MS Equipment Carrying and Setting Works
MS Equipment Carrying and Setting Works
MS Equipment Carrying and Setting Works
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
NAME PROJECT
LOCATION
DATE SUBMITTED :
(Day) (Month) (Year)
DATE CHECKED :
(Day) (Month) (Year)
:
DATE APPROVED
(Day) (Month) (Year)
DATE REVISED :
(Day) (Month) (Year)
REMARKS FROM :
GENERAL CONTRACTOR : CLIENT/OWNER
CONTENT
1. General........................................................................................................4
2. Equipments..................................................................................................4
3. Materials......................................................................................................4
4. Unloading Equipment..................................................................................5
6. Lifting of AC Equipment.............................................................................7
9. Setting of Pumps.......................................................................................30
Page 1 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Page 2 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Project
Industrial Plant (Mining, Oil & Gas, etc) Building : (Low Rise/High Rise)
Project Category
Power Plant Other :
Location
Owner
Designer/Engineer
Contractor
Sub-Contractor
Number of Storey
Building Height
Page 3 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
1. General
1.1. This method is specially prepared for the State Name of Projectand Location.
1.2. Work coverage includes supply of equipment, material and resources by PT.
SARANA UTAMA ADIMANDIRI to the point of completion including acceptance
by the owner authorized representative.
2. Equipment
Item Description
1 Telescopic Crane
2 Forklift/Pallet Truck
3 Chain Block
4 Scissor Lifting Machine
5 Oxy-Acetylene/Cutting Outfit
6 Welding Machine
7 Electric Drill
8 Hammer Concrete Drill
3. Materials
Item Description
1 Steel Rope
2 Manila Rope
3 Steel Bars
4 Full Threaded Rod
5 Anchor Bolt/Expansion Shield
6 Scaffoldings
Page 4 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Hydrant Box
Fire Extinguisher
4. Unloading Equipment
Incinerator Location
Page 5 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Lifting works will be done by using appliance assist Mobile Crane cap. 25 ton, Job Site
planning and preparation prior to work shall be as follows:
Access road and area where crane and other equipment maneuvershall be checked
for its condition and shall be free from scattered materials and standing water.
The concerned materials, accessories, crane, tools and equipment shall be checked
for availabilityat site and ready to be used prior to starting of lift.
Crane on site shall be compromised to prevent the lifts in terms of weight and boom
extension.
Secure all material to prevent movement or possible dislodgement.
Make barrier and warning sign "Do not Enter - Lifting in Progress and Lifting
Zones"
A Pre-Lift Meeting shall be held before lifting any materials to ensure everybody at
site understands the lifting method.
Check the crane position with the outriggers, should be firm with suficient footing
for lifting.
Prior to lifting operation, the lifting supervisor shall conduct a tool box meeting to
all personnelinvolved including crane operator and signalmen.
The concerned material, tools and equipment shall be cheked for availability at site
and readyto be used prior to starting of lifting and installation of Equipment
A pre-work meeting shall be held before erection ofthe incinerator to ensure
everybody in the area understands the erection procedure.
Tools and Equipment which are expected to be utiliized but not limited to the list in the
table below:
Table-1: Erection Tools and Equipment
N Quantit
Description Specification Unit Remark
o y
A Erection
1 Mobile Cap. 25 Tons
Page 6 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Crane
2 Trolley Cap. 2 Tons Unit 2
3 Hand Pallet Cap. 750 Kg Unit 2
B Lifting Support
1 Manila Rope Cap. 350 Kg ( ø 3/4" ) Roll 2
2 Webbing Rope Cap. 6 Ton Nos 2
Wire
3 Cap. 6 Tons Nos 2
rope
6. Lifting of AC Equipment
AC Outdoor Sling/Webbing
Foundation
AC Outdoor
Foundation Spreader Bar
Fan Room
Pallet
ź FFL
4,175
8,675
ź FFL
8,675
ź GFL
4,500
ź GFL
Page 7 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Anchor Bolt
B C D B M12X50-6
Access door
150
E
Drain Connection A
G
D B
F
B C M
A
E
"A"
E F E Ancho
Steel Angle M12X
Page 8 of G49
65x65x6t
Foundation
150
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Coil section
Discharge
Filter section
Bolt
M12X50-6
Access door
150
"A"
Page 9 of 49
E F E Anchor Bolt
Steel Angle M12X50-6
G
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Discharge
Refrigerant
Pipe connection
"A"
E F E Anchor Bolt
Angle M12X50-6
65x65x6t G
Page 10 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
For the right hand and the rear side out, hold the bottom of piping and
then position it to the requiredposition, the condensation drain hose
can be taped to the pipe.
