TENDER DOCUMENT
FOR
PACKAGE-4
PACKAGE-4
LUPECH POWER DISTRIBUTION FACILITY FOR PETROCHEMICAL
AND LUBE INTEGRATION PROJECT “LUPECH” (J-18) PROJECT AT
IOCL GUJARAT REFINERY, INDIA
(BIDDING DOCUMENT NO.: 077154C/T/LuPech(J-18)/PACKAGE-4)
CONTENTS OF TENDER
1. PART- I TECHNO COMMERCIAL (UNPRICED)
(REFINERIES DIVISION)
PACKAGE-4
PART- I: TECHNO-COMMERCIAL
TECHNIP CENTRE,
MASTER INDEX
PART I & II
Bidding Document No : 077154C/T/Lupech(J18)/PACKAGE-4 P a g e 1 of 5
PART I: TECHNO COMMERCIAL
NO. OF
SL.NO DESCRIPTION
PAGES
1. COVER PAGE 1
2. MASTER INDEX 5
5. ATTACHMENTS TO ITB
MASTER INDEX
PART I & II
Bidding Document No : 077154C/T/Lupech(J18)/PACKAGE-4 P a g e 2 of 5
NO. OF
SL.NO DESCRIPTION
PAGES
MASTER INDEX
PART I & II
Bidding Document No : 077154C/T/Lupech(J18)/PACKAGE-4 P a g e 3 of 5
NO. OF
SL.NO DESCRIPTION
PAGES
7.20 1
S - FORMAT FOR INDEPENDENT ESI
9.2 SCC-PART B 29
MASTER INDEX
PART I & II
Bidding Document No : 077154C/T/Lupech(J18)/PACKAGE-4 P a g e 4 of 5
NO. OF
SL.NO DESCRIPTION
PAGES
MASTER INDEX
PART I & II
Bidding Document No : 077154C/T/Lupech(J18)/PACKAGE-4 P a g e 5 of 5
PART II: PRICED PART
No of
SL. NO DESCRIPTION
Pages
1 COVER PAGE 1
TABLE OF CONTENTS
A. INTRODUCTION............................................................................................................................ 2
B. BRIEF SCOPE OF WORK ............................................................................................................ 2
C. SALIENT FEATURES OF NOTICE INVITING TENDER (NIT) ..................................................... 3
D. EARNEST MONEY DEPOSIT (EMD) .......................................................................................... 13
E. GENERAL.................................................................................................................................... 13
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
A. INTRODUCTION
M/s. TECHNIP INDIA LIMITED (TPIL) as CONSULTANT on behalf of OWNER M/s. INDIAN OIL
CORPORATION LIMITED (IOCL) invite e-Bids for execution of Package-4 comprising of POWER
DISTRIBUTION FACILITY FOR PETROCHEMICAL AND LUBE INTEGRATION PROJECT “LUPECH” (J-
18) PROJECT AT IOCL GUJARAT REFINERY, INDIA on Domestic Competitive Bidding under Single
Stage Two-Bid system (Part-1: Techno-Commercial Part and Part -2: Price Part) from competent Bidders
with sound Technical and Financial capabilities fulfilling the Qualification Criteria as stated elsewhere in this
document.
Bidder shall execute the work on Lump Sum Turn Key Basis (LSTK) with single point responsibility and the
scope includes Project Management, Consistency Checks, Power System Studies as mentioned in Bidding
Documents, Site development and enabling jobs, Topography Survey, Soil Investigation and underground
scanning mentioned in the bid and co-ordination for the same with Owner/PMC, Total Procurement (including
first fill of consumables, special tools and tackles, Pre-Commissioning Spares, Commissioning Spares, Start-
up spares & Mandatory spares), Fabrication, Manufacturing, Quality Assurance, Inspection & Expediting,
Third Party Inspection, Supplies, Transportation, Insurance, Handling & Storage of all Equipment, Materials,
items and other Construction Materials at yard/site, Fabrication, Assembly, Construction, Erection, Installation
of all equipment pertaining to LuPech Power Distribution facility including civil, Structural, HVAC, Piping,
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Electrical and Instrumentation including tie-ins, Testing, Insulation and Painting, Obtaining all Statutory
Approvals Pre-commissioning & Mechanical Completion, Preparation of operating manuals, Training of
Owner’s O&M personnel, consumables for 6 (six) months operation, Contract closure activities ,Final
invoice/billing and handing over of the facilities with Final and “As Built” drawing/documentation, supply of
spares with necessary support and services during defect liability period.
For detailed scope, refer the relevant sections of the Bidding Document.
Virtual Site Visit & Pre-Bid Meeting at 10:30 Hrs on 14-Jul-2021. via
Site Visit and Pre-Bid Video Conferencing (Preferably Microsoft Teams) or in the following
7. Meeting address:
IOCL, Project Department, Scope Complex, Core-2, 7, Institutional
Area, Lodhi Road, New Delhi-110003
12.1 Intending Bidders shall meet the minimum qualification criteria detailed below to qualify.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
The Bidders shall have to furnish proof of their qualification credentials and other relevant
documents mentioned in the Bidding Document along with the Part-I (Techno-commercial bid).
A Bidder who meets the BQC Criteria as set out below (Refer Sl. Nos. 12.3, 12.4 & 12.5) can directly
12.2
quote for the job.
a) The Bidder should have successfully executed and completed One contract with single point
responsibility involving “Supply, Installation, Testing and Commissioning of minimum 33
kV voltage grade switchgear facility”. References of Revamp / Retrofit projects shall not be
considered for qualification.
b) The Bidder should have also successfully executed and completed atleast one contract with
single point responsibility involving “Installation, Testing and Commissioning of Extra High
Voltage (66kV & above) Class Power Transformers”.
12.3.1
c) In addition to the above, Bidder should have successfully executed and completed atleast one
contract with single point responsibility involving “Civil works of Substation building/Motor
Control Center Room/Control room building for Electrical Installation”.
d) Bidder should have the experience of “Design / Engineering for facility specified under criteria
a) & c) above”.
e) Bidder shall meet the criteria a), b), c) & d) above either in single contract (or) in multiple
contracts.
In case the Bidder meets the criteria 12.3.1.a), b) & c) above on its own, but do not have the
Design/Engineering experience mentioned in criteria 12.3.1.d), the bidder can be considered
acceptable, provided Bidder engages an Engineering Sub-Contractor who has carried out
Design/Engineering of the Work referred in criteria 12.3.1.d) above.
12.3.2
Bidder to furnish with his bid, the Memorandum of Understanding (MOU) with the proposed
'Engineering Subcontractor' for executing the Design / Engineering for this subject Tender. In case
of Bidder being successful, the MOU with Engineering Sub-Contractor (submitted during Pre-
Qualification), shall be binding on the Bidder till the pendency of the contract. Changes of
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Engineering Sub-contractor during execution of job shall be subject to approval of IOCL / PMC
without any cost and time implication.
i) The electrical equipment and facility referred in 12.3.1 a), b) and d) above must have been
commissioned within the last 10 years ending on last day of the month immediately previous to the
month in which last date of bid submission falls (in case of extended bid submission date, original
bid submission date shall be considered).
The electrical equipment and facility referred in 12.3.1 a), b) & d) should also have been in operation
for at least 1 (one) year after commissioning.
ii) Proof of commissioning from Owner/End User shall be submitted by the Intending Bidder along
with the Technical Bid.
12.3.3 However, for operation for at least 1 (one) year after commissioning, any one of the following
document is required to be submitted by the bidder along with the Bid.
• Certificate for Operation for 1 year from client OR
• Certificate of Release of full Security Deposit (Bank Guarantee) by Client against the
defect liability period OR
• Certification by CEO/CFO with due notarization that Defect Liability Period is completed
and there is no claim by client on account of performance of the Plant/Equipment OR
• For reference job of IOCL in support of successful operation of one year, bidder need
not submit any additional certificate. However, the qualification of the reference job
order submitted by the bidder for the tender will be checked internally by IOCL based
on the information submitted with the bid.
Bidder should submit valid electrical Contractor license and electrical supervisor license suitable to
work on maximum system voltage level (mentioned in the subject tender) issued by respective Govt
authority for Gujarat State along with the bid, else to perform installation of all electrical items through
12.3.4 a Sub Contractor having valid electrical Contractor License and Electrical Supervisor License issued
by respective Govt Authority. A self-affidavit in this regard shall be signed and submitted by
CEO/CFO of the bidding entity along with bid.
To establish the Positive Net Worth, Bidder shall furnish the latest Audited Financial Statement
including Auditors reports, Audited Balance Sheet, Profit & Loss Account, Notes, Annexure (if any)
etc.
In case Net worth is negative in the immediate preceding financial year, the bid shall be
rejected.
The net worth means paid up share capital, share application money pending allotment* and reserve
# less accumulate losses and deferred expenditure to the extent not written off.
# Reserves to be considered for net-worth shall be all reserves created out of the profits and
securities premium account but shall not include reserves created out of revaluation of assets write
back of depreciation and amalgamation.
*Share application money pending allotment will be considered only in respect of share to be
allotted.
Less: Deferred revenue expenditure to the extend not written off XXX
Net-worth XXX
Bidder shall not have consecutive negative PAT for the last three Financial Years
The failure to meet criteria (a) & (b) above will render the bid submitted to be summarily
rejected.
For 12.4.1 and 12.4.2 above, in case the Financial Year closing date is within 9 months of bid
due date and Audited Annual Report of immediate preceding financial year is not available, bidder
has the option to submit the financial details of the previous year immediately prior to the last
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
financial year. Otherwise, it is compulsory to submit the financial details of the immediate preceding
financial years.
Example, in case, Audited Annual Report of immediate preceding Financial Year (year ending 31st
March) is not available and where bid closing date is up to 31st December, the financial details of
the previous year immediately prior to the last financial year may be submitted However, in case the
bid closing date is after 31st December, it is compulsory to submit the financial details of the
immediate preceding financial year only.
Any of the following documents furbished by the bidder in support of above clause shall be
acceptable:
A) Audited published Annual Report OR
B) Audited Balance Sheet and Profit & Loss statement OR
C) Financial statements duly certified by a practicing Chartered Accountant (not being an
employee or a Director and not having any interest in the bidder’s company) where audited
accounts are not mandatory as per law.
➢ One “similar” successfully completed contract valuing not less than the amount equal to
INR. 35,30,63,000.
OR
12.5.1 ➢ Two “similar” successfully completed contracts each valuing not less than the amount equal
to INR. 28,24,50,000.
OR
➢ Three “similar” successfully completed contracts each valuing not less than the amount
equal to INR. 21,18,38,000.
Date of Mechanical Completion will be considered as completion date and that should fall within
the qualifying period.
The above values of completed contract(s) shall be exclusive of GST /Service Tax.
“Similar” nature of job is as defined at Sr. no. 12.5.2
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
12.6 DOCUMENTATION
The bidder shall, in his own interest, furnish complete documentary evidence, as under, to justify
that the bidder meets the Qualification Criteria as given above.
Notwithstanding any other condition/ provision in the tender documents, bidders are required to
submit complete documents pertaining to BQC along with their offer. Failure to meet the BQC will
render the bid to be summarily rejected. IOCL reserves the right to complete the evaluation based
on the details furnished by the bidder, with or without seeking any additional supporting documents
/clarifications.
For Technical and Commercial experience criteria:
a) The Bidder shall furnish documentary proof in form of the copy of work order(s)/ contract
agreement(s)/ relevant supporting documents like data sheet, drawings, SOR etc complying
the technical criteria mentioned above / relevant pages of contract document(s) mentioning
the value and the scope of work, completion certificate(s) by owner/ Consultant indicating
executed value and certificate(s) of commissioning of previous plants from owner/ Consultant,
fulfilling the qualification criteria for themselves as well as their proposed Engineering Sub-
Contractor, as applicable.
b) In case, the executed value of job is more than work order value and bidder claims that they
12.6.1 are meeting the BQC requirement on the basis of executed value, then it is the responsibility
of the bidder to submit the documentary evidence of final executed value (such as copy of
Final Bill, executed value mentioned in Completion Certificate etc.) along with his bid.
c) In case Executed Value is not mentioned in the Completion Certificate, Work Order value with
amendments, if any, shall be considered towards BQC requirements. Where the executed
value is not mentioned in the Completion Certificate, the copy of certified Bill shall also be
acceptable for determining the Executed Value if submitted along with Completion Certificate.
Executed Value or Work Order Value, whichever is higher, shall be considered towards BQC
requirements as above and Offer shall be evaluated accordingly.
d) Executed value mentioned in the completion certificate should be exclusive of Service Tax/
GST. In case the value of job submitted by the bidder does not have clarity with regard to
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
inclusion/ exclusion of Service Tax/GST, the amount appearing in the certificate shall be
considered exclusive of Service Tax/GST and shall be evaluated accordingly.
ii. Bidder has to submit a Certificate from the End User/ Owner/Consultant of the Owner
stating that the Main Contractor has intimated them about the engagement of Bidder
as a Sub-Contractor OR the Bidder had been allowed/permitted as a Sub-Contractor
in the concerned job(s).
iii. Copies of Completion/Commissioning Certificates (as the case may be) issued by the
Owner/ Owner’s Consultant/Main Contractor. The said Certificates shall have details
like work order no./date, brief scope of work, ordered & executed value of the job,
completion date etc. In case bidder is not able to furnish the completion certificates
from the Owner/Owner’s Consultant in his name then the Certificate issued in the
name of Main Contractor shall also be considered as proof of completion of the
relevant job.
iv. If the bidder cites any reference of a job executed for IOCL or executed for some client
through PMC and the bidder is not able to furnish documentary evidence, the internal
records of IOCL or PMC (as the case may be) shall be considered.
f) A job executed by a bidder for its own plant/ projects can’t be considered as experience for
the purpose of meeting requirement of BQC of the Bidding Document. However, jobs
executed for Subsidiary/ Fellow subsidiary / Holding company will be considered as
experience for the purpose of meeting BQC subject to submission of tax paid invoice(s) duly
certified by Statutory Auditor of the bidder towards payments of statutory tax in support of the
job executed. Such bidders shall submit these documents over and above the other required
documents under the various Clauses of BQC.
g) For Indian Bidders, Order value(s) in multiple currencies shall be converted to equivalent INR
at the exchange rate of SBI bill selling rate as on the date of award of such proposed qualifying
work(s).
h) In case where the Bidder cites the reasons of Non-Disclosure Agreement for its inability to
submit necessary documents in support of meeting the Experience Criteria, a Certificate in
original, certifying all the required information, issued by CEO/ CFO of the company along
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
with a declaration that the bidding company is not in a position to submit the required
documents owing to NDA with an endorsement by Chartered Accountant / Statutory Auditor
/ Certified Public Accountant (not being an employee or a Director or not having any interest
in the bidder(s) company / firm) shall be accepted.
Wherever Chartered Accountant / Statutory Auditor / Certified Public Accountant (not being
an employee or a Director or not having any interest in the bidder(s) company / firm) is not in
a position to endorse such CEO / CFO's certificate due to local regulations, CEO / CFO's
certificate without endorsement may be accepted provided a reference of the local regulation
restricting this endorsement is given in the CEO / CFO certificate.
a) For fulfilling the Financial Criteria, annual audited financial statements (Balance Sheet, Profit
and Loss Account, Auditor Report and all other Schedules / notes to Balance sheet and Profit &
12.6.2 Loss Account) of the bidder shall be considered as acceptable proof.
b) Not used.
c) In connection with the submission of various documents against Financial Criteria, the Bidder
shall specifically refer to the Sl.No. 12.4 of BQC also.
Submission of authentic documents is the prime responsibility of the bidder. Wherever IOCL has
concern or apprehension regarding the authenticity/ correctness of any document, IOCL reserves
the right to get the documents verified from issuing authority/any relevant source. If documents (part
or full) are found forged, such offers will be summarily rejected, EMD will be forfeited, orders if any
13
placed against subject tender will be terminated and may be debarred from future tenders. For the
purpose of verification bidders shall submit complete client details with names, address, phone
number, e-mail ID etc.
Offer must be uploaded on e-tender website www.iocletenders.nic.in
14 Mode of Submission. before the last date & time of submission of tender.
Offer submitted using any other mode will not be accepted.
15 OTHER REQUIREMENTS
15.1 Independent ESI (Employees State Insurance) Code or undertaking for Independent ESI code in
the Format given in Bidding Forms (Form-S).
NOTES:
a) Bidders who would like to quote directly shall have ESI Registration in their own name and submit
Copy of the same Registration Certificate along with the Bid.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
If ESI Registration is not available during Bidding as mentioned above, necessary Undertaking shall
b) be given by the Bidder as per the Tender provisions that once the Job is awarded, the successful
Bidder shall arrange for the ESI Registration as per the Statutory requirements.
All bidders shall be required to submit the Power of Attorney in the name of authorized
signatory who is submitting the bid with his Digital Signature Certificate & Signature. Also,
15.2
Power of Attorney of the Person who has signed the bid (if a different person) shall be
submitted.
Bidders who would like to quote directly shall have PF Registration in their own name and shall
15.5 submit Copy of the PF Registration Certificate along with the Bid.
Bids of such Bidders, who shall not submit the copy of valid PF Registration Certificate as
per above requirement, will be rejected.
Integrity Pact
17 Applicable
Agreement
20 Language English
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
The offer of the Bidder shall remain valid for 06 (Six) months from
the last date of submission of Tender / Revised offer (if applicable
as permitted by the Owner). On account of exigencies if bidders are
21 Validity of Bids asked to extend their validity the same should be without any deviation
including change in the prices. However, the bidders would be allowed to
withdraw the tender. If a bidder still deviates or changes price, its offer
would likely to be rejected.
EMD is currently not applicable for this tender. Bidder shall sign and submit the format of bid security
declaration in lieu of EMD attached as per Annexure-II of NIT.
E. GENERAL
Bidder to note the following before bidding:
1. Offers from following types of bidders will not be accepted
a) Who are in the Holiday/ Suspension /Banning List / Negative list of Licensor or IOCL or its
Administrative Ministry, MoP&NG on due date of submission of bid / during the process of
evaluation of the bids.
b) Bidders who are under liquidation, court receivership or similar proceedings. In this connection,
Bidder shall submit an Affidavit stating that they are not under liquidation, court receivership or
similar proceedings.
c) Consultant or their subsidiary Company or companies under the management of Consultant
for execution of the same project for which they are working as Consultant, with the exception
of participation as TPIA for the same job.
d) Not Used
e) Bidder(s) who are undergoing insolvency resolution process or liquidation or bankruptcy
proceeding under Insolvency and Bankruptcy Code, 2016 (Code).
f) Bidder(s) whose insolvency resolution process or liquidation or bankruptcy proceeding is
initiated under the above Code at any stage of evaluation of the bid.
2. The subject tender is an e-tender & can be downloaded from IOCL website,
https://iocletenders.nic.in The tender document will not be issued in person or sent by post. Mere
obtaining tender document through IOCL website shall, however, not be construed that the
bidder/agency is considered qualified.
4. Bidders are advised to read the instructions for participating in the e-tendering from the website
https://iocletenders.nic.in The Help Documentation placed at Home Page provides necessary
guidance to bidders for using the e-Tendering site. A user ID will be issued to each prospective
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
5. Bidder shall download the Bidding Document in his own name and submit the bid directly. The
Bidding Document is non-transferable. Bids submitted by Bidder/s who have not downloaded the
bidding document either directly or through their authorized person will be rejected. Please note that
the person having Power of Attorney to do bidding process on behalf of the bidder shall only
submit/upload the bid document using their own DSC.
6. As far as possible Bidders are requested to clarify all the queries related to tender before the bid
opening and ensure compliance of all provisions of the bidding document.
7. The bidder is expected prior to the submission of its/his/their bid, as a prudent and experienced
Contractor to make its/his/their own assessment of all the requirements of the work and of the
accuracy, correctness and completeness of any estimate, data, or information furnished by the
OWNER in the Tender Documents and of the availability, suitability, propriety, adequacy and/or
soundness of any suggestion made by the OWNER in the Tender Documents as hereinabove
referred to.
8. All documents furnished by the bidder in support of meeting the Bidder’s Qualification Criteria (BQC)
shall be self-certified.
All documents submitted by the bidder towards meeting BQC shall be furnished in a separate
booklet titled as "Documentation against Bidder Qualification Criteria" with proper indexing.
9. Submission of authentic documents is the prime responsibility of the bidder. Wherever IOCL has
concern or apprehension regarding the authenticity/ correctness of any document, IOCL reserves
the right to get the documents verified from issuing authority/any relevant source. If documents (part
or full) are found forged, such offers will be summarily rejected, EMD will be forfeited, orders if any
placed against subject tender will be terminated and may be debarred from future tenders. For the
purpose of verification of documents, bidders shall submit complete client details with names,
address, phone number, e-mail ID etc.
10. IOCL/PMC reserves the right to carry out capacity & capability assessment of the bidder using in-
house information and past performance.
11. Relevant supporting documents towards other requirements specified are also to be uploaded along
with bid failing which bid is liable for rejection.
12. IOCL reserves the right to reject any or all of the tenders or any parts of the tender so received and
may cancel the tender in part or full, extend the due date of Tender submission etc. without assigning
any reason.
13. In case any Bidder is found to be involved in cartel formation, his Bid will not be considered for
evaluation / placement of order. Such Bidder will also be debarred from bidding in future.
14. Canvassing in any form by the Bidder or by any other agency on their behalf may lead to
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
15. Legal dispute, if any, shall only be within the jurisdiction of Local Court unless mentioned otherwise.
16. All communication will be made through e-Tendering web site (www.iocletenders.nic.in). However,
IOCL reserve the right to take cognizance of the communication made outside e-Tendering Portal
under exceptional circumstances.
17. Bidder cannot make any claim against IOCL towards its expense incurred in connection with the
preparation and delivery of their bids, participating in the discussion and other expenses incurred
during bidding process.
18. Offers not meeting statutory requirement are liable for rejection.
19. Bidders are advised to visit Announcement section/ Information for DSC/ Bidders Manual Kit/ FAQ
of e-Tender Portal before bidding.
20. Any Addendum/Corrigendum/Sale date extension in respect of above Tender shall be issued on our
website: https://iocletenders.nic.in only and no separate notification shall be issued in the press.
Bidders are therefore requested to regularly visit our website to keep themselves updated. Failure
of Bidder to submit tender without taking cognizance of Corrigendum / Amendment (if any) issued
by IOCL shall make bid liable for rejection.
21. IOCL does not take any responsibility for the correctness of tender documents obtained from any
other source. Bidders are advised to visit above mentioned website before submitting their offer for
official version of the tender document including any corrigendum / amendment if any, which shall
be binding to the bidder.
22. Owner reserves its right to allow Public Sector Enterprises (Central/State), purchase preference
as admissible/applicable from time to time under the existing Govt. Policy.
23. Owner shall also follow the Public Procurement Policy on Procurement of Goods and services from
Micro and Small Enterprises (MSEs) Order 2012.
24. In case of a MSE bidder, documentary evidence as per the prevailing Government policy shall be
acceptable. In addition duly authenticated document in this regard shall be submitted. However, in
case authenticated document is not submitted in original, the same can be accepted provided a
valid MSE certification is available on Government portal (www.nsicspronline.com) or Government
Udyog Aadhar portal.
25. For detailed specifications, terms and conditions and other details, refer complete Bidding
Document.
26. A Memorandum of understanding has been signed by IOCL with Transparency International on
18.01.2008 for adoption of Integrity Pact in major Tenders. Bidder shall submit the Integrity
Agreement & the covering letter in the prescribed Formats (enclosed in the Bid Document)
duly signed along with the Bid.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
28. The terms “Pre-qualification Criteria (PQC)” and “Bidder Qualification Criteria (BQC)” shall
have the same meaning in the Bidding Document.
29. The terms ‘Sl.No.’, ‘Sr.No.’, ‘Cl.No.’ and ‘Clause No.’ used in this NIT document shall have the
same meaning.
33. Bidders shall submit the following documents in Original to PMC / IOCL within Seven (07) days from
the date of Un-priced Bid opening:
34. The bidder is also expected prior to finalization of its/his/their bid to visit and examine the job site
and its surroundings and to familiarize itself/himself/themselves of the ground realities, the
availability, existence and suitability of facilities and sources of supply required for the work(s) and
the environmental conditions which can be encountered, and collect all data and other information
which the bidder may require for preparation and formulation of its/his/their bid. The CONTRACTOR
will not to be entitled to make any claim against the OWNER or to raise any objection or defense to
any claim based on the ignorance of existing or expected conditions, or on the lack of adequate
information, or of any plan, estimate or expectation based on a different perception or expectation
or information.
35. The tenderer shall be deemed before tendering to have undertaken a thorough study of the
proposed work, the job site(s) involved, the site conditions, soil conditions, the terrain, the climatic
conditions, the labour, power, material, and equipment availability, transport and communications
facilities, the availability and suitability of borrow areas, the availability of land for right of way and
temporary office and accommodations, quarters, and all other facts and facilities necessary or
relevant for the formulation of the bid, supply of materials and the performance of work
36. Unsolicited clarifications to the offer and / or change in the prices during the validity period would
render the bid liable for rejection.
37. Techno-commercial part of the Bids shall be opened 14:30 Hrs. (IST) on the due date. Time and
date of opening of Price Bids shall be notified through e portal to the qualified and acceptable bidders
at a later date. Bidders may view the Bid opening through IOCL e- Tendering portal:
https://iocletenders.nic.in
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
38. Bidders shall quote their most competitive rates. Negotiations will not be conducted with the bidders
as a matter of routine. However, Owner reserves the right to conduct negotiations.
39. Bidder should make sure that their Price- Bid (Part-II/BOQ) contains only prices. Rates mentioned
elsewhere shall not be taken into cognizance. Offer shall be liable for rejection if any condition
directly or implied, recorded in Priced Bid (Part-II/BOQ).
40. After opening of the technical bids but before the opening of the price bids, the bids may be rejected
for unsatisfactory performance or adverse comments which have come to the notice of
Owner/Consultant after the issue of the tender enquiry
41. Refer ITB of the tender document /Special Instruction to Bidder (SITB) of e-tender web site for more
details.
42. The offer of the Bidder shall remain valid for 06 (Six) months from the last date of submission
of Tender / Revised offer (if applicable as permitted by the Owner). On account of exigencies if
bidders are asked to extend their validity the same should be without any deviation including change
in the prices. However, the bidders would be allowed to withdraw the tender. If a bidder still deviates
or changes price, its offer would likely to be rejected.
43. Bidders may raise disputes/ complaints, if any, with the nominated Independent External Monitor
(IEM). The IEM for this tender are
i. Shri Basant Seth, Former CMD, Syndicate Bank and Information Commissioner, CIC
ii. Shri Madhusudan Prasad, IAS (Retd.)
All complaints / communication to IEMs with regard to this tender may be sent on email id: iem-
iocl@indianoil.in
Hard copy of the same can also be sent by post at the following address which will be suitably
communicated / forwarded to the IEM’s.
IP Secretariat
Indian Oil Corporation Limited, Room No.542, 5th floor, Core 6,
Scope Complex, Lodhi Road, New Delhi – 110 003
iem- iocl@indianoil.in
44. Bidders from a country which shares a land border with India will be eligible to bid in this tender only
if the bidder is registered with the Competent Authority in line with requirements specified by
Government of India. Broad Guidelines in this regard is specified in Annexure- I. The bidder shall
complete the registration process before last date of bid submission and submit documentary
evidence in this regard, failing which their bids will be rejected.
45. Notwithstanding any other condition/ provision in the tender documents, bidders are required to
submit complete documents pertaining to PQC along with their offer. Failure to meet the PQC will
render the bid to be summarily rejected. IOC reserves the right to complete the evaluation based on
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
the details furnished by the bidder, with or without seeking any additional supporting documents
/clarifications
46. Fax of Acceptance (FOA)/LOA (Letter of Acceptance) will be issued by the OWNER to the
successful BIDDER.
(i) that I/ we have availed the benefit the waiver of EMD while submitting our offer against
the subject tender and No EMD being deposited for the said Tender.
(ii) that in the event we withdraw/ modify our bid during the period of validity OR I/We fail
to execute formal contract agreement within the given timeline OR I/We fail to submit
a performance security within the given timeline OR I/we commit any other breach of
Tender conditions / Contract which attracts penal action of forfeiture of EMD and I/we
will be suspended from being eligible for bidding / award of all future contract(s) of
Indian Oil Corporation Limited for a period of one year from the date of committing
such breach.
INSTRUCTIONS TO BIDDERS
INSTRUCTIONS TO BIDDERS
Table of Contents
A. GENERAL .................................................................................................................................................. 4
1. SCOPE OF BID .............................................................................................................................. 4
2. CARTEL FORMATION ................................................................................................................... 4
3. ELIGIBLE BIDDERS ....................................................................................................................... 4
B. CONTENTS OF BIDDING DOCUMENT ...................................................................................................... 4
4. BIDDING DOCUMENT .................................................................................................................. 4
5. CLARIFICATION OF BIDDING DOCUMENT, PRE-BID MEETING & SITE VISIT ............................... 5
6. AMENDMENT OF BIDDING DOCUMENT ..................................................................................... 7
7. ACKNOWLEDGEMENT & CONFIRMATION .................................................................................. 7
C. PREPARATION OF BIDS ........................................................................................................................... 7
8. COST OF BIDDING ....................................................................................................................... 7
9. LANGUAGE OF BID ...................................................................................................................... 8
10. DOCUMENTS COMPRISING THE BID ........................................................................................... 8
11. INTEGRITY PACT .......................................................................................................................... 9
12. BIDS ON CONSORTIUM BASIS ................................................................................................... 10
13. COMPLETE SCOPE OF SUPPLIES/WORK .................................................................................... 12
14. BID PRICES AND DISCOUNTS..................................................................................................... 14
15. CURRENCIES OF BID AND PAYMENT ......................................................................................... 15
16. DOCUMENTS ESTABLISHING THE QUALIFICATIONS OF THE BIDDER ....................................... 17
17. SPECIAL DOCUMENTATION REQUIREMENT ............................................................................. 19
18. PERIOD OF VALIDITY OF BIDS ................................................................................................... 20
19. BID SECURITY ............................................................................................................................ 20
20. FORMAT AND SIGNING OF BID ................................................................................................. 22
21. GOODS AND SERVICE TAX (GST) ............................................................................................... 22
22. ALTERNATIVE BIDS .................................................................................................................... 22
D. SUBMISSION AND OPENING OF BIDS ................................................................................................... 23
23. SEALING AND MARKING OF BIDS.............................................................................................. 23
24. DEADLINE FOR SUBMISSION OF BIDS ....................................................................................... 24
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
INSTRUCTIONS TO BIDDERS
A. GENERAL
1. SCOPE OF BID
In connection with the Notice Inviting Tender (NIT), Technip India Ltd. (hereinafter referred as “TPIL” or
“PMC or CONSULTANT”) on behalf of Indian Oil Corporation Limited (hereinafter referred as “OWNER”
or “IOCL” or “IOC”) invites e-Bids for PACAKGE-4: POWER DISTRIBUTION FACILITY FOR
PETROCHEMICAL AND LUBE INTEGRATION PROJECT “LUPECH” (J-18) PROJECT AT IOCL
GUJARAT REFINERY, India under Single Stage Two-Bid system (Part-1: Techno-Commercial Part
and Part -2: Price Part) for the scope covered under the Bidding Document (hereinafter for the purpose
of these instructions collectively referred to as the “WORKS” as specified in Bid Data Sheet (BDS)).
2. CARTEL FORMATION
In case any Bidder is found to be involved in cartel formation, his bid will not be considered for evaluation
/ placement of order. Such bidder will also be debarred from bidding in future.
3. ELIGIBLE BIDDERS
3.1. A bidder may be a firm or a company, who, have been issued the Bidding Document intends to submit
bid, in response to Notice Inviting Tender (NIT) on Domestic Open competitive basis.
3.2. A bidder who is on Holiday/ Negative list of Owner on due date of submission of bid/ during the process
of evaluation of the bids, the offers of such bidders shall not be considered for bid
opening/evaluation/award.
3.3. Deleted.
4. BIDDING DOCUMENT
4.1. The Bidding Document shall in general consist of the following and should be read in conjunction with
any amendment issued in accordance with Clause No 6.0 of ITB.
INSTRUCTIONS TO BIDDERS
4.2. Although all the details presented in this Bidding Document have been compiled with reasonable care,
the bidder is expected to examine the Bidding Document, including all instructions, forms, terms,
specifications and drawings in the Bidding Document and it includes all the documents as per Table of
Contents. In case of any ambiguity or incompleteness, the bidder must bring it to the attention of
CONSULTANT immediately and prior to submission of Bid.
4.3. Bidding document once issued in case of limited competitive bidding is non-transferable. However, in
case of Open Competitive Bidding, since the Bidding Document is available for free downloading on the
portal, any bidder may submit the Bid and the same shall be evaluated in line with the provisions of the
Bidding Document.
4.4. Bidders shall treat the Bidding Documents and contents therein as strictly confidential.
4.5. The Bidding Document is and shall remain the exclusive property of the Owner/CONSULTANT without
any right to Bidder to use them for any purpose except for the purpose of bidding.
5.1. Bidders in their own interest are advised to take part in the Pre-bid meeting seriously by issuing their
genuine queries and also by attending the Pre-Bid meeting by their competent personnel. This will help
the bidder to submit their best prices based on the clear understanding of the Techno-Commercial
scope.
5.2. Bidder’s authorized representative(s) shall attend the Pre-Bid meeting on the prescribed day at the given
venue specified in NIT. During the pre-bid meeting, all the technical and commercial issues shall be
discussed and concluded to ensure that the bid received subsequent to Pre-Bid meeting shall be without
any deviations to terms and conditions. Hence, bidders shall treat the Pre-Bid meeting as utmost
important and depute competent & senior person capable of taking on the spot decision to sort out all
the technical and commercial issues.
However, in case any bidder does not attend the Pre-Bid meeting, it shall be understood that the bidder
has a clear understanding of the scope, terms & conditions of the bidding document and does not have
any comments/deviations to the requirements of the bidding document.
5.3. In order to ensure fruitful discussions during Pre-Bid meeting, the bidder is requested to submit any
queries/clarification/information pertaining to Bidding document in writing delivered by hand or by e- mail
in the format provided in Bidding Forms so as to reach Two Days prior to Pre-Bid meeting. These queries
shall be replied during Pre-Bid meeting. The editable soft copies of the queries shall also be e-mailed to
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
concerned persons specified in BDS, to enable CONSULTANT to prepare replies to the queries in the
same format expeditiously.
5.4. The bidders are required to participate in the Pre-Bid meeting after going through the entire bidding
document along with BQC. Bidder shall come with all technical and commercial points on which they
need clarifications and also to ensure that they possess all the supporting documentation for meeting
the BQC (if any). In case of any doubt, they may discuss the same during the Pre-Bid meeting to avoid
any techno-commercial clarifications/ discussions post bid.
5.5. Based on the Pre-bid meeting / discussions and queries, necessary Addendums may be issued, if
deemed necessary by OWNER / PMC.
5.6. The OWNER’s responses to Bidder’s queries / clarifications raised will be furnished as expeditiously as
possible. Any modification of the Bidding Documents which may become necessary as a result of the
pre-bid meeting / conference shall be sent to all Bidders to whom the Bidding Documents have been
issued, through the issue of an Amendment / Addendum. The response to pre-bid queries shall not form
part of the Bidding Document unless issued as an Addendum / Amendment.
5.7. Deleted
5.8. Bidder in their own interest shall submit bids fully complying to bidding document requirements and
CONSULTANT shall reserve the right to proceed with the available compliant bids for evaluation without
raising any technical/ commercial queries.
5.9. Bidder is advised to visit and examine the Project Site and its surroundings and obtain for itself on its
own responsibility all information that may be necessary for preparing the bid and entering into a contract
for execution of the WORKS. All costs towards the same including the cost of visiting the Site shall be
at the bidder’s own expense. Claims of any kind due to variation or ignorance of site conditions and
environmental conditions shall not be eligible in any circumstances.
5.10. Bidder and any of its personnel will be granted permission by Owner to enter upon its premises and
lands/ Project Site for the purpose of such visit, but only upon the express condition that the bidder and
its personnel will relieve and indemnify Owner and its personnel from and against all liability in respect
thereof, and will be responsible for death or personal injury, loss of or damage to property, and any other
loss, damage, costs, and expenses incurred as a result of the inspection. Bidder shall refer BDS for
schedule and contact details related to site visit.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
6.1. At any time prior to the deadline for submission of bids, CONSULTANT may, for any reason whether at
his own initiative or in response to the clarification requested by the prospective bidder(s), issue
amendment in the form of Amendment/ Addendum.
6.2. Any addendum issued shall be part of the Bidding Documents and shall be uploaded on IOCL
e-Tendering Portal (https://iocletenders.gov.in/).
6.3. To give bidders reasonable time in which to take an addendum into account in preparing their bids,
CONSULTANT may extend the deadline for the submission of bids, pursuant to Clause 24.3 of ITB.
6.4. For Amendment / Addendum issued during the bidding period, bidder shall consider the impact in his
bid.
6.5. CONSULTANT may also for any reason issue amendment subsequent to receiving the bids. Any
amendment thus issued shall become part of Bidding Document. Bidder shall follow the instructions
issued along with Amendment with regard to submission of impact on quoted price / revised price, if any.
7.1. Within 05 (Five) days of downloading the Bidding Document, Bidder shall acknowledge the receipt of
Bidding Document and confirm his intention to submit his Bid as per the Proforma enclosed as Annexure
- I to ITB.
7.2. Bidder must furnish the Acknowledgement-Cum-Consent Letter positively. Bidder should download the
Bidding Document in their name and while downloading the Bidding Document shall give complete and
correct contact details while downloading the document.
C. PREPARATION OF BIDS
8. COST OF BIDDING
8.1. All direct and indirect costs associated with the preparation and submission of bid (including clarification
meetings and site visit, if any), shall be to Bidder’s account and the CONSULTANT/ OWNER will in no
case be responsible or liable for those costs, regardless of the conduct or outcome of the bidding
process.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
9. LANGUAGE OF BID
9.1. The Bid, as well as all correspondence and documents relating to the bid exchanged by the bidder and
CONSULTANT, shall be in the English language. Supporting documents and printed literature that are
part of the Bid may be in another language provided they are accompanied by an accurate translation
of the relevant passages in the English language, in which case, for purposes of interpretation of the
Bid, such translation shall govern.
9.2. In case a bidder submits any of the Bidder Qualification support documents in any language other than
English, then it will be the responsibility of such foreign vendor to also provide the English translation
copy of the same duly certified, stamped and signed by their Local Chamber of Commerce. Translation
by Indian Embassy/ High Commission or authorized/ approved translation agencies (by Indian embassy/
high commission or any other authority) shall also be acceptable.
Electronic Bids (e-bid) in two parts i.e. PART-I (Techno-commercial part) & PART-II (Priced part) as
detailed below shall be submitted in e-tendering portal in accordance with the instructions and terms &
conditions enclosed with the Bidding Document.
Bid Security/EMD is not applicable in this Tender, bidders shall ignore this clause and all relevant
clauses appearing anywhere in this ITB (including in its Annexures/Attachments) on the matter
of Bid Security/EMD)
(a) The Bid Security shall be submitted in original as per clause 19.12 of ITB or any extension
thereof as duly notified in writing by CONSULTANT, at the address mentioned in BDS.
Note: Scanned copy of Bid security shall be uploaded in “FEE FOLDER” in e-tendering portal.
(a) Schedule of Prices/ Schedule of Rates with prices filled in. The rates are to be filled in accordance
with instructions provided in preamble to Schedule of prices, in e-tendering portal, without making
any changes in the format/names of the file/ worksheet.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
(b) Deviations to terms and conditions, presumptions, overwriting etc. shall not be stipulated in Price
part of bid and price bids shall not contain any stapled slips. In case of any conditions stipulated in
price bids or the price bid containing any stapled slips, the bids of such bidders shall be summarily
rejected and shall not be considered for further evaluation. Evaluation shall be carried out excluding
such bidder(s.)
11.1. Indian Oil Corporation Limited (OWNER) has signed an MOU with Transparency International India for
adoption of the Integrity Pact Program. The MOU is available at IOCL website
http://www.iocl.com/aboutus/Draft MOU.pdf. Owner is committed to follow the principles of transparency,
equity and competitiveness in public procurements.
11.2. Bidder has also to commit the same through executing an Integrity Pact Agreement (IPA) and
declarations which is now part of this tender document. In absence of the same, the tender would be
summarily rejected. Format of Integrity agreement and declaration are enclosed as Attachment-III to
ITB and are also available at Indian Oil Website www.iocl.com.
IPA will prevail over General Conditions of Contract with regard to specific clauses of the IPA including
consequential breaches by the bidders.
11.3. Any violations/alleged violation of IPA would not be subject matter of arbitration.
11.4. Integrity pact agreement shall be returned by the Bidder along with the bid documents, duly signed by
the same signatory who is authorized to sign the bid documents. Bidder’s failure to submit the integrity
pact duly signed shall result in the bid not being considered for further evaluation.
11.5. Bidders may raise disputes/ complaints, if any, with the nominated Independent External Monitor.
11.6. Offers of Bidders who sign & submit the Integrity Pact Program (as applicable) will only be considered
for evaluation. In case the Bidder does not sign the Integrity Pact Agreement (IPA), a reasonable grace
time may be given to the party to comply with the requirements. In case of non-submission within the
grace period / refusal by any party to sign the IPA agreement, the offer of such bidder shall be rejected.
11.7. Following members have been appointed as IEM (Independent External Monitor) by the Commission
for the subject work of "LuPech" (J-18) Project:
1. Shri Basant Seth, Former CMD, Syndicate Bank and Information Commissioner, CIC.
2. Ms. M. C. Borwankar, IPS (Retd.).
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
IP Secretariat:
Indian Oil Corporation Limited, Room No. 542, 5th Floor, Core 6, Scope Complex, Lodhi Road,
New Delhi – 110003. INDIA.
E-mail: iem-iocl@indianoil.in
(As Consortium/JV Bidding is not allowed in this tender, bidders shall ignore this clause / all
relevant clauses appearing anywhere in this ITB (including in its Annexures/Attachments) on the
matter of Consortium/JV Bidding)
12.1 The Bids shall contain copy of the original Memorandum of Understanding (MOU) between the
consortium members. The MOU shall be converted to a definitive Agreement between the parties after
award of job and before signing of Contract which shall be done within three months from the date of
award. The Agreement must remain in force at least till the pendency of the Contract.
12.2 The leader of the consortium shall represent the Consortium in all dealings with the OWNER and for
providing any information or clarification sought from the Consortium, and this authorization shall be
evident in legally executed Power of Attorney signed by legally authorized signatories of all the
consortium members so as to enable such representative member(s) to be in-charge and to act on
behalf of and to bind the other member.
12.3 The Bid shall be signed by authorized signatory of the Bidder / Leader of the Consortium.
12.4 The consortium leader shall be authorized to incur liabilities and receive instructions for and on behalf
of any and all member(s) of the Consortium and all dealings including billing and payments shall be done
exclusively with the leader of the consortium.
12.5 All dealings had with and/or all acts, deeds, matters and things and things done by or payments made
to and invoices/documents drawn and/or negotiated by the lead member shall be binding upon the
Contractor and each member of the consortium, and in so far as CONSULTANT shall require a
discharge in respect of any dealing had or act, deed, matter or thing done or payment made as aforesaid,
the same shall constitute a valid discharge to CONSULTANT.
12.6 Each and every member of the consortium shall be jointly and separately liable to CONSULTANT/ IOCL
for and in respect of all liabilities obligations of the Contractor under the Contract.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
12.7 It will be open to the members of the consortium to nominate amongst themselves the distribution of the
Foreign Currency payments and the Indian Rupees payments under the Contract and submit the same
to the OWNER together with the bid.
12.8 The OWNER may accept the distribution of payment between the consortium/ joint venture members/
partners and make payment accordingly, subject to the following;
i. Each of the consortium/ joint venture members/ partners shall within their respective
entitlements, raise invoices for Running Account and other payments due to the
CONTRACTOR in terms of the Contract for presentation to the consortium leader, who shall
present the Invoices(s) to the OWNER after the consortium leader has duly certified the Invoice
for payment, provided however that such certification shall be made by means of the
CONTRACTOR’S letters prepared separately from the Invoices. Such certification shall be in
addition to any other certification required in terms of the Contract or otherwise with respect to
such payment.
ii. If the Consortium/ Joint venture contains a foreign member or partner, deduction of tax at
source on all payments shall be as per the rate certified by the Indian Income Tax authorities
in respect of each member/ partner for such payments. Pending receipt of such certificate from
Income Tax Authorities, the owner shall not release any payment to the members/ partner.
iii. Payments shall be made by the OWNER to the separate members/ partners against their
separate certified Invoices transmitted through the consortium leader and any such payment
shall constitute payment to the consortium/ joint venture and shall give a valid discharge to the
OWNER in the same manner as if made directly to the Consortium Leader.
iv. It shall be up to the consortium members/ partners claiming the separate payments to obtain
such sanctions, consents and/ or permits required from the Reserve Bank of India or other
authorities concerned to authorize separate payments to and/or separate accounts of each
consortium member, failing of which all payments will be made only to the Consortium leader
disregarding of any agreed distribution.
12.9 All the members of the Consortium shall be jointly and severally responsible for the Performance of the
CONTRACT in accordance with its terms and a statement to this effect shall be deemed to be included
in the authorization mentioned under clause 12.3 above as well as in the Bid and shall be specifically
included in the Form of Contract (in the case of successful bid).
12.10 The constitution of the Consortium/JV or the relative distribution of the Work(s) and/or activities amongst
the consortium members as approved by CONSULTANT shall not be altered or assigned, as the case
may be except with the prior written consent of CONSULTANT/OWNER and any contrary alteration or
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
12.11 Contract Performance bank guarantee of the required amount can be furnished by any member of the
consortium/JV.
12.12 Above mentioned Clauses mentioned for Bidding on Consortium Basis shall be applicable for Bidding
Joint Venture (JV) basis also. In this regard, Bidders are also requested to go through the relevant
provisions/stipulations mentioned in the Bidding Document while Bidding on Consortium /JV basis.
13.1 The complete scope of supplies and work/services has been defined in the Bidding Documents. Only
those bidders who take complete responsibility and who bid for the complete scope of supplies and
work/services as contained in the Bidding Document shall be considered for further evaluation.
13.2 If the CONTRACTOR is required to engage a Sub-Contractor for any part of work, then such Sub-
Contractors shall have prior proven experience of similar work and shall require specific approval by
OWNER after award of work. Following the notification of Acceptance of Bid, the CONTRACTOR will
submit to the OWNER for approval the details of Sub-Contractors in line with requirement of SCC.
The list of Construction Sub-Contractors proposed in the Bids by the Bidders shall be considered as
indicative only.
13.3 If a proposed Sub-Contractor has been approved by the OWNER, the CONTRACTOR shall not replace
such approved Sub-Contractor with another Sub-Contractor without obtaining the OWNER’s prior
approval for the proposed replacement.
13.4 The Bidder shall along with the bid furnish its Project Execution Plan, which shall be evaluated for
technical acceptability of the Bids.
13.5 The Project Execution Plan shall be submitted as per following basic guidelines:
13.5.1 As a minimum, the following activities shall be performed by the CONTRACTOR directly and shall not
be Sub-Contracted:
(i) Overall Project Management
(ii) Planning, Scheduling, Monitoring
(iii) Procurement
(iv) Quality Control
(v) Construction Management
(vi) Commissioning
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
13.5.2 Bidder shall identify the key persons responsible for the above activities of work by identifying the
relevant persons and submitting the bio-data of such Personnel:
Project Management
▪ Project Director
▪ Project Manager at Contractor’s home office
▪ Project Manager for this work stationed at site
▪ Project Coordinators
Planning, Scheduling, Monitoring
▪ Planning & Scheduling Manager
▪ Planning Engineer
Procurement
▪ Procurement Manager
▪ Procurement Engineer
▪ Expeditor
Construction Management
▪ Resident Construction Manager
▪ Lead Construction Engineer for disciplines
• Civil/Structural
• Mechanical Equipment
• Electrical
• Instrumentation
• Safety Officer
• QA/QC Engineer
Project Engineering Management
▪ Engineering Manager
▪ Lead Engineer for all disciplines such as:
• Process
• Civil/Structural
• Pressure Vessels
• Rotary Equipment
• Mechanical / Static Equipment
• HMTD Equipment
• Electrical
• Instrumentation
• Piping
• Commissioning
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
Bidder shall furnish the bio-data of all key personnel as mentioned above who are working within Bidder’s
Organization
13.5.3 Bidder shall submit a commitment from its Chief Executive that the Project Progress Schedule shall be
monitored by its board and all actions required to arrest the failure/delays shall be initiated by them at
the appropriate time. Such action plan document shall be sent by the CONTRACTOR’s home office to
the Executive Director/ OWNER.
13.5.4 Bidder shall ensure that the Project Execution Plan submitted by it is adequate for completing the work
in all respects. All details as mentioned above shall be submitted along with Bid in the first instance.
13.5.5 Project Execution Plan shall be evaluated by the CONSULTANT/OWNER and in case the same is not
found adequate for this work, such Bid(s) shall be treated Technically Not Acceptable and such Bid(s)
shall not be considered for price opening.
14.1 The prices must be quoted strictly in the format provided in the Bidding Document. Conditional discount,
if offered, shall not be considered for evaluation.
14.2 The Total Lumpsum Price shall be quoted in the FORM SP-0 of the Price Schedule comprising the total
of the Lumpsum prices given in FORM SP-1 and FORM SP-2. For Lumpsum Prices quoted in FORM
SP-1 & FORM SP-2, break-up shall be quoted in terms of % in FORM SP-4 & FORM SP-5 respectively.
FORM SP-4 and FORM SP-5 shall be submitted in UN-PRICED OFFER only. For further details, Bidder
shall refer to Preamble to Schedule of Prices and SP FORMS for compliance.
14.3 Unless stated otherwise in the Bidding Document, the Contract shall be for the total works as described
in Bidding Document, based on the Schedule of Rates/ Prices submitted by the bidder and accepted by
CONSULTANT/OWNER.
14.4 Bidder shall quote for all the items of Schedule of Rates/Prices after careful analysis of cost involved for
the performance of the complete item considering all parts of the Bidding Document. In case any activity
is not specifically covered in description of item under ‘Schedule of Rates/Prices' but is required to
complete the work as per Scope of Work, Scope of Supply, Specifications, Standards, Drawings,
General Conditions of Contract, Special Condition of Contract or any other part of Bidding Document,
the rates/ prices quoted shall be deemed to be inclusive of cost incurred for such activity.
14.5 Rates/ prices quoted by the bidder, shall remain firm, fixed and valid till the completion of the Works and
will not be subject to variation on any account except as otherwise specifically provided in the Bidding
Documents.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
14.6 Discount, if any, must be indicated in the column provided in Schedule of Rates/Prices only, provided in
the Bidding Document.
14.7 All duties, taxes, and other levies payable shall be as per Special Conditions of Contract.
14.8 It shall be the duty of the CONTRACTOR to duly observe and perform all laws, rules, regulations, orders
and formalities applicable to GST & Customs Duty, etc. on the import, manufacture, sale and/or supply
of any material to the OWNER and performance of the works under the Contract. The CONTRACTOR
shall keep the OWNER indemnified from and against any and all claims, demands, prosecutions,
actions, proceedings, penalties, damages, demurrages and/or other levies whatsoever made or levied
by any Court, Tribunal or the Customs or other Authorities with respect to any alleged breach, evasion
or infraction of such duties, taxes, charges or levies or any breach or infraction of any applicable laws,
rules, regulations, orders or formalities concerning the same and from the consequence thereof.
15.1 Foreign Bidders may quote prices for materials and services to be imported into India either in Indian
Rupees or in Foreign Currency or in a combination of Indian Rupees and a Foreign Currency.
15.2 For the purpose of this clause and any other relevant provisions in these documents, Foreign Currency
(FC) shall mean and be limited to US DOLLARS, EURO and JAPANESE YEN.
However, maximum no. of currencies of quote shall be limited to currencies (1) Indian Rupees and any
one of the allowed Foreign Currencies mentioned above.
i. Also, Bidders shall quote the price for materials and services to be procured from India and
for expenses to be incurred in India only in Indian Rupees.
ii. Indian bidders may quote the prices for materials and services to be imported into India in
Foreign Currency. Such bidders quoting in foreign currency shall separately indicate in a
list the materials and services to be imported into India and the Foreign Currency price
payable for such materials and services. However, for evaluation purposes, the bid price
shall be converted to Indian Rupees by converting the Foreign Currency into Indian Rupees
at the Bill selling rate of State Bank of India, New Delhi prevailing on the day of opening of
the price bid.
15.3 Indian bidders who have indicated materials or services to be imported into India, and who have
indicated the Foreign Currency price for such materials and/or services in their bids as specified above,
shall on proof of payment be paid the Rupee equivalent of the Foreign Currency paid for the relevant
materials or services imported into India limited to the maximum of the Foreign Currency indicated in the
priced bid in relation to such supplies or services at the TT buying rate for concerned currency of the
State Bank of India, New Delhi prevailing on the date of payment , with the intention that the risk of
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
fluctuations in the exchange rate between the concerned foreign currency and the Indian Rupee to the
extent indicated above shall be borne by the OWNER. If as a result, there shall remain any unutilized
foreign currency indicated in the priced bid relevant to the formation of the Contract in relation to such
supplies or services, these shall be considered to be the CONTRACTOR’s fee for the relative
procurement or services, as the case may be, and shall be added to and paid for separately, in the Final
Bill, in addition to the price of services, in Indian Rupees equivalent of such unutilized foreign currency
balance(s) converted at the currency Bill Selling rate of the concerned currency of State Bank of India,
New Delhi prevailing on the date of price bid opening or at the TT buying rate of the concerned currency
of State Bank of India, New Delhi prevailing on the date of Mechanical Completion, whichever is less. In
case of unutilized foreign currency while converting from supply to service, non cenvatable taxes &
duties and income tax at source shall be to the CONTRACTOR’s account.
15.4 If in the performance of the Contract, the successful bidder obtains or procures within India any materials
or services which at the time of the bid were indicated to be procured or provided from outside India,
such bidder shall be paid only the Indian Rupee equivalent of the foreign currency cost of such materials
or services as indicated in the priced bid relevant to the formation of the Contract, converted at the
currency TT buying rate for the relevant currency of the State Bank of India, New Delhi prevailing on the
date of payment by the CONTRACTOR or at the Bill Selling Rate of State Bank of India, New Delhi
prevailing on the day of priced bid opening, whichever is less, for such supplies or services. Any change
in such sourcing shall be subject to the OWNER’s prior consent. However, in such a case, the DDP
price indicated in the Contract shall stand reduced by the price attributable to such supplies.
15.5 If in the performance of the Contract, the successful bidder obtains or procures from outside India any
materials or services which at the time of the bid were indicated to be procured or provided from within
India, such bidder shall be paid only the Indian Rupees indicated in the Bill of Materials or in the Schedule
of Activities, as the case may be, for such materials or services. However, such changes shall not oblige
the OWNER to pay customs duties (including counter vailing duties and special or additional custom
duties, IGST etc.) in excess of such duties payable on the DDP value of imported materials indicated by
the Bidder in the SP-1.
Definition: DDP as per incoterms 2010 is – Delivered Duty Paid: Seller bears cost, risk and
responsibility for cleared goods at named place of destination at buyer’s disposal. Seller is responsible
for import clearance, duties and taxes so buyer is not “importer of record”.
15.7.1 Bidders shall not directly or indirectly quote foreign currency component of their lumpsum price bid
beyond a ceiling of 24% (Twenty Four percent) of the total lumpsum price. The balance shall be quoted
in Indian Rupees only.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
15.7.2. In case a bidder quotes a foreign currency component more than 24% (Twenty Four percent) of the
lumpsum price, the differential amount of the foreign currency in excess of 24% (Twenty Four percent)
shall be converted into Indian Rupees at the relative currency TT buying rate of the State Bank of India,
New Delhi prevailing on the day of price bid opening, which shall be paid in the Final Bill in the price of
services.
15.7.3. For the purposes of calculating the said percentage the foreign currency shall be converted into Indian
Rupees at the TT buying rate of the State Bank of India, New Delhi for relative currency on the due
date of submission of bid/ revised price bid, whichever is later
16.1 If specified in the NIT(Notice Inviting Tender) / bidding document, bidder(s) intending to participate the
shall fulfill the Bidder Qualification Criteria (BQC) specified in the Detailed NIT/ bidding document. The
experience and finance details submitted by the Bidders shall be evaluated with respect to the
Qualification Criteria specified in the NIT/ Bidding document. Bidders are requested to submit all
qualification details along with relevant supporting documents in the first instance itself as
CONSULTANT may finalize the qualification based on details submitted without asking for any
additional details submitted without asking for any additional details. In view of this, Bidder, in their own
interest, must submit experience details for as many jobs as possible that, in his opinion, meet the
Bidder Qualification Criteria (BQC).
16.2 Bids of only those bidders who are found to qualify based on the Qualification Criteria specified in the
NIT shall be considered for detailed Techno-commercial evaluation. Decision of
OWNER/CONSULTANT in this regard shall be final and binding.
16.3 While evaluating the Bidder’s conformity with Qualification Criteria, only such works shall be taken into
consideration, the details of which have been submitted along with the bid.
16.4 Copy of Work Order/ notification of award of work along with documentary evidence of its completion
is mandatory, which establishes that the bidder has been awarded a work and proof of completion
which establishes that the works under reference has been completed.(unless otherwise there is any
specific mention in the bidding document regarding consideration of work in progress).
INSTRUCTIONS TO BIDDERS
to facilitate due evaluation/ consideration/ of its / his/ their tender. Past experience or certification(s)
given with respect to or in connection with a work or job for which a bidder has been placed on the
blacklist or holiday list (howsoever designated or called) by Indian Oil Corporation Ltd. or by any
Government or other organization mentioned in the Declaration of blacklisting / holiday listing shall
not be considered for determining the bidder’s experience or qualification for work(s)
notwithstanding that the period of blacklisting/ holiday listing in respect thereof has expired.
ii. If any information given by a bidder / tenderer is found to be incorrect in any particular considered
by the Owner to be relevant for the evaluation of the bid/ tender, or is found by the Owner to
misrepresent or conceal facts, or if any of the documents submitted by the bidder/ tenderer in support
of or relevant to the bid/ tender is found by the OWNER to be forged, false or fabricated, the OWNER
may reject the bid, and without prejudice to any other right(s) of action or remedy available to the
OWNER, the OWNER may forfeit the Earnest Money given by the bidder in the Form of Earnest
Money Deposit or bank guarantee in order to compensate the OWNER for the expenses incurred
by it in considering the bid (and not by way of penalty) and take action for putting the bidder / tenderer
on holiday list for such period as the Owner in this behalf considers warranted and/ or remove the
bidder/ tenderer from any approved lists of vendors/ contractors. If prior to the discovery of the
incorrect information, misrepresentation or forged, false or fabricated document (s), the bid / tender
has resulted in a contract, the Contract shall be liable to be terminated by the OWNER pursuant to
the provisions of Clause 7.0.1.0 of the General Conditions of Contract with consequences of
termination as provided in Section 7 of the General Conditions of Contract.
(i) Each tenderer/bidder shall give a declaration in the prescribed format annexed to the bidding
forms that he / it / they is / are not under any blacklist or holiday list declared by the OWNER
or by any Department of the State or Central Government or by any other Public Sector
Organization, and that there is no inquiry in respect of any corrupt or fraudulent practice
pending against him/it/them. In case he / it / they is / are under any such list, or any inquiry is
pending, he / it / they shall in the declaration give full details thereof. Such declaration in respect
of a partnership firm or association of persons shall cover every partner or member of the
association, and in the case of company, shall cover every director and principal shareholder
of the company and any holding company and/or subsidiary company (ies), if any.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
(ii) If a tenderer is on any such List or if any such inquiry is pending against it/him/them or if the
bidder has suppressed information or makes a false declaration in relation thereto, the OWNER
reserves the right to reject the bid. If the bidder has suppressed any such information or made
a false declaration, then without prejudice to any other right(s) of action or remedy available to
the OWNER, the OWNER may forfeit the Earnest Money given by the bidder in the Form of
Earnest Money Deposit or bank guarantee in order to compensate the OWNER for the
expenses incurred by it in considering the bid (and not by way of penalty) and take action for
putting the bidder / tenderer on holiday list for such period as the OWNER in this behalf
considers warranted and / or remove the bidder / tenderer from any approved list of vendors /
contractors. If prior to the discovery of the incorrect information, or misrepresentation, the bid /
tender has resulted in a contract, the Contract shall be liable to be terminated by the OWNER
pursuant to the provisions of Clause 7.0.1.0 of the General Conditions of Contract with
consequences of termination as provided in Section 7 of the General Conditions of Contract.
(iii) The Declaration to be furnished in this behalf in the Format attached to bidding form.
(i) The bidder/tenderer shall give a declaration in the prescribed format annexed under bidding
form that it/he/they is/are not engaging nor will engage child labour, and that if the
Contract/work is awarded to the bidder pursuant to the bid, the bidder/tenderer undertakes to
comply with all laws, rules and regulations concerning the engagement of child labour or
concerning the engagement of persons below a prohibited age or of a prohibited sex in any
hazardous or prohibited activity.
(ii) The declaration with regard to engagement of child labour shall be in the format attached under
bidding forms.
17.1 All supporting documents, pertaining to “Bidder Qualification Criteria” including the copy of MSE
certificate, if any, shall be submitted.
17.2 Submission of authentic documents is the prime responsibility of the bidder. Bidders should ensure
submission of complete information / documentation in the first instance itself.
17.3 Wherever CONSULTANT / OWNER has concern or apprehension regarding the authenticity/
correctness of any document, CONSULTANT / OWNER reserves a right of getting the document cross
verified from the document issuing authority.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
18.1 Bids shall remain valid for the period specified in the BDS after the bid submission deadline date
prescribed by CONSULTANT / OWNER in accordance with Clause 24 of ITB. A bid with shorter validity
shall be rejected by CONSULTANT / OWNER as non-responsive. Bidders shall not be entitled during
the above period, without the consent of CONSULTANT / OWNER in writing, to revoke or cancel their
Bid or to vary the Bid given or any term thereof. In case of bidders revoking or cancelling their Bid or
varying any terms in regard thereof without the consent of CONSULTANT / OWNER in writing,
CONSULTANT / OWNER shall forfeit Bid security, submitted along with the bid and shall reject their
bids. Such Bidder may also be put on Holiday list/ Negative List.
18.2 In exceptional circumstances, prior to the expiration of the bid validity period, CONSULTANT / OWNER
may request bidders to extend the period of validity of their bids. The request and the responses shall
be made in writing. If a bid security is requested in accordance with Clause 19.1 of ITB, it shall also be
extended for 3 (Three) months beyond the deadline of the extended validity period. A bidder may refuse
the request without forfeiting its bid security. A bidder granting the request shall not be permitted to
modify its bid.
19.1 Bidder shall furnish as part of its bid, a Bid Security, in original form and, in the amount and currency
specified in the BDS.
19.2 Bids not accompanied with EMD shall be rejected. However, exemption of EMD will be applicable for,
Government organizations, Central/ State PSUs, JVs of IOCL and Micro or Small Enterprises (MSEs)
registered with District Industries Centers or Khadi and Village Industries Commission or Khadi and
Village Industries Board or Coir Board or National Small Industries Corporation or Directorate of
Handicrafts and Handlooms or any other Body specified by Ministry of Micro, Small and Medium
Enterprise provided that certificate issued by the relevant agency is valid (wherever validity is specified
in the certificate) on the date of Un-priced Bid Opening. Scanned copy of Registration certificate or
Udyog Aadhar Memorandum should be uploaded in the e-procurement website under e-bidding.
Documentary evidence; in support of such claims of bidder shall be provided.
19.3 The registration certificate Micro or Small Enterprises (MSEs) issued from any one of the agencies
mentioned at Clause 19.2 of ITB must be valid as on close date of the tender. The successful bidder
should ensure that the same is valid till the end of the contract period.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
19.4 The MSEs who have applied for registration or renewal of registration with any of the above
agencies/bodies, but have not obtained the valid certificate as on close date of the tender, are not
eligible for exemption/preference.
19.5 OWNER / CONSULTANT shall not pay any interest on Bid Security furnished. Further, in case bank
guarantee submitted is found to be fake, bid of such bidder shall be rejected and may initiate action as
deemed necessary as per CONSULTANT / OWNER Policy.
19.6 The bid security shall be in any of the following forms at the bidder’s option:
a) an unconditional guarantee in favour of “Indian Oil Corporation Ltd., Refineries Division (Details
as per Attachment-II to ITB), issued by any Bank (Selection of Bank shall be as per SCC Part
B), strictly in the format provided in GCC, however, Bid Security in the form of Bank Guarantee
shall be acceptable only in cases where value of Bid Security is more than INR. 1.00 Lakh (In
case bidder opt to submit Bank Guarantee, follow instruction of document “FAQs-IOCL-Online-
EMD” available along with Enquiry / Bidding Documentation e-tender portal);
b) (Online through RTGS/ NEFT through e-tendering portal (for all values).
(Bidder to follow instruction of document “FAQs-IOCL-Online-EMD” available along with
Enquiry/ Bidding Documentation e-tender portal).
19.7 Authorized Indian representatives associates of foreign bidders shall be allowed to submit EMD online
through RTGS/ NEFT through e-tendering portal also.
19.8 The bid security shall be valid for Three (3) Months beyond the validity period of the bid, or beyond any
period of extension if requested under Clause 18.2 of ITB.
19.9 EMD/ Bid securities shall be released to the bidders in the following circumstances:
i) EMD/ Bid securities of bidders whose price bids are not opened/ disqualified during techno-
commercial bid evaluation (unsuccessful Bidder) shall be released immediately by
CONSULTANT after approval of price bid opening.
ii) EMD/ Bid securities of bidders qualified in the techno-commercial bid but unsuccessful for
placement of Purchase Order shall be released after final approval of the placement of Purchase
Order by the competent authority.
iii) EMD/ Bid securities of the successful bidder shall be sent to IOCL & shall be released by IOCL
on receipt of acceptable PBG.
iv) In case CONSULTANT / Owner decides to cancel / annul the enquiry at any stage during the
bidding process but before the award (as applicable), EMD/ Bid securities of the bidders shall
be returned at the earliest from the date of such decision.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
19.10 The offer shall be rejected, EMD shall be forfeited and the Bidder shall be put on "Holiday/ Suspension/
banning list, as applicable" of CONSULTANT & IOCL (as per their prevailing policy) in case:
a) The bidder alters / modifies / withdraws the bid suo-moto after opening the bid(s) within the
validity period and / or submits multiple bids/ alternative bids.
b) If the successful bidder fails to accept arithmetical corrections
c) If the Information/ documents submitted by the bidder in the bid is found to be false/ forged, the
successful bidder fails to execute the order.
19.11 In case of Bank guarantees, if these are sent directly by the Bank, a certified copy of the said BG shall
be enclosed along with the techno-commercial offer.
19.12 Original EMD, as applicable, shall be submitted to CONSULTANT within Seven (7) working days from
the date of opening of techno-commercial (unpriced) bids, failing which their bid shall not be considered,
as per provisions of respective clause notwithstanding the fact that a copy of EMD was uploaded earlier
by the bidder on the e-tendering portal.
19.13 Offer submitted along with Swift message (in place of Firm EMD) or EMD having value less than required
value, shall be rejected & not considered for further evaluation.
20.1 The e-bid shall be digitally signed (e-signed) using the digital signature of a person duly authorized to
sign on behalf of the bidder. The digital signature used for signing the bid shall be issued in the name of
such authorized person and the certificate details, available from the signed documents, should indicate
the details of the signatories. All documents/files of the bid shall be signed by using the digital signature
issued in the name of the person having valid Power of Attorney (POA) at the time of bid submission.
Any consequences resulting due to such signing (e-signing) shall be binding on the bidder.
21.1 In the event of any conflict or inconsistency in provision of Taxes / GST related clauses in the bidding
document; the enacted GST shall prevail over the interpretation of existing clauses.
A bidder (i.e., the bidding entity) shall, on no account submit more than one bid either directly (as a
single bidder or as a member of consortium/JV) or indirectly (as a sub-contractor) failing which following
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
All bids submitted by such bidder (say “A‟) either as a single bidder or as a consortium/JV, shall stand
rejected and BID SECURITY, if any, in case of all such bids submitted by bidder “A‟ shall be forfeited.
If another bidder (say “B‟) has proposed bidder “A‟ as a sub-contractor then bidder “B‟’s bid shall also
be rejected. However, in case the bidder “B‟ has also proposed an alternative subcontractor who is other
than the bidder “A‟, then bidder “B‟’s bid shall be evaluated with the proposed alternative sub-contractor
only. Hence, every bidder shall ensure in his own interest that his proposed sub-contractor is not
submitting alternative/ multiple bids. Wherever a bidder proposes a sub-contractor, consent/ MOU with
the sub- contractor shall be enclosed
Note: However, in case CONSULTANT has proposed a list of sub-contractors/ sub-vendors in the
enquiry document itself which shall be common for all the bidders, the provision at (B) above shall not
be applicable as long as only the sub-contractors/ sub-vendors are common in case of various bidders
23.1 The bidder shall submit the, original Bid Security, as per the requirement of clause 10.2 of ITB, in
separate sealed envelopes, duly marking the envelopes as per following:
23.2 The envelope shall bear the name and address of the bidder and bear a warning not to open before the
time and date for bid opening.
