGP S-723 “Specification for
Electric Process Heaters”.
Regarding the power and control assembly, enclosures for LV applications shall be arc resistant.

2.8.16 CAS levels

IOGP Quality Requirements define CAS (Conformity Assessment System) levels, from A (the
maximum extent of verification) to D (the minimum extent of verification). Inspection and
testing activities, and COMPANY intervention, regardless from the entity that purchases the
equipment (e.g. COMPANY, CONTRACTOR or VENDOR), shall be minimum as follows.
• CAS “A” according to MOD.ELE.MVS.002 “Quality requirements for high voltage
switchgear and controlgear (IOGP S-620Q) (IDS)”
• CAS “C” according to MOD.ELE.RMA.023 “Quality requirements for low voltage three
phase cage induction motors (IOGP S-703Q) (IDS)”

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 72 of 93

• CAS “C” according to MOD.ELE.TRA.002 “Quality requirements for transformers (IOGP S-


720Q) (IDS)”
• CAS “C” according to MOD.ELE.FMX.008 “Quality Requirements for Electric Process
Heaters (IOGP S-723Q) (IDS)”
• CAS “B” according MOD.ELE.UPS.002 “Quality Requirements for AC Uninterruptible Power
Systems (UPS) (IEC 62040-3) (IOGP S-701Q) (IDS)”
• CAS “B” according to MOD.ELE.UPS.006 “Quality Requirements for DC Uninterruptible
Power Systems (UPS) (IEC 62040-5-3) (IOGP S-702Q) (IDS)”
• CAS “C” according to MOD.ELE.RMA.003 “Quality Requirements for High Voltage Three-
phase Cage Induction Motors (IEC) (IOGP S-704Q) (IDS)”
• CAS “D” according to MOD.ELE.ACB.002 “Quality Requirements for Batteries (IEC) (IOGP
S-740Q) (IDS)”

2.8.17 Safe shutdown of machinery

If systems for safe shut down of turbines relying on electrical power are required, such as DC
UPS with battery back-up, these shall be with redundant battery back-up for the required
autonomy period and they shall be certified EPL “Gb”, even if located in safe area. Such system
shall not rely on equipment not certified EPL “Gb”. The gas group shall be determined at project
level, considering the potential emission sources present in the nearby hazardous areas.

2.8.18 Adjustable Speed Electrical Power Drive Systems

Adjustable speed electrical power drive systems (including converters, transformers, filters if
any and motors) shall comply with IEC 61800 (all parts excluding IEC 61800-4).
With reference to IEC 61800-5-1:2016, subclause 4.3.3.3, protective measures against direct
contacts shall be provided even in case of installation in closed electrical operating areas.
Minimum protection degree of the drive enclosure shall be IP31. In case live parts need to remain
energized when the enclosure is open (e.g. during maintenance or installation), they shall be
protected to at least IPXXB.
With reference to IEC 61800-5-1:2016, subclause 4.3.5.1, protective class 0 is not allowed.
Adjustable speed electrical power drive systems shall include the protections against short
circuit, overload, ground fault for the motor and for the converter.
In case of outdoor installation, minimum protection degree of the drive enclosure shall be IP55.

BULK MATERIALS

2.9.1 Lighting system

The lighting systems shall be in accordance with:


• EN 12464 “Light and lighting – lighting of work places”
- Part1: Indoor work places
- Part2: Outdoor work places
• EN 1838 “Lighting application – Emergency lighting”.
LED luminaries shall be used indoors. These shall also be used outdoors, following a verification
of compatibility with ambient conditions. If such conditions are not met, alternatives are
permitted, such as high pressure sodium lamps.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 73 of 93

LED lighting luminaires shall be selected within risk groups RG0 and RG1, according to IEC TR
62778:2014, Table 1.
Luminaires in external areas and in mechanically ventilated spaces drawing outside air shall be
constructed in AISI 316L stainless steel, GRP or aluminium alloy.
The lighting systems is divided and classified as follows:

2.9.1.1 Normal lighting (NL)

Normal lighting is the lighting system designed to enable normal operating activities.
The normal lighting for outdoors areas, roads, yards and tanks shall be designed maximising the
use of floodlight towers.
Floodlight towers shall comply with 28917.ENG.ELE.STD.
The location of the floodlight towers, the types, number and orientation of floodlights shall be
chosen to guarantee proper lighting illumination level both for work and for people’s safety.
To reduce lighting pollution, floodlight towers shall be fitted with:
• narrow-beam floodlights
• screens to prevent the beam of the headlights to come out from the fence
Local lighting systems (i.e. lighting fixture poles) shall be used in addition to the floodlight towers
system, to illuminate dark areas, stairs, local controls and instrumentations apparatus.

2.9.1.1.1 Power supply and electrical distribution (NL)


The normal lighting shall be fed from the main electrical system.
The electrical distribution to normal outdoor lighting circuits shall be derived directly from
electrical substation plant in one of the following ways:
• from lighting distribution panel fed through isolation transformer from a main
switchboard (i.e. Power Centre);
• from "light section" of Auxiliary Services Panel (ASP) through isolation transformer. The
ASP is normally fed directly from a main switchboard (i.e. Power Centre);
• from Auxiliary Service Panel fed directly from a main switchboard (i.e. Power Centre)
through isolation transformers;
• from "light section" of Power Motor Control Centre (PMCC) through isolation transformer
(if necessary to limit the short circuit value).
The normal outdoor light system shall be provided with two operating modes, with
automatic/manual selector, as follows:
• in automatic mode by crepuscular switch (one for the whole plant);
• in manual mode (always ON).
The power supply for crepuscular switch shall be fed by UPS.
Control circuit for crepuscular switch shall be 'fail-safe', i.e., it shall switch the lights ON if a fault
occurs in the crepuscular switch and an alarm shall be raised to the EMS.

2.9.1.2 Emergency lighting (EL)

The emergency lighting system shall consist of the same normal lighting system described in the
previous paragraph but powered by the emergency power system.
The lamps, belonging to the normal lighting system, which will be reenergized by the emergency
system, shall be defined in order to guarantee at least the 30% of the lighting level in normal
operating conditions.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 74 of 93

The floodlight towers shall not concur to this minimum value of 30%, although it is permitted to
connect these to the emergency distribution.

