Michelle Go ARCH-4B BUILDING TENCHNOLOGY 5

STRUCTURAL FRAMING
COLUMN 1 (C-1) 4pcs, [LxWxH = 0.432]
CEMENT 5.184(4) = 20.736 BAGS
SAND 0.216(4) = 0.864 CU M
GRAVEL 0.432(4) = 1.728 CU M

FOOTING 1 (F-1) 4 pcs, [LxWxH = 0.672]


CEMENT 8.064 (4) = 32.256 BAGS
SAND 0.336 (4) = 1.344 CU M
GRAVEL 0.672 (4) = 2.688 CU M

FOOTING TIE BEAM (FTB-1) 2pcs, [A=0.615], L / R


CEMENT 6.48 (2) = 12.96 BAGS
SAND 0.3075 (2) = 0.615 CU M
GRAVEL 0.615 (2) = 1.23 CU M

FOOTING TIE BEAM (FTB-1) 1pcs, [A=0.54], REAR


CEMENT 6.48 BAGS
SAND 0.27 CU M
GRAVEL 0.54 CU M

FOOTING TIE BEAM (FTB-1) 1pcs, [A=0.39], FRONT


CEMENT 4.68 BAGS
SAND 0.195 CU M
GRAVEL 0.39 CU M

CHB BELOW NGL


6" CHB EXTERIOR 2SIDES(L/R), [A = 2.46 SQM]
2.46 X 12.75 = 30.75 (2) = 61.5 pcs

6" CHB EXTERIOR REAR SIDE, [A = 2.16 SQM]


2.16 X 12.5 = 27 pcs

6" CHB EXTERIOR FRONT SIDE, [A = 1.56 SQM]


1.56 X 12.5 = 19.5 pcs

4" CHB INTERIOR (0.80 X .60 = 0.48)


0.48 X 12.5 = 6 pcs

4" CHB INTERIOR (2.50 X .60 = 1.50)


1.50 X 12.75 = 18.75 pcs

4" CHB INTERIOR (.10 X .60 = 0.06)


0.06 X 12.5 = 0.75 pcs
ROOF BEAM
ROOF BEAM 1 (RB-1) 2pcs L/R, (4.10 x .20 x .40 = 0.328)
CEMENT 0.326 X 12 = 3.936 (2) = 7.872 BAGS
SAND 0.328 X .50 = 0.164 (2) 0.328 CU M
GRAVEL 0.328 X 1 = 0328 (2) = 0.656 CU M

ROOF BEAM 1 (RB-1) 2pcs F/REAR, (3.60 x .20 x .40 = 0.288)


CEMENT 0.288 X 12 = 3.456 (2) = 6.912 BAGS
SAND 0.288 X .50 = 0.744 (2) = 1.488 CU M
GRAVEL 0.288 X 1 = 0.288 (2) = 0.576 CU M

INTERIOR
INTERIOR WALL (3.00 X .80 = 2.4 SQM)
4" CHB 2.4 X 12.5 = 30 pcs CHB
PLASTERING BOTH SIDES
CEMENT 2.4 X .450 = 1.08 (2) = 2.16 BAGS
SAND 2.4 X .025 =0.06 (2) = 0.12 CU M
MORTAR
CEMENT 2.4 X .792 = 1.9008 BAGS
SAND 2.4 X .4355 =1.044 CU M

INTERIOR WALL (2.50 X 3.00 = 7.5 SQM)


4" CHB 7.5 X 12.5 = 93.75 pcs
PLASTERING BOTH SIDES
CEMENT 7.5 X .450 = 3.375 (2) = 6.75 BAGS
SAND 7.5 X 0.25 = 0.187 (2) = 0.374 CU M
MORTAR
CEMENT 7.5 X .792 = 5.94 BAGS
SAND 7.5 X .0435 = .0326 CU M

INTERIOR DOOR (.10 X 3.00 = 0.3 SQM)


4" CHB 0.3 X 12.5 = 3.75 pcs
PLASTERING BOTH SIDES
CEMENT 0.3 X .450 = 0.135 (2) = 0.27 BAGS
SAND 0.3 X 0.25 = 0.0075 (2) = 0.015 CU M
MORTAR
CEMENT 0.3 X .792 = 0.2376 BAGS
SAND 0.3 X .835 = 0.013 CU M