23.3 If envelope is not sealed and marked as required, CONSULTANT / OWNER will assume no
responsibility for the misplacement or premature opening of the envelope.
23.4 Bidders shall submit bids (Part-I & Part-II) electronically through IOCL’s e-tendering portal by logging in
to website https://iocletenders.gov.in, on or before the bid submission date and time. Bidders are
required to register themselves at https://iocletenders.gov.in. No registration fee would be charged from
the bidders.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
23.5 Bidders are required to upload the bid along with all supporting documents & priced part on IOCL’s e-
tendering portal by logging in to website https://iocletenders.gov.in only.
23.6 Bidders to refer Bidders Manual Kit - Open Source Software Link available on the website to get
acquainted with the E-Tendering System in advance and obtain/seek clarifications, if any from IOCL e-
tendering Portal Helpdesk, whose contact information is provided in the E-Tendering website.
23.7 Various links such as “Help for Contractor”, “Information about DSC”, “FAQ”, “Resources Required”,
“Bidders Manual Kit” etc. are available on home page of https://iocletenders.gov.in/nicgep/app facilitating
vendors to participate in the bidding process. Bidder are advised to download & utilize the available
information/documents under these links for activities like Registration in IOCL portal, obtaining User ID
& Password, uploading & submission of e-bids etc.
23.8 Bidders are advised in their own interest to carefully go through Instructions for E-tendering and other
related document available against various help links so as to ensure that bids are uploaded in E-
tendering website well before the closing date and time of bid submission.
23.9 The bidder is required to make a proposal in a format as outlined in BDS to achieve the objective of
maintaining a uniform proposal structure from all bidders.
23.10 The bid shall be submitted by uploading relevant document in respective covers/folders provided in the
e- tendering website.
24.1 Bidders shall submit their bids electronically in the e-tendering portal, within the date and time specified
in the BDS.
24.2 Bid Security in accordance with ITB clause 19 (copy of documentary evidence as per ITB clause 19.2 in
case of exemption under MSE/PSU/JV of IOCL), in original, must be received by CONSULTANT at the
address and no later than the date and time for submission in accordance to ITB clause 10.2.
24.3 CONSULTANT may, at its discretion, extend the deadline for the submission of bids by amending the
Bidding Documents in accordance with Clause 6 of ITB, in which case all rights and obligations of
CONSULTANT and bidders previously subject to the deadline shall thereafter be subject to the deadline
as extended.
25.1 E-tendering system shall close immediately after the deadline for submission of bid. Any bids being
submitted in physical form (other than Part-III of Bid) shall not be considered for opening / evaluation /
award and will be returned to such bidders.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
25.2 In the event the Bid Security in original, in accordance with ITB clause 24.2, are not submitted within the
deadline, the bids shall be declared late and shall not be considered for further evaluation,
notwithstanding the fact that the bid has been submitted in electronic form within the deadline. However,
in case of exemption from submitting Bid Security under MSE/PSU/JVs of IOCL as per ITB clause 19.2,
then bidder shall submit the copy of documentary evidence as per ITB clause 19.2.
25.1 The bidder may modify, re-submit or withdraw its e-bid after the bid submission, but, before the due date
and time for submission of Bid following the electronic bid submission procedures.
25.2 No bid shall be withdrawn, substituted, or modified in the interval between the deadline for submission
of bids and the expiration of the period of bid validity or any extension thereof.
27.1 CONSULTANT shall verify the availability of requisite scanned copy of BID SECURITY/ documentary
evidence of exemptions from submission of Bid Security under MSE / PSU / JV of IOCL (if applicable),
prior to opening of Part-I of e-Bid. Techno-commercial e-Bid of those bidders shall be considered for
opening, who have uploaded the requisite Bid Security in e- tendering Portal.
27.2 CONSULTANT shall open Part-I of all bids received in the e-tendering portal except the cases where
scanned copy of BID SECURITY / documentary evidence of exemptions from submission of Bid Security
under MSE / PSU / JV of IOCL (if applicable) not uploaded.
a) Scanned Copy of Bid Security uploaded in e-tendering Portal shall be opened first and verified
that whether Bid Security has been furnished as per bid requirement.
b) Upon meeting the requirement of Bid Security as per Clause 19 of ITB, opening of documents
of Part–I, submitted in electronic form shall be processed on the e- Procurement module of
the e-tendering portal.
c) If a bidder has not complied with Bid Security requirement b) above, such bidder’s offer (Part-
I) is not proceeded for further opening and rejected out rightly.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
(ii) Part-II of bid of only those bidders whose bids is determined to be technically and commercially
acceptable by CONSULTANT shall be opened. Bidders selected for opening of their priced bids
shall be informed about the date, time and place of price bid opening.
28. CONFIDENTIALITY
28.1 A bidder may seek clarification regarding the bidding document provisions, bidding process and/ or
rejection of his bid. CONSULTANT shall respond to such requests within a reasonable time. However,
such information relating to the evaluation of bids and recommendation of contract award shall not be
disclosed to any other persons not officially concerned with the bidding process.
28.2 Any attempt by a bidder to influence CONSULTANT / Owner in the evaluation of the bids or Contract
award decisions shall render their Bid liable for rejection.
28.3 Notwithstanding Clause 28.2 of ITB, from the time of bid opening to the time of Contract award, if a
bidder wishes to contact CONSULTANT on any matter related to the bidding process, it shall be done
so in writing only.
29.2 A substantially responsive bid is one that meets the requirements of the Enquiry/Bidding Documents
without deviation.
29.3 Bidder should not be under liquidation, court receivership or similar proceedings. Bidder shall submit
self-certificate in this regard. Failure to do so or the bidder is under court receivership or similar
proceedings, their bids shall not be considered.
30.1 Bidders should ensure that the Bid submitted is substantially responsive Bid in the first instance itself.
Evaluation may be completed based on the content of the Bid itself without seeking any subsequent
additional information which may result in rejection of Bid. However, CONSULTANT/OWNER may, at
its discretion, may request bidder to submit the necessary information or documentation, within a
reasonable period of time, to withdraw material deviation, reservation, or rectify omission in the bid
related to documentation requirements. Requesting information or documentation on such account shall
not be related to any aspect of the price of the Bid. CONSULTANT’s request for clarification and the
response shall be in writing.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
30.2 No change, including any voluntary increase or decrease, in the prices or substance of the bid shall be
sought, offered, or permitted. Bidder shall not be allowed to submit any price implication or revised price
after submission of Bid unless the same is called for by CONSULTANT in writing.
30.3 Any clarification submitted by a bidder that is not in response to a request by CONSULTANT shall not
be considered. Failure of the bidder to comply with the request may result in the rejection of its Bid.
30.4 If a bidder does not provide clarifications of its bid by the date and time set in CONSULTANT’s request
for clarification, its bid shall be evaluated with available information which may result in rejection of their
bid.
31.1 Prior to price opening of bids, CONSULTANT will determine whether each bid is accompanied with
required Bid Security, as applicable;
i) Fulfills the technical, financial, commercial experience and other requirements as specified in the
bidding document.
ii) Considering any clarifications and/ or requirement pursuant to clause 30 of ITB;
iii) Any other relevant factor, if any that CONSULTANT/OWNER deems necessary or prudent to be
taken into consideration.
31.2 CONSULTANT / OWNER reserve the right to use in-house information for assessment of capability of
bidder and their performance on jobs completed/ in progress for evaluation purpose.
32.1 There will be no Purchase Preference to Micro and Small Enterprises/ bidder as per Public Procurement
Policy for MSEs in his tender.
32.2 For facilitating promotion and development of micro and small enterprises, CONSULTANT/ IOCL is
committed to promote the procurement of supplies/ services from MSEs in Orders/ contracts awarded
by CONSULTANT/ IOCL. Accordingly, bidders are also encouraged to promote the same by considering
MSE sub-suppliers/ sub-contractors to the extent possible under the Orders/ Contracts awarded on them
by CONSULTANT/ IOCL. After award of work, supplier/ contractor shall furnish statement along with
copies of orders/ FOAs placed by them on their sub-suppliers/ sub- contractors who are MSEs, to
CONSULTANT Project Manager/ RCM, as applicable.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
33.1 Priced Bid (Part-II) of only those bidders whose bids is determined to be technically and commercially
acceptable by CONSULTANT / OWNER shall be opened. Bidders selected for opening of their priced
bids shall be informed about the date, time and place of price bid opening.
34.2 Bidders shall be requested to accept correction of arithmetical errors. Failure to accept the correction in
accordance with Clause 34.1 of ITB above, shall result in the rejection of the Bid and Bid Security shall
be forfeited.
35.1 CONSULTANT shall compare the price bids based on the evaluation methodology and loading criteria,
if any, provided in BDS to determine the lowest evaluated bid.
35.2 Wherever BDS / BoQ permits bidder to quote prices in more than one currency, for evaluation and
comparison purposes, the currency(ies) of the Bid shall be converted into a single currency, and that will
be Indian Rupees only at the Bill selling exchange rate published by the State Bank of India, on the day
of price bid opening.
35.3 Suo moto price change: In case of any suo moto change in price, following shall apply:
After opening of Not Acceptable, Bid shall be rejected In case of suo moto price
unpriced bid without offering any opportunity to the decrease:
bidder to withdraw the same, Action 1. Tender evaluation shall be
regarding Holiday Listing may be taken. done without considering suo
EMD shall be forfeited. moto Price decrease.
2. Ordering shall be done
considering suo moto Price
decrease.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
36. CONSULTANT’S RIGHT TO ACCEPT ANY BID, AND TO REJECT ANY OR ALL BIDS
36.1 CONSULTANT / OWNER reserves the right to accept or reject any or all the bids at his discretion and
may annul the Bidding process, without thereby incurring any liability to bidders.
F. AWARD OF CONTRACT
37.1 Subject to Clause 38.1 of ITB, the OWNER shall award the Contract to the bidder who has been
determined to be the lowest evaluated bid in-line with ITB clause 35 above. However, if in the opinion of
CONSULTANT / Owner, the total price or certain item rates quoted by the recommended bidder are
considered high, CONSULTANT / Owner may invite such bidder for price negotiation. Recommended
bidder shall attend such negotiation meetings and if requested by CONSULTANT / Owner shall provide
the analysis of rates/break-up of amount quoted by him for any or all items of Schedule of Rates/ Prices
to demonstrate the reasonability. As a result of negotiation, bidder may offer rebate on his earlier quoted
Price.
38.1 Prior to the expiration of the period of bid validity, the OWNER shall notify the successful bidder, in
writing, that its bid has been accepted. The notification letter (hereinafter and in the General Conditions
of Contract called the “Letter of Acceptance (LOA)/ Fax of Acceptance (FOA)”) shall specify the sum
that the OWNER will pay the Contractor in consideration of the execution and completion of the Works.
38.2 Until a formal contract is prepared and executed, the notification of award along with this Bidding
Document together with the annexed documents, modifications, deletions agreed upon shall constitute
a binding contract between the successful bidder and the OWNER.
39.1 Promptly upon issue of LOA/ FOA, the successful bidder shall sign, the Contract Agreement on a non-
judicial stamp paper and of appropriate value. The cost of non-judicial stamp paper shall be borne by
the successful bidder.
INSTRUCTIONS TO BIDDERS
40.1 Contractor shall provide the assistance in IOCL ERP- SAP system for the execution of work, as & when
required by IOCL.
IOCL has 09 operating Refineries, namely Paradip in the state of Odisha, Guwahati Refinery in the State
of Assam, Barauni Refinery in the State of Bihar, Gujarat Refinery in the State of Gujarat, Mathura
Refinery in the State of U.P., Haldia Refinery in the State of West Bengal, Panipat Refinery in the State
of Haryana, Bongaigaon Refinery in the State of Assam & Digboi Refinery in the State of Assam.
It may please be noted that all the Refineries shown above are declared as "prohibited place" under
Official Secrets Act 1923, where entry of personnel is restricted/conditioned. It may also be noted that
the Visa to be issued by Govt. of India, normally contains the clause towards no permission for entry/visit
to such place, a default condition which if not removed/struck-off by the Visa issuing authorities will
create impediment/restriction in movement of personnel of foreign origin deployed at particular Refinery,
to carry out an activity in terms of engagement/contract with M/s. Indian Oil Corporation Limited. The
same should be kept in mind while submitting request for issue of Visa by your office.
For the benefit of the Project, it is desired that the CONTRACTOR shall maintain Project Specific Bank
Accounts, with a bank approved by the OWNER to ensure that finances released by the OWNER, line
of credit received from the lenders to meet working capital requirements and all revenues & other
receipts arising from the CONTRACT and under any agreements are deposited into such Account(s).
Withdrawals and appropriations during the Contract Period, at any relevant time, from such Account(s)
shall be made only for the purpose of Project/Project Facilities and Services.
In case after price bid opening the lowest evaluated bidder (L1) is not awarded the job for any mistake
committed by him in bidding or withdrawal of bid or varying any term in regard thereof leading to re-
tendering, OWNER shall forfeit Earnest Money paid by the bidder and such bidders shall be debarred
from participation in re-tendering of the same job(s)/ item(s).
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
44.1 Bidders are required to furnish the complete and correct information/ documents required for evaluation
of their bids. If the information/ documents forming basis of evaluation is found to be false/ fake/ forged,
the same shall be considered adequate ground for rejection of the bids and forfeiture of earnest money
deposit.
44.2 OWNER requires that the CONTRACTOR observes the highest standard of ethics during the execution
of Contract. In pursuance of this policy, OWNER defines, for the purposes of this provision, the terms
set forth below as follows:
a) “Corrupt Practice” means the offering, giving, receiving, or soliciting of anything of value to influence
the action of public official in contract execution;
c) “False/Fake” means to make or construct falsely. “Faked alibi” is a made, manufactured, or false
alibi. Something that is not what is purports to be; counterfeit, an imposter.
d) “Forgery” means the false making or the material altering of a document with the intent to defraud.
A signature of a person that is made without the person’s consent and without the person otherwise
authorizing it. A person is guilty of forgery if, with the purpose to defraud or injure anyone or with
knowledge that he is facilitating a fraud or injury to be perpetrated by anyone, the actor (i) alters any
writing of another without his authority (ii) makes, completes, authenticates, executes, issues or
transfers any writing, so that it purports to be the act of another who did not authorize that act or to
have been executed at a time or place or in a numbered sequence other than was in fact the case,
or to, be a copy of an original when no such original exists. Utters any writing which he knows to be
false in a manner specified in (i) & (ii) above.
44.3 OWNER may terminate the Contract if it discovers subsequently that the CONTRACTOR had engaged
in Corrupt Practices or Fraudulent Practices in competing for the Contract.
45.1 It will be the responsibility of the bidder to inform IOCL within 15 days from the date of order of insolvency
resolution process or liquidation or bankruptcy proceeding passed by the Adjudicating Authority namely,
National Company Law Tribunal (NCLT) or Debt Recovery Tribunal (DRT) under the Insolvency and
Bankruptcy Code.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
INSTRUCTIONS TO BIDDERS
45.2 If bidder refuses or fails to share the information regarding their status of insolvency resolution process
or liquidation or bankruptcy proceeding in their bid or at any later stage, their offer is liable to be rejected
by IOCL.
45.3 IOCL reserves the right to cancel/ terminate the contract without any liability on the part of IOCL
immediately on the commencement of insolvency resolution process or liquidation or bankruptcy
proceeding of any party under the contract.
45.4 IOCL reserves its right to evaluate and finalize the bid without considering the bid of any party
undergoing insolvency resolution process or liquidation or bankruptcy proceeding under the code
regardless of the stage of tendering.
45.5 A declaration / undertaking shall be submitted from the bidder in the Format (As per Attachment IX of
ITB) along with techno commercial bid.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT - I
INSTRUCTIONS TO BIDDERS
To,
M/s ………………………
………………………………..
………………………………..
………………………………..
Fax no:
E-mail:
Name of Work:
Dear Sir,
We hereby acknowledge receipt of a complete set of Bidding Document along with enclosures for subject
works, downloaded from website as per the Master Index for our use in preparing the Bid.
We undertake that the contents of the above Bidding Document shall be kept confidential and further that
the drawings, specifications and documents shall not be transferred and that the said documents are to be
used only for the purpose for which they are intended.
A. We intend to bid as requested for the subject works and furnish following details with respect to
our quoting office:
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT - I
INSTRUCTIONS TO BIDDERS
POSTAL ADDRESS
TELEPHONE NUMBER
TELEFAX NUMBER
CONTACT PERSON
E-MAIL ADDRESS
MOBILE NO. OF BIDDER
POSTAL ADDRESS
TELEPHONE NUMBER
TELEFAX NUMBER
CONTACT PERSON
E-MAIL ADDRESS
MOBILE NO. OF BIDDER
C. We are unable to bid for the reasons given below and we are returning the entire set of Bidding
Documents.
Reasons for non-submission of Bid
---------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------
---------------------------------------------------------------------------------------------------------
ATTACHMENT - I
INSTRUCTIONS TO BIDDERS
NOTE: Bidder is requested to furnish the details mentioned at A and B or C immediately after
receipt of Bidding Document.
ATTACHMENT-II
INSTRUCTIONS TO BIDDERS
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 1 of 1
IOCL Address & Bank Details for Bank Guarantee in lieu of Bid Security
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT-III
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 1 of 11
To,
-------------------------------------------------
---------------------------------------------
Sub: Tender no.
Dear Sir
IndianOil Corporation Limited (IOCL) hereby declares that IOCL has signed an MOU dated 18th
January 2008 with Transparency International India for the adoption of the Integrity Pact Program
and stands committed to following the principles of transparency, equity and competitiveness in
public procurement. The said MOU can be accessed at the IOCL website i.e.
http://www.iocl.com/Aboutus/DraftMOU.pdf
The subject Notice Inviting Tender (NIT) is an invitation to offer made on the condition that the
Bidder will sign the Integrity Agreement in the prescribed proforma, which is an integral part of tender
documents, failing which the tenderer/bidder will stand disqualified from the tendering process and the
bid of the bidder would be summarily rejected.
This Declaration shall form part and parcel of the Integrity Agreement and signing of the same
shall be deemed as acceptance and signing of the Integrity Agreement on behalf of the Corporation.
Yours faithfully
For and on behalf of Indian Oil Corporation Limited
( )
Chief Project Manager
Indian Oil Corporation Ltd
Project Department
Scope Complex, Core-2, 4th Floor
Lodhi Road, New Delhi- 110 003
Note: The copy of the Integrity Agreement, duly signed by the Authorized Signatory shall be provided
to the bidders on specific request.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT-III
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 2 of 11
Ref. Dated:
To,
Dear Sir,
The Bidder acknowledges that Indian Oil Corporation (IOCL) has signed the MOU with Transparency
International India for the adoption of the Integrity Pact Program and stands Committed to following the
Principles thereof as enumerated in the Integrity Agreement enclosed with the tender document.
The Bidder agrees that the Notice Inviting Tender (NIT) is an invitation to offer made on the conditions that
the Bidder will sign the enclosed Integrity Agreement, which is an integral part of the tender documents,
failing which the tenderer will stand disqualified from tendering process. The Bidder acknowledges that the
Bid would be kept open in its original form without variation or modification for a period of ______ days (state
the number of days from the last date for the receipt of tenders stated in the NIT) AND THE MAKING
OF THE BID SHALL BE REGARDED AS AN UNCONDITIONAL AND ABSOLUTE ACCEPTANCE of this
condition of NIT.
Bidder confirms acceptance and compliance with the Integrity Agreement in the letter and spirit and further
agrees that execution of the said Integrity Agreement shall be separate and distinct from the main contract,
which will come into existence when bid is finally accepted by IOCL. The Bidder acknowledges and accept
the duration of the Integrity Agreement which shall be in line with Article 8 of enclosed Agreement.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT-III
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 3 of 11
Bidder acknowledges that in the event of Bidder’s failure to sign and accept the Integrity Agreement, while
submitting the Bid, IOCL shall have unqualified, absolute and unfettered right to disqualify the tender and
reject the bid in accordance with the terms and conditions of the tender.
Yours faithfully,
(Note- One copy of this letter along with Integrity agreement duly signed must be returned along with offer)
The Integrity Pact Agreement (IPA and other IP documents) are hoisted on www.iocl.com. All the prospective
bidders willing to participate in the tenders where Integrity Pact Agreement is applicable shall have to
necessarily sign the IPA (as per the latest version as hosted on www.iocl.com ) in order to be eligible to
participate in the tender. The present version of the Integrity Pact Agreement is as below.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT-III
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 4 of 11
Preamble
AND WHEREAS the Principal/OWNER values full compliance with all relevant laws of the land, rules,
regulations, economic use of resources and of fairness/transparency in its relationship with its Bidder(s)
and Contractor(s).
AND WHEREAS, in order to achieve these goals, the Principal/OWNER has appointed Independent External
Monitors (IEM), to monitor the Tender process and the execution of the Contract for compliance with the
principles as laid down in this Agreement.
AND WHEREAS to meet the purpose aforesaid both the parties have agreed to enter into this Integrity
Agreement (hereinafter referred to as “Integrity Pact” or “Pact”), the terms and conditions of which shall also
be read as integral part and parcel of the Tender documents and Contract between the parties.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT-III
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 5 of 11
NOW, THEREFORE, in consideration of mutual covenants contained in this Pact, the parties hereby agree
as follows and this Pact witnesseth as under:
1) The Principal/OWNER commits itself to take all measures necessary to prevent corruption and to
observe the following principles:
• No employee of the Principal/ OWNER, personally or through any of his/her family members,
will, in connection with the Tender, or the execution of the Contract, demand, take a promise
for or accept, for self or third person, any material or immaterial benefit which the person is not
legally entitled to.
• The Principal/OWNER will, during the Tender process, treat all Bidder(s) with equity and
reason. The Principal/OWNER will, in particular, before and during the Tender process,
provide to all Bidder(s) the same information and will not provide to any Bidder(s) confidential
I additional information through which the Bidder(s) could obtain an advantage in relation to
the Tender process or the Contract execution.
• The Principal/OWNER shall endeavour to exclude from the Tender process any person,
whose conduct in the past has been of biased nature.
2) If the Principal/OWNER obtains information on the conduct of any of its employees which is a criminal
offence under the Indian Penal Code (IPC) /Prevention of Corruption Act, 1988 (PC Act) or is in
violation of the principles herein mentioned or if there be a substantive suspicion in this regard, the
Principal/OWNER will inform the Chief Vigilance Officer and in addition can also initiate disciplinary
actions as per its internal laid down policies and procedures.
1) The Bidder(s)/Contractor(s) commits himself to take all measures necessary to prevent corruption. He
commits himself to observe the following principles during his participation in the Tender process and
during the Contract execution:
a) The Bidder(s)/Contractor(s) will not, directly or through any other person or firm, offer, promise or give
to any of the Principal/OWNER’s employees involved in the Tender process or execution of the
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT-III
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 6 of 11
Contract or to any third person any material or other benefit which he/she is not legally entitled to, in
order to obtain in exchange any advantage of any kind whatsoever during the Tender process or
during the execution of the Contract.
b) The Bidder(s)/Contractor(s) will not enter with other Bidder(s) into any undisclosed agreement or
understanding, whether formal or informal. This applies in particular to prices, specifications,
certifications, subsidiary contracts, submission or non-submission of bids or any other actions to
restrict competitiveness or to cartelize in the bidding process.
c) The Bidder(s)/Contractor(s) will not commit any offence under the relevant IPC/PC Act. Further the
Bidder(s)/Contractor(s) will not use improperly, (for the purpose of competition or personal gain), or
pass on to others, any information or document provided by the Principal/OWNER as part of the
business relationship, regarding plans, Technical proposals and business details, including
information contained or transmitted electronically.
d) The Bidder(s)/Contractor(s) of foreign origin shall disclose the names and addresses of
agents/representatives in India, if any. Similarly, Bidder(s)/Contractor(s) of Indian Nationality shall
disclose names and addresses of foreign agents/representatives, if any. In a tender, e ither the Indian
agent on behalf of the principal/OEM or principal/OEM itself can bid but both cannot bid simultaneously
for the same item/product in the same tender. Further, if an agent submits bid on behalf of the
principal/OEM, the same agent shall not submit a bid on behalf of another principal/OEM in the same tender
for the same item/product. Copy of CVC guidelines dated 13/01/2012 is annexed hereto as Annexure-
A.
e) The Bidder(s)/Contractor(s) will, when presenting his bid, disclose (with each tender as per proforma
enclosed) any and all payments he has made, is committed to or intends to make to agents, brokers
or any other intermediaries in connection with the award of the Contract.
2) The Bidder(s)/Contractor(s) will not instigate third persons to commit offences outlined above or be
an accessory to such offences.
Article 3. Disqualification from Tender Process and exclusion from future contracts
1) If the Bidder(s)/Contractor(s), either before award or during execution of Contract has committed a
transgression through a violation of Article 2 above or in any other form, such as to put his reliability
or credibility in question, the Principal/OWNER is entitled to disqualify the Bidder(s)/Contractor(s) from
the Tender process or terminate the Contract, if already executed or exclude the Bidder/ Contractor
from future contract award processes. The imposition and duration of the exclusion will be
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT-III
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 7 of 11
determined by the severity of transgression and determined by the Principal/OWNER. Such exclusion
may be for a period of 1 year to 3 years as per the procedure prescribed in the guidelines for holiday
listing of the Principal/OWNER.
2) The Bidder/ Contractor accepts and undertakes to respect and uphold the Principal/OWNER’s absolute
right to resort to and impose such exclusion.
3) Apart from the above, the Principal/OWNER may take action for banning of business dealings/holiday
listing of the Bidder/Contractor as deemed fit by the Principal/OWNER.
Without prejudice to any rights that may be available to the Principal/OWNER under law or the Contract
or its established policies and laid down procedures, the Principal/OWNER shall have the following
rights in case of breach of this Integrity Pact by the Bidder(/Contractor(s):
1) Forfeiture of EMD/Security Deposit: If the Principal/OWNER has disqualified the Bidder(s) from the
Tender process prior to the award of the Contract or terminated the Contract or has accrued the right
to terminate the Contract according to Article 3, the Principal/OWNER apart from exercising any legal
rights that may have accrued to the Principal/OWNER, may in its considered opinion forfeit the Earnest
Money Deposit/ Bid-Security amount of the Bidder/Contractor.
1) The Bidder declares that no previous transgressions occurred in the last 3 years with any other
Company in any country confirming to the anti-corruption approach or with any other Public Sector
Enterprise in India that could justify his exclusion from the Tender process.
2) If the Bidder makes incorrect statement on this subject, he can be disqualified from the Tender
process or action can be taken for banning of business dealings/ holiday listing of the Bidder/
Contractor as deemed fit by the Principal/ OWNER.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT-III
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 8 of 11
3) If the Bidder/Contractor can prove that he has resorted \recouped the damage caused by him and
has installed a suitable corruption prevention system, the Principal/OWNER may, at its own discretion
as per laid down organizational procedures, revoke the exclusion prematurely.
2) The Principal/OWNER will enter into Pacts on identical terms as this one with all Bidders and
Contractors.
3) The Principal/OWNER will disqualify Bidders, who do not submit, the duly signed Pact between the
Principal/OWNER and the bidder, along with the Tender or violate its provisions at any stage of the
Tender process, from the Tender process.
1) The Principal/OWNER has appointed competent and credible Independent External Monitor(s) (IEM)
for this Pact. The task of the Monitor is to review independently and objectivel y, whether and to what
extent the parties comply with the obligations under this Pact.
2) The IEM is not subject to instructions by the representatives of the parties and performs his functions
neutrally and independently. He reports to the Chairman, Indian Oil Corporation Limited.
3) The Bidder(s)/Contractor(s) accepts that the IEM has the right to access, without restriction, to all
Project documentation of the Principal/OWNER including that provided by the Contractor. The
Contractor will also grant the IEM, upon his request and demonstration of a valid interest, unrestricted
and unconditional access to his or any of his Sub-Contractor’s project documentation. The IEM is
under contractual obligation to treat the information and documents of the
Bidder(s)/Contractor(s)/Subcontractor(s) with confidentiality.
4) In case of tenders having estimated value of Rs 150 Crores or more, the Principal/OWNER will provide
to the IEM sufficient information about all the meetings among the parties related to the Project and
shall keep the IEM apprised of all the developments in the Tender Process.
5) As soon as the IEM notices, or believes to notice, a violation of this Pact, he will so inform the
Management of the Principal/OWNER and request the Management to discontinue or take corrective
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT-III
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 9 of 11
action, or to take other relevant action. The IEM can in this regard submit non-binding
recommendations. Beyond this, the IEM has no right to demand from the parties that they act in a
specific manner, refrain from action or tolerate action.
6) The IEM will submit a written report to the Chairman, Indian Oil Corporation Limited within 6 to 8
weeks from the date of reference or intimation to him by the Principal/OWNER and, should the
occasion arise, submit proposals for correcting problematic situations.
7) If the IEM has reported to the Chairman, Indian Oil Corporation Limited a substantiated suspicion of
an offence under the relevant IPC/PC Act, and the Chairman, IOCL has not, within reasonable time
taken visible action to proceed against such offence or reported it to the Chief Vigilance Officer, the
IEM may also transmit the information directly to the Central Vigilance Commissioner.
8) The word “IEM” would include both singular and plural.
Article 8- Duration of the Pact
This Pact begins when both the parties have legally signed it. It expires for the Contractor/Vendor 12
months after the completion of work under the Contract or till the continuation of defect liability period,
whichever is more and for all other Bidders, till the Contract has been awarded.
If any claim is made/lodged during the time, the same shall be binding and continue to be valid
despite the lapse of this Pact as specified above, unless it is discharged/determined by the Chairman,
IOCL.
Article 9-Other Provisions
1) This Pact is subject to Indian law, place of performance and jurisdiction is the Head
Office/Headquarters of the Division of the Principal/OWNER, who has floated the Tender.
2) Changes and supplements need to be made in writing. Side agreements have not been made.
3) If the Contractor is a partnership or a consortium, this Pact must be signed by all the partners and
consortium members. In case of a Company, the Pact must be signed by a representative duly
authorized by board resolution.
4) Should one or several provisions of this Pact turn out to be invalid, the remainder of this Pact remains
valid. In this case, the parties will strive to come to an agreement to their original intentions.
5) Any dispute or difference arising between the parties with regard to the terms of this Agreement/Pact,
any action taken by the OWNER/Principal in accordance with this Agreement/ Pact or interpretation
thereof shall not be subject to arbitration.
All rights and remedies of the parties hereto shall be in addition to all the other legal rights and
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT-III
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 10 of 11
remedies belonging to such parties under the Contract and/or law and the same shall be deemed to
be cumulative and not alternative to such legal rights and remedies aforesaid. For the sake of brevity,
both the Parties agree that this Pact will have precedence over the Tender/Contract documents with
regard any of the provisions covered under this Pact.
IN WITNESS WHEREOF the parties have signed and executed this Pact at the place and date first
above mentioned in the presence of following witnesses:
WITNESSES:
Note: In case of Purchase Orders wherein formal agreements are not signed references
to witnesses may be deleted from the last part of the Agreement.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT-IV
INSTRUCTIONS TO BIDDERS
3. That the document(s) submitted as mentioned above, by M/s……… along with the Bid document
for meeting the Bidder Qualification Criteria there under, vide covering letter no…. dated…..
towards Tender No …… for…………………are authentic, genuine, copy of their originals and
have been issued by the issuing authority mentioned above and no part of the document(s) is
false, forged or fabricated.
4. That no part of this affidavit is false and that this affidavit and the above declaration in
respect of genuineness of the documents has been made having full knowledge of (i) the
provisions of the Indian Penal Code in respect of offences including, but not limited to those
pertaining to criminal breach of trust, cheating and fraud and (ii) provisions of bidding conditions
which entitle the IOCL/Technip to initiate action in the event of such declaration turning out to be
a misrepresentation or false representation.
5. I depose accordingly.
DEPONENT
VERIFICATION
I, ………………………. the deponent above named do hereby verify that the factual contents of this
affidavit are true and correct. No part of it is false and nothing material has been concealed there
from.
Verified at ……………. on this………….day of……………………….20…
DEPONENT
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT-V
INSTRUCTIONS TO BIDDERS
Signature
Name & Designation (CEO or CFO or Company Secretary)
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT-VI
INSTRUCTIONS TO BIDDERS
Tender No : …………………………………
(i) I/We am/are not undergoing insolvency resolution process or liquidation or bankruptcy
proceeding as on date.
(ii) I/We am/are undergoing insolvency resolution process or liquidation or bankruptcy proceeding
as on date as per details mentioned below. (Attached detail with technical bid)
It is understood that if this declaration is found to be false, Indian Oil Corporation Ltd. shall have the right to
reject my/our bid, and forfeit the EMD. If the bid has resulted in a contract, the contract will be liable for
termination without prejudice to any other right or remedy (including black listing or holiday listing)
available to Indian Oil Corporation Ltd.
Bidder shall have positive Net worth. To establish the same, bidder shall furnish the latest Audited Financial
Statement including Auditors reports, Audited Balance Sheet, Profit & Loss Account, notes, Annexures (if
any) etc.
Net-worth Calculation:
The net worth means paid up share capital, share application money pending allotment* and reserve # less
accumulate losses and deferred expenditure to the extent not written off.
# Reserves to be considered for the purpose of net-worth shall be all reserves created out of the
profits and securities premium account but shall not include reserves created out of revaluation of
assets, write back of depreciation and amalgamation.
*Share application money pending allotment will be considered only in respect of share to be
allotted.
Accordingly, the definition of net worth shall be as follows:
Paid up share capital XXXX
Add: Share Application Money pending allotment XXXX
Add: Reserves (As defined Above) XXXX
Less: Accumulated Losses XXXX
Less: Deferred Revenue Expenditure to the extent not written off XXXX
Networth XXXX
Notes:
1. Any of the following documents shall be furnished by the bidder in support of Net Worth calculations above:
(a) Audited published Annual Report OR
(b) Audited Balance Sheet and Profit and Loss Statement OR
(c) Financial statements duly certified by practicing Chartered Accountant (not being an employee or a
Director and not having any interest in the bidder’s company) where audited accounts are not mandatory as
per law.
2. In case the financial year closing date is within 9 months of bid due date and audited annual report of
immediate preceding financial year is not available, bidder has the option to submit the financial details of the
three previous years immediately prior to the last financial year. Otherwise, it is compulsory to submit the
financial details of the immediate three preceding financial years.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT-VII
INSTRUCTIONS TO BIDDERS
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 2 of 2
Example, In case, audited annual report of immediate preceding financial year (year ending 31st March) is not
available and where bid closing date is up to 31st December, the financial details of the three previous years
immediately prior to the last financial year may be submitted. However, in case the bid closing date is after
31st December, it is compulsory to submit the financial details of the immediate three preceding financial years
only.
3. In case a bidder (Parent Company) is having wholly owned subsidiaries but only a single consolidated
annual report is prepared and audited, which includes the financial details of their
wholly owned subsidiaries, consolidated audited annual report shall be considered for establishing the
financial criteria subject to statutory auditor of the bidder certifying that separate annual report of bidder
(without the financial data of subsidiaries) is not prepared and audited.
4. Further, in case a bidder is a subsidiary company and separate annual report of the bidder is not
prepared and audited, but only a consolidated annual report of the Parent Company is available, consolidated
audited annual report shall be considered for establishing the financial criteria
subject to statutory auditor of the parent company certifying that separate annual report of bidder
is not prepared and audited
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT - VIII
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 1 of 3
OR
Financial details of the above mentioned Company, as per latest available audited balance sheet are as
follows: Auditor/CA to select either of the following options and strike off the other.
a. In case bidder is a parent company, i.e., having its wholly owned subsidiaries: Auditor to select either of
the following options and strike off the other.
i. Financial details are of parent company without the financial data of subsidiaries
ii. Financial details are of parent company including the financial data of subsidiaries. It is certified
that separate annual report of bidder, without the financial data of subsidiaries, is not prepared
and audited.
OR
b. In case bidder is a subsidiary company: Auditor to select either of the following options and strike off
the other.
OR
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT - VIII
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 2 of 3
c. In case bidder does not have any subsidiary or parent company, Financial details of are of the
company itself.
Sr.No Description Year Value Currency
(_______________)
1 Turnover Latest Financial Year
(________________)
Preceding 1st Year
(________________)
Preceding 2nd Year
(________________)
2 Networth Latest Financial Year (*)
(________________)
Example, In case, audited annual report of immediate preceding financial year (year ending 31st
March) is not available and where bid closing is up to 31st December, the financial details of the
three previous years immediately prior to the last financial year may be submitted. However, in case
the bid closing date is after 31st December, it is compulsory to submit the financial details of the
immediate three preceding financial years only.
2. In case a bidder (Parent Company) is having wholly owned subsidiaries but only a single
consolidated annual report is prepared and audited, which includes the financial details of their
wholly owned subsidiaries, consolidated audited annual report shall be considered for establishing
the financial criteria subject to statutory auditor of the bidder certifying that separate annual report
of bidder (without the financial data of subsidiaries) is not prepared and audited.
3. Further, in case a bidder is a subsidiary company and separate annual report of the bidder is not
prepared and audited, but only a consolidated annual report of the Parent company is available,
consolidated annual report shall be considered for establishing the financial criteria subject to
statutory auditor of the parent company certifying that separate annual report of bidder is not
prepared and audited.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT - VIII
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 3 of 3
4. Networth Calculation: Networth means paid up share capital, Share Application Money pending
allotment* and reserves # less accumulated losses and deferred expenditure to the extent not written
off. Networth has been calculated using the following formula, as per provisions of the enquiry
document:
# Reserves to be considered for the purpose of networth shall be all reserves created out of the
profits and securities premium account but shall not include reserves created out of revaluation of
assets, write back of depreciation and amalgamation.
*Share Application Money pending allotment will be considered only in respect of share to be allotted.
5. Turnover: Turnover shall be calculated including Excise Duty but excluding other incomes.
6. Networth and Turnover has been calculated using the above mentioned formulae and after giving
effect to the impact of Audit Qualifications given in the Audit Report.
Signature
ANNEXURE - IX
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 1 of 3
OR
We, M/s ________________________________, having our registered office at
_________________________________ certify that statutory auditor is not mandatory for the Company as
per prevailing law and M/s _______________, a CA firm having their registered address
______________________________ having certificate number ___________ are practicing chartered
Accountant, not being an employee or a Director or not having any interest in our Company.
Financial details of our Company, as per latest available audited balance sheet are as follows: Company to
select either of the following options and strike off the other.
a. In case bidder is a parent company, i.e., having its wholly owned subsidiaries: Company to select either
of the following options and strike off the other.
i. Financial details are of parent company without the financial data of subsidiaries
ii. Financial details are of parent company including the financial data of subsidiaries. It is certified
that separate annual report of bidder, without the financial data of subsidiaries, is not prepared
and audited.
OR
b. In case bidder is a subsidiary company: Auditor to select either of the following options and strike off
the other.
i. Financial details are of subsidiary Company
ii. Financial details are of Parent Company including the financial data of subsidiaries. It is
certified that separate annual report of bidder, i.e., subsidiary, is not prepared and audited.
OR
c. In case bidder does not have any subsidiary or parent company, Financial details of are of the
company itself.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE - IX
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 2 of 3
Note:
1. In case the financial year closing date is within 9 months of bid due date and audited annual report
of immediate preceding financial year is not available, bidder has the option to submit the financial
details of the three previous year immediately prior to the last financial year. Otherwise, it is
compulsory to submit the financial details of the immediate three preceding financial years.
Example, In case, audited annual report of immediate preceding financial year (year ending 31st
March) is not available and where bid closing is up to 31st December, the financial details of the
three previous years immediately prior to the last financial year may be submitted. However, in case
the bid closing date is after 31st December, it is compulsory to submit the financial details of the
immediate three preceding financial years only.
2. In case a bidder (Parent Company) is having wholly owned subsidiaries but only a single consolidated
annual report is prepared and audited, which includes the financial details of their wholly owned
subsidiaries, consolidated audited annual report shall be considered for establishing the financial
criteria subject to statutory auditor of the bidder certifying that separate annual report of bidder
(without the financial data of subsidiaries) is not prepared and audited.
3. Further, in case a bidder is a subsidiary company and separate annual report of the bidder is not
prepared and audited, but only a consolidated annual report of the Parent company is available,
consolidated annual report shall be considered for establishing the financial criteria subject to
statutory auditor of the parent company certifying that separate annual report of bidder is not prepared
and audited.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE - IX
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 3 of 3
4. Networth Calculation: Networth means paid up share capital, Share Application Money pending
allotment* and reserves # less accumulated losses and deferred expenditure to the extent not written
off. Networth has been calculated using the following formula, as per provisions of the enquiry
document:
# Reserves to be considered for the purpose of networth shall be all reserves created out of the
profits and securities premium account but shall not include reserves created out of revaluation of
assets, write back of depreciation and amalgamation.
*Share Application Money pending allotment will be considered only in respect of share to be allotted.
5. Turnover: Turnover shall be calculated including Excise Duty but excluding other incomes.
6. Networth and Turnover has been calculated using the above mentioned formulae and after giving
effect to the impact of Audit Qualifications given in the Audit Report.
Signature
Name and Designation
ATTACHMENT - X
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 1 of 3
a. In case bidder is a parent company, i.e., having its wholly owned subsidiaries: Company to select
either of the following options and strike off the other.
i. Financial details are of parent company without the financial data of subsidiaries
ii. Financial details are of parent company including the financial data of subsidiaries. It is certified that
separate annual report of bidder, without the financial data of subsidiaries, is not prepared and
audited.
OR
b. In case bidder is a subsidiary company: Auditor to select either of the following options and strike off
the other.
i. Financial details are of subsidiary Company
ii. Financial details are of Parent Company including the financial data of subsidiaries. It is certified that
separate annual report of bidder, i.e., subsidiary, is not prepared and audited.
OR
c. In case bidder does not have any subsidiary or parent company, Financial details of are of the
company itself.
Sr.No Description Year Value Currency
(_______________)
1 Turnover Latest Financial Year
(________________)
Preceding 1st Year
(________________)
Preceding 2nd Year
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT - X
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 2 of 3
(________________)
2 Networth Latest Financial Year (*)
(________________)
Example, In case, audited annual report of immediate preceding financial year (year ending 31st
March) is not available and where bid closing is up to 31st December, the financial details of the three
previous years immediately prior to the last financial year may be submitted. However, in case the
bid closing date is after 31st December, it is compulsory to submit the financial details of the
immediate three preceding financial years only.
2. In case a bidder (Parent Company) is having wholly owned subsidiaries but only a single consolidated
annual report is prepared and audited, which includes the financial details of their wholly owned
subsidiaries, consolidated audited annual report shall be considered for establishing the financial
criteria subject to statutory auditor of the bidder certifying that separate annual report of bidder
(without the financial data of subsidiaries) is not prepared and audited.
3. Further, in case a bidder is a subsidiary company and separate annual report of the bidder is not
prepared and audited, but only a consolidated annual report of the Parent company is available,
consolidated annual report shall be considered for establishing the financial criteria subject to
statutory auditor of the parent company certifying that separate annual report of bidder is not prepared
and audited.
4. Networth Calculation: Networth means paid up share capital, Share Application Money pending
allotment* and reserves # less accumulated losses and deferred expenditure to the extent not written
off. Networth has been calculated using the following formula, as per provisions of the enquiry
document:
# Reserves to be considered for the purpose of networth shall be all reserves created out of the profits
and securities premium account but shall not include reserves created out of revaluation of assets,
write back of depreciation and amalgamation.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ATTACHMENT - X
TO
INSTRUCTIONS TO BIDDER
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 3 of 3
*Share Application Money pending allotment will be considered only in respect of share to be allotted.
5. Turnover: Turnover shall be calculated including Excise Duty but excluding other incomes.
6. Networth and Turnover has been calculated using the above mentioned formulae and after giving
effect to the impact of Audit Qualifications given in the Audit Report.
Signature
Name and Designation
3. ITB 3.1 & 3.3 Enquiry Basis is: Domestic Competitive Bidding
4. ITB 3.2 & 19.14 Consortium/Joint Venture (JV) Bids are not acceptable as per NIT.
5. ITB 5.2 i. Last date for submission of pre-bid queries: as per NIT.
ii. The pre-bid meeting is scheduled as following:
Schedule: As per NIT
Venue: As per NIT
6. ITB 5.2, 10.2 The detail of Contact Persons for any query/clarification/ communication/Postal
address:
8. ITB 10, 19.1, The last Date and time of submission of Bids & Bid Security shall be AS
25.0 MENTIONED IN NIT.
URL for e-tendering portal is https://iocletenders.nic.in.
12. ITB 18 The offer of the Bidder shall remain valid for 06 (Six) months from the last
date of submission of Tender / Revised offer (if applicable as permitted by
the Owner). On account of exigencies if bidders are asked to extend their validity
the same should be without any deviation including change in the prices.
13. ITB 32 Purchase preference as admissible under the prevailing procurement policy for
MSEs is not applicable to this tender.
14. ITB 34,35 The evaluation and comparison of bids shall be carried out as per following:
VI. 2 Years O&M spares quoted in FORM SP-6 shall not be considered for
evaluation.
FORM-A
FORM OF BID
(TO BE GIVEN ON BIDDER’S LETTER HEAD)
Ref: Date:
From:
To
Indian Oil Corporation Ltd.
(Refineries Division)
Project Department
New Delhi.
Dear Sirs,
Having examined the Bidding Documents consisting of the Invitation for Bid, Instructions to Bidders, General
Conditions of Contract, Special Conditions of Contract, Specifications, Technical requirements, Time Schedule,
Form of Contract, Form of Bid, Price Schedule and Amendment(s) to the Bidding Documents (if any), and
having understood the provisions of the said Bidding Documents and having thoroughly studied the
requirements of Indian Oil Corporation Ltd. relative to the work for in connection with the LUPECH POWER
DISTRIBUTION FACILITY FOR PETROCHEMICAL AND LUBE INTEGRATION PROJECT “LUPECH” (J-
18) PROJECT AT IOCL GUJARAT REFINERY, INDIA and having conducted a thorough study of the job site(s)
involved, the site conditions, soil conditions, the climatic conditions, labour, power, water, material and
equipment availability, the transport, communication facilities and access to site, the availability and suitability
of borrowed earth areas, the availability of land and/or premises for temporary office and accommodation
quarters and all other factors and facilities and things whatsoever necessary or relevant to the formulation of
the Bid and the performance of Work, I/we hereby submit our bid/offer for the performance of the proposed
services and supplies in accordance with the terms and conditions and within the time mentioned in the Bidding
Documents at the lumpsum price quoted by me/us in the Price Schedule(s) included within the Bidding
Documents and arrived at by adding the Price of Materials/Supplies and the Price of Services & Site works as
per the Price Schedule. If the Work is awarded to me/us, I/we undertake to perform the Work and make the
supplies in accordance with the Contract Documents as defined in the Form of Contract forming part of the
Bidding Documents and accept the terms and conditions of Contract as laid down therein and undertake within
30 (Thirty) days of receipt of the Letter/FAX of Acceptance to deposit with the Chief Finance Manager, Indian
Oil Corporation Ltd. (Refineries Division) a sum equivalent to 3% (Three percent) of the Lumpsum price as
specified in the Letter of Acceptance by way of Bank Guarantee from a Scheduled Bank in India (which includes
Indian Branch of a foreign Bank), and to commence work at the job site(s) involved within 60 (Sixty) days from
the Acceptance of Bid, and to sign the formal Contract in terms of the Form of Contract forming part of the
Bidding Documents within 15 (Fifteen) days of receipt of the Letter of Acceptance from or on behalf of Indian
Oil Corporation Ltd., failing which Indian Oil Corporation Ltd. shall be at liberty, without further reference to
me/us and without prejudice to any of its other rights or remedies, to terminate the Contract.
I/ We further undertake to keep my/this Bid/offer open for a period of not less than 6 (six) months from the date
of opening of bids specified in the Instruction to Bidders forming part of the Bidding Documents.
I/We hereby further state that I/We/None of us (in the case of partnership firm) was/were employed as Directors
of Indian Oil Corporation Ltd. during the period of 2 (Two) years immediately preceding the date hereof OR
I/We hereby declare that I Shri………………. one of our partners (in the case of partnership firm) was employed
as a director in Indian Oil Corporation Ltd., during the period of 2 (Two) years immediately preceding the date
hereof and that Shri ……………………. OR I/We has/have obtained previous permission of Indian Oil
Corporation Ltd. to make this Bid. I/We hereby declare that Shri ……………… one of directors was employed
as a director of Indian oil Corporation Ltd. during a period of 2 (Two) years immediately preceding the date
hereof and that Shri ……………. /I/We has / have obtained previous permission of Indian Oil Corporation Ltd.
to make this Bid.
(i) Original Power of Attorney or other proof of authority of the person who has signed the Bid or Copy of
Power of Attorney or other authority duly certified by a Notary Public in proof of authority of the person
who has signed the Bid:
(ii) Information Regarding Bidder in the form annexed to the Form of Bid.
(iii) Table of Contents (Master Index) of the Bidding documents including all
AMENDMENTS/ADDENDUMS issued till the due date for submission of Bid, duly signed as a token of
receipt of the complete set of the Bidding Document.
(iv) Additional documents as listed below:
………………………………………………………………………………..
………………………………………………………………………………..
………………………………………………………………………………..
I/We hereby undertake that the statements made herein and the information given in the Annexures referred to
above are true in all respects and that in the event of any such statement or information being found to be
incorrect in any particular the same may be construed to be a misrepresentation entitling Indian Oil Corporation
Ltd. to avoid or terminate any resultant Contract.
I/We further undertake as and when called upon by Indian Oil Corporation Ltd. to produce for its inspection,
original(s) of the documents(s) of which copies have been annexed hereto.
Yours faithfully,
(Signature(s) of the Bidder(s))
Name & Designation of authorized person signing the Bid on behalf of the Bidder(s)
Full Name and address of the Bidder(s)
ATTACHMENT-I TO FORM-A
(To be furnished with the Bid separately for each consortium member in case of bids on consortium basis)
1. In Case of Individuals.
2. In case of Partnership.
(Note: In case of Consortium bid, these details shall be provided for each member of consortium)
ATTACHMENT 1 FOR FORM B
FORM-B
INFORMATION ABOUT BIDDER
(OTHER DETAILS)
To
Technip India Limited
For
Indian Oil Corporation Limited
LIST OF DIRECTORS
We, …………………. [Name of the Bidder] hereby represent that we have gone through and
understood the Bidding Documents (including but not limited to) the Commercial & Technical
Requirements/ Specifications in the entire Bidding Document and that our Bid has been prepared
accordingly in compliance with the requirements stipulated in the said documents.
We are submitting the Table of Contents of Bidding Documents and amendments, if any, as part of our
Bid duly signed and stamped on each page in token of our acceptance. We are not submitting the total
Bidding Document as part of our Bid but undertake that said Bidding Documents consists of Part-I –
Techno Commercial, Part-II – Price Part, Part III - Technical and addendums/amendments, if any, shall
be deemed to form part of our bid and in the event of award of work to us, all the parts shall be
considered for constitution of Contract Agreement. Further, we shall sign and stamp each page of these
documents as a token of Acceptance and as a part of the Contract in the event of award of Contract to
us.
_____________________________
(NAME OF BIDDER)
PLACE: ______________
DATE: ______________
NOTE: This declaration should be signed by the Bidder’s representative who is signing the Bid
FORM– D
We * hereby agree to fully comply with, abide by and accept without variation, deviation or
reservation all technical, commercial and other conditions whatsoever of the tender documents of
Tender no.___________ and all Addenda issued by Technip India Limited on behalf Indian Oil
Corporation Ltd.
We further hereby waive, withdraw and abandon any and all deviations, variations, objections or
reservations whatsoever thereto here to-before set out, given or indicated in our offer, clarifications,
correspondence, communications, or otherwise with a view that the price bid submitted may be treated
to conform in all respects, with the terms and conditions of the said tender documents including all
Addenda.
We further hereby confirm that the price quoted in the price bid are as per the provisions of the tender
document and there is no deviation to the provisions in the price bid.
**
We confirm that during detailed engineering, we will review and recommend the required Special tools
& tackles and Commissioning spares, wherever specified in the enquiry document and supply the same
without any additional cost and time implication to Purchaser.
We further hereby waive, withdraw and abandon any and all assumptions, deviations, variations,
objections or reservations whatsoever hereto set out, given or indicated in our offer, clarifications,
correspondence, communications, or otherwise with a view that the price bid and price implication (if
any) submitted may be treated to conform to, in all respects, with the terms and conditions of the said
Bidding Document including all Technical and Commercial Amendments.
**
For and on behalf of
Authorised signatory
** The bid compliance letter must be signed by the person (s) authorized to sign.
FORM–F
SELF DECLARATION
Bidder’s declaration as furnished in the declaration here shall supersede the stipulations mentioned
elsewhere in their bid.
I hereby declare that neither I in my personal name or in the name of my proprietary concern M/s
_____________________ which is submitting the accompanying Bid/ Tender nor any other
concern in which I am proprietor nor any partnership firm in which I am involved as a Partner, are
presently or have during the last three years, been placed on any blacklist or holiday list declared by
Indian Oil Corporation Limited or by any department of any Government (State, Provincial, Federal or
Central) or by any Public Sector Organization in India or in any other country nor is there pending any
inquiry by Indian Oil Corporation Ltd. Or any Department of the Government or by any Public Sector
Organization in India or in any other country, in respect of any corrupt or fraudulent practice(s) against
me or any other of my proprietorship concern(s) or against any partnership firm(s) in which I am or was
at the relevant time involved as a partner, except as indicated below:
(Here given particulars of blacklisting or holiday listing, and /or inquiry and in absence thereof state
“NIL”)
I hereby further declare that none of the contracts, supplies, jobs, works or services with respect to
which I or my proprietary concern or any partnership firm in which I am a partner claims qualification
under the accompanying bid/tender has at any time been the subject of any contract, supply, job, work
or service for or in relation to which an order of black-listing or holiday listing has at any time been
made.
In the case of a Partnership Firm:
We hereby declare that neither we, M/s _____________________ submitting the accompanying Bid/
Tender nor any partner involved in the said firm either in his individual capacity or as proprietor or
partner of any other firm or concern presently are or within the past three years have been or has been
on any blacklist or holiday list declared by Indian Oil Corporation Limited Or by any department of
Government (State, Provincial, Federal or Central) or by any Public Sector Organization in India or in
any other country nor is there any pending inquiry by Indian Oil Corporation Ltd. Or by any Department
of any Government (State, Provincial, Federal or Central) or by any Public Sector Organization in India
or in any other country, in respect of any corrupt or fraudulent practice(s) against us or any partner or
any other concern or firm of which he is proprietor or partner, except as indicated below:
(Here given particulars of blacklisting or holiday listing, and /or inquiry and in absence thereof state
“NIL”)
We hereby further declare that none of the contracts, supplies, jobs, works or services on the basis of
which our aforesaid firm submitting the accompanying bid claims qualification under the accompanying
bid/tender has been the subject of any contract, supply, job, work or service for or in relation to which
an order of black-listing or holiday listing has at any time been made.
In the case of Company
We hereby declare that neither we or a parent, subsidiary or other company under direct or indirect
common parent (associate company) are presently nor have within the past three years been placed
on any holiday list or blacklist declared by Indian Oil Corporation Limited Or by any Department of any
Government (State, Provincial, Federal or Central) or by any Public Sector Organization in India or in
any other country; and that there is no pending inquiry by Indian Oil Corporation Limited or by any
Department of any Government (State, Provincial, Federal or Central) or by any Public Sector
Organization in any country against us or a parent or subsidiary or associate company as aforesaid in
India or in any other country, in respect of corrupt or fraudulent practice(s), except as indicated below:
(Here given particulars of blacklisting or holiday listing and/or inquiry and in absence thereof state “NIL”)
We hereby further declare that none of the contracts, supplies, jobs, works or services on the basis of
which we claim qualification under the accompanying bid/tender has been the subject of any contract,
supply, job, work or service for or in relation to which an order of black-listing or holiday listing has at
any time been made.
It is understood that if this declaration is found to be false in any particular, Indian Oil Corporations Ltd.
shall have the right to reject my/ our bid, and if the bid has resulted in a contract, the contract is liable
to be terminated without prejudice to any other right or remedy (including black listing or holiday listing)
available to Indian Oil Corporation Limited.
Note:
(i) The bidder shall indicate/disclose also the job/work/contract with respect to which the bidder
has been blacklisted/ placed on the holiday list, and the reasons for such blacklisting/holiday
listing as disclosed in the show-cause notice.
(ii) Except as indicated in the Instructions to Bidders, the above declaration is for information
purpose only.
FORM–H
Name of Work:
b) Neither we nor any of our nominated sub-contractor(s) are engaging Child Labour in any of our
work(s) in terms of the provisions of The Child Labour (Prohibition and Regulation) Act, 1986
and other applicable laws.
c) We as well as our nominated sub-contractor(s) undertake to fully comply with provisions of The
Child Labour (Prohibition and Regulation) Act, 1986 and other applicable labour laws, in case
the work is awarded to us.
d) It is understood that if I/We, either before award or during execution of Contract, commit a
transgression through a violation of Article b /c above or in any other form, such as to put my/our
reliability or credibility in question, the Owner is entitled to disqualify us from the Tender process
or terminate the Contract, if already executed or exclude me / us from future contract award
processes. The imposition and duration of the exclusion will be determined by the severity of
transgression and determined by the Owner. Such exclusion may be for a period of 1 year to 3
years as per the procedure prescribed in the guidelines for holiday listing of the Owner.
e) I/We accept and undertake to respect and uphold the Owner's absolute right to resort to and
impose such exclusion.
NOTE:
1. The Pre-Bid Queries may be sent by e-mail to concern persons, the details of which is provided in
BDS.
2. Also send the editable native file (in excel format) through email.
Bidder’s reply/ confirmation as furnished in the Commercial Questionnaire (CQ) shall supersede the
stipulations mentioned elsewhere in their bid.
2.0 Confirm that Earnest Money Deposit (EMD) as per bid stipulations have
been furnished along with bid.
3.0 Confirm that the following documents are submitted with Part-I : (Part I – as
per our Master Index)
a) All documents as per CHECKLIST.
b) Master Index as enclosed with Bidding Document is submitted in unpriced
part duly signed and stamped on each page.
c) Copy of Addendum/ Amendments as a token of acceptance (Applicable, if
issued).
4.0 Confirm that price has been submitted in the e-tender portal as per the
manner stated in the ITB.
5.0 Schedule of Rates / Price
a) Price must be filled in the BOQ uploaded in the e-tender portal in excel.
Please note that the format is not to be edited / altered by the bidder.
b) Confirm that rate/ price has been quoted for all items of SOR.
c) Confirm that deviation/ terms & conditions are not mentioned in the price
part. In case any terms and condition is mentioned in the price part, the
same shall be treated as null and void.
6.0 Confirm that you have studied complete Bidding Document including
Technical and Commercial part and your Bid is in accordance with the
requirements of the Bidding Document.
7.0 Confirm your compliance to total Scope of Work mentioned in the Bidding
Document.
8.0 Confirm your acceptance for `Scope of Supply' mentioned in the Bidding
Document and confirm that all materials shall be supplied as per Standards
and Specification.
9.0 Confirm your acceptance for Time Schedule as mentioned in Bidding
Document.
SL. BIDDER'S REPLY/
TECHNIP’S QUERY
NO. CONFIRMATION
10.0 Confirm that in your quoted price taxes & duties have been considered in
accordance with the provision of General Conditions of Contract (GCC) and
Special Conditions of Contract (SCC).
11.0 Confirm that your quoted price includes all types of insurance as per the
provisions of GCC and SCC.
12.0 Confirm that all costs resulting from safe execution of Work, such as safety
practices, use of protective clothing, safety glasses and helmet, safety
precaution taken during monsoon, or any other safety measures to be
undertaken by the Contractor for execution of work are included in the
quoted rates/ price.
13.0 Confirm that you have your own QA/ QC programme for executing this work.
In case of award of work, you will submit all QA/QC documents as per
ITB/Bidding documents.
14.0 Confirm that you have uploaded the Bid on e-tender portal as per the
instructions given in ITB.
15.0 Confirm that None of the Directors of BIDDER is a relative of any Director of
Owner or the BIDDER is a firm in which any Director of Owner or his relative
is a Partner or the BIDDER is a private company in which none of director
of Owner is a member or Director.
16.0 Bidder to confirm whether they require the interest bearing Mobilisation
Advance as per Special Conditions of Contract. YES
In case the bidder does not indicate the requirement of Mobilisation, it shall NO
be presumed that the bidder does not require the Mobilisation Advance and
their offer shall be evaluated accordingly. (Tick, as applicable)
Notes:
1. Bidder shall furnish the experience details as above of Projects which the bidder considers suitable for
their pre-qualification. OWNER/PMC reserve the right not to evaluate any other Project/details
2. Bidder to note that BQC form shall be filled as per the proformas as stated along with the copies of
work order and completion certificates.
3. Bidder to note that non-submission of relevant supporting documents may lead to rejection of their PQ
bid. It is to be ensured that all relevant supporting documents shall be submitted along with the PQ bid
in the first instance itself. Pre-qualification may be completed based on the details so furnished without
seeking any subsequent additional information.
FORM_K-2 FINANCIAL DETAILS
A. AUDITED ANNUAL TURNOVER REPORTS FOR LAST 3 YEARS
A.1
COMPANY ANNUAL PROFIT NET PROFIT – NET WORTH * Exchange
TURNOVER INR or US $ AFTER TAX, (US$/INR) rate
(US$/INR) INTEREST & considered (if
DEPRECIATION any currency
(US$/INR) other than
US$)
Year 1
Year 2
Year 3
# Profit after Tax (PAT) + depreciation + other expenses which do not result in cash outflow can be
treated as cash accruals
FORM-L
BANK MANDATE FORM
(For Indian Bidder)
1. Bidder Name :
2. Bidder Code :
3. Address of the Bidder :
4. Particulars of Bank Account of Bidder
a. Name of the Bank :
b. Name of the Branch and Address of the Branch :
c. Branch Code:
d. 9-Digit MICR code Number of the Bank & Branch
(As appearing in the MICR Cheque issued by
the bank) (Please do not give multicity cheque book
code Number)
e. Type of account (Saving Bank, Current or Cash Credit):
f. Account Number :
g. RGTS/IFSC Code (11 digit) :
h. NEFT Code No. :
5. E-mail address of the Bidder :
6. Contact Person(s) of the Bidder :
I/we declare that the particulars given above are correct and complete and I/we accord our consent for
receiving all our payments through Electronic Mechanism.
Place :
Date :
(Signature of the Authorised Official of the Bank)
Bank’s Stamp
NOTE: To be submitted along with Copy cancelled cheque
FORM –M
CHECK LIST
Bidder is requested to fill this checklist and ensure that all details/ documents have been furnished as called
for in the Bidding Documents along with duly filled in, signed & stamped checklist with each copy of the
"Unpriced bid (Part–I)”.
(2) Power of Attorney in favour of the person who has signed the bid.
Submitted
(4) EMD
Submitted
(11) Form SP-4 and Sp-5 indicating % break-up of Form SP-1 & SP-2
Submitted
(18) Details of proposed Organization for Home and Site Office as per
Bidding FORM-Q.
Submitted
SL. FULL POSTAL DESCRIPTION CONTRACT START SCHEDULED ACTUAL ACTUAL REMARKS
NO. ADDRESS OF CLIENT & VALUE DATE COMPLETION COMPLETION COMPLETED
NAME OF OFFICER-IN- OF WORK DATE DATE VALUE
CHARGE (US $)
FORM-O
DEPLOYMENT SCHEDULE OF CONSTRUCTION EQUIPMENT
CAPACITY
NO.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 .. .. .. 32
TOTAL
1 CRANES
1.2 1000 MT
1.3 500 MT
1.4 300 MT
1.5 150 MT
1.6 75 MT
1.7 50 MT
1.8 20 MT
1.9 15 MT
1.10 10 MT
1.11 5 MT
2 DIESEL
GENERATORS
2.1 500 KVA
CAPACITY
NO.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 .. .. .. 32
TOTAL
3 COMPRESSORS
3.1 600 CFT
3.2 350 CFT
4 WELDING M/CS
4.1 DIESELWELDING
M/C
4.2 DIESEL
GENERATOR
4.3 WELDING TRANS
FORMERS/REC-
TIFIERS
4.4 TIG WELDING
M/CS
5 GRIT BLASTING
M/CS
6 SPRAY PAINTING
M/CS
7 STRESS
RELIEVING M/CS
8 RADIOGRAPHY
M/CS
9 TEST PUMP
10 WATER PUMP
FORM-O
CAPACITY
NO.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 .. .. .. 32
TOTAL
11 TRANSPORTAION
EQPT
11.1 TRACTOR -TRAILOR
11.2 TRUCKS
11.3 BUS
12 JACKS
12.1 MECHANICAL
12.2 HYDRAULIC
13 CIVIL
13.1 EXCAVATORS
13.2 DUMPERS
13.6 MIXER
13.7 VIBRATORS
13.8 COMPACTORS
FORM-O
CAPACITY
NO.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 .. .. .. 32
TOTAL
13.9 THEODOLITES
14.0 OTHERS
14.1 INSULATION
TESTING
EQUIPMENT
14.2 SECONDARY
INJECTION
TESTING KIT
14.4 CALIBRATION
EQUIPMENT
14.5 OTHER TOOLS &
TACKLES
_______________________________
(STAMP & SIGNATURE OF BIDDER)
Note: Deployment schedule shall be as per Time for completion as defined in Appendix II to SCC/amendment if
any. Bidder agrees to augment the above list with additional numbers/category/type/capacity, if required as per
contract or/and as directed by OWNER/PMC to complete the work within the completion schedule and contract
price.
FORM-P
In this Proposal FORM, Bidder shall detail out Methodology of Execution of work, as applicable for the
following:
1. Methodology of execution of residual basic design and detailed engineering considering/ furnishing
▪ Availability of 3D modelling with PDMS/S3D/Equivalent software along with details such as number
of work stations, available experienced manpower etc.
▪ Availability of latest IT communication system and Engineering Documentation Management &
control & Transfer of deliverables
▪ Exposure of engineering company for above software
▪ Key personnel to be deployed by main bidder, either at Bidder's design office or design office of
Engineering sub-contractor, for review, approval and monitoring.
▪ Distribution matrix of month wise major key quantities to be executed for the entire construction
duration
Sr. Item description
Unit Total qty Month wise quantities
No
1 Piles Nos
2 RCC M3
3 Structural fabrication MT
4 Structural erection MT
5 Piping welding (Shop) ID
6 Piping welding (Field) ID
7 Electrical cable laying Mtr
8 Instrumentation cable Mtr
laying
▪ Mobilization of heavy duty crane for installation of heavy lifts mentioned under (4) below.
▪ Labour productivity/day considered
- Welder (Shop Inch dia)
- Welder (Field Inch dia)
- Carpenter (Sqm)
- Bar bender (Kg)
▪ Monsoon working
- % of normal efficiency
- Period of such efficiency in a year
▪ Extent of mechanization of construction processes/equipment
- Excavation
- Concrete works
- Modular structure/extent of modularization
- Auto welding
▪ Philosophy of fabrication of Pipe Spools, Structural Steel, Site Fabricated Tank components etc.
(Example – Pipe fabrication at site or at different shop located outside, Supply of prefabricated
structural steel from shop outside site location etc.,).
▪ All other details mentioned in the document titled “Project Execution Plan” enclosed with the
Technical portion of the Bidding Document.
4. Details of Heavy Lifts involved in the project and its execution methodology
DATE
FORM-Q
The Bidder shall submit herein details of Head Office and Project/Site Organisation proposed to be
deployed for execution of work. Bidder shall also furnish the bio-data of Site-in-Charge and key
personnel to be deployed meeting the minimum criteria specified in the SCC.
Bidder understand that the said proposal represents the minimum deployment and the Bidder
acknowledges that the said deployment may have to be augmented with additional number and/or
categories, if required if directed by Engineer-in-Charge in order to compete the work within the
completion schedule and quoted lumpsum price.
4.7 INSTRUMENTATION
4.7.1 WORKENGINEER
LEAD
4.7.2 SITE ENGINEER
4.7.3 SUPERVISORS
4.8 QUALITY ASSURANCE/
QUALITY CONTROL
4.8.1 QC/QA MANAGER
4.8.2 INSPECTOR (CIVIL)
4.8.3 INSPECTOR (PIPING)
4.8.4 INSPECTOR (MECH
EQPT)
FORM-R
1. Deployment schedule shall be as per Time period for completion as defined in Appendix II to SCC/subsequent amendment
if any.
2. Bidder/Contractor agrees to augment the above list with additional numbers/category/type/qualification/specialization,
etc., required as per contract or/and as directed by OWNER/PMC to complete the work within the completion schedule
and contract price.
FORM-S
Strike out Not Applicable Clause/ section and furnish relevant document.
(a) If Available:
If independent ESI code is available, please indicate code __________ and annex the copy of the
same.
“In case job is awarded, party will acquire independent ESI code within 15 days of the date of issue
of Work order. The gate pass for labour shall be issued only after furnishing the independent ESI
code to Engineer-in-Charge (EIC). In case party fails to acquire the independent ESI code, EIC
reserves the right to cancel the work order, forfeit the EMD and initiate suitable penal action as
deemed fit by IOCL.”