2.9.1.2.1 Power supply and electrical distribution (EL)


The requirements of 2.9.1.1.1 shall be applied, with the following modification:
• Emergency lighting distribution shall be supplied by dedicated switchboard, separate from
normal distribution lighting.

2.9.1.3 Emergency escape lighting (EEL)

The emergency escape lighting system shall be implemented through lighting fixture with
instantaneous insertion lamps. Indoor lamps shall always be on, with exception of sleeping
rooms (including sleeping rooms in infirmary area) and cinemas, in which the lamps shall be
normally off and shall be automatically turned on when power is not available on all the AC
incomers to the UPS feeding them.
Outdoor lamps shall be controlled in two modes, as shown in 28882.ENG.ELE.STD:
• In manual mode, always on
• In automatic mode, by means of crepuscular switch
The power supply for crepuscular switch shall be fed by UPS.
Control circuits for crepuscular switches shall be 'fail-safe', i.e., they shall switch the lights ON if
a fault occurs in the crepuscular switches and an alarm shall be raised to the EMS.
The lighting fixtures shall be positioned in the critical points of the plants and buildings, in order
to detect and allow the use of escape ways and the orientation of the personnel present.
Spot lightings shall be foreseen in proximity of communication points with control rooms and/or
rescue centres (i.e. phone and interphone locations).
Emergency escape lighting fixtures shall be placed all along transit ways with lightings that are
sufficient to allow personnel movement, along escape ways and where specifically required by
safety standards and regulations.
Floodlights shall not be used to concur to the lighting levels required for emergency escape
lighting.

2.9.1.3.1 Lighting fixture with incorporated battery


The use of lighting fixture with incorporated battery shall be limited to:
• indoor areas
• plants where centralized UPS powering system is not foreseen
• containerized packages (such as the internal of gas turbine enclosures).
These types of illuminating tools shall be equipped with control systems that automatically switch
ON of lamps through battery only in case of failure of AC power supply.
Such lamps shall be either fluorescent or LED type. These shall be connected to emergency
distribution network.
All emergency escape lighting fixtures shall be equipped with diagnostics system for both the
lamp and the incorporated battery. Diagnostics shall be at least with local visual indication, and
if required in project documentation, also with remote signaling through hardwired or wireless
systems.
For autonomy time, refer to 2.8.7.5.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 75 of 93

2.9.1.3.2 Power supply and electrical distribution (EEL)


The emergency escape lighting without incorporated battery shall be powered by 230V AC UPS.
The distribution of emergency escape lighting shall not be subject to voltage control or any other
device that may prevent the proper operation of lamps. The distribution of emergency escape
lighting in the distribution panel shall be separate from other UPS distribution.
The emergency escape lighting with incorporated battery shall be powered by emergency
distribution.

2.9.1.4 Additional requirements for lighting inside the buildings

The normal, emergency and safety lighting systems in buildings and cabins, such as electric
substations and control rooms, shall be managed by dedicated electrical switchboards installed
inside each building or cabin.
Each switchboard shall be provided with a normal lighting section, emergency lighting section
and Emergency escape lighting section, in exception to 2.9.1.2.1. Each section shall be provided
with general circuit breaker, MCB with RCD for every circuit and shall not be affected by
crepuscular switch state. Exception shall be made for IT system distributions, for which RCD is
not applicable.

2.9.1.5 Illumination level

According to 20231.ENG.ELE.STD, a study of illumination level (outdoor and indoor) is required.


The minimum illumination level required for the normal lighting shall be in accordance with EN
12464 with the following note:
• Battery room, Transformer room, Power generation room refer to Table 5.3 of EN
12464-1, point 5.3.1.
• Control room refer to Table 5.3 of EN 12464-1, point 5.3.2.
• Outdoor process area refer to Table 5.10 of EN 12464-2, with a minimum average
lighting level of 100 lux.
Emergency escape lighting level shall be in accordance with EN 1838 with the following note:
• par. 4.2.1 the reference is 5lx instead of 1lx
• par. 4.3.1 the reference is 2lx instead of 0,5lx
• par. 4.4.1: high risk area lighting level of 15 lx shall be applied everywhere with
exception of escape routes and general areas

2.9.2 Motor Control Station

For LV motors, motor control station shall be required in the project documents considering the
operability and maintenance requirements.
It shall comply with the classification of hazardous areas as per point 2.8.2 and shall be equipped
with the following lamps (led type):
• Green light – Motor Control Station enabled;
• White light – User ready to start;
and controls:
• Start-Stop control mode selector switch, with three positions: 0 = Central, position of
rest; Start: normally open contact, closes to left, with spring return to 0; Stop = normally
closed contact, opens to right, with latched position, padlockable. Starting shall be
operational only if enabled from the DCS or UCP, stopping shall always be available.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 76 of 93

For MV motors, a local stop shall be foreseen. It shall always be operational, latched and
padlockable in the stop position. If the push button is in the stop position, the motor shall not
be seen as available for starting in the DCS or UCP.
Different arrangements (e.g. additional ammeter or emergency pushbutton) shall be provided if
required in the project documents.
For fire-fighting pumps, see specific requirements in relevant regulations.

2.9.3 Power and convenience sockets

Unless otherwise specified in the project documents, the power sockets shall be:
• 690V/400 V, 32 A, 3-Ph+N+E (or 3-Ph+E for IT systems);
• 230V, 16 A, 1-Ph+N+E (or 2-Ph+E for IT systems).
These shall be provided with interlock.
Convenience sockets shall comply with local rules of the Country where the equipment is
installed.

2.9.4 Conduits

The conduit type shall be:


• hot dip galvanized;
• heavy PVC (for road crossing only).
Each conduit shall be filled with cables for 40% of its capacity or less.
In road crossings 50% reserve conduit or heavy PVC have to be considered at plant completion.
Pipe conduit penetration through walls or ship/hull decks shall be avoided.

2.9.5 Cable trays

The electrical cable trays shall be ladder type and these shall be provided with cover.
The materials indicated in TABLE 16 shall be used.