Hose drain
Page 11 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Hose drain
Outdoor Unit
Page 12 of 49
Liquid Pipe
Suction Pipe
Power/control cable
Sleeve w/Silicon seal
Thermal Insulator
Page 13 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
680
860-890
840
780
840
840
Page 14 of 49
298
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Max.750
840 840
298
298
200
840
298
Double nut
950 2
Ceiling board
8 4 1
5
Figure 20 A/C Ceiling Cassette Type Installation DiagramCeiling Cassette Corner Type
Page 15 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Indoor Unit
Indoor Unit
DETAIL-A
Suspension bolt should
extend outward 30 to 50 mm
extend outwar
1,350 7 1,350
1,440
215 Double nut
Hanging Rod 3/8" 5
148 Hanging Rod 3/8"
67 DETAIL-A
20 215
170
140
800
6
65 1,310 65 65 1,310
1,350
350 Page 16 Hangeing
of 49 Rod 3/8"
215
Hangeing Rod 3/8"
148 4 225
225 225 67
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
1,350
170
140
20
65 1,310 65
Ceiling Board 3
1,440
2
r Unit bottom View 1
FigureFigure
22 . A/C
22 A/CIndoor UnitSide
Indoor Unit Side View
View
350
Hangeing Rod1,350
3/8"
4 Hangeing Rod 3/8"
215
225 225
148 225
67
215
170
215
125
170
190
230
125
45
190
225
230
280
20
20
45 710 45
710
45
350
800
250
Ceiling Board
225
800 8
8
45
65 1,310 65
( Ceiling opening )
1310
1310
1,440
1,400 ( Ceiling
Page 17 of 49
1,400 ( Ceiling opening ) Figure 25.Ceilin
350
Hangeing Rod 3/8"
4
225 225
215
170
20
45 710 45
Ceiling Board
800
8
Figure 24 A/C Indoor Unit Side View
( Ceiling opening )
1310
( Ceiling opening )
1310
760
710
760
710
1,4001,400
( Ceiling opening )
( Ceiling opening )
Figure 25.Ceiling
Figure Opening
25.Ceiling Opening
Figure 25 Ceiling Opening
Page 18 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
1,160 1
680
300
275
105
8 170
6
2
1,160 5
3
Hanging Position 4
1,220
Page 19 of 49
0 210
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
1,160 5
3
Hanging Position 4
1,220
260 210
Hang
680
220
Ceiling
Figure 27 A/C Indoor Unit Top View
Hanging Position
1,220
Hanging rod Page 20 of 49
195
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Hanging Position
1,220
Hanging rod
10
195
30 1,160 30(Service space)
Hanging Rod
195 5
Ceiling
1,160
Wall
10
Page 21 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Page 22 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Control cover
Control cover
Conecting wire
Conecting wire
Connection pipe
Connection pipe
Drain pipe
Drain pipe
Page 23 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
R-48 NU 900 320 620 350 350 140 24 500 150 150
1 2 3
FL
Anchor Bolt Detail
FL
Anchor Bolt Detail
FL FL
Anchor Bolt Detail
Page 25 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
B C D B Stopper
Block out
100x100x200h-6
150
E
G
F
E
B C D B
Rubber s
FL
150
"B"
100
FL
150
Anchor Bolt
M14X160-6
B C D B
A DE
Page 26 of 49
Stopper
Rubber sheet
Dubble lock nut
Anchor Bolt M12X50
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
B C D B
Stopper
Rubber sheet
FL Dubble lock nut
150
Foundation
100 DETAIL " B "
Anchor Bolt
M14X160-6
UNP 75X75
Hole Ø 15-4 UNP 75X
167.5 365
700
UNP 75X75
UNP 75X75 UNP
UNP 75X75
UNP 75X
162.5
1,115
1,115
75 290 325
Page 27 of 49
50
UNP 75X75
700
75 1,250 75
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
1,400
UNP 75X75
75 75 1,100 75 75
700
UNP 75X75 UNP 75X75
UNP 75X75
UNP 75X75
UNP 75X75 UNP 7
162.5
1,115
1,115
1,115
75 290 325
50
UNP 75X75
700 700
75 1,250 75
150 1,100 150
700
365
Page 28 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
UNP 75X75
1,115
1,400
1,400 75 175 900 175 75
900 175 75
700
365
700
Note : Fan unit is weight more than 100 Kg hunging support by steel construction
Page 29 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Finished wall
Wire guard Fan Frame
Sealicon seal Wir
Shutter
Fan motor
Rain hood
Sealicon seal
Steel frame
Finished wall
7 5
Fan Frame Wire Guard Hole S
2 4
Wire Guard
Hole
Rain hood
6
3
Bolt Bolt
1 Fan
1 motor
Elect. wire
1
2 Figure 44 Wall Fan - Industrial Type
3
4
5
6
7
Page 30 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Finished wall
7 5 Shutter fr
Hole
2 4
Wire Guard
Rain hood
6
3
Bolt Bolt
1 1
Page 31 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
8.