In case bidder claims exemption from obtaining independent ESI code, bidder must submit
documentary evidence towards the same along with the bid. IOCL will examine the submitted
documents during tendering and convey the decision to the party. If the exemption claim is accepted
by IOCL, the party will have to furnish an indemnity bond indemnifying IOCL against any eventuality
regarding ESI becoming applicable to the party during the tenure of the contract. In case the
exemption claim of party is not acceptable to IOCL the same will be conveyed to the party and party
will be governed by above clause (b). In response to IOCL communication conveying non-
acceptance of party’s exemption claim, party will submit acceptance to above clause (b).
In case, party does not agree to any of the above clauses (a), (b) or (c), the offer of party shall
be liable for rejection.
PROJECT: PACKAGE-4 (LUPECH POWER DISTRIBUTION FACILITY) FOR GUJARAT REFINERY CAPACITY
EXPANSION FROM 13.7 TO 18 MMTPA (J-18) PROJECT IOCL GUJARAT REFINERY, VADODARA, GUJARAT,
INDIA
FORM-T
Based on the defined scope of work as detailed out in various sections of this tender
documents, bidders shall require to furnish technical information on equipment, bulk
material and site work for the defined package using these formats along with the
unpriced Bids. The information sought in this section is purely meant for reviewing the
understanding of the CONTRACTOR assessment with respect to defined scope of works
at the time of bidding stage. However, the quantum of work as indicated shall in no way
be considered from be a contractual obligation. In any case, it shall be the exclusive
responsibility of the CONTRACTOR to ensure that all the equipment, material, hardware
etc., as required for completion and successful commissioning of the plant is included in
their scope and shall be supplied by the CONTRACTOR without any time and cost
implication.
1. HVAC System
2. PIPING
3. ELECTRICAL WORK
4. INSTRUMENT WORK
5. CIVIL WORK
TECHNICAL INFORMATION REQUIRED FOR ASSESSING QUANTUM OF WORK – FORM T
PROJECT: PACKAGE-4 (LUPECH POWER DISTRIBUTION FACILITY) FOR GUJARAT REFINERY CAPACITY EXPANSION FROM 13.7 TO 18 MMTPA (J-18)
PROJECT IOCL GUJARAT REFINERY, VADODARA, GUJARAT, INDIA
NOTES:
1. The information being sought in this section is specifically for the purpose of assessing quantum of work and not from any
contractual angle. Data being indicated here should be true to the best of information available / worked out by bidder.
TECHNICAL INFORMATION REQUIRED FOR ASSESSING QUANTUM OF WORK – FORM T
PROJECT: PACKAGE-4 (LUPECH POWER DISTRIBUTION FACILITY) FOR GUJARAT REFINERY CAPACITY EXPANSION FROM 13.7 TO 18 MMTPA (J-18)
PROJECT IOCL GUJARAT REFINERY, VADODARA, GUJARAT, INDIA
Sl. No. Description Total Length (m) Total Weight (kg) No. of Valves Strainers Steam Traps Remarks
AG UG Pipes Fittings Flanges Hand/Gear MOV
A CS Piping (Non IBR)
1 UP TO 1.5”
2 2" TO 8"
3 10" TO 12"
4 14" and above
C SS Piping
1 UP TO 1.5”
2 2" TO 8"
3 10" TO 12"
4 14" and above
D CS Piping (IBR)
1 UP TO 1.5”
2 2" TO 8"
3 10" TO 12"
4 14" and above
E AS Piping (IBR)
1 UP TO 1.5”
2 2" TO 8"
3 10" TO 12"
TECHNICAL INFORMATION REQUIRED FOR ASSESSING QUANTUM OF WORK – FORM T
PROJECT: PACKAGE-4 (LUPECH POWER DISTRIBUTION FACILITY) FOR GUJARAT REFINERY CAPACITY EXPANSION FROM 13.7 TO 18 MMTPA (J-18)
PROJECT IOCL GUJARAT REFINERY, VADODARA, GUJARAT, INDIA
Sl. No. Description Total Length (m) Total Weight (kg) No. of Valves Strainers Steam Traps Remarks
AG UG Pipes Fittings Flanges Hand/Gear MOV
4 14" and above
F Tracing
1 UP TO 1.5”
2 2" TO 8"
3 10" TO 12"
4 14" and above
G Special Items
NOTES:
1. The information being sought in this section is specifically for the purpose of assessing quantum of work and not from any
contractual angle. Data being indicated here should be true to the best of information available / worked out by bidder.
2. Complete information should be furnished against each item.
TECHNICAL INFORMATION REQUIRED FOR ASSESSING QUANTUM OF WORK – FORM T
PROJECT: PACKAGE-4 (LUPECH POWER DISTRIBUTION FACILITY) FOR GUJARAT REFINERY CAPACITY EXPANSION FROM 13.7 TO 18 MMTPA (J-18)
PROJECT IOCL GUJARAT REFINERY, VADODARA, GUJARAT, INDIA
Sl. No. Work Description Type Specification Unit Qty. Any Other Remarks
required info
Required Information
1. 33 kV GIS Fixed type Rating, quantity, type and make No
2. Auxiliary Distribution Fixed Type Rating, quantity, type and make No
Boards e.g., LVDBs,
MLDB, EMLDB, ASBs
3. 220kV/33 kV Power Oil filled outdoor type Rating, quantity, type and make No
Transformers
4. UPS and associated 1) 110V AC UPS for Type, rating, size, make and No
batteries and DB for Instrumentation quantity
instrumentation and
electrical
5. Battery and battery 1) 110V Battery charger Type, rating, size, make and No
charger for Electrical quantity
2) 110V Battery charger
for Critical lighting
6. EHV Cables XLPE Type, rating, size, make and Mtrs.
7. HV and MV Power XLPE, FRLS quantity Rating,
Type, rating, quantity,
size, make type
and Mtrs. Bidder shall
Cables and make
quantity provide breakup as
per cable size
8. MV control cables XLPE, FRLS Type, rating, size, make and Mtrs -do-
including lighting cables quantity
9. Industrial and LED Type, rating, make and quantity Nos. Bidder to provide
Flameproof Lighting breakup as
fittings including industrial and
receptacles flameproof
TECHNICAL INFORMATION REQUIRED FOR ASSESSING QUANTUM OF WORK – FORM T
PROJECT: PACKAGE-4 (LUPECH POWER DISTRIBUTION FACILITY) FOR GUJARAT REFINERY CAPACITY EXPANSION FROM 13.7 TO 18 MMTPA (J-18)
PROJECT IOCL GUJARAT REFINERY, VADODARA, GUJARAT, INDIA
Sl. No. Work Description Type Specification Unit Qty. Any Other Remarks
required info
Required Information
10. Bulk material Rating, quantity, type and make
a. Cable trays
b. Earthing and lightning
protection material
c. Lighting and small power
panels
d. Lighting poles including
high mast lighting
e. Cable termination kits Bidder to provide
breakup as per
cable size
f. Cable glands
NOTES:
1. The information being sought in this section is specifically for the purpose of assessing quantum of work and not from any
contractual angle. Data being indicated here should be true to the best of information available / worked out by bidder.
2. Bidder to list any additional item considered / required to complete the tender as per attached specifications, scope of work and
good engineering practice.
TECHNICAL INFORMATION REQUIRED FOR ASSESSING QUANTUM OF WORK – FORM T
PROJECT: PACKAGE-4 (LUPECH POWER DISTRIBUTION FACILITY) FOR GUJARAT REFINERY CAPACITY EXPANSION FROM 13.7 TO 18 MMTPA (J-18)
PROJECT IOCL GUJARAT REFINERY, VADODARA, GUJARAT, INDIA
Sl. No. Item Description Type Specification Unit Qty. Any Other Remarks
required info
Required Information
A. INSTRUMENTS
1. Gas Detection Gas Detectors/Transmitters, Different types No
Hooters, Beacons, Sounders
etc.
PROJECT: PACKAGE-4 (LUPECH POWER DISTRIBUTION FACILITY) FOR GUJARAT REFINERY CAPACITY EXPANSION FROM 13.7 TO 18 MMTPA (J-18)
PROJECT IOCL GUJARAT REFINERY, VADODARA, GUJARAT, INDIA
NOTES:
1. The information being sought in this section is specifically for the purpose of assessing quantum of work and not from any
contractual angle. Data being indicated here should be true to the best of information available / worked out by bidder.
2. The information shall cover all instruments, cables, erection material etc.
TECHNICAL INFORMATION REQUIRED FOR ASSESSING QUANTUM OF WORK – FORM T
PROJECT: PACKAGE-4 (LUPECH POWER DISTRIBUTION FACILITY) FOR GUJARAT REFINERY CAPACITY EXPANSION FROM 13.7 TO 18 MMTPA (J-18)
PROJECT IOCL GUJARAT REFINERY, VADODARA, GUJARAT, INDIA
9. Grating SQM
PROJECT: PACKAGE-4 (LUPECH POWER DISTRIBUTION FACILITY) FOR GUJARAT REFINERY CAPACITY EXPANSION FROM 13.7 TO 18 MMTPA (J-18)
PROJECT IOCL GUJARAT REFINERY, VADODARA, GUJARAT, INDIA
NOTES:
1. The information being sought in this section is specifically for the purpose of assessing quantum of work and not from any
contractual angle. Data being indicated here should be true to the best of information available / worked out by bidder.
FORM – V
EXCEPTIONS AND DEVIATIONS
S.
PART N O . /
NO. PAGE NO. CLAUSE NO. SUBJECT EXCEPTIONS / DEVIATION
VOLUME
NOTE: 1. If unavoidable, Bidder may stipulate deviations to the requirements of the Tender document only in this format.
3. Any deviations stated elsewhere in the bid shall not be taken into account and may render the bid non-responsive a n d liable to be
rejected.
NAME OF WORK :
TENDER No. :
UNIQ E-TENDER ID :
I/ we confirm that we have quoted the rates in the tender considering Inter-alia the following
documents, as applicable for the subject tender:
I/we hereby certify that we have fully read and thoroughly understood the tender requirements and
accept all terms and conditions of the tender including all documents mentioned above and all
corrigendum/addendum issued. Our offer is in confirmation to all the terms and conditions of
the tender including all corrigendum/addendum and minutes of the pre-bid meeting, if any except
the deviations stated in format of “Deviations / Exceptions”. In the event of award of contract to us, the
complete tender document along with addendum /corrigendum, if any as uploaded by Indian Oil
Corporation Limited at e-tender portal [https://iocletenders.nic.in] under the subject referring to the
above-mentioned tender number shall be considered for constitution of Contract Agreement.
I/ we declare that none of the electronic documents have been tampered with. In case of
tampering of electronic documents, the bid shall be rejected outright and EMD forfeited without prejudice
to any other rights or remedies available to IOCL.
I / we further undertake and confirm that all the documents submitted by us along with the bid are true
and genuine to the best of our knowledge and belief. In case at any time, any document /
information furnished by us are found to be forged / false / fabricated / misleading, we shall be solely
liable for any legal consequences, penal actions including holiday listing by IOCL.
Name :……………..………………………
Designation :………………….………………….
Company Name :…………………………………...
Contact Number :……………….………………….
Email ID : …………………….………………
3(752&+(0,&$/$1'/8%(
,17(*5$7,21352-(&7
³/X3HFK´-
,2&/*8-$5$75(),1(5<
SECTION 8
GENERAL CONDITIONS
OF
LUMPSUM TURNKEY (LSTK) CONTRACT
CONTENTS
SECTION – 1 DEFINITIONS 1
SECTION – 2 GENERAL 8
1
SECTION – 4 PERFORMANCE OF WORKS 46
4.0.0.0 General
4.1.0.0 The Job Sites
4.2.0.0 Compliance with Codes and Standards
4.3.0.0 Time for Completion
4.4.0.0 Price Adjustment for Slippage in Completion
4.5.0.0 Schedule of Activities
4.6.0.0 Report and Records
4.7.0.0 Quality Assurance/Quality Control Programme
4.8.0.0 Execution of the Work
4.9.0.0 Sub-Contracts
4.10.0.0 Relationship with Consortia
4.11.0.0 Misconduct
SECTION – 5 INSPECTION AND TESTING 64
5.0.0.0 Inspection and Testing of Materials
5.1.0.0 Inspection and Testing of Works
5.2.0.0 Tests, Commissioning and Possession of Works
5.3.0.0 Completion Certificate
5.4.0.0 Defect Liability Period and Latent Defects
5.5.0.0 Contractor’s Guarantees
5.6.0.0 Commissioning
5.7.0.0 Guarantee Performance Tests
5.8.0.0 Spare Parts
SECTION – 6 MEASUREMENTS, CERTIFYING INSPECTIONS AND
81
PAYMENTS
6.0.0.0 Certifying Inspections
6.1.0.0 Measurement
6.2.0.0 Final Bill
6.3.0.0 Price Schedule
6.4.0.0 Advance and On Account Payment
6.5.0.0 Mode of Payment and Tax Deductions
6.6.0.0 Claims by the Contractor
6.7.0.0 Discharge of Owner’s Liability
6.8.0.0 Final Certificate and Release of Security
6.9.0.0 Claims of Owner
SECTION – 7 TERMINATION 95
7.0.0.0 Termination
2
SECTION – 8 MISCELLANEOUS 101
8.0.0.0 Personal Acts and Liabilities
8.1.0.0 Taxes
10.0.0.0 General
10.1.0.0 First Aid and Industrial Injuries
10.2.0.0 General Rules
10.3.0.0 Contractor's Barricades
10.4.0.0 Scaffolding
3
10.5.0.0 Excavation and Trenching
10.6.0.0 Demolition
10.7.0.0 Safety Equipment
10.8.0.0 Risky Places
10.9.0.0 Hoisting Equipment
10.10.0.0 Electrical Equipment
10.11.0.0 Maintenance of Safety Devices
10.12.0.0 Display of Safety Instructions
10.13.0.0 Enforcement of Safety Regulations
10.14.0.0 No Exemption
10.15.0.0 Entry Passes
10.16.0.0 Gate Passes
10.17.0.0 Work Permit
10.18.0.0 Vehicle Permit
10.19.0.0 Special Safety Regulations
10.20.0.0 Deductions from Contract Price
10.21.0.0 Special Contributions
APPENDICES 127
(i) Contractor’s Labour Regulations (Appendix-I)
(ii) Model Rules for Labour Welfare (Appendix-II)
(iii) Safety Practices during Construction (Appendix-III)
(iv) Form of Contract (Appendix-IV)
(v) Form of Bank Guarantee to Cover Earnest Money Deposit (EMD)
(Appendix-V)
(vi) Form of Bank Guarantee to Cover Lumpsum Advance
(Mobilisation) (Appendix-VI)
(vii) Form of Bank Guarantee to Cover Security Deposit
(Appendix-VII)
4
SECTION – 1
DEFINITIONS
************************************
2.1.2.1 The Bank Guarantee(s) shall be extended by such further period(s) as the
OWNER may require until performance of all the Contractor’s obligations
under the Contract.
2.1.2.2 Without prejudice to any other right or remedy available to the OWNER, the
OWNER may at any time and from time to time before issue of the Final
Certificate under the Contract require the CONTRACTOR by notice in writing
to renew the Bank Guarantee(s) for such period(s) as the OWNER may deem
fit, and upon such request, the CONTRACTOR shall renew the Bank
Guarantee(s) for the required period(s), and without prejudice to any other
right or remedy under the Contract, and unless the OWNER shall not have
required such renewal, the OWNER shall be entitled to encash the Bank
Guarantee(s) or any of them which are not renewed at least 14 (Fourteen)
days prior to the date of expiry thereof .
2.1.3.0 The Security Deposit shall be held by the OWNER as security for the due
performance of the CONTRACTOR’S obligations under the contract,
PROVIDED that nothing herein stated shall make it incumbent upon the
OWNER to utilise the Security Deposit in preference to any other remedy
which the OWNER may have, nor shall be construed as anywise confining the
claims of the OWNER against the CONTRACTOR to the quantum of the
security deposit.
2.1.4.0 Upon determination of the contract prior to completion of the work(s) for any
cause, the OWNER shall insofar as the Security Deposit constitutes cash
refund, and insofar as Security Deposit is in any other form, release/
discharge/ return, as the case may be, to the CONTRACTOR the unutilised
balance of the Security Deposit, if any, for the time being remaining in the
hands of the OWNER, after settlement of accounts and discharge of all
2.6.2.0 A Change Order Proposal may be initiated by the CONTRACTOR only within
21 (twenty one) days from the date of issue of orders or instructions relative to
any works for which the CONTRACTOR claims the additional payment or
compensation. The Change Order Proposal made by the CONTRACTOR
shall set out the reasons for the proposal and the basis on which the increase
in the Lumpsum Price is proposed to be calculated and shall give particulars
of the order or instruction from which it arises.
2.6.2.1 If the CONTRACTOR fails to initiate a Change Order Proposal within the time
and in the manner specified in Clause 2.6.2.0, the OWNER shall not be liable
for or in respect of a claim or Change Order Proposal subsequently or
otherwise made or initiated by the CONTRACTOR in respect of such orders
or instructions, and the CONTRACTOR hereby waives and relinquishes any
and all rights in respect of any such claim or Proposal subsequently or
otherwise made or initiated by the CONTRACTOR.
2.6.3.1 The OWNER shall within 3 (three) weeks thereafter examine the Proposal and
the recommendations of its Project Management Consultant with respect
thereto and convey in writing to the CONTRACTOR its approval or
disapproval in principle of the Change Order Proposal.
2.6.3.2 If the Change Order Proposal is made by the OWNER or if the OWNER
conveys its approval in principle to the Change Order Proposal made by the
CONTRACTOR, the CONTRACTOR shall within 3 (three) weeks of receiving
the Change Order Proposal or OWNER’s approval in principle, as the case
may be, submit to the OWNER, the Engineer-in-Charge and the OWNER’s
Project Management Consultant in writing its detailed engineering analysis
and costing of the change by way of reduction or increase, as the case may
be, in the Lumpsum Price.
2.6.3.3 The OWNER’s Project Management Consultant shall review the detailed
engineering and costing of the change proposed by the CONTRACTOR and
submit to the OWNER and the CONTRACTOR its comments thereon within
three (3) weeks of the receipt thereof.
2.6.4.0 If a Change Order is not issued by the OWNER within 18 (eighteen) weeks of
initiation of the Change Order Proposal by the OWNER or within seven (7)
weeks of the CONTRACTOR’s compliance with Clause 2.6.3.2, whichever is
later, the OWNER or the CONTRACTOR may apply to the Engineer-in-
Change for fixing an ad hoc price for the activities covered by the change
which shall be 90% (ninety per cent) of the cost of such change, as estimated
by the Engineer-in-Charge, and the OWNER shall pay such ad hoc price for
such activities in accordance with the payment terms specified in the Contract
Documents.
2.6.5.0 If the OWNER has not given its in principle approval to a Change Order Proposal
initiated by the CONTRACTOR in accordance with the provisions of Clause
2.6.2.0, or if the OWNER and the CONTRACTOR are unable to agree on the
costing of the Change Order Proposal as envisaged in Clause 2.6.3.4, the
Change Order Proposal made by the CONTRACTOR shall be deemed to be a
claim of the CONTRACTOR under Clause 6.6.1.0 to which the provisions of
Clause 6.6.1.0 and associated provisions with regard to the CONTRACTOR’s
claims shall mutatis mutandis apply.
2.6.6.0 Provided always that the provisions with respect to a Change Order or a Change
Order Proposal shall not be applicable if:
(a) the change of supply or services or work is required by the OWNER or
Engineer-in-Charge before approval of detailed design or engineering to
meet the requirements of the Contract.
(b) the change of supply or services or work is necessary at any time in order
for the CONTRACTOR to comply with the requirements of the Contract
or the CONTRACTOR’s responsibilities under the Contract.
(c) the additional supply or services or works are required because of any
delay or deficiency attributable to the CONTRACTOR.
(d) the additional Work/services and/or materials are required to make good
the CONTRACTOR’s Warranties and/or Guarantees as set forth in the
Contract.
(e) the change relates to the repair, rectification or re-performance of any of
the defective work(s) or materials within the CONTRACTOR’s scope or
supply or services or work
2.6.7.0 Unless otherwise agreed between the CONTRACTOR and the OWNER, the price
implications of a Change Order Proposal for addition to or subtraction from the
Lumpsum Price shall be calculated on the following basis:
(A) (i) For Materials covered under the CONTRACTOR’s scope of supply (including
equipment) incorporated in work(s) not being Civil and Structural Works covered by
(B) below, at cost of such materials involved in the work(s) to which the Change
Order Proposal relates, as witnessed by the Supplier’s relative invoices;
(ii) For works and services, other than Civil and Structural works covered by (B)
below, at the cost of labour and consumables and utilities involved in the works to
which the Change Order Proposal relates and the cost of equipment involved in the
SECTION – 2 - GENERAL Page 19 of 192
execution of such work, the cost of the equipment to be worked out by amortization
in the manner provide in Clause 2.6.7.1;
(iii) 6 % (six per cent) of (i) and (ii) above to cover design and other engineering and
overall co-ordination costs.
(iv) 15% (fifteen per cent) of the total of (i), (ii) and (iii) above to cover all other costs,
overheads and profit.
(B) (i) For Civil and Structural works involved in the works to which the Change Order
Proposal relates, on basis of the CPWD rates then prevailing for the location of the
works or, in the absence of the existence of CPWD rates for the location, at the
applicable State PWD rates, which cover costs, overheads and profit;
(ii) 6 % (six per cent) of (i) above to cover design and other engineering and overall
co-ordination costs.
2.6.7.1 Unless otherwise agreed, for the purposes of calculating the increase or reduction
in the Lumpsum Price consequent upon a Change Order Proposal with respect to
any works other than Civil and Structural work(s) covered by Clause 2.6.7.0 (B), as
and from the date of the initiation of a Change Order Proposal, the CONTRACTOR
shall on each day prepare and submit to the OWNER, a statement of time worked
by all labour employed in the work/services to which the Change Order Proposal
relates and showing the description and quality and invoiced costs of all
CONTRACTOR supplied materials (including equipment) incorporated in the works
and the cost of materials and utilities and equipment utilized for the work to which
the Change Order Proposal relates. Such statement shall be submitted by the
CONTRACTOR on a daily basis to the OWNER after obtaining the comments (if
any) and signature of the Engineer-in-Charge thereon. At the end of each
month, the CONTRACTOR shall deliver to the OWNER for approval a price
statement of the cost of labour, materials, utilities and equipment used in this
behalf. The cost of mechanical equipment utilized for the work shall be worked out
on a capital amortization of 2000 (two thousand) working days. Notwithstanding
any dispute as to the cost allocation, the Statement shall be signed by the
Engineer-in-Charge with a Note of dissent as a record of the views of the
Engineer-in-Charge thereon.
2.6.7.2 Unless otherwise agreed, the amount calculated under Clause 2.6.7.0 shall solely
determine the rights of the OWNER or the CONTRACTOR, as the case may be,
pursuant to a Change Order Proposal in respect of which the OWNER is entitled to
a reduction in the Lumpsum Price or the CONTRACTOR is entitled to an increase
in the Lumpsum Price.
2.6.7.3 It is hereby specifically clarified as follows:
(a) Nothing provided herein shall in any manner permit the CONTRACTOR to
disobey any order(s) or instruction(s) of the OWNER or the Engineer-in-Charge or
other person or authority competent to issue such order(s) or instruction(s) or to
await the outcome of the process set forth herein for claiming or determining the
cost implications or implementing such order(s) or instruction(s).
(b) The CONTRACTOR shall within the Scope of Work and Services be bound to
promptly and timely implement such order(s) or instruction(s).
(c) The time taken in implementing the process herein set forth shall in no
circumstances constitute a ground for extension of time under Clause 4.3.5.0 or
Clause 4.3.6.0 or otherwise.
(d) Any delay or inability by the Project Management Consultant to consider and/or
submit its recommendations on a Change Order Proposal in accordance with
Clause 2.6.3.0 or to review and/or submit its comments in accordance with Clause
2.6.3.3, or by the OWNER to examine the Change Order Proposal or
recommendations of the Project Management Consultant, or convey its approval
or disapproval to the Change Order Proposal in accordance wth Clause 2.6.3.1 or
to convey its agreement or to issue a Change Order under Clause 2.6.3.4 shall in
(i) The Job Site/Work Front was in whole or part not timely provided to the
CONTRACTOR in accordance with the Front Release Programme or
otherwise; or
(ii) Any other front required for progressing further with the work is not timely
made available to the CONTRACTOR in whole or part; or
(iv) The progress of any work is delayed or interrupted for a cause not
attributable to the CONTRACTOR.
In all such cases the CONTRACTOR’s sole remedy shall be extension of time
so far as permissible under and in accordance with the provisions of Clause
4.3.5.0 and/or 4.3.6.0 and the CONTRACTOR hereby waives any and all
contrary rights or claims for compensation or damages or otherwise.
************************************
3.0.2.0 MATERIALS
3.0.2.1 These General Conditions of Contract shall, on issue of the Letter of
Acceptance to the CONTRACTOR, constitute a firm and indivisible contract
for the sale and supply, to the OWNER, of all materials required for
incorporation in the permanent works as determined by the CONTRACTOR,
within the scope of work, to be necessary to establish, commission and
operate (so far as concerns mandatory spares) the Plant/ Unit delivered on
CIF basis at Indian port of CONTRACTOR’s choice in respect of imported
materials and delivered ex-factory in respect of other materials, at the price
of materials specified in the Price Schedule. It is hereby clarified that the said
contract shall include a contract for the sale and supply within the price of
materials (and any recoveries in respect thereof under any policy of insurance)
of all materials required for the replacement of any defective materials and any
materials lost, damaged or destroyed during transit, storage, fabrication,
erection or otherwise prior to the issue of the Completion Certificate.
3.0.2.2 (a) Supplier’s invoices in respect of materials covered within the scope of supply
under Clause 3.0.2.1 shall be made out by the Supplier in favour of the
OWNER and the materials shall be consigned to the OWNER. Where the
CONTRACTOR is the supplier, the invoices shall be drawn by the
CONTRACTOR as the Supplier.
(b) The Supplier’s invoices for imported materials shall include the cost of all pre-
delivery tests and third party inspections, but shall not include the
CONTRACTOR’s procurement charges.
(c) The Supplier’s invoices for indigenously supplied materials shall include all
pre-delivery tests, but shall not include the CONTRACTOR’s procurement
charges.
(d) The invoices for indigenously supplied materials shall also include the taxes,
duties and other levies on the supply which are reimbursable by the OWNER.
Reimbursement shall, however, be subject to the satisfaction of the conditions
and provision of the documents required to qualify for the reimbursement.
3.0.2.3 The CONTRACTOR shall be responsible at his own cost and initiative within
the scope of services, to take delivery of the materials from the port of delivery
in India in respect of imported materials and from the factory or ware-house or
(i) If the CONTRACTOR shall have given written notice to the Engineer-in-
Charge and to the OWNER specifying the Utility(ies) required and the
anticipated date of actual requirement of such Utility(ies) for
commissioning to match the actual progress of the work by the
CONTRACTOR at least 15 (fifteen) days prior to such requirement; and
3.6.8.0 Water supply by the OWNER to the CONTRACTOR shall be entirely at the
risk of the CONTRACTOR as to the continuity and regularity of supply and
maintenance and adequacy of pressure without any warranty by or liability to
the OWNER in respect thereof and without entitlement to the CONTRACTOR
on grounds of discontinuance, irregularity, drop or rise in pressure or other
cause whatsoever to claim from the OWNER any damages, compensation or
extension of time or otherwise in respect thereof or the consequences
thereof.
3.7.0.0 LAND
3.7.1.0 Without prejudice to the provision of Clause 3.4.1.0 hereof and following
Clauses thereunder, the OWNER may at its discretion and convenience, if it
has sufficient available land at its disposal, provide land to the
CONTRACTOR near or about any job site, for the construction of the
CONTRACTOR’s field office(s), godown(s), workshop(s), assembly yard,
residential accommodation and/or temporary works or any of them required
for/or in connection with the execution of the works.
3.7.2.0 The CONTRACTOR shall at his own cost and initiative construct temporary
buildings or other accommodation or works necessary and make suitable
arrangement for water and power supply thereto and for provision of sanitary,
drainage and de-watering arrangements in respect thereof in accordance with
plans/designs, layouts previously approved by the Engineer-in-Charge in this
behalf.
3.7.3.0 Any land provided by the OWNER to the CONTRACTOR within the
provisions hereof shall be strictly on a license basis, and shall not create any
right, title or interest whatsoever in the CONTRACTOR therein or in respect
thereto.
3.7.4.0 The CONTRACTOR shall pay to the OWNER, license fee @ Rs. 1000/-
(Rupees One Thousand only) per month or part thereof for upto 500 (Five
Hundred) square meters of land or part thereof made available to it by the
OWNER and Rs. 200/- (Two Hundred only) per month or part thereof for
SECTION – 3 - MATERIALS, LABOUR, EQUIPMENT AND FACILITIES Page 43 of 192
each additional 100 (One Hundred) square meters of land or part thereof
made available by the OWNER to the CONTRACTOR or at such other
rate(s) of license fee as specified by the OWNER in this behalf from time to
time for any land made available to the CONTRACTOR within the
provisions hereof, and the OWNER shall be entitled (without prejudice to
any other mode of recovery), to recover the license fee from the Running
Account and Final Bill(s) of the CONTRACTOR and/or other payments due or
becoming due to the CONTRACTOR from time to time.
3.7.5.0 Notwithstanding anything herein provided, the OWNER reserves the right at
any time during the pendency of the work to call upon the CONTRACTOR to
vacate the land or any part thereof on giving 7 (Seven) days’ written notice to
the CONTRACTOR in this behalf.
3.7.6.0 Forthwith upon expiry of such notice or on completion of the works or earlier
determination of the contract, the CONTRACTOR shall remove all
constructions, works, piping and other installation whatsoever not forming part
of the contractual works, put up or erected by the CONTRACTOR upon the
land, and shall have the land cleared, leveled and dressed to the satisfaction
of the Engineer-in-Charge.
3.7.7.0 The CONTRACTOR shall not be entitled, upon any vacation or notice within
the provisions of clause 3.7.5.0 hereof, to claim any resultant compensation
or damage from the OWNER nor shall such notice or vacation constitute a
ground or basis for any claim by the CONTRACTOR for compensation or
damages or ground for extension of time for completion.
3.7.8.0 The OWNER shall be entitled at any time without notice to the
CONTRACTOR, to suspend or withdraw use by the CONTRACTOR of any
part of such area or land or access thereto and no suspension or withdrawal
of such facility, or disruption or inadequacy thereof by virtue of flood, storm,
fire, disrepair or other cause whatsoever, shall form the basis of any claim by
the CONTRACTOR for compensation or damages or ground for extension of
time for completion.
3.7.9.0 Notwithstanding anything herein provided, the provisions of clause 7.0.6.0
hereof and related Clauses applicable consequent upon termination of
contract, shall apply to any breach by the CONTRACTOR of his obligations,
within the provisions of Clauses 3.4.4.0, 3.5.3.0, 3.6.3.0 and 3.7.6.0 hereof as
to a breach of clause 7.0.5.0 hereof.
3.11.0.0 EQUIPMENT
3.11.1.0 The CONTRACTOR shall be exclusively responsible to arrange for
importation into India in its own name on drawback or re-export or other basis
all equipment, if any, required to be imported into India for the purposes of the
work and to pay and bear the customs, import and other duties and levies (if
any) payable thereon or in respect thereof, and will be solely responsible for
the timely and proper compliance of all applicable terms and conditions and
formalities relative thereto.
3.11.2.0 The CONTRACTOR shall within 28 (Twenty Eight) days from the date of
receipt of Acceptance of Bid, furnish to the Engineer-in-Charge a list of the
said equipment which he proposes to import into India on a draw-back/re-
export basis for the purposes of the work, together with complete details
thereof. The OWNER may without obligation or responsibility furnish to the
Import Licensing Authorities in India its recommendations relative to import of
such equipment which the OWNER considers necessary for the work. The
OWNER may also without obligation or responsibility render such assistance
as may be reasonably required by the CONTRACTOR from the OWNER to
enable the CONTRACTOR to obtain the relative Import License(s)/Permit(s)
for the importation of the said equipment on a draw-back/re-export basis.
3.12.3.0 All materials and equipment Imported into India by or on behalf of the
CONTRACTOR for and in connection with the work and any obligation
undertaken or recommendation, facility or assistance provided by the
OWNER relative thereto shall be on the clear understanding that the
materials and equipment shall be utilised only for and relative to the
performance of the work covered by the Contract.
3.12.4.0 All the equipment and temporary works and materials when brought to or
erected on the job site, shall be exclusively intended for execution of works
and the CONTRACTOR shall not remove the same or any part thereof,
except for the purpose of moving it from one part of the job site to another,
without the prior consent in writing of the Engineer-in-Charge.
3.12.5.0 Upon completion of the works, the CONTRACTOR shall within the scope of
work remove from the job site all the equipment and temporary works
remaining thereon.
3.12.6.0 All equipment, materials and temporary works shall at all times be and remain
at the risks of the CONTRACTOR in all respects. The OWNER shall not, at
any time, be liable for the loss or destruction of or damage to any equipment,
temporary works or materials for any reason whatsoever.
***************************
4.0.0.0 GENERAL
4.0.1.0 All works shall be performed and executed by the CONTRACTOR in strict
conformity with the job description(s), Specification(s), Plan(s), drawing(s),
design(s) and other contract documents applicable to the specific work(s) and
any relative instructions as may be issued to the CONTRACTOR by the
Engineer-in-Charge from time to time.
4.0.2.0 The Engineer-in-Charge shall be entitled from time to time or at any time, at
their discretion, to issue written orders or instructions to the CONTRACTOR
relative to the performance and/or execution of work(s) by the
CONTRACTOR or otherwise, relative to any matter touching or affecting the
contract or arising therefrom and to revise or revoke any orders or instructions
previously issued, and the CONTRACTOR shall, subject to the provisions of
the following clause, obey and/or abide thereby.
4.0.2.1 Should the CONTRACTOR require any clarification in respect of any orders
or instructions issued by the Engineer-in-Charge, or should there appear to
the CONTRACTOR to be any contradiction between any orders or
instructions issued by the Engineer-in-Charge and the contract documents or
any of them, the CONTRACTOR shall refer the matter immediately in writing
to the Engineer-in-Charge for his decision before proceeding further with the
work and the decision of the Engineer-in-Charge on any such matters shall be
final and binding upon the CONTRACTOR, who shall perform the work
accordingly, without entitlement to any claim against or compensation from
the OWNER resultant upon such order, instruction or decision.
4.0.3.0 The CONTRACTOR shall, within 28 (Twenty Eight) days of receipt of
notification of acceptance of bid, name Engineer(s) responsible for the work
at the job site on behalf of the CONTRACTOR. The said Engineer(s) of
CONTRACTOR shall be the representative(s) of the CONTRACTOR at the
job site for and relative to all actions and transactions and dealings on behalf
of the CONTRACTOR and to whom all plans, designs, drawings, orders and
instructions or other documents or communications for or relative to the job
site may be given, with the intent that all transactions and dealings had with
the said Engineer(s) shall be deemed to have been had with the
CONTRACTOR, and any and all plans, drawings, orders, instructions,
documents or communications delivered to said Engineer(s) shall be deemed
to have been delivered to the CONTRACTOR. The CONTRACTOR shall also
independently or from amongst the said Engineer(s) designate one person to
be the CONTRACTOR’s Project Manager with whom the OWNER may also
deal with as the CONTRACTOR’s representative in the manner specified
above, and who is authorized to take decisions on behalf of the
CONTRACTOR and to co-ordinate amongst the aforesaid Engineer(s) of the
CONTRACTOR.
4.0.3.1 The CONTRACTOR shall also nominate, at the job site, a Deputy Site
Representative (which nomination shall also be subject to the approval of the
Engineer-in-Charge) to deputize for the CONTRACTOR’s Representative(s)
during periods of unavoidable absence.
4.0.4.0 The CONTRACTOR shall also provide and maintain, at or about the job site,
an office for the working accommodation of the CONTRACTOR’s engineer
and staff. Such office shall remain open and attended at all hours during
SECTION – 4 - PERFORMANCE OF WORKS Page 49 of 192
which work is being performed at the job site, for the receipt of instructions,
notices, and other communications.
4.0.5.0 The CONTRACTOR shall, within the scope of work erect and/or cause to be
erected any and all temporary works, ancilliary works and enabling works,
including preparing approaches and working areas for movement and
operation of cranes, preparing and leveling areas for assembly and erection,
dewatering of surface and sub-soil water and protection of existing works,
drains, pipes, trenches, cables overhead and underground works and other
facilities and utilities falling within the job site and/or approximate thereto and
repair and/or re-placement of any and all existing works, drains, pipes,
trenches, cables, wires and facilities and/or utilities damaged or destroyed by
the CONTRACTOR or which may have to be temporarily or permanently
diverted or re-routed to enable the contractual works.
4.0.6.0 The CONTRACTOR shall co-operate with and afford the OWNER and other
contractors engaged at site, access to the work and shall supply at cost as
determined by the Engineer-in-Charge (whose decision will be final), power
and water for the performance of the work entrusted to them and/or for the
carriage and storage of materials by them and whenever any work by the
CONTRACTOR is being done in association, collaboration or in proximity with
any other contractors, the CONTRACTOR shall co-operate with the OWNER
or other contractor(s)/ agency(ies) involved in such work and shall ensure the
harmonious working between the CONTRACTOR and the
OWNER/contractor(s)/agency(ies) involved, and shall comply with any
instructions issued by the Engineer-in-Charge for the purpose.
4.0.7.0 The OWNER shall be entitled, at its discretion, to appoint one or more
engineers and/or other personnel at or about its job site on behalf of the
OWNER to do such acts, deeds, matters and things as may be necessary to
safeguard the OWNER’S interests including (but not limited to), at the
discretion of the OWNER, supervision and testing of the works being
conducted by the CONTRACTOR at the job site and/or for rendering such
assistance to the CONTRACTOR relative thereto as the OWNER or such
Engineer(s) or personnel shall or may deem fit, it being understood, however,
that the presence of any engineers or personnel of the OWNERS at or about
the job site for any supervision, inspection or test performed or conducted by
any such engineer(s) or any personnel of the OWNER in respect of any
work(s) or any other assistance rendered by such engineer(s) and/or
personnel to the CONTRACTOR relative thereto, shall be without any
attendant obligation or liability of the OWNER vis-à-vis the CONTRACTOR,
nor shall relieve the CONTRACTOR of his/its full responsibility in respect of
the work(s) under the contract or bind the OWNER to accept as satisfactory
or complete and/or in accordance with the contract, any work(s) performed by
the CONTRACTOR which has/ have been supervised, inspected, tested or
assisted by the said engineer(s) and/or personnel of the OWNER.
4.0.8.0 If the CONTRACTOR’s work or any part thereof shall be consequent or
resultant upon any works performed by any other person or shall be in
continuance thereof or otherwise based or founded or dependant thereon, the
CONTRACTOR shall before commencing with his/its work, bring to the notice
of the Engineer-in-Charge, in writing, any defects existing in said prior works.
4.2.2.5 The CONTRACTOR shall plan, well in advance for the collection of materials
and equipment and the erection of such tarpaulins, sheds, wind breakers
and/or other protection as shall or may be necessary for work during adverse
weather conditions.
4.2.2.6 The CONTRACTOR shall also arrange and bring to job site and install such
pumps and special equipment and machinery as may be necessary to enable
work during the monsoon or adverse weather conditions and shall, at his own
cost and initiative, arrange for dewatering the job sites so as to keep the
construction site and areas to be worked upon free of water.
SECTION – 4 - PERFORMANCE OF WORKS Page 52 of 192
4.2.2.7 The CONTRACTOR shall not be entitled to any extra compensation or
remuneration for or relative to any work during the monsoon or adverse
weather conditions or for or relative to any special arrangements to be made
and/or equipment or machinery to be brought to the job sites and/or operated
to enable such workings.
4.3.3.0 If the CONTRACTOR shall fail to submit to the OWNER a Progress Schedule
as envisaged above or if the Engineer-in-Charge and CONTRACTOR shall
fail to agree upon the Progress Schedule as envisaged above, then the
Engineer-in-Charge shall in consultation with the CONTRACTOR prepare the
Progress Schedule (the dates of progress as fixed by the Engineer-in-Charge
being final and binding upon the CONTRACTOR except as herein otherwise
expressly provided), and shall issue the Progress Schedule so prepared to
the CONTRACTOR, and the provisions of clause 4.3.2.0 shall apply relative
thereto as though it was as approved Progress Schedule.
4.3.8.1 The term “OWNER’s hold up” as employed in this Contract applies to a delay
by the OWNER in providing a drawing, specification, approval, change,
alteration, instruction, work front, input, material or facility or utility which the
OWNER is required to provide under the Contract and on which the progress
or further progress of the work is dependant and will include any act of the
OWNER or any other contractor appointed by the OWNER which prevents or
interrupts the further progress of the whole work or a substantial portion
thereof.
4.3.8.2 In granting or refusing in whole or part an application of the CONTRACTOR for
extension of time and in calculating the number of days for which extension of
time, if any, is to be granted to the CONTRACTOR, the Engineer-in-Charge or
OWNER, as the case may be, shall be guided by the following principles:
SECTION – 4 - PERFORMANCE OF WORKS Page 55 of 192
(i) An extension of time shall only be granted on and with reference to an
application made by the CONTRACTOR to the Engineer-in-Charge in
compliance with the provisions of Clauses 4.3.5.0 and 4.3.5.1 hereof.
(a) Extension of time will only be considered in respect of delay with respect
to Owner’s hold-up which continues after the expiry of the 15 (fifteen)
days notice period specified in (ii) above.
(v) If the extension is sought on ground(s) of force majeure, then subject to the
satisfaction of (ii) above, extension of time shall be permissible only in respect
of the number of days during which the performance of any activity or all
activities were insurmountably prevented by the force majeure and impacted
the critical path.
4.3.9.0 Upon an extension of the time for completion of the work or any part of the
work or any operation(s) involved therein, the extended date of completion
shall be deemed to be the relative date of completion in the Progress
Schedule.
4.3.10.0 The extension of time shall be the sole remedy of the CONTRACTOR for any
cause or event of delay and the CONTRACTOR shall not be entitled in
addition to or in lieu of such extension, to claim any damages or
compensation for extended stay or otherwise whether under the law
governing contracts or quasi-contracts or any other relationship, and the
CONTRACTOR hereby waives and disclaims any and all contrary rights.
4.3.11.0 No assurance, representation, promise or other statement by any personnel,
Engineer or representative of the OWNER in relation to extension of time for
commencement or completion of any work(s) or operation thereof or of the
entire works under the Contract shall be binding upon the OWNER or shall
constitute an extension of time for commencement or completion of the entire
work(s) or any part or operation thereof within the provision of Clause 4.3.5.0
or Clause 4.3.6.0 hereof, unless the same is communicated to the
CONTRACTOR by the Engineer-in-Charge under Clause 4.3.5.0 or by the
Executive Director under Clause 4.3.6.0 and the writing specifically states to
embody an extension of time within the provisions of Clause 4.3.5.0 or 4.3.6.0
as the case may be, and without prejudice to the foregoing, the mere
agreement or prescription of a Progress Schedule by the Engineer-in-Charge
or any representative of the OWNER at variance with the Progress Schedule,
or approved Progress Schedule, as the case may be, referred to in Clause
4.3.2.0 and/or 4.3.3.0, or containing an extended time of commencement or
completion in respect of the entire work(s) or any part or operation thereof
shall not anywise constitute an extension of time in terms of the contract so
as to bind the OWNER or to relieve the CONTRACTOR of all or any of his/its
liabilities under the Contract, nor shall constitute a promise on behalf of the
OWNER or a waiver by the OWNER of any of its rights in terms of the
Contract relative to the performance of the contract within the time specified
or otherwise, but shall be deemed only (at the most) as a guidance to the
CONTRACTOR for better organising his work on a recognition that the
CONTRACTOR has failed to organise his work and/or to perform the same
within the time specified in the Progress Schedule established within the
SECTION – 4 - PERFORMANCE OF WORKS Page 57 of 192
provisions of clause 4.3.2.0 or 4.3.3.0 hereof as the case may be.
4.9.0.0 SUB-CONTRACTS
4.9.1.0 The CONTRACTOR shall not assign, sub-contract or subject the whole or
any part of the work in any manner to any third party lien, right or interest,
provided that the CONTRACTOR may, with the prior written approval of
Engineer-in-Charge and subject to the other provisions in this behalf, sub
contract any particular work or part of the work to a subcontractor approved
by the Engineer-in-Charge.
SECTION – 4 - PERFORMANCE OF WORKS Page 64 of 192
4.9.2.0 Each Sub-Contractor shall be covered by the contract on the same basis as
the CONTRACTOR, provided, however, that notwithstanding approval of the
Sub-Contract as aforesaid and notwithstanding that the OWNER/Engineer-in-
Charge shall have received a copy of the Contract between CONTRACTOR
and Sub-Contractor, the CONTRACTOR shall be and shall remain exclusively
responsible to the OWNER, for which purposes the Sub-Contractor shall, vis-
a-vis the OWNER, be deemed to be the servant/agent of CONTRACTOR
employed for the performance of the particular work with full responsibility on
CONTRACTOR for all acts, omissions and defaults of the Sub-Contractor.
4.9.3.0 Subject as herein above in this behalf specifically permitted and provided, the
CONTRACTOR shall not sub-contract or assign any work under the Contract,
and any sub-contract in breach hereof shall be deemed to be an assignment
of the Contract or part or portion thereof sub-contracted, as the case may be.
4.9.4.0 If any sub-contractor engaged upon the work at the site executes any work
which in the opinion of the Engineer-in-Charge is not of the requisite standard
(the opinion of the Engineer-in-Charge being final in this behalf), the
Engineer-in-Charge may after consulting the CONTRACTOR, by written
notice to the CONTRACTOR require the CONTRACTOR to terminate such
sub-contract, and the CONTRACTOR shall upon the receipt of such notice,
terminate such sub-contract at the risks and cost of the CONTRACTOR, and
shall keep OWNER indemnified against the consequences.
4.9.5.0 Notwithstanding such sub-contract being approved by Engineer-in Charge as
herein envisaged, the CONTRACTOR shall, at the commencement of every
month, furnish the Engineer-in-Charge with a list of all sub-contractors
engaged and working at the site during the previous month, with particulars of
the general nature of the works performed by them.
5.5.2.0 GENERAL
5.5.2.1 (i) The UNIT designed, supplied and installed and/or erected by the
CONTRACTOR shall on operation under local conditions when operated
under the specified operating conditions operate to the desired capacity
to produce the desired product(s) of desired purity(ies) and quantity(ies)
at desired economy(ies). Excluded from the scope of this guarantee are
defects and shortcomings arising wholly out of defects in design(s)
furnished by a Process Licensor other than CONTRACTOR.
(ii) The materials supplied and incorporated in the UNIT including plant and
machinery and instruments shall be of good quality and workmanship
and shall conform in all respects to the specifications and the provisions
of the Contract.
(iii) The work performed pursuant to the Contract including civil and
associated work shall be of good quality and workmanship and shall
conform in all respect to the specifications and the provisions of the
Contract.
(iv) The plant, machinery and systems incorporated in the UNIT shall be so
designed and arranged that even after the expiry of the said 2 (Two)
years period, the spares, spare parts and/or suitable replacement parts
shall be and remain available at reasonable cost to enable trouble free
operation of the UNIT for its reasonable life expectancy.
5.6.0.0 COMMISSIONING
5.6.1.0 The CONTRACTOR shall be responsible to commission the UNIT and to
prove the CONTRACTOR’s performance guarantees with respect thereto.
The commissioning shall, to the extent necessary, be carried out under the
supervision of Licensor, Engineer-in-Charge and with the assistance of the
OWNER's personnel. The CONTRACTOR shall, within his responsibilities for
and the scope of Commissioning the UNIT, train OWNER's personnel at the
site of the UNIT in such number and for such period as the CONTRACTOR
considers reasonably necessary for Commissioning the PLANT.
5.6.2.0 It is envisaged that the UNIT will be commissioned within 3 (three) months of
Mechanical Completion, and the mobilisation and/or retention of the
CONTRACTOR's personnel until completion of Final Testing and
Commissioning shall be included within the Lumpsum Price of services. If,
however, for any reason not attributable to the CONTRACTOR the
Commissioning of the UNIT cannot be undertaken within 3 (three) months of
Mechanical Completion of the UNIT, the CONTRACTOR may, in consultation
with the OWNER, demobilise some or all of its personnel brought to or
retained at the site for the purpose of Commissioning. The CONTRACTOR
shall re-mobilise the required personnel on receipt of notice for
Commissioning, and the OWNER and the CONTRACTOR shall agree upon
the reasonable cost to be incurred by the CONTRACTOR for re-mobilisation
of such personnel, which shall be payable in addition to the price of services
specified in the Contract, and this additional amount shall be included within
and form part of the Final Bill of the CONTRACTOR.
5.6.3.0 In addition, within the CONTRACTOR's responsibilities for Commissioning
and within the price of services, the CONTRACTOR shall be required to
maintain watch and ward of and ensure the safety and integrity of the UNIT
until successful completion of Commissioning and issue of Commissioning
and Performance Test Certificate for the UNIT. If Commissioning of the UNIT
5.7.4.0 The CONTRACTOR’s guarantees shall be deemed to have been met once all
guarantees have been established during one or more performance tests
carried out in respect of the UNIT.
**********************************
6.1.0.0 MEASUREMENT
6.1.1.0 All measurements shall be in the metric system, and except where expressly
indicated to the contrary in the Contract, all measurements shall be taken in
accordance with the procedure set forth in the Contract documents
notwithstanding any provision(s) in the relative standard method of
measurement or any other general or local custom to the contrary.
6.1.2.0 All measurements shall be taken jointly by the Engineer-in-Charge or his
representative on the one hand and the CONTRACTOR or his representative
on the other hand, and the CONTRACTOR shall be bound to present himself
or his authorised representative for measurement(s) whenever so required by
the Engineer-in-Charge or his designated representative, and shall remain
present throughout the time required for joint measurements.
6.1.3.0 If the CONTRACTOR absents himself for any reason whatsoever on any date
appointed for joint measurements, the joint measurements shall be taken by
the Engineer-in-Charge or his representative in the absence of the
CONTRACTOR and such measurements signed by the Engineer-in-Charge
or his representative shall be final and binding upon the CONTRACTOR.
6.1.4.0 Measurements shall be signed and dated on each page by the
CONTRACTOR/CONTRACTOR’s representative and Engineer-in-Charge or
his representative. If the CONTRACTOR objects to any of the measurements
recorded, including the mode of measurement, such objection shall be noted
in the Measurement Book/Sheet against the item objected to and such note
shall be signed by the CONTRACTOR/CONTRACTOR’s representative and
Engineer-in-Charge or his representative. In the absence of any noted
objections as aforesaid, the CONTRACTOR shall be deemed to have
accepted the relative measurements as entered in the Measurement Book/
Sheets and shall be barred from making or recording any objection in respect
of the measurements recorded in the Measurement Book/Sheets.
6.1.5.0 All measurement(s) relative to which any objection have been noted in the
Measurement Book/Sheet shall be submitted to the Engineer-in-Charge for
his decision, and the decision of the Engineer-in-Charge relative thereto
(whether on the correct measurement to be adopted or on the mode of
measurement to be adopted) shall be final and binding upon the
CONTRACTOR.
(h) If the OWNER is satisfied that 25% (twenty five per cent) of the Mobilization
Advance and interest accrued till then on the Mobilization Advance has been repaid
to or recovered by the OWNER, the OWNER may on the application of the
CONTRACTOR, if the Bank Guarantee submitted by the CONTRACTOR covers and
secures only the Mobilization Advance, permit the CONTRACTOR to substitute the
Bank Guarantee by a Bank Guarantee in a format approved by the OWNER from a
Scheduled Bank in India acceptable to the OWNER for an amount reduced by 25%
(twenty five per cent) of the Bank Guarantee sought to be substituted.
(i) The provisions of paragraph (h) hereof above, shall mutatis mutandis apply to
the OWNER's satisfaction that the CONTRACTOR has repaid 50% (fifty per cent)
and/or 75% (seventy five per cent), as the case may be, of the Mobilization Advance,
and interest upto then accrued till then on the Mobilization Advance.
(j) Any Bank Guarantee furnished to secure the Mobilization Advance shall be valid,
in the first instance, for a period of 3 (three) months beyond the period of Mechanical
Completion/completion of all the works under the Contract specified in the Time
Schedule. The CONTRACTOR shall prior to the expiry of any period for which a
Bank Guarantee is valid, at the request of the OWNER, suitably extend the validity of
the Bank Guarantee(s) for such further period or periods as may be required by the
OWNER failing which, without prejudice to any other right or remedy available to the
OWNER, the OWNER shall be entitled to encash the Bank Guarantee(s) and
recover in part or whole the outstanding mobilization advance and interest from the
proceeds of the encashment.
(k) All other conditions stipulated in Clause 2.1.3.0 and Clause 2.1.4.0 hereof shall
be applicable to the Mobilization Advance(s).
6.4.2.1 (a) Interest shall be applied on the portion of the Mobilization Advance outstanding
from any amount certified for payment under a Running Account Bill up to the date of
recovery or up to a period of thirty (30) days from the date of submission of the
Running Account Bill complete in all respects to the Engineer-in-Charge, whichever
is earlier.
SECTION – 6 - MEASUREMENTS, CERTIFYING INSPECTIONS AND PAYMENTS Page 86 of 192
(b) Interest shall be applied on the portion of the Mobilization Advance outstanding
from any amount certified for payment under the Final Bill upto the date of recovery
or up to a period of ninety (90) days from the date of submission of the Final Bill
complete in all respects to the Engineer-in-Charge, whichever is earlier. The Final
Bill shall be deemed to be submitted on the date when the Engineer-in-Charge has
acknowledged receipt of the Final Bill without conveying any reservation.
6.4.2.2 The provisions aforesaid in Clause 6.4.2.0 and Clause 6.4.2.1 shall mutatis mutandis
apply to any other advance which the OWNER may agree to grant the
CONTRACTOR in relation to the Contract.
6.4.2.3 Nothing provided in the foregoing clauses hereof shall anywise be deemed to confer
any rights or entitlement on the CONTRACTOR to receive on-account payments or
Advance payments of any kind whatsoever, nor shall any failure or delay by the
OWNER to make any advance or on-account payment(s) as herein envisaged or
otherwise afford the CONTRACTOR a ground or basis for extension of time for
completion or otherwise relieve the CONTRACTOR from any of its/his liabilities
under the Contract, it being clearly understood that these on-account payments or
advance payments are only by way of assistance to the CONTRACTOR.
6.4.2.4 The Mobilization Advance shall be utilized by the CONTRACTOR solely for and in
the execution of the Contract and for no other purpose, and the CONTRACTOR
shall satisfy the OWNER/Engineer-in-charge in this regard whenever required. If it is
found that any of the advance(s) have been utilized by the CONTRACTOR in whole
or part for any other purpose or if the Contract is for any reason cancelled or
terminated, the OWNER may at its discretion recall the said advances or the
unrecovered portion(s) thereof, as the case may be, and without prejudice to any
other right or remedy available to the OWNER, recover the same by recourse to any
Bank guarantee(s) furnished by the CONTRACTOR to the OWNER.
6.4.3.0 The approved Bill of Materials shall form the basis for the calculation of “on-
account” payments with respect to supplies of materials. It is understood,
however, that the Bill of Materials or approval thereof by the OWNER shall not
in any way relieve the CONTRACTOR of its full responsibility to supply to the
OWNER within the scope of supply, any and all materials whatsoever required for
the performance of the work within the scope of work, or otherwise
howsoever confine the responsibility of the CONTRACTOR within the scope of
supply to the supply of materials indicated in the Bill of Materials, nor shall it
otherwise be assumed or be deemed or construed as an acceptance by the
OWNER of the adequacy or sufficiency of the materials listed in the Bill of
Materials to meet the quantitative and/or qualitative requirements of the materials
required to be supplied by the CONTRACTOR under the scope of supply or
otherwise in any manner operate to bind the OWNER or to limit the liability of the
CONTRACTOR, such Bill(s) of Materials being designed only to provide a basis
for making “on account” payments to the CONTRACTOR for materials supplied,
with a view that the OWNER shall make “on account” payments to the
CONTRACTOR for the various materials supplied on the basis thereof in the
manner and at the time in this behalf provided for in the contract.
6.4.4.0 The approved Schedule of Activities shall form the basis for the calculation of on
account payments with respect to services/works performed by the
CONTRACTOR. It is however understood that the Schedule of Activities or
approval thereof by the OWNER shall not in any way relieve the CONTRACTOR
of his full responsibility to perform within the scope of services/works whatsoever
is required for the performance of the work covered by the scope of work or
SECTION – 6 - MEASUREMENTS, CERTIFYING INSPECTIONS AND PAYMENTS Page 87 of 192
otherwise however confine the responsibility of the CONTRACTOR to the
performance of the services indicated in the Schedule of Activities, nor shall
otherwise be assumed or be deemed or construed as an acceptance by the
OWNER of the adequacy or sufficiency of the work/activities listed in the Schedule
of Activities to meet the quantitative and/or qualitative requirements of services
required to be performed or work required to be done by the CONTRACTOR
under the scope of services or otherwise in any manner operate to bind the
OWNER or to limit the liability of the CONTRACTOR, such Schedule of Activities
being designed primarily to provide a basis for making On Account payments to
the CONTRACTOR for works/services performed, with a view that the
OWNER shall make “On Account” payments to the CONTRACTOR for the
work/services performed on basis thereof in the manner and at the time in this
behalf provided for in this Contract.
6.4.5.0 For the purposes of making “on account” payments for the work performed,
monthly or otherwise as the Engineer-in-Charge may specify in this behalf, the
CONTRACTOR shall make a quantitative assessment of the work performed by
the CONTRACTOR as listed in the Schedule of Activities during the preceding
month or other specified period and shall submit a Running Account Bill (in the
form prescribed by the OWNER) in quadruplicate to the Engineer-in-Charge for
the works performed during the said month/period with detailed measurement
thereof, the said Running Account Bill(s) to be drawn by applying the rates
applicable under the Schedule of Activities to the applicable items, which shall be
subject to certification by the Engineer-in-Charge specified for the purpose. The
Engineer-in-Charge shall thereafter have a summary verification undertaken of the
work and quantities entered in the Running Account Bills and shall certify the
Running Account Bills for payments on basis of such verification.
6.4.5.1 For the purpose of making “On Account” payment for materials supplied
within the scope of supply other than payments made in advance monthly or
otherwise as the Engineer-in-Charge may specify in this behalf, the
CONTRACTOR shall make a quantitative list of material supplied by the
CONTRACTOR within the scope of supplies at the job site and of the “On
Account” payment made in respect thereof prior thereto, and of the “On Accounts”
payment(s) becoming due in respect thereof during the preceding month or other
specified period as the case may be supported by the Certificate of Verification
and Good Condition given by the Engineer-in- Charge in order to qualify for the
relative on account payment claimed as due. The CONTRACTOR shall submit
such assessment in the form of a Running Account Bill prepared in the format
prescribed or approved by the OWNER in this behalf in quadruplicate to the
Engineer-in-Charge. The Running Account Bill(s) shall be drawn by applying
applicable parts of the price(s) for relative materials as indicated in the Bill(s) of
materials for the applicable item(s) and shall be subject to certification by the
Engineer-in-Charge. The Engineer-in- Charge shall thereafter have a summary
verification undertaken of the materials and quantities entered in the Running
Account Bill(s) and of the amount claimed and shall certify the Running Account
Bill(s) for payment on the basis of such verification.
6.4.6.0 The amount certified for payment by the Engineer-in-Charge on any Running
Account Bill within the provisions for “on account” payments in the Contract
documents shall be conclusive for the determination of any “on account”
payments and no claim shall be entertained by the OWNER contrary thereto or in
contradiction thereof.
6.4.6.1 In any certificate for on account payment, the Engineer-in-Charge shall be
authorised to adjust in whole or part, any previous amount certified by error.
6.8.2.1 Upon issue of the Final Certificate, the CONTRACTOR shall be deemed to
have released, acquitted and discharged the OWNER from and against all
SECTION – 6 - MEASUREMENTS, CERTIFYING INSPECTIONS AND PAYMENTS Page 94 of 192
claims (known or unknown), liens, demands or causes of action of any kind
whatsoever arising out of or relating to the Contract or otherwise howsoever
touching or affecting the same.
6.8.3.0 Forthwith on application made by the CONTRACTOR in this behalf
accompanied by the Final Certificate, or within 84 (Eighty Four) days of the
OWNER passing the CONTRACTOR’s Final Bill, whichever shall be later, the
OWNER shall cancel and return to the CONTRACTOR all previous Bank
Guarantees remaining unutilised in the hands of the OWNER, and upon such
cancellation and return, the OWNER shall stand discharged of all obligations/
liabilities under the Contract provided that the cancellation and return of any
Bank Guarantee(s) furnished by the CONTRACTOR as and by way of
security deposit shall be subject to the CONTRACTOR replacing such Bank
Guarantee(s) with a Bank Guarantee from any Bank in India (including the
Indian Branch of foreign Bank) in a format acceptable to the OWNER
covering 10% (ten percent) of the value (as determined by the OWNER) of
equipments/works replaced or repaired during the Defect Liability Period for
the unexpired term of defect liability in respect thereof plus a 3 (three) months
claim period.
************************
7.0.0.0 TERMINATION
7.0.1.0 Notwithstanding anything elsewhere herein provided and in addition to any
other right or remedy of the OWNER under the CONTRACT or otherwise
(including the right of the OWNER to discount by way of price adjustment
under the provisions of Clause 4.4.0.0 hereof and associated Clauses
thereunder), the OWNER shall be entitled to terminate the CONTRACT by
written notice at any time during its currency on or after occurrence of any
one of the following events/contingencies, namely :
(i) Breach or failure by the CONTRACTOR of any of the obligations of
the CONTRACTOR under the Contract, including :
(a) Failure to start the work within 84 (Eighty Four) days of the
date of issue of the Acceptance of Bid by the OWNER,
notwithstanding the OWNER having made available to the
CONTRACTOR the work front necessary for the
commencement of work.
(b) Failure to commence work at site within 21 (Twenty-One) days
of the time prescribed in this behalf in the Progress Schedule
or to commence supply of any material within 21 (Twenty One)
days of the time prescribed in this behalf in the Delivery
Schedule.
(c) Failure to carry out or carry on the works or any of them to
meet the Progress Schedule resulting in a delay of 28 (Twenty
Eight) days or more in the actual performance of the work, or
failure to complete any supplies to meet the Delivery Schedule
resulting in a delay of 28 (Twenty Eight) days or more in the
scheduled deliveries of materials.
(d) Failure to provide at the job site, within 21 (twenty one) days of
being required to do so by the Engineer-in-Charge, sufficient
labour, material, equipment, machinery, temporary works
and/or facilities required for the proper and/or due execution of
the work or any part thereof.
(e) Failure to execute the works or any of them in accordance with
the Contract or disobedience of any order or instruction of the
Engineer-in-Charge or negligence or lack of expertise in the
performance of the work, or failure to supply materials of
quality conforming to the requirements of the contract.
(f) Abandonment of the works or any part thereof.
(g) Substantial suspension of the works or any part thereof for a
period of 14 (Fourteen) days or more without the authority of
the Engineer-in-Charge.
(h) Failure to execute the Contract in terms of the Form of
Contract forming part of the Bid Documents within 30 (thirty)
days of the date of issue of the Letter of Acceptance by the
OWNER or within such extended period as may be permitted
by the OWNER in this behalf.
*********************************
8.1.0.0 TAXES
8.1.1.0 Except as herein elsewhere expressly otherwise provided, the
CONTRACTOR shall be exclusively liable for the payment of any and all fees,
cesses, duties, taxes and levies now or hereafter imposed, increased or
modified in respect of any work done and/or material supplied and for the
payment of all contributions and taxes for unemployment compensations,
welfare, insurance, old age pension and/or annuity or gratuity now or
hereinafter imposed by the Central or State Government or authority with
respect to or covered by the wages, salaries or other compensations paid to
person employed or engaged by the CONTRACTOR, and the
CONTRACTOR hereby undertakes to indemnify and keep indemnified the
OWNER from and against the same and all claims, actions, demands and
payments whatsoever against the OWNER whatsoever arising therefrom or in
connection therewith.
8.1.2.0 Except as herein elsewhere expressly otherwise provided, the
CONTRACTOR shall be liable for and shall pay any and all Indian fees,
cesses, taxes, duties and levies assessable against CONTRACTOR in
respect of or pursuance to the Contract.
8.1.3.0 In addition, the CONTRACTOR shall be responsible for payment of all Indian
duties, levies, and taxes assessable against the CONTRACTOR or
CONTRACTOR’s employees or Sub-contractor’s whether corporate or
personal or applicable in respect of property.
(ii) If after the date of the last Price Bid of the CONTRACTOR relevant to the
Contract and prior to the Relevant Date, any new output tax is introduced in
addition to the taxes then existing relevant to the execution of the works, on
proof of payment by the CONTRACTOR, the OWNER will reimburse the
CONTRACTOR the amount of such new tax paid by the CONTRACTOR in
respect of the work performed by the CONTRACTOR upto the Relevant Date.
(iii) If after the date of the last Price Bid of the CONTRACTOR relevant to the
Contract and prior to the Relevant Date, a new output tax is introduced in lieu of
an existing output tax(es) and the rate and impact of the new tax is in excess in
aggregate of the rate and impact of existing tax(es) which it replaces, the
OWNER shall on satisfactory proof reimburse the CONTRACTOR the
additional tax paid by the CONTRACTOR as a result of the imposition of the
new tax in respect of the work performed by the CONTRACTOR upto the
Relevant Date. If, on the other hand, the rate and impact of the new tax is less
than the aggregate rate and impact of the tax(es) which it replaces, the
CONTRACTOR shall pass on to the OWNER the benefit thereof as determined
by the OWNER (whose decision in this behalf shall be final and binding on the
CONTRACTOR) by reduction in the amounts payable by the OWNER to the
CONTRACTOR.
(iv) If after the Acceptance of Tender and prior to the Relevant Date, the Goods
and Service Tax or equivalent New Central Tax in lieu of Excise Duty, Service
Tax and Central Sales Tax and/or any other Central Taxes (in this clause
hereinafter referred to as the “New Central Tax”) is introduced and the rate of
such New Central Tax is higher than the combined rate of the Central taxes
which it replaces, then the OWNER will reimburse the CONTRACTOR the
additional output tax burden borne by the CONTRACTOR by virtue of the
higher rate of the New Central Tax in respect of the work performed by the
CONTRACTOR upto the Relevant Date. In calculating the additional output tax
burden for the purpose of reimbursement, benefit of any difference in
abatement in the original Central Tax and the New Central Tax shall be passed
on to the Owner.
(v) If the New Central Tax is levied at a rate lower than the combined rate of the
Central taxes which it replaces, the CONTRACTOR shall pass on to the
OWNER the benefit or advantage which it has gained as a result of the lower
rate of the New Central Tax along with any difference in abatement in the
original Central Tax and the New Central Tax.
(vi) If, after the Acceptance of Tender, and prior to the Relevant Date, the State(s) in
which the work(s) is/are to be carried out imposes a Goods and Service Tax or
equivalent New State Tax in lieu of VAT, Local Sales Tax (including tax on sale
of goods under works contracts) and Entry Tax and/or any other State Tax(es)
is introduced, (in this clause hereinafter referred to as the “New State Tax”) and
SECTION – 8 - MISCELLANEOUS Page 103 of 192
the rate of such New State Tax is higher than the combined rate of the State
taxes which it replaces, then the OWNER will reimburse the CONTRACTOR
the additional tax burden borne by the CONTRACTOR by virtue of the higher
rate of the New State Tax in respect of the work performed by the
CONTRACTOR upto the Relevant Date. In calculating the additional tax burden
for the purpose of reimbursement, benefit of any difference in abatement in the
original State Tax and in the New State Tax shall be passed on to the Owner.
(vii) If the New State Tax is levied at a rate lower than the combined rate of the
State taxes which it replaces, the CONTRACTOR shall pass on to the OWNER
the benefit or advantage which it has gained as a result of the lower rate of the
New State Tax along with any difference in abatement in the original State Tax
and the New State Tax.
(viii) If, after the acceptance of tender and prior to the Relevant Date, the New
Central Tax and the New State Tax is replaced by an Integrated Goods and
Service Tax (howsoever designated) (hereinafter called the “Integrated Tax”)
then the provisions of Sub-clauses (iv) to (vii) above shall mutatis mutandis
apply with respect to such Integrated Tax to the extent that it replaces the New
Central Tax and the New State Tax, and in applying the said Sub-clauses, the
increase or benefit shall be calculated with reference to the impact of the
Integrated Tax in comparison to the combined impact of the New Central Tax
and the New State Tax.
(ix) For purpose of calculating the impact of any benefit to be passed to the
OWNER under sub-clauses (iii), (iv), (v), (vii) and (viii) above, if the
CONTRACTOR fails to submit satisfactory documents in relation to such benefit
to the OWNER then the benefit shall be determined by the OWNER and such
determination by the OWNER shall be final and binding on the CONTRACTOR.