TABLE 16: Cable trays: materials/installation

MATERIAL INSTALLATION
AISI 316L
Offshore and Onshore outdoors in an aggressive
Glass Reinforced Polyester (GRP) environment (e.g. marine environment)

GALVANIZED STEEL Offshore indoors and onshore in non-aggressive


environment

GRP cable trays shall not be used for cables that are required to be fire resistant.
Cable trays (ladder type) shall be filled with one layer of cables only, with exception of lighting,
small power and control circuits, for which bunched installation is acceptable.
Cable trays shall have at least 30 cm between the bottom of a tray and the cover of the cable
tray below. In the space below the false floor of the electrical room, a minimum free space of 80
cm shall be kept between parallel cable tray routes, in order to allow the access of a person.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 77 of 93

Cable routes shall be designed to keep at least 20% of spare space after project completion.
For characteristics of cable trays, refer to COMPANY Standard 28916.ENG.ELE.STD “Cable
ladders and cable trays”. The use of special parts built in during construction in yard (like curves,
T section, slopes etc.) shall be strictly forbidden. All parts shall be part of the VENDOR cable
trays part list. No other assemblies shall be permitted.
For surface treatments of cable trays, refer to COMPANY standard 29000.ENG.CPI.STD (offshore
and coastal areas) or 29001.ENG.CPI.STD (onshore). Requested durability, when mentioned in
29000.ENG.CPI.STD or 29001.ENG.CPI.STD, shall always be more than 15 years.
For routing installation criteria refer to COMPANY Standard 28045.ENG.STA.PRG. (paragraph of
instrumentation cable ladders/trays).

2.9.6 Cable glands

Cable glands shall be sealed type.


Cable glands for equipment required to be certified for hazardous areas shall comply with IEC
60079.
Cable glands for equipment not required to be certified for hazardous areas shall comply with
IEC 62444.
Effective earth continuity shall be guaranteed between the cable armour/braid and the gland
plate or the internal earth terminal.
If required in the project documentation, the cable glands shall be with anti-loosening facilities.
With metallic cable glands, metallic gland plates shall be used.
For outdoor installations, AISI 316L or nickel plated brass shall be used.

2.9.7 Multi-cable Transit (MCT)

The following recommendations shall be considered:


• Selection of proper material (stainless or galvanized material) considering corrosion, fire,
blast, hazardous location (vapour tight barrier), water, etc.
• If single core cables pass through a transit, non-magnetic materials shall be specified for
the MCT, to avoid inductive heating.
• If bolted to concrete, holes shall have adequate distance from opening to avoid cracking
• Cables must approach cable transit at 90° intersection
• Use different windows to segregate power cables from control cables
MCTs shall be block type. Foam filling is not acceptable.
Multi - cable transits shall be sized for 20% spare capacity at project completion.

2.9.8 Electrical resistance trace heating

Electrical resistance trace heating shall comply with IEC/IEEE 60079-30-1 and IEC/IEEE 60079-
30-2.
If electrical resistance trace heating is entirely installed in non-hazardous areas, and if
compliance with IEC/IEEE 60079-30-1 and IEC/IEEE 60079-30-2 is not requested in 3.3, IEC
62395-1 and IEC 62395-2 may be used instead of IEC/IEEE 60079-30-1 and IEC/IEEE 60079-
30-2.
Switchgear, local panels, junction boxes and transformers part of electrical resistance trace
heating system shall comply in addition with relevant requirements indicated in the present
document, and referenced standards.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 78 of 93

Power transformers dedicated to trace heating shall have a kVA rating at least equal to the 125%
of calculated maximum trace heating loads.
The choice of the protective devices shall consider the start-up currents and the time necessary
to reach the design operating conditions, starting from the minimum possible temperature. No
more than five heating devices or segments shall be connected to the same protective device.
Back-up trace heaters shall be provided to satisfy the following requirements:
• At least 20% of back-up trace heaters shall be provided.
• In case of interruption of a single circuit, for protection intervention or maintenance, it
shall be possible to switch on a back-up trace heater to keep the required performances
of the trace heating system.
• If the trace heating is classified as emergency service, in case of fault of a circuit, a back-
up trace heater shall be designed to switch on in automatic.
Alarms generated by the electrical resistance trace heating system shall be visible in a manned
location. As a minimum, alarms shall be raised in case of fault on a trace heating circuit and in
case of temperatures outside the required operating limits.
The distribution to trace heating loads shall be designed in such a way that:
• The fault or unavailability of a single transformer does not leave any trace heating service
as unavailable.
• The fault or unavailability of a single switchgear busbar, or of a single local panel, does
not leave any trace heating service classified as emergency, or necessary for power
generation start up, or necessary for production, as unavailable.
Additional requirements for electrical resistance trace heating systems, depending on the
standard followed as per above requirements, are described in 2.9.8.1 and 2.9.8.2.

2.9.8.1 Electrical resistance trace heating following IEC/IEEE 60079-30-1 and


IEC/IEEE 60079-30-2

The methods to guarantee that sheath temperatures do not exceed the limits required in
IEC/IEEE 60079-30-1 and IEC/IEEE 60079-30-2, with respect to temperature class or ignition
temperature, and the methods for temperature control, shall be proposed by VENDOR, including
the use of temperature controllers, temperature limiters and sensors, and subject to COMPANY
approval.
Routine tests shall be as per IEC/IEEE 60079-30-1. Test reports shall be provided.
Type test reports shall be provided as per IEC/IEEE 60079-30-1.
The data indicated in IEC/IEEE 60079-30-2, Annex A, shall be provided by CONTRACTOR in
project specification or data sheet.
For systems located in non-hazardous areas, but nonetheless required to follow the requirements
of IEC/IEEE 60079-30-1 and IEC/IEEE 60079-30-2, the requirements shall be those of EPL “Gc”
as a minimum.
Documentation requirements shall be as per IEC/IEEE 60079-30-1, clause 7 and subclauses,
and IEC 60079-30-2, 8.7.2.3.
In addition, electrical resistance trace heating shall comply with IEC 60079-14.

2.9.8.2 Electrical resistance trace heating following IEC 62395-1 and IEC 62395-2

The methods of temperature control, including the use of temperature controllers, temperature
limiters and sensors, shall be proposed by VENDOR and subject to COMPANY approval.
Routine tests shall be as per IEC 62395-1. Test reports shall be provided.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 79 of 93

Type test reports shall be provided as per IEC 62395-1.