9. Setting of Pumps
Spring Water
M-1
Pump
A leveling pad where its top is leveled as desired of base plate of pump. The
leveling pad will be made and cure atleast 3 daysprior to start of pump
installation.
Surface of pump foundation shall be chipped and roughened. (see figure 53)
Similar treatment shall be applied to surface of foundation bolt holes.
Roughen and clean the foundation. Surface of grouting hole must have rough
surface and must be free fromthe pollution. Remove any loose particle, dirt or
oil-soaked concrete.All base plate surface which will be in contact with grout
must be clean.
Page 32 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
WP-1 Water Lift Pump 225 550 1000 170 360 700 290 205
FP-1 Fire Pump 320 660 1300 180 440 800 180 440
Leveling pad/Shims
Block out
G
F
H
E
G
D
A B A
Leveling pad/Shims
AG AF
AH
AB AC AD AC AB
AE
Page 33 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Leveling pad/Shims
AG AF
AH
AB AC AD AC AB
AE
Use shims under base for support at anchor bolt to position base
approximately.
By adding or removing shims under the base, level and plumb the pump shaft
and flanges. The base plate does not have to be leveled.
Approximately 15-20mm of the top of concrete foundation shall be
roughened/chipped to remove the weakupper layer of concrete, damage
concrete and any oil-soaked area.
Draw anchor nuts tight against base, and observe pump and motor shaft or
coupling hubs for alignment.
If alignment need improvement, add shims or wedges at appropriate position
under base,so that retightening of anchor nuts will shift shafts into closer
alignment. Repeat procedures until a reasonable alignment is reached.
Shims
Page 34 of 49
Anchor Bolt M12X160-4
Leveling pad
Pump base pate
Manju
Concrete foundation
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Shims
Anchor Bolt M12X160-4
Leveling pad
Pump base pate
Manju
Concrete foundation
Floor finished
Steel bar
Proper rough alignment must be made during unit setting and grouting.Every
alignment check must be preceded by a run-out measurement at the coupling
flanges. Always log the results. All reading for radial and axial misalignment are
determined in the gauge positions: top, bottom, right and left, every 90º while both
shafts are simultaneously turned.Alignment shall be carried out with clock gauge in
radial and axial direction. The maximum admissible axial misalignment is 0.05mm
on diameter, although ≤ 0.03mm is preferable.The maximum admissible radial
misalignment is 0.01mm on diameter, although ≤ 0.05mm is preferable.
Page 35 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
The dial readings will indicate whether the driver has to be raised,
lowered or moved to either sideAccurate alignment of shaft centers can
be obtained whith this method even where faces or outsidediameters of
the coupling are not square or cocentric with the bores
Grout compensates for uneven foundation, distributes weight of unit and prevents
shiftings. Use an approved, non-shrinking grout, after setting and leveling unit.
Page 36 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
After the grout has thoroughly hardened, check the foundation bolts and
tighten if necessary.
Check the alignment after the foundation bolts are tightened.
Approximately 14 days after the grout has been poured or when the grout has
thoroughly dried, apply an oil-based paint to the exposed edges of the grout to
prevent air and moisture from coming in contact with the grout.