8.1.4.1 If there is an increase in the rate of output tax (CST, VAT, Excise Duty, Service
Tax and Goods and Service Tax (GST) etc) or any new output tax is introduced
in addition to the exiting taxes in lieu of existing taxes where the total financial
implication on account of new output taxes is more and arises beyond the
contractual completion period (“Relevant Date” as described in 8.1.4.0 (i)),
Owner shall reimburse the same, if the increase in output taxes or new output
taxes is entitled for tax credit to the Owner. In other cases, Contractor shall bear
the increase in the rates of existing taxes or any new output tax.
8.1.5.0 The CONTRACTOR shall ensure that it is registered with the respective tax
authorities in the Centre and the applicable State(s) in which the work is to be
executed, and shall submit to the OWNER self attested copy(ies) of such
registration certificate(s). Any taxes/duties/levies claimed by the CONTRACTOR
shall be claimed by issuing a proper Invoice raised on the OWNER indicating
details/elements of all taxes charged and necessary requirements as prescribed
under the respective tax laws. The CONTRACTOR shall mention correct and
valid registration numbers applicable to the tax charged on all invoices raised on
the OWNER.
8.1.5.1 The CONTRACTOR shall reimburse to or make good to the OWNER any loss to
the OWNER resulting from a claim by the OWNER of any tax credit being
rejected/disallowed by any tax authority due to non deposit of taxes or non-
compliance of tax laws by the CONTRACTOR or of any requirement or formality
to be fulfilled by the CONTRACTOR to qualify the OWNER for such tax credit.
8.1.5.3 The OWNER will issue/provide Road Permits to the CONTRCTOR only in
respect of material directly purchased by the OWNER and transported by the
CONTRACTOR. In such event, the CONTRCTOR will be obliged to ensure the
proper utilization of the Road Permit issued /provided by the OWNER for the
specific supply, and in case of the seizure of goods or vehicle transporting the
goods, the CONTRCTOR will be solely responsible for release of the
goods/vehicle and shall reimburse the OWNER any resultant litigation costs
incurred by the OWNER.
(iii) The Building and Other Construction Workers’ Welfare Cess Act, 1996,
8.2.1.2 The CONTRACTOR shall also be responsible at its own cost and initiative to
pay directly to the prescribed authorities and bear any and all cess(es) payable
under the Building and Other Construction Workers’ Welfare Cess Act, 1996
with respect to the contract and work covered thereunder and with respect to
any subsidiary contract or sub-contract entered into by the CONTRACTOR for
the performance thereof, and shall indemnify and keep indemnified the OWNER
from and against any liability in respect thereof.
8.15.1.1 Application for such consent shall be submitted to the OWNER in writing
outlining the intended use of the relative material and shall be submitted to
the OWNER at least one month prior to the expected use accompanied by
the text of the relative publication in which it is sought to be used.
Photographs should be accompanied by their caption. An application shall not
be understood to have been permitted unless expressly permitted in writing
by the OWNER.
8.16.0.0 WAIVER
8.16.1.0 It shall always be open to the OWNER, by written communication to the
CONTRACTOR, to waive in whole or part any right or the enforcement of any
right or remedy which the OWNER may have against the CONTRACTOR or
of any obligations which the CONTRACTOR may have hereunder, provided
always that :
SECTION – 8 - MISCELLANEOUS Page 114 of 192
i) No waiver shall be presumed or inferred unless made in a written
communication addressed by the OWNER to the CONTRACTOR and
specifically communicated as a Waiver;
ii) No waiver of any right or part of any right on one occasion shall be
deemed to be a waiver or abandonment of that right for all occasions with
the intent that a waiver once given shall be limited to the specific waiver
and shall be without prejudice to the right of the OWNER to insist upon
the strict adherence of the attendant obligations of the CONTRACTOR
and/or the future enforcement of the right by the OWNER in respect of the
same and/or any other dependent obligation.
8.17.0.0 CONTRACTOR'S ESTABLISHMENT
8.17.1.0 It is understood that the establishment of the CONTRACTOR (and any Sub-
contractor engaged by the CONTRACTOR) constitutes an independent
establishment involved inter alia in undertaking works and/or services for
others of the nature and kind forming the subject matter of the Contract. It is
consequently understood that all the employees of the CONTRACTOR (and
any Sub-contractor engaged by the CONTRACTOR) are the employees of
the independent establishment of the CONTRACTOR or Sub-contractor (as
the case may be) who have been and will be appointed solely for and/or with
reference to the work of that establishment, and have not been and will not be
appointed specifically or otherwise for the sole purpose of the work covered
by the present Contract. To this end, each CONTRACTOR (and Sub-
contractor engaged by the CONTRACTOR) shall issue to each of its
employees deputed to the job-site to perform any work in relation to the
Contract, a regular letter of appointment for employment in the
CONTRACTOR's/ Sub-contractor's independent establishment, with authority
in the CONTRACTOR/ Sub-contractor to employ or depute him for or in
relation to any work or engagement assumed by the CONTRACTOR/Sub-
contractor from time to time in the course of its business and the production of
a certified copy of each letter of appointment duly acknowledged by the
concerned employee shall be a pre-condition for the issue of a Gate Pass to
any employee of the CONTRACTOR/Sub-contractor into any area, the entry
to which is restricted by the OWNER.
*******************************
9.0.0.0 ARBITRATION
9.0.1.0 Subject to the provisions of Clauses 6.7.1.0, 6.7.2.0 and 9.0.2.0 hereof, any dispute
arising out of a Notified Claim of the CONTRACTOR included in the Final Bill of the
CONTRACTOR in accordance with the provisions of Clause 6.6.3.0 hereof, and any
dispute arising out of any claim(s) of the OWNER against the CONTRACTOR shall
be referred to the arbitration of a Sole Arbitrator selected in accordance with the
provisions of Clause 9.0.1.1 hereof. It is specifically agreed that the OWNER may
prefer its claim(s) against the CONTRACTOR as counter-claim(s) if a Notified Claim
of the CONTRACTOR has been referred to arbitration. The CONTRACTOR shall
not, however, be entitled to raise as a set-off, defence or counter-claim any claim
which is not a Notified Claim included in the CONTRACTOR's Final Bill in
accordance with the provisions of Clause 6.6.3.0 hereof.
9.0.1.1 The Sole Arbitrator referred to in Clause 9.0.1.0 hereof shall be selected by the
CONTRACTOR out of a panel of 3 (three) persons nominated by the OWNER for
the purpose of such selection, and should the CONTRACTOR fail to select an
arbitrator within 30 (thirty) days of the panel of names of such nominees being
furnished by the OWNER for the purpose, the Sole Arbitrator shall be selected by
the OWNER out of the said panel.
9.0.1.2 If a dispute arises with reference to any of the matters referred to in Paragraphs (i)
and/or (ii) of Clause 9.0.2.0 hereof before the appointment of the sole Arbitrator
under this clause, such dispute shall be referred for decision of the General Manager
under Clause 9.0.2.0 hereof and the appointment of the sole Arbitrator under this
Clause shall be subject to and without prejudice to Clause 9.0.2.0 and the sole
Arbitrator so appointed shall refrain from proceeding in the arbitration so far as
concerns any such disputed matter until the decision of the General Manager or his
nominee is rendered under Clause 9.0.2.0 in respect thereof. If a dispute with
respect to any of the said matters arises after a statement of claim is filed during the
course of the arbitration proceedings commenced under Clause 9.0.1.0 with respect
to any of the said matters, the Arbitrator shall forthwith refrain from proceeding
further in the arbitration so far as concerns any such disputed matters until the
decision of the General Manager or his nominee under Clause 9.0.2.0 is rendered,
and if necessary, the Arbitrator so appointed under this Clause shall direct the
parties before him for the purpose to make reference of such dispute(s) to the
General Manager or his nominee under Clause 9.0.2.0.
9.0.2.0 Any dispute(s) or difference(s) with respect to or concerning or relating to any of the
following matters are hereby specifically excluded from the scope, purview and ambit
of the Arbitration Agreement embodied in Clause 9.0.1.0 with the intention that any
dispute or difference with respect to any of the said following matters and/or relating
to the Arbitrator's or Arbitral Tribunal's jurisdiction with respect thereto shall not and
cannot form the subject- matter of any reference or submission to arbitration under
Clause 9.0.1.0, and the Arbitrator or the Arbitral Tribunal shall have no jurisdiction to
entertain the same or to render any decision with respect thereto, and such matter
shall be referred to the General Manager for decision by the General Manager or his
nominee and shall be decided by the General Manager or his nominee, as the case
may be (whose decision shall be final and binding on the OWNER and the
CONTRACTOR) prior to the Arbitrator appointed under Clause 9.0.1.0 proceeding
with or proceeding further with the reference, as the case may be. The said excluded
matters are:
9.2.0.0 GENERAL
9.2.1.0 Notwithstanding the existence of any arbitration or conciliation in terms hereof or
otherwise, the CONTRACTOR shall continue and be bound to continue and perform
all its/ his outstanding obligations in all respects under the Contract (unless the
Contract is determined by the OWNER), and the CONTRACTOR shall remain liable
and bound in all respects under the Contract.
9.2.2.0 The provisions of this Section 9 shall apply for the resolution of disputes between the
OWNER and the CONTRACTOR irrespective of whether the CONTRACTOR is a
foreign entity or an Indian entity, or whether the CONTRACTOR is an undertaking in
public sector or the private sector.
*******************************
SECTION – 8 - MISCELLANEOUS Page 119 of 192
SECTION – 10
SAFETY CODE AND REGULATIONS
10.0.0.0 GENERAL
10.0.1.0 The CONTRACTOR shall adhere to safe construction practices and guard
against hazardous and unsafe working conditions and shall comply with the
OWNER's safety rules as set forth herein.
10.0.2.0 In addition, the CONTRACTOR shall adhere to and be bound by the "Safety
Practices During Construction" (OISD-GDN-192) formulated by the Oil
Industry Safety Directorate from time to time. A copy of the existing "Safety
Practices During Construction" as presently formulated by the Oil Industry
Safety Directorate is annexed hereto as Appendix III.
10.0.3.0 In the event of any irreconcilable conflict between the “Safety Practices
During Construction” prescribed by the Oil Industry Safety Directorate and the
Safety provisions set out herein, the "Safety Practices During Construction"
established by the Oil Industry Safety Directorate shall prevail to the extent of
the irreconcilable conflict.
10.0.4.0 In this Section any reference to the Refinery shall wherever applicable include
any existing Plant, Unit or Installation (other than a Refinery) in or adjacent to
which the job site or any part thereof is located.
10.4.0.0 SCAFFOLDING
10.4.1.0 Suitable scaffolding shall be provided for workmen for all works that cannot
safely be done from the ground or from solid construction except such short
period work as can be done safely from ladders. When a ladder is used, an
extra person shall be engaged for holding the ladder and if the ladder is used
for carrying materials as well, suitable footholds and handholds shall be
provided on the ladder and the ladder shall be given an inclination not steeper
than 1 in 4 (1 horizontal 4 vertical)
10.4.2.0 Scaffolding or staging more than 12' above the ground floor, swung or
suspended from an overhead support or erected with stationary support shall
have a guard rail properly attached, bolted, braced and otherwise rewinded at
least 3' high above the floor or platform of scaffolding or staging and
extending along the entire length of the outside and ends thereof with only
such openings as may be necessary for the delivery of materials. Such
scaffolding or staging shall be so fastened as to prevent it from swaying from
the building or structure.
10.4.3.0 Working platforms, gangways and stairways should be so constructed that
they should not sag unduly or unequally and if the height of the platform or
the gangway or the stairway is more than 12' above ground level or floor
level, they should be closely boarded, should have adequate width and
should be suitably fastened as described in Clause 10.4.2.0 above.
10.4.4.0 Every opening in the floor of a building or in a working platform shall be
provided with suitable fencing or railing whose minimum height shall be 3 feet
to prevent the fall of persons or materials by providing.
10.4.5.0 Safe means of access shall be provided to all working platforms and other
working places. Every ladder shall be securely fixed. No portable single
ladder shall be over 30' in length while the width between the side rails in rung
ladder shall in no case be less than 11.5" for ladder up to and including 10' in
length. For longer ladders this width would be increased by at least ¼'' for
each additional foot of length. Uniform step spacing shall not exceed 12''.
Adequate precautions shall be taken to prevent danger from electrical
equipment. No materials on any site of work shall be so stacked or placed as
to cause danger or inconvenience to any person or public. The
CONTRACTOR shall also provide all necessary fencing and lights to protect
the workers and staff from accidents, and shall be bound to bear the
expenses of defence of every suit, action or other proceedings, that may be
brought by any person for injury sustained owing to neglect of the above
precautions and to pay damages and costs which may be awarded in any
such suit or action or proceedings to such person, or which may with the
consent of the CONTRACTOR be paid to compromise any claim by any
person.
10.6.0.0 DEMOLITION
10.6.1.0 Before any demolition work is commenced and also during the process of
such work all roads and open areas adjacent to the work site shall either be
closed or suitably protected.
10.6.2.0 No electric cable or apparatus which is liable to be a source of danger over a
cable or apparatus used by the operator shall remain electrically charged.
10.6.3.0 All practical steps shall be taken to prevent danger to persons employed, from
risk of fire or explosion or flooding. No floor, or other part of the building shall
be so overloaded with debris or material as to render it unsafe.
10.14.0.0 NO EXEMPTION
10.14.1.0 Notwithstanding anything provided in Clauses 10.0.0.0 to 10.13.0.0, the
CONTRACTOR shall be bound by the provisions of any other Act or rules in
force in the Republic of India, with a view that the provisions hereof shall be in
addition thereto and not in lieu thereof.
10.14.2.0 The works throughout including any temporary works shall be carried on in
such a manner as not to interfere in any way whatsoever with the traffic on
any roads or footpaths at the site or in the vicinity thereof or with any existing
works whether the property of the OWNER or of a third party.
10.14.3.0 In addition to the above, the CONTRACTOR shall abide by the safety code
provision as per CPWD Safety Code framed from time to time.
10.14.4.0 The CONTRACTOR shall also arrange to obtain valid gate passes for his
men and equipment from the concerned authorities of the Refinery/Project
10.14.5.0 No man/material/equipment not covered by valid passes shall be permitted
within the Refinery/ Project area and no material/equipment shall be permitted
to be taken out of the Refinery/Project area, unless authorised by the
concerned authorities of the Refinery/Project. The CONTRACTOR shall be
held fully responsible for any or all delays/ losses/ damages that may result
consequent on any lapse(s) that may occur on the part of his sub-
contractors/employees in this regard.
*******************************
The following documents listed in Appendices hereto shall be deemed to form part of
these General Conditions of LSTK Contracts:
(i) CONTRACTOR’s LABOUR REGULATIONS (APPENDIX-I)
(ii) MODEL RULES FOR LABOUR WELFARE (APPENDIX-II)
(iii) SAFETY PRACTICES DURING CONSTRUCTION (APPENDIX-III)
(iv) FORM OF CONTRACT (APPENDIX-IV)
(v) FORM OF BANK GUARANTEE TO COVER EARNEST MONEY DEPOSIT
(EMD) (APPENDIX-V)
(vi) FORM OF BANK GUARANTEE TO COVER LUMPSUM ADVANCE
(MOBILISATION) (APPENDIX-VI)
(vii) FORM OF BANK GUARANTEE TO COVER SECURITY DEPOSIT
(APPENDIX-VII)
*******************************
*******************************
1. Definitions
(a) "Workplace" means a place at which, on an average, twenty or more workers
are employed on any day during which the Contract work is in progress.
(b) "Large Workplace" means a place at which, on an average 500 or more
workers are employed.
2. First Aid
i) At every workplace, there shall be provided and maintained in a readily
accessible place First Aid appliances including an adequate supply of sterilized
dressings and sterilized cotton wool as prescribed in the Factory Rules of the
State in which the work is carried on. The appliances shall be kept in good order
and in large work places, they shall be placed under the charge of a responsible
person who shall be trained in First Aid treatment and who shall also be readily
available during working hours. The First Aid boxes at the rate of not less than
one box for 150 contract labour or part thereof shall be ordinarily employed.
Adequate arrangement shall be made for immediate recoupment of
items/equipment when necessary.
ii) At large work places, where hospital facilities are not available within easy
distance of the Works, First Aid posts shall be established and be run by a
trained compounder.
Where large work places are remotely situated far away from regular hospitals,
an indoor ward shall be provided with one bed for every 250 employees.
Where large work places are situated in cities, towns or in their suburbs and no
beds are considered necessary owing to proximity of city or town hospitals,
suitable transport shall be provided to facilitate removal of urgent cases to these
hospitals. At other workplaces, some conveyance shall be kept readily available
to take injured person or persons suddenly taken seriously ill to the nearest
hospital.
At large work places, there shall be provided and maintained an ambulance room
of the prescribed sizes, containing the prescribed equipment and in the charge of
such medical and nursing staff as may be prescribed. For this purpose, the
relevant provisions of the Factory Rules of the State Government area where the
work is carried on may be taken as the prescribed standard.
3. Accommodation for labour : The Contractor shall during the progress of the
Works, provide, erect and maintain necessary temporary living accommodation and
ancillary facilities for labour at his own expense and to standard and scales as
approved by the Engineer-in-charge. However, following specifications shall be
followed :
(a) (i) The minimum height of each hut at the eaves level shall be 2.10m (7ft)
and the floor area to be provided will be at the rate of 2.7 sq.m (30sq.ft.)
for each member of the worker's family staying with the labourer.
(ii) The Contractor shall in addition construct suitable cooking places having
a minimum area of 1.80mX 1.50m (6' x 5') adjacent to the hut for each
family.
*******************************
CONTENTS
SECTION DESCRIPTION
1.0 INTRODUCTION
2.0 SCOPE
3.0 DEFINITIONS
4.0 GENERAL DUTIES
4.1 GENERAL DUTIES OF EXECUTION AGENCIES
4.2 GENERAL DUTIES OF OWNERS
5.0 SAFETY PRACTICES AT WORK PLACES
5.1 GENERAL PROVISIONS
5.2 MEANS OF ACCESS AND EGRESS
5.3 HOUSEKEEPING
5.4 PRECAUTIONS AGAINST THE FALL OF MATERIALS AND PERSONS AND
COLLAPSE OF STRUCTURES
5.5 PREVENTION OF UNAUTHORISED ENTRY
5.6 FIRE PREVENTION AND FIRE FIGHTING
5.7 LIGHTING
5.8 PLANT, MACHINERY, EQUIPMENT AND HAND TOOLS
6.0 CONSTRUCTION ACTIVITIES
6.1 EXCAVATION
6.2 SCAFFOLDING, PLATFORMS & LADDERS
6.3 STRUCTURAL WORK, LAYING OF REINFORCEMENT & CONCRETING
6.4 ROAD WORK
6.5 CUTTING/WELDING
6.6 WORKING IN CONFINED SPACES
6.7 PROOF/PRESSURE TESTING
6.8 WORKING AT HEIGHTS
6.9 HANDLING AND LIFTING EQUIPMENT
6.10 VEHICLE MOVEMENT
6.11 ELECTRICAL
6.12 OFFSHORE
6.13 DEMOLITION
6.14 RADIOGRAPHY
6.15 SAND/SHOT BLASTING/SPRAY PAINTING
6.16 WORK ABOVE WATER
7.0 ADDITIONAL SAFETY PRECAUTION FOR UNITS WITH HYDROCARBONS
8.0 FIRST
9.0 DOCUMENTATION
10.0 SAFETY AWARENESS & TRAINING
11.0 REFERENCES
ANNEXURE - I
1.0 INTRODUCTION
Safety in Construction Management deserves utmost attention especially in the
hydrocarbon industry, such as Exploration, Refineries, Pipelines and Marketing
installations, Gas Processing units etc. Construction is widely recognised as one of
the accident-prone activities. Most of the accidents are caused by inadequate
planning, failure during the construction process and/or because of design
deficiencies. Besides property loss, accidents also result in injuries and fatalities to
the personnel; same needs to be prevented.
The reasons for accidents during construction activities are related to unique nature
of the industry, human behaviour, difficult work-site conditions, extended odd duty
hours, lack of training & awareness and inadequate safety management. Unsafe
working methods, equipment failure and improper housekeeping also tend to
increase the accident rate in construction.
Ensuring good quality of materials, equipment and competent supervision along with
compliance of standard engineering practices shall go a long way to in built safety in
the system.
The objective of this standard is to provide practical guidance on technical and
educational framework for safety and health in construction with a view to:
(a) prevent accidents and harmful effects on the health of workers arising from
employment in construction;
(b) ensure appropriate safety during implementation of construction;
(c) provide safety practice guidelines for appropriate measures of planning, control
and enforcement.
2.0 SCOPE
This document specifies broad guidelines on safe practices to be adhered to during
construction activities in oil industry. However, before commencing any job, specific
hazards and its effects should be assessed and necessary corrective/preventive
actions should be taken by all concerned. The document is intended only to
supplement and not to replace or supersede the prevailing statutory requirements,
which shall also be followed as applicable. For Personal Protective Equipment
(PPE's), OISD-STD-155 (Part I&II) shall be referred to. The scope of this document
does not include the design aspects and quality checks during construction.
3.0 DEFINITIONS
Definitions of various terminology are given below:
· Adequate, appropriate or suitable are used to describe qualitatively or
quantitatively the means or method used to protect the worker.
· Brace: A structural member that holds one point in a fixed position with respect to
another point; bracing is a system of structural members designed to prevent
distortion of a structure.
· By hand: The work is done without the help of a mechanised tool.
· Competent Authority: A stautory agency having the power to issue regulations,
orders or other instructions having the force of law.
· Competent person: A person possessing adequate qualifications, such as
suitable training and sufficient knowledge, experience and skill for the safe
performance of the specific work. The competent authorities may define
appropriate criteria for the designation of such persons and may determine the
duties to be assigned to them.
i) Only ropes with a known safe working capacity should be used as lifting ropes.
ii) Lifting ropes should be installed, maintained and inspected in accordance with
manufacturers' instructions.
iii) Repaired steel ropes should not be used on hoists.
iv) Where multiple independent ropes are used, for the purpose of stability, to lift a
work platform, each rope should be capable of carrying the load independently.
6.10 VEHICLE MOVEMENT
6.10.1 Park vehicles only at designated places. Don't block roads to create hindrance for
other vehicles.
6.10.2 Don't overload the vehicle.
6.10.3 Obey speed limits and traffic rules.
6.10.4 Always expect the unexpected and be a defensive driver.
6.10.5 Drive carefully during adverse weather and road conditions.
6.10.6 Read the road ahead and ride to the left.
6.10.7 Be extra cautious at nights. Keep wind screens clean and lights in working
condition.
6.10.8 All vehicles used for carrying workers and construction materials must undergo
predictive/preventive maintenance and daily checks
6.10.9 Driver with proper valid driving license shall only be allowed to drive the vehicle
6.10.10 Routes shall be leveled, marked and planned in such a way so as to avoid potential
hazards such as overhead power lines and sloping ground etc.
6.10.11 While reversing the vehicles, help of another worker should be ensured at all times
6.10.12 An unattended vehicle should have the engine switched off
6.10.13 Wherever possible one-way system shall be followed
6.10.14 Barriers/fixed stops should be provided for excavation/openings to prevent fall of
vehicle
6.10.15 Load should be properly secured
6.10.16 The body of the tipper lorry should always be lowered before driving the vehicle off.
6.10.17 Signs/signals/caution boards etc. should be provided on routes.
*******************************
*******************************
FORM OF CONTRACT
CONTRACT NO.:
THIS CONTRACT made at New Delhi this ………….. day of 200 BETWEEN INDIAN
OIL CORPORATION LTD., a Government of Indian Undertaking registered in India under
the Indian Companies Act-1956, having its registered Office at G-9, Ali Yavar Jung Marg,
Bandra (East), Mumbai-400051 and the Head Office of its Refineries Division of Indian Oil
Corporation Ltd. (Refineries Division), at Scope Complex, Core-2, 4th Floor, 7 Institutional
Area, Lodhi Road, New Delhi-110003 (hereinafter referred to as the “OWNER” which
expression shall include its successors and assigns) of the One Part;
AND
, a Company registered in India under the Indian Companies Act
1913/1956 having its registered office at (hereinafter referred to as
the “CONTRACTOR”) of the other part :
WHEREAS
WHEREAS the OWNER issued Tender No. for Residual Process Design,
Detailed Engineering, Procurement, Supply, Transportation, Storage, Fabrication,
Construction, Installation, Testing, Pre-commissioning, Commissioning, Performance,
Guarantee Test Run and handing over of Unit for the of
Indian Oil Corporation Ltd. at .
AND WHEREAS the Contract with respect to the said Tender has been awarded to the
CONTRACTOR, pursuant whereto, the CONTRACTOR has to make supplies of materials
and to execute works and to undertake services with the use of the said material as more
specifically mentioned and described in the Contract Documents as hereinafter defined.
AND WHEREAS it is desirable to have a formal Document setting out the documents which
comprise the Contract and determining certain other aspects as hereinafter appearing.
ARTICLE 1
CONTRACT DOCUMENTS
1.1 The Contract Document shall comprise the following:
(i) Letter Inviting Bid/Invitation to Bidder
(ii) Instructions to Bidder
(iii) General Conditions of Contract
(iv) Special Conditions of Contract (including the Scope of Work and Time
Schedule)
(v) Specifications
(vi) Plans Exhibits to
1.2 A copy of each of the Tender Documents is annexed hereto and the said copies have
been collectively marked Annexure ‘A’ while a copy of the Detailed Letter of
Acceptance of Tender alongwith Annexures thereto and a copy of Notification of
Acceptance of Bid dated……………….are annexed hereto & said copies have been
collectively marked as Annexure-‘B’.
1.3 Where the CONTRACTOR is a Consortium of one or more entities or persons, all
members of the Consortium shall be jointly and severally liable for the performance
of the Contract and of all obligations of the CONTRACTOR arising under the
Contract and for the discharge of all the CONTRACTOR’s liabilities to the OWNER
under or in respect of the Contract and any claim of the OWNER without any
limitation of liability as between the OWNER and the members aforesaid,
notwithstanding the existence of any agreement between the said members inter se
limiting the liability of any member for or in the performance of any duties or
obligations under the Contract.
ARTICLE 2
SERVICES, SUPPLIES AND WORK
2.1 The CONTRACTOR shall make the Supplies specified in the Contract Documents
upon the terms and conditions and within the time specified in the Contract
Documents.
2.2 The CONTRACTOR shall undertake the works and perform the services specified in
the Contract Documents upon the terms and conditions and within the time specified
in the Contract documents.
ARTICLE 3
PRICE AND COMPENSATION
3.1 Subject to and upon the terms and conditions contained in the Contract Documents,
the OWNER shall pay CONTRACTOR the price for the said supplies and
Compensation for the said works and services as specified in respect to each in the
Contract Documents upon the satisfactory completion of the said supplies and
satisfactory performance of the services and/or otherwise as may be specified in this
behalf in the Contract Documents.
ARTICLE 5
ENTIRE CONTRACT
5.1 The Contract Documents mentioned in Article-1 hereof embody the entire Contract
between the parties hereto, and the parties declare that in entering this Contract they
do not rely upon any previous representation, whether express or implied and
whether written or oral, or any inducement, understanding or agreements of any kind
not included within the Contract Documents and all prior negotiations,
representations, contracts and/or agreements and understandings are hereby
cancelled.
ARTICLE 6
NOTICES
6.1 Subject to any provisions in the Contract documents to the contrary, any notice, order
or communication sought to be served by the CONTRACTOR on the OWNER with
reference to the CONTRACT shall be deemed to have been sufficiently served upon
the OWNER notwithstanding any enabling provisions under any law to the contrary,
only if delivered by hand or by Courier to the Engineer-in-Charge as defined in the
General Conditions of Contract.
6.2 Without prejudice to any other mode of service provided for in the Contract
Documents or otherwise available to the OWNER, any notice, order or other
communication sought to be served by the OWNER on the CONTRACTOR with
reference to the CONTRACT, shall be deemed to have been sufficiently served if
delivered by hand or through Courier to the principal office of the CONTRACTOR at
or other address for service subsequently notified by
CONTRACTOR to the OWNER in this behalf in writing.
ARTICLE 7
WAIVER
7.0 No failure or delay by the OWNER in enforcing any right or remedy of the OWNER in
terms of the CONTRACT or any obligation or liability of the CONTRACTOR in terms
thereof, shall be deemed to be a waiver of such right, remedy, obligation or liability,
as the case may be, by the OWNER and notwithstanding such failure or delay, the
OWNER shall be entitled at any time to enforce such right, remedy, obligation or
liability, as the case may be.
ARTICLE 9
LANGUAGE OF CONTRACT AND COMMUNICATION
9.0 The language of the Contract shall be English and all communications, drawings,
design, data, information, codes specifications and other document whatsoever
supporting the bid or otherwise exchanged under the Contract shall be in English. In
the event that any technical documentation is in any language other than English, the
document should be translated and presented to the OWNER/Engineer-in-Charge in
English and English document/translated document shall be regarded as the only
authentic document.
ARTICLE 10
GOVERNMENT OF INDIA NOT LIABLE
10.0 It is expressly understood and agreed by and between the CONTRACTOR and the
OWNER that the OWNER is entering into this agreement solely on its own behalf
and not on behalf of any other person or entity. In particular, it is expressly
understood and agreed that the Government of India is not a party to this agreement
and has no liabilities, obligations or rights thereunder. It is expressly understood and
agreed that the OWNER is an independent legal entity with power and authority to
enter into contracts, solely in its behalf under the applicable laws of India and general
principles of Contract Law. The CONTRACTOR expressly agrees, acknowledges
and understands that the OWNER is not an agent, representative or delegate of the
Government of India. It is further understood and agreed that the Government of
India is not and shall not be liable for any acts, omissions, commissions, breaches or
other wrongs arising out of the Contract. Accordingly, CONTRACTOR hereby
expressly waives, releases and foregoes any and all actions or claims, including
cross claims, impleader claims or counter claims against the Government of India
arising out of this Contract and covenants not to sue the Government of India on any
matter, claim, cause of action or thing whatsoever arising out of or under this
Contract.
ARTICLE 11
NO LIABILITY ON DIRECTOR AND EMPLOYEE
11.0 No Director, employee, consultant or agent of the OWNER or other person
representing the OWNER or acting on behalf of the OWNER in or pursuant to the
Contract or in the discharge of any obligation to the OWNER under the Contract or
otherwise in relation to the Contract shall have any personal liability to the
CONTRACTOR or any Sub-Contractor, agent, representative, director or employee
of the CONTRACTOR or to any other person acting for or on behalf of the
CONTRACTOR and the CONTRACTOR on its own behalf and on behalf of its Sub-
BY BY
(THIS DAY OF 20 )
2. 2.
*******************************
BG NO:
DATED :
VALID UPTO :
To,
Indian Oil Corporation Limited
(Refineries Division)
Dear Sirs,
In consideration of Indian Oil Corporation Limited (Refineries Division) (hereinafter called "the
Corporation" which expression shall include its successors and assigns), having agreed interalia to
consider the tender of (Name of the Tenderer)
having its Head Office/Registered Office at (Address
of the Tenderer) (hereinafter called the "Tenderer" which expression shall include its successors and
assigns), for the work of (Name of the Project/Work) at to
be awarded under Tender No. upon the Tenderer furnishing an undertaking
from the Bank as hereinafter appearing in lieu of cash deposit of the Earnest Money.
1. This Guarantee/Undertaking shall be a continuing guarantee and shall remain in full force and
effect for all claims or demands made by the Corporation on the Bank until the Corporation
discharges this Guarantee/Undertaking subject, however, that the Corporation shall have no
claims under this Guarantee/Undertaking after the midnight
of 200_ _or any written extension(s) thereof.
PROVIDED that if the aforesaid work tendered for or any part thereof shall be awarded to the
Tenderer on or before the said date, whether on the basis of accompanying tender or any
other basis, then the validity of this guarantee/undertaking shall stand automatically extended
for all claims and demands made by the Corporation for a further three months.
3. It shall not be necessary for the Corporation to proceed against the Tenderer before
proceeding against the Bank and the Guarantee/Undertaking herein contained shall be
enforceable against the Bank as principal debtor notwithstanding the existence of any other
undertaking or security for any indebtedness of the Tenderer to the Corporation and
notwithstanding that any such security shall at the time when claim is made against the Bank
or proceedings taken against the Bank hereunder, be outstanding or unrealised.
4. The amount stated by the Corporation in any demand, claim or notice made with reference to
this guarantee shall as between the Bank and the Corporation for the purpose of these
Presents be conclusive of the amount payable by the Bank to the Corporation hereunder.
5. The liability of the Bank to the Corporation under this Guarantee/Undertaking shall remain in
full force and effect notwithstanding the existence of any difference or dispute between the
Tenderer and the Corporation, the Tenderer and the Bank and/or the Bank and the
Corporation or otherwise howsoever touching these Presents or the liability of the Tenderer to
the Corporation, and notwithstanding the existence of any instructions or purported
instructions by the Tenderer or any other person to the Bank not to pay or for any cause
withhold or defer payment to the Corporation under these Presents, with the intent that
notwithstanding the existing of such difference, dispute or instructions, the Bank shall be and
remain liable to make payment to the Corporation in terms thereof.
7. Without prejudice to any other mode of service, a demand or claim or other communication
may be transmitted by the Corporation to the Bank either by post or by fax. If transmitted by
fax, the transmission shall be complete as soon as acknowledged by the Bank.
This_ day of 20
Yours faithfully
Signature :
*******************************
BG NO:
DATED :
VALID UPTO :
To,
INDIAN OIL CORPORATION LIMITED
(Refineries Division)
Dear Sirs,
WHEREAS Indian Oil Corporation Limited (hereinafter called "the Corporation" which expression shall
include its successor and assigns) has awarded to _(Name &
Address of the Contractor) hereinafter called "the Contractor" which expression shall include its
successors and assigns) the work of (Name of the Project/Work)
under and in terms of a Contract as evidenced by a Letter of Acceptance
No. dated issued by the Corporation to the Contractor
read with the relevant Tender Documents (hereinafter collectively called "the Contract" which
expression shall include any formal contract entered into between the Corporation and the Contractor
in supersession of the said Letter of Acceptance and all amendments and/or modifications therein or
in the terms of the said advance as herein stipulated) :
AND WHEREAS the Corporation has agreed to advance the Contractor, inter-alia, a sum of
Rs._ (Rupees_ only) (hereinafter
called "the said Advance"), upon the condition, inter-alia, that the said Advance together with interest
thereon at the rate of %( percent) per annum on the amount of the said Advance for
the time being outstanding shall without prejudice to any other mode of recovery available to the
Corporation be recoverable by the Corporation by deduction from the gross accepted amount of any
Running Account Bills and the Final Bill of the Contractor commencing from the first Running Account
Bill of the Contractor, and meanwhile, the said Advance shall be secured by an undertaking from a
Bank as hereinafter appearing.
i) This Guarantee/Undertaking shall be a continuing guarantee and shall remain valid and
irrevocable for all claims of the Corporation upon the Bank made up to the midnight
of _provided that the Bank shall upon the written request of the Corporation
made upon the Bank at any time within 6 (six) months from the said date extend the validity of
the Bank Guarantee by a further 6 (six) months so as to enable claims to be made under this
Guarantee by a further 6 (six) months from the said date with the intent that the validity of this
Guarantee shall automatically stand extended by a further 6 (six) months upon such request
by the Corporation.
ii) The Corporation shall have the fullest liberty without reference to the Bank and without
affecting in any way the liability of the Bank under this guarantee/undertaking, at any time
and/or from time to time to amend or vary the contract and/or any of the terms and conditions
thereof or relative to the said Advance and/or to extend time for performance of the said
contract in whole or part and/or payment of the said Advance in whole or part or to postpone
for any time and/or from time to time any of the said obligations of the Contractor and/or the
rights, remedies or powers exercisable by the Corporation against the Contractor and either
to enforce or forbear from enforcing any of the terms and conditions of or governing the said
Contract and/or the said Advance, or the securities, available to the Corporation and the Bank
shall not be released from its liability under these Presents and the liability of the Bank shall
remain in full force and effect notwithstanding any exercise by the Corporation of the liberty
with reference to any or all the matters aforesaid or by reason of time being given to the
Contractor or any other forbearance, act or omission on the part of the Corporation or any
indulgence by the Corporation to the Contractor or of any other act, matter or thing
whatsoever which under any law could (but for this provision) have the effect of releasing the
Bank from its liability hereunder or any part thereof and the Bank hereby specifically waives
any and all contrary rights whatsoever.
iii) The obligations of the Bank to the Corporation hereunder shall be as principal to principal and
shall be wholly independent of the Contract and it shall not be necessary for the Corporation
to proceed against the Contractor before proceeding against the Bank and the
guarantee/undertaking herein contained shall be enforceable against the Bank as Principal
debtor notwithstanding the existence of any undertaking or security for any indebtedness of
the Contractor to the Corporation (including relative to the said Advance) and notwithstanding
that any such undertaking or security shall at the time when claim is made against the bank or
proceedings taken against the Bank hereunder, be outstanding or unrealised.
iv) As between the Bank and the Corporation for the purpose of this undertaking, the amount
stated in any claim, demand or notice made by the Corporation on the Bank with reference to
this undertaking shall be final and binding upon the Bank as to be the amount payable by the
Bank to the Corporation hereunder.
vi) This undertaking shall not be determined or affected by any change in the constitution of the
Bank or that of the Contractor or the Corporation or any irregularity in the exercise of
borrowing powers by or on behalf of the Contractor.
vii) Without prejudice to any other mode of service, a demand or claim or other communication
may be transmitted by the Corporation to the Bank either by post or by fax. If transmitted by
fax, the transmission shall be complete as soon as acknowledged by the Bank.
(i) The Bank's liability under this guarantee/undertaking shall not exceed
(Amount in figures
& words);
(iii) The Bank shall be released and discharged from all liability under this
guarantee/undertaking unless a written claim or demand is issued to the Bank on or
before _or the date of expiry of any extension(s) thereof if this
guarantee/undertaking has been extended.
ix) The Bank doth hereby declare that Shri who is the
(designation) of the Bank is authorised to sign this undertaking on
behalf of the Bank and to bind the Bank thereby.
Yours faithfully,
Signature :
Name & Designation:_
*******************************
Dear sir,
In consideration of Indian Oil Corporation Limited (Refineries Division) (hereinafter called the
Corporation which expression shall include its successors and assigns) having awarded certain Work
for and relative to the installation of a (Name of Project) at of the Corporation to (Name &
address of Contractor) (hereinafter called the “CONTRACTOR”) upon certain terms and conditions
mentioned in the Corporation’s Letter of Acceptance No. ……….. Dated …………… read with the
CONTRACTOR’s bid and the relative Bid Documents (hereinafter collectively called the “Contract”
which expression shall include any formal Contract entered into between the Corporation and the
CONTRACTOR in supersession of the said Letter of Acceptance and all amendments and/or
modifications in the Contract) inclusive of the condition that the Contractor shall cause to be furnished
a Bank Guarantee from a Scheduled Bank in India (which includes the Indian Branch of a foreign
Bank acceptable to the Corporation) as hereinafter appearing in lieu of cash Security deposit.
We ………………. (Name of the Bank) a body corporate registered/constituted under the laws
of………………….. (hereinafter called the “BANK” which expression shall include its successors and
assigns) with the intent to bind the Bank and its successors and assigns, do hereby unconditionally
and irrevocably undertake to pay the Corporation at the project office of the Indian Oil Corporation at
New Delhi on first demand in writing without protest or demur or proof of condition any and all
amounts from time to time demanded by the Corporation from the Bank with reference to this
Guarantee/Undertaking upto an aggregate limit of US $ ……………………. (United States Dollars
…………………………….. only) and Indian Rupees ……………………….. (Rupees
…………………………….. only).
(i) The Guarantee/Undertaking herein contained shall remain in full force and effect during
the entire period that would be taken for the performance for the Contract and until the
claims of the Corporation relative thereto are satisfied and/or discharged and the
Corporation accordingly discharges this Guarantee/Undertaking subject, however, that
the Corporation shall have no claim under this Guarantee/Undertaking after midnight of
…….. 200 , unless a notice of the claim under this Guarantee/ Undertaking has been
served on the Bank before the expiry of the said date, in which event the same shall be
valid notwithstanding that the same is enforced after the expiry of the said date, provided
that the Bank shall upon the written request of the Corporation made at any time within 6
(six) months after the expiry of the said date extend this Guarantee/Undertaking for a
further 6 (Six) months from the said date within which the Corporation may make a
demand.
(iii) It shall not be necessary for the Corporation to proceed against the CONTRACTOR
before proceeding against the Bank and the Guarantee/Undertaking herein contained
shall be enforceable against the Bank notwithstanding the existence of any other security
for any indebtedness of the CONTRACTOR to the Corporation (including relative to the
security deposit) and notwithstanding that any such security shall at the time when claim
is made against the Bank or proceeding taken against the Bank hereunder, be
outstanding or unrealised.
(iv) The amount stated by the Corporation in any demand, claim or notice as due to the
Corporation from the CONTRACTOR shall as between the Bank and the Corporation for
the purpose of these presents be conclusive of the amount payable by the Bank to the
Corporation hereunder.
(v) The liability of the Bank to the Corporation under this Guarantee/Undertaking shall remain
in full force and effect notwithstanding the existence of any difference or dispute between
the CONTRACTOR and the Corporation, the CONTRACTOR and the Bank and/or the
Bank and the Corporation, or otherwise howsoever touching or affecting these presents
or the liability of the CONTRACTOR to the Corporation, and notwithstanding the
existence of any instructions or purported instructions by the CONTRACTOR or any other
person to the Bank not to pay or for any cause withhold or defer payment to the
Corporation, under these presents, with the intent that notwithstanding the existence of
such difference, dispute or instructions, the Bank shall be and remain liable to make
payment to the Corporation in terms hereof.
(vi) The Bank shall not revoke this Guarantee/Undertaking during its currency except with the
previous consent of the Corporation in writing and also agrees that any change in the
constitution of the CONTRACTOR or of the Bank or of the Corporation shall not discharge
the Bank’s liability hereunder.
(viii) The Bank doth hereby declare that Shri …………………………….. (Name and
Designation of the person) is authorised to sign this Guarantee/Undertaking on behalf of
the Bank and to bind the Bank thereby.
Yours faithfully,
For
Signature
Name and designation
Name of the Branch
*******************************
Table of Contents
1. DEFINITIONS ...................................................................................................................................... 5
2. GENERAL ............................................................................................................................................ 6
3. LOCATION OF SITE .......................................................................................................................... 8
4. SITE VISIT............................................................................................................................................ 8
5. SCOPE OF SUPPLY AND SCOPE OF WORK ............................................................................. 9
6. CONDITIONS FOR ISSUE AND RECONCILIATION OF MATERIAL .................................... 14
7. TIME SCHEDULE ............................................................................................................................. 14
8. SITE CLEANING ............................................................................................................................... 15
10. INFORMATION ABOUT EXISTING UNDERGROUND / OVERHEAD STRUCTURES/
UTILITIES/ PIPELINES .............................................................................................................................. 17
11. EMPLOYMENT OF LOCAL LABOUR AND PREFERENCE TO LAND LOSERS AND/OR
DEPENDENT OF LAND LOSERS............................................................................................................. 18
12. SETTLEMENT OF DISPUTE BETWEEN GOVT.DEPT. /PUBLIC SECTOR
UNDERTAKINGS ......................................................................................................................................... 18
13. CONCILIATION ................................................................................................................................. 19
14. ERRANT BIDDER ............................................................................................................................ 19
15. CORRUPT AND FRAUDULENT PRACTICES............................................................................ 19
16. SITE ORGANISATION..................................................................................................................... 21
17. GENERAL GUIDELINES DURING AND BEFORE ERECTION: ............................................. 21
18. MECHANISATION OF CONSTRUCTION ACTIVITIES AND MOBILISATION OF
CONSTRUCTION EQUIPMENT ............................................................................................................... 22
19. QUALITY ASSURANCE SYSTEM ................................................................................................ 23
20. TESTS AND INSPECTION OF WORKS ...................................................................................... 24
21. DISTINCTION BETWEEN SUB-STRUCTURE AND SUPERSTRUCTURE. ......................... 26
22. COMPLETION DOCUMENTS ........................................................................................................ 26
23. ADDITIONAL WORKS/ EXTRA WORKS .................................................................................... 27
24. HEALTH, SAFETY AND ENVIRONMENT (HSE) MANAGEMENT / SAFETY NORMS ...... 27
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
1. DEFINITIONS
▪ The “PROJECT” shall mean the project embracing the works and/or unit(s) forming the subject
matter of the Bid and resultant Contract.
▪ The “OWNER” shall mean Indian Oil Corporation Ltd., a Company incorporated in India and includes
the Owner’s personal representatives or successors as assigned by them from time to time.
▪ “PMC” or “CONSULTANT” shall mean TECHNIP INDIA LIMITED (TPIL), India, appointed by
‘OWNER’ M/s INDIAN OIL CORPORATION LIMITED and shall include its successors and permitted
assigns. The words “PROJECT MANAGEMENT CONSULTANT”, “PMC” & “CONSULTANT or
Authorized Representative” are synonymous.
▪ The “CONTRACTOR” shall mean the bidder selected by the OWNER for the performance of the
work and supply of materials and shall include the successors and permitted assigns of the
CONTRACTOR, and if the CONTRACTOR is joint venture or consortium, shall include each
member thereof.
▪ “Bidder” / “Tenderer” means any person, company, firm or body who is submitting Bid against the
Tender Enquiry floated by the Owner/PMC.
▪ “Bidding document / Tender document” means the totality of the documents including addendum
issued to the bidder based on which bid is to be submitted.
▪ “Government Authority” means the Government of India, any state government or any local
authority or any department, instrumentality or agency thereof or any corporation (to the extent
acting in a legislative, judicial or administrative capacity and not as a contracting party with Owner
or the Contractor) or commission under the direct or indirect control of such central, state or local
government or any political sub-division thereof or any court, tribunal or judicial body within India.
▪ “Contractor's Representative” means the person nominated by the Contractor to act on its behalf
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
for the purposes of the Contract and notified as such in writing to Engineer-in-Charge (EIC) with
copy to Owner.
▪ “DESIGN BASIS” shall mean requirements as specified in the Contract document and for
undertaking Basic and Detailed Engineering of the Plant under Contractor’s scope of work.
▪ “EFFECTIVE DATE” of Contract shall be the date of issue of Fax of Acceptance (FOA)/Letter of
Acceptance issued by the Owner accepting the Contractor’s bid.
▪ “EPC” shall mean the work for the Engineering, Procurement and Construction of the Project.
▪ “Foreign Bidder/Company” shall mean the Bidder/company registered outside India & their
operations shall be predominantly outside India.
▪ Foreign Currency means any of currency out of United States Dollar, EURO and Japanese Yen.
▪ “MECHANICAL COMPLETION” or “READY FOR START UP” or “RFSU” shall mean completion
of the PLANT as defined elsewhere in the Contract.
▪ “PLANT” shall mean the Units and Facilities comprised in the Project.
▪ “SYSTEM” shall mean the breakdown of the “Plant” into precisely demarcated sections or
components other than UNIT as detailed in the CONTRACT to facilitate smooth start up and
commissioning of the Plant.
▪ “VENDOR/ SUPPLIER” shall mean any third party supplying any of the equipment / materials for
setting up Plant covered under Contractor’s Scope of Work.
▪ “WORK” shall mean the responsibilities to be discharged by Contractor for fulfilling its obligations
under this Contract.
2. GENERAL
2.1 These Special Conditions of Contract (SCC) (Part-A & Part-B) shall be read in conjunction with the
General Conditions of Contract (GCC), Notice Inviting Tender / Instruction to Bidder, Schedule of
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Prices, specifications of work, drawings and any other document forming part of this Contract
wherever the context so requires.
2.2 Notwithstanding the sub-division of the document into these separate sections and volumes, every part
of each shall be deemed to be supplementary of every other part and shall be read with and into the
Contract so far as it may be practicable to do so.
2.3 If any provision in the General Conditions of Contract is repugnant to or at variance with any
provision (s) of the Special Conditions of Contract and / or the Agreed Variations or if any
provision of the Special Conditions of Contract is repugnant to or at variance with any provision(s) of
the Agreed Variations, and the two cannot be reconciled or otherwise co-exist, then unless a different
intention appears, the provision (s) of the Special Conditions of Contract shall be deemed to override
the provision (s) of General Conditions of Contract and the provision (s) of the Agreed Variations shall
be deemed to override the provision (s) of the Special Conditions of Contract, but only to the extent
that such repugnancies in the General Conditions of Contract cannot be reconciled with the Special
Conditions of Contract and / or Agreed Variations or to the extent that such repugnancies in the
Special Conditions of Contract cannot be reconciled with the Agreed Variations, as the case may be.
2.4 It will be the CONTRACTOR’s responsibility to bring to the notice of Engineer-in-charge any
irreconcilable conflict in the Contract documents before starting the work (s) or making the supply with
reference to which the conflict exists. Decision then conveyed by OWNER / PMC to the CONTRACTOR
shall be considered as FINAL and shall be binding upon the CONTRACTOR without any cost and time
implications.
2.5 Wherever it is stated in this Bidding Document that such and such a supply is to be effected or such
and such a work is to be carried out, it shall be understood that the same shall be effected/carried out
by the CONTRACTOR at his own cost, unless a different intention is specifically and expressly stated
herein or otherwise explicit from the context. Contract value (also referred to as Contract Price) shall
be deemed to have included such cost.
2.6 The materials, design and workmanship shall satisfy the applicable relevant Indian Standards, the job
specifications contained herein & codes referred to. Where the job specifications stipulate
requirements in addition to those contained in the standard codes and specifications, these additional
requirements shall also be satisfied. In the absence of any Standard / Specifications/Codes of practice
for detailed specifications covering any part of the work covered in this Bidding Document, the
instructions/ directions of Engineer-in-Charge will be binding on the CONTRACTOR.
2.7 In the absence of any Specifications related to any material, design or work(s) the same shall be
performed/ supplied/ executed in accordance with best Engineering practice as per the
instructions/directions of the Engineer-in-Charge, which will be binding on the CONTRACTOR.
2.8 In case of an irreconcilable contradiction in the commercial terms or conditions to the extent that the
two provisions cannot co-exist, the following shall prevail in order of precedence.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
i) Contract Agreement
ii) Detailed Letter of Acceptance
iii) Statement of Agreed Variations
iv) Special Conditions of Contract
v) Instructions to Bidders
vi) Price Schedule
vii) General Conditions of Contract
viii) Other documents
i) Formal Contract
ii) Detailed Letter of Acceptance
iii) Statement of Agreed Variations
iv) Job specifications/ Scope of Work
v) P&ID and other attached Drawings
vi) Technical/Material Specifications
vii) Quality Assurance Procedures
viii) Applicable Codes & Standards
ix) Special Conditions of Contract
x) General Conditions of Contract
xi) Price Schedule
xii) Instructions to Bidders
3. LOCATION OF SITE
The site for Gujarat Refinery is located at Vadodara on the west coast of India, in the State of Gujarat,
at a distance of approx. 400 KM from Kandla Port. The Vadodara refinery site is about 100 KM by
road from Ahmedabad – the capital city of Gujarat and is well connected by road, rail & air with other
parts of the country.
4. SITE VISIT
4.1 The bidder is advised to visit and examine the site of works and its surroundings and obtain for itself
on its own responsibility all information that may be necessary for preparing the bid and entering into
the Contract. Claims of any kind due to variation or ignorance of site conditions and environmental
conditions will not be eligible in any circumstances.
As per Covid protocol, Bidders to reach site before site visit and follow the local quarantine
duration /test as per refinery procedure.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
4.2 The cost of visiting the site shall be at Bidder’s own expenses.
4.3 The bidder and any of its personnel or authorized representatives will be granted permission by IOCL
to enter upon its premises and land for the purpose of such inspection. It is understood that as an
implicit condition of such permission, the bidder, its personnel and/or authorized representative(s) shall
be understood to have released and indemnified IOCL and its personnel from and against all liability in
respect thereof and to have assumed all responsibility for personal injury (whether fatal or otherwise),
loss of or damage to person or property and any other loss, damage, cost and expenses incurred as a
result of such visit, including those sustained by any negligence or other act of tort on the part of IOCL
and/or its personnel and CONSULTANTS. During such visits the Bidder shall abide by all the rules and
regulations, as applicable.
4.4 Bidders may contact the following person at site for the purpose of site visit:
5.1 General
The scope of work in general includes scope of work specified in various Technical
Documents/Specifications provided in Technical portion of the bidding document and Schedule of
Prices (SOP) enclosed in the Bidding Document.
CONTRACTOR shall perform the Work in accordance with the terms of this Contract and to ensure
that the Works are completed according to the requirements and the terms and conditions of the
Contract and in compliance with the Completion Schedule set forth as described in Annexure A-II to
this SCC.
5.2 The Scope of Work which CONTRACTOR is required to perform is more particularly described
elsewhere within the tender documents and the Specifications, and includes but not limited to.
(a) The scope of work shall include validation of basic design, Detailed Design & Engineering,
Procurement, Supply, Transportation up to Site, Storage, Construction, Erection, Installation,
Testing and Commissioning and all other related jobs for successful completion of POWER
IMPORT FACILITY for LuPech project. Contractor shall obtain all applicable statutory
approvals including approval from Electrical Inspector for subsequent efficient and trouble free
operation of the substation. Complete 220 / 36 KV Substation Package including, 2 x 115/140
MVA ONAN/ONAF, 220 kV / 36 kV Power Transformers , 220kV Cables, new 33 KV GIS in a
new Substation building including construction of the new Substation building with associated
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Bidder shall execute the work on Lump Sum Turn Key Basis (LSTK) with single point
responsibility and the scope includes Project Management, Consistency Checks, Power
System Studies as mentioned in Bidding Documents, Site development and enabling jobs,
Topography Survey, Soil Investigation and underground scanning mentioned in the bid and co-
ordination for the same with Owner/PMC, Total Procurement (including first fill of consumables,
special tools and tackles, Pre-Commissioning Spares, Commissioning Spares, Start-up spares
& Mandatory spares), Fabrication, Manufacturing, Quality Assurance, Inspection & Expediting,
Third Party Inspection, Supplies, Transportation, Insurance, Handling & Storage of all
Equipment, Materials, items and other Construction Materials at yard/site, Fabrication,
Assembly, Construction, Erection, Installation of all equipment pertaining to LuPech Power
Distribution facility including civil, Structural, HVAC, Piping, Electrical and Instrumentation
including tie-ins, Testing, Insulation and Painting, Obtaining all Statutory Approvals Pre-
commissioning & Mechanical Completion, Preparation of operating manuals, Training of
Owner’s O&M personnel, consumables for 6 (six) months operation, Contract closure activities
,Final invoice/billing and handing over of the facilities with Final and “As Built”
drawing/documentation, supply of spares with necessary support and services during defect
liability period.
(b) Procurement services and supply of all materials required for the completion of the works;
(c) Complete Site Works Planning including Construction, Commissioning & Commissioning
planning, Start-up & PGTR and Contract Closure;
(d) Barricading / water curtains/ hard strata development for movement of fabricated equipment
and high lifting capacity cranes, few works specifically indicated outside Battery Limits like
trenches from the unit to control room, trenches for FW line up to tie-in, trenches for laying
incoming power cable up to sub-station, trenches between substation and control room etc.
(e) Construction of the work, including enabling, Site development and preparatory works, piling
and Civil Works, Structural, Piping, Insulation, Painting, Electrical, Instrumentation and the
installation of all facilities together with all Pre-commissioning and interconnection and hook-
up services including battery limit hook ups;
(h) Mechanical Completion, Commissioning, test runs (PGTR) and plant start up.
(i) Procurement and delivery of Spare parts for Start-Up, Commissioning and Mandatory
Spares as specified in the Contract;
(k) Repairs and remedial works required during the defects liability period; and
(l) Contract Closure and Work required to attain the Completion Certificate.
5.3 Owner/PMC shall have the right at any time and at its own discretion to increase or decrease the
SCOPE OF WORK and in such case Clause 2.6.0.0 of the ‘General Conditions of Contract’ and sub-
clauses thereby shall apply.
5.4 EMISSIONS:
Contractor shall follow local applicable emission standards. Contractor shall guarantee that these limits
are not exceeded.
a) Notwithstanding the requirements for Statutory Approvals set forth in Clause 8.20.0.0 of the General
Conditions of Contract, it is obligatory on the part of EPC contractor to carry out the technical audit of
their detailed engineering and construction work as per detailed specified elsewhere in the tender
document and submit the report along with the corrective actions for approval. The decision on the
corrective action suggested by OWNER/PMC shall be binding on the EPC contractor. No implication
shall be admissible because of the implementation of suggestive corrective action.
In addition to above, if found necessary, OWNER and / or PMC may carry out, or, if it so desires, may
appoint independent consultant(s) to carry out technical audit / safety audit / certification of the detailed
design and engineering of the work and / or the constructed installations to ensure conformance to the
approved drawing documents and relevant national/international standards and CONTRACTOR shall
extend full co-operation to OWNER or the PMC’s personnel while performing such activities.
Notwithstanding such audit, CONTRACTOR shall not be absolved of its responsibilities nor shall its
liabilities, duties or obligations be diminished under this Contract.
b) CONTRACTOR shall implement the recommendations of the reports prepared by OWNER and / or the
audit team of third party consultant(s) engaged by OWNER and shall perform or re-perform work to
remedy any and all deficient design and engineering as identified in the audit team’s report, or
incorporate sound and viable recommendation to improve such design and engineering at
CONTRACTOR’s own cost and expense.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
5.6.1 A 5 (five) years Comprehensive Annual Maintenance Contract (PWCAMC) for following listed Item (with
the spares) shall be entered into by the CONTRACTOR with the OEMs/Vendors prior to expiry of the
Defect Liability Period. CONTRACTOR shall be coordinating with the Vendors/OEMs for performing
the required supply and services under PWCAMC Contract Period. Prior to expiry of Defect Liability
Period, OWNER shall enter into a Contract for PWCAMC with the OEMs/Vendors for the listed items,
CONTRACTOR has to coordinate with the OEMs/Vendors and facilitate for entering into PWCAMC
Contract with OWNER. CONTRACTOR shall be fully responsible for transfer of obligations to
OEMs/Vendors based on the terms and conditions agreed between the CONTRACTOR and OWNER
for PWCAMC Contract period. OEMs/Vendors will follow all the terms and conditions of contract related
to PWCAMC along with LSTK GCC.
a) Electrical Items
AC UPS, DC Battery Charger, HVAC System, Gas Detection System (GDS) as specified in SP-
07
5.6.2 The Bidder shall indicate a separate price for the Comprehensive Post Warranty Annual Maintenance
Contract (PWCAMC) in his bid in FORM SP-7. The Prices for PWCAMC shall remain valid up to the
defect liability period. After award of work, the price for PWCAMC shall remain FIRM till the completion
of scope of work of PWCAMC.
5.6.3 Within Ten days of placement of Order for PWCAMC, PBG for 3% of the annual PWCAMC amount
shall be submitted and the same shall be renewed on yearly basis. In absence of a valid PBG, payment
for PWCAMC shall not be released.
5.6.4 The PWCAMC includes complete servicing, regular & preventive maintenance and breakdown/
Emergency / shutdown maintenance whenever required for above listed item. This also includes spares
and Consumables required for repair or replacement of the above listed item.
5.6.5 PWCAMC Charges are inclusive of all the charges for Transportation, Lodging, Boarding, all insurances
including third party insurance and all other incidental charges. The prices also include cost of spares
and damaged parts (in case of comprehensive maintenance contract). OWNER does not have any
liability, whatsoever, over and above the prices of PWCAMC. The PWCAMC charges quoted by the
bidder shall be exclusive of all output taxes and duties. The output taxes & duties shall be paid as per
prevailing rate against tax invoice and related documents of the Contractor. (Only basic cost to be
quoted by the bidder & applicable output taxes/GST shall be paid extra at that time prevailing rate). The
price shall be quoted by the Contractor shall take into account the input tax credit available to them.
5.6.6 The PWCAMC charges also include arranging hand tools & tackles, special tools etc. required to carry
out the work.
5.6.7 The payments shall be made on quarterly basis upon completion of services required in each quarter
against submission of Bills duly certified by the Engineer-in-charge.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
5.6.8 The minimum terms and conditions for the PWCAMC are specified under Clause 5.6.10 for which the
CONTRACTOR shall include in its price bid.
A. Preventive Maintenance
Once in a year the Owner shall inform the PWCAMC Supplier/Agency, one month in advance, the
planned shutdown dates. Site visit, minimum of 6 days per year shall be scheduled as per Owner
intimation. The PWCAMC Supplier /Agency shall mobilize during this period to carry out the preventive
maintenance. This Includes inspection of all hardware and software, fault prediction, inspection of
power supply quality, checks on environmental operating conditions, calibration checks, major repairs
and replacements, replacement of electronics modules or any other parts likely to fail due to aging,
cleaning of each component like electronic modules connectors, etc. flushing of sampling lines and
cleaning of all fillers, valves and preparing detailed reports. This visit shall be in addition to those
required for periodic maintenance and shall be part of PWCAMC.
B. Periodic Maintenance
Site visits, minimum 4 times a year (minimum of 16 days per year). Schedule of visits shall be discussed
and finalized with Owner. Periodic maintenance shall include inspection of general healthiness of the
systems, study and advice on daily maintenance, inspection of all hardware and software, running of
test programs, on-line servicing and solving reported problems. Checks shall be conducted on running
systems / sub-systems like:
d. Cleaning/replacing all filters in analyzer sampling system, checking and rectifying leaks,
etc.
This shall include maintenance of operating and application software to improve upon system
performance. This includes application and operating software modification & debugging, supply and
fixing of patches released by licensors / manufacturers to remove bugs or upgrading the running
version, software/firmware update and software patches as released by the PWCAMC supplier/agency.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
PWCAMC supplier agency shall ensure trouble free operation of the system after software updated in
line with the requirements, etc.
D. Emergency Services
i. In the event of any malfunction of any of the systems / items for which the PWCAMC is in force, the
PWCAMC Supplier /Agency shall depute the concerned experts to Site so as to rectify the failed system
items within 24 hours after receipt of a written intimation or Telephone call from IOCL.
ii. The PWCAMC Supplier/Agency shall maintain at his premises or of the other agencies / vendor
charged with the maintenance a stock of necessary spares required. In an event of breakdown,
repairing or replacement should be possible within 24 hours maximum without any lead time for
procurement of spares. The PWCAMC shall include not only the supply of spares for maintenance but
shall also include Labour and materials at no additional cost to repair the ANALYSERS (ALL TYPES)
system and any devices applicable.
iii. The PWCAMC Supplier /Agency liability to provide maintenance spares shall not, however, be confined
in any manner to be requirement of maintenance spares estimated by the PWCAMC Supplier /Agency.
The PWCAMC Supplier /Agency, shall, within the scope of the Maintenance Contract, be required to
fulfil or replenish any shortfall in the maintenance spares without additional cost to OWNER.
iv. During Defects Liability Period and Comprehensive Annual Maintenance Contract (PWCAMC) period,
the PWCAMC Supplier/Agency shall arrange and maintain in, VADODARA (GUJARAT) all the
hardware and consumables required for un-interrupted running / calibration / maintenance of the above
Items. In the event of any malfunction of the hardware / software, the experienced service engineer
shall be made available at Site so as to rectify and put back in service the defective system / item within
24 hours.
v. Owner's personnel shall work on the system on a day to day basis and wherever possible, inform the
PWCAMC Supplier /Agency about the type of failure of hardware / software, based on diagnostics or
other information available. However, CONTRACTOR shall be fully responsible to attend, Identify the
root cause and rectify the failure in the shortest possible time.
7. TIME SCHEDULE
7.1 The Work shall be executed strictly as per Time Schedule given in Annexure A- II to this SCC.
7.2 Delay by OWNER in providing Utilities and Feedstock will not be reason for waiver of price adjustment,
if concurrently CONTRACTOR has delayed the completion of the project..
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
7.3 If the Contractor is also one of the suppliers of items supplied by Owner in the Contract, the
delay on account of supply of such material against the Owner's Purchase order and or Work
order will not be a basis for extension of time without imposition of price reduction schedule on
account of such delays.
8. SITE CLEANING
8.1 The CONTRACTOR shall clean and keep clean the work site from time to time to the satisfaction of the
Engineer In-Charge for easy access to work site and to ensure safe passage, movement and working.
All dismantled material shall be shifted /removed by CONTRACTOR at his own cost to designated
place.
8.2 If the work involves dismantling of any existing structure in whole or part, any RCC foundation, paved
area care shall be taken to limit the dismantling up to the exact point and/ or lines as directed by the
Engineer In-Charge and any damage caused to the existing structure beyond the said line or point shall
be repaired and restored to the original condition at the cost and risk of CONTRACTOR to the
satisfaction of the Engineer-in-Charge, whose decision shall be final and binding upon the
CONTRACTOR.
8.3 The CONTRACTOR shall dispose of the unserviceable materials, debris etc as directed by Engineer-
in-Charge outside the Refinery Complex and into the designated area outside the Municipal
Corporation Limits of the City selected by the CONTRACTOR in due permission of local administrative
authorities for dumping of the debris, waste etc. The quoted Prices shall be inclusive of the above
activities also. The CONTRACTOR shall sort out, clear and stack the serviceable materials obtained
from the dismantling/renewal at places as directed by the Engineer-in-Charge.
8.4 No extra payment-shall be paid on this account. The Prices quoted in SOR are deemed to be
inclusive of all the costs towards all the above activities as well.
8.5 The CONTRACTOR shall be the custodian of the dismantled materials till the Engineer- in-
Charge takes charge thereof.
8.6.1 CONTRACTOR shall submit the temporary facilities layout for approval of OWNER/PMC.
8.6.2 CONTRACTOR shall design, supply, construct and maintain the temporary facilities such as Site office,
fabrication yard, laydown area, ware house, grit blasting/painting area etc. as described in this Tender
Documents.
8.6.3 CONTRACTOR shall dismantle the temporary facilities upon completion of their work and as instructed
by OWNER without any extra cost to OWNER.
8.6.4 The area for temporary construction (TCF) is shown in the overall layout. In case Contractor requires
additional area, Contractor shall hire the space outside the Refinery at their Own Cost. Land outside
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
the refinery premises arranged by Contractor for the Job will be treated as “Job Site/Site” and shall be
covered by Insurance provided by Owner. This Job Site/Site outside the refinery premises should be
within the radial distance of 25 Km from Refinery.
CONTRACTOR shall plan the following at his temporary construction facilities as minimum:
9. STATUTORY APPROVALS
9.1 Obtaining statutory approvals, required as defined in Contractor’s scope under Technical Scope of
Work, shall be the responsibility of the Contractor. Contractor shall arrange the inspection of the works
by the authorities and necessary co-ordination and liaison work in this respect. The application on
behalf of the OWNER for submission to relevant authorities along with copies of required certificates
complete in all respects shall be prepared and submitted by the Contractor well ahead of time so that
the actual construction/ commissioning of the work is not delayed for want of the approval/inspection
by concerned authorities.
9.2 Statutory fees paid, if any, for all such inspections and approvals by authorities shall be deemed to
be included in the quoted prices, if not specified otherwise.
9.3 Any change/ addition required to be made to meet the requirements of the statutory authorities shall be
carried out by the Contractor free of charge and without any change in schedule. The inspection and
acceptance of the work by statutory authorities shall however, not absolve the Contractor from any of
his responsibilities under this Contract.
9.4 All statutory approvals other than specified under 9.1 above shall be obtained by OWNER and provided
to the Contractor.
9.5 Payment of minimum wages to workmen by 7th of every month shall be done by CONTRACTOR
including maintenance of PF & other statutory obligations. CONTRACTOR shall submit the supporting
documents for the same to OWNER/PMC.
10.1 OWNER/PMC shall provide, to the best possible extent, details with respect to existing underground
and above ground structures, overhead lines, cables, pipelines and utilities at the job site to the
CONTRACTOR. The CONTRACTOR shall execute the work in such a manner that the said structures,
utilities, pipelines etc. are not disturbed or damaged, and shall indemnify and keep indemnified the
OWNER from and against any destruction thereof or damages thereto. Moreover, CONTRACTOR shall
prepare drawings showing all the above stated details accurately and submit to Engineer- in-Charge.
The Prices quoted in SOR are deemed to be inclusive of the costs towards this activity.
10.2 OWNER/PMC will provide the indicative Underground Scanning Report, wherever possible, for reference
during Bidding stage. It shall be contractor ‘s responsible to reverify the underground facilities within
their battery limit including in the allocated TCF area. Any precautions necessary to avoid damage to
these facilities shall be in the contractor scope .Re-scanning of the area, if necessary, shall be in the
contractor’s scope.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
10.3. In case any facilities are required to be re-routed, CONTRACTOR shall carryout the same to complete
the job within the contractual Time Schedule. Implication if any shall be considered by Owner/PMC on
merit. The decision of OWNER/ PMC in this regard shall be final and binding on the CONTRACTOR.
The CONTRACTOR shall ensure that local labour, skilled and/or unskilled, to the extent available shall
be employed in this work. Special preference shall be given to persons and/or dependents of persons
whose land has been acquired for the project work. In case of non-availability of suitable labour in any
category out of the above persons, labour from outside may be employed.