Documentation requirements shall be as per IEC 60519-10, clause 13, and IEC 62395-2,
4.7.11.3.
In addition, electrical resistance trace heating shall comply with IEC 60519-10.

2.9.9 Junction boxes

Refer to 28915.ENG.ELE.STD.

INSTALLATION REQUIREMENTS

2.10.1 Electrical rooms

Electrical rooms shall be located in a safe area. If not technically feasible, a positively pressurized
system shall be foreseen. A pressurization system shall also be considered in the case of heavy
pollution (sand, dust, etc.).
Electrical rooms shall be designed with modular bays guaranteeing their extension at least at
one end of the short side.
The following equipment shall not be installed in the same rooms as the electrical switchboards
and UPS:
• Generator;
• Resin (1) /Oil transformer;
• Batteries (2).
Note 1 The installation of dry type resin transformers in the switchroom is permitted if an additional
protective enclosure is foreseen. See 2.8.5.2 for details.
Note 2 See 2.10.1.3

Additional multiservice room shall be foreseen and used for:


• spare parts warehouse;
• documentation archive;
• operator workstation (desk & seat).
The location of the equipment inside the electrical rooms shall consider the following:
• space for easy access and for safe condition of work for the operating and maintenance
people;
• escape routes and emergency exits;
• cables entry;
• future extensions of already installed switchgears and panels (at each side of the MV and
LV main switchgears, free space for at least one column shall be provided);
• future installations.
Equipment shall be installed in accordance with the installation instructions and relevant
supporting base frame drawings provided by the VENDOR.
TABLE 17 shows the required minimum clearances.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 80 of 93

TABLE 17: Switchboards and electrical equipment minimum free space


Front Side
Rear Side
Equipment minimum
minimum [mm]
[mm]
Batteries Racks 800 0
UPSs, LV Inverters/soft starter 800 (1)

MV switchgears 1400 800(5)


Power Centre 1000 0(2)
Motor Control Centre 800 0(2)
Panels 800 0
Power Transformers (3)
800(4)
Neutral earthing resistor (3)
500(4)

Notes:
1. VENDOR installation instruction.
2. With rear access: 600mm.
3. Minimum distance from fence considering operation, maintenance and safety as per VENDOR
recommendation.
4. Valid for the other three sides.
5. In case rear accessibility is required for maintenance.
In case of equipment with doors, the minimum front side clearance shall be equal to the door’s
width plus 200mm.
The minimum vertical clearance from equipment to ceiling shall be 450 mm. In case of presence
of flaps for the evacuation of gases produced during internal arc, the distances recommended
by VENDOR shall be respected. In case such gases are evacuated by means of a conduit, the
space on top of the conduit may be reduced below 450 mm, according to VENDOR
recommendations.
At least one access door shall be sized to allow the passage of the single largest part of an
equipment (at least the complete largest and tallest switchgear column).
A free area under the floor shall be provided to allow the installation of cable trays and cables.
The minimum available space excluding the space taken by the structure, shall be:
• cable cellar: 1800 mm;
• floating floor: 800 mm.

2.10.1.1 Generator room

Generator room shall be installed in a non-hazardous area.


It shall be located close to their associated step-up transformers, if any, and near the relevant
switchgear room.
Generator control panel and start-up batteries shall be installed in the generator room.
A crane for maintenance purpose shall be foreseen.

2.10.1.2 Transformer bay

Outdoors, power transformers shall be installed in a fenced area. As an alternative, these may
be installed in a room with one side open to the outside by means of grating or louvers.
A key interlock shall be implemented to guarantee that opening of the gates of the fence (or of
the door to the room) shall be possible only if the transformer is powered off, unless the

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 81 of 93

transformer is mechanically protected to avoid direct contacts, or if all potentially live parts are
located out of reach, at a minimum height as per indications of IEC 61936-1.
Unless the transformer is oil immersed type connected to overhead lines, outdoor transformer
bay shall be equipped with canopy. Canopy shall be sloped to avoid the stagnation of water.
Neutral earthing resistors shall be placed in proximity of transformers.
Oil immersed transformers shall be provided with:
• oil catchment pit below the power transformer;
• fire-walls between each transformer (1).
NOTE 1 the separation distance between transformers shall be in accordance with IEC 61936-1. If it is not
practical or economic to allow for adequate clearance, then a fire-resistant separating wall shall be installed,
in accordance with IEC 61936-1.
For oil immersed transformers, the direction of emission of liquid from the pressure relief device
shall be away from the position of possible approach of an operator to the bay in which the
transformer is installed.

2.10.1.3 Battery room

The electrical equipment inside the battery room shall be certified EPL “Gb”, gas group IIC or
IIB+H2, temperature class T3. The battery room ventilation shall be as per 20453.ENG.MEC.PRG
(onshore) or 20452.ENG.MEC.PRG (offshore), and in compliance with IEC 62485-2. A minimum
of two extracting fans shall be provided. The floor shall be resistant to the electrolyte used for
the batteries.

2.10.2 Cabling and wiring

If cables of different insulation voltage levels and different services (e.g. power and electrical
control cables) are installed in the same cable tray, a metal barrier shall be used to separate
them.
The cable routes of safety users shall be kept separate from those in normal and emergency
system. Cables used for safety users shall be “fire resistant” type.
Single core cables shall be laid in trefoil or in linear laying with transposition of each phase.
Moreover, all crossings, passages, penetration of single core cables shall be realized in non-
magnetic material.
Laying of cables on the floor, on the ground, or on the bottom of the area under false floor, is
not permitted.
The required minimum depth for underground cables shall be:
• 1 m for MV cables
• 0,8 m for LV cables
Underground duct banks shall be provided with suitable cable pulling pit at both ends of the duct
bank in order to ease the cable pulling.
Cables shall be identified by means of the application of appropriate labeling in AISI 316L with
letters engraved in compliance with the COMPANY standard 20198.VAR.LCI.STD.
The label shall be installed:
• At both cable ends
• Where the cable changes the direction
• Before and after cable penetration (MCT, wall, etc.)
For MCTs, see 2.9.7.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 82 of 93

In addition, the following cable entry methods for wall crossing may be used:
• sleeves welded to the plate, to be sealed with a locking compound and plugging fibre
after the insertion of cables;
• sleeves welded to the plate, with cable glands screwed to the external side;
• sealed and threaded transits provided with a threaded locking rings for the closing plate.