MORTAR BELOW NGL


6" CHB EXT. L/R, [A=2.46 SQM]
CEMENT 2.46 X 1.526 = 3.75 BAGS
SAND 2.46 X .0844 = 0.207 CU M

6" CHB REAR ELEVATION, [A=2.16 SQM]


CEMENT 2.16 X 1.526 = 3.29 BAGS
SAND 2.16 X .0844 = 1.82 CU M

6" CHB FRONT ELEVATION, [A=1.56 SQM]


CEMENT 1.56 X 1.526 = 2.38 BAGS
SAND 1.56 X .0844 = 0.13 CU M

4" CHB INTERIOR, (.80 X .60) = [A=0.48]


CEMENT 0.48 X .792 = 0.03 BAGS
SAND 0.48 X .0435 = 0.002 CU M

4" CHB INTERIOR, (2.50 X .60) = [A=1.50]


CEMENT 1.50 X .792 = 1.188 BAGS
SAND 1.50 X .0435 = 0.652 CU M

4" CHB INTERIOR DOOR, (.10 X .60) = [A=0.06]


CEMENT 0.06 X .792 = 0.047 BAGS
SAND 0.06 X .0435 = 0.502 CU M

ELEVATION
FRONT ELEVATION (2.6 X 3.60 = 9.36 SQM)
DOOR 2.1 X = 2.1 SQM
WINDOW .70 X 1.20 = 6.42 SQM
6" CHB FRONT ELEVATION
6.42 X 12.5 = 80.25 pcs
PLASTERING
CEMENT 6.42 X 9.50 = 2.889 (2) = 5.778 BAGS
SAND 6.42 X 0.25= 0.16 (2) = 0.32 CU M
MORTAR
CEMENT 6.42 X 1526 = 9.79 BAGS
SAND 6.42 X 1.526 = 0.54 CU M

REAR ELEVATION (2.6 X 3.6 = 9.36 SQM)


.60 X .80 = .48 SQM
WINDOW
9.36 - 0.48 = 8.98 SQM
6" CHB REAR ELEVATION
8.98 X 12.5 = 112 pcs
PLASTERING
CEMENT 8.92 X .450 = 4.041 (2) = 8.082 BAGS
SAND 8.98 X .025 = 0.22 (2) = 0.44 CU M
MORTAR
CEMENT 8.98 X 1.526 = 13.70 BAGS
SAND 8.98 X .0844 = 0.75 CU M

LEFT ELEVATION (2.6 X 4.10 = 10.66 SQM)


6" CHB FRONT ELEVATION
10.66 X 12.5 = 133.25 pcs
PLASTERING
CEMENT 10.66 X .450 = 4.797 (2) = 9.594 BAGS
SAND 10.66 X .025 = 0.26 (2) 0.52 CU M
MORTAR
CEMENT 10.66 X 1.526 = 16.26 BAGS
SAND 10.66 X .0844 = 0.899 CU M

RIGHT ELEVATION (2.6 X 4.10 = 10.66 SQM)


1.20 X 1.20 = 1.44
WINDOW
10.66 - 2.88 = 7.78 SQM
6" CHB RIGHT ELEVATION
7.78 X 12. = 97.25 pcs
PLASTERING
CEMENT 7.78 X .450 = 3.501 (2) = 7.002 BAGS
SAND 7.78 X .025 = 0.1945 (2) = 0.389 CU M
MORTAR
CEMENT 7.78 X 1.526 = 11.87 BAGS
SAND 7.78 X .0844 =0.656 CU M
CEMENT (BAGS) SAND (CU M) GRAVEL (CU M) 4" CHB (pcs) 6" CHB (pcs)
20.736 0.864 1.728 6 61.5
32.256 1.344 2.688 18.75 27
12.96 0.615 1.23 0.75 19.5
6.48 0.27 0.54 30 80.25
4.68 0.195 0.39 93.75 112
7.872 0.328 0.656 3.75 133.25
6.912 1.488 0.576 97.25
2.16 0.12
1.9008 1.044
6.75 0.374
5.94 0.0326
0.27 0.015
0.2376 0.013
3.75 0.207
3.29 1.82
2.38 0.13
0.03 0.002
1.188 0.652
0.047 0.502
5.778 0.32
9.79 0.54
8.082 0.44
13.7 0.75
9.594 0.52
16.26 0.899
7.002 0.389
11.87 0.656
201.9154 14.5296 7.808 153 530.75
TOTAL: 202 BAGS 15 CU M 8 CU M 153 PCS 4" CHB 531 PCS 6" CHB