The CONTRACTOR shall not recruit personnel of any category from among those who are
already employed by the other agencies working at site but shall make maximum use of local
labour available.
CONTRACTOR shall arrange land for construction of Labour camp outside the Refinery.
CONTRACTOR shall ensure all migrant workers stays in labour camp. CONTRACTOR shall develop
and maintain all necessary facilities in labour camp like power, water, hutments, sanitation facilities,
medical facilities, drainage, transportation facilities etc. as minimum.
During this COVID-19 pandemic, CONTRACTOR shall also consider adequate precautionary safety
measures in the labour camp as per the govt guidelines and the same shall be form part of the quoted
price.
12.1 If the CONTRACTOR is the PSU or P.S.Enterprise or is a Govt.Dept., any disputes or differences
between the CONTRACTOR and the OWNER hereto arising out of any notified claim of the
CONTRACTOR in terms hereof and/or arising out of any amount claimed by the OWNER (whether or
not the amount claimed by the OWNER or any part thereof shall have been deducted from the final bill
of the CONTRACTOR or any amount paid by the OWNER to the CONTRACTOR in respect of the
work), then in suppression of the provisions of Section 9 of the General Conditions of the Contract, the
following provisions shall apply, namely; such disputes of differences shall be resolved amicably by
mutual consultation or through the good offices or empowered agencies of the Government. If such
resolution is not possible, then the unresolved disputes or differences shall be referred by either party
for Arbitration to the Sole Arbitrator in the Department of Public Enterprises to be nominated by the
Secretary to the Government of India in-charge of the Department of Public Enterprises in line with
applicable DPE guidelines for settlement of commercial disputes between CPSEs or between CPSEs
& Government Departments issued by Department of Public Enterprises and as modified from time to
time.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
The Arbitration and Conciliation Act, 1996 shall not be applicable to the arbitrator under this clause.
The award of the arbitrator shall be binding upon parties to the dispute, provided, however any party
aggrieved by such award may make a further reference for setting aside or revision of the award of
Law Secretary, Department of Legal Affairs, Ministry of Law & Justice, Government of India. Upon such
reference the dispute shall be decided by the Law Secretary or the Special Secretary/Additional
Secretary whose decision shall bind the parties finally and conclusively. The parties to the dispute will
share equally the cost of Arbitration as intimated by the Arbitrator.
12.2 Notwithstanding the existence of any dispute or arbitration in terms hereof or otherwise, the
CONTRACTOR shall continue and be bound to continue and perform the works to completion in all
respects according to the CONTRACT( unless the Contract or works determined by the OWNER) and
the CONTRACTOR shall remain liable and bound in all respects under the Contract.
13. CONCILIATION
Notwithstanding any other mechanism for dispute resolution provided under the General Condition of
Contract, with a view to speedy resolution, the CONTRACTOR and OWNER may at any time endeavor
to settle through conciliation a dispute referable for settlement by Conciliation under and in accordance
with the Indian Oil Corporation Limited Conciliation Rules, 2014 (hereinafter referred to the ''said
Rules'') as amended from time to time. The said rules may be downloaded from the OWNER's Website
www.iocl.com and if not available, a copy thereof may be obtained from the OWNER on written request.
In case after price bid opening the lowest evaluated bidder (L1) is not awarded the job for any mistake
committed by him in bidding or withdrawal of bid or varying any term in regard thereof leading to re-
tendering, OWNER shall forfeit Earnest Money paid by the bidder and such bidders shall be debarred
from participation in re-tendering of the same job(s)/ item(s).
15.1 Bidders are required to furnish the complete and correct information/ documents required for evaluation
of their bids. If the information/ documents forming basis of evaluation is found to be false/ fake/ forged,
the same shall be considered adequate ground for rejection of the bids and forfeiture of earnest money
deposit.
15.2 OWNER requires that the CONTRACTOR observes the highest standard of ethics during the execution
of Contract. In pursuance of this policy, OWNER defines, for the purposes of this provision, the terms
set forth below as follows:
a) “Corrupt Practice” means the offering, giving, receiving, or soliciting of anything of value to
influence the action of public official in contract execution;
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
d) “Forgery” means the false making or the material altering of a document with the intent to
defraud. A signature of a person that is made without the person’s consent and without the
person otherwise authorizing it. A person is guilty of forgery if, with the purpose to defraud or
injure anyone or with knowledge that he is facilitating a fraud or injury to be perpetrated by
anyone, the actor (i) alters any writing of another without his authority (ii) makes, completes,
authenticates, executes, issues or transfers any writing, so that it purports to be the act of
another who did not authorize that act or to have been executed at a time or place or in a
numbered sequence other than was in fact the case, or to, be a copy of an original when no
such original exists. Utters any writing which he knows to be false in a manner specified in (i)
& (ii) above.
15.3 OWNER may terminate the Contract if it discovers subsequently that the CONTRACTOR had engaged
in Corrupt Practices or Fraudulent Practices in competing for the Contract.
Bidders are required to sign the Integrity Agreement & Covering letter and submit the same along with
the covering letter in the proforma attached as Attachment to ITB. Offers of the Bidders who signed
and accepted the Integrity Agreement will only be taken up for evaluation.
15.5 In case, the information/document furnished by the CONTRACTOR forming basis of evaluation of its
bid is found to be false/fake/forged after the award of the Contract, OWNER shall have the right to
terminate and get the remaining works executed by a third party at the risk & cost of the CONTRACTOR
and without any prejudice to other rights available to OWNER under the Contract such as forfeiture of
the Contract Performance Bank Guarantee, withholding of payment etc.
15.6 In case, this issue of submission of false/fake documents comes to the notice after execution of the
works, OWNER shall have full right to forfeit any amount due to the CONTRACTOR along with forfeiture
of the Contract Performance Bank Guarantee furnished by the CONTRACTOR.
15.7 Further, any CONTRACTOR which is found guilty of any corrupt or Fraudulent Practice or submission
of false/fake/forged documents, shall be put on the negative/ holiday list of OWNER debarring them
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
The CONTRACTOR shall without prejudice to his overall responsibilities and liabilities to provide
adequate qualified and skilled personnel on the work and augment the same as decided by the
Engineer-in-Charge depending on the exigencies of work. In addition to this CONTRACTOR shall
deploy Safety Supervisors to ensure safer working conditions at site. In case where the works are Sub-
Contracted by the main CONTRACTORs, Safety Supervisors are to be provided by the main
CONTRACTOR.
17.1 The CONTRACTOR shall be responsible for organizing the lifting of the equipment in the proper
sequence for orderly progress of the work and to ensure that access routes for erecting the other
equipment are kept open. CONTRACTOR shall submit the equipment erection plan to the Engineer-in-
charge considering sequence of erection for approval.
17.2 Orientation of all foundations, elevations, lengths and disposition of anchor bolts and diameter of holes
in the supports and saddles shall be checked by the CONTRACTOR well in advance of the installation.
Rectifications, including chipping of foundations, shall be carried out where necessary in consultation
with the Engineer-in-Charge. If a structural member needs to be dismantled to facilitate the
equipment erection, this shall be done by the CONTRACTOR after ensuring proper stability of the main
structure in consultation with the Engineer-in-Charge. All such dismantled members shall be put back
in position to the satisfaction of Engineer-in-Charge after the completion of the equipment erection.
17.3 During the performance of the work the CONTRACTOR shall at his own cost keep structures, materials
and equipment adequately braced by guys, struts or other approved means which shall be supplied
and installed by the CONTRACTOR as required till the installation work is satisfactorily completed.
Such guys, shoring, bracing, strutting, planking supports etc. shall not interfere with the work of other
agencies and shall not damage or cause distortion to other works executed by the CONTRACTOR or
other agencies.
17.4 The CONTRACTOR shall duly comply with manufacturer(s) recommendations and detailed
specifications for the installation of the various equipment and machines.
17.5 Various tolerances required as marked on the drawings and/or in accordance with the specifications
and/or instructions of the Engineer-in-charge shall be maintained. Verticality shall be verified with the
Theodolite and shall be maintained.
Utmost safety has to be observed during the erection of heavy equipment like columns, reactors etc.
For each equipment, a method statement (erection scheme) signed by contractor’s HSE and approved
by PMC/ Owner has to be prepared by the contractor which shall include the details of the crane, where
the crane will be placed, how crane will move/travel with the equipment, how the equipment is held by
the crane, boom swing, capacity of the slings etc and prove that the crane is capable of lifting and
placing the equipment on the ready foundation safely. Slings used to hold the equipment shall be tested
before use.
17.7 Testing of Safety Equipment’s Record of all the safety equipment used at site shall be kept at site office
including the test dates, validity of testing and re-testing dates. All the failed equipment shall be
segregated and differently colored with paint for easy identification so that those are not used.
Record of failed equipment shall be maintained till the closure of the contract. Month wise color coding
for easy identification of valid test certificates of the equipment shall be done. Record of the testing of
safety equipment shall be reviewed by Consultant / Owner periodically.
17.8 CONTRACTOR shall comply to OWNER’s work permit and others safety philosophy system like JSA,
before any critical and erection activities.
18.1.1 The CONTRACTOR shall mechanize the construction activities to the maximum extent by
deploying all necessary construction equipment/machinery in adequate numbers and capacities.
18.1.2 It shall be the responsibility of the CONTRACTOR to carry out leveling / dressing / grading with a proper
approach for the movement of equipment and machinery, at his own cost. No extra payment shall be
made by the OWNER for leveling / dressing / grading. The CONTRACTOR shall acquaint himself with
availability of access, facilities such as railway siding, local labour etc. and the CONTRACTOR may
have to build temporary access roads to aid his work and the quoted and agreed Prices shall be deemed
to include the same.
18.1.3 For speedy execution of work, CONTRACTOR shall also ensure use of latest computer software
for at least the following:
a) Billing
c) Progress Reporting
e) Safety Records
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
f) Resource Deployment
g) Communication
18.1.4 CONTRACTOR further agrees that Contract Price is inclusive of all the associated costs, which he
may incur for actual mobilization, demobilization required in respect of use of mechanized
construction techniques and that the OWNER/PMC in this regard shall entertain no claim whatsoever.
18.1.5 Calibration Requirements of Monitoring and Measuring Devices at Construction Site. Refer
Annexure A-XIV to this SCC.
The CONTRACTOR shall without prejudice to his responsibilities to execute and complete the work as
per the specifications and Time Schedule, progressively deploy minimum construction equipment, tools
and tackles and further augment the same depending on the exigencies of work and as decided by the
Engineer-in-Charge so as to suit the construction schedule within scheduled completion date without
any additional cost to OWNER. The bidder shall submit a list of construction equipment he proposes to
deploy for the subject work along with deployment schedule. No construction equipment shall be
supplied by the OWNER, unless specified by Owner specifically in the bidding document.
In addition to the Clause No. 4.2.2.0 of General Conditions of Contract, CONTRACTOR shall submit
within 15 days of award of work, to the Engineer-in Charge / OWNER, his contingency plan for work
during monsoon clearly stating their methodology/ strategy to progress uninterruptedly during monsoon
mentioning the deployment of resources viz, numbers, capacity, category of equipment and
manpower on a weekly basis for approval. During monsoon and other periods, it shall be the
responsibility of the BIDDER to keep the construction work site free from water, at his own cost by
deploying suitable dewatering pumps. The CONTRACTOR shall adhere to the Special Conditions
specified in Annexure A-III to this SCC.
19.1 CONTRACTOR shall include in his offer the Quality Assurance Program containing the overall
quality management and procedures which is required to be adhered to during the execution of
Contract. After the award of the Contract, detailed quality assurance program to be for the
execution of Contract under various divisions of works will be mutually discussed and agreed to.
The CONTRACTOR shall establish, document and maintain an effective quality assurance system as
outlined in recognized codes. Specification for Quality Management System using Quality Control
Checklists is attached as Annexure-A-IV to this SCC for Contractor’s reference and developing the
Quality Programme and Formats for approval of OWNER / CONSULTANT.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
19.2 Quality Assurance System plans / procedures of the CONTRACTOR shall be furnished in the form of
a QA Manual. This document should cover details of the personnel responsible for the quality
assurance, plans or procedures to be followed for quality control in respect of Design, Engineering,
Procurement, Supply, Installation, Testing and Commissioning. The quality assurance system should
indicate organizational approach for quality control and quality assurance of the construction activities,
at all stages of work at Site as well as at manufacturer's works and dispatch of materials.
19.3 The Quality Assurance plan for various equipment and materials, construction procedure etc. shall be
furnished to the OWNER/PMC prior to commencement of site work /manufacturing /erection.
OWNER/PMC shall review the same within 03 (three) weeks of its submission.
19.4 The OWNER / PMC or their representative reserve the right to inspect / witness, review any or all
stages of work at shop/site as deemed necessary for quality assurance.
19.5 The CONTRACTOR has to ensure the deployment of Quality Assurance and Quality Control (QA &
QC) Engineer(s) depending upon the quantum of work. This QA / QC group shall be fully responsible
to carry out the work as per standards and all code requirements. In case Engineer-in-charge feels that
QA/QC Engineer(s) of CONTRACTOR are incompetent or insufficient, CONTRACTOR has to deploy
other experienced Engineer(s) as per site requirement and to the full satisfaction of Engineer-In-
Charge.
19.6 In case the CONTRACTOR fails to follow the instructions of Engineer-in-charge with respect to the
above clauses, next payment due to him shall not be released unless and until CONTRACTOR
complies with the instructions to, the full satisfaction of Engineer- in-charge.
19.7 CONTRACTOR shall establish field laboratory at Site for day-to-day routine test of samples to be
taken during construction. CONTRACTOR shall indicate the equipment to be made available at the
field laboratory for this purpose.
19.8 The CONTRACTOR shall post Quality Assurance and Quality Control Engineer(s) depending upon the
quantum of work. This QA / QC group shall be fully responsible to carry out the work as per standards
and codes requirement. In case OWNER feels that CONTRACTOR’s QA / QC Engineer(s) are
incompetent or insufficient in numbers, the CONTRACTOR shall further deploy their experienced
Engineer as per Site requirement.
19.9 Contractor shall deploy skilled ASNT Level-III personnel for interpretation and ASNT Level-II
skilled personnel for scanning and reporting.
20.1 The CONTRACTOR shall carry out the various tests as enumerated in the bidding document and as
per direction of Engineer-in-charge either on field or outside laboratories concerning the execution of
work and supply of the material by CONTRACTOR. All the expenses shall be borne by the
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
CONTRACTOR and shall be considered as included in the quoted price. The inspection shall be done
by following:
a) Third Party Inspection agency nominated by the OWNER for all supply items among the following:
CONTRACTOR shall give prior notice sufficiently ahead of time to the Engineer-in-charge and also to
the authorities / TPI to conduct inspection/ to witness such tests.
20.2 All the tests either on the field or at outside laboratory or at any other place, concerning the
execution of the work and supply of materials by the CONTRACTOR shall be carried out by the
CONTRACTOR at his own cost.
20.3 The work is subject to inspection at all times by the Engineer-in-charge. The CONTRACTOR shall carry
out all instructions given during inspection and shall ensure that the work is being carried out according
to the technical specifications of this bidding document, the technical documents that will be furnished
to him during performance of work and the relevant codes of practice furnished to him during the
performance of the work.
20.4 The CONTRACTOR shall provide, for purposes of inspection, access ladders, lighting and
necessary instruments at his own cost including Low Voltage (24V) lighting equipment for I
inspection of work. Compressed air for carrying out works shall be arranged by the
CONTRACTOR at his own cost.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
20.5 Any work not conforming to the execution drawings, specifications or codes shall be rejected
forthwith and the CONTRACTOR shall carry out the rectifications at his own cost.
20.6 All results of inspection and test will be recorded in the inspection reports, pro-forma of which will be
approved by the Engineer-in-charge. These reports shall form part of the Completion Documents.
20.7 For materials supplied by OWNER, CONTRACTOR shall carryout the tests, if required by the
Engineer-in-charge, and the cost of such tests shall be reimbursed by the OWNER at actual to the
CONTRACTOR on production of documentary evidence.
20.8 Inspection and acceptance of the work shall not relieve the CONTRACTOR from any of his
responsibilities under this contract.
20.9 Cost towards repeat tests and inspection due to failures, repairs etc. for reasons attributable to the
CONTRACTOR shall be borne by the CONTRACTOR.
20.10 Various tests as specified in specifications shall be carried out to the entire satisfaction of
OWNER/PMC.
20.11 PMI testing shall be carried out of all the alloy steels material at site and report to be submitted the
Owner/ PMC before execution of jobs.
21.1 To distinguish between work in sub-structure and superstructures, the following criteria shall
apply:
21.2 For all equipment pedestals, pipe racks, other foundations and RCC structures, work done up to 300mm
level above finished grade level will be taken as work in sub- structure and work above this level
will be treated as work in superstructures.
21.3 Irrespective of what has been stated above, all pavements, RCC retaining wall, all pipe sleepers and
any similar item would be taken as work done in sub-structure irrespective of locations nomenclature,
and levels given anywhere. Where not specifically pointed out all works in sumps, drains manholes,
tank pads, cable trenches or such similar items would be taken as work in sub-structure.
22.1 The CONTRACTOR shall carryout various tests as called for in bidding document either on field or at
outside approved laboratories at his own cost. All test results and related documents shall be submitted
in Original + 3 (Three) hard copies + soft copies as part of completion documents for the work..
22.2 The following documents in-addition to documents specified in GCC shall be submitted in hard
binder by the CONTRACTOR as a part of completion documents:
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
c) Execution drawing with all corrections / alterations duly marked and carried out during
the execution of the work and in as built condition.
d) Field Test report for all Civil, Structural and Electrical, instrumentation system.
f) Original “No Demand Certificate” from the Administration & Personnel Department
regarding vacation of Land, housing accommodation if any, recovery of rents, hire
charges, return of surplus material, reconciliation statement for all the material issued etc.
i) Any other drawing/ document/ report specified elsewhere in the Bidding Document.
j) All the site jobs PMI, radiography, PWHT and others NDT reports.
Note: CONTRACTOR shall be eligible to apply for issue of Completion Certificate only after
submission of completion documents as mentioned above.
23.1 OWNER reserves their right to execute any additional works/ extra works, during the execution of
Work, either by themselves or by appointing any other agency, even though such works are
incidental to and necessary for the completion of Work awarded to the CONTRACTOR. In the
event of such decisions taken by OWNER, CONTRACTOR is required to extend necessary
cooperation, and act as per the instructions of Engineer-in-Charge. This is without prejudice to the
rights of the OWNER to get the additional works/ extra works executed by the CONTRACTOR.
24.1 In addition to the safety practices as per Section 10 and clause 8.4.0.0 of General Conditions of
Contract, OISD Guidelines-192, OISD Guideline-207, PMC specifications on Health, Safety and
Environment (HSE) Management enclosed as Annexure-A-V, OWNER prescribed work permit system
and job safety analysis procedure shall be followed before under taking any work inside OWNER‟s
premises.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
24.2 Considering the above, the CONTRACTOR shall establish, document and maintain an effective
Health, Safety and Environment (HSE) management system.
24.3 The Engineer-in Charge is responsible for ensuring that CONTRACTOR conforms to the safety
requirements as set forth in the Contract documents at all times. In the event of CONTRACTOR
violations of the safety requirements, and violations that result in physical injury or fatality, OWNER
has the right to deduct from any payment due to CONTRACTOR the amounts prescribed in clause
8.4.0.0 of the General Conditions of Contract and, dependent on the nature of the injury or if fatal,
CONTRACTOR shall be also liable to make contributory payments according to clause 8.4.0.0 of the
General Conditions of Contract.
24.4 In the event of violation by the CONTRACTOR of any stipulation mentioned in the above documents
or violation of any statutory provisions related to HSE, PMC/OWNER shall impose immediate
stoppage of work without any time or cost implication to the OWNER, till the contractor takes remedial
action to the satisfaction Engineer in charge. The decision for stoppage of work shall be final and
binding on the CONTRACTOR.
24.5 In case of conflict between the requirements of the various specifications and/or the requirements
specified in the bidding document including penalties, the more stringent requirement shall be
followed.
24.6 The CONTRACTOR shall arrange for OISD audits in different phases of project as per advice of EIC
without any extra cost implication
26.1 Format for Advance Bank Guarantee is enclosed in Annexure A-VI to this SCC:
26.2.1.1 BG upto Rs.2 Crore can be accepted if it is issued by an Indian branch of any scheduled bank
appearing in the Second Schedule to the RBI Act, 1934.
26.2.1.2 BG of above Rs.2 Crore can be accepted if it is issued by an Indian branch of:
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
a) Any Nationalized / PSU bank appearing in the Second Schedule to the RBI Act, 1934.
Or
b) Any scheduled bank (other than a Nationalized Bank / PSU bank) having at least desired Credit
Rating at the time of acceptance of BG:
Apart from above, BG, irrespective of its amount, issued by any other bank including but not limited
to non-scheduled banks, foreign branches of scheduled banks and foreign branches of foreign
banks, can be accepted provided such BG is counter guaranteed by any bank mentioned above.
The CONTRACTOR shall note that, in case of acceptance of BG issued or counter guaranteed by a
bank mentioned at para 26.2.1.2.b, if the credit rating of such bank falls below the Credit Rating
mentioned under clause 26.2.1.2.b during the validity period of BG, the Vendor shall either submit a
fresh BG or get the existing BG counter guaranteed, at its own cost, through a bank mentioned above
at 26.2.1.2.b (having at least desired Credit Rating as mentioned above, if applicable). In case of non-
submission of bank guarantee(s), without prejudice to any other right or remedy available to the owner,
the owner shall be entitled to encash the bank guarantee(s).
26.2.3 The vendor at the request of the owner extend the validity of the Bank Guarantee(s) for such further
period(s) as may be required failing which without prejudice to any other right or remedy or remedy
available to the owner, the owner shall be entitled to en-cash the bank guarantee(s).
26.2.4 The vendor to ensure the validity of all bank guarantee(s) as stipulated else-where in the bidding
documents/contract and no payments shall be released to the vendor, if the validity of the bank
guarantee(s) is less than 30 days unless otherwise specifically intimated to the vendor.
27.1 Qualification and Experience of Key Supervisory Personnel to be deployed for this work shall be as
per Annexure A-VII to this SCC. CONTRACTOR shall submit bio-data of Key Supervisory Personnel
meeting the requirement of this Annexure which will be reviewed and approved by Engineer-in-Charge.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
27.2 All key staff employed at the site by the CONTRACTOR shall be considered essential to the
performance of the work, and all key staff shall be subjected to approval of OWNER/ Engineer-in-
Charge. However, such approval shall not relieve the CONTRACTOR of any of his contractual
obligations. No staff including Resident Engineer and other technical supervisory staff shall be
removed or transferred from the work with the prior written permission of the OWNER/ Engineer-in-
Charge. The OWNER / Engineer-in-Charge shall however have the authority to order the removal of
staff from site of any undesirable personnel, the replacement of such personnel shall be carried out
by the CONTRACTOR within 15 (fifteen) days from the notification from OWNER/ Engineer-in-
Charge. If key staff becomes unavailable for assignment to the work for reasons beyond the
CONTRACTOR’s control, the CONTRACTOR shall immediately notify the OWNER/Engineer-in-
Charge to evaluate the impact on the project. Prior to substitution or addition of any key staff,
the CONTRACTOR shall obtain OWNER’s / Engineer-in-Charge’s written consent as to the
acceptability of replacements or additions to such personnel. The CONTRACTOR shall at all
times be fully responsible for the acts, omissions, defaults and neglect of all his representatives,
agents, servants, workmen and suppliers and this of his Sub-Contractors.
28.1 OWNER/ CONSULTANT shall furnish the relevant existing grid point with Bench Mark, on the land. It
shall be CONTRACTOR’s responsibility to set out the necessary control points in and to set out the
alignment of the various works. The CONTRACTOR shall employ an efficient survey team for this
purpose and the accuracy of such setting out works shall be the CONTRACTOR’S responsibility.
28.2 The CONTRACTOR shall give the Engineer-in-Charge not less than 24 (Twenty-four) hours advance
notice in writing of his intention to set out or give levels for any part of the work so that arrangements
may be made for checking the same.
28.3 Work shall be scheduled so as to enable checking lines and levels on any part of the work.
28.4 The CONTRACTOR shall within the scope of work provide all assistance, tools, gauges and
instruments required to enable the Engineer-in-Charge to check the setting out of works.
CONTRACTOR shall coordinate with PMC for his day-to-day activities and provide free access and
assistance during the inspections and other activities to be carried out by CONSULTANT.
CONTRACTOR shall comply to the requirements of PMC and obtain all the clearances from PMC for
his work.
30.1 The drawings (if any) accompanying the bidding document are of indicative nature and issued for
bidding purpose only. Purpose of these drawings is to enable the bidder to make an offer in line with
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
the requirements of the OWNER. However, no extra claim whatsoever, shall be entertained for
variation in the “Approved/Issued for Construction” and “Bid Drawings” regarding any changes of work.
Construction shall be as per drawings / specifications issued / approved by the Engineer-in-
charge during the course of execution of work.
30.2 The drawings and documents to be submitted by the CONTRACTOR to OWNER/PMC after award of
the work as per the requirements enlisted in the bidding document elsewhere shall be for
OWNER/PMC’s review, information and record. The CONTRACTOR shall ensure that drawings and
documents submitted to OWNER/PMC are accompanied by relevant calculations, data as required and
essential for review of the document / drawings by OWNER/PMC.
30.3 All documents and drawings including those of CONTRACTORs sub-vendor’s manufacturer’s etc. shall
be submitted to OWNER/PMC after having been fully vetted in detail, approved and corrected by the
CONTRACTOR & shall bear CONTRACTORs seal / certifications to this effect. All documents /
drawings & submissions made to OWNER/PMC without compliance to this requirement will not be
acceptable and the delay & liability owing to this shall be to the CONTRACTOR’s account.
30.4 The review of documents and drawings by OWNER/PMC shall not be construed by CONTRACTOR as
limiting any of his responsibility to meet the requirements of specifications, drawings etc. and liabilities
for mistakes and deviations. Upon receiving the comments on the drawing / documents reviewed by
OWNER/PMC, CONTRACTOR shall incorporate the comments as required and ensure their
compliance. The subsequent submission by the CONTRACTOR of the updated drawings / documents
shall be accompanied by a compliance report etc. The submissions calling for repeated reviews by the
OWNER/PMC shall be avoided by the CONTRACTOR.
30.5 Any inaccuracies, errors and non-compliance to contractual requirements will be rectified by the
CONTRACTOR. Delay occurring on this shall be to the account of the CONTRACTOR.
31. SUB-CONTRACTING
31.1 If the CONTRACTOR is required to engage a Sub-contractor for any part of work, then such sub-
contractors shall have prior proven experience of similar work and shall require specific approval by
OWNER before award of sub-contract as per attached as Annexure A-VIII to this SCC.
31.2 Following the notification of Acceptance of Bid, the CONTRACTOR will submit to the OWNER for
approval, the details of sub-contractors to these Special Conditions of Contract. CONTRACTOR shall
ensure that very competent and resourceful agencies with proven track record and performance should
be proposed for the work to be sub-contracted.
31.3 Any bidder who had submitted the bid for this tender and does not get the Contract because of his
being not the lowest will be prohibited from working as sub-contractor for execution of this Contract.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
32.1 The CONTRACTOR or its nominated Sub-CONTRACTOR (s), as the case may be, shall have a valid
electrical CONTRACTOR‟s license for working in the State in which the job site is located. The
CONTRACTOR shall furnish a copy of the same to Engineer-in-charge before commencement of any
electrical work or work pertaining to Electrical System.
32.2 No Electrical work or work pertaining to electrical system (s) shall be permitted to be executed
without a valid Electrical CONTRACTORs License being produced by the CONTRACTOR or Sub-
CONTRACTOR, as the case may be intending to execute the work.
33.1 Contract Clause for acceptance of Structural Steel & TMT Bars
33.1.1 The Contractor shall purchase Structural Steel and TMT Reinforcement Bars from the approved
Manufacturers as per the Master Supplier/Vendor List attached with the Bidding Document.
However, in the event any of the above approved Manufacturers do not quote for the above steel
material due to quantity limitations/constraints, CONTRACTOR may, with the prior approval of
OWNER/PMC, procure such items from the Authorized Stockist(s) of the Manufacturer (s) subject to
fulfillment of the conditions related to furnishing of the MTCs (confirming to the applicable IS Codes)
and Sample Testing as mentioned in the Tender Document.
In addition to availability of MTC (confirming to the applicable IS Codes), for each category/ size of
structural steel procured, one sample from every 50 MT or part thereof shall be drawn and tested in
approved laboratory. The charges for such testing shall be borne by the contractor.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
• Under 10 mm bars one sample for each 25 MT (or part thereof) for consignment below 100
MT and one sample each 40 MT (or part thereof) for consignment above 100 MT shall be
tested.
• For 10 mm to 16 mm bars, one sample for each 35 mm MT (or part thereof) for consignment
below 100 MT and one sample each 45 MT (or part thereof) for consignment above 100MT
shall be tested.
• Over 16 mm bars one sample for each 45 MT (or part thereof) for consignment below 100 MT
and one sample each 50 MT (or part thereof) for consignment above 100 MT shall be tested.
33.2.1 The Cement supplied by the Contractor shall be from the approved Manufacturers as per the
Vendor List attached with the Bidding Document.
In the event of non-availability of cement from the approved Manufactures, the CONTRACTOR shall
propose additional vendor(s) to OWNER/PMC for their prior approval, before procurement of Cement.
However, delay if any, by OWNER / PMC in approving any vendors proposed by CONTRACTOR, or
rejection if any vendors(s), by OWNER/PMC, shall not entitle the CONTRACTOR for any claim for time
extension or any cost implication.
33.2.2 Tests after receipt of Cement at Site: Each batch of cement (week wise as mentioned on cement
bags) supplied by the contractor after delivery at site shall be subject to the tests and analysis
required by the relevant Indian Standard codes. The contractor shall carry out and bear the cost of
all tests and analysis to ensure quality of cement before using in actual works.
34. CONSTRUCTION
34.1 The CONTRACTOR shall within the scope of work observe in addition to specifications, all
national and local laws, ordinances, rules and regulation and requirements pertaining to the
work.
34.2 Various procedures and methods to be adopted by CONTRACTOR during the construction as required
in the respective specifications shall be submitted to OWNER/ CONSULTANT in due time and well in
advance of the specific work for approval.
34.3 The CONTRACTOR shall carry out required supervision as per Quality Assurance Plan and furnish all
assistance required by OWNER/ CONSULTANT in carrying out inspection work. OWNER/
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
CONSULTANT will have authorized representatives present who shall have free access to the work
at all times. If an OWNER/ CONSULTANT representative notifies the CONTRACTOR‟S representative
of any deficiency in any work or in the supervision thereof, the CONTRACTOR shall make every effort
to carry out such instructions consistent with best industry practice.
35.1 All erection shall be carried out by deploying a crane(s) of suitable capacity. Erection by derrick shall
not be permissible. The CONTRACTOR shall submit erection schemes for erection of critical equipment
/ Barricading to Engineer-in-Charge for his approval. No equipment / barricading shall be erected in
the absence of an approved erection scheme for such equipment.
35.2 The quoted Prices of the CONTRACTOR shall be deemed to include load testing of the crane as
required to establish the lifting capacity of the crane.
36.1 ERECTION and Barricading Works shall be carried out as per Drawings and Technical Specifications
attached with the Tender Document and as per instructions of PMC/OWNER.
36.2 Job shall be carried out on round the clock 24 x7 basis with intermittent break as per agreement with
PMC/OWNER.
36.3 CONTRACTOR should ensure testing of Construction materials at local approved IOCL authorized
approved testing laboratory prior to starting of the job and get approval of CONSULTANT.
36.4 Maintenance personnel with all tools & tackles and spares should be available on round the clock
basis for attending the breakdown of equipment, machinery, pump etc. immediately after breakdown.
36.5 Contractor shall use wire rope of reputed make only along with valid Test Certificate to avoid accidents.
Spare wire rope shall be kept readily available to avoid downtime.
36.6 Winch & Fly wheel to be provided with Safety Guard without which the rig shall not be allowed to be
operated.
36.7 100% PPE to be used by all workmen and personnel engaged for the job, otherwise penalty shall be
imposed as per GCC.
36.8 The CONTRACTOR shall deploy and ensure availability of qualified supervisor including safety
supervisor having full knowledge of jobs and safety on round the clock basis.
36.9 In case of non-availability of water by OWNER, the CONTRACTOR shall arrange water without any
extra cost to OWNER.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
36.10 Dress code: All the CONTRACTOR‟s workers and officers should use uniform during working hrs. at
site and reflecting jackets in night working hours.
36.11 OWNER/ CONSULTANT reserves the right to physically check/verify the Ownership/availability of the
equipment at any stage prior to award of work. Bidder shall organize and coordinate the inspection
process. OWNER/CONSULTANT’s option shall be final and binding in this regard.
36.12 Bidder to confirm that these equipment’s are available for deployment in this project site and shall be
timely mobilized in good working condition to maintain work progress. BIDDER has option to propose
equipment’s OWNED or HIRED sources against this category.
36.13 Bidder to deploy well qualified ASNT Level III interpreter and Level II Personnel for scanning and
reporting for NDT.
37.1 It is expressly understood that Govt. of India is not a party to this Contract and has no liability,
obligations or rights hereunder. It is expressly understood that OWNER is an independent legal
entity with power and authority to enter into the Contract solely on its behalf under the Applicable
Laws and general principles of contract law.
37.2 The CONTRACTOR expressly agrees and acknowledges and understands that OWNER is not an
agent, representative or delegate of Government of India.
38. GENERAL REQUIREMENTS FOR RADIOGRAPHY & OTHER NDT FOR MECHANICAL /
COMPOSITE ITEM RATE CONTRACTS
38.1 CONTRACTOR shall appoint radiography/ NDT agency (ies) only after acceptance of such agency(ies)
by OWNER/PMC. However, acceptance of radiography/ NDT agency by OWNER/PMC shall not
absolve the CONTRACTOR of his responsibility to execute radiography work as per requirements of
the Contract.
38.2 CONTRACTOR shall mobilize Radiography/ NDT agency at site along with adequate number of
radiography resources/ NDT equipment & appliances, commensurate with the welding activity and
quantum of Radiography/ NDT work load to avoid delays in Radiography / NDT and consequent
generation of back log. In the event of generation of back log leading to Delay / Holdup of subsequent,
activities OWNER/PMC has right to engage additional agency for carrying out the radiography at the
risk and cost of CONTRACTOR including 100% overhead charge.
38.3 Date and extent of mobilization of radiography/ NDT agency/resources shall be agreed by the
CONTRACTOR and the Engineer-in-Charge at the start of work.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
a) To verify that radiographs are being taken on the prescribed / selected welds / spots only, 5%
of already radiographed spots shall be selected by the Engineer-in- Charge or his designated
person for check shots. The check shots shall be taken up before any further radiography
work.
b) The CONTRACTOR will be paid for the check shots at the quoted rates if no variation is found.
If mismatch / variation is found in any of the check shot as per para 38.3 a), CONTRACTOR
shall have to take re-radiography of the entire lot represented by check shot (a day production
or more as decided by Engineer In-Charge). In such cases, no payment will be made for the
check shots as well as the re-radiography of the entire lot represented by the check shot.
c) In the event of any non-matching / variation is observed in re-radiography of the entire lot a
per para 38.3 b) above with reference to the earlier radiographs taken, the radiography agency
shall be forthright debarred from site. CONTRACTOR shall then carryout re-radiography up to
maximum of 100% of all the prescribed / selected welds/ spots radiographed by the debarred
radiography agency (as per direction of the Engineer In-Charge) at his own cost by engaging
a separate Radiography agency acceptable to OWNER/PMC. The process for verification of
radiographs through check shots shall be continued as per clause 38.3 a) above from the lots
selected by the Engineer In-charge till 2 (two) consecutive lots are found with matching check
shot radiographs to the satisfaction of OWNER/PMC.
d) CONTRACTOR shall be responsible for the repair of faulty welds and or all the required extra
radiography and inspection of the faulty welding work. In case of faulty weld, 100% radiography,
on Contractor account, shall be done on the weld performed as per code. Owner/PMC shall
absolute discretion in the selection of weld, which are to be radiographed.
f) As per Code & Standard, in place of Radiography CONTRACTOR shall arrange Automated
Ultrasonic Testing (AUT) or Semi-Automated Ultrasonic Testing suitable for full penetration butt
weld of piping, as required.
g) Air conditioned Dark Room with facilities like running water and those required for developing
and viewing radiograph films.
39.1 The CONTRACTOR shall adhere to the requirements for DOCUMENT REQUIREMENTS AND
REVIEW PROCEDURE as per Part-I section 11.2.
40.1 CONTRACTOR agrees that the Work and all systems, components and parts of the Work shall
comply with:
i. those design criteria, codes and standards which are specified in this Contract, Scope
of Work and as agreed between CONTRACTOR and OWNER/PMC; and
ii. list of Engineering Standards and Specifications developed for the Project
iii. the requirements of all relevant Indian authorities, including without limitation:
a) Factories Act;
d) Liquid effluent discharge, as per Minimal National Standards for liquid effluents and
i) Requirements of other authorities concerned with the Project or out of any license,
permission, sanction, approval or no objection relative thereto.
CONTRACTOR also agrees that all design criteria, codes and standards included in this Contract
are and at all times prior to the Acceptance of the Work will be in compliance with the requirements of
such authorities.
40.2 CONTRACTOR shall perform all design and engineering in accordance with the Engineering
Standards and Specifications, International Codes and Standards, and National Codes and
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Standards as detailed in clause 40.1 here above, Licensor Specifications and Standards, National
and Local Rules and Regulations.
Revisions of the above as at the date of submission of the last Price-Bid against this Tender shall be
utilized by CONTRACTOR-
In any areas of conflict, the order of precedence, commencing with the highest, shall be as
follows:
The information given in each of the above shall be used, as above, in conjunction with all other
above listed documents. In cases of conflict between documents in the same level of the hierarchy,
the CONTRACTOR shall provide its interpretation in writing of the most stringent requirement for
OWNER/PMC’s approval. In all such cases of conflict, OWNER/PMC’s decision shall be final.
Any deviations to the above require prior OWNER/PMC’s approval. If standards or specifications are
not available for specific applications, CONTRACTOR shall develop such standards and specifications,
based on industry standards and practices, its own experience, and on the basis of fit for purpose. All
new and revised Contract standards or specifications shall be submitted to OWNER/PMC for approval.
The Plant shall be engineered and constructed to minimize the Plant’s environmental impact.
Any modification to agreed design criteria will be subject to CONTRACTOR providing detailed
justification and OWNER/PMC’s approval of the same.
41.2 Add the following at the end of Clause No. 1.0.53.0 of the GCC:
At any stage during currency of the Contract, while carrying out the design and engineering job as part
of this Contract, Contractor shall adhere to/follow the latest revision (notwithstanding that such a
revision has taken place after submission of last price bid) of the applicable specifications and
standards including but not limited to OISD Standards as mentioned elsewhere in the tender. Such
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
design and engineering jobs shall be taken up by the Contractor at any stage without any extra cost to
the OWNER. However, cost towards supply, construction/erection/modification, testing and
commissioning of any facility/system caused due to such revision(s) after submission of last price bid
shall be settled as per the Change Order clause of the Contract.
41.3 Clause No. 10.20.2.0 (ii) (a) of GCC shall be read as follows:
Any reportable physical injury as per Indian Factory Act-1948: - a price reduction of 0.5% of the Lump
sum Price (maximum of Rs.2,00,000) per injury in addition to Rs. 5,000.00.
The CONTRACTOR shall within 30 (Thirty) days from the date of issue of the Acceptance of Bid furnish
Security Deposit in an amount equivalent to 3% (Three percent) of the Lumpsum Price in the manner
specified in Clause 2.1.2.0 hereof. Such security deposit is to be held by the OWNER in lieu of cash as
security for the due performance of the CONTRACTOR’S obligation under the contract and due
discharge of CONTRACTOR’s liabilities under and/or arising out of the Contract.
As and by way of the said Security Deposit, the CONTRACTOR shall within 30 (Thirty) days from the
date of issue of Acceptance of Bid submit one or more unconditional Bank Guarantee(s) from one or
more Bank(s) in India acceptable to the OWNER and in a format, provided by the OWNER, for a sum
equivalent to 3% (Three percent) of the Lumpsum Price of the Contract. Such Bank Guarantee(s) to
the extent that the Lumpsum Price as designated in Foreign Currency, shall be for an amount of 3%
(Three percent) of the designated Foreign Currency(ies), and to the extent that the Lumpsum Price as
designated in Indian Rupees, shall be for an amount of 10% (Ten percent) of the designated Indian
Rupees, and shall be valid in the first instance for a period of not less than 3 (three) months after the
expiry of the defect liability period, reckoned from the scheduled date of final completion under the
Contract.
41.6 In line 3 of Clause 8.6.1.0 of GCC, words “or for or” shall stand deleted
41.7 Appendix-V to GCC : Form of Bank Guarantee in lieu of Earnest Money Deposit is not applicable for
this tender.
41.8 Appendix-VII to GCC: FORM OF BANK GUARANTEE IN LIEU OF SECURITY DEPOSIT is modified
and revised Form of Bank Guarantee is attached as Annexure-A-XXIII of SCC
For the purpose of Payment, the list of critical Tagged items is as per Annexure A-IX.
CONTRACTOR shall finalize the orders for all long lead items within 03 months from the Effective
date of Contract/FOA.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
The performance evaluation of Contractor shall be done as per the enclosed Annexure A-XV to this
SCC.
44. GUARANTEES
Notwithstanding the CONTRACTOR Guarantee provisions expressly stated in clause 5.5.0.0 of the
General Conditions of Contract, CONTRACTOR further warrants the Guarantee requirements for
engineering, materials, supply, construction, workmanship and performance within the guarantee
parameters as set forth in the Scope of Work and in Annexure A-X to this SCC. Should the works and
/ or any part thereof fail to meet the guarantee provisions stipulated herein Special Conditions of
Contract, CONTRACTOR’s obligations & liabilities shall be as determined by the Engineer-in-Charge,
in collaboration with OWNER, under the provisions of the Contract.
45.1 As part of and required by CONTRACTOR’S quality assurance procedures for inspection of
materials / equipment, CONTRACTOR shall, within the Scope of Supply and at its sole cost and
expense, engage a Third-Party Inspection Agency (TPIA).
45.2 CONTRACTOR shall utilize TPIA(s) in the procurement by CONTRACTOR of major / critical equipment
and packaged items, materials of construction and Site construction activities for the duration of the
Project.
45.3 CONTRACTOR shall determine the in-country and out-country (India and outside India) capabilities
of TPIA(s) and engage them accordingly.
45.4 CONTRACTOR shall prepare a list of where they propose to utilize TPIA(s) as part of the scope of
supply. This list shall be submitted by CONTRACTOR for review by Engineer-in-Charge. Engineer-in-
Charge may accept or reject a TPIA based on the review and Contractor has to comply with the
directions of Engineer-in-Charge in this regard.
45.5 CONTRACTOR and / or Vendor / Subcontractor QAP / Inspection and Test Plan shall be reviewed by
OWNER/PMC to ensure that all required inspection and tests on associated work scope has been
covered and to identify and designate which inspection and tests require to be monitored /inspected /
witnessed by TPIA Inspectors.
45.6 TPIA Inspectors to report directly to Contractor as confirmation of their independence and to
issue Inspection Reports, Test Results etc., directly to Contractor for onward issue to OWNER.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
45.7 CONTRACTOR and / or Vendor / Subcontractor to formally notify OWNER in timely advance of Pre-
Inspection Meetings, planned inspection and tests, inspection releases, etc., where such activities
require TPIA participation
45.8 CONTRACTOR shall be responsible for monitoring and verifying all tests and for carrying out or
supervising (as the case may be) all inspections required. Inspection by such TPIA(s) shall not relieve
the CONTRACTOR of its obligations and responsibilities under this Contract.
IOCL has 9 operating Refineries, namely Guwahati Refinery in the State of Assam, Barauni Refinery
in the State of Bihar, Gujarat Refinery in the State of Gujarat, Mathura Refinery in the State of U.P.,
Haldia Refinery in the State of West Bengal, Panipat Refinery in the State of Haryana, Bongaigaon
Refinery in the State of Assam & Digboi Refinery in the State of Assam and Paradip refinery in the state
of Odisha.
It may please be noted that all the Refineries shown above are declared as "prohibited place" under
Official Secrets Act 1923, where entry of personnel is restricted / conditioned. It may also be noted
that the Visa to be issued by Govt. of India, normally contains the clause towards no permission for
entry / visit to such place, a default condition which if not removed / struck-off by the Visa issuing
authorities, will create impediment / restriction in movement of personnel of foreign origin deployed at
particular Refinery, to carry out an activity in terms of engagement / Contract with M/s. Indian Oil
Corporation Limited. The same should be kept in cognizance while submitting request for issue of Visa
by CONTRACTOR’s office.
Refer Annexure A-XI to this SCC. – Not Applicable for this tender
The list of Free Issue Materials is indicated in Annexure A-XII to this SCC.
49.1 Bidder shall comply with the “Policy to Provide Purchase Preference (linked with local content) (PP-LC)
in all Public Sector Undertakings under the M/o P&NG-Amended regarding” Dtd. 17th November-2020,
attached as Annexure A-XIII to this SCC. Bidders shall go through the document for better
understanding of the provisions of the Policy.
49.2 The prescribed Local Content in the Policy shall be applicable on the date of Notice Inviting Tender
(NIT).
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
49.3 It shall be noted that Local Content in the Job shall be calculated by the Bidder as specified in Clause
6.0 of the Policy as applicable (Clause No. 6.2 for Service Contracts and Clause No.6.3 for EPC/LSTK
Contracts).
49.4 Bidders shall furnish the required documents as mentioned in the Clause No.7.1.2 of the above Policy
along with their Techno-Commercial Offer. These details shall be uploaded in the e-tender portal along
with the other documents to be submitted as per the Tender requirements.
49.5 All the bidders have to submit the above documents irrespective of the fact that they want to avail the
benefits under the PPLC Policy or Not.
49.6 Bidders shall note that this Job shall NOT be split and shall be awarded to a single Contractor only.
49.7 In this connection, all the Bidders have to submit an UNDERTAKING/ DECLARATION in the FORMAT
attached as Attachment-1 to the Annexure-A-XIII. In case Bidder wants to avail purchase preference
under PP-LC Policy, Bidder shall submit the declaration form for availing purchase preference and
undertaking duly filled, signed & stamped along with the unpriced Bid as advised in the concerned
Annexure A-XIII to this SCC.
In addition to the GCC provisions for Spare Parts under Cl. 5.8.0.0, the CONTRACTOR shall carry out
SAP codification of surplus materials/mandatory spares, in consultation with PMC/Owner.
CONTRACTOR shall also submit Spare Parts Interchangeability List (SPIR) as per OWNER’s format,
attached as Annexure A-XVI to this SCC.
51. OFFICE ACCOMMODATION, SERVICES AND FACILITIES FOR PMC / OWNER’S PERSONNEL
AT CONTRACTOR'S WORK STATIONS/OFFICES
At any stage during the currency of Contract, in case if so required, PMC/OWNER may depute their
Personnel (maximum 10 Numbers at one occasion) to Contractor’s Home Office in India/Abroad for
expediting/reviewing the Design & Engineering Jobs or for any other specific job in connection with
the subject Contract. This shall include the Offices (In India/ Abroad) of Contractor’s
Design/Engineering CONSULTANT, Supplier(s), Vendor(s) etc. Normally such deployment/deputation
shall be for shorter durations only. In such situations, CONTRACTOR shall ensure that the
PMC/Owner’s Personnel are facilitated with necessary Office Space, Office furniture & equipment,
communication facilities including High Speed Internet, other office supplies etc. which are reasonably
required for the effective completion of the intended job of PMC/Owner’s personnel. Also, facilities and
assistance for Printing, Photocopying and Scanning shall be ensured by the Contractor. Further, the
Contractor shall ensure that the common facilities like Canteen Services, Courier Services, Clerical
/Secretarial Services etc. are also provided to the Personnel during such a period(s) of their
deputation/deployment to the concerned Offices.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Safety is to be given prime importance. During execution, CONTRACTOR shall strictly follow the
safety procedures, precautions, norms laid down by OWNER time to time.
CONTRACTOR shall establish the document and maintain an effective Health, Safety and
Environment (HSE Management System. CONTRACTOR shall include in his offer, the Health,
Safety and Environment (HSE) Management procedure which is required to be adhered to during the
execution of Contract.
53.1 ENTRY PASSES, GATE PASSES, WORK PERMITS AND SAFETY REGULATIONS
The works under this contract are to be carried out in areas within the near vicinity of operating plant.
As such, CONTRACTOR is required to abide by safety and security regulations of OWNER/
CONSULTANT enforced from time to time.
53.1.1.1 The CONTRACTOR has to apply for photo entry passes for his workers & staff in a prescribed proforma
available with OWNER / CONSULTANT. The photo entry passes shall be issued by OWNER for a
maximum period of 4 months and if extension is required by the CONTRACTOR, CONTRACTOR has
to apply separately for extension. As a special case, temporary passes for a maximum period of 7 days
may be issued.
In case of loss of any entry pass, the CONTRACTOR has to lodge FIR with local police station and
inform the Engineer-in-charge and shall have to pay Rs.150/- against each entry pass.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
53.1.1.2 The CONTRACTOR is required to keep track of all entry passes issued and returned. Identity card
issued by the Security Section should always be carried/ displayed by the CONTRACTOR's employee
or person while working inside the Plant.
53.1.1.3 The CONTRACTOR and his subcontractors should leave the location of OWNER’s premises after
the work is completed.
53.1.2.1 To bring materials/equipment/tools/tackles etc. inside the plant for construction work, the
CONTRACTOR has to produce challans/ proper documents to OWNER / CONSULTANT personnel at
gate. The materials shall be checked thoroughly by OWNER’s / CONSULTANT personnel at Gate and
recorded in their register before allowing any material to bring inside the plant by CONTRACTOR. It is
CONTRACTOR's responsibility to see that the recorded entry no., date, signature of OWNER/
CONSULTANT with stamp challans / supporting documents signed by company's personnel at gate
during entry.
53.1.3.1 When the work is to be carried out in hazardous areas, hot work permit is to be obtained before start
of work for all the jobs which are capable of generating flame, spark, heat etc. namely, Gas cutting,
grinding, welding, use of any electrical/ diesel/ petrol/ battery operated prime mover/ machine/
tools/ equipment/ generator sets/ mixer machine/ drilling machine/ pumps/crane, fork lifter/ hand
truck/ trailer, chipping/ breaking of rocks/concrete, hacksaw cutting and drilling, etc.
53.1.3.2 Cold work permits are to be obtained for the jobs which are not coming under the category of hot work
and where there is no risk of fire, viz, transportation/ backfilling of ordinary soil in manual process,
piling testing, hydro testing, shuttering, fixing of reinforcement, hand mix concreting, plastering, brick
work etc.
53.1.3.3 According to nature of work and use of various types of equipment & tools the CONTRACTOR has
to apply for cold/hot permits in a prescribed format at least 2 days before the work is planned to start.
No work permit shall be issued by OWNER/ CONSULTANT unless proper arrangement is made by
the CONTRACTOR to ensure safe performance of work inside the plant. Job wise and area wise
permits shall be issued to the CONTRACTOR and against each permit at least one construction
supervisor and one safety supervisor of required level shall always be made available at site by the
CONTRACTOR. These safety permit shall be issued at one point contact by OWNER/
CONSULTANT.
53.1.4.1 Permits are to be obtained separately for entry/use of vehicles/ trailers etc. inside the plant.
ii) Valid Road tax certificate, fitness certificate and insurance policy from competent authority.
ii) No permit is valid if it is not renewed by the shift in charge/ shift representative in shifts (Morning &
Evening)
iii) The permit shall be issued for a maximum period of one month and if extension is required, the
CONTRACTOR has to apply for fresh permit.
iv) No permit is valid on holidays unless special permission is obtained from the competent authority.
The work shall be carried out inside the plant as per safety practices enforced by OWNER/
CONSULTANT safety section and instructions of Engineer-in-charge issued from time to time. Many
times, it may happen that the working hours shall be drastically reduced or increased to meet certain
safety requirements and the CONTRACTOR shall meet these requirements without any additional
time and financial implications.
To obtain work permit and to satisfy all conditions laid down therein, shall be the responsibility of the
CONTRACTOR. No claim for idling of machinery, plant, manpower etc. for safety reasons or non-
issuance of work permit by In-charge, Safety Section shall be considered.
The CONTRACTOR shall abide by all safety regulations of the plant and ensure that safety for specific
job kit as stipulated in the factory act/ safety handbook is issued to the employee during the execution
of work, failing which all the works at site shall be suspended.
OWNER/ CONSULTANT shall permit CONTRACTOR and his authorized construction personnel to
freely move, in and out of the site, subject to the observance of security and safety regulations of
OWNER /CONSULTANT. In view of specific security requirement for the refinery installation and its
Strictest observance, all personal of CONTRACTOR or his authorized construction personnel
(skilled/ unskilled) are required to have detail police verification for the purpose of issue of photo pass
required for entry and free movement at work site. They will also have to bear with the restriction and
limitation of /exit to work site as per the security requirement.
When doing hot work inside the plant the CONTRACTOR must ensure that the fire hose is hooked up
with the fire water system and extended to the work spot. Fire extinguisher must be kept near the
working spot. Area around and below the hot working place must be adequately protected from falling/
coming out of sparks/hot metals from the booth made of ceramic cloth or some other suitable
material may be proposed for hot job booth for fire blanketing purposes.
The CONTRACTOR must arrange sufficient number of fire hoses and firefighting equipment of
approved quality at his own cost to carry out hot job inside the plant.
Welding & electrical cables should be of approved quality, and no jointing and loose connection shall
be permitted.
At the end of the working day the CONTRACTOR must inform electrical section to switch off power at
sub-station end.
The CONTRACTOR must provide cotton dress, safety shoe, safety helmet, safety belt, hand gloves
of approved quality to his workers to meet the safety requirement of various jobs to be carried out
inside the plant.
IFR cover all made mandatory for welders, gas cutters and grinders.
Vehicle must not ply on any road within the plant at speed exceeding 20KM/hr.
Mobile crane/ loaded trucks/ trailers must not exceed speed limit of 15 KM/hr inside the plant.
56. DOMESTICALLY MANUFACTURED IRON & STEEL POLICY (DMI&S) & DOMESTICALLY
MANUFACTURED ELETRONIC PRODUCTS
Refer Annexure – A-XXI enclosed to SCC and Notification dated 7th Sep 2020.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Bidder’s personnel shall observe/abide by site working conditions prevailing at the existing site,
safety codes, Indian laws and local laws.
All foreign nationals coming to India for execution of projects / orders will have to apply for necessary
visa. In their own interest bidders are advised to check latest visa rules from relevant sources in their
country in case foreign nationals are required to be deputed to India during execution of order. Visa
should not contain the clause “Not valid for Prohibited, Restricted and Cantonment Areas”.
Bidder’s quoted prices for training at vendor’s office shall include all the charges. However, all
expenses towards owner’s personnel / representatives deputed to contractor’s Office and / or Plant
for training, in respect of travelling, boarding and lodging and travel and living expenses in the place
of work will be borne by the OWNER. The CONTRACTOR shall, however, provide reasonable office
accommodation, furniture, clerical assistance, e-mail and telephone facilities required by such
personnel / representatives for the performance of their duties free of cost to the OWNER.
CONTRACTOR agrees to use the latest design software and tools listed in section 11.2, Document
requirement and review procedure for Detailed Engineering, Planning and Reporting.
SPECIAL CONDITIONS
OF
LSTK CONTRACT
a. The Price quoted shall be Lump sum Price on Turnkey (Supply of services at Project Site) basis. Total
payments to be made to the Contractor shall be limited to Lump sum price indicated in the Price Bid,
irrespective of the progressive payments made during execution based on the split up of price.
b. Obligation of the Contractor is not limited to the quantities that the Contractor may either indicate in
the Breakup of Lump Sum Prices along with his bid or in further detailed breakup of lump sum prices
to be furnished after award of Work. Contractor shall carry out and complete entire scope of
work/supplies/services as detailed in various sections/volumes of the Bidding Document within the
quoted Lump Sum Price.
c. Lump sum prices quoted by the Contractor shall include cost of any other supplies/work(s) /services
not specifically mentioned in the Bidding Document but necessary for the efficient, trouble free
operation of the Plant and to make this package job complete.
d. Contractor to note that breakup of Lump sum price in SP forms are for interim payment purpose only
and total price payable under the Contract shall be restricted to the Lump Sum Price/Contract Price.
e. The total of prices quoted for Engineering portion (in FORM SP-2) and Supply portion (in FORM SP-
1) taken together shall not exceed 70 % of the total Lump Sum Price (in FORM SP-0). In case the
price for Engineering and Supply component exceeds the above-mentioned limit, then such additional
amount shall be payable to the Contractor in the Final Bill.
f. The Price for Engineering Price indicated in FORM SP-2 shall not exceed 7% of Total Lump Sum
Price (in FORM SP-0). In case the price for Engineering Price Component exceeds the above-
mentioned limit, then such additional amount shall be payable to the Contractor in the Final Bill.
g. Spares for start-up/commissioning and mandatory spares required, are in CONTRACTOR's scope
and deemed to be included in their quoted Lump sum Prices.
a. Following Forms of Schedule of Price are also enclosed. FORM SP-6 indicating 2 years O&M
spares.
b. FORM SP-7 for Comprehensive Post Warranty Annual Maintenance Contract (CPWAMC)
Services for five years various Instrumentation and Electrical equipment after defect liability
period of the contract.
h. It shall be the duty of the CONTRACTOR to duly observe and perform all laws, rules, regulations,
orders and formalities applicable to, CGST, SGST & IGST and Customs Duty, etc. on the import,
manufacture, sale and/or supply of any material to the OWNER and performance of the works under
the Contract. The CONTRACTOR shall keep the OWNER indemnified from and against any and all
claims, demands, prosecutions, actions, proceedings, penalties, damages, demurrages and/or other
levies whatsoever made or levied by any Court, Tribunal or the Customs or other Authorities with
respect to any al6leged breach, evasion or infraction of such duties, taxes, charges or levies or any
breach or infraction of any applicable laws, rules, regulations, orders or formalities concerning the
same and from the consequence thereof.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
i. Comprehensive AMC charges submitted vide FORM-SP 7 shall be considered for price bid evaluation
purpose. (to be decided on case to case basis) IOCL reserves right to accord AMC work order to
Bidder after completion of defect liability period.
The entire Scope of jobs under this Contract has been classified as Supply of Service in relation to an
immovable property under GST (Excluding items for which separate Work Order is issued for Supply as
per clause 3.4.1 of SCC Part B) and the place of supply of Services shall be the location at which the entire
Scope of Works to be carried out as mentioned elsewhere in the Bidding Documents. Accordingly, the
CONTRACTOR is required to take GST registration for supply of Services and subsequent invoicing to the
OWNER under the Contract.
The quoted prices shall remain firm and fixed, and valid, until completion of the Contract, unless specifically
mentioned otherwise elsewhere in the Tender. The applicable SGST & CGST/IGST and Customs Duty,
SWS was quoted by the bidder separately in Form SP-03 and GST on Services in foreign currency by
foreign bidder/ foreign member of Consortium/ JV shall be loaded on the Lump sum quoted Price for price
comparison. No other taxes and duties except the quoted rates in Form SP-03 shall be eligible for
reimbursement, unless specifically mentioned otherwise elsewhere in the Tender.
3.1 CENTRAL GOODS & SERVICE TAX (CGST) & STATE GOODS & SERVICE TAX (SGST) /
INTEGRATED GOODS & SERVICE TAX (IGST).
a) The CONTRACTOR shall be reimbursed at actual Central Goods & Service Tax (CGST) & State
Goods & Service Tax (SGST) payable in India on the intra-State supplies to the OWNER against
submission of invoice issued in accordance with the Invoice Rules. Where supplies are inter-state in
nature, the CONTRACTOR shall charge Integrated Goods & Service Tax (IGST). The Invoice issued
under GST shall be as per provisions of Central Goods and Service Tax and Rules made there under.
At present following particulars are required to be contained in the Invoice: -
vi. Name and address of the recipient and the address of the delivery, along with the State
and its code,
x. Taxable value of supply of goods or services taking into discount or abatement if any;
xi. Rate of tax (Central Tax, State Tax, Integrated Tax (for inter-state supply), Union
Territory Tax or cess);
xii. Amount of tax charged in respect of taxable services (Central Tax, State Tax,
Integrated Tax (for inter-state supply), Union Territory Tax or cess);
xiii. Place of supply along with the name of State, in case of supply in the course of inter-
state trade or commerce;
xiv. Address of the delivery where the same is different from the place of supply;
xv. Whether the tax is payable under Reverse Charge basis and
Above details are only for illustration purposes and it is obligatory for the Contractor to issue
GST Invoice as per provisions of Central Goods and Service Tax and Rules made there under.
b) In case of any advance including Mobilization Advance given as per Contract, the CONTRACTOR
shall issue a Receipt Voucher (RV) or GST Invoice containing all details as per Central GST Act and
Rules made there under at the time of issue of RV or Invoice.
c) In case of any Price Variation of Construction Materials applicable as per SCC Clause 8 and any
Foreign Exchange fluctuation, the CONTRACTOR shall issue a GST Invoice containing all the details
stated in (a) (i) to (xv).
d) In case of Price Adjustment for delay in Completion applicable as per GCC Clause No. 4.4.0.0, the
Contractor may issue a Credit Note under Central Goods and Service Tax Act and rules made
thereunder for the Price Reduction amount containing all the details as per law in force at the time of
issue of Credit Note. However, Contractor has the option to issue a Commercial Credit Note without
GST implication. In either case Credit Note has to be issued within 30 days from the date of intimation
of invocation of Price Adjustment under GCC Clause No. 4.4.0.0
e) If Contractor does not issue Credit Note in terms of clause (d) above, the Owner shall issue a GST
Invoice for the amount of Price Reduction plus applicable GST withheld in terms of Clause 6.4.7.3 of
GCC.
f) Where a GST Invoice is issued by the Owner, the amount of price reduction (excluding GST), on a
written request made by the Contractor, may be released under a cover of Bank Guarantee of
equivalent amount issued in favour of the owner. In case GST Invoice is not issued, amount withheld
(including GST), on a written request made by the contractor may be released under a cover of Bank
guarantee of equivalent amount issued in favor of the owner. The format and other requirement of
Bank Guarantee shall be same as defined in Clause 6.4.7.3 of GCC. Amount to be withheld as per
clause no 6.4.7.3 of GCC shall be withheld after including applicable GST on the amount withheld.
This Bank Guarantee shall be valid for a period so that same may remain in force till the invocation
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
g) In case of recovery on account of License Fees on Land as per GCC Clause No. 3.7.0.0, Owner shall
issue an Invoice including applicable GST for adjustment against RA / Final Bills.
h) It's the obligation on the part of Bidder / Vendor / Contractor / Consultant to discharge his liability by
payment of GST to Government of India in cash OR utilization of Input Tax credit in respect of such
supply of services through GST Invoice under this Contract, so that Owner can avail Input Tax credit
on such supply. In the event that the input tax credit of the GST charged by the Bidder / Vendor /
Contractor / Consultant is denied by the tax authorities to OWNER due to delay by Bidder / Vendor /
Contractor / Consultant, in issue of Invoice, Debit Notes or Credit notes, filing of Return of Outward
Supplies, payment of taxes or filing of any other Returns as required under GST Laws and Rules, or
timely corrections, rectification or modification in the detail of Return of Outward Supplies or any other
Returns, etc. Owner shall be entitled to recover such amount from the Bidder / Vendor / Contractor /
Consultant by way of adjustment from the next invoice or from Bank Guarantee. In addition to the
amount of GST, Owner shall also be entitled to recover interest and penalty, in case same is imposed
by the tax authorities on Owner.
3.2 The Bidder / Contractor should refer to Clause 3.0.8.0, 6.5.2.0 and other associate clauses of GCC, which
shall be applicable with respect to Taxes and Duties and other levies.
3.3 There will be no materials under the scope of Contract which will be directly consigned to Owner, unless
otherwise specifically mentioned elsewhere in the tender. The OWNER will not issue / provide Road Permits
/ e-Way bill to the CONTRACTOR except in respect of material directly purchased by the OWNER.
3.4.1 The CONTRACTOR must have the GSTIN in India. The CONTRACTOR has to clear imported
consignment (except EPCG cases) in its own GSTIN along with their Importer Exporter Code (IEC) in
Bill of Entry on payment of Customs Duty & SWS, IGST, GST Compensation Cess etc. as may be
applicable, at the time of import. In EPCG cases, customs clearance shall be within the scope of
OWNER.
3.4.2 EPCG Or Project Import benefit or any other such Scheme or Benefit (hereinafter collectively called
“Special License(s)”) whereunder Owner is entitled to imports goods with concessional rate of Custom
Duty is not envisaged for this Tender. However, if any time during the tenure of the contract but before
Mechanical Completion, Owner opts to avail the benefit of EPCG or Project Import, same shall be
communicated to the Contractor forthwith and the Contractor shall be bound to afford all facilities,
opportunity, and assistance as defined in clauses hereunder enabling Owner to avail benefits of EPCG
or Project Import Licenses at the time of import of goods. The amount of taxes and duties payable under
imported material shall be limited to the amount quoted by CONTRACTOR in SP-03 Forms of tender,
after adjusting benefits under Special License(s).
3.4.3 Where the Owner opts to avail the benefits of EPCG/Post export EPCG, EPCG/Post export EPCG
License shall be provided to LSTK Contractor and customs clearance shall be done under Indian Oil
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
import export code by endorsement of EPCG License number in Bill of entries as the Owner will be the
importer on record.
In case OWNER opts to avail the benefits of EPCG/Post export EPCG and Customs clearance of
imported consignments is done in the Indian Oil Import Export Code, the amount of duties, taxes etc to
be paid/reimbursed to contractor shall be mutually agreed by Owner and Contractor before opting for
above.
3.4.4 Supply of Imported Goods by Indian Bidder on OWNER account/ Supply of Imported Goods by
Foreign Bidder (in case of direct bidding) or Foreign member of Consortium/JV.
The Foreign Bidder / Foreign Member of the Consortium or JV shall supply the imported materials
entirely on OWNER account. The material shall be consigned to OWNER and import shall be done on
OWNER’s name. Separate Order for Imported Supplies shall be issued under umbrella Contract of total
LSTK works.
All the imported consignments shall be cleared under GSTN/ IEC Code of OWNER as importer of goods
on payment of Customs Duty by OWNER on Import Invoice value as per approved billing break-up, but
all formalities for necessary clearance from Customs is on Contractor account. The Owner’s
responsibility for payment of Customs Duty and related taxes and duties (SWS on Customs Duty, IGST)
for imports for the purpose of permanent incorporation in the Works, shall be limited to the applicable
merit rate of Customs Duty calculated on the amount of Foreign Currency quoted in FORM SP-1.The
amount paid by Owner in excess of amount quoted in form SP-3 shall be recovered from the Contractor.
The CONTRACTOR shall within 7 (seven) days of dispatch/ shipment of any such materials, forward to
the OWNER the Supplier’s/ Vendor’s Invoice in line with approved billing breakup of the materials for
the purpose of assessing Customs and other Import Duties, Bill of Lading/Airway Bill, package wise
packing list, Certificate of Origin and other relevant documents relating to the identification of the
materials, the assessment of Customs Duties and the clearance of the goods through Customs. The
CONTRACTOR shall be fully responsible for Port and Customs clearance including stevedoring,
handling, unloading, loading and storage and for satisfying all Port and Customs formalities for the
clearance of the goods, including preparation of the Bill(s) of Entry and other documents required for
import and/or clearance of the goods. The CONTRACTOR shall also be fully responsible for any delays,
penalties, demurrages, shortages and other charges and losses, if any, in this regard”. All the facilitation
shall be provided by LSTK Contractor including de-bonding process with Customs.
3.4.5 I) Supply of imported goods by Indian Bidder’s on (CONTRACTOR) account
In case, the percentage quoted at Sr. No.: 2 of Form SP-3 is less than the actual rate applicable
on last price bid submission date, the reimbursement of taxes will be limited to the rate quoted in
form SP-03.
II) Supply of imported goods by Indian Bidder on OWNER account/ Supply of imported goods
by Foreign Bidder (in case of direct bidding) or Foreign member of Consortium
In case, the percentage quoted at Sr. No: 2 of Form SP-3 is less than the actual rate applicable on
last price bid submission date, the differential amount on account of above-mentioned rate variation
will be recovered from Running Account Bills of the contractor”.
3.4.6 If for any reason, other than a Change Order, the total imported materials mentioned in FORM SP-
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
1 of the Price Schedule are exceeded or any penalty or other charges or higher rate of duty
than applicable to relative imports is levied on the OWNER with respect thereto, the Customs
Duty/penalties and other charges or levies, if any, to the extent of the excess levied, shall be to the
CONTRACTOR‟s account and shall be borne and paid wholly by the CONTRACTOR as and by
way of adjustment/deduction in the price of materials payable.