2.10.3 Lighting system

Every floodlight tower shall be provided with local panel containing the protective device for all
floodlight and for other electrical accessories (e.g. electric motor for mobile crown). The
enclosure shall be in accordance with the hazardous area classification. For details, refer to
28917.ENG.ELE.STD.
The power on three-phase or three-phase with neutral circuits shall be uniformly distributed
among the three phases. Similarly, the power on the single-phase distribution to luminaires shall
be balanced on the upstream three phase supply system.
The power to adjacent lighting fixtures shall be supplied from different circuits (at least 2) so
that in case of fault or planned cut-off of a circuit, part of the lighting can still be kept in
operation.
With the aim to avoid stroboscopic effects, feeding of luminaires in the same areas shall be
provided from different phases.
Circuit breakers feeding lighting circuits shall be designed considering the inrush current of the
lighting fixtures.
Lighting distribution to luminaires shall be single phase except for:
• Floodlight tower;
• Street lights.
The cable sections shall be coordinated with the corresponding entrances on the lamp
enclosures; if this cannot be achieved, a local junction box (one for each lighting fixture) shall
be foreseen.

2.10.4 Earthing system

If MV or HV equipment are present, a global earthing system shall be adopted for the entire
facility, according to the definition of IEC 61936-1 and EN 50522.

2.10.4.1 HV substations

The grid mesh of grounding system shall be calculated in order to comply with the requirements
of IEC 61936-1, but in any case it shall not be larger than 5 m x 5 m.
Surge arresters shall be connected with the shortest routes and, in any case, with large elbow
bending, to the earth electrode.
Every equipment and every other metal structures shall be connected to the earth electrode by
means of two earth wires.
Air insulated high voltage substation shall be protected against lightning by means of overhead
earthing wires.
The frame structures supporting the overhead earthing wires may be used as natural down-
conductor, provided their metallic continuity is proved.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 83 of 93

2.10.4.2 MV and LV substations

A buried bare-wire ring shall be provided around the electric substations; the ring shall be
connected to the general earth electrode of the plant in at least four points. A ring of bare
conductor along the internal perimeter of the switchboard room or of the relevant cables room
is required, and shall be connected at external ring in at least four points. Every switchboard
shall be connected at the internal bare-wire in at least two points.
The substation metal structures and/or concrete reinforcement bars shall be electrically bonded
and shall be connected to the earth electrode, according to reference rules.
In substations with concrete flooring, with a pre-welded metal grid, the grid shall be connected
to the earth electrode by means of earthing bars.

2.10.4.3 Electric equipment

Electric equipment shall be protected against indirect contacts; in particular:


a) Medium voltage equipment shall be connected to the earth electrode by means of two
different earthing bars through two different conductors.
b) Low voltage equipment, including sockets, shall be connected to the earth electrode by
means of one earthing bar through one conductor.
For low voltage equipment on metal structures, the structures themselves shall be normally
used as a supplementary equipotential conductor, provided their metallic continuity is
guaranteed.
c) Switchboards and control boards in field shall be provided with an earthing bar to which all
PE conductors shall be connected.
d) Luminaries shall be connected to the earth bolt or earthing bar of the relevant switchboard
by means of a PE conductor.
e) luminaries and small power equipment installed outside the area relevant to the earth
electrode shall be earthed with a dedicated earth electrode, made of a horizontally buried
bare wire, at least 10 m long, or by a rod.
f) PE conductor shall be distributed to all LV users, in TN and IT systems.
As exception to the above, equipment having double or reinforced insulation shall comply with
the requirements of IEC 60364-4-41, of IEC 61439-1 (for LV switchgear), of IEC 62040-1 and
IEC 62477-1 (for UPS).

2.10.4.4 Metal structures, equipment and interconnecting

Any metal structures, equipment, columns, tanks, rails etc. which are inside the area relevant
to the earth electrode shall be connected to the earth electrode through earthing conductors or
through other metal structures.
Electrical continuity shall be guaranteed in the piping spools to avoid sparking due to static
electricity. The flanges shall guarantee electrical continuity. If this is not achieved through the
metal to metal contact on the flange and the flange serrating bolts (due to painting insulation
thickness or nonconductive gaskets), this shall be achieved through bonding jumpers directly
installed on the flanges bolts. If flange insulation gaskets are foreseen to avoid corrosion between
different piping materials, isolating sparking gap connectors shall be used.
Any metal structures, cable trays, rails, pipes etc. entering or leaving the plant earth electrode
area shall be interrupted by means of insulating joints.
The armour or braid of electrical cables shall be earthed at both ends. The armour or braid shall
be capable to sustain the earth fault current flowing through it for the time necessary for the

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 84 of 93

intervention of the protections. For single core cables, the sizing of the cable shall also consider
the flowing of current in the armour during normal operation.
Screen of electrical cables, if present, shall be earthed at one end only. If one end is on field or
in classified area, this shall be the one to be earthed, otherwise it shall be earthed on switchgear
side. A specific study shall be made to verify the voltages between the screen and earth on the
unearthed side, considering the worst case (in terms of cable current and cable length).
Unearthed screen extremities shall be covered and isolated against the possibility of accidental
contact during inspection or maintenance activities. The unearthed side shall be isolated at least
with the same insulation level of the cable nominal voltage.
Specific requirements for interconnecting cables inside packages (e.g. motor and adjustable
speed electrical power drive system), if different from those above indicated, shall be declared
by the VENDOR.
Onshore, if a cable is connecting equipment located in areas with separate earth electrodes, the
armour or braid shall be in one of the two following conditions:
• Earthed at one end only. This is not permitted in LV. If one end is in classified area, this
shall be the one to be earthed. A specific study shall be made to verify the voltages
between armour or braid and earth on the unearthed side, and unearthed armour
extremities shall be covered and isolated against the possibility of accidental contact
during inspection or maintenance activities. The unearthed side shall be isolated at least
with the same insulation level of the cable nominal voltage.
• Earthed at both ends. In this case, the earthing system of each of the two facilities shall
be verified also against an earth fault in the other facility.
In respect of electrostatic charges and lightning, all pipes penetrating a structure (e.g. plant unit
or building) shall be connected to the earth electrode at the point of penetration; furthermore,
their metallic continuity shall be verified and in case it is not guaranteed, equipotential
connections shall be installed. Earthing connections shall be designed considering cathodic
protection systems, if present.