Table11Pump List
Anchor bolt size
Item No Description Q'ty/Unit Remark
(mm)
See Detail-A
Shims
Anchor Bolt
Leveling pad Pump base pate
Manju
Grouting
Concrete foundation
10
1,100
200
Page 38 of 49
Page 39 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
200
Figure 58 Pressure Tank Elevation View
1,100
Anchor Bolt M16X160-4
Foot
1,100
10
11
Page 40 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
1,400 1,400
2,800
2,800
2,800
2,800
20,000
Manila Rope
2,800
Cap.25 Ton
3,200
Page 41 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
1,400 1,400
Ladder Pipe
WS/Drain
2,800
2,800
2,800
2,800
20,000
2,800
Ladder
2,800
3,200
Page 42 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Table12Nozzle List
Page 43 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
1,100
40
1,000 200
500
1.500
1,400
1.500
1,000
150
1,100 200
Base Frame Tank
150 & Steel Plate65 Elevated Water Tank Elevation View
Figure
( Hotdip Galv. )
Page 44 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
11
12
1,030
Break Wall
1,210
( Wall opening )
140270 140
Wall finished
1,210
140270 140
Wall finished
1,210
Concrete upstand
GFL
Page 46 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Reducer
Hydrant pipe
1,201
1,055
Valve
Concrete upstand
225
OHB
Valve 65A
Foundation 140 720 140
1,000
Indicator Lamp
720
20 680 20
184 240
Alarm Bell 104 80
2 0 1 8 02 0
1 ,1 4 0
Valve
880
816
L 50X50X5t
20
1 0105 0 2 4 0
Support
GL
14. Setting of Fire Extinguisher [Fire Extinguisher Model : AP-35P (ABC Type)]
Page 48 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
1 Lifting, transporta- Defective lifting gear Injury to personnel due to Equipment selection & Inspect-
tion and handling and crane, poor drop loads, hit by falling cion criteria, preventive
during all phases rigging and lifting object, struck by/against maintenance, safe lifting
of erection practices for loading/ equipment, pinned by procedure.
unloading. material, Proper manual handling and
Late start/Lost production stacking.
2 Marking, cutting High noise during Potensial damage to Toolbox meeting, full time
and welding cutting and grinding, risk or eyesight, potential fire supervision, Ensure the use of
of steel materials associated with gas or hearing explosion, risk appropriate equipment and
cylinders, defective hoses of electrocusion grounding
defective electrical and Los production. Correct use of Personal Protective
welding cables and Equipment
inadequate electrical
grounding
3 Scaffolding and Defective scaffold Several injuries can result Tool box meeting, full time supervision
Working at material, poor scaffold from hit by falling objects Ensure that tools and equipment
height erection practices, Falling from height. are properly scured on platforms.
unscured objects at height Correct use of Personal Protective
wrong use of scaffold Equipment, especially safety harnes.
for unintended purpose Scaffold inspection program.
such as lifting can cause
collapse.
Page 49 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Page 50 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Date Area/Block
Checked By
Project Name
System Location
Equipment Installation Condition
NO Equipment
Visual Location
. Type/Model Supporting Connection Elevation Finishing Remark
Condition
□OK □OK □OK □OK □OK □OK □OK
□NG □NG □NG □NG □NG □NG □NG
□OK □OK □OK □OK □OK □OK □OK
□NG □NG □NG □NG □NG □NG □NG
□OK □OK □OK □OK □OK □OK □OK
□NG □NG □NG □NG □NG □NG □NG
□OK □OK □OK □OK □OK □OK □OK
□NG □NG □NG □NG □NG □NG □NG
□OK □OK □OK □OK □OK □OK □OK
□NG □NG □NG □NG □NG □NG □NG
□OK □OK □OK □OK □OK □OK □OK
□NG □NG □NG □NG □NG □NG □NG
□OK □OK □OK □OK □OK □OK □OK
□NG □NG □NG □NG □NG □NG □NG
□OK □OK □OK □OK □OK □OK □OK
□NG □NG □NG □NG □NG □NG □NG
□OK □OK □OK □OK □OK □OK □OK
□NG □NG □NG □NG □NG □NG □NG
Page 51 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Page 52 of 49
METHOD STATEMENT MS-009
FOR
Rev.
EQUIPMENT CARRYING &
SETTING WORKS Date
Page 53 of 49