3.4.7 (i) The OWNER will not bear any liability towards payment of Safeguard Duty, Anti-Dumping Duty,
Protective Duty and applicable IGST on same Or Countervailing Duty on subsidized
articles or any other such duties of Customs imposed by the Government under Customs
Tariff Act, 1975 applicable on import of any materials to India for the subject work.
(ii) If Bidder intends to source import of goods from a country with which India has Free Trade
Agreement or Comprehensive Economic Partnership Agreement or any such Agreement or Treaty,
or under Generalized System of Preference (GSP), Bidder is advised to satisfy and ensure that all
laws and regulations related to such imports are strictly complied with. In case such imports are on
Owners Account, same shall not be undertaken without knowledge and written consent of the Owner.
3.4.8 The CONTRACTOR shall provide the OWNER with all documents necessary for the OWNER to claim
Input Tax credit (ITC) under GST as claimed in the GST invoice. Should the CONTRACTOR fail to
provide any such document(s) resulting in a shortfall in the ITC to the Owner, such shortfall shall be
made good by the CONTRACTOR, and shall be deductible without prejudice to any other mode of
recovery from the Running Account or other bills or payments to the CONTRACTOR.
3.4.9 ISSUE OF ESSENTIALITY CERTIFICATE AND IMPORTS AGAINST EPCG AND OTHER
SPECIAL LICENSE(S)
a) The Essentiality Certificate (EC) shall be issued to the CONTRACTOR for value not exceeding
the CIF value quoted in form SP-1
b) The OWNER shall not be obliged to provide the documents to obtain the Essentiality Certificate
or Special License (s) as the case may be, for materials consigned to CONTRACTOR or any
Supplier for use in fabrication and for materials imported by indigenous Sub-contractors.
c) In order to enable the OWNER to obtain Essentiality Certificate or other applicable Special
License(s) from the concerned authorities, the CONTRACTOR shall furnish the OWNER and
CONSULTANT the required particulars (e.g. Description of Materials, Quantity, Value, Vendor
particulars, Purchase Order particulars, Port of Discharge, etc.) at least 10 (Ten) weeks prior
to the expected receipt of relative materials at Indian Port. The OWNER does not assume any
responsibility or liability for any delay in timely issue of Essentiality Certificate or EPCG or other
Special License(s) covering the materials imported into India for incorporation in the works or
for the issue of Essentiality Certificate with respect to any import by the CONTRACTOR. Where
Owner fails to provide Essentiality Certificate to the Contractor for reasons not attributable to
the Contractor, the Contractor should make a request to the Owner for clearance of goods
under merit rate of duty to avoid any delay in execution of Projects.
commissioning or otherwise up to and until issue of the Completion Certificate shall also be
provided by the OWNER in accordance with the provisions hereof foregoing, provided that the
OWNER shall not pay nor shall be liable to pay any customs or customs related duties on any
value beyond the said duties payable at the aforesaid applicable rate(s) on the CFR value of
imported materials indicated in Form SP-1 of the Price Schedule.
e) The CONTRACTOR shall appoint a Customs House Clearing Agent of good standing and
ensure speedy customs clearance.
f) The CONTRACTOR shall be responsible to register the import License / Essentiality Certificate
with Customs Authorities at the Port of Import, and to answer and sort out queries (if any) raised
by Customs Authorities with regard to any import(s).
g) On completion of the Works / Unit, the CONTRACTOR shall undertake a reconciliation of the
materials imported for permanent incorporation in the Works with the EC / PAC / Special
License(s) provided by the OWNER. Such reconciliation shall be a pre-condition to the release
of any payment against the Final Bill and / or release of any bank guarantee furnished by way
of security deposit to the OWNER.
h) If for any cause the CONTRACTOR is unable to complete the reconciliation of imported
materials at the Site with the Essentiality Certificate or EPCG or other Special Licenses with
the Customs or other Authorities concerned before the payment to the CONTRACTOR of the
Final Bill, the CONTRACTOR shall submit a suitable bank guarantee in a format and from a
bank in India (including the Indian branch of a foreign bank) acceptable to the OWNER for an
amount mutually agreed between the OWNER and CONTRACTOR to secure the OWNER
against any claims by the Customs or other concerned Authority for duty or penalty on any un-
reconciled material imported by the CONTRACTOR, and release of payment against the Final
Bill shall be subject to the CONTRACTOR furnishing such bank guarantee. The said bank
guarantee shall be valid for a period of one (1) year and shall be renewed thereafter until the
CONTRACTOR furnishes satisfactory proof of reconciliation with the Customs Authority of the
imports under the Contract and release of the Bond submitted in this behalf by the OWNER to
the Customs Authorities. If the un-reconciled value of imported materials and penalties leviable
thereon are greater than the amount payable on the Final Bill, then this Bank Guarantee shall
be submitted to the OWNER prior to release of the Bank Guarantee(s) submitted by the
CONTRACTOR towards security deposit.
3.5.1 The CONTRACTOR shall be exclusively responsible and liable to pay taxes on income comprised in
all or any payments arising out of the Contract, whether payable / paid in India or in any other
jurisdiction and quoted prices shall be inclusive of Income Tax.
3.5.2 Withholding tax / tax deductible at source is applicable to all payments to be made to the
CONTRACTOR. Withholding / deduction is required to be made at the rates specified in the Indian
Income Tax Act. However, in case of non-resident contractors, lower of the rate of withholding tax as
available in the relevant Double Taxation Avoidance Convention or Agreements (DTAA) as notified
or amended from time to time as compared to the rate applicable as per relevant Finance Act will be
applicable subject to certain specified documentary compliances. Therefore, it is incumbent upon the
Contractor to decide and declare whether it intends to take benefits of lower rate of Withholding Tax
and commit to provide necessary documents. As per extant provisions of Income Tax Act and Rules
made there under following documents are mandatory for this purpose (a) Tax Residency Certificate
(TRC) issued by the competent authority of the country of residence of the Contractor (b) Form 10F
as described in Income Tax Rules, 1962 and (c) Copy of PAN/A declaration in specified format in lieu
of Permanent Account Number (PAN).d) No PE Certificate for availing benefit under DTAA.
3.5.3 The Indian Income Tax Act and rules made there under contains provisions permitting deduction of
tax at a lesser rate if the CONTRACTOR is able to justify to the Income Tax Authorities such lesser
rate of deduction. However, a deduction once made has to be deposited by the OWNER with the
Income Tax Authorities in India and will not be adjustable by the OWNER. It is therefore in the interest
of the CONTRACTOR that prior to release of any payment due to the CONTRACTOR under the
Contract that the CONTRACTOR obtains, from the relevant Income Tax Authorities in India, a
certificate specifying the rate of deduction / withholding of Income tax at source, failing which,
payment to the CONTRACTOR shall be made by the OWNER after Withholding / deduction at the
highest rate as may be applicable to the non-resident contractors as per Provisions of Income Tax
Act, 1961.
Building and Other Construction Workers’ Welfare CSS Act, 1996 and the rules framed there under shall
be applicable for the job and the CONTRACTOR shall be responsible to comply with all provisions of the
same. The Cess as per the Act shall be deducted at source from the Bills of the CONTRACTOR by the
Owner/Engineer-in-Charge as per the prevailing rate. The Cess collected shall be remitted to the
“Secretary, Building and Other Construction Workers Welfare Board” of the concerned State. The
CONTRACTOR shall be responsible to submit final Assessment Return of the Cess amount to the
Assessing Officer after adjusting the Cess deducted at source. BOCW Cess will be deducted at applicable
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
rate and deposited with appropriate authorities as per Statutory Provisions as may be applicable.
The BOCW cess shall be deducted at the applicable rates on the total cost of construction.
5. PROVIDENT FUND
a) The CONTRACTOR shall strictly comply with the provisions of Employees Provident Fund Act
and register the establishment with the concerned Regional Provident Fund commissioner
before commencing the work. The CONTRACTOR shall deposit “Employees” and “Employers”
contributions in the designated account with the designated Authority every month. The
CONTRACTOR shall furnish along with each running bill, the challan/receipt for the payment of
provident fund made to the RPFC for the preceding month(s).
b) In case the Provident Fund Authority's receipted challan referred to above is not furnished, the
OWNER shall deduct 5% (Five percent) of the payable amount from the CONTRACTOR'S
running bill and retain the same as a security for the payment of the Provident Fund. Such
retained amounts shall be refunded to the CONTRACTOR only on production of challan / receipt
of the Provident Fund Authority for the period covered by the related deduction.
The following provisions shall be read in conjunction with the provisions of Section 6.4.0.0 of the General
Conditions of Contract (GCC). The following provisions shall supersede the GCC provisions to the extent
of repugnance and variance, if any. The billing of the entire price of materials, services and reimbursement
for Taxes & Duties shall be done from and to a single point only.
6.1.1 5% on Signing of the formal Contract between the OWNER and the CONTRACTOR and on
submission of:
• Bank Guarantee(s) equivalent to 110% of Mobilization advance covering the Foreign
Currency portion and the Rupee portion of the said advance(s), valid for 3 months beyond
scheduled date of commissioning of the PLANT, from any Bank as mentioned in the
Special Conditions Contract (SCC-Part-A) and in a format acceptable to the OWNER. The
CONTRACTOR shall at the request of the OWNER suitably extend the validity of the Bank
Guarantee (s) for such period or periods as may be required failing which, without prejudice
to any other right or remedy available to the OWNER, the OWNER shall be entitled to
encash the bank Guarantee(s).
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
6.1.3 The advance paid to the CONTRACTOR shall be used only for execution of this Contract and the
CONTRACTOR shall satisfy the OWNER/Engineer-in-Charge in this regard whenever required. If it is
found that the said advance has been utilized by the CONTRACTOR in whole or part for any other
purpose, the OWNER may at its discretion forthwith recall the entire advance and without prejudice to
any other right or remedy available to the OWNER, recover the same by recourse to any Bank
Guarantee(s).
6.1.4 The Indian Rupee advance(s) shall carry interest @ 7.70 % per annum calculated on the reducing
unadjusted balance(s) of the Indian Rupee advance(s) and the advance(s) shall, without prejudice to
any other mode of recovery available to the OWNER, be recovered from the Bills of the CONTRACTOR
@ 10% (Ten percent) of the Certified Bill amount. The interest accrued thereon shall be additionally
deducted from the amount payable.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
6.1.5 Foreign Currency Advance(s) shall carry interest @ 7.70 % per annum on the reducing unadjusted
balance(s) for relative foreign currency. The advance (s) shall, without prejudice to any other mode of
recovery as may be available to the OWNER, be recovered from the bills of the Contractor made out
in the relative foreign currency @ 10% (ten percent) of the amount payable against the bill. The interest
accrued thereon shall be additionally deducted from the amount payable.
6.1.6 All recoveries against advances shall first be apportioned to interest and then to principal. At the request
of the CONTRACTOR, the Engineer-in-Charge shall certify the mobilization advance repaid and the
Bank Guarantee issued on behalf of the CONTRACTOR to secure the mobilization advance shall stand
reduced by the amount and the currency of the repayment certified. Such reduction shall be allowed
not more than 06(six) occasions during the currency of Bank Guarantee.
6.1.7 TDS on interest recovered on mobilization advance will be deposited by the Contractor and same would
be reimbursed by the Owner against submission of Form-16.
6.1.8 The Contractor to ensure the validity of all bank guarantees as stipulated elsewhere in the Contract
and no payment shall be released to the Contractor if the validity of the bank guarantee is less than 30
days unless otherwise specifically intimated to the Contractor.
6.1.9 The CONTRACTOR shall note that the rating of bank sanctioning the Bank Guarantee(s) should not
fall below the rating of “A” from Moody’s or equivalent (from other rating agency) in case of foreign bank
and of at least “AA” from CRISIL or equivalent (from other rating agency) in case of Indian banks during
the tenor of the Bank Guarantee(s). In case the rating falls below threshold level at any time during the
tenor of the Bank Guarantee(s), the CONTRACTOR will arrange to replace the Bank Guarantee(s), at
its cost, through a bank acceptable to OWNER. In case of non- submission of replaced Bank
Guarantee(s), without prejudice to any other right or remedy available to the OWNER, the OWNER
shall be entitled to en-cash the Bank Guarantee(s).
6.1.10 The unadjusted balance of the Mobilization Advance shall be adjusted in full against payments due on
Mechanical Completion.
Subject to the other provisions of the Contract documents, on account payments shall be made as
follows:
Subject to the other provisions of Contract documents, on account payments for the supplies will be
made as follows:
i) 10% (Ten percent) of total supply value as per SP-1 of Price Part of the tender (excluding cost
of Mandatory Spares and cost of construction materials like Cement, Reinforcement Steel etc.)
on placement of Purchase Order for major critical tagged items (as per list of major tagged
equipment attached to this SCC as Annexure-A-IX) on pro-rata basis. This payment shall be
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
released after submission of Bank Guarantee for equivalent value. This bank guarantee shall
be valid up to the Contractual Date of Completion plus three months. However, this Bank
Guarantee shall be released after receipt of all materials at Site and issue of certificate of
verification and good condition in respect thereof in accordance with Clause 3.0.6.4 of the
General Conditions of Contract. The value of advance Bank Guarantee will be allowed to be
reduced on the written request of the CONTRACTOR in not more than 04 (four) occasions
during the execution of the Contract and on recommendation and certification of Engineer-in-
Charge for receipt and acceptance of materials in good condition at Site and on adjustment of
advance by Owner’s Finance department.
Note:
Where the sale of materials to the OWNER is deemed to take place in the course of
international trade through endorsement / transfer of shipping documents during
transit in high seas, the above documents shall be endorsed in favour of the OWNER.
Note:
Where the sale to the OWNER is deemed to take place by endorsement / transfer of
Railway Receipt or Truck / Lorry or any receipt during transit, the above documents
shall be endorsed in favour of the OWNER.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
iii) On Issue of Certificate of Verification and Good Condition at Site, against Contractor's Certified
Running Account Bill(s):
20% (Twenty percent) of DDP price excluding GST of imported / indigenous materials as
indicated in the Bill of Materials on submission of:
iv) 5% (Five percent) of DDP price excluding GST of imported material / indigenous materials as
indicated in the Bill of Materials and on issue of Mechanical Completion Certificate against
CONTRACTOR’s certified running Accounts Bill(s).
v) 2% (Two percent) of the DDP price excluding GST of imported materials / indigenous material
as indicated in the Bill of Materials on successful commissioning of the plant / works against the
CONTRACTOR’s certified Running Account Bill(s)
vi) 1% (One percent) of the DDP price excluding GST of the imported materials / indigenous
materials as indicated in the Bill of Materials on issue of Commissioning and Performance Test
Certificate against the CONTRACTOR’s certified Running Account Bill(s)
vii) 2% (Two percent) of the DDP price excluding GST of the imported materials / indigenous
materials as indicated in the Bill of Materials on completion of all jobs against the
CONTRACTOR’s certified Final Bill
Note: DDP as per Incoterms 2020 is - “Delivered Duty Paid” means that the seller delivers the
goods when the goods are placed at the disposal of the buyer, cleared for import on the arriving
means of transport ready for unloading at the named place of destination. The seller bears all
the costs and risks involved in bringing the goods to the place of destination and has an
obligation to clear the goods not only for export but also for import, to pay any duty for both
export and import and to carry out all customs formalities.
Stage payment against "Proof of dispatch of Materials" shall be released on submission of the
following documents with the CONTRACTOR’s invoice:
a) Signed invoice(s)
b) A full set of certified copies of clean onboard bills of lading / airway duly certified by
OWNER's port offices at major ports preferably Kolkata (as the case may be) and all
originals of clean onboard bills of lading / airway.
c) Certificate of country of origin issued by a competent authority.
d) Packing list / Delivery Challan (as applicable)
e) Manufacturer’s Test Certificate
f) Third Party Inspection Release Note clearly indicating that material has been
inspected and accepted as per QAP approved by OWNER/PMC, or waiver certificate
issued by OWNER/PMC.
Note:
Where the sale of materials to the OWNER is deemed to take place in the course of
international trade through endorsement / transfer of shipping documents during
transit in high seas, the above documents shall be endorsed in favour of the OWNER
ii) 30% (Thirty percent) of DDP price excluding GST of imported / indigenous material as indicated
in the Bill of Materials on receipt of material at Site and acceptance thereof, against Contractor's
Certified Running Account Bill(s)
iii) 5% (Five percent) of DDP price excluding GST of imported / indigenous materials as indicated
in the Bill(s) of Materials on providing Gate Passes and after carrying out all activities to facilitate
capitalization of Mandatory Spares through entering its receipt in OWNER’s ERP System,
against Contractor's Certified Running Account Bill(s)
iv) 3% (Three percent) of the DDP price excluding GST of the imported materials / indigenous
materials as indicated in the Bill(s) of Materials on issue of Commissioning and Performance
Test Certificate against the CONTRACTOR’s certified running Accounts Bill(s)
v) 2% (Two percent) of the DDP price excluding GST of the imported materials / indigenous
materials as indicated in the Bill of Materials on completion of all jobs against the
CONTRACTOR’s certified Final Bill
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
6.2.3.1 90% (Ninety percent) of the supply value of indigenous material as indicated in the Bill(s) of Materials
against receipt of material at Site and acceptance thereof against CONTRACTOR’s certified Running
Account Bill(s).
6.2.3.2 5% (Five percent) of the supply value of indigenous material as indicated in the Bill(s) of Materials on
issue of Mechanical Completion Certificate against CONTRACTOR’s certified Running Account
Bill(s).
6.2.3.3 2% (Two percent) of the supply value of indigenous material as indicated in the Bill(s) of Materials on
successful Commissioning of the plant / works against CONTRACTOR’s certified Running Account
Bill(s)
6.2.3.4 1% (One percent) of the supply value of indigenous material as indicated in the Bill(s) of Materials on
issue of Commissioning and Performance Test Certificate against CONTRACTOR’s certified
Running Account Bill(s)
6.2.3.5 2% (Two percent) of the supply value of indigenous material as indicated in the Bill(s) of Materials on
completion of all jobs against CONTRACTOR’s Final Bill.
6.2.4 Wherever percentage payment (as per Clause No. 6.2, “ON ACCOUNT PAYMENTS” above) is
applicable against the receipt of Materials/Items (Imported or Indigenous) at Site, payment shall be
made as per the payment terms mentioned above on receipt of Materials/Items within Owner’s
premises and acceptance thereof. However, in case of those Materials/Items (Imported/Indigenous)
which are stored/kept at Contractor’s Stores/Lay-down area/Fabrication Yard which is outside the
Owner’s premises, percentage payment against receipt of such materials/items shall be made to the
Contractor on submission of Bank Guarantee (in the Format to be approved by the Owner and from
a Bank acceptable to Owner) of equivalent amount. This Bank Guarantee shall be over and above
any other Bank Guarantee(s) specified in “ON ACCOUNT PAYMENTS” above. Such Bank
Guarantee(s) shall be released only on receipt of the concerned Materials/Items within Owner’s
premises and acceptance thereof by the Engineer-in-Charge. Also, other stipulations/provisions of
the “ON ACCOUNT PAYMENTS” above shall be fulfilled by the Contractor in this regard. The
maximum outstanding amount at any time under these provisions is limited to 10% of Contract Value.
i) 35% (Thirty Five percent) after completion of 30% 3D Model review, on pro-rata basis on
submission of approved for construction drawings, P&IDs, other deliverable as per approved
DCI and their approval under Code-2 (commented as noted) against the Contractor’s certified
Running Account Bill(s).
“Note: For the purpose of release of above payment towards civil / piling drawings, same shall
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ii) 40% (Forty percent) after completion of 60% 3D Model review, on pro-rata basis on submission
of all approved for construction drawings, P&IDs, Other deliverable as per approved DCI and
their approval under Code 4 (approved with no comments - Final) against the Contractor’s
certified Running Account Bill(s).
v) 05% (Five percent) on submission of As-Built drawings for the Plant / Unit along with its electronic
files against the CONTRACTOR’s certified Running Account Bill(s).
vi) 02% (Two percent) on successful Commissioning of the Plant / works against the
CONTRACTOR’s certified Running Account Bill(s).
vii) 01% (One percent) on issue of Commissioning and Performance Test Certificate against the
CONTRACTOR’s certified Running Account Bill(s).
viii) 02% (Two percent) on completion of all jobs against the CONTRACTOR’s certified Final Bill.
i) 20% (Twenty percent) on completion of Piling works on pro-rata basis as per the approved
Schedule of Activities against the CONTRACTOR’s certified Running Account Bill(s).
ii) 70% (Seventy percent) on pro-rata basis against the CONTRACTOR’s certified Running
Account Bill(s) on completion of individual item of work as per approved Schedule of Activities,
provided that in case piling is not involved then payment percentage shall be 90% (Ninety
percent) on pro-rata basis on completion of individual item(s) of Work as per Schedule of
Activities.
iii) 5% (Five percent) on issue of Mechanical Completion Certificate against the CONTRACTOR’s
certified Running Account Bill(s).
iv) 2% (Two percent) on successful Commissioning of the Plant / works against the
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
v) 1% (One percent) on issue of Commissioning and Performance Test Certificate against the
CONTRACTOR’s certified Running Account Bill(s).
vi) 2% (Two percent) on completion of all jobs against the CONTRACTOR’s certified Final Bill
i) 10% (Ten percent) on finalization of quantity, plan and submission of fabrication drawings
against the CONTRACTOR’s certified Running Account Bill(s).
ii) 50% (Fifty percent) against fabrication of materials on pro-rata basis against the
CONTRACTOR’s certified Running Account Bill(s).
iii) 30% (Thirty percent) on erection, alignment, grouting and painting etc. on pro-rata basis
against the CONTRACTOR’s certified Running Account Bill(s).
iv) 5% (Five percent) on issue of Mechanical Completion Certificate against the CONTRACTOR’s
certified Running Account Bill(s).
vi) 1% (One percent) on issue of Commissioning and Performance Test Certificate against the
CONTRACTOR’s certified Running Account Bill(s).
vii) 2% (Two percent) on completion of all jobs against the CONTRACTOR’s certified Final Bill
C.1 PIPING
ii) 40% (Forty percent) on completion of erection and welding including NDT as applicable, on
pro-rata basis against the CONTRACTOR’s certified Running Account Bill(s).
iii) 10% (Ten percent) on completion of hydro-testing, on pro-rata basis against the
CONTRACTOR’s certified Running Account Bill(s)
vi) 1% (One percent) on issue of Commissioning and Performance Test Certificate against the
CONTRACTOR’s certified Running Account Bill(s).
vii) 2% (Two percent) on completion of all jobs against the CONTRACTOR’s certified Final Bill
C.2 INSULATION
i) 90% (Ninety percent) on completion of insulation works, on pro-rata basis against the
CONTRACTOR’s certified Running Account Bill(s).
iii) 2% (Two percent) on successful Commissioning of the Plant / works against the
CONTRACTOR’s certified Running Account Bill(s).
iv) 1% (One percent) on issue of Commissioning and Performance Test Certificate against the
CONTRACTOR’s certified Running Account Bill(s).
v) 2% (Two percent) on completion of all jobs against the CONTRACTOR’s certified Final Bill.
C.3 PAINTING
i) 15% (Fifteen percent) on pro-rata basis on surface preparation & primer application against
the CONTRACTOR’s certified Running Account Bill(s).
ii) 75% (Seventy Five percent) on pro-rata basis on Final Painting against the
CONTRACTOR’s certified Running Account Bill(s).
iv) 2% (Two percent) on successful Commissioning of the Plant / works against the
CONTRACTOR’s certified Running Account Bill(s).
v) 1% (One percent) on issue of Commissioning and Performance Test Certificate against the
CONTRACTOR’s certified Running Account Bill(s).
vi) 2% (Two percent) on completion of all jobs against the CONTRACTOR’s certified Final Bill
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
C.4 EQUIPMENT
i) 50% (Fifty percent) on completion of erection, on pro-rata basis against the CONTRACTOR’s
certified Running Account Bill(s).
ii) 40% (Forty percent) on completion of alignment & grouting, on pro- rata basis against the
CONTRACTOR’s certified Running Account Bill(s).
iv) 2% (Two percent) on successful Commissioning of the Plant / works against the
CONTRACTOR’s certified Running Account Bill(s).
v) 1% (One percent) on issue of Commissioning and Performance Test Certificate against the
CONTRACTOR’s certified Running Account Bill(s).
vi) 2% (Two percent) on completion of all jobs against the CONTRACTOR’s certified Final Bill.
C.5 TANKS
i) 45% (Forty Five percent) on completion of pre-fabrication and erection on pro-rata basis
against the CONTRACTOR’s certified Running Account Bill(s).
ii) 40% (Forty percent) on completion of welding, NDT, grouting etc. on pro-rata basis against
the CONTRACTOR’s certified Running Account Bill(s).
iii) 5% (Five percent) on completion of hydrostatic testing against the CONTRACTOR’s certified
Running Account Bill(s).
vi) 1% (One percent) on issue of Commissioning and Performance Test Certificate against the
CONTRACTOR’s certified Running Account Bill(s).
vii) 2% (Two percent) on completion of all jobs against the CONTRACTOR’s certified Final Bill.
i) 50% (Fifty percent) on erection / installation etc. on pro-rata basis against the
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ii) 40% (Forty percent) on testing loops and system on pro-rata basis against the
CONTRACTOR’s certified Running Account Bill(s).
iv) 2% (Two percent) on successful Commissioning of the Plant / Works against the
CONTRACTOR’s certified Running Account Bill(s).
v) 1% (One percent) on issue of Commissioning and Performance Test Certificate against the
CONTRACTOR’s certified Running Account Bill(s).
vi) 2% (Two percent) on completion of all jobs against the CONTRACTOR’s certified Final Bill.
Note: For the purpose of payment of second milestone of 40%, “testing loops and system” shall
mean “continuity & erection protocol” in respect of electrical cables, earthing strips and cable trays.
(E) INSTRUMENTATION
i) 50% (Fifty percent) on erection / installation etc. on pro-rata basis against the
CONTRACTOR’s certified Running Account Bill(s).
ii) 40% (Forty percent) on testing loops and system on pro-rata basis against the
CONTRACTOR’s certified Running Account Bill(s).
iv) 2% (Two percent) on successful Commissioning of the Plant / Works against the
CONTRACTOR’s certified Running Account Bill(s).
v) 1% (One percent) on issue of Commissioning and Performance Test Certificate against the
CONTRACTOR’s certified Running Account Bill(s).
vi) 2% (Two percent) on completion of all jobs against the CONTRACTOR’s certified Final Bill.
Note: For the purpose of payment of second milestone of 40%, “testing loops and system” shall
mean “continuity & erection protocol” in respect of Field Instruments.
(F) COMMISSIONING
(I) All payments other than the Mobilization Advance shall be released only after submission of
preliminary planning and monitoring documents and Progress Schedule
Notwithstanding contained in GCC, the provision of Insurance is modified to the following extent:
7.1 OWNER is in the process of taking the Marine cum Erection Insurance of the project for permanent
materials and services. Any loss or damage to the materials or any of them during ocean transportation,
Air transportation, port/ custom clearance, during inland and port handling, inland transportation, storage,
erection, final test and commissioning, shall be to the account of CONTRACTOR, and the CONTRACTOR
shall be exclusively responsible within the scope of supplies in respect of materials and within the scope of
services in respect of works to make good any damage or loss to the materials and works by way of repairs
and/or replacement, as the case may be, pending insurance claim, and no delay shall be made by the
CONTRACTOR in repair/replacement pending such claim. OWNER shall raise the insurance claim in case
of damage to the materials and/or works, and all supporting documents for such claims shall be handed
over by the CONTRACTOR to the OWNER immediately. CONTRACTOR shall provide all assistance for
such a claim.
7.2 Insurance Policy covers IOCL as Principal owner/beneficiary and its contractors, sub-contractors as Co-
insured.
7.3 The CONTRACTOR shall bear the entire cost of arranging all documents/ information, facilitating
inspection/ discussions by the officials/surveyors deputed by the Insurer. The CONTRACTOR shall make
all efforts to get settlement of claim at the earliest, and no time extension for completion of work will be
given for delay on this account.
7.4 The cost of Excess (deductible) and depreciation (if any) will be borne by the CONTRACTOR are as follows:
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
5% of claim
Other Perils – Normal Rs. 45
amount subject to Rs.10 Lakhs Rs. 20 Lakhs Rs. 100 Lakhs
Period/ Catalysts Lakhs
minimum of
Rs. 150
Terrorism Cover Rs.50 Lakhs Rs. 75 Lakhs Rs. 500 Lakhs
Lakhs
• The Excess shall be applicable per event per insured.
• The Excess for Fire and Explosion shall be same as for Normal / Testing Period.
• Excess clause shall be applicable for the respective LSTK / Conventional Contract (s) based on
Original Award / Contract Value (excluding taxes and duties)
7.5 CONTRACTOR shall be solely liable to adhere to the requirements of the insurer for settlement of claims
without prejudice to the rights of OWNER/Insurer. During claim, following steps which are not exhaustive
are required to be taken care by CONTRACTOR:
• Timely information of occurrence of risk event i.e. within 24 hours, for conducting survey.
• Protecting the rights of insurer while issuing acknowledgements
• Lodging of monetary claims in time and furnishing of requisite documents to surveyors/ Insurer.
• Taking necessary precautions so that the loss/damage is not aggravated further.
• Damaged goods to be protected fully.
• Clear the site by dismantling & removing the damaged material to designated location after
verification & survey by Insurer.
Any money received by the OWNER under any policy or policies of insurance shall be held by the
OWNER for proportionate payment to the CONTRACTOR in respect of any appropriate repairs
undertaken and/or replacement(s) made by the CONTRACTOR. Should the CONTRACTOR fail to
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
undertake in whole or in part such repairs and/or replacement(s) and other works necessary
consequent upon the occurrence of any contingency covered by such insurance, OWNER shall be
entitled to get the work done in whole or in part for such repair/replacement through any other agency
(ies), without prejudice to any other rights or remedies available to the OWNER, at the sole risk & cost
of the CONTRACTOR.
7.6 Separate insurance policy to the extent of deductibles on account of excess may be arranged by Contractor at
his own cost.
7.7 CONTRACTOR shall at his own cost and expense cover all insurance required under the prevailing statutes for
his personnel and his sub-contractors. This shall include but not be limited to individual personal accident
insurance / coverage under Workmen Compensation Act etc.
7.8 CONTRACTOR shall at his own cost and expense also obtain suitable insurance policies to cover all third-party
liabilities, vehicles, and all his tools, tackles, construction equipment etc.
7.9 CONTRACTOR shall ensure compliance to all other indemnity and insurance as stipulated in the General
Conditions of Contract (GCC).
8. PRICE VARIATION
The price variation shall be applicable on basic supply price of bulk steel material for site
fabrication/construction for permanent incorporation in work e.g. Structural steel, Reinforcement
bars, Steel Gratings, CS Plates only. The Contract Price shall be adjusted for any increase/decrease on
account of variation in steel prices as per the formula below:
Vm = IR x Q x (M – Mo)
Mo
Where
Vm = Variation in Price
IR = Basic Rate of steel item INR 58,704.40 /- For Structural Steel
INR 55,462.10 /- For Reinforcement bars.
INR 55,993.44 /- For CS Plates
INR 53,099.31 /- For Grating
The above rates are on the date of submission of last priced bid.
Q = Qty. of Structural Steel, Reinforcement bar and Steel Grating / Chequered Plate/ CS Plates
supplied by CONTRACTOR.
Mo = All India Wholesale Monthly Price Index for Steel Commodity relevant for items mentioned
below released by Office of Economic Advisor to Govt. of India, Ministry of Commerce and
Industry (http://www.eaindustry.nic.in) on due date of submission of last price bid.
M = All India Wholesale Monthly Price Index for Steel Commodity relevant for items mentioned
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
below released by Office of Economic Advisor to Govt. of India, Ministry of Commerce and
Industry (http://www.eaindustry.nic.in) one month prior to the month in which the Steel
materials are received at designated site or tax invoice date, whichever is earlier.
a) Structural Steel: All India Wholesale Monthly Price Index for Steel- LONG
b) Reinforcement: All India Wholesale Monthly Price Index for Steel- LONG
c) CS Plates : All India Wholesale Monthly Price Index for Steel - FLAT
d) Grating: All India Wholesale Monthly Price Index for Steel-FLAT
The Escalation towards materials shall be granted provided the Contractor brings the material to site within
90% of Contractual completion or extended completion period, if extended due to reasons not attributable
to the Contractor. For the materials, which are brought at site beyond the above time period, price variation
clause shall not be applicable. Price variation shall not be applicable in items other than mentioned above.
In case of de-escalation of All India Wholesale Monthly Price Index for Steel item/ items, the Contractor has
to submit the relevant details for calculation of decrease in Contract price and in case of failure from the
Contractors side in this regards, variation amount as workout by the EIC/OWNER shall be withheld from
the running account bills till submissions relevant details for final adjustment in Lump sum price, if any.
9.1.1 Clause 3.3.0.0 & 3.4.0.0 of the General Conditions of Contract and its sub-clauses shall be modified as
follows.
Subject to availability, construction power shall be provided by the OWNER from the nearest Substation
/ tapping point on chargeable basis. The cost of power supply shall be recovered by the OWNER from
CONTRACTOR‟S running account/ final bill as per the table given hereunder on Lump sum basis based
on the category of Load demand depending on their connected load. The connected load in different
categories.
In the event of power requirement (and or availability of power) is for less than one-month pro-rata cost
will be arrived on the basis of above rates.
9.1.2 At the time of applying for construction power the CONTRACTOR shall furnish the name plate rating of
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
each equipment for which power is required, to arrive at the category of feeder allocation as stated above.
9.1.3 Contracts which do not require load demand to owner, no charges for construction power shall be levied.
9.1.4 The construction power shall be made available to the CONTRACTOR which might have grid
disturbance, and no time extension or compensation shall be payable on this account. Therefore, the
CONTRACTOR shall within the price of services make alternate arrangement to cope with such
eventuality. Additional power, if required, to meet the contractual requirements, shall be arranged by the
CONTRACTOR at its own cost.
9.1.5 The CONTRACTOR shall make his own arrangements for laying of cable and making necessary
distributions, terminations, feeder pillars, junction boxes etc. All necessary safety precautions as per the
normal safety practices and as directed by the Engineer-in-charge shall be followed by the
CONTRACTOR.
9.1.6 Construction Power shall not be supplied outside the battery limit of the Project by the OWNER.
Clause 3.4.00 & 3.6.0.0 of the General conditions of Contract and its sub-clauses shall be modified as
follows.
Subject to availability, Construction water shall be provided by OWNER on chargeable basis. The cost of
water supply shall be recovered by the OWNER from CONTRACTOR‟S running/ final account bill at 0.25%
of construction services quoted in FORM SP-2 in running account bill/ final bill value in all the Contracts
irrespective of nature, type and discipline of the Contract. Except contracts which are not executed inside
OWNERS premises, no charges for construction water shall be levied.
However, in case OWNER is not able to provide construction water due to any reason whatsoever,
CONTRACTOR shall be responsible for making all arrangements for Construction water at his cost. Any
statutory requirements/ documentation etc. to this effect shall be met by the CONTRACTOR.
Non-availability of water due to any reason shall not entitle the CONTRACTOR for any claim against
OWNER on account of cost and time implications.
Wherever Structural/ Piping works are included in the scope, the responsibilities of CONTRACTOR shall
include establishing and maintaining of a proper fabrication workshop with transportation facilities to site
to carryout fabrication of steel structures, piping specials etc., preparing approaches working areas for the
movement/operation of cranes and leveling the areas for assembly / erection to ensure effective
mechanization on the works.
The Land required for setting up all the temporary facilities like Fabrication Yard (including blasting &
painting areas), Batching Plant, Storage Areas, Warehouses, Labour Hutments etc. shall be arranged by
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Contractor at their-own cost outside the Refinery Premises. All the infrastructure arrangements in
connection with these facilities including Water, Power, Security Arrangements etc. shall be in the scope
of Contractor without any extra cost to Owner.
However, land for setting up the Site Office of Contractor shall be provided by the Owner within the
Refinery premises on chargeable basis. The License Fee for the allotted land shall be charged as per the
relevant provisions mentioned in GCC (Refer Clause No. 3.7.0.0)”.
Contracts which does not use land for site offices/fabrication yard and warehouse etc. shall not be liable
to pay the licensee fee to the owner.
The OWNER shall not permit any land at site to be used for residential purposes nor shall the OWNER
otherwise provide or arrange any land for temporary accommodation of the CONTRACTOR‟s personnel
or labour. The CONTRACTOR shall at its own cost and initiative arrange land for residential
accommodation for its staff and workers and the price of services shall be deemed to include the same
Without prejudice to stipulation in General Conditions of Contract, CONTRACTOR should follow following
billing system:
The bills will be prepared by the CONTRACTOR on their PCs as per the standard formats and codification
scheme proposed by OWNER/ CONSULTANT. The CONTRACTOR will arrange for necessary software (if
the Consultant / Owner doesn’t provide any specific software) for data entry to capture the relevant billing
data for subsequent processing.
The CONTRACTOR will submit these data to OWNER/CONSULTANT in an electronic media along with
the hard copy of the bill, necessary enclosures and documents. The CONTRACTOR will also ensure the
correctness and consistency of data so entered with the hard copy of the bill submitted for payment.
OWNER/CONSULTANT will utilize these data for processing and verification of bill of the CONTRACTOR.
All payments to and recoveries from the bill of CONTRACTOR shall be rounded off to the nearest Rupee.
Wherever the amount to be paid/ recovered consists of a fraction of a Rupee (Paise), the amount shall be
rounded off to the next higher rupee if the fraction consists of 50 (fifty) paise or more and if the fraction of a
Rupee is less than 50 (fifty) paise, the same shall be ignored.
per occasion.
• Any reportable physical injury, as per Indian Factory Act 1948, a penalty of 0.5% of the
contract value (maximum of INR 2,00,000) per injury in addition to INR.5,000/per
occasion as in item (a).
(iv) In case of any conflict between the penalties mentioned in the HSE section enclosed with
the Part-A of SCC and this clause, the more stringent clause shall be followed.
a) The LSTK/EPCC Contractor shall be allowed to take back all left over/surplus project materials (both
sourced/bought from India as well as from abroad on which Custom Duty has been paid by the
Contractor as Owner of said materials) from the Project Site which are not required for the Project.
b) The handing over of project left over/surplus materials/scrap materials generated by the LSTK
Contractor, after the completion of the project will be subjected to the following:
i. An inventory shall be made by the LSTK Contractor of all left over/surplus materials including but not
limited to scrap, wastages and unserviceable material supplied and/or remaining at the project site in
possession of the Contractor, upon completion of the contract.
ii. Such surplus material shall be allowed to be taken out only after completion of the commissioning
activities for the project (here "Project" shall mean the project embracing the works and/or unit(s)
forming the subject matter of the Bid and resultant Contract).
iii. Necessary approval from Owner will be taken by the LSTK Contractor for taking out the leftover/
surplus materials from project site after obtaining due recommendation from the Project Management
Consultant /E-I-C, as applicable. However, any leftover/surplus project materials procured under
EPCG License or Project Import Regulations or any other similar schemes or regulations shall
continue to be the property of the Owner and shall not be allowed to be taken out from Project
Site/Locations by the CONTRACTOR whether during or after completion of the Contract.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
iv. On any project surplus/left over materials being handed over to the LSTK Contractor, GST at
applicable rate (at the time of handing over / transfer) will be charged to the LSTK Contractor. Such
invoice value on Project surplus/ left over materials will have a notional value (which will be based on
purchase price of previous PO or as mutually decided by Owner and LSTK Contractor). This value
shall be only for the purpose of tax compliance.
v. Any project left over items, which are no longer required for Project and which has insignificant residual
value, should be suitably disposed of or be destroyed off by the LSTK Contractor, with prior approval
of OWNER.
vi. If the project left over/surplus materials are not removed by the CONTRACTOR from the Project site,
within a period of 2 (Two) Months after due intimation by OWNER/OWNER's representative
to CONTRACTOR to do so, Owner shall be free to dispose these left over/surplus project materials
at its sole discretion without any recourse to the Contractor.
vii. Notwithstanding the same, value realized from disposal of project left over/surplus project materials
not so removed by LSTK Contractor shall be retained by the Owner and LSTK Contractor shall not
raise any claim in any manner whatsoever for the value so realized by OWNER.
Within 60 DAYS of award of the job, the LSTK Contractor shall propose and submit the desired
quantity(ies) of Project Materials (both sourced/bought from India as well as from abroad on which
Custom Duty has been paid by the Contractor as Owner of said materials) to be brought to the Site,
to the E-I-C, for approval. The Contractor shall propose such quantities keeping in mind that dumping
of bulk materials at Site is avoided and at the same time the job progress is not hampered for lack of
availability of Materials. Contractor can make subsequent changes/modifications in these finalized
quantity (ies) with the specific approval of Owner/Engineer-in-Charge.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
ANNEXURE A-I
CONTENTS
1.1 Necessary indents shall be raised by the Contractor as per procedure laid down by the
PMC/OWNER, when the materials are required for incorporation in permanent works.
1.2 Materials shall be issued only for permanent works and not for temporary works, enabling
works etc. unless specifically approved by PMC/OWNER.
1.3 The Contractor shall bear all other cost including lifting, carting from issue points to work site/
Contractor’s store, custody and handling etc. and return of surplus/serviceable scrap
materials to Owner's storage points to be designated by the PMC/OWNER. No separate
payment for such expenditure shall be made.
1.4 No material shall be allowed to be taken outside the plant without a gate pass.
1.5 The Contractor shall be responsible for proper storage, preservation and watch & ward of
the materials.
2.1 All unused/ scrap materials shall be the property of the Owner and shall be returned in good
and acceptable condition category wise by the Contractor at his own cost to Owner's Store(s)
along with proper materials codes as per OWNER’s SAP system and where ever codes are
not available, Contractor has to give the details in proper formats in order to generate the
new codes. Contractor to ensure that the deposition of all unused/ scrap materials/spares
shall start before six months of Mechanical Completion.
2.2 No credit shall be given to the Contractor for return of scrap. The Contractor should quote
the rates accordingly. Contractor shall make his own arrangements for weighing the cut offs
to be returned to Owner's stores.
2.3 In case the Contractor fails to return unused materials/ accountable scrap, then recovery for
ANNEXURE A-I
CONDITIONS FOR ISSUE AND
RECONCILIATION OF MATERIALS
such quantity of materials, not returned by the Contractor shall be affected at following penal
rates from the Contractor's bills or from any other dues of the Contractor to the Owner:
SR.
MATERIAL PENAL RATES
NO.
Note:
i) Landed Rate shall be arrived from the latest Purchase Order of respective
material received at site by OWNER/PMC.
ii) In case more stringent penal rates have been indicated elsewhere in the Contract
(based on Project requirement), the same shall supersede the above rates.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
ANNEXURE A-II
TIME SCHEDULE
ANNEXURE A-II
TIME SCHEDULE
TIME FOR
NAME OF WORK
COMPLETION
The scope of work shall include validation of basic design, Detailed Design & 16 (Sixteen) Months
Engineering, Procurement, Supply, Transportation up to Site, Storage, Construction, for Mechanical
Erection, Installation, Testing and Commissioning and all other related jobs for Completion (MC) and
successful completion of LUPECH POWER DISTRIBUTION FACILITY for LuPech thereafter 1 month for
project. Contractor shall obtain all applicable statutory approvals including approval Commissioning. The
from Electrical Inspector for subsequent efficient and trouble free operation of the said date of
substation. Complete 220 / 33 KV Substation Package including, 2 x 115/140 MVA Mechanical
ONAN/ONAF, 220 kV / 33 kV Power Transformers, 220kV Cables, new 33 KV GIS Completion will be
in a new Substation building including construction of the new Substation counted from the date
building with associated LT AC & DC System, Interconnection of existing 33 KV of issue of Fax of
System at CGP-1 with the new 33 KV GIS, Substation Control, Protection and Acceptance (FOA).
Automation System, Illumination, Earthing, lightning Protection, AC &
Ventilation and Fire Detection, Alarm & Protection system along with associated
Civil, Structural, Architectural, etc. and successful commissioning of LuPech
Power Distribution facility shall be in the scope of the Package CONTRACTOR.
Bidder shall execute the work on Lump Sum Turn Key Basis (LSTK) with single
point responsibility and the scope includes Project Management, Consistency Checks,
Power System Studies as mentioned in Bidding Documents, Site development and
enabling jobs, Topography Survey, Soil Investigation and underground scanning
mentioned in the bid and co-ordination for the same with Owner/PMC, Total
Procurement (including first fill of consumables, special tools and tackles, Pre-
Commissioning Spares, Commissioning Spares, Start-up spares & Mandatory
spares), Fabrication, Manufacturing, Quality Assurance, Inspection & Expediting, Third
Party Inspection, Supplies, Transportation, Insurance, Handling & Storage of all
Equipment, Materials, items and other Construction Materials at yard/site, Fabrication,
Assembly, Construction, Erection, Installation of all equipment pertaining to LuPech
Power Distribution facility including civil, Structural, HVAC, Piping, Electrical and
Instrumentation including tie-ins, Testing, Insulation and Painting, Obtaining all
Statutory Approvals Pre-commissioning & Mechanical Completion, Preparation of
operating manuals, Training of Owner’s O&M personnel, consumables for 6 (six)
months operation, Contract closure activities ,Final invoice/billing and handing over of
the facilities with Final and “As Built” drawing/documentation, supply of spares with
necessary support and services during defect liability period.
ANNEXURE A-II
TIME SCHEDULE
NOTES:
1. The time of completion shall be reckoned from the date of Notification of award i.e. date of issue of Fax of
Acceptance (FOA)/ Letter of Acceptance (LOA) whichever is issued earlier.
2. The time indicated above is for completing the works in all respects as per Scope of Work, Design, drawings,
specifications and shall also include the time required for testing and rectification etc., if any, as per
specifications and to complete the works to the satisfaction of Engineer-in-Charge.
LIST OF MILESTONES
LuPech Power Distribution Facility Tender Key Milestones
Month from the Effective
S.No Milestone Description
Date of Contract
1 Submission of Electrical Design
2nd Month
Documents
2 Civil & Structural Drawings - Approval 4th Month
3 Transformers & 33kV GIS Ordering 4th Month
4 Ordering completion of all Equipment 6th Month
5 Completion of all civil works including
Substation Building & Equipment 12th Month
foundations
6 Delivery of Power Transformers / 33kV
13th Month
GIS
7 Equipment delivery completion 14th Month
8 Transformers & 33kV GIS Installation
14th Month
Completion
9 Equipment Installation completion 15th Month
10 Mechanical completion 16th Month
11 Commissioning completion 17th Month
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 1 of 3
ANNEXURE A-III
ANNEXURE TO SCC
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 2 of 3
1. Contractor must take due cognizance of the presence of rainy season / days in his scheduled
completion period and accordingly, shall take all necessary actions to protect, reorganize and
progress the work, uninterruptedly during the monsoon period.
2. Contractor to collect all meteorological data from the local authority and collect necessary
information about the intensity, frequency and period of rainy season.
3. No extension of time due to interruption /suspension of work, water logging, reduced /slowing
down of progress, non-availability of manpower etc., whatsoever may be the reason, shall
be tenable on account of monsoon and further no claim for stand-by of manpower and
equipment, other resources etc. shall be paid for.
4. The successful bidder shall be required to submit within 15 days of Letter of Acceptance
of offer / award of work, to the PMC/OWNER his contingency plan for work during
monsoon, clearly stating their methodology / strategy to progress uninterruptedly during
monsoon mentioning the deployment of resources viz, numbers, capacity, category of
equipment and manpower on a weekly basis for approval. The contingency plan shall include
all provisions for constructing and maintaining temporary infrastructure like approach road,
temporary drains in and around work area, dewatering whether natural or forced to keep
the work area free from water logging so as to maintain the same always in a state worthy
of vehicular, human and equipment movement. The work area shall be so isolated as
to restrict run-off from the adjacent areas in the work area / site.
5. Contractor shall put up temporary sheds for fabrication of formwork and reinforcement. For
fabrication of steelwork / piping proper rainproof shed with concretized floor of adequate area
shall be made.
7. The contractor must indicate the structures / areas that he would like to progress (as per the
project schedule and priority) particularly during the monsoon clearly indicating the sub-phases
of construction like foundation / sub structure, superstructure etc.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 3 of 3
8. Contractor shall procure and stock sufficient quantities of materials (if required, outside the
plant premises, the land for which is to be arranged by the contractor at his cost and expenses)
viz. coarse and fine aggregates, bricks etc. adequate for the planned volume of the work during
the monsoon, well in advance of the onset of same so that progress of work is not affected
on this account. PMC/OWNER shall be free to inspect such storing arrangement (particularly
at places outside of the pant areas), at any appropriate time as deemed fit by them.
9. All electrical installations, equipment shall be placed on plinths above ground under proper rain
shed to avoid any inundation, short circuit and hazards of electrocution.
10. Contractor shall organize his work particularly for the underground activities in foundation,
excavation in a way that instead of opening up fronts everywhere and in scattered locations
(provided there is no priority concern) only those many structures and /or areas should be
worked where concerted and continuous effort and resources could be engaged to bring the
work up to the desired level expeditiously to minimize any rework resulting from water
accumulation / rain.
11. To maintain the standard welding quality and progress, localized welding booth in sufficient
numbers as per instruction of PMC shall be installed for protection against wind and rain.
12. Contractors item rates shall be including all costs and expenses including supply of materials
required for monsoon protection like tarpaulins, shed, structural, GI sheet etc. for the above
provisions and no separate payment shall be made on this account.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE A-IV
Specification - Quality
Management System
Document no: 077154C-QMS-PACKAGE-0004 Rev: A Page 2 of 16
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4
SPECIFICATION
QUALITY MANAGEMENT SYSTEM
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Specification - Quality
Management System
Document no: 077154C-QMS-PACKAGE-0004 Rev: A Page 3 of 16
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4
Table of Contents
1. Purpose ............................................................................................................................................ 4
2. References ....................................................................................................................................... 4
3. Definitions &Abbreviations ............................................................................................................ 4
4. Responsibility .................................................................................................................................. 5
5. Quality Management System ........................................................................................................ 5
6. Quality System Requirements ...................................................................................................... 5
7. Audit ................................................................................................................................................ 10
8. Project Quality Plan ......................................................................................................................... 11
9. Training and Awareness .................................................................................................................. 11
10. Management Design Changes ......................................................................................................... 12
11. Feedback / Lesson Learnt ................................................................................................................ 12
12. Preservation and Storage ................................................................................................................ 12
13. Documentation & Records .............................................................................................................. 12
14. Quality Monitoring and Performance Reporting ............................................................................ 13
15. Key Performance Indicators (KPI) for Quality:................................................................................. 14
ANNEXURE-1 .................................................................................................................................... 15
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Specification - Quality
Management System
Document no: 077154C-QMS-PACKAGE-0004 Rev: A Page 4 of 16
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4
1. Purpose
This document describes the Quality Management System Requirement to be met by
CONTRACTOR after award of work or during contract execution. In case of any conflict between
this specification & other provisions of the tender document, the same shall be brought to the
notice of PMC by the CONTRACTOR, which will be resolved prior to the placement of the order.
This document shall be applicable for all works to be carried out by CONTRACTOR (including
Sub-Contractors working for the CONTRACTOR) for achieving overall objective of quality of
various activities during any phase of the project.
2. References
• ISO 9001:2015 requirements
Specification - Quality
Management System
Document no: 077154C-QMS-PACKAGE-0004 Rev: A Page 5 of 16
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4
4. Responsibility
It is CONTRACTOR’S prime responsibility to arrange/produce/manage the products and services
conforming to contract specifications and also inspect all equipment, material and work at
various stages of execution as per approved QAP/ITP. CONTRACTOR shall co-ordinate all
efforts in this regard with the PMC/ OWNER and other involved agencies, giving adequate
desired input that all activities performed are as per approved QAP/ITPs and supporting
documents are readily available. Verification by PMC/OWNER at any stage shall not relieve
CONTRACTOR of his responsibility for the quality of the product.
Specification - Quality
Management System
Document no: 077154C-QMS-PACKAGE-0004 Rev: A Page 6 of 16
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4
Specification - Quality
Management System
Document no: 077154C-QMS-PACKAGE-0004 Rev: A Page 7 of 16
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4
The quality planning shall result into the Quality assurance plan, Inspection and Test
plan(ITP)and job procedures of quality for the project activities in the scope of
CONTRACTOR. These documents shall be submitted to PMC/OWNER for review /
approval. Also, any Record or document requested by PMC/OWNER during the
execution of the project as per agreed review process shall be submitted for review by
PMC/OWNER and CONTRACTOR shall carry out changes based on review.
6.6 Requirements for sub-contracting / purchasing of services specified in contract / tender
shall be adhered to. Wherever requirements are not specified, the CONTRACTOR shall
establish and maintain a robust quality system for purchasing / sub- contracting to
ensure that purchased product / service conforms to specified requirements. Criteria for
selection of sub-contractor, evaluation, re-evaluation, maintenance of purchasing data and
verification of purchased product (sub-Contractor services), constitute important
components of this requirement.
6.7 CONTRACTOR shall adhere to design control exactly as per ISO 9001 and provide
assurance that the design meets the performance standard criteria and has been
undertaken in accordance with the design basis. CONTRACTOR should submit required
records as evidence for review of PMC/ OWNER as and when required and shall carry out
changes based on PMC/ OWNER review.
6.8 CONTRACTOR shall forward to PMC/ OWNER for review the plan for engineering
describing the responsibility for various activities and technical interfaces, necessary
resources required for effective planning.
6.9 CONTRACTOR shall ensure, the sub-contractor to establish their quality plans for the
scope of work in conformance with the CONTACTOR quality plan and review & approval
of the same.
6.10 CONTRACTOR shall ensure, the Supplier and their sub-suppliers to establish and
implement the inspection and verification necessary for ensuring that the suppliers / sub-
suppliers products/works meets specified Purchase Order requirements.
6.11 CONTRACTOR will be totally responsible for furnishing the complete and correct technical
documents / specification to his sub vendor and subcontractor. It is responsibility of the
contractor to ensure that relevant specifications indicated in the tender documents are
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Specification - Quality
Management System
Document no: 077154C-QMS-PACKAGE-0004 Rev: A Page 8 of 16
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4
Specification - Quality
Management System
Document no: 077154C-QMS-PACKAGE-0004 Rev: A Page 9 of 16
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4
Specification - Quality
Management System
Document no: 077154C-QMS-PACKAGE-0004 Rev: A Page 10 of 16
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4
Specification - Quality
Management System
Document no: 077154C-QMS-PACKAGE-0004 Rev: A Page 11 of 16
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4
6.29 All deficiencies noticed and reported by PMC / OWNER shall be analyzed by the
CONTRACTOR and appropriate corrective actions shall be implemented. CONTRACTOR
shall intimate PMC / OWNER of all such corrective action implemented by him.
6.30 CONTRACTOR shall have documented procedure for control of documents and it shall be
submitted for review to PMC / OWNER.
6.31 CONTRACTOR should follow the standards, specification and approved drawings.
Concession/Deviation shall be allowed only in case of unavoidable circumstances. In such
situations, Concession /Deviation request must be made by the CONTACTOR and the
Concession /Deviation request format will be finalized after the award of contract.
6.32 All project records shall be carefully kept, maintained and protected for any damage or loss
until the project completion, then handed over to PMC / OWNER as per contract
requirement, or disposed as per relevant project procedure after informing PMC/OWNER.
7 Audit
The CONTRACTOR shall plan & carry out internal / external QMS audit for the job. The quality
audit program, as per contractual scope such as, Detail Engineering, Procurement, Construction
including vendor and sub-Contractor, Pre- commission & Commissioning shall be prepared
for systematic approach & surveillance of the Quality Management system. The audit program
and report shall be submitted to PMC / OWNER for review.
PMC/ OWNER’s representative will have right to participate, any internal audit conducted during
the execution of the work.
PMC / OWNER may conduct the Quality and technical Audits independently to ensure that the
CONTRACTOR works are in compliance with contract requirements.
CONTRACTOR shall be responsible for implementing Quality Assurance Program and
auditing of his SUBCONTRACTORs and vendors.
PMC / OWNER shall keep regular surveillance on Quality Assurance Program of
CONTRACTOR and his SUBCONTRACTORs and vendors and ensure its implementation.
PMC / OWNER shall conduct quality audit of the CONTRACTOR/ project facility during various
phases of the project at periodic intervals which will be finalized after award of the contract (for
eg.30%,60%,90%)
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Specification - Quality
Management System
Document no: 077154C-QMS-PACKAGE-0004 Rev: A Page 12 of 16
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4
The contractors internal audit and the audit at subcontractors/supplier’s premises shall be:
Specification - Quality
Management System
Document no: 077154C-QMS-PACKAGE-0004 Rev: A Page 13 of 16
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4
Specification - Quality
Management System
Document no: 077154C-QMS-PACKAGE-0004 Rev: A Page 14 of 16
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4
All the necessary documentation & records shall be maintained by CONTRACTOR till
completion of project and handed over to PMC/OWNER in requisite copies as a part of
completion documents. Wherever PMC/OWNER personnel were directly involved particularly in
witness and hold point, the copies of the records shall also be provided to personnel on
completing inspection of those activities.
Records including duly authorized & signed As-built Drawings shall be maintained in Hard & Soft
form by the CONTRACTOR and requirement shall be extended further to his Vendors and
Sub-CONTRACTORs.
Records and Certification shall demonstrate evidence of project activities performed, effective
implementation of the QMS, compliance to project requirements, record of changes, non-
conformities including deviations & waivers, assurance & verification results achieved and
traceability.
All documentation related to Guarantees and Warrantees shall be stored for the period as agreed
with PMC/OWNER and shall be handed over to P M C / OWNER upon successful
commissioning.
CONTRACTOR shall submit following documents related to QMS.
Along with BID;
• ISO 9001:2015 Certificate
• Project Quality Plan (A brief description of the CONTRACTOR’s quality assurance system
and statement detailing how quality assurance will be implemented for the Project)
• List of other relevant quality procedures used to control the Project.
All the records shall be numbered as agreed with the PMC/OWNER after award of contract.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Specification - Quality
Management System
Document no: 077154C-QMS-PACKAGE-0004 Rev: A Page 15 of 16
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4
Specification - Quality
Management System
Document no: 077154C-QMS-PACKAGE-0004 Rev: A Page 16 of 16
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4
ANNEXURE-1
Quality Review
Function Measure Threshold
Indicator Frequency
SPECIFICATION
A 05.30.2021 Issued for Implementation Mohit Sharma Ashish Dwivedi Chintamani Ganapathy P Sayee
Umesh Patel Mohapatra Sankara
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
TABLE OF CONTENTS
Contents
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
HSE GENERAL
1. SCOPE
This document defines the requirements of the OWNER on Health, Safety and Environment (HSE)
associated with the CONTRACTOR and any other agency to be practiced at construction worksites at
all time. This specification establishes the Health, Safety and Environmental (HSE) management
requirement to be complied by Contractors / Vendors including their sub-contractors / sub vendors
during construction for project site.
This specification is not intended to replace the necessary professional judgment needed to design &
implement an effective HSE system for construction activities and the contractor is expected to fulfil
HSE requirements in this specification as minimum. Requirements stipulated in this specification shall
supplement the requirements of HSE Management given in relevant Act(s) / legislations, IOCL -
General Conditions of Contract (GCC), Technip India Limited group guidelines and procedure,
requirements the most stringent shall apply.
2. REFERENCE DOCUMENTS
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
BS : British Standard
PMC : Project Management Consultant
ELCB : Earth Leakage Circuit Breaker
EPC : Engineering, Procurement and Construction
EPCC : Engineering, Procurement, Construction and Commissioning
ESI : Employee State Insurance
GCC : General Conditions of Contract
GM : General Manager
GTAW : Gas Tungsten Arc Welding
HOD : Head of Department
HSE : Health, Safety & Environment
HV : High Voltage
IS : Indian Standard
IE : Indian Electricity
JSA : Job Safety Analysis
LOTO : Lock Out & Tag Out
LPG : Liquefied Petroleum Gas
LSTK : Lump Sum Turn Key
MV : Medium Voltage
PPE : Personal Protective Equipment
RCM : Resident Construction Manager or Site-in-Charge
ROW : Right of Way
SCC : Special Conditions of Contract
SLI : Safe Load Indicator
TBM : Tool Box Talks
• The use of ‘Shall’ indicates a mandatory requirement.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
The CONTRACTOR shall have a documented HSE policy and objectives to cover commitment of
their organization to ensure Health, Safety and Environment aspects in their line operation. Within
4 weeks of the notification of acceptance of the tender, the CONTRACTOR shall submit a detailed
and comprehensive Contract specific HSE Plan. The HSE Plan shall include detailed policies,
procedures and regulations with detailed implementation will ensure compliance of the contract
provisions.
The HSE Plan shall include the following but not be restricted to:
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• A list of HSE hazards anticipated for this Contract and sufficient information to demonstrate
the CONTRACTOR’s proposals for achieving effective and efficient health and safety
procedures;
• A description of the HSE training courses and emergency drills which shall be provided
by the CONTRACTOR, with an outline of the syllabus to be followed.
• Details of the safety equipment which shall be provided by the CONTRACTOR, including
personal protective equipment;
• A statement of the CONTRACTOR ’s procedures for ensuring that CONTRACTOR 's
Equipment used on the Project Site are maintained in a safe condition and are operated in
a safe manner;
4.1.3 Indemnification
Contractor shall indemnify & hold harmless, Owner/PMC & their representatives, free from any and
all liabilities arising out of non-fulfillment of HSE requirements or its consequences.
The Contractor shall designate/deploy various categories of HSE personnel at site as indicated below
in sufficient number. i.e deployment of safety officer/Safety Engineer is compulsory at project site.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
HSE Manager
Should be Technical graduate engineers (Chemical / Mechanical / Electrical / Civil) with 10 years’
experience and above as supervisor in Oil & Gas / Refinery / Petrochemicals or Bulk Chemical
Manufacturing companies or Large Construction sector. He / she must be able to communicate,
write and read English.
And Degree or Diploma in Industrial Safety with one subject of construction safety from a recognized
Institute (Institute recognized by AICTE / State council of technical education for India) or from
RLI/CLI.
HSE Officer
Should be a Science Graduate (Chemistry / Physics / Mathematics) with 5 years’ experience and
above as supervisor in Oil & Gas / Refinery / Petrochemicals or Bulk Chemical Manufacturing
companies or Large Construction sector. He / she must be able to communicate, write and read
English.
And Degree or Diploma in Industrial Safety with one subject of construction safety from a recognized
Institute (Institute recognized by AICTE / State council of technical education for India) or from
RLI/CLLI.
HSE Engineer
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
And Degree or Diploma in Industrial Safety with one subject of construction safety from a recognized
Institute (Institute recognized by AICTE for India). He / she must possess site safety leadership
attributes.
The Contractor shall be fully responsible for planning, reporting, implementing and monitoring of
HSE requirements and compliance of laws & statutory requirements. The Contractor shall also
ensure that the HSE requirements are clearly understood & implemented conscientiously by their
site personnel at all levels at site. The Contractor shall ensure physical presence of their field
engineers / supervisors, during the continuation of their contract works / site activities including all
material transportation activities.
Physical absence of experienced field engineers / supervisors of Contractor at critical work spot
during the course of work, may invite severe penalization as per the discretion of EIC, including
halting / stoppage of work. Contractor shall furnish their annual Inspection Plan, in line with project
issues /subjects, frequency and performers to Owner/PMC.
The Contractor shall regularly review inspection report internally and implement all practical steps /
actions for improving the status continuously. The Contractor shall ensure important safety checks
right from beginning of works at every work site locations and to this effect “Daily Safety Check List”
shall be prepared by field engineer & duly checked by safety personnel for conformance.
Adequate records for all inspections shall be maintained by the Contractor and the same shall be
furnished to Owner/PMC, whenever sought. The Contractor shall not carry-out work by engaging
single worker anywhere without any supervisor anytime during day or night.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
engineers) and a report shall be furnished to Owner/PMC ”Safety walk through report as attached”
followed by compliance for unsatisfactory remarks.
As a general practice lifting tools/tackles, machinery, accessories etc. shall be inspected, tested and
examined by competent people (approved by concerned State authorities) before being used at site
and also at periodical interval (e.g. during replacement, extension, modification,
elongation/reduction of machine/parts, etc.) as per relevant statutes.
Hydra, cranes, lifting machinery, mobile equipment / machinery / vehicles(as attached), etc. shall
be inspected regularly by only competent / experienced personnel at site and requisite records for
such inspections shall be maintained by every contractor.
Contractor shall also maintain records of maintenance of all other site machinery (e.g. generators,
rectifiers, compressors, cutters, etc.) & portable tools / equipment being used at project related
works (e.g. drills, abrasive wheels, punches, chisels, spanners, etc.). The Contractor shall not make
use of arbitrarily fabricated ‘derricks’ at project site for lifting / lowering of construction materials.
All sites facilities and working condition should be periodically inspected by Contractor and records
are to be maintained.
The contractor shall develop a system to implement Behaviour-Based Safety (BBS) through which
work groups can identify, measure and change the behaviours of employees and workers.
The BBS process shall include the following:
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Contractor through its own HSE committee shall implement the above process. The necessary
procedures and reporting formats shall be developed by the contractor for approval by Owner/PMC.
Contractor shall observe individual’s behaviour for safe practices adapted for utilization/execution of
work for the following as a minimum:-
❖ PPE
❖ Tools & equipment
❖ Hazard Identification & control
❖ House keeping
❖ Confined space entry
❖ Hot works
❖ Excavation
❖ Loading & unloading
❖ Work At height
❖ Stacking & storage
❖ Ergonomics
❖ Procedures
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
The contractor shall measure an activity in both leading & trailing indicators for statistical and
performance measurement. The activities pertaining to key performance indicators are covered in
Monthly HSE Report. The contractor shall try to achieve a statistically fair record and strive for its
continual improvement.
❖ Number of Safety Inductions carried-out at site (for workmen & staff members)
❖ Number of HSE inspections carried out
❖ Number of “Safety Walk Through” carried-out by site-head.
❖ Number of HSE shortfalls / lapses identified per contractor & closed-out in time.
❖ Number of Safety Meetings conducted (in-house / with contractors)
❖ Number of HSE Audits made (Internal & External) vis-à-vis non Conformance
❖ raised
❖ Number of HSE Awareness / Motivational program conducted by contractors
❖ Number of HSE Trainings conducted at site for supervisors & workmen
❖ Study of Near miss case reported
❖ Encouragements / Awards / Recognitions to workmen, job supervisors & field engineers.
❖ Suggestions for improvement
❖ Calculation of HSE statistics viz frequency rate, severity rate, LTA free Manhours
❖ Analysis of incidents / accidents (nature, severity, types etc.)
❖ Study of Incident / Accident with respect to :- Variety , Period of the year / project span
❖ Timings of the incident / accident
❖ Age profile of victims and Body parts involved
❖ Penalty levied for causing incident / accident
4.1.9 Documentation
The Contractor shall evolve a comprehensive, planned and documented system covering the
following as a minimum for implementation and monitoring of the HSE requirements and the same
shall be submitted for approval by owner/PMC.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
❖ HSE Organogram
❖ Site specific HSE Plan
❖ Safety Procedures, forms and Checklist. Indicative list of HSE procedures
❖ Risk Assessment & Job Safety Analysis for critical works as format attached.
The monitoring for implementation shall be done by regular inspections and compliance of the
observations thereof. The Contractor shall get similar HSE requirements implemented at his sub-
contractor(s) work site/office. However, compliance of HSE requirements shall be the responsibility
of the Contractor. Any review/approval by Owner/PMC shall not absolve contractor of his
responsibility/liability in relation to fulfilling all HSE requirements.
The CONTRACTOR shall submit an Audit plan to CONSULTANT indicating the type of audits. Project
Manager / RCM holds the ultimate responsibility in ensuring implementation of HSE audit program
during the construction work.
The CONTRACTOR shall conduct an internal HSE audit on quarterly basis and submit a report to
CONSULTANT. Internal HSE audits are to be conducted by Qualified HSE Internal Auditors with the
prior approval of the CONSULTANT.
External HSE audits are to be conducted by external agencies that are competent with ISO qualified
auditors with the prior approval of the CONSULTANT.
Audit shall be conducted as per the guidelines of ISO, ILO, OISD. External HSE audit shall be
conducted requirement basis throughout the period of the contract. The coverage of the external
audit shall include the following items but not limited to:
i) HSE Management :
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
❖ Organization
❖ Communication and Motivation
❖ Inspection
❖ Emergency preparedness
❖ Education and Training
❖ Work permit system First-aid and Medical Facilities
❖ Welfare measures
❖ Environmental Management
ii) Technical:
❖ Building and Structure
❖ Construction operational safety
❖ Material safety
❖ Hand tools and Power tools
❖ Electrical system
❖ Safety Appliances
❖ Fire prevention and control
❖ Housekeeping & Maintenance and Machinery safety
❖ Scaffolding etc.
CONTRACTOR shall make the listed documents available for the review at the time.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
All audit findings as detailed in the audit checklists shall be grouped together as priority 1 and 2 as
detailed below in a separate listing.
Priority 1: Actions to rectify gaps or weakness should generally be implemented within one-week
time, if risk potential is high or unacceptable.
Priority 2: Actions should be generally implemented or rectified with a maximum of 4 weeks, if not
rectified would create a likelihood of minor injury or business loss.