2.10.4.5 Buildings

A bare-wire ring, horizontally buried at a minimum depth of 0,5 m and at a distance of 0,5 m up
to 1 m, shall be provided around buildings. The ring shall be connected to the general earth
electrode of the system in at least four points by means of an earthing terminal or earthing bar.
The main metallic structures of buildings shall be connected at regular intervals, not exceeding
20m, to the above mentioned ring, alongside the reinforcing bars of concrete. All external masses
shall be connected to the ring.

2.10.4.6 Metal fences

Metal fences which are inside the earth electrode area shall be connected to the latter at least
in two points and, in any case, every 20m.
Metal fences located outside the plant earth electrode area shall not be connected to the plant
earth electrode. If there are electrical equipment mounted on them (e.g. lighting fixtures, electric
gates) or nearby in such a way that they could be touched by a person at the same time as the
fence, a separated local earth electrode shall be provided buried under the fence itself. Such
equipment shall be fed through isolation transformer; for the cables supplying the transformer,
armour and screen shall not be earthed on transformer side and the PE conductor shall not be
provided. Users shall be protected with residual current protection.
If electric gates and/or lighting affect only a small part of the fence, the affected fence shall be
insulated from the other parts.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 85 of 93

2.10.4.7 Tankers - mobile containers of flammable materials

Tankers and other mobile containers of flammable materials shall be connected to the fixed
filling/discharging equipment and earthed by means of specific devices, before the flammable
materials are transferred.
The specific devices shall be in “Ex d” execution, suitable for operation in the hazardous area.
They shall be anti-tearing type which unlocks automatically in case it is forgotten, and they shall
be provided with interrupting facilities (e.g. auxiliary contacts) to allow the starting of the pump
or block it.

2.10.4.8 Pipeline valve control rooms

In pipeline valve control rooms which contain motor-driven valves, in metallic continuity with
the pipeline, the motor controlling the valve shall not be connected to the earth system of the
plant.
Protection against indirect contacts shall be guaranteed with isolation transformer. For the cables
supplying the transformer, armour and screen shall not be earthed on transformer side and the
PE conductor shall not be provided. Users shall be protected with residual current protection.

2.10.5 Lightning system

For installation criteria of lightning system refer to IEC 62305 series.

2.10.6 Aviation warning lighting

Aviation warning lights shall be installed in accordance with Volume 1 Chapter 6 of ICAO Annex
14. The luminaires shall consist of a double lamp unit with automatic changeover to the stand-
by lamp upon failure of the operating lamp.

2.10.7 Power and convenience sockets

Power sockets shall be provided for operative and maintenance purposes. Their position shall be
close to the point of possible use.
The sockets shall be located as indicated in the TABLE 18.

TABLE 18: Type, quantity and position of the sockets

AREA SOCKETS POSITIONS

Process area excluding elevated platforms and 1 socket 690V/400V 32A every 30 m of range
passageways 1 socket 230V-16A every 15 m of range

Process area: 1 socket 690V/400V 32A


Elevated platforms and in the proximity of
1 socket 230V-16A
personnel passageways
Power socket 690V/400V 32A
Power socket 230V-16A
Building / Prefabricated cabins inside the plant
perimeter Convenience socket 230V-16A
quantity and position according to the usage
purpose

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 86 of 93

The convenience socket (wall mounted) in the building or prefabricated cabins (package type)
shall be installed at an elevation not lower than 300 mm from the floor (measured from the
socket's centre line).

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 87 of 93

3 ADDITIONAL REQUIREMENTS FOR OFFSHORE PLANTS

GENERAL

The design of the electrical system for offshore installation shall comply with chapter 2 of the
present document, with the exceptions and amendments indicated in this chapter 3.
The design of electrical systems for offshore installations shall be in accordance with IEC 61892.
In case IEC 61892 has different requirements than chapter 2 or chapter 3 of the present
document, the most stringent requirement shall be applied. Due to limited space and evacuation
time in case of danger, specific requirements regarding people safety shall be foreseen..
Materials and equipment with low risk of fire and smoke emission shall be used.
Cables with low smoke and zero halogen emission shall be used.
Outdoor equipment shall be rated IP 56 or IP 66 (IP 65 or IP 66 for lighting fixtures). For
transformers, refer to 2.8.5 and subparagraphs.
A floating floor shall be provided within switchroom (with minimum height of 800 mm) for cable
routing. Cable penetrations shall be by MCT.
In addition to TABLE 4, for emergency loads refer to IEC 61892-2, Annex B, considering that
some of the loads are however already classified as safety in the present document.
In some countries (e.g. Italy) the local regulation requires the segregation between emergency
switchroom and normal switchroom.
For FPSO and floaters, the main emergency switchgear shall be separate, and in a different
room, with respect to normal and essential switchgear.
For dry type transformers, AFWF cooling method is permitted, but only if the following two
conditions are verified:
• The transformer is not energized when the system is powered from emergency power
sources.
• The water system necessary for cooling is available and operational without prior
energization of the transformer.
If liquid immersed transformers are installed, the requirements of IEC 61936-1 shall be complied
with in this respect, in addition to the requirements of IEC 61892-6.
Liquid immersed transformers shall have internal cooling medium indicated with letter “K”
according to IEC 60076-2.

