Parameters

E(demand)
Penalty
Interest rate
C
K
Lead Time
We need To convert Tao to yr as per your demand

STD Dev per lead time


Mean per lead time

Step 1
h

Safety Stock

H.C
O.C
P.C

2. Total Cost

3. Time between Orders

4. The proportion of order Cycles in which no stock-occurs


200 per yr
25 per jar
0.2 yr
10 $
50 $/order
6 mnth
0.5 yr

25 mean
100 STD

2 $/unit/period

42 Jars

195 $/yr/unit
90.09 $/yr/unit
20.61 $/yr/unit

305.70 $/yr/unit

0.555 yrs

it is my 1-F ( R ) at my optimal Solution 96%


itr Q(1) R [4]
0 100 143.00
1 110 142.00
2 111
100

1 Answer (Q,R) = (111,142)


WE STOP AFTER ITR 2 is close to ITR 1 (Q)
1-F( R ) [2] Z[3] L(Z) [5] N( R ) [6]
0.04 1.75 0.0162 0.405
0.044 1.71 0.0183 0.458
0.0444
0.04
Parameters
E(demand)
Penalty
Interest rate
C
K
Lead Time
We need To convert Tao to yr as per your demand

Mean per lead time


STD Dev per lead time

Step 1
h

Safety Stock

H.C
O.C
P.C

2. Total Cost

3. Time between Orders

4. The proportion of order Cycles in which no stock-occurs


3360 per yr
12.8 per jar
0.28 yr
1.5 $
15 $/order
5 mnth
0.42 yr

1400 mean
172.177234267484 STD

0.42 $/unit/period

440 Jars

299.88 $/yr/unit
91.97 $/yr/unit
22.97 $/yr/unit

414.82 $/yr/unit

0.163 yrs

it is my 1-F ( R ) at my optimal Solution 99%


itr Q(1)
0 490
1 542
548

1 Answer
WE STOP AFTER ITR 2 is close to ITR 1 (Q)
R [4] 1-F( R ) [2] Z[3] L(Z) [5]
1846.00 0.00478516 2.59 0.0015
1840.00 0.00529296875 2.56 0.0017

(Q,R) = (82,114)
TER ITR 2 is close to ITR 1 (Q)
N( R ) [6]
0.258
0.293
Parameters
E(demand)
Penalty
Interest rate
C
K
Lead Time
We need To convert Tao to yr as per your demand

STD Dev per lead time


Mean per lead time

Step 1
h

Safety Stock

H.C
O.C
P.C

2. Total Cost

3. Time between Orders

4. The proportion of order Cycles in which no stock-occurs


3360 per yr
12.8 per jar
0.28 yr
1.5 $
100 $/order
5 mnth
0.416666666666667 yr

172.18
1400

0.42 $/unit/period

383 Jars

439.53 $/yr/unit
253.20 $/yr/unit
25.11 $/yr/unit

717.84 $/yr/unit

0.395 yrs

it is my 1-F ( R ) at my optimal Solution 96%


itr Q(1) R [4]
0 1265 1786.00
1 1323 1783.00
2 1327

1 Answer (Q,R) = (1327,1783)


WE STOP AFTER ITR 2 is close to ITR 1 (Q)
1-F( R ) [2] Z[3] L(Z) [5] N( R ) [6]
0.012353515625 2.25 0.0042 0.723
0.012919921875 2.23 0.0045 0.775
Parameters
E(demand)
Penalty
Interest rate
C
K
Lead Time
We need To convert Tao to yr as per your demand

STD Dev per lead time


Mean per lead time

Step 1
h

Safety Stock

H.C
O.C
P.C

2. Total Cost

3. Time between Orders

4. The proportion of order Cycles in which no stock-occurs


456 per yr
400 per jar
0.4 yr
18.8 $
75 $/order
3 wks
0.0576923076923077 yr

8.89960
26.3076923076923

7.52 $/unit/period

22.6923076923077 Jars

542.886153846154 $/yr/unit
345.45 $/yr/unit
19.68 $/yr/unit

908.02 $/yr/unit

0.217 yrs

it is my 1-F ( R ) at my optimal Solution 96%


itr Q(1) R [4]
0 96 49.00
1 99 49.00
2 99

1 Answer (Q,R) = (99,49)


WE STOP AFTER ITR 2 is close to ITR 1 (Q)
1-F( R ) [2] Z[3] L(Z) [5] N( R ) [6]
0.003957894737 2.66 0.0012 0.011
0.004081578947 2.65 0.0012 0.011