The CONTRACTOR shall submit the Compliance report within 15 days of conducting initial audit for
priority1 observations and within 04 weeks for priority observations to CONSULTANT. In case of
non-conformity of items mentioned by auditor, the CONSULTANT shall take necessary steps
including stoppage of work and or imposing any penalty for getting the item implemented. Failure of
CONTRACTOR to conduct External / Internal HSE Audit. If the CONTRACTOR fails to conduct the
external/ Internal HSE audit in time, the CONSULTANT at the cost of CONTRACTOR shall get it
done.
4.1.11 Meetings
The Contractor shall ensure participation of his top most executive at site (viz. Resident Construction
Manager / Resident Engineer / Project Manager / Site-in-Charge) in Safety Committee / HSE
Committee meetings arranged by Owner/PMC usually on monthly basis or as and when called for.
In case Contractor’s top most executive at site is not in a position to attend such meeting, he shall
inform Owner/PMC in writing before the commencement of such meeting indicating reasons of his
absence and nominate his representative – failure to do so may invite very stringent penalization
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
against the specific Contractor, as deemed fit in Contract. The obligation of compliance of any
observations during the meeting shall be always time bound. The Contractor shall always assist
Owner/PMC to achieve the targets set by them on HSE management during the project
implementation.
In addition, the Contractor shall also arrange internal HSE meetings chaired by his top most
executive at site on weekly basis and maintain records. Such internal HSE meetings shall essentially
be attended by field engineers / supervisors (& not by safety personnel only) of the Contractor and
its associates. Records of such internal HSE meetings shall be maintained by the Contractor for
review by Owner/PMC or for any HSE Audits.
5.1 General
The contractor shall identify all operations that can adversely affect the health of its workers and
issue & implement mitigation measures. CONTRACTOR shall establish a format for Pre-
employment medical examination for their employees and Subcontract workers in compliance with
BOCW Act / Factories Act.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
A list of the available hospitals including locations and their phone numbers shall be displayed at
site offices including CONTRACTORS’
Pre-employment medical fitness criteria for the persons assigned to HSE sensitive job like confined
space, radiation, crane and fork lift operators, vehicle drivers; and exposure to hazardous chemicals
and noise should include specific medical tests / examination related to the these activities.
To eliminate radiation hazard, Tungsten electrodes used for Gas Tungsten Arc Welding shall not
contain Thorium. Appropriate respiratory protective devices(hood with respiratory devices) shall be
used to protect workmen from inhalation of air borne contaminants like silica, asbestos, gases,
fumes.
Contractor workers carrying slag blasting operation shall use slag blasting hood with vortex cooling
system, airline supply and face shields, with respiratory protection. Workmen shall be made aware
of correct methods for lifting, carrying, pushing & pulling of heavy loads. Wherever possible, manual
handling shall be replaced by mechanical lifting equipment. For jobs like
drilling/demolishing/dismantling where noise pollution exceeds the specified limit of 85 decibels, ear
muffs shall be provided to the workers.
To avoid Work Related Upper Limb Disorders (WRULD) and backaches, Display Screen Equipment
workplace stations shall be carefully designed & used with proper sitting postures. Power driven
hand-held tools shall be maintained in good working condition to minimize their vibrating effects and
personnel using these tools shall be taught how to operate them safely & how to maintain good
blood circulation in hands.
The CONTRACTOR shall ensure at a construction site an occupational health centre, mobile or
static is provided and maintained in good order.
5.4 Ambulance
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
The CONTRACTOR shall be provided an ambulance at construction site for transportation of serious
cases of Incident or sickness of workers to hospital promptly and such ambulance and room are
maintained in good repair and is equipped with standard facilities.
The CONTRACTOR shall provide one latrine seat for every 20 workers up to 100 workers and
thereafter one for every additional 50 workers. In addition one urinal accommodation shall be
provided for every 100 workers.
When women are employed, Separate latrine and urinals accommodation shall be provided on the
same scale and maintained and shall comply with the requirements of public health authorities.
CONTRACTOR shall provide Adequate rest shelter cum lunch room for the workers. The rest shelter
shall be well illuminated and ventilated by providing sufficient lights, fans & windows. The rest
shelters shall have sufficient numbers of tables and chairs and drinking water facility etc.
5.7 Canteen
In every workplace wherein not less than 250 workers are ordinarily employed the CONTRACTOR
shall provide an adequate canteen. Reasonable canteen facilities at site and in Labour camps at
appropriate location depending upon site conditions. Contractor shall make use of “industrial” variety
of LPG cylinder & satisfactory illumination at the canteens.
Necessary arrangement for efficient disposal of wastes from canteens & urinals /toilets shall also be
made and regular review shall be made to maintain the ambience satisfactorily hygienic & shall also
comply with all applicable statutory requirements.
The CONTRACTOR shall make in every worksite, effective arrangements to provide sufficient supply
of wholesome drinking water with minimum quantity of 5 liters per workman per day. Quality of the
drinking water shall conform to the requirements of national standards on Public Health (i:e IS10500).
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
While locating these drinking water facilities due care shall be taken so that these are easily accessible
within a distance of 200m from the place of work for all workers at all location of work sites. All such
points shall be legible marked “Drinking Water” in a language understood by a majority of the workmen
employed in such place and such point shall be situated within six meters of any washing places, urinals
or latrines. CONTRACTOR shall submit Drinking water Test Report as per IS : 10500 every quarter to
CONSULTANT / Client
The CONTRACTOR shall provide temporary living accommodation to all workers. These
accommodations shall have cooking place, bathing, washing and lavatory facilities as per local
legislation. Adequately ventilated / illuminated rooms at Labour camps & its hygienic up-keeping.
Contractor shall, at the minimum, ensure the following facilities at work sites:
A crèche at site where 10 or more female workers are having children below the age of 6 years.
Adequately ventilated / illuminated rooms at labour camps & its hygienic up-keeping. Reasonable
canteen facilities at site and in labour camps at appropriate location depending upon site conditions.
Contractor shall make use of “industrial” variety of LPG cylinder & satisfactory illumination at the
canteens. Necessary arrangement for efficient disposal of wastes from canteens & urinals /toilets shall
also be made and regular review shall be made to maintain the ambience satisfactorily hygienic & shall
also comply with all applicable statutory requirements. Adequately lighted & ventilated Rest rooms at
site (separate for male workers and female workers). Urinals, Toilets, drinking water, washing facilities,
adequate lighting at site and labour camps, commensurate with applicable Laws / Legislation.
5.11 First-Aid
The Contractor shall arrange suitable First-aid measures such as First Aid Box, trained
personnel/nurse (male) to administer First Aid, stand-by Ambulance vehicle and The Contractor
shall arrange installation of fire protection measures such as adequate number of steel buckets with
sand & water and adequate number of appropriate portable fire extinguishers to the satisfaction of
Owner/PMC. The Contractor shall deploy trained supervisory personnel / field engineers to cater to
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
any emergency situation. Spraying chemicals / repellent at site shall be made available to prevent
Snakes. Anti-venom shall be kept in First Aid box.
Contractor medical department shall have an ongoing first-aid training program for their staff.
Subcontractors are responsible for ensuring first-aid training for their staff. Training shall be
structured and based on international standard. At least 1 person out of 50 will follow the first-aid
basic training course. All safety staff shall be trained. All the first-Aiders will be identified by a sticker.
The CONTRACTOR shall ensure at a construction site one First-aid box for 100 workers provided and
maintained for providing First-aid to the workers. Every First-aid box is distinctly marked “First-aid” and
is well equipped.
CONTRACTOR will ensure for availability of adequate number of qualified first aider available at site.
Number of first aiders will depend on type and size of work. Minimum one first aider should be available
in a group of workers engaged in a specific task. For this, the CONTRACTOR will ensure that a
suitable number of personnel receive formal first aid training from a recognized agency. Before
deploying the workforce this should happen and refresher training of the same also need to be taken
care.
CONTRACTOR shall take measures to prevent mosquito breeding at site. The measures to be taken
shall include:
i) Empty cans, oil drums, packing and other receptacles, which may retain water shall be deposited
at a central collection point and shall be removed from the site regularly.
ii) Still waters shall be treated at least once every week with oil in order to prevent mosquito
breeding.
iii) CONTRACTOR’S equipment and other items on the site, which may retain water, shall be stored,
covered or treated in such a manner that water could not be retained.
iv) Posters in both Hindi and English or local Languages, which draw attention to the dangers of
permitting mosquito breeding, shall be displayed prominently on the site.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
v) The CONTRACTOR at periodic interval shall arrange to prevent mosquito breeding by fumigation
/ spraying of insecticides. Most effective insecticides shall include SOLFAC WP 10 or Baytex,
The Ideal Larvicide etc.
vi) . Spraying of chemicals shall be done to keep away mosquitoes and to kill its larvae. Ensure
availability of proper medical care for the infected victim. Medical Awareness shall be created
among site personnel regarding Malaria.
5.13 Noise
The CONTRACTOR shall consider noise as an environmental constraint in his design, planning and
execution of the Works and provide demonstrable evidence of the same. The CONTRACTOR shall,
take all appropriate measures to ensure that work carried out by the CONTRACTOR and by his
Subcontractor, whether on or off the Site, will not cause any unnecessary or excessive noise which
may disturb the occupants of any nearby dwellings, premises with similar sensitivity to noise.
The CONTRACTOR shall ensure that all powered mechanical equipment used in the Works shall be
effectively sound reduced using the most modern techniques available including but not limited to
silencers and mufflers. Noise level shall be as prescribed by standards. The CONTRACTOR shall
construct acoustic screens or enclosures around any parts of the Works from which excessive noise
may be generated. The same may be varied from time to time by and at the sole discretion of the
CONSULTANT, In the event of a breach of this requirement, the CONTRACTOR shall immediately re-
deploy or adjust the relevant equipment or take other appropriate measures to reduce the noise levels
and thereafter maintain them at levels which do not exceed the said limits. Such measures may include
without limitation the temporary or permanent cessation of use of certain items of equipment.
Construction material should be operated and transported in such a manner as not to create
unnecessary noise as outlined below:
Perform Work within the procedures outlined herein and comply with applicable codes, regulations,
and standards established by the Central and State Government and their agencies.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Keep noise to the lowest reasonably practicable level. Appropriate measures will be taken to ensure
that construction works will not cause any unnecessary or excessive noise, which may disturb the
occupants of any nearby dwellings, premises with similar sensitivity to noise.
Use equipment with effective noise-suppression devices and employ other noise control measures.
5.14.1 Ventilation
The CONTRACTOR shall ensure at a construction site of a building or other construction work or
confined areas that all working areas are provided with ventilation system as approved by the
CONSULTANT and the fresh air supply in such areas is not less than 6m3/min for each worker
working in such areas and the free air flow movement inside such tunnel is not less than 9m/min.
The oxygen level shall not be less than 19.5% in the working environment.
5.14.2 Illumination
The CONTRACTOR shall take every effort to illuminate the work site. The CONTRACTOR shall
conduct a monthly illumination monitoring by Lux meter for all the locations and the report shall be
sent to the CONSULTANT on periodical basis as planned and the same shall be reviewed during
the monthly HSE committee meeting.
5.15 Radiation
The use of radioactive substances and radiating apparatus shall comply with the Govt. regulatory
requirements and all subsidiary legislation. Operations involving ionizing radiation shall only be
carried out after having been reviewed without objection by the CONULTANT representative and
shall be carried out in accordance with a method statement. Each area containing irradiated
apparatus shall have warning notices and barriers, as required by the Regulations, conspicuously
posted at or near the area. Radioactive substances will be stored, used or disposed shall be strictly
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
in accordance with the Govt. Enactments. The CONTRACTOR shall ensure that all site personnel
and members of the public are not exposed to radiation. Periodical medical check have to be carried
out as stipulated in the HSE Plan.
Awareness about local laws on this issue shall form part of the Induction Training and compulsory
work-site discipline.
The Contractor shall ensure that all personnel working for him comply with “No-Smoking”
requirements of the Owner as notified from time to time. Cigarettes, lighters, auto ignition tools or
appliances as well as intoxicating drugs, dry tobacco powder, etc. shall not be allowed inside the
project / plant complex.
6. SAFETY REQUIREMENTS
Water Sprinkling shall be done to control dust. While storing, soil or other fine particles material shall
be stored in low height of the heap. Cover them with empty gunny bags to prevent dust particle
flying. Vegetation clearing shall be carried out on a needs basis.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
❖ Rooms, Latrines, bathroom, urinals and surrounding area to be maintained in a clean and
sanitary condition cleaning twice per day.
❖ Walls, ceilings, and partitions of every latrine / urinal white washed or colour washed once in
every period of four months.
❖ Smoking is strictly prohibited inside the accommodations, kitchen, recreation rooms, in vicinity
of LPG storage area. Designated smoking areas to be provided with fire extinguishers.
❖ All Electrical panels shall be provided with 30 mA rating ELCB.s. Provide fire extinguishers for
electrical panels.
❖ Pest control to be done periodically. Handling of pesticides is done by trained personnel with
suitable PPE. Pesticides and related chemicals are stored in a dedicated well-ventilated storage
room displaying MSDS.
❖ Sewage Treatment Plant (STP) to be set up with in the camp area for treatment of sewage &
waste water and disposed such that it does not present a hazard to health and environment. Six
monthly environmental monitoring of influent sewage water and effluent sewage water of STP
shall be carried out through MOEF approved agency.
❖ All waste water, sewage, food waste and any other waste material are disposed as per
Environment Protection Act/Rules & respective Waste Management Rules.
❖ Separate first aid facility with male nurse to be provided for camp in case site first aid center is
not within the reach.
❖ Sufficient nos. of First Aid Boxes shall be provided at adequate locations. First aid facility & first
aid boxes shall be inspected monthly by male nurse.
❖ Doctor consultation shall be made available on Every Sunday at Camp.
❖ Adequate and appropriate type of Fire Fighting Equipment to be installed in camp and checked
regularly and maintained to use readily.
❖ Assembly points to be designated. Emergency Telephone Contact numbers to be displayed at
prominent location in camp.
❖ Adequate emergency lights are installed in kitchen and evacuation routes.
❖ Sufficient number of camp occupants to be trained on basic firefighting, fire warden and first aid,
❖ Indoor /outdoor recreational facilities to be provided for camp occupants.
❖ Contractor (s) shall depute camp supervisor and also persons for carrying daily housekeeping,
maintenance work etc.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
❖ Camp office / sitting arrangement for camp Supervisors. Weekly/monthly camp inspection shall
be done by camp supervisor.
❖ Food handlers of camp undergo pre-employment and periodic medical exams for any infectious,
contagious and other communicable diseases
6.3 Security
If security is Contractor (s) scope then contractor (s)’s security control team shall carry out activities
to maintain overall site security. No one shall access the site except through designated access
gates manned and controlled by security guards. Access without a proper gate pass shall be denied
under all circumstances except for emergency.
Contractors (s) & its subcontractor (s) shall obtain the police verification of the all workers/
supervisors and the same is to be submitted to the PMC /Client. All the staff & workers & staff to
have photo IDs.
Contractor (s) shall develop and implement Site Security Plan which shall include minimum
following. This plan shall be reviewed and regularly monitored by Owner / PMC
Contractor (s) shall appoint Security staff through the security agency having statutory license for
security agency (Private Security Agency Regulation Act, 2005 (PSARA) and ensure that they
implement the programs necessary to maintain compliance.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Fire prevention warning signs shall be displayed at the site. The fire prevention signs shall include
the following:
❖ Action to be taken in the “event of a fire” signs shall be displayed in all offices.
❖ Information signs for the use of fire extinguishers to be displayed.
❖ Fire equipment layout signs shall be displayed.
Contractor (s) shall display safety signs, signals and banners and they shall include minimum
following:
❖ Emergency escape route signs at the site and in all offices shall be displayed
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
A scaffold tagging system (color coded) is to be employed at the site. Safety signs shall be
prominently displayed on all scaffolds erected at the site indicating "RED” tag to indicate “Do not
use" and “GREEN” tag to indicate "safe for use".
The Contractor shall ensure that housekeeping is maintained and shall follow
a) All surplus earth and debris are removed/disposed off from the working areas to
designated location(s).
b) Unused/surplus cables, steel items and steel scrap lying scattered at different places within
the working areas are removed to identify location(s).
c) All wooden scrap, empty wooden cable drums and other combustible packing materials, shall
be removed from work place to identified location(s).
d) Roads shall be kept clear and materials like pipes, steel, sand, boulders, concrete, chips and
e) bricks etc. shall not be allowed on the roads to obstruct free movement of men & machineries.
f) Fabricated steel structural, pipes & piping materials shall be stacked properly for erection.
g) Water logging on roads shall not be allowed.
h) No parking of trucks/trolleys, cranes and trailers etc. shall be allowed on roads, which
may obstruct the traffic movement.
i) Utmost care shall be taken to ensure over all cleanliness and proper upkeep of the working
areas.
j) Trucks carrying sand, earth and pulverized materials etc. shall be covered while moving
within the plant area/ or these materials shall be transported with top surface wet.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
k) The contractor shall ensure that the atmosphere in plant area and on roads is free from
particulate
matter like dust, sand, etc. by keeping the top surface wet for ease in breathing.
l) At least two exits for any unit area shall be assured at all times – same arrangement is
preferable for digging pits / trench excavation / elevated work platforms / confined spaces etc.
m) Welding cables and the power cable must be segregated and properly stored and used the
same shall be laid away from the area of movement and shall be free from obstruction.
n) Schedule for upkeep/cleaning of site to be firmed up and implemented on regular basis
The Contractor shall carry-out regular checks (minimum one per fortnight) for maintaining high
standard of housekeeping and maintain records for the same.
The Contractor shall arrange FIRE DRILL at each site at least once in three months, involving site
workmen and site supervisory personnel & engineers. The Contractor shall maintain adequate
record of such fire drills at project site.
The Contractor shall ensure that all their staff, workers and visitors including their sub-contractor(s)
have been issued (records to be kept) & wear appropriate PPEs like nape strap type safety helmets
preferably with head & sweat band with ¾” cotton chin strap (made of industrial HDPE), safety shoes
with steel toe cap and antiskid sole, full body harness (CЄ marked and conforming to EN361),
protective goggles, gloves, ear muffs, respiratory protective devices, etc. All these gadgets shall
conform to applicable IS Specifications /CE or other applicable international standards. The
Contractor shall implement a regular regime of inspecting physical conditions of the PPEs being
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
issued / used by the workmen of their own & also its sub-agencies and the damaged / unserviceable
PPEs shall be replaced forthwith.
For shot blasting, the usage of protective face shield and helmets, gauntlet and protective clothing
is mandatory. Such protective clothing should conform relevant IS Specification.
Contractor shall ensure procurement & usage of following safety equipment/ accessories
(conforming to applicable IS mark / CE standard) by their staff, workmen & visitors including their
subcontractors all through the span of project construction / pre-commissioning/ Commissioning.
a. PPEs (Helmet, Spectacle, Ear-muff, Face shield, Hand gloves, Safety Shoes, Gum boot)
b. Barricading tape / warning signs
c. Rechargeable Safety torch (flame-proof)
d. Safety nets (with tie-chords)
e. Fall arresters
f. Portable ladders (varying lengths)
g. Life-lines (steel wire-rope, dia not less than 8.0 mm)
h. Full body harness (double lanyard)
i. Lanyard
j. Karabiner
k. Retractable fall arresters (various length)
l. Portable fire extinguishers (DCP type) – 5 kg capacity
m. Portable Multi Gas detector
n. Sound level meter
o. Digital Lux meter
p. Fire hoses & flow nozzles
q. Fire blankets / Fire retardant cloth (with eyelets)
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
The Contractor shall issue Permit To Work ( PTW ) at height after verifying and certifying the
checkpoints as specified in the attached permit. He shall also undertake to ensure compliance to
the conditions of the permit during the currency of the permit including adherence of personal
protective equipment. Contractor’s Safety Officer shall verify compliance status of the items of permit
document after implementation of action is completed by Contractor’s execution / field engineers at
work site. Job Safety Analysis (JSA) for specific works at height shall be kept attached with particular
Permit To Work ( PTW )) at site for ready reference & follow-up.
Such PFW shall be initially issued for one single shift or expected duration of normal work and
extended further for balance duration, if required. Owner/PMC can devise block-permit system at
any specific area, in consultation with project specific HSE Committee to specify the time-period of
validity of such PFW or its renewal. Owner/PMC’s field Engineers/Safety Officers/Area Coordinators
may verify and counter sign this permit (as an evidence of verification) during the execution of the
job.
All personnel shall be medically examined & certified by registered doctor, confirming their ‘medical
fitness for working at height. The fitness examination shall be done once in six months.
In case work is undertaken without taking sufficient precautions as given in the permit, Owner/PMC
Engineers may exercise their authority to cancel such permit and stop the work till satisfactory
compliance/rectification is arranged made. Contractors are expected to maintain a register for
issuance of permit and extensions thereof including preserving the used permits for verification
during audits etc.
The Contractor shall arrange and ensure use of Fall Arrester Systems by his workers. Fall arresters
are to be used while climbing/descending tall structures or vessels / columns etc. These arresters
should lock automatically against the anchorage line, restricting free fall of the user. The device is
to be provided with a double security opening system to ensure safe attachment or release of the
user at any point of rope. In order to avoid shock, the system should be capable of keeping the
person in vertical position in case of a fall.
The Contractor shall ensure that Full body harnesses conforming EN361 and having authorized CЄ
marking is used by all personnel while working at height. The lanyards and life lines should have
enough tensile strength to take the load of the worker in case of a fall. One end of the lanyard shall
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
be firmly tied with the harnesses and the other end with life line. The harness should be capable of
keeping the workman vertical in case of a fall, enabling him to rescue himself. The Contractor shall
provide Roof Top Walk Ladders for carrying out activities on sloping roofs in order to reduce the
chances of slippages and falls.
The Contractor shall ensure that a proper Safety Net System is used wherever the hazard of fall
from height is present. The safety net, preferably a knotted one with mesh ropes conforming to IS
5175/ ISO 1140 shall have a border rope & tie cord of minimum 12mm dia. The Safety Net shall be
located not more than 6.0 meters below the working surface extending on either side up to sufficient
margin to arrest fall of persons working at different heights.
In case of accidental fall of person on such Safety Net, the bottom most portion of Safety Net should
not touch any structure, object or ground.
The Contractor shall ensure positive isolation while working at different levels like in the pipe rack
areas. The working platforms with toe boards & hand rails shall be sufficiently strong & shall have
sufficient space to hold the workmen and tools & tackles including the equipment required for
executing the job. Such working platforms shall have mid-rails, to enable people work safely in sitting
posture.
• Suitable scaffoldings will be provided for workmen for all works that cannot safely be done from
the ground. When a ladder is used, extra workmen shall be engaged for holding the ladder and
if the ladder is used for carrying materials as well, suitable foot holds and handholds shall be
provided on the ladder shall be given an inclination not steeper than 1 to 4 (1 horizontal and 4
vertical). Length of ladder shall not be more than 6 meters. The IS 2750 Specification of
scaffolding could be use as guidance. Specifications having better methods shall also be
allowed on approval of IOCL & TIL.
• Only steel scaffolding shall be used.
• Scaffolding or staging more than 12’ above the ground or floor, swing or suspended from an
overhead support or erected with stationary support shall have a guard rail properly attached,
bolted, braced and at least 3’ high above the floor or platform of scaffolding or Staging and
extending along the entire length of the outside and ends thereof with only such openings as
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
may be necessary for the delivery of materials. Such scaffolding or staging shall be so fastened
to prevent it from swaying.
• Working platform, gangways and stairways should be so constructed that they should not sag
unduly or unequally.
• Every opening in the floor of the building or in a working platform be provided with suitable
fencing or railing whose minimum height shall be 03 feet & Kick boards to stop loose materials
and off cuts falling over.
• Safe means of access will be provided to all working platforms and other working places; every
ladder shall be securely fixed. No portable single ladder shall be over 30’ in length while the width
between the steps shall in no case be less than 11.5 inches for ladder up to and including 10’ in
length. For longer ladder this width would be increased to at least 1’4’’.
• Adequate precautions shall be taken to prevent danger from electrical equipment.
• No materials on any of the site works shall be stacked or placed as to cause or inconvenience to
any person or public. All necessary fencing and lights are to provide so as to protect the workers
and staff from accidents.
• No scaffolding shall be erected, dismantled or altered except under the supervision of competent
person.
• Only trained and experienced scaffolders shall be allowed to work on scaffolding with “Do Not Use”
scafftag.
• Before being taken into use and display board “safe to use” shall be provided. Scaffold fit for use
shall be provided with green tags, whereas scaffold under erection not fit for use shall be provided
with RED Tag.
Or International standards :
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
The Contractor shall assign to his workmen, tasks commensurate with their qualification, experience
and state of health. All lifting tools, tackles, equipment, accessories including cranes shall be tested
periodically by statutory/competent authority for their condition and load carrying capacity. Valid test
& fitness certificates from the applicable authority shall be submitted to Owner/PMC for their
review/acceptance before the lifting tools, tackles, equipment, accessories and cranes are used.
The contractor shall not be allowed to use defective equipment or tools not adhering to safety norms.
Contractor shall arrange non-sparking tools for project construction works in operating plant areas /
hydrocarbon prone areas. Wherever required the Contractor shall make use of Elevated Work
Platforms (EWP) or Aerial Work Platforms (mobile or stationary) to avoid ergonomically risks and
workmen shall be debarred to board such elevated platform during the course of their shifting /
transportation.
Contractor shall ensure installation of Safe Load Indicator (SLI) on all cranes (while in use) to
minimize overloading risk. SLI shall have capability to continuously monitor and display the load on
the hook, and automatically compare it with the rated crane capacity at the operating condition of
the crane. The system shall also provide visual and audible warnings at set capacity levels to alert
the operator in case of violations. The contractor shall be responsible for safe operations of different
equipment mobilized and used by him at the workplace like transport vehicles, engines, cranes,
mobile ladders, scaffoldings, work tools, etc. The Contractor shall arrange periodical training for the
operators of hydra, crane, excavator, mobile machinery, etc. at site by utilizing services from
renowned manufacturers.
Hazardous, inflammable and/or toxic materials such as solvent coating, thinners, anti-termite
solutions, water proofing materials shall be stored in appropriate containers preferably with lids
having spillage catchment trays and shall be stored in a good ventilated area. These containers
shall be labeled with the name of the materials highlighting the hazards associated with its use and
necessary precautions to be taken. Respective MSDS (Material Safety Data Sheet) shall be made
available at site & may be referred whenever problem arises.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Where contact or exposure of hazardous materials are likely to exceed the specified limit or
otherwise have harmful effects, appropriate personal protective equipment such as gloves,
goggles/face-shields, aprons, chemical resistant clothing, respirator, etc. shall be used.
The work place shall be checked prior to start of activities to identify the location, type and condition
of any asbestos materials which could be disturbed during the work. In case asbestos material is
detected, usage of appropriate PPEs by all personnel shall be ensured and the matter shall be
reported immediately to PMC/ Owner.
The contractor shall establish a regular cleaning and basic housekeeping programme that covers
all aspects of the workplace to help minimize the risk of slips, trips & falls. The contractor shall take
positive measures like keeping the work area tidy, storing waste in suitable containers & harmful
items separately, keeping passages, stairways, entrances & exits especially emergency ones clear,
cleaning up spillages immediately and replacing damaged carpet/ floor tiles, mats & rugs at once to
avoid slips, trips & falls.
6.13 Barriers
Appropriate barriers must be provided in hazardous situations and during work presenting hazards.
This is to be done in conformity with the table below and each CONTACTOR shall provide enough
barriers for their own activities:
Situation Barrier
Open grated flooring, pit or gutter Uprights and horizontals (hard barricades)
Acid/caustic treatment of equipment Red and white tape combined with pictogram
signs
High pressure bead or grit blasting
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Situation Barrier
High pressure jetting Yellow and black barrier tape combined with
pictogram signs
Work with X-rays
Hoisting operations Special red and white barrier tape with printed
inscription
(Demolition) work involving asbestos-containing Yellow/black barrier tape or chain and warning
products notice
The CONTRACTOR shall develop a Work Permit system, which is a formal written system used to
control certain types of work that are potentially hazardous. A work permit is a document, which
specifies the work to be done, and the precautions to be taken. Work Permits form an essential part
of safe systems of work for many construction activities. They allow work to start only after safe
procedures have been defined and they provide a clear record that all foreseeable hazards have
been considered. Permits to Work are usually required in high-risk areas as identified by the Risk
Assessments. Permit to Work format as attached.
A permit is needed when construction work can only be carried out if normal safeguards are dropped
or when new hazards are introduced by the work. Examples of high-risk activities include but are
not limited to:
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
A Work Permit authorization form shall be completed with the maximum duration period not
exceeding 12 hours. Copy of each Permit to Work shall be displayed, during its validity, in a
conspicuous location in close proximity to the actual works location to which it applies.
The batching plant / casting yard shall be effectively planned for smooth flow of Unloading and
stacking the aggregates reinforcements and cement, batching plant, transport of concrete, casting
the segment, stacking the segment and loading the segments to the trucks. As far as possible the
conflicts should be avoided.
The batching plant / casting yard shall be barricaded and made as a compulsory PPE zone.
If in case of material unloading area is not maintainable as PPE zone, the same shall be segregated
properly and made as a non-PPE zone with appropriate barricading. Electrical system shall also be
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
suitably planned so that location of diesel generator, if any, location of DBs, routing of cables and
positioning of area lighting poles/masts does not infringe on any other utility and pose danger.
Drainage shall be effectively provided and waste water shall be disposed after proper treatment.
Time office, canteen, drinking water, toilet and rest place shall be suitably located for the easy
access to workers. All the facilities shall be properly cleaned and maintained during the entire period
of operation. Manual handling of cement shall be avoided to a larger extent. Whenever it is
absolutely necessary the workmen shall be given full body protection, hand protection and
respiratory protection as a basic measure of ensuring better health.
The PPEs provided to cement handling workmen shall conform to international standards. Access
roads and internal circulation roads shall be well laid and maintained properly at all time. Non-
adherence to any of the above provision shall be penalized as per relevant penalty clause.
The Contractor shall ensure identification of all Occupational Health, Safety & Environmental
hazards in the type of work he is going to undertake and enlist mitigation measures. Contractor shall
carry out Job Safety Analysis (JSA)/Risk Analysis specifically for high risk jobs / critical jobs like
a) Working at height (+2.0 Mts height) for cold incl. color washing, painting, insulation
& hot works.
b) Work in confined space,
c) Deep excavations & trench cutting (depth > 1.2 mts.)
d) Operation & Maintenance of Batching Plant.
e) Shuttering / concreting (in single or multiple pour) for columns, parapets & roofs.
f) Erection & maintenance of Tower Crane.
g) Erection of pipes (full length or fabricated) at height more than 2.0 Mts. height with
Crane of 50T capacity.
h) All lifts using 50T Crane plus mechanical pulling.
i) All lifts using two cranes in unison (Tandem Lifting).
j) Any lift exceeding 75% capacity of the lifting equipment (hydra, crane etc.).
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
The necessary HSE measures devised shall be put in to place, prior to start of an activity & also
shall be maintained during the course of works, by the Contractor. Copies of such JSAs shall be
kept available at work sites by the Contractor to enable all concerned carrying out checks /
verification.
6.17 Accessibility
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
The Contractor shall provide safe means of access(in sufficient numbers) & efficient exit to any
working place including provisions of suitable and sufficient scaffolding at various stages during all
operations of the work for the safety of his workmen and Owner/PMC.
The Contractor shall implement use of all measures including use of “life line”, “fall-arresters”,
“retractable fall arresters” , “safety nets” etc. during the course of using all safe accesses & exits, so
that in no case any individual remains at risk of slip & fall during their travel.
The access to operating plant / project complex shall be strictly regulated. Any person or vehicle
entering such complex shall undergo identification check, as per the procedures in force /
requirement of Owner/PMC.
The Contractor shall ensure adequately planned road transport safety management system. The
vehicles shall be fitted with reverse warning alarms & flashing lights / fog-lights and usage of seat
belts shall be ensured. The Contractor shall also ensure a separate pedestrian route for safety of
the workers and comply with all traffic rules & regulations, including maintaining speed limit of 20
kmph or indicated by owner for all types of vehicles / mobile machinery. The maximum allowable
speed shall be adhered to.
In case of an alert or emergency, the Contractor must arrange clearance of all the routes, roads,
access. The Contractor shall deploy sufficient number of traffic controllers at project site routes /
roads/ accesses, to alert reversing movement of vehicles & machinery as well as pedestrians.
Dumpers, Tippers, etc. shall not be allowed to carry workers within the plant area and also to & from
the labour colony to & from project sites. Hydras shall only be allowed for handling the materials at
fabrication/ storage yards and in no case shall be allowed to transport the materials over project /
plant roads. The Contractor shall not deploy any such mobile machinery / equipment, which do not
have competent operator and / or experienced banks-man / signal-man. Such machinery /
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
equipment shall have effective limit-switches, reverse-alarm, front & rear-end lights etc. and shall be
maintained in good working order.
The Contractor shall not carry-out maintenance of vehicles / mobile machinery occupying space on
project / plant roads and shall always arrange close supervision for such works. For pipeline jobs,
the contractor shall submit a comprehensive plan covering transportation, loading / unloading of
pipes, movement of side booms, movement of vehicles on the ROW, etc. Contractor’s shall arrange
/install visible road signs, diversion boards, caution boards, etc on project roads for safe movement
of men and machinery.
6.19 Communication
All persons deployed at the work site shall have access to effective means of communication so that
any untoward incident can be reported immediately and assistance sought by them. All health &
safety information shall be communicated in a simple & clear language easily understood by the
local workforce. For information to all, typical subjects that should be communicated are: - Inside
the company (Top to down)
a. Complaints
b. Compliances on safety defects / shortfalls
c. Suggestions
d. Proposals for changes & improvements
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Contractor shall take appropriate measures and necessary work permits/clearances if work is to be
done in or around marshy areas, river crossings, mountains, monuments, etc. The Contractor shall
make right assessment and take all necessary action for developing work areas to make them safe
& suitable for crane operations or other vehicular movement before carrying out any project related
activity / operation. Contractor shall take all necessary actions to make the surroundings of its site
establishments (site office, stores, lay-down area etc.) work-worthy safe and secure.
Contractor shall conduct daily TBT with workers prior to start of work and shall maintain proper
record of the meeting. A suggested format is attached. The TBT is to be conducted by the immediate
supervisor of the workers. The Contractor shall conduct TBT before start of every morning or evening
shift or night shift activities, for alerting the workers on specific hazards and their appropriate dos &
don’ts. The Contractor shall provide sufficient rests to the site workmen and their foremen to avert
fatigue & thereby endangering their lives during the course of site works.
Initial induction of workers into Construction oriented activities and appraising them about the
methodology of works and how to carry-out safely and the same should not be inter mixed with Tool
Box Talks or HSE Training. In this regard careful action should be made & maintained for imparting
HSE induction to every individual, irrespective of his task/designation/level of employment, whereas,
HSE Training should be imparted to specific person/group of people who are to carry-out that
specific task more than once – for example, Riggers must be trained for working at heights, welders
must be trained for work in confined space, fitters/carpenters, mesons must be trained for work at
heights, etc
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Contractor shall conduct Safety induction programme on HSE for all his workers and maintain
records. The Gate Pass shall be issued only to those workers who successfully qualify the Safety
induction programme.
The Contractor shall brief the visitors about the HSE precautions which are required to be taken
before their proceeding to site and make necessary arrangements to issue appropriate PPEs like
Aprons, hard hats, ear-plugs, goggles & safety shoes etc., to his visitors. The Contractor shall always
maintain relevant acknowledgement from visitor on providing him brief information on HSE actions.
Contractor shall ensure that all his personnel possess appropriate training to carry out the assigned
job safely. The training should be imparted in a language understood by them and should specifically
be trained about
The Contractor shall make regular program for conducting Safety Training on various topics related
to various activities & their safe-guarding utilizing experienced persons / outside agency / faculty. A
program for Safety Training (indicative list as attached) shall be furnished by the Contractor in its
HSE Plan .
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
For offshore and jetty jobs, contractor shall ensure that all personnel deployed have undergone a
structured sea survival training including use of lifeboats, basket landing, use of radio
communication etc. from an agency acceptable to Owner/PMC
The contractor shall develop a method of check & balance through self-assessment & enhancement
techniques and shall explore the opportunities for continual improvement in the HSE system
The contractor shall encourage his workforce to promote HSE efforts at workplace by way of
organizing workshops/seminars/training Programmes, celebrating HSE awareness weeks &
National Safety Day, conducting quizzes & essay competitions, distributing pamphlets, posters
material on HSE, providing incentives for maintaining good HSE practices and granting incentives /
bonus for completing the job without any lost time accident.
Reporting to CONSULTANT
All Incidents and dangerous occurrences shall immediately be informed verbally to the
CONSULTANT. This will enable the CONSULTANT to reach to the scene of Incident / dangerous
occurrences to monitor assist any rescue work and / or start conducting the investigation process so
that the evidences are not lost. Reports of all Incidents (fatal / injury) and dangerous occurrences
shall also be sent within 24 hours as per format provided in the CONSULTANT (Incident reporting
format as attached). No Incident / dangerous occurrences are exempted from reporting to the
CONSULTANT. Any willful delay in verbal and written reporting to the CONTRACTOR shall be
penalized.
Accident Investigations
Investigations should be conducted in an open and positive atmosphere that encourages the
witnesses to talk freely. The primary objective is to ascertain the facts with a view to prevent future
and possibly more serious occurrences. Incidents and Dangerous Occurrences which result in death,
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
serious injury or serious damage must be investigated by the CONTRACTOR immediately to find out
the cause of the Incident / occurrence so that measures can be formulated to prevent any recurrence.
Near misses and minor Incidents should be investigated in detail by the CONTRACTOR as soon as
possible as they are signals that there are inadequacies in the safety management system.
It is important after any Incident or dangerous occurrence that information relating to the incident is
gathered in an organized way. The following steps shall be followed;
Consider all possible causes and the interaction of different factors that led up to the Incident, and
identify the most probable cause. The cause of an Incident should never be classified as carelessness.
The specific act or omission that caused the Incident must be identified.
All the HIPO (High Potential) Incidents / Near misses are subject to TOPSET investigation by
CONSULTANT. In case of fatal / dangerous occurrence the CONSULTANT shall also conduct
independent investigation. CONTRACTOR and his staff shall extend necessary co-operation and
testify about the Incident. The CONTRACTOR shall take every effort to preserve the scene of Incident
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
till the CONSULTANT completes the investigation. All persons summoned by the CONSULTANT in
connection to witness recording shall obey the instructions without delay. Any willful suppression of
information by any person shall be removed from the site immediately and / or punishable.
The contractor shall generate a work permit before entering a confined space. People, who are
permitted to enter into confined space, must be medically examined & certified by registered doctor,
confirming their ‘medical fitness for working in confined space’. All necessary precautions
mentioned therein shall be adhered to. An attendant shall be positioned outside a confined space
for extending help during an emergency. All appropriate PPEs and air quality parameters shall be
checked before entering a confined space. It shall be ensured that the piping of the equipment
which has to be opened is pressure- free by checking that blinds are in place, vents are open and
volume is drained. Inside confined space works, only electrical facilities / installations of 24V shall
be permitted. Contactor shall ensure usage of safe suitable arrangement of oxygen supply for
individual workmen (during the course of work in confined space), if oxygen concentration is found
to be less than 19.5% (v/v) there.
6.27 Lock Out and Tag Out (LOTO) for isolation of energy source
Contractor shall follow the LOTO/Isolation procedure of owner for all energy source isolations
installed/under purview by /of owner i.e.. “Brown field” . For all the other energy source (not under
purview of client/owner) i.e. “Green field” Contractor shall develop a system to ensure the isolation
of equipment, pipelines, Vessel, electrical panels from the energy source covering following as
minimum:-
❖ Identification of all energy source viz electrical, mechanical, hydraulic, pneumatic, chemical,
thermal, gravitational, radiation and other forms of stored or kinetic energy.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
❖ Establishing the energy isolation devices viz: manually operated electrical circuit breakers,
disconnection switches, blind flanges, etc.
❖ Installation of Lock Out devices for preventing the inadvertent release of stored energy and Tag
Out devices ( “Danger”, “Do Not operate” or Do not Remove” tags) to indicate that testing,
maintenance or servicing is underway and the device cannot be operated until the tag out device
is removed.
❖ Lock Out and Tag out log book
❖ Permit for isolation and de-isolation of energy source
❖ Availability of competent persons like experienced operators at substations, pump house, units,
etc.,
Contractor shall ensure that all the sources are locked out and tagged properly before giving
clearance to start the job. After the completion of job, contractor shall ensure all tools and tackles
are removed and nobody is present in the working area and signing on LOTO log book Only on
confirmation of above the contractor will remove their lock and tag from the isolation points and give
instructions for energizing the same. Only the person carrying out the task shall himself carry the
key for the lock in /Lock out. LOTO tags as attached.
❖ OISD STD 173: Fire prevention & protection system for electrical installations
All electrical installations shall be approved by the concerned statutory authorities. All temporary
electrical installations / facilities shall be regularly checked by the licensed/competent electricians
of the Contractor and appropriate records shall be maintained Inspection of temporary electrical
booth/installation at project construction site”. Such inspection records are to be made available to
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Shall make Single Line Diagram (SLD) for providing connection to each equipment’s &
• machinery and the same (duly approved by Owner/PMC) shall be pasted on the front face
of DBs (distribution boards) or JBs (Junction boxes) at every site.
• Ensure that electrical systems and equipment including tools & tackles used during
construction phase are properly selected, installed, used and maintained as per provisions
of the latest revision of the Indian Electrical/ applicable international regulations.
• Shall deploy qualified & licensed electricians for proper & safe installation and for regular
inspection of construction power distribution system/points including their earthing. A copy
of the license shall be submitted to Owner/PMC for records. Availability of at least one
competent (ITI qualified) / licensed electrician (by State Elec. authorities) shall be ensured
at site round the clock to attend to the normal/emergency jobs.
• All switchboards / welding machines shall be kept in well-ventilated & covered shed/ with
rain shed protection. The shed shall be elevated from the existing ground level to avoid
water logging inside the shed . Installation of electrical switch board must be done taking
care of the prevention of shock and safety of machine.
• No flammable materials shall be used for constructing the shed. Also flammable materials
shall not be stored in and around electrical equipment / switchboard. Adequate clearances
and operational space shall be provided around the equipment.
• Fire extinguishers and insulating mats shall be provided in all power distribution centers.
• Temporary electrical equipment shall not be employed in hazardous area without obtaining
safety permit.
• Proper housekeeping shall be done around the electrical installations.
• All temporary installations shall be tested before energizing, to ensure proper earthing,
bonding, suitability of protection system, adequacy of feeders/cables etc.
• All welders shall use hand gloves irrespective of holder voltage.
• Multilingual (Hindi, English and local language) caution boards, shock treatment charts and
instruction plate containing location of isolation point for incoming supply, name & telephone
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
No. of contact person in emergency shall be provided in substations and near all distribution
boards / local panels.
• Operation of earth leakage device shall be checked regularly by temporarily connecting
series
• test lamp (2 bulbs of equal rating connected in series) between phase and earth. ELCB
tester
• /test meter shall be used for testing ELCBs
• Regular inspection of all installations at least once in a month.
• The following features shall also be ensured for all electrical installations during construction
• phase by the contractor:
• Each installation shall have a main switch with a protective device, installed in an enclosure
• adjacent to the metering point. The operating height of the main switch shall not exceed
• 1.5 M. The main switch shall be connected to the point of supply by means of armored
cable.
• The outgoing feeders shall be double or triple pole switches with fuses / MCBs. Loads in a
• three phase circuit shall be balanced as far as possible and load on neutral should not
exceed
• 20% of load in the phase.
The installation shall be adequately protected against overload, short circuit and earth leakage by
the use of suitable protective devices. Fuses wherever used shall be HRC type. Use of rewireable
fuses shall be strictly prohibited. The earth leakage device shall have an operating current not
exceeding 30 mA. All connections to the hand tools / welding receptacles shall be taken through
proper switches, sockets and plugs.
All single phase sockets shall be minimum 3 pin type only. All unused sockets shall be provided
with socket caps. Only 3 core (P+N+E) overall sheathed flexible cables with minimum conductor
size of 1.5 mm2 copper shall be used for all single phase hand tools.
Only metallic distribution boxes with double earthing shall be used at site. No wooden boxes shall
be used. All power cables shall be terminated with compression type cable glands. Tinned copper
lugs shall be used for multi-strand wires / cables.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Cables shall be free from any insulation damage. Minimum depth of cable trench shall be 750 mm
for MV & control cables and 900 mm for HV cables. These cables shall be laid over a sand layer
and covered with sand, brick & soil for ensuring mechanical protection. Cables shall not be laid in
waterlogged area as far as practicable. Cable route markers shall be provided at every 25 M of
buried trench route. When laid above ground, cables shall be properly cleated or supported on
rigid poles of at least 2.1 M high. Minimum head clearance of 6 meters shall be provided at road
crossings.
Underground road crossings for cables shall be avoided to the extent feasible. In any case no
underground power cable shall be allowed to cross the roads without pipe sleeve. All cable joints
shall be done with proper jointing kit. No taped/ temporary joints shall be used.
An independent earthing facility should preferably be established within the temporary installation
premises. All appliances and equipment shall be adequately earthed. In case of armoured cables,
the armor shall be bonded to the earthing system. All cables and wire rope used for earth
connections shall be terminated through tinned copper lugs.
In case of local earthing, earth electrodes shall be buried near the supply point and earth continuity
wire shall be connected to local earth plate for further distribution to various appliances. All
insulated wires for earth connection shall have insulation of green colour. Separate core shall be
provided for neutral. Earth / Structures shall not be used as a neutral in any case. ON/OFF position
of all switches shall be clearly designated / painted for easy isolation in emergency.
All necessary grounding and/or bonding precautions shall be taken to prevent the generation of
static electricity in areas where this may cause hazard or fire such as, motorized agitation, mixing
splash filling, grit blasting hoses, paint spraying and ventilation fans.
When flammable liquids are transferred from one container to another, bonding between the two
conductive containers, prior to pouring, shall be in place.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Adequate safety measures must govern the use of portable tools particularly:
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
- Only insulated or non-conducting tools should be used on or near live electrical installations.
- Only non-sparking tools shall be used near or in the presence of flammable Liquids / vapors
or
- explosive dusts or vapors.
- Heads of hammers and other sharp tools shall be dressed or ground to a suitable radius on
the
- edge as they begin to mushroom or crack.
- Tools should be switched off when not in use and positively isolated before any adjustment,
- cleaning or maintenance is done.
6.31 Grinding
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Lifting appliances means a crane, hoist machinery, derrick, winch, gin pole, sheer legs, jack, hoist
drum, slewing machinery, slewing bearing fasteners, lofting machinery Sheave’s, pulley blocks,
hooks or other equipment used for lifting materials, objects or building workers and lifting gears
means ropes, chain slings, shackles, hooks, lifting lugs, wire ropes, lifting eyebolts and eye nuts
and other accessories of a lifting appliance..
Use of Hydra is prohibited at site. In place of Hydra, F-15 crane can be used on prior approval by
Site Manager / HSE Manager.
No machine shall be selected to do any lifting on a specific job until its size and Characteristics
are considered against:
i) The weights, dimensions and lift radii of the heaviest and largest loads
ii) The maximum lift height, the maximum lift radius and the weight of the loads that must be handled
at each
iii) the number and frequency of lifts to be made
iv) How long the crane will be required on site
v) the type of lifting to be done (for example, is precision placement of loads important
vi) The type of carrier required (this depends on ground conditions and machine capacity In its
operating quadrants: capacity is normally greatest over the rear, less over the side, and non-
existent over the front
vii) Whether loads will have to be walked or carried
viii) Whether loads will have to be suspended for lengthy periods
ix) The site conditions, including the ground where the machine will be set up, access roads and
ramps it must travel, space for erection and any obstacles that might impede access or operation.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
The CONTRACTOR shall ensure that a valid certificate of fitness issued for all lifting appliances
including synchronized mobile jacks, pre-stressing hydraulic jacks, jacks fitted with launching
girders etc. and CONTRACTORs approval before inducting to the site. Only after obtaining the
approval from the CONSULTANT any lifting appliances and gear shall be used.
The laminated photocopies of fitness certificate issued by competent person, the CONTRACTOR’
approval letter, the operators’ photo, manufacturer’s load chart and Conditions of Contract on
Health, Safety and Environment, competency certificate shall always be either kept in the operator
cabin or pasted on the visible surface of the lifting appliances.
All lifting appliances and loose gears shall be clearly marked for its safe working load and
identification by stamping or other suitable means. The CONTRACTOR shall also maintain a
register containing a system of identification of all tools and tackles, its date of purchase, safe
working load, competent person date of examination etc.
All lifting appliances including all parts and gears thereof, whether fixed or movable shall be
thoroughly tested and examined by a competent person once at least in every six months or after
it has undergone any alterations or repairs liable to affect its strength or stability. Within the validity,
if the lifting appliances are shifted to a new site, re-examination by the same competent person
for ensuring its safety shall also be done.
CONTRACTORs can utilize the services of any competent person as defined in Factories Act,
1948 and approved by Chief Inspector of Factories with the permission of the CONSULTANT.
All alarms and signals like automatic safe load indicators (SLI), boom angle indicators, boom
extension indicators, over lift boom alarm, swing alarm, hydraulic safety valves, mechanical radius
indicators, load moment indicators etc. shall be periodically examined and maintained always in
working condition.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
CONTRACTOR shall ensure that Equipment shall be properly marked with an identification
number and safe working load and be inspected and color coded each quarter by
CONTRACTORs as indicated below.
Any equipment which is unfit for use must be color coded Red and removed from site immediately.
Every lifting appliances and gears like cranes, F15 crane etc., if so constructed that the safe
working load may be varied by raising or lowering of the jib or otherwise shall be attached with an
automatic indicator of safe working loads approved by Bureau of Indian standards/ International
certifying bodies which gives a warning to the operator and arrests further movements of the lifting
parts.
The CONTRACTOR shall not employ any person to drive or operate a lifting machine like crane,
F15 crane etc. whether driven by mechanical power or otherwise or to give signals to work as a
operator of a rigger or derricks Possesses the knowledge of the inherent risks involved in the
operation of lifting appliances by undergoing a formal training at any institution of national
importance acceptable to CONSULTANT Is medically examined periodically .
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Out-of level
One of the most severe effects of being out-of fit level is that side loads develop in the boom. Because
of side loads all mobile cranes lose capacity rapidly as the degree of out-of-level increases and
therefore.
Boom
• The boom is one of the more critical elements of the crane and must be in perfect condition
at all time. No boom section with a bent lattice member shall be allowed
• All welds shall be crack and corrosion free
• No member of the boom shall be bent
• All telescopic booms shall be free from cracks, rust, flaking or cracked paint, bulges, greases
or varnishes.
• The sweep area (work area) of the construction machinery shall be always free from
obstructions.
• All hydraulic piping and fittings shall be maintained leak proof.
• The operator cab shall possess good and safe:
• Structure, windows and windshield wipers
• Drivers chair and foot rest
• Control handles
• Cab instrumentation
• Telecommunication
• Cab out fitting
• Wind indicator with an adjustable set point shall be in a position representative for the wind
on the crane. The indicator shall give continuous information regarding constant speeds and
gusts.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• The primary requirement in rigging shall be to assess the weight of load before attempting
any lift.
• All hooks shall be fitted with Master Rings having certificate of fitness from the competent
person, so that the hooks are subjected to balance vertical loading only.
• Only four legged slings shall be allowed which includes master link (ring), intermediate
master link (ring) if necessary, chain / wire rope sling, sling hook or other terminal fitting.
Conditions of Contract on Safety
• Hand spliced slings up to 32mm diameter shall not be used at site for any lifting purpose.
• No load shall be slewed over public areas without stopping the pedestrians and road traffic.
A separate pedestrian path shall be provided at the beginning of site activities.
• Requirements of outriggers
All outriggers shall be fully extended and at all tyre are clear of the ground. Heavy duty blocking
having large bearing area shall be necessary to prevent sinking of floats. All loads shall have tag-
lines attached in order to ensure that the load can be controlled at all times.
No close working to any live overhead power line is permitted without the operation of a strict Permit
to Work. Minimum lighting is to be ensured at all lifting operations. Failure to do any of the above
shall attract penalty from the CONTRACTOR as per relevant clause
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Personnel occupying the man basket shall complete “Working at Height” training and follow
100% tie-off procedure.
• Prior to use each day and at each new work location, the Work Basket shall undergo a full
cycle test at 200% of the maximum design capacity.
• A qualified design engineer shall design the Man Basket with a safety factor more than 5.
• Man Baskets shall be at least 1.2 m square on plan and provide head clearance which allows
personnel to stand upright.
• Man Basket weight, maximum number of personnel, and load capacity shall be posted on
the basket.
• Cranes carrying personnel in Man Basket shall be uniformly leveled within 1% of the level
grade and located on firm footing.
• Crane travel shall be prohibited while carrying persons.
• The total weight of the loaded Man Basket and related rigging shall NOT exceed 25% of
Crane rated capacity.
• The minimum safety factor of load hoist wire rope shall be 7.
• Lifting and lowering speeds shall NOT exceed 30 m /minute.
• Use a full body harness with double lanyards attached to the crane hook to prevent the
worker(s) from being ejected or pulled from the basket.
• A Pre-Lift Meeting attended by the responsible supervisor/foremen, crane operator,
signalman and personnel to be lifted shall be held before the beginning of personnel lift at
each new work location and thereafter for any personnel newly assigned to the lifting work.
6.35 Heavy Lifts
The contractor shall submit detailed rigging studies plan for PMC/ Owner approval prior to lifting
equipment which cannot be erected with a crane of approx. 100 MT capacity due to constraints of
its dimensions, location of foundation height, approach & weight. Contractor shall generate the
“Permit for heavy lift/critical erection”. Prior to actual lifting activities, contractor shall check the
validity of the crane inspection certificate issued by statutory/ competent authority. This
requirement shall also apply to all rigging equipments utilized for the job. The contractor shall, at
all times, be responsible for all rigging activities. The Contractor shall ensure medical fitness of all
workmen who are engaged / involved in erection of equipments, vessels etc. and such fitness
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
checks shall be carried-out every six months interval with the help of a registered medical
practitioner & record shall be maintained
Adequate safety measures such as positive barricading, usage of appropriate PPEs, permit to
work, etc. shall be taken during all heavy or critical lifts. For lifting any material (irrespective of
shape, size or volume), at any height, it is always advisable to prepare a Plan of Erection (PoE)
taking into consideration hazards & risks associated therein – this can enable people to put their
own experiences of various natures & side-by-side establish a practical method for risk-free
erection / lifts. The contractor shall prepare PoE & shall document the same, when risks are
identified as “medium” or “high” and the same shall be approved by its competent / qualified
engineer.
6.36 Excavation
The Contractor shall obtain permission from competent authorities prior to excavation wherever
required. The Contractor shall locate the position of buried utilities (water line, cable route, etc.)
by referring to project / plant drawing / in consultation with Owner/PMC. The Contractor shall start
digging manually to locate the exact position of buried utilities & thereafter use mechanical
means.
The Contractor shall keep soil heaps at least 1.2 M away from edge or a distance equal to depth
of pit (whichever is more) The Contractor shall maintain sufficient “angle of repose” during
excavation – shall also provide slope or suitable bench as decided by Owner/PMC. The Contractor shall
arrange “battering” or “benching” wherever required for preventing collapse of edge of
excavations. The Contractor shall identify & arrange de-watering pump or well-point system to
prevent earth collapse due to heavy rain / influx of underground water.
The Contractor shall arrange protective fencing / barricading with warning signal around
excavated pits, trenches, etc. along with minimum 2 (two) entries, exits / escape ladders. The
Contractor must avoid “underpinning” / under-cutting to prevent collapse of chunk of earth during
excavation. The Contractor shall use “stoppers” to prevent over-run of vehicle wheels at the edge
of excavated pits / trenches. The Contractor shall arrange strengthening of “shoring” &
“strutting” proactively to avoid collapse of earth / edges due to vehicular movement in close
proximity of excavated areas / pits / trenches, etc.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Site shall be barricaded and provided with warning signs including night warning lamps at
appropriate locations for traffic diversion.
Experienced drivers with valid driving license shall drive road rollers, bitumen sprayers and
pavement finishers and all vehicles on site.
Employees handling hot bitumen sprayers or spreading bitumen aggregate mix or mixing bitumen
with aggregate shall be provided with PVC hand gloves and rubber gumboot up to knee joints. If
bitumen accidentally falls on ground, sprinkle sand immediately to cover it and to prevent anybody
stepping on it. It shall then be removed with the help of spade.
For cement concrete roads, besides site barricading and installation of warning signs for traffic
diversion, safe practices mentioned in the section on 'Concreting' shall be also applicable.
Use PPEs such as Safety Goggle, Apron, Safety helmet, Dust mask and Safety Shoes at site.
• All rig accessories must be thoroughly examined & certified by 3rd party competent
authority.
• Only trained or authorized persons shall operate the piling/boring rig and other equipment.
Competency certificate of rig operator to be submitted to PMC.
• Piling/boring area shall be barricaded and sign boards should be installed.
• Surface of the piling/boring area shall be levelled for the safe movement of Rigs.
• Pile pieces once removed during dressing operation shall not be left on edge of excavated
pit; it shall be shifted to designated area.
• Check underground utilities before work commences.
• Guys, outriggers or counter weight shall be provided for stability.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Route the electrical cables such that they will not get damaged mechanically and will not
come in contact with water.
• Guards for rotating parts of machines are in place.
• Wear ear plug/muffs when working at high noise area.
• Periodic servicing & maintenance to rig, all the parts & accessories shall be done.
• Discard the damaged or cracked accessories immediately. Replace them at once.
• Ensure sound condition of the main rope attached to the hammer and is in accordance with
the weight of the hammer.
• Ensure proper tightness, slackness of the guy ropes as per requirement of the job.
• Use of Tripod type of rig for boring/piling is not allowed. Rigs shall be inspected as per
checklist during piling and boring.
6.39 Bar Bending and Cutting
Only trained persons shall carry out bar bending and cutting activities. Supervisor shall ensure
that all rotating parts are guarded. Good housekeeping shall be maintained in bar cutting area.
Protruding bars shall be cut or guarded. Use safety helmet, safety shoes, safety goggles, and
leather gloves while Bar Bending and Cutting.
6.40 Shuttering
Cutting machine shall be guarded while cutting and joining plywood. Shutters shall be stacked and
stored properly. Loose shuttering shall be secured properly to prevent fall of shutters. Shuttering
activity shall be barricaded. Rebars shall be capped / secured to prevent injuries.
Structural steel or prefabricated parts should be stored and handled in such a manner that they
shall not fall or overturn. Racks are to be set on firm ground.Structural steel or prefabricated parts
should be lifted, by methods or appliances that prevent them from spinning accidentally.
While structural steel or prefabricated parts are being erected, the employees shall be provided
with appliances for guiding them as they are being lifted and set down, so as to avoid crushing of
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
hands and to facilitate the operations. Use of such appliances should be ensured.
A raised structural steel or prefabricated part shall be secured against external agencies such as
wind and passing loads before its release from the lifting appliance.
When adverse weather conditions such as high-speed wind or reduced visibility entail risks of
accidents the work should be carried on with particular care, or if necessary, interrupted.
Personnel shall not be on any scaffold or other temporary elevated work area during storms or
high winds - sustained winds more than 65 kph (40 mph) - unless the scaffold or working level is
indoors or otherwise unaffected by the weather conditions. Outdoor scaffolds or elevated work
platforms shall not be used during thunderstorms or when there is likelihood of lightning. Structural
steel parts that are to be erected at a great height should as far as practicable be assembled on
the ground.
When structural steel or prefabricated parts are being erected, a sufficiently extended area
underneath the workplace should be barricaded or guarded and no one shall be allowed to work
underneath. Ensure that employees use PPE like Safety Helmet, Safety Hand gloves, Safety
Shoes.
Reinforcement:
All protruding reinforcing steel, onto and into which employees could fall, shall be guarded to
eliminate the hazard of piercing. Ensure that employees use PPE like safety helmet, safety shoes,
safety glasses / goggles, gloves etc. DO NOT stand on cantilever rods. While transporting material
by trucks / trailers, the rods protruding outside should be tied and tagged with red flags/lights.
Concreting:
Barricade the concreting area while pouring at height / depths. Keep vibrator hoses, pumping
accessories in good condition. Pipelines in concrete pumping system shall not be attached to
temporary structures such as scaffolds and formwork support as the forces and movements may
affect their integrity.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Safety cages & guards around moving motors/parts etc. should be provided in concreting mixers.
Use PPEs like gloves, PVC / Rubber, Safety Shoes / Gumboots with steel toe, safety goggles,
safety helmet etc. while handling concrete and wear respirators for handling with cement. Use
Safety shoes, while climbing on structure/ scaffold or at higher elevation. Earthing of electrical
mixers, vibrators, etc. should be done and verified. Cleaning of rotating drums of concrete mixers
shall be done from outside. LOTO Work Permit with positive Isolation / and tag out devices shall
be ensured prior to entry.
Where concrete mixers are driven by internal combustion engine, exhaust points shall be located
away from the employee workstation so as to eliminate their exposure to obnoxious fumes. Ensure
adequate lighting arrangements for carrying out concrete work during night. Projected re-bars
which may cause injury shall be provided with protective caps/covers.
Before erecting temporary shelters like sheds or tents anywhere within the site/plant premises,
written permission of the concerned authorities must be obtained. Temporary fixtures like; sheds,
tents, etc. shall be erected in conformity with normal safety standards. Thatched roof to such
fixtures will not be permitted.
Temporary piping, hose connections and electrical wiring must be laid as in such manner that
they do not cause tripping or hitting hazard. Temporary sheds can be constructed only for the
storing of the material /site office. It should not be used for any other purpose. The shed shall be
made of safe construction material and good aesthetic view. The shed shall be made strictly at
the authorized location and size. All windows shall be either of wire mesh or glass.
After completion of the job, shed must be demolished informing to concerned authorities and area
must be cleaned. All precautions shall be taken to ensure that any temporary electrical wiring used
within Plant premises will not cause spark or shock.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Contractor (s) shall not use LPG gas cylinder inside site.
• Where a cylinder is designed to accept a valve protection cap, caps shall be in place
except when the cylinder is in use or connected.
• Be checked for leaks by means of soapy liquid applied to each joint.
• Be stored separately, oxygen and acetylene cylinders shall be at least 5 meters apart.
• Be stored vertically, separated and marked ‘EMPTY’ or ‘FULL’.
• Be stored in well-ventilated areas.
• Be shielded from direct sunlight or any heat /ignition source.
• Be secured vertically during use and transportation. Cylinders shall never be used in a
horizontal position.
• Not be lifted by any slings, rolled or used as rollers themselves.
• Be fitted with Flashback Arrestors at the torch and the regulator, being devices designed
to prevent an explosive mix developing in either cylinder.
• No attempt shall be made to transfer gas from one cylinder to another.
• The regulator and other equipment shall be connected and a test shall be made to ensure
that all joints are gas tight and free from leakage. The regulator shall be suitable for the
equipment being used.
• Be fitted with approved pressure reducing regulator and gauges for the intended use.
• Not have joint fittings on acetylene cylinders made of copper or silver, as when in contact
with the gas, these metals form explosive compounds.
• No jointing compound or grease shall be applied to the threaded joints of the cylinders
and fittings.
• Have leaking cylinders taken out of service immediately, removed outdoors and closely
attended until completely and safely depressurized.
• Not have cylinders positioned directly beneath a working area as molten metal may fall
onto hoses causing leaks and possibly igniting the gases.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Contractor shall ensure that flash back arrestors conforming to BS: 6158 or equivalent are installed
on all gas cylinders as well as at the torch end of the gas hose, while in use. All cylinders shall be
mounted on trolleys and provided with a closing key. Empty & filled-up gas cylinders shall be
stored separately with TAG, protecting them from direct sun or rain. Minimum 2 nos. of Portable
DCP type fire extinguishers (10 kg) shall be maintained at the gas cylinder stores. Stacking &
storing of compressed gas cylinders shall be arranged away from DG set, hot works, Elect. Panels
/ Elec. boards, etc. The burner and the hose placed downstream of pressure reducer shall be
equipped with Flash Back Arrester/Non Return Valve device. The hoses for acetylene and oxygen
cylinders must be of different colours. Their connections to cylinders and burners shall be made
with a safety collar.
At end of work, the cylinders in use shall be closed and hoses depressurized. Cutting of metals
using gases, other than oxygen & acetylene, shall require written concurrence from Owner.
All welding machines shall have effective earthing at least at distinctly isolated two points. In order
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
to help maintain good housekeeping, and to reduce fire hazard, live electrode bits shall be
contained safely and shall not be thrown directly on the ground. The hoses of Acetylene and
Oxygen shall be kept free from entanglement & away from common pathways / walkways and
preferably be hanged overhead in such a manner which can avoid contact with cranes, hydra or
other mobile construction machinery.
Hot spatters shall be contained / restricted appropriately (by making use of effective fire-retardant
cloth/fabric) and their flying-off as well as chance of contact with near-by flammable materials shall
be stopped. The Contractor shall arrange adequate systems & practices for accumulation /
collection of metal & other scraps and remnant electrodes and their safe disposal at regular
interval so as to maintain the fabrication and other areas satisfactorily clean & tidy. All gas
cylinders must have a cylinder cap on at all times when not in use.
A) CONTRACTOR shall ensure the following criteria during catalyst Storage and Handling
• The catalyst containers are to be handled carefully without bumping and must never be rolled to
avoid any damage of the catalyst.
• The catalyst drums should be inspected carefully for damage during shifting from store to site,
and Drums must not be stacked on their sides or stacked more than four drums high, even when
held on pallets.
• The lids should be left on the drums until just before the catalyst is to be charged, and if the lids
are accidentally knocked off or removed for inspection, it is important that they should be replaced
as soon as possible, so that contamination of the catalyst is avoided. If the drum lid cannot be
replaced, then the catalyst should be re-drummed without delay, this process shall be carried out
in presence of CONTRACTOR’s representative.
• Handled the Catalyst drums as gently as possible. Suitable space is required for storing the
drums between deliveries and charging, and double handling shall be avoided if this space is
close to the equipment to be loaded.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Catalyst Drums must not be rolled, and if manual handling is unavoidable, the suitable drum
barrows, opening levers and skids should be provided.
• Adopt a good method of sieving, which is to pass the catalyst over a simple inclined screen, since
vibrating screens can cause additional unnecessary damage and loss. The mesh spacing should
be about half of the smallest dimension of the catalyst pellet.
• Suitable masks must be provided for those who are engaged in this kind of operation, and some
Provisions should be made to collect the fines for disposal, based on catalyst supplier
recommendation.
• Reforming catalyst does not usually require sieving, but CONTRACTOR shall ensure broken
rings should be removed whilst the socks are being charged, since relatively broken rings can
affect the tube pressure drop significantly.
• All the substances can be kept in three categories – one which does not burn, other which burn
and the third one, which produces oxygen and may be the cause of fire. While storing, the first
thing is that the solids and liquids should be kept separately and the properties must be seen
before it is decided to store at one place.
B) CONTRACTOR shall ensure to follow/ implement the below General applicable safety
rules during Catalyst Loading.
• Wear protective clothing and gear provided and required for plant operation.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Wear a Full body Harness double Lanyard this Shock absorber when working at elevated
locations if adequate protection against falling is not available.
• Wear a suitable air mask when working on pipelines or equipment containing hydrocarbons, toxic
gases or chemicals.
• Use the correct hose for air, water, steam or chemicals; secure it during use. Tag any hose that
needs repairing and send it to the workshop. Clean chemical hoses after use.
• Be sure that hoses are in good condition and that all connections are tight so that there is no
chance of leakage that could result in a hazardous situation.
• When using steam hoses, crack the steam valve at first until all water in the hose is discharged
and the hose is heated up. This will prevent high velocity water jets from the hose.
• Report hazards immediately and take all measures to mitigate the hazard.
• Be thoroughly familiar with the location and operation of all firefighting equipment, blankets,
safety showers, gas mask, and other safety equipment.
• When giving clearance to maintenance to perform work in the unit, be sure the equipment is in a
safe condition to work on. Be specific in your instructions and be sure that they are understood
and followed. Check to see if instructions are being observed.
• Isolate the equipment to be opened for clean-out or repairs. Leave rest of the equipment inactive
with valves closed. Isolation is to be done by blinding-off.
• Purge the equipment with nitrogen, especially those that have contained H2S and hydrocarbon.
Thereafter, steam-out with purge steam to remove heavy hydrocarbons. While purging and
during initial steam-out operations, vent to flare.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Close vent, and open the drain. Steam-out any liquid to the sewer for half an hour. Beware that
hydrocarbons can contain H2S and that release of H2S from the drained-out condensate could
occur.
• Check for the presence of hydrocarbon vapors within certain proportions. If toxic vapors present,
a test for these should be made.
• Precaution in loading unloading of catalyst drums. Drums shall be kept on pallets. This includes
safety precaution of crane & lifting tools/tackles.
• Catalyst fine dust is poisonous and irritating to eyes and skin, a minimum dust respirator, Apron,
face mask, goggles and hand gloves to be used.