NEUTRAL EARTHING

The neutral configuration in offshore installation shall be in accordance with TABLE 19:

TABLE 19: Neutral earthing – selection guide


PLATFORM FPSO - FLNG
Medium Voltage Low Voltage Medium Voltage Low Voltage
Neutral earthed by Neutral directly Neutral earthed by Neutral directly
impedance or earthed impedance or neutral earthed for living
earthing transformer for main, emergency earthing quarter, Heat tracing
(1)
generator and power transformer(1) (TN-S)
distribution. (TN-S)
Neutral isolated for
Neutral isolated for AC-UPS (IT)
AC-UPS (IT)

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 88 of 93

Neutral isolated or
impedance earthed
for power
distribution, process
users, vessel users,
essential generators,
emergency
generators (IT)

Notes:
(1) According to par. 2.7.5.1

Regarding the UPS, see par. 2.7.5.3. Regarding other low voltage switchgear with IT system,
insulation control devices shall be provided. In case of earth fault, an alarm shall be raised to
the EMS, with indication of the faulty busbar. The faulty feeder shall be identified by means of
visual indication on the front of the switchgear.
28880.ENG.ELE.STD has been designed for TN systems. If IT system is used,
28880.ENG.ELE.STD shall be updated by CONTRACTOR on project basis and submitted for
COMPANY approval.
In IT systems, the neutral conductor shall not be distributed.

PROTECTION AGAINST EXPLOSION AND FIRE HAZARD

In addition to par. 2.8.2, the requirements of ignition source control indicated in IEC 61892-1
shall be followed.
Moreover, considering a future reclassification of area, or to standardize and to reduce the spare
parts, electrical bulk materials shall be certified EPL “Gc” also if installed in outdoor non-
hazardous areas.
Electrical resistance heat tracing systems located outdoors, or required to fulfil the requirements
for installation in hazardous area due to ignition source control principles indicated in IEC 61892-
1, shall comply with IEC/IEEE 60079-30-1 and IEC/IEEE 60079-30-2.

PROTECTIVE DEVICE

Contrary to what is indicated in IEC 61892-2, subclause 11.2.3, the backup protection device is
not permitted; all devices shall have a breaking or making short-circuit capacity higher than the
prospective short-circuit current at the point where these are installed.
In addition to 2.7.7.1, in offshore it is permitted to use a FCL (fault current limiter) also for new
facilities, subject to COMPANY approval.
The use of FCL for new facilities shall also be subject to both the following conditions:
• The FCL is installed in, or connected to the switchgear to which main power generation
is connected.
• The nominal system voltage utilized for the switchgear where the main power generation
is connected is 11 kV for 50 Hz systems or 13,8 kV for 60 Hz systems, and the switchgear
has a rated short time withstand current equal to the maximum permitted in TABLE 7.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 89 of 93

ESSENTIAL POWER GENERATION SYSTEM

In addition to main and emergency power generators, essential power generators shall be
installed for FPSO-FLNG and may be required for offshore platforms.
Essential power generators shall guarantee the supply of all preferential users necessary to
maintain the unit in habitable condition, naval loads, offloading loads and all the process and
utilities to assure proper subsea field preservation. For additional details, see IEC 61892-2,
Annex A.
The typical configuration is 1+1, i.e. 2 generators each sized for 100% of load (1 running + 1 in
stand-by).
It shall be possible to feed the whole emergency distribution network from essential power
generation, and the whole plant under main power source.
In case of loss of main power sources, essential generators shall be capable to start and to
connect to the loads even if the emergency power generation is not operational.
Contrary to what is indicated in IEC 61892-2, subclause 4.2.1, essential power generators shall
not be used as spares of main power generators to fulfill the N+1 sparing philosophy requested
in 2.8.3.2, unless specifically authorized by COMPANY.
In case essential power generation is necessary for the black start of the facility, or to restore
the main power sources following a shut-down, essential generators shall be in N+1 sparing
philosophy.
TABLE 20 describes the operating mode for FPSO and floaters.

TABLE 20: Generation system operation mode for floaters


MODE OF MAIN POWER ESSENTIAL POWER EMERGENCY POWER
OPERATION GENERATION GENERATION GENERATION
EMERGENCY
OFF OFF ON
MODE
SAILING OFF ON OFF
PRODUCTION ON OFF OFF
PRODUCTION
AND
ON (1)
OFF(2)(3) OFF
OFFLOADING
MODE

Notes:
(1) When the required total power exceeds the power rating of N generators, all generators may work
(including the stand by generator), subject to specific COMPANY authorization.
(2) When one main generator is out of service, a configuration with essential generators running may
be foreseen, subject to specific COMPANY authorization.
(3) Production and offloading mode may be supplied by Main and essential generator together, subject
to specific COMPANY authorization.

CABLES

All electrical power and control cables (included internal wiring of switchgear and other enclosure
for electrical equipment) shall be in accordance with IEC 61892 with the following amendment:

3.6.1 IEC 61892-2 “System design”

• § 9.1 Cables

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 90 of 93

In addition to what is indicated in the reference paragraph, the following circuits shall be
realized with cables low smoke, halogen free and fire resistant, according to IEC 61034-
2, IEC 60754-1, IEC 60754-2 and IEC 60331 series:
- Power and control of firefighting system;
- Fire and gas detection system (1)
- Emergency escape lighting;
- Interconnecting cables from battery to UPS;
- Navigation Aids, Aeronautical obstruction lights, helideck lights, helideck and boat
landing status lights.
- Radio communication (1)
- Other emergency and critical loads defined in the project specification.
Note (1): See also COMPANY Standard 28045.ENG.STA.PRG.

3.6.2 IEC 61892-4 “Cables”

• § 4.1 Type of cables


The sentence “All cables shall be low smoke and halogen free” shall be replaced with “All
cables shall be low smoke, halogen free and flame retardant, according to IEC 61034-2,
IEC 60754-1, IEC 60754-2, IEC 60332-3-22”.
• Cables to be routed where there is risk of deposits or dripping of liquid hydrocarbons shall
have been qualified according to the type tests of immersion in mineral oil as per IEC
60092-360 Table 6 and IEC 60811-404.
• § 4.2 Voltage rating – Power frequency cable
The system category of cables shall be “B”.
The “C” system category shall be chosen in case the operating philosophy requires the
continuity of the electrical user with one phase earthed, or in case the system is not
designed to open the circuit on first earth fault.
• § 4.4. Cross-sectional areas of conductors and current-carrying capacities
The maximum permissible service temperature of the conductor shall be 90°. Cables shall
not be designed to be used with a temperature of the conductor over 90°C in continuous
service.

3.6.3 IEC 61892-6 “Installation”

• § 14 Cables and wiring


In addition to what is indicated in the reference paragraph, cables laying on two layers in
cable trays is acceptable for low voltage cables only.

3.6.4 Other requirements

The outer sheath compounds of cables shall be SHF 1 or SHF 2 according to IEC 60092-360.
Even if indicated in IEC 60228, Aluminum conductor for electrical cables is not permitted.
Routine tests, sample tests, type tests shall be performed as per indications of reference
standards IEC 60092-353 (Tables 4, 5, 6), IEC 60092-354 (Tables 3, 4, 5).
Test after installation shall be performed as per Annex A of IEC 60092-354.
When fire resistance is required, type tests shall be as per IEC 60092-353 Table 7 and as per
Annex A of IEC 61892-4:2019.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 91 of 93

Reports of the tests shall be provided. Type tests already performed do not need to be repeated,
if so permitted in reference standards.
DC voltage test of the insulation shall be avoided.

3.6.5 CPR cables

For projects for facilities in the European Union, see the requirements of 2.8.11.10.

EARTHING AND BONDING

If a cable is connecting two different plants of which at least one is offshore, the armour shall
be earthed at both ends. The earthing system of each of the two facilities shall also be verified
against the possibility of earth fault in the other facility.

LIGHTNING PROTECTION SYSTEM

The requirements and recommendations of IEC 61892-2, IEC 61892-3 and IEC 61892-6 shall be
complied with, in addition to specific regulations of the classification society. The protection of
exposed vents against the possibility of lightning strike shall be verified.

LIGHTING

The par 2.9.1 is applicable with the following notes:


• The lighting system shall also be in accordance with IEC 61892-2. In case of conflict
with the EN 12464 and the EN 1838, the IEC 61892-2 shall prevail. For parameters
related to lighting and not specified in the IEC 61892-2, the EN 12464 shall be applied.
• With reference to IEC 61892-2 Annex G, it shall be considered as mandatory. In Annex
G.3, consider 10lx instead of 1lx.
• Lighting distribution panels shall be separate between normal, emergency, and
emergency escape lighting fed from UPS.
• Emergency escape lighting shall always be certified EPL “Gb”.
• Local accessories and junction boxes of emergency escape lighting shall always be
certified EPL “Gb”.

NAVIGATION & AERONAUTICAL AIDS SYSTEM FOR OFFSHORE PLATFORMS AND


FLOATERS

Navigation and aeronautical aids system shall comply with COMPANY Standard
20174.ENG.ELE.STD.

SWIVEL AND TURRET

Concerning the electrical parts of the swivel and turret, IEC 61892-2 shall be complied with,
including the recommendations included in Annex D.
Electrical distribution through the swivel shall be designed in such a way that a failure of any
feeder passing through slip rings does not render any essential, emergency or safety service
unavailable.
A minimum of 20% spare slip rings shall be provided on medium and low voltage swivel, if
present. As a minimum, swivel paths sufficient for two spare feeders for medium voltage and
two spare feeders for low voltage shall be provided. Rating of the spares shall be selected based

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 92 of 93

on the maximum rating of the slip rings foreseen, unless specifically otherwise approved by
COMPANY.

SUBMARINE CABLES

This paragraph is applicable to submarine cables connecting two surface facilities, and does not
cover umbilicals or feeding of subsea facilities.
Submarine cables and related accessories shall comply with IEC 63026, for the voltage ranges
and water depths therein indicated. For the purpose to choose submarine cable rated voltages,
the system shall be considered to be of Category C as per IEC 63026.
Submarine cables and related accessories shall be sized considering a margin of 20% on the
calculated current requirements.
Where a greater protection of the cable is required (e.g. in sea beds in presence of rocks or
reefs) an additional layer shall be applied to the armour, as explained in subclause 5.8 of IEC
63026.
As a minimum, the characteristics of the cable listed in clause 6 of IEC 63026 shall be provided
by VENDOR.
Routine tests, sample tests, type tests and tests after installation shall be performed as per IEC
63026. The possibility to keep the validity of type tests performed on similar cables shall be as
described in clause 12 of IEC 63026. In any case, COMPANY shall be entitled to witness all the
tests. Reports of all tests, including type tests on similar cables, shall be provided.
DC voltage tests of the insulation shall be avoided.
The cable shall include the minimum possible number of joints.
Progressive numbering for the determination of the length, repeated at constant 1 m intervals
on the external sheath of the cable, shall be provided.
If delivery in drums is applied, the extremities of each cable delivery length shall be sealed and
fixed to the drum. The extremities of each cable delivery length shall be accessible for checks
and tests without need of unwinding the cable. The internal and external flanges of the drums
shall be provided with metallic label indicating at least the following:
• Data at points a) and b) of clause 6 of IEC 63026
• Number of cores and conductor cross section
• Cable identification code number
• Drum identification number
• Length of cable on the drum
• Total weight of drum and cable
As a minimum, optical fibre shall be provided in order to realize intertripping and interlocking
functions between switchgear feeder and switchgear incomer located upstream and downstream
of the cable, as indicated in 2.7.8 and 28881.ENG.ELE.STD. Optical fibre inside the cable shall
comply with IEC standards developed by technical committee 86 and subcommittees.
Submarine cables and their accessories, if used for dynamic applications such as connection to
floating installations, or if used beyond the water depth limits indicated in IEC 63026, shall have
been subject to a qualification process. The procedure for such qualification process, that shall
consider the effects of extreme loads and a fatigue analysis related to conditions of installation
and during operational life, shall be proposed by VENDOR and subject to COMPANY approval.
The qualification process shall include fatigue testing and shall be based on sound technical and
scientific publications, such as:
• Cigré TB623 “Recommendations for Mechanical Testing of Submarine Cables”
• DNVGL-RP-F401 “Electrical power cables in subsea applications”

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.
eni spa 20208.ENG.ELE.PRG
Rev. 13 July 2021
Sheet 93 of 93

The report of the qualification process shall be provided to COMPANY.

ENGINEERING COMPANY STANDARD


Documento riservato di proprietà di Eni spa. Esso non sarà mostrato a terzi né utilizzato per scopi diversi da quelli per i quali è stato inviato.
This document is property of Eni spa. It shall neither be shown to third parties nor used for purposes other than those for which it has been sent.

You might also like