• Standard vessel entry procedure should be followed at all times, this includes minimum,
followings
• A person stationed outside the vessel. This individual should be equipped with rescue gears and
an independent air supply.
• Catalyst should be loaded, unloaded, handled, and stored under the supervision of a competent
person as per guidance of CONSULTANT, persons familiar with hazards and the precautions to
be deputed for emergency.
• Be familiar with Materials Safety Data Sheets of Catalyst to be handled in the respective area.
• Lifting appliances used should be of good construction and free from defects. They should be not
be overloaded or overfilled.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• When highly flammable catalyst are being loaded or unloaded, adequate firefighting equipment
should be provided so that an incipient fire can be controlled immediately.
• Where necessary, non-sparking tools should be provided and used in explosive atmospheres.
• Foodstuff and other articles for consumption must be stored well away from Catalyst classified
as toxic or harmful or which have a strong smell.
• Take all the care to see that passages are not blocked. Easy accessibility should be kept to reach
the substance from all the sides. In solid storage, always care should be taken to maintain first
in, first out otherwise on long storage decomposition may take place causing unknown hazards.
6.46 Explosives/Blasting operations
Blasting operations shall be carried out as per latest Explosive Rules (Indian / International) with
prior permission. The Contractor shall obtain license from Chief Controller of Explosives (CCoE)
for collection, transportation, storage of explosives as well as for carrying out blasting operations.
The Contractor shall prepare exclusive method statement (in cognizance with statutory
requirements) for diffusing unfired explosives, if any, at project site before carrying out actual task.
Nowhere blasting shall be carried out by the Contractor or its agency without the involvement of
competent supervisor and licensed blaster / shot blaster
• CONTRACTOR shall produce detailed Method Statement, Risk Assessment and Job Safety
Analysis prior to work commencing.
• CONTRACTOR shall ensure grit blasting shall be carried out in an enclosed designated area,
levelled, and with sufficient safe access, both to the area, and around the work pieces.
• Only proper grit blast shall be used. Under no circumstances shall products containing free silica
be used.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Personnel involved in the actual blasting of material shall be protected by a blast hood that meets
approved standards and providing both respiratory and eye protection.
• The nozzle shall be fitted with a properly functioning dead mans handle, and a standby man shall
stay by the blast pot and Nozzle and hose must be earthed.
• Standby men shall be provided with suitable respiratory and eye protection.
• Spent grit shall be collected and properly disposed off.
6.48 Painting
CONTRACTOR shall provide Specific training on the MSDS of the painting and any other solvents
used in paint related work. Workers shall be instructed and trained on the hazards related to their
work, particularly for long term activities, in the correct handling of chemicals and on the correct use
of the equipment.
CONTRACTOR shall consider HSE aspects during selection and purchasing of painting
material.
• Use and storage of flammable paints and solvents shall be kept to well ventilated restricted areas;
• These areas shall be suitably marked with the appropriate warning signs;
• No painting preparation and application should be carried out close to ignition sources (welding,
cutting, smoking areas, sparking tools, etc.) unless safe measure are taken;
• Electrical lighting and equipment shall be explosion-proof when required in areas where solvent
vapors are likely to be present;
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Fire extinguishers shall be located at the storage and at the work areas.
B ) Paint Application
• Avoid touching any part of the body and wear protective equipment when handling irritating
materials;
• Adequately ventilate all painting areas and provide approved or equivalent respiratory protection
where necessary;
• Introduction of solvents and paint in confined space shall be subjected to hazard analysis,
because can cause serious health and fire risks;
• While painting in confined space, natural ventilation may be not sufficient and forced ventilation
shall be foreseen (fresh air inlet of the ventilation system should be located near the top, and the
discharge should be located near the bottom);
• If the confined space has a low volume (from about 15 cube meters) then suitable respirator
apparatus can be used as necessary;
• Often while painting workers are exposed to fall hazards so fall protection system shall be applied;
• Painting operators shall wash thoroughly before eating and at the end of the day. Adequate
washing facilities shall be foreseen. Solvents shall never be used for personnel washing.
c) Spray Painting
• All workmen spray painting shall wear chemical cartridge respirators or airline hoods depending
upon the hazards of the paint (containing toxic solvents);
• Overall or other full body working dress shall be wear by spray painters;
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• All pressurized equipment shall be handled carefully. System, hoses, etc. shall be anti-static type
and so grounded as needed;
• Operators and their assistants shall know how to operate and de-energize the equipment in
accordance to manufacturer's recommendations;
• Before using airless spray equipment, all guards recommended by the manufacturer shall be in
place (hoses, conjunction safe lash, etc.) and the system shall be grounded to prevent static
build-up; No spray gun should be pointed at anyone or part of the user's body;
• The area around spray painting activity should be enclosed by fence thick net (better if fire
resistant) or equivalent to protect outside personnel and things from paint over spray. Work areas
shall be kept as clean as practicably possible;
The person in charge of hydrostatic testing must fully understand the safety requirements and
procedures involved with pressure testing. All persons who will work on the pressure test must be
informed of the potential hazards and the necessary safety precautions.
Supports
Piping, vessels, supports and foundations designed for gas service shall not be overloaded by the
extra weight of the test liquid. Temporary supports and braces may be required.
• Vents of adequate capacity shall be installed at high points, to vent air / gas from the item while
it is being filled with the test liquid.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Hazardous gases or vapors must be vented clear of any area where personnel are working or
where there is any possible source of ignition.
• Drains must be installed at a suitable location to allow removal of the test liquid.
• Only approved rating blinds shall be used and all vent bolts tightened to proper torque levels
• HP pipe end points and areas very close to HP vents shall be barricaded and suitable safety
signage displayed in local languages and English.
Valves
Where isolation valves are used to contain test pressures, they must be of adequate rating for the
pressure to be encountered. If isolation valves are used in lieu of blinds, provisions shall be made to
ensure that no over-pressurizing can occur in equipment that is not being tested, due to possible
valve leak.
Vacuum
On vessels or tanks which could collapse if subjected to a vacuum, there must be sufficient vent relief
capacity to assure that the vessel cannot be subjected to a vacuum by draining the test fluid or by
sudden cooling.
General Requirements
• Do not approach system never previously tested, corroded piping or vessels, or vessels with
welds never previously tested during the stepwise increase in pressure to the strength test
pressure.
• After the strength test pressure has been reached and held for a specified interval, the equipment
may be approached.
• The actual pressure at which the system under test will be approached for close inspection shall
be specified in the test procedure.
• Pressure relief valve(s) shall be used to prevent over pressuring of the equipment.
• Any ancillary equipment not under test must be isolated by valves or blind flanged and vented or
disconnected.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Only calibrated test gauges and recorders shall be used and test gauges should be mounted in
the upright position. Pump discharge gauges must be visible to the pump operator for the
duration of the test.
• The equipment / vessel shall have adequate vacuum relief capacity to avoid damage or collapse,
when draining the test liquid.
• Lines should be drained and dried mechanically when the test liquid is corrosive or otherwise
hazardous. The pressure rise during a pressure test should be gradual and under control to allow
time for material to strain, and time for personnel to check for leaks.
• A system under test shall be depressurized (with the exception of pressure due to a liquid head)
before any work is done to stop leaks or repair weakness, including the tightening of bolts. In
tightness tests, bolts may be tightened without depressurizing, if specifically approved in the
written test procedure.
• A block valve is required on the line from the test pump to the equipment under test.
• Air shall not be used to displace test fluid from underwater equipment unless it has been
determined that the equipment will not float.
• Salt water must not be used for testing any material subject to stress corrosion cracking in the
presence of chloride ions (such as stainless steel type 304 or 18.8 - CrNi).
• Possible changes in pressure due to thermal expansion, contraction or hydrostatic heads must
be taken into account.
• Written procedures approved prior to testing shall be followed for the disposal of test mediums
containing chemical additives for control of corrosion or bacteria.
• All tests need test manifold fitted with gauge, valve and PRV. The test manifold need to be
certified.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
All air receivers and compressors shall be in good condition and properly maintained.
Air receivers shall be individually identified and marked with their safe working pressure. All air
receivers must be fitted with a properly set pressure relief valve.Air receiver and related relief valve
shall be accompanied by a valid test certificate, which shall be kept on site by CONTRACTOR and
shown to the CONSULTANT representative before bringing the vessel onto site. Guard should be
constructed to compressed air in order to prevent worker to get into contact with the hazardous
machine. Air receivers shall be examined and the pressure relief valve tested by an independent
examiner at yearly intervals.
A register of all air receivers containing:-
The contractor shall adhere to safe demolishing/ dismantling practices at all stages of work to guard
against unsafe working practices. The contractor shall disconnect service lines (power, gas supply,
water, etc.)/ make alternate arrangements prior to start of work and restore them, if required as
directed by PMC/ Owner at no extra cost.
Before carrying out any demolition/ dismantling work, the contractor shall take prior approval of
Owner/PMC and generate. For revamp jobs in operating plants where location of underground
utilities is not known with certainty, the contractor shall depute an experienced engineer for
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
supervision and shall make adequate arrangements for Firefighting & First-Aid during the execution
of these activities.
The Contractor shall arrange approved Job Safety Analysis (JSA) / Method Statement for the
specific demolition / dismantling task and corresponding action plan commensurate with hazards /
risks associated therein. In no case any activity related to demolition / dismantling shall be carried
out by the Contractor without engaging own supervision / field engineer.
6.52 Maintenance Work-Machine, equipment, DG, etc.
Preventive maintenance schedule of vehicles, tools, equipment, etc. shall be prepared and done
according and pertaining records shall be maintained. All electrical, mechanical, construction
equipment and /or construction vehicle, power operated and battery operated equipment, machines
and tools shall be certified and inspected by concerned Contractor (s) discipline jointly with HSE
and provide colour code of the month on the machine, tools and/or equipment. Each machine, tools
or equipment shall be inspected every month with defined colour code.
Contractor (s) must maintain the records of all inspection and maintenance activities and to produce
whenever demanded by Client / PMC. Legal requirements shall be followed for DG Sets as per
Indian Electricity Act/Rules and Environment Protection Act/Rules. Practice preventive
maintenance of vehicles and machines and maintain associated records and documents. Exhaust
of the prime mover, if IC engine is used, should be fitted with PESO approved spark arrester (in
case of work in hazardous area).
As a minimum, the contractor shall ensure adherence to following safety requirements while
working in or in the close vicinity of an operating plant:
a) Contractor shall obtain permits for Hot work, Cold work, Excavation and Confined Space
from Owner in the prescribed format.
b) The contractor shall monitor record and compile list of his workers entering the operational
plant/unit each day and ensure & record their return after completing the job.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
c) Contractor’s workers and staff members shall use designated entrances and proceed by
designated routes to work areas only assigned to them. The workers shall not be allowed to enter
units' area, tanks area, pump rooms, etc. without work authorization permit.
d) Work activities shall be planned in such a way so as to minimize the disruption of other
activities being carried out in an operational plant/unit and activities of other contractors.
e) The contractor shall submit a list of all chemicals/toxic substances that are intended to be
used at site and shall take prior approval of the Owner.
f) Specific training on working in a hydrocarbon plant shall be imparted to the work force and
mock drills shall be carried out for Rescue operations/First-Aid measures.
g) Proper barricading/cordoning of the operational units/plants shall be done before starting
the construction activities. No unauthorized person shall be allowed to trespass. The height and
overall design of the barricading structure shall be finalized in consultation with the Owner and
shall be got approved from the Owner.
h) Care shall be taken to prevent hitting underground facilities such as electrical cables,
hydrocarbon piping during execution of work.
i) Barricading with water curtain shall be arranged in specific/critical areas where
hydrocarbon vapors are likely to be present such as near horton spheres or tanks. Positioning of
fire tenders (from owner) shall also be ensured during execution of critical activities.
j) Emergency evacuation plan shall be worked out and all workmen shall be apprised about
evacuation routes. Mock drill operations may also be conducted.
k) Flammable gas test shall be conducted prior to any hot work using appropriate measuring
instruments. Sewers, drains, vents or any other gas escaping points shall be covered with flame
retardant tarpaulin.
l) Respiratory devices shall be kept handy while working in confined zones where there is a
danger of inhalation of poisonous gases. Constant monitoring of presence of Gas/ Hydrocarbon
shall be done.
m) Clearance shall be obtained from all parties before starting hot tapping, patchwork on live
lines and work on corroded tank roof.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
o) Welding spatters shall be contained properly and in no case shall be allowed to fall on the
ground containing oil. Similar care shall be taken during cutting operations.
p) The vehicles, cranes, engines, etc. shall be fitted with spark arresters on the exhaust pipe
and got it approved from Safety Department of the Owner.
q) Plant air should not be used to clean any part of the body or clothing or use to blow off dirt
on the floor.
r) Gas detectors should be installed in gas leakage prone areas as per requirement of
Owner's plant operation personnel.
s) Experienced full time safety personnel shall be exclusively deployed to monitor safety
aspects in running plants
The CONTRACTOR shall prepare and submit Emergency preparedness & Response Plan for
approval of their respective work sites within 30 days of site mobilization. The plan shall integrate
the emergency response plans of the CONTRACTOR and all his CONTRACTORS.
The Emergency Response Plan shall detail the CONTRACTOR’s procedures, including
Construction Phase and pre-commissioning & commissioning Phase referring site TRA/HIRA.
detailed communications arrangements, for dealing with all emergencies that could affect the Site.
This include where applicable, injury, sickness, evacuation, fire, chemical spillage, severe weather
and rescue.
Emergency awareness trainings shall be part of Site Emergency preparedness and response Plan.
Employees shall be fully made aware about potential emergencies and their role and
responsibilities during emergencies in HSE induction and subsequent emergency management
awareness programs.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
The CONTRACTOR shall ensure that an Emergency Response Plan is prepared to deal with
emergencies arising out of :
• Fire and explosion
• Collapse of lifting appliances and equipment
• Collapse of building or structure etc.
• Gas leakage or spillage of dangerous goods or chemicals
• Bomb threatening, criminal or terrorist attack
• Drowning of worker
• Landslides getting workers buried floods, Earthquake, storms etc.
8. ENVIRONMENTAL MANAGEMENT
Contractor shall ensure proper storage and utilization methodology of materials that are detrimental
to the environment. Where required, Contractor shall ensure that only the environment friendly
materials are selected and emphasize on recycling of waste materials, such as metals, plastics,
glass, paper, oil & solvents.
The waste that cannot be minimized, reused or recovered shall be stored and disposed of safely.
In no way, toxic spills shall be allowed to percolate into the ground. The contractor shall not use the
empty areas for dumping the wastes.
The contractor shall strive to conserve energy and water wherever feasible. The contractor shall
ensure dust free environment at workplace by sprinkling water on the ground at frequent intervals.
The air quality parameters for dust, poisonous gases, toxic releases, harmful radiations, etc. shall
be checked by the contractor on daily basis and whenever need arises.
The contractor shall not be allowed to discharge chemicals, oil, silt, sewage, sullage and other
waste materials directly into the controlled waters like surface drains, streams, rivers, ponds. A
discharge plan suggesting the methods of treating the waste before discharging shall be submitted
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
to Owner/PMC for approval. For pipeline jobs, top soil shall be stacked separately while making
ROW through fields. This fertile soil shall be placed back on top after backfilling.
For offshore construction barges, arrangements shall be made for safe disposal of human, food
other wastes and applicable laws in this regard shall be followed
8.2 Rules & Regulations
All persons deployed at site shall be knowledgeable of and comply with the environmental laws,
rules & regulations relating to the hazardous materials, substances and wastes. Contractor shall
not dump, release or otherwise discharge or disposes off any such materials without the express
authorization of Owner/PMC. An indicative list of Statutory Acts & Rules relating to HSE to be
displayed
8.3 Weather Protection
Contractor shall take appropriate measures to protect workers from severe storms, rain, solar
radiations, poisonous gases, dust, etc. by ensuring proper usage of PPEs like Sun glasses, Sun
screen lotions, respirators, dust masks, etc. and rearranging/ planning the construction activities to
suit the weather conditions. Effective arrangement (without creating inconvenience to project
facilities & permanent installations) for protecting workmen from hailstorm, drizzle in the form of
temporary shelter shall be made at site
8.4 Sustainable Development
It includes:
• The activities to put in place and prevent the working place from intentional offences in the country
(Security Management System)
• The implementation of the requirements of Corporate Social Responsibility.
• The activities regarding the safeguard of health of people, the prevention from incidents and the
protection of the natural Environment (HSE Management System).
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• The Prevention and Protection Service in the offices as required by Indian Law.
8.5 Air Quality
The CONTRACTOR shall take all necessary precautions to minimize fugitive dust emissions from
operations involving excavation, grading, and clearing of land and disposal of waste. He shall not
allow emissions of fugitive dust from any transport, handling, construction or storage activity to
remain visible in atmosphere beyond the property line of emission source for any prolonged period
of time without notification to the CONSULTANT.
The CONTRACTOR shall use construction equipment designed and equipped to minimize or
control air pollution. He shall maintain evidence of such design and equipment and make these
available for inspection by CONSULTANT.
If after commencement of construction activity, CONSULTANT believes that the CONTRACTOR’S
equipment or methods of working are causing unacceptable air pollution impacts then these shall
be inspected and remedial proposals shall be drawn up by the CONTRACTOR, submitted for
review to the CONSULTANT and implemented.
In developing these remedial measures, the CONTRACTOR shall inspect and review all dust
sources that may be contributing to air pollution. Remedial measures include use of additional/
alternative equipment by the CONTRACTOR or maintenance/modification of existing equipment
the event that approved remedial measures are not being implemented and serious impacts persist,
the CONSULTANT may direct the CONTRACTOR to suspend work until the measures are
implemented, as required under the Contract.
CONTRACTOR’S transport vehicles and other equipment shall conform to emission standards
fixed by Statutory Agencies of Government of India or the State Government from time to time. The
CONTRACTOR shall carry out periodical checks and undertake remedial measures including
replacement, if required, so as to operate within permissible norms.
The CONTRACTOR shall establish and maintain records of routine maintenance program for
internal combustion engine powered vehicles and equipment used on this project. He shall keep
records available for inspection by CONSULTANT. Emission level shall be as prescribed by
standards.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
The CONTRACTOR shall cover loads of dust generating materials like debris and soil being
transported from construction sites. All trucks carrying loose material should be covered and loaded
with sufficient free- board to avoid spills through the tail board or side boards.
The CONTRACTOR shall promptly transport all excavation disposal materials of whatever kind so
as not to delay work on the project. Stockpiling of materials will only be allowed at sites designated
by the CONSULTANT. The CONTRACTOR shall place excavation materials in the
dumping/disposal areas designated in the plans.
The temporary dumping areas shall be maintained by the CONTRACTOR at all times until the
excavate is re-utilized for backfilling or as directed by CONSULTANT. Dust control activities shall
continue even during any work stoppage.
The CONTRACTOR shall place material in a manner that will minimize dust production. Material
shall be minimized each day and wetted, to minimize dust production. During dry weather, dust
control methods must be used daily especially on windy, dry days to prevent any dust from blowing
across the site perimeter.
The CONTRACTOR shall water down construction sites as required to suppress dust, during
handling of excavation soil or debris or during demolition. The CONTRACTOR will make water
sprinklers, water supply and water delivering equipment available at any time that it is required for
dust control use. Dust screens will be used, as feasible when additional dust control measures are
needed specially where the work is near sensitive receptors.
The CONTRACTOR shall provide a wash pit or a wheel washing and/or vehicle cleaning facility at
the exits from work sites such as construction depots and batching plants. At such facility, high-
pressure water jets will be directed at the wheels of vehicles to remove all spoil and dirt.
The CONTRACTOR shall design and implement his blasting techniques so as to minimize dust,
noise, vibration generation and prevention fly rock. Blasting technique should be consistent not only
with nature and quaintly of rock to be blasted but also the location of blasting.
The CONTRACTOR shall give preference to explosives with better environmental characteristics.
The CONTRACTOR shall protect structures, utilities, pavements roads and other facilities from
disfiguration and damage as a result of his activities. Where this is not possible, the CONSULTANT
shall restore the structures, utilities, pavements, roads and other facilities to their original or better,
failing which the rectification/restoration work shall be carried out at the risk and cost of the
CONTRACTOR.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
The CONTRACTOR shall submit to the CONSULTANT an Air Monitoring and Control Plan (AMCP)
under contract specific Site Environmental Plan to guide construction activity insofar as it relates to
monitoring, controlling and mitigating air pollution.
The following key areas shall be monitored by Contractor (s) (by self or and by MOEF/PCB
approved third party/Lab) for their respective owned/hired vehicles / equipment / plants / machines
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
and allocated area: All Vehicles shall possess valid PUCs. Any out of legal permissible limit Vehicle
shall be serviced.
All connected DGs noise and stack emission shall be monitored six monthly for key pollutants as
specified by Owner / PMC.
Ambient Air & Noise shall be monitored six monthly minimum at two sample locations for following
key pollutant. Mandatory Parameters to monitor : SO2, NO2, PM10, PM2.5, Ozone, Lead, CO
Parameters to monitor depending upon site air pollution sources / aspects & impacts study or
requirement from Owner / PMC: Ammonia, Benzene, Arsenic, Benzo (a) Pyrene and Nickel.
Site walk inspections should be used to monitor for excessive visible engine/ motor emissions (i.e.
black smoke), with offending vehicles and equipment removed from site until the motor can be
repaired or replaced. Dust emissions shall be monitored as part of site walks/ inspections, and any
particularly dust generating activities recorded, along with corrective action taken
The CONTRACTOR shall comply with the Indian Government legislation and other State
regulations as they relate to water pollution control and monitoring. A drainage system should be
constructed at the commencement of the Works, to drain off all surface water from the work site
into suitable drain outlet.
The CONTRACTOR shall provide adequate precautions to ensure that no spoil or debris of any
kind is pushed, washed, falls or deposited on land adjacent to the site perimeter including public
roads or existing stream courses and drains within or adjacent to the site. In the event of any spoil
or debris from construction works being deposited or any silt washed down to any area, then all
such spoil, debris or material and silt shall be immediately removed and the affected land and
areas restored to their natural state by the CONTRACTOR to the satisfaction of the
CONSULTANT.
The CONTRACTOR shall ensure that earth, bentonite, chemicals and concrete agitator washings
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
etc. are not deposited in the watercourses but are suitably collected and residue disposed off in a
manner approved by local authorities.
All water and waste products (surface runoff and wastewater) arising on the site shall be collected
and removed from the site via a suitable and properly designed temporary drainage system and
disposed off at a location and in a manner that will cause neither pollution nor nuisance.
Any mud slurry from drilling, diaphragm wall construction or grouting etc. shall not be discharged
into the drainage system unless treatment is carried out that will remove silt, mud particles,
bentonite etc. The CONTRACTOR shall provide treatment facilities as necessary to prevent the
discharge of contaminated ground water.
The CONTRACTOR shall discharge wastewater arising out of site office, canteen or toilet facilities
constructed by him into sewers after obtaining prior approval of CONSULTANT / Client. A
wastewater drainage system shall be provided to drain wastewater into the sewerage system.
The bentonite mixing, treatment and handling system shall be established by the CONTRACTOR
giving due regard to its environmental impacts. The disposal of redundant bentonite shall be
carefully considered whether in bulk or liquid form. The disposal location will be advised and
agreed with the relevant authorities. The CONTRACTOR shall take measures to prevent
discharge of oil and grease during spillage from reaching drainage system or any water body. Oil
removal / interceptors shall be provided to treat oil waste from workshop areas etc.
The SUB-CONTRACTOR shall apply to the appropriate authority for installing bore wells for water
supply at site.
The CONTRACTOR shall maintain ecological balance by preventing deforestation and defacing
of natural landscape. The CONTRACTOR shall, so conduct his construction operations, as to
prevent any avoidable destruction, scarring or defacing of natural surroundings in the vicinity of
work.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Where destruction, scarring, damage or defacing may occur as a result of operations relating to
Permanent or Temporary works, the same shall be repaired, replanted or otherwise corrected at
CONTRACTOR’S expense. All work areas shall be smoothened and graded in a manner to
conform to natural appearance of the landscape as directed by the OWNER / CONSULTANT.
The CONTRACTOR shall take all necessary precautions to minimize fugitive dust emissions from
operations involving excavation, grading, and clearing of land and disposal of waste. The
CONTRACTOR shall not allow emissions of fugitive dust from any transport, handling,
construction or storage activity to remain visible in atmosphere beyond the line of emission source
for any prolonged period of time without notification to the CONSULTANT / OWNER.
The CONTRACTOR shall cover loads of dust generating materials like debris and soil being
transported from construction sites. All trucks carrying loose material should be covered and
loaded with sufficient free- board to avoid spills through the tail board or side boards.
The CONTRACTOR shall promptly transport all excavated disposal materials of whatever kind so
as not to delay work on the project. Stockpiling of materials will only be allowed at sites designated,
if any, by the OWNER. The temporary dumping areas shall be maintained by the CONTRACTOR
at all times until the excavated material is re-utilized for backfilling or as directed by OWNER /
CONSULTANT.
The CONTRACTOR shall water down construction sites as required to suppress dust, during
handling of excavation soil or debris or during demolition. The CONTRACTOR will provide water
sprinklers, water supply and water delivering equipment available at any time that it is required for
dust control use. Dust screens will be used, as feasible when additional dust control measures
are needed especially where the work is near sensitive receptors.
The CONTRACTOR shall ensure that earth, muck, detonate, chemicals and concrete agitator
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
washings etc. are not deposited in the water courses but are suitably collected and residue
disposed off in a manner approved by local authorities.
Any mud slurry from piling, drilling or grouting etc., shall not be discharged into the drainage system
unless treatment is carried to remove silt, mud particles, bentonite etc. The CONTRACTOR shall
provide treatment facilities as necessary to prevent the discharge of contaminated ground water.
The CONTRACTOR shall discharge waste water arising out of site office, canteen and toilet
facilities constructed by him into sewers after obtaining prior approval of agency controlling the
system. A waste water drainage system shall be provided to drain waste water into the sewerage
system.
Such a mechanism is intended to ensure that the designation of areas for the segregation and
temporary storage of reusable and recyclable materials are incorporate into the WMP. The WMP
should be prepared and submitted to the CONSULTANT for approval. The CONTRACTOR shall
handle waste in a manner that ensures that they are held securely without loss or leakage thus
minimizing potential for pollution. The CONTRACTOR shall maintain and clean waste storage
areas regularly.
The CONTRACTOR shall remove waste in a timely manner and disposed off at landfill sites after
obtaining approval of Conservancy and Local Municipal Corporation for its disposal.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
The CONTRACTOR shall identify the nature and quantity of hazardous waste generated as a
result of his activities and shall file a ‘Request for Authorization’ with Local Pollution Control
Committee along with a map showing the location of storage area.
It shall be the responsibility of the CONTRACTOR to ensure that hazardous wastes are stored,
based on the composition, in a manner suitable for handling, storage and transport. The labeling
and packaging is required shall be easily visible and be able to withstand physical conditions and
climatic factors. The CONTRACTOR shall approach only Authorized Recyclers of Hazardous
Waste for disposal of Hazardous Waste, under intimation to the CONSULTANT.
Hazardous and/or toxic materials e.g. solvent coating or thinners shall be stored in appropriate
containers. Each material MSDS shall be available at the storage place. Sufficient numbers of fire
extinguishers shall be deployed outside the storage area. Chemical spills shall be contained and
cleaned up immediately to prevent further contamination.
Where contact or exposure with hazardous materials could have harmful effects, appropriate
personal protective equipment e.g. Safety helmet, hand gloves, eye goggles, aprons, chemical
resistant clothing, dust mask and respirators shall be used. In area of high noise besides other
PPE ear defenders like ear plugs or ear muff shall be used.
If any waste (paints, insulation, refractory wastes etc.) encountered or generated as a result of
CONTRACTOR’S activity, then all such wastes classified as hazardous under the “Hazardous
Wastes (Management & Handling) Rules, 1989, amendment 2003” shall be disposed off in
compliance with the procedure given in the rules under the aforesaid act.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Storage Ground surface will be concreted to prevent any leaks or spills from storages
seeping into the ground.
• The impervious bund/ secondary containment system such as bund shall be as per strandard
specifications. If more than one container is stored, the system must be capable of storing
110% of the biggest container’s capacity or 25% of their total capacity, whichever is the
greater.
• Suitable firefighting equipment will be provided in close proximity to the storage areas.
• Spill containment and clean-up materials (Spill clean-up kits) will be kept to deal with
emergency spills while storage and transportation. They usually consist of equipment to
contain and absorb spills and will typically include absorbent granules, sand bags,
absorbent booms, absorbent pads, polythene sheeting, and polythene sacks.
• All maintenance and servicing activities will be performed in an appropriately constructed
maintenance and servicing floor in order to prevent spills from seeping into the ground.
• Prior to unloading the content from a fuel, chemical or oil tank or loose barrel, hoses and
connections will be checked to ensure that they are free from defects. Holding tanks will also
be checked to ensure they are effectively grounded.
• Personnel handling such products will be provided with suitable and appropriate personal
protective equipment, which they will be required to wear at all times. Contractor (s) shall
provide training to their persons involved with the storage, handling, transport, decanting and
disposal of hazardous chemicals in areas under their control.
• Resources, to the extent practical, will be preserved in their existing condition. Construction
activities shall be confined to areas necessary to conduct the Work as required by the
Contract schedule, plans, specifications, or other documents. Environmental protective
measures and procedures shall be provided to limit habitat disruption and mitigate
environmental damages that may occur during construction or other activities.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Contractor (s) employees shall not deface, injure, or destroy shrubs, grass, or other
landscaping in the project or surrounding area, or remove or cut same without advance
written permission from PMC/ Client.
8.13 Energy Management
The CONTRACTOR shall use and maintain equipment so as to conserve energy and shall be
able to produce demonstrable evidence of the same upon CONSULTANT request.
ii) Use of energy efficient lighting, which uses energy efficient luminaries
iii) Adequate and uniform illumination level at construction sites suitable for the task
iv) Proper size and length of cables and wires to match the rating of equipment
The CONTRACTOR shall design site offices maximum daylight and minimum heat gain. The
rooms shall be well insulated to enhance the efficiency of air conditioners and the use of solar
films on windows may be used where feasible.
Construction shall provide details of safety, pollution control and energy conservation measures
to be undertaken under the project and estimate the cost towards the same. The amount shall be
earmarked in the total project cost towards implementation of all such measures.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
VENDOR’s qualification
VENDOR shall have a valid prequalification certificate. For new VENDORS, the evaluation shall
include HSE criteria to verify VENDOR’s capability to meet Technip’s principles in terms of health,
safety and environment. This shall be done through HSE questionnaire, filled in by VENDOR at
bidding stage and part of the Commercial bid Tabulation.
An audit at vendor premises including a HSE part could be . The audit can be performed by any
project member on the basis of an audit check list or by Project HSE manager if deemed necessary.
CONTRACTOR shall follow up and monitor VENDORS HSE performances throughout the execution
of the work. In case repetitive violations are reported without improvement from the VENDOR
despite notification, Project Procurement and HSE Manager shall decide to perform an audit of
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
VENDOR’s premises. The outcomes of the audit and progress made by VENDOR shall serve the
purpose of VENDOR final evaluation and VENDORS prequalification for future projects.
VENDOR REPRESENTATIVES
CONTRACTOR shall inform VENDOR of the relevant rules to apply and shall guide VENDOR into
their implementation by providing necessary assistance and training.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
In addition to HSE controls mentioned in above part “Operation Control during Construction
phase”, Contractor (s) shall follow following Operation Control during Pre-commissioning and
Commissioning Phases.
Pre-commissioning and commissioning area shall be segregated with barriers / fences and safety
& warning signs from the other units which are still under construction. Colored tape and warning
signs may also be applied where hard barricades are not practical with permission of Owner /
PMC. Access to this commissioning area shall be limited; no person shall be allowed to enter
inside the barricade without authorization by Pre-commissioning and commissioning group such
as a pass card, a sticker, etc. Works in the commissioning area shall be authorized with the Pre-
commissioning and commissioning PTW.
PPE requirement in the Pre-commissioning and commissioning area shall be decided by the
PMC& Contractor (s) HSE Managers with advice of the commissioning manager and client
representative.
All personnel in the area must complete the Pre-commissioning and commissioning safety
training. Trained security guards shall ensure access control.
Contractor (s) HSE team and the Commissioning team shall hold a commissioning HSE training
for all persons who are required to work in the Pre-commissioning and commissioning area
including third party’s personnel. Person who attends the commissioning safety training shall be
recorded, identified by badge, helmet sticker and commissioning pass card.
Emergency Response Plan for Pre-commissioning and commissioning area shall be established
before Pre-commissioning and commissioning activity starts by Client, PMC& Contractor (s) and
shall be reviewed and updated as per the site condition.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Prior to hydro-carbons introduction into the area during the Pre-commissioning and
commissioning stage, mobile phone communication may be allowed to use. However, once hydro-
carbons have been introduced, no mobile phone shall be allowed and all communications shall
use either dedicated land lines or approved intrinsically safe radio systems (Walky-Talky), e.g.
explosion-proof type radios. Spark arrestors shall be provided on the vehicle and engines exhaust
outlet.
Daily Pre-commissioning and commissioning meeting shall be held to address the overall plant
Pre-commissioning and commissioning activities including weekly look ahead, progress,
interfaces, simultaneous work activities, safety, emissions, utilities requirements, security, etc.
Representatives for all related personnel include HSE Manager shall attend this meeting.
The Contractor (s) Commissioning Manager shall issue written Commissioning Notice before main
commissioning activities (e.g. power receive, nitrogen in, hydro-carbon in, main rotating machine
test and in service, etc.) are started in the plant and/or system. The notice shall be sent to the all
related parties, defining the impending change in plant status with enough detail to enable clear
understanding of the nature and location of the changes. Issuing the Commissioning Notice
provides formal notification to all related parties.
Contractor (s) Site HSE managers shall inform this Commissioning Notice to HSE staff (including
night shift staff and medical team).
Client / Contractor (s) shall obtain, as per agreed contract conditions, an authorization from the
State Pollution Control Board as per Rule 6 of Hazardous and Other Wastes (Management and
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Transboundary Movement) Rules, 2016 for handling, storage and disposal of hazardous waste
generated during Construction, Pre-commissioning and Commissioning Phases of this project.
Waste effluent such as waste gas, chemical, oily water, etc. will be generated during
commissioning. These waste effluents shall be controlled by Contractor (s) as per Client and legal
requirements. Dust control shall be accomplished by proper housekeeping. Disposal of the
chemical wastes shall be in accordance with the Client Specification and Legal Requirements.
Permanent drainage system or temporary arrangement shall be ready for use prior to chemical/oil
handling. Flare and oily sewer systems shall be in service prior to Hydro-Carbon Introduction
In case live drain system connect into a construction area drain system, segregation of the drain
system between the construction area and Pre-commissioning and commissioning area is
required to avoid flammable liquid / vapor leakage into the construction area.
During the commissioning and initial start-up phases unusual high sound pressure levels are
generated by the activities, these would include such items as air and steam blowing, safety vent
lifting, machinery runs without complete acoustic enclosures etc. Suitable protection shall be
available and provided to the people expected to work in these effected areas.
Special precautions shall be taken by involving the supervision and direction of the electrical team.
• Inform hazards and area to all related parties in the daily Tool Box Meeting.
• Ensure that the area of the motor solo run shall be taped or barricaded. Suitable Warning
Notice / Signs indicating “Equipment in Service – Keep Away” or “Test Runs in progress
– Keep Away” shall be positioned to cover all points of access.
• Ensure that motor tests shall be monitored continuously and not be left
unattended under any circumstances.
• Ensure licensed electrician, trained & competent personnel are only involved in the
Electrical Activity.
• The Machinery is checked for the unguarded rotating part. & precaution taken to avoid
any injury by guarding the same or barricading.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Management of pressurized system and air blow discharge point are the most essential. Special
precautions shall be taken.
• Follow Permit to work system.
• Barricade the exit blow out points and put a warning notice indicating “Air
Blowing is in Progress – Keep Away”
• Barricade and put a warning sign around the pressurized area.
• Provide protection for facilities around discharge points.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Ensure that hose couplings and any other temporary connection or pipe spool shall be
properly secured.
• Confirm line and equipment being adequately supported
• Air blowing generates big noise near the blow point, so ear protection shall be worn by
operator and persons working in vicinity.
• Ensure trained & experienced personnel are only involved in the Activity.
• Ensure that design pressure of line is checked and pressurization of line is maintained well
below design pressure.
• The Air pressurization system is checked, for proper connection, pressure gauges,
leakage from the flanges etc.
• The Card Board Blasting event is communicated using check/ clearance sheet.
• Ensure personnel are provided with Safety Helmet, Safety Shoes, Ear Plugs, Dust Mask, &
Safety Goggles.
• During card board blasting, compressed gas will be suddenly released with high energy and
foreign particles may come out along with gas, so special precaution to be taken care.
• All unwanted materials to be cleaned and all the temporary arrangement to be removed for
original reinstatement after completion of the activity.
Management of water discharge point is the most essential. Special precautions shall be taken.
• Follow Permit to work system.
• Inform hazards and area to all related parties in the daily Tool Box Meeting.
• Barricade the discharge points and put a warning notice indicating “Water flushing is in
Progress – Keep Away
• Provide cover or protection to equipment around discharge points.
• Proper positive isolation for other equipment and lines shall be ensured.
• Ensure that all electrical equipment, welding machines, temporary electrical supply systems
etc. shall be covered or removed from the area.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Ensure that sewer system or surface drains must be capable of disposing of the water to avoid
any water build-up in the area.
• Ensure that soft soil shall be protected with planks or sheeting to minimize erosion.
• Ensure that hose couplings and any other temporary connection or pipe spool shall be
properly secured.
• Drain the residue water and dry the line if required.
• Waste water / Waste disposal shall be as per legal and client requirements.
• Equipment/ materials below the flushing point shall be covered
• Inform hazards and area to all related parties in the daily Tool Box Meeting.
• Barricade the discharge points and put a warning notice indicating “Steam blow in Progress –
Keep Out”.
• Open all drain valves on the steam header and/or steam traps to drain condensate
until warming up completion.
• Provide permanent or temporary insulation at flange and pipe surface if required.
• Flow the steam slowly for warming up.
• Check line and shoes to avoid abnormal thermal expansion during warming up and steam
blowing.
• Utilize silencer or silent blow system at the blowing point, if required.
• Ensure that no person is working in vicinity of the vents and drains during steam blowing
operations.
• Proper positive isolation for other equipment’s shall be ensured.
• Leak test of the system shall be conducted prior to charging of pressurized steam.
• Until the warming up all drains must be opened.
• Provide adequate pressure in lines.
• Provide minimum bends in pipes to minimize Water hammering.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Ear protection shall be worn by operator and persons working in vicinity. Reduce the fluid
velocity/ flow during venting.
• Ensure F- keys / Valve handle keys readily available to operate the valves.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Ensure that the pipe shall be adequately ventilated with atmospheric air. Fans or air movers
shall be used.
• Ensure that a Safety Watcher shall be stationed at the entry point at all times in contact by
radio with those entering.
• Ensure that internal means of safe access shall be provided to inspect vertical sections.
• Provide physical/positive isolation to avoid the unexpected introduction of nitrogen, hydro-
carbon, etc. into the system from its adjacent system(s) where has been in service.
• Check temperature in the pipe.
Characteristic of Chemical is the most essential. Special precautions shall be taken involving the
supervision and direction of the commissioning department.
• Chemical shall be handled in according with MSDS instructions. Display MSDS at storage
area.
• Train personnel for safe handling of chemicals.
• Barricade the area, display warning signs. Restrict unauthorized entry near chemical
storage, tanks & chemical pump.
• Secondary containment shall be provided for chemical storage & handling systems.
• Provide eye wash and emergency shower.
• Confirm line and equipment being adequately supported.
• Check all flanges, valves/ pipeline leakage shall be monitored.
• Leak test of the system shall be conducted prior to charging.
• Inspect temporary hoses & connections prior to use.
• Do not attend leakages without proper PPE. Wear PPE as per MSDS. Provide Spill Kit.
• Suitable type of fire extinguisher shall be provided.
• Ensure that chemical drainage system should be ready for use for spillage. Other adjacent
drainage system where is not ready for use shall be plugged to prevent the system from
contamination with the chemical. Provide temporary curved area if drainage system is not
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
available.
• Stand-by absorber or counteragent.
• Establish emergency actions (emergency car, medical service, etc.).
• Disposal of the chemical wastes shall be in accordance with the Client Specification
and Legal Requirements.
• Ensure trained & experienced personnel are only involved in the Activity.
• Proper Permit to work system is implemented prior to commissioning the Heater.
• The Heater is charged under supervision in line with the manufactures / process
Manual and The Stand by firefighting personnel is recommended.
• Establish LOTO system for electrical safety control and isolate all circuits which should not be
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
energized.
• Inform activities to all related parties in daily Tool Box Meeting.
• Record valve position requirement and control the position by specific person.
9.15 Rotating Machine Run
Risk of personnel injury and equipment damage will be extremely increased during rotating machine
running. Special precautions shall be taken involving the supervision and direction of the
commissioning department.
• Follow PTW.
• Inform hazards and area to all related parties in the Daily Tool box Meeting.
• Ensure that the rotating machine shall be completely assembled including the coupling guard.
• Ensure that all necessary documents and certificates shall be confirmed and approved by the
Commissioning Group and Owner.
• Ensure that the area of the pump or compressor to be tested shall be taped or barricaded.
Suitable Warning Notice / Signs indicating “Equipment in Service – Keep Out” or “Test Runs
in progress – Keep Out” shall be positioned to cover all points of access.
• Ensure that the live line in the pump or compressor circuits shall be clearly identified with ‘Live
Line’ notices and the test system shall be positively isolated from other sections of the plant.
• Ensure that machinery tests shall be monitored continuously and not be left unattended under
any circumstances.
• Isolate motor/turbine properly from its power source after run.
• Ensure proper earthing to the equipment’s.
High energy fluid is in the system during Tightness Test. Special precautions shall be taken involving
the supervision and direction of the commissioning department.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Follow PTW.
• Ensure that the required PPE should be worn.
• Ensure that suitable communication such as two way radios are ready for use.
• Inform hazards and area to all related parties in the daily Tool Box Meeting.
• Barricade the area and put a warning notice indicating “Tightness Test in Progress –
Keep Out”.
• Line for testing is identified checked for the fittings, Joints, etc. secured at the ends and shall
be clearly identified with ‘Live Line’ notices.
• Ensure that test system shall be isolated from other sections of the plant.
• Water once used for service testing it shall be disposed-off safely if necessary.
• Separate calibrated gauges to be provided for pressuring piping & equipment.
• Nip points of Pressure machine shall be guarded properly.
• The pressurization system is checked, for proper connection, pressure gauges etc.
• Flanges and fasteners of the recommended size and strength to withstand the test pressure
shall be used.
• Separate calibrated gauges provided for pressuring piping & equipment.
• Hoses shall be of proper rating, tested & certified.
• Ensure necessary precautions, stepwise increase in pressure.
• Close supervision and trained personal required for Proof Testing / Leak Testing jobs.
• The gas used as test fluid, if not air, shall be nonflammable and nontoxic.
• Ensure that depressurizing point must be surrounded with a barricade or caution tape, If the
tightness test uses nitrogen as pressurization medium.
• Other activities in area shall be stopped during leak testing.
Risk of asphyxiation will be extremely increased after Nitrogen Introduction. Special precautions
shall be taken involving the supervision and direction of the commissioning department.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Inform hazards and area to all related parties in the daily Tool Box Meeting.
• Barricade the area and put a warning notice indicating “Nitrogen Purge in Progress –
Keep Away
• Ensure that the N2 contained line shall be clearly identified with ‘Live Line’ notices.
• Ensure that Nitrogen Hose color coding is followed.
• Ensure that N2 purging and blanketing system shall be positively isolated by spade from other
sections of the plant.
• Ensure that all construction work should be restricted as per work permit Procedure.
• Ensure that confined space entry permit shall be strictly controlled during/after inserting with
N2.
Potential Risk is extremely increased after Hydro-Carbon Introduction into the system because
flammable explosive and/or toxic fluid exists in the system. The Commissioning Manager and the
Site HSE Manager must confirm and agree that the system is safe and suitable to introduce hydro-
carbon. Pre Startup Safety Review (PSSR) shall be conducted to ensure that the plant or system
and facilities can proceed for start-up / initial operation of the plant or part of plant safely.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
in place.
• Ensure that emergency response plan in place and emergency drill conducted.
• Ensure that site public address system shall be in service.
• Ensure that site safety rules regarding smoking shall be amended within the effected safety
areas such that smoking is only allowed in specifically dedicated and tested locations.
• Ensure that hot work permits shall be required for any potential ignition producing activities
within the effected designated safety areas.
• Provide suitable PPEs.
• Ensure that the use/carrying of mobile phone shall not be allowed within the designated safety
areas nor shall ignition materials such as lighters or matches.
• Ensure that use of vehicles and temporary generators shall be restricted and strictly controlled.
• Ensure that waste gas system (flare, vent stack, incinerator, etc.) and drainage system (oily
water sewer, waste water treatment, etc.) shall be in service.
• Ensure that Specific Toxic Gas Detection System shall be in service and fully operational.
• Ensure that personal multi gas detectors shall be worn by personnel working within high
hazard areas.
• Ensure that toxic gas leak response plans shall be in place and fully operational.
• Ensure that training for the hazards of Specific Toxic Fluid and required alarm responses shall
be provided to all personnel working within the designated safety areas.
• Ensure that wind socks, muster points, safety shelters shall be identified and available.
• Ensure that gas mask or air mask arrangement shall be considered.
• Ensure antidote / first aid measures suggested in MSDS are in place and people are trained
for their use / application.
9.20 Feed intake in to the Plant
• Ensure all personnel trained in the Commissioning activity are only involved in the Job.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Spades are applied to separate live systems from systems under construction or
commissioning. Once hydro-carbon or nitrogen is introduced into the system, live systems
shall be physically isolated from non-live system, and isolation points shall be strictly
controlled. Isolation spades shall be controlled as per isolation procedure.
Access to CCR and the rooms where control systems are stored shall be limited and controlled
by the Commissioning Manager. Personnel working in the CCR shall have taken the safety
induction and any special training relating to the CCR building for emergency response and
evacuation. Communications for both commissioning and operations shall use radio system
compatible intrinsically safe equipment. Mobile phone use is not permitted in the CCR building
to avoid any effects to control system. PTW shall be issued and authorized by the
Commissioning Manager before starting the work in CCR and the rooms where equipment
related to control system.
9.23 HVAC Room
HVAC system is important to protect equipment/computers such as DCS and electrical panel
and comfortable work in the building. Access to HVAC Rooms shall be limited and controlled
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
by HVAC representative.
PTW for the HVAC is to be issued and authorized by the HVAC responsible personnel before
starting the work in HVAC room. Personnel working in the HVAC Room shall have taken the
safety induction and any special training relating to the HVAC for emergency action and
evacuation.
All vehicles and engines entering in pre-commissioning & commissioning area shall be fitted
with Indian standard complied spark arrester on all exhausts. All vehicles driven on site shall
be maintained in roadworthy condition and be registered with the appropriate authority in
accordance with the relevant laws and regulations. Vehicle shall have the RC book, valid
fitness certificate, transport permit, PUC and Insurance document before entering into the site.
Each driver of these vehicles shall hold a valid driving license authorizing him / her to drive
that class of vehicle and sufficient experience of driving. Only vehicles necessary during pre-
commissioning & commissioning operation shall be permitted to enter the construction site.
Motorcycles/three wheeler shall not be permitted. Driver to follow the speed limit e.g. below
20km/h within the site.
Practice preventive maintenance of vehicles and machines and maintain associated records
and documents.
10. PENALTY
The CONTRACTOR shall adhere consistently to all provisions of HSE requirements. In case of
non–compliance or continuous failure in implementation of any of HSE provisions; OWNER
/CONSULTANT may impose stoppage of work without any Cost and Time implication to OWNER
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
and / or impose a suitable penalty for non – compliance with a notice of suitable period.
All fatal accidents and other personnel accidents shall be investigated by a team of
CONTRACTOR’s senior personnel for root cause and recommend corrective and preventive
actions. Findings shall be documented and suitable actions taken to avoid recurrences shall be
communicated to OWNER /CONSULTANT. OWNER / CONSULTANT shall have the liberty to
independently investigate such occurrences and CONTRACTOR shall extend all necessary held
and co– operation in this regard
Any violation of applicable safety , health and environment related norms results in penalty. A
detailed listed is attached in Attachment # xxxx.
OWNER/ CONSULTANT shall have the right to deduct charges for any other unsafe act and or
condition depending upon the gravity of the situation on a case-to-case basis.
The CONSULTANT shall have the right to stop the work at his sole discretion, if any unsafe
condition or unsafe act is found . In such cases, the CONTRACTOR shall be informed in writing
about the nature of hazards and possible injury / Incident. The CONTRACTOR shall not proceed
with the work until he has complied with each direction to the satisfaction of CONSULTANT.
The CONTRACTOR shall not be entitled for any damages / compensation for stoppage of work,
due to safety reasons and the period of such stoppage of work shall not be taken as an extension
of time for Completion of the Facilities and will not be the ground for waiver of levy of liquidated
damages
CONTRACTOR has developed a broad range of HSE incentive programs designed to motivate
its employees and Subcontractors to maintain a high level of HSE performance. CONTRACTOR
HSE recognition programs are administered at two levels.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
At company level through the designation of the ‘CONTRACTOR of the Month’ for the Sub-
contractor that has demonstrated the best safety performance over the previous month. At
employees level through the designation of the employees/crews of the week.
Other ways to increase H&S awareness will include: Bulletin boards illustrating safe man-hours
worked Employee Safety awards dinners Hard-hat decals for safe performance . CONTRACTOR
hats and similar items given to top safety performers. Subcontractor Safety awards ceremonies
where similar awards are presented to Sub-contractor personnel.
In addition, CONTRACTOR construction and HSE management will randomly select individuals
each week, and find where this person are working.
The person will be visited; if he is working safely (all PPE and similar) and can answer two simple
HSE related questions then a small prize will be awarded. In addition, the supervisor of each
person will also receive an award. If the person is not working safely or cannot answer the
questions, then he and his supervisor will be educated and positively reinforced but no award
made.
The CONTRACTOR shall comply Social Accountability that protect Human Rights, and aims to
develop, to monitor and to encourage a policy of protection of Workers’ Rights. It defines precise
requirements regarding the following themes:
• Child Labor
• Forced Labor
• Health and Safety
• Freedom of Association and Right to Collective Bargaining
• Discrimination
• Disciplinary Practices
• Working hours
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
• Remuneration
The Contractor shall submit a comprehensive Health, Safety and Environment Plan or programme
for approval by Owner/PMC prior to start of work. The Contractor shall participate in the pre-start
meeting with Owner/PMC to finalize HSE Plans which shall including the following:
Contractor shall implement approved Health, Safety and Environment management programme.
Contractor shall also ensure the following :
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
To arrange workmen compensation insurance, registration under ESI Act, third party liability
insurance, registration under BOCW Act, etc, as applicable.
To arrange all HSE permits before start of activities (as applicable), like permits for hot work,
working at heights, confined space, Radiation Work Permit, Demolishing/ Dismantling Work
Permit, Permit for erection/modification & dismantling of scaffolding, Permit for heavy lift/critical
erection, Permit for energy Isolation & De-isolation” ,storage of chemical / explosive materials &
its use and implement all precautions mentioned therein. In this regard, requirements of Oil
industry Safety Directorate Standard No. Std -105 "Work Permit Systems” shall be complied with
while working in existing Oil or Gas processing plants. List of the persons involved shall be
maintained as annexure to the work permit issued for a particular activity.
To submit, timely, the completed checklist on HSE activities, Monthly HSE report (as attached) is
compulsory wherever the facility is available else a hard copy is to be submitted), accident/
incident reports, investigation reports etc. as per Owner/PMC requirements.
Compliance of instructions on HSE shall be done by Contractor and informed urgently to
Owner/PMC. that his top most executive at site attends all the Safety Committee/HSE meetings
arranged by Owner/PMC and carries out safety walk through regularly. Only in case of his absence
from site that a second senior most person shall be nominated by him, in advance, and
communicated to Owner/PMC for performing the above tasks.
Display at site office and at prominent locations HSE Policy, caution boards, list of hospitals,
emergency services available, safety signs like Men at work, Speed Limits, Hazardous Area,
various do’s & don’ts, etc.
Identify, assess, analyze & mitigate the construction hazards & incorporate relevant control
measures before actually executing site works. (HIRAC = Hazard Identification, Risk Analysis and
Control).
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
machinery (stationary & mobile) before being used at site and also at periodical interval, through
own resources and also by 3rd party competent agencies (as deemed fit in statutes). Records of
such test, examination etc. shall be maintained & shall be submitted to Owner/PMC as & when
asked for.
Carryout audits/inspection (internal & external) at his works as well as sub-contractor works as
per approved HSE plan/procedure/programme & submit the compliance reports of identified
shortfalls for Owner/PMC review.
Arranging HSE training for site workmen (of his own & sub-contractors) through internal or external
faculty at periodical intervals. Assistance & cooperate during HSE audits by Owner/PMC or any
other 3rd party and submit compliance report.
Generate & submit of HSE records/report as per this specification. apprise Owner/PMC on HSE
activities at site regularly. Carry-out all dismantling activities safely, with prior approval of
Owner/PMC representative.
The Contractor shall ensure that “Hot works” and painting works do not continue at the same place
/ location at project site for which chance or probability of “fire” incident exists.
The contractor shall review the HSE management system of the sub-contractors in line with the
requirements given in this specification. The contractor shall be held responsible for the
shortcomings observed in the HSE management system of the sub-contractor(s) during execution
of the job.
ATTACHMENTS
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
1. Small size Roller Bandages, 1 Inch Wide (Finger Dressing small) 6 Pcs.
2. Medium size Roller Bandages, 2 Inches Wide (Hand & Foot Dressing) 6 Pcs.
3. Large size Roller Bandages, 4 Inches Wide (Body Dressing Large) 6 Pcs.
4. Large size Burn Dressing (Burn Dressing Large) 4 Pkts.
5. Cotton Wool (20 gms packing) 4 Pkts.
6. Antiseptic Solution Dettol (100 ml.) or Savlon 1 Bottle
7. Mercurochrome Solution (100 ml.) 2% in water 1 Bottle
8. Ammonia Solution (20 ml.) 1 Bottle
9. A Pair of Scissors 1 Piece
10. Adhesive Plaster (1.25 cm X 5 m) 1 Spool
11. Eye pads in Separate Sealed Pkt. 4 pcs.
12. Tourniqut 1 No.
13. Safety Pins 1 Dozen
14. Tinc. Iodine/ Betadin (100 ml.) 1 Bottle
15. Polythene Wash cup for washing eyes 1 No.
16. Potassium Permanganate (20 gms.) 1 Pkt.
17. Tinc. Benzoine (100 ml.) 1 Bottle
18. Triangular Bandages 2 Nos.
19. Band Aid Dressing 5 Pcs.
20. Iodex/Moov (25 gms.) 1 Bottle
21. Tongue Depressor 1 No.
22. Boric Acid Powder (20 gms.) 2 Pkt.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
❖ The Gas Cylinder Rules and the Static & Mobile Pressure Vessels Rules
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
1. The Law & Safety – Statutory Requirement / Applicable statutes / Duties of employer /
employee
2. Policy & Administration – Why HSE? / Duties & Responsibilities of Safety Personnel at
project site / Effect of incentive on accident prevention
3. HSE & Supervision – Duties of Supervisor / HSE integrated supervision / Who should be
held responsible for site accidents?
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
10. Electricity & Safety – ELCB / Fuse / Powered tools / Project illumination
14. Cranes & Other Lifting machinery – Legal requirements vis-à-vis essential safety
requirements.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
17. Working at Heights – Use of ladder / Work on roofs / Scaffolds / Double harness lanyard
Life savings. Safety Nets / Floor openings / line / Fall arrest
4. PENALTY TABLE
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
20 Non-compliance while confined space work activity Rs. 25,000/- per occasion
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
39 Failure to implement HSE promotional activities i.e.. Rs. 5,000/- per occasion
HSE Campaign or event celebration or implementation
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
HSE Steering Committee Monthly & as High Mgmt (Site and/or office) and HSE Mgrs of
Meeting required Contractor and client
Weekly Contractor Mgmt Weekly Attendance of HSE M in the weekly Contractor Mgmt
Meeting Meeting
Contractor HSE Dept. Every 2 weeks All Contractor HSE Dept members
meeting
Task Instructions Daily Supervisors, Foremen, Workers, HSE SVs
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Equipment (type ?)
At bringing onto Site by Sub-contractor’s’ inspectors
Inspection
Equipment Pre-use
Daily by operators/users of equipment/facilities
Inspection
LPI System (loss by CM, Const. SVs, and others assigned HSE
Weekly
prevention inspections) Contractor’s staff
Weekly areas
walkthroughs and By subcontractors / contractor / client Mgrs and HSE
Weekly
weekly management staff
Site walkthrough
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
4) Work Permit Daily or as for all work required locations by PTW system
required
5) Sanitation & Health Service
Monthly HSE Equipment Inspection Monthly from Inspectors to HSE M & CMs
Report
7) Housekeeping
Work Site areas Daily by every work crew after day’s work
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Movement of May cause Barricade the excavated area with proper lighting
vehicles/ cave-in or arrangements
equipment’s slides. Maintain at least 2m distance from edge of cut
close to the edge Persons may get and use stop blocks to prevent over-run
of cut. buried. Strengthen shoring and strutting
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Scattering of stone Can hurt people Use PPE like goggles, face mask, helmets etc.
pieces in atmosphere
Rock excavation Entrapping of persons/ May cause severe Barricade the area with red flags and blow siren
by blasting animals. injuries or prove before blasting.
(Contd) fatal
Misfire May explode Do not return to site for atleast 20 minutes or unless
suddenly announced safe by designated person.
Piling Work Failure of pile- driving Can hurt people Inspect Piling rigs and pulley blocks before the
equipment beginning of each shift.
Noise pollution Can cause Use personal protective equipment’s like ear plugs,
deafness and muffs, etc.
psychological
Extruding rods/casing imbalance.
Can hurt people Barricade the area and install sign boards Provide
first-aid
Working in the vicinity Can cause Keep sufficient distance from Live-Electricity as per
of 'Live- Electricity' electrocution/ IS code.
Asphyxiation Shut off the supply, if possible
Provide artificial/rescue breathing to the injured
(B) Air pollution by cement May affect Wear respirators or cover mouth and nose with wet
CONCRETING Respiratory cloth.
Handling of ingredients Hands
System may get Use gloves & other PPE.
injured
Protruding Feet may get Use Provide platform above reinforcement for
reinforcement rods. injured movement of workers.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
Earthing of Can cause Ensure earthing of equipment’s and proper
electrical mixers, electrocution/ functioning of electrical circuit before
vibrators, etc. asphyxiation commencement of work.
not done.
Passage to work Improperly tied and Ensure the stability and strength of passage
place designed before commencement of work.
props/planks may Do not overload and stand under the passage.
collapse
(C) Curtailment and Persons may get Use PPE like gloves, shoes, helmets, etc. Avoid
REINFORCEMEN binding of rods injured usage of shift tools
T Carrying of rods Workers may get Provide suitable pads on shoulders and use
for short injured their hands safety gloves.
distances/at and shoulders. Tie up rods in easily liftable bundles Ensure
heights proper staging.
Checking of Rods may cut or injure Use measuring devices like tape, measuring
clear distance/ the fingers rods, etc.
cover with hands
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Hitting projected Persons may get Use safety shoes and avoid standing
rods and injured and fell down unnecessarily on cantilever rods Avoid wearing
standing on of loose clothes
cantilever rods.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Welding of tanks, Explosion may Empty & purge them before welding
container or pipes occur Never attach the ground cable to tanks, container
storing flammable or pipe storing flammable liquids
liquids Never use LPG for gas cutting
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Loss of Radio Same as above Try to locate with the help of Survey Meter. Inform
isotope BARC/AERB (*)
(F) ELECTRICAL Short circuiting Can cause Use rubberized hand gloves and other PPE
INSTALLATION Electrocution or Fire Don't lay wires under carpets, mats or door ways.
ANDUSAGE Allow only licensed electricians to perform on
electrical facilities
Use one socket for one appliance
Ensure usage of only fully insulated wires or cables
Don't place bare wire ends in a socket
Ensure earthing of machineries and equipment’s Do
not use damaged cords and avoid temporary
connections
Use spark-proof/flame proof type field distribution
boxes.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
(G) FIRE Small fires can Cause burn injuries In case a fire breaks out, press fire alarm system
PREVENTION become big and may prove fatal and shout "Fire, Fire"
AND ones and may Keep buckets full of sand & water/ fire
PROTECTION spread to the extinguishing equipment near hazardous
surrounding locations
areas Confine smoking to 'Smoking Zones' only. Train
people for using specific type of fire fighting
equipment’s under different classes of fire
Keep fire doors/shutters, passages and exit doors
unobstructed
Maintain good housekeeping and first-aid boxes
(for details refer Appendix-B)
Don't obstruct assess to Fire extinguishers.
Do not use elevators for evacuation during fire.
Maintain lightening arrestors for elevated
structures
Stop all electrical motors with internal combustion
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Short circuiting Same as above Can Don't lay wires under carpets, mats or door ways
of electrical cause Electrocution Use one socket for one appliance.
system Use only fully insulated wires or cables Do not
allow open/bare connections Provide all
connections through ELCB
Ensure earthing of machineries and equipment’s
(H) VEHICULAR Crossing the Personal injury Obey speed limits and traffic rules strictly Always
MOVEMENT Speed Limits expect the unexpected and be a defensive driver
(Rash driving) Use seat belts/helmets
Blow horn at intersections and during overtaking
operations.
Maintain the vehicle in good condition
Adverse Same as above Read
Do notthe road ahead
overtake and ride
on curves, to theand
bridges leftslopes
Keep the
weather wind screen and lights clean Do not turn at speed.
condition Recognize the hazard, understand the defense
and act correctly in time.
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
Consuming Same as above Alcohol and driving do not mix well. Either
alcohol before choose alcohol or driving.
and during the If you have a choice between hitting a fixed object
driving or an on-coming vehicle, hit the fixed object
operation Quit the steering at once and become a
passenger. Otherwise take sufficient rest and
then drive.
Do not force the driver to drive fast and round the
clock.
Do not day dream while driving
Falling objects/ May prove fatal Ensure effective braking system, adequate
Mechanical visibility for the drives, reverse warning alarm..
failure Proper maintenance of the vehicle as per
manufacturer instructions
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
(I) PROOF Bursting of May cause injury Prepare test procedure & obtain
TESTING piping Collapse and prove fatal CONSULTANT/Owner's approval
(HYDROSTATI of tanks Provide separate gauge for pressurizing pump
C/PNEUMATIC Tanks flying off and piping/equipment
TESTING) Check the calibration status of all pressure
gauges, dead weight testers and temperature
recorders
Take dial readings at suitable defined intervals
and ensure most of them fall between 40-60% of
the gauge scale range
Provide safety relief valve (set at pressure slightly
higher than test pressure) while testing with air/
nitrogen
Ensure necessary precautions, stepwise increase
in pressure, tightening of bolts/nuts, grouting, etc.
before and during testing
Keep the vents open before opening any valve
while draining out of water used for hydro-testing
of tanks.
Pneumatic testing involves the hazard of released
energy stored in compressed gas. Specific care
must therefore be taken to minimize the chance
of brittle failure during a pneumatic leak test.
Test temperature is important in this regard and
must be considered when the designer chooses
the material of construction.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
A pressure relief device shall be provided, having
a set pressure not higher than the test pressure
plus the lesser of 345 KPa (50 psi) or 10% of the
test pressure.
The gas used as test fluid, if not air, shall be
nonflammable and nontoxic.
(J) Person can fall May sustain severe Provide guard rails/barricade at the work place
WORKING AT down injuries or prove Use PPE like full body harness, life line, helmets,
HEIGHTS fatal safety shoes, etc.
Obtain a permit before starting the work at height
above 3 meters
Fall arrest and safety nets, etc. must be installed
Provide adequate working space(min. 0.6 m)
Tie/weld working platform with fixed support Use
roof top walk ladder while working on a slopping
roofs
Avoid movement on beams
May hit the Keep the work place neat and clean Remove the
scrap/material scrap immediately
stacked at the
ground or in
between
Material can fall May hit the workers Same as above plus
down working at lower Do not throw or drop materials or equipment from
levels and prove height. I.e. do not bomb materials
fatal All tools to be carried in a tool-kit Bag or on
working uniform Remove scrap from the planks
Ensure wearing of helmet by the workers working
at lower levels
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Overloading Same as above Safe lifting capacity of derricks and winches written on them
of lifting shall be got verified
equipment’s The max. safe working load shall be marked on all lifting
equipment’s
Check the weight of columns and other heavy items painted on
them and accordingly decide about the crane capacity, boom
and angle of erection
Allow only trained operators and riggers during crane operation.
Overhead Can cause Do not allow boom or other parts of crane to come within 3m
electrical electrocution and reach of overhead HT cables Hook and load being lifted shall
wires fire preferably remain in full visibility of crane operators.
(M) Person can Person May Provide guard rails for working at height
SCAFFOLDI fall down sustain severe Face ladder while climbing and use both hands. Ladders shall
NG, injuries and extend about 1m above landing for easy access and tying up
FORMWORK prove fatal purpose
AND LADDERS Do not place ladders against movable objects and maintain
base at 1/4 unit of the working length of the ladder.
Suspended scaffolds shall not be less than 500 mm wide and
tied properly with ropes
No loose planks shall be allowed
Use PPE, like helmets, safety shoes, etc
Failure of Same as above Inspect visually all scaffolding materials for stability and
scaffolding anchoring with permanent structures.
material Design scaffolding for max. load carrying capacity.
Scaffolding planks shall not be less than 50X250 mm full
thickness lumber or equivalent. These shall be cleated or
secured and must extend over the end supports by at least
150mm and not more than 300mm
Don't overload the scaffolds
Do not splice short ladders to make a longer one. Vertical
ladders shall not exceed 6m.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Material can Persons working Remove excess material and scrap immediately Carry the tools
fall down at lower level in a tool-kit bag only
gets injured Provide safety nets
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
TYPE OF EFFECT OF
ACTIVITY PREVENTIVE MEASURES
HAZARD HAZARD
(N) Personal Can cause injury or Do not take rest inside rooms built for welding
STRUCTU negligence and casualty machines or electrical distribution system.
R AL danger of fall Avoid walking on beams at height
WORKS Wear helmet with chin strap and full body harness
while working at height.
Use hand gloves and goggles during grinding
operations
Cover or mark the sharp and projected edges Do not
stand within the operating radius of cranes
Lifting/ slipping Same as above Do not stand under the lifted load
of material Stack properly all the materials. Avoid slippage during
handling
Control longer pieces lifted up by cranes from both
ends
Remove loose materials from height Ensure
tightening of all nuts & bolts
(O)PIPELIN Erection/ Can cause injury Do not stand under the lifted load
E WORKS lowering failure Do not allow any person to come within the radii of
the side boom handling pipes
Check the load carrying capacity of the lifting tools &
tackles
Use safe Load Indicators Use appropriate PPEs
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
INCIDENT REPORT
1. GENERAL INFO
INCIDENT
Company Incident Contractor Incident
OWNERSHIP*
PERSON IN CHARGE
2. FACTS
RESPONSIBLE REPORTING
CLIENT*
CENTER
YES NO
INCIDENT
Access / Egress AUTHORITIES INFORMED If Yes, who?
CATEGORISATION
3. CLASSIFICATION
WORK ACTIVITY *
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
ACTIVITY *
Equipment damage
EXPERIENCE IN POSITION
PART OF BODY HARMED*
(days)
EXPERIENCE ON
POSITION*
INSTALLATION /SITE (mths)
3.2 – ENVIRONMENT
ENVIRONMENTAL
INCIDENT CLASSIFICATION Please select
*
DESCRIPTION *
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
PRIMARY EXTHINGUSHING
FIRE TYPE * Please select
SYSTEM
DESCRIPTION
4. LOSS POTENTIAL *
POTENTIAL RECURRENCE/SEVERITY POTENTIAL RISK
Potential recurrence: A B C D E R Low (1- R Medium (16- R High (64-
Severity: 1 2 3 4 5 8) 32) 256)
5. IMMEDIATE CAUSES – Report immediate causes at first instance. Consult the following list and describe more as needed.
Check below which causes best indicate reason for existence of acts and/or conditions identified. Add other causes if not
listed. Why it happened? – Which condition was under-standard? - Generally more than one.
PEOPLE ORGANIZATION
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Used faulty / defective tools / equipment Leakage (fuel, radiation, chemical, gas) etc
16P 31T
Worked on equipment in operation / live Plant / equipment status was not correct
17P 32T
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Immediate CAUSES - Report the immediate causes and describe more if needed
6. UNDERLYING CAUSES – Which specific human factor or work factor have leaded to immediate causes (at least one for
each immediate cause)? – Why that act or condition was present? - The root causes shall be removed by an action plan.
PEOPLE ORGANISATION
Lack of attention / due care / poor work practice Inadequate planning / risk assessment
P6 O29
Poor decision-making / judgment Lack of / ineffective job plans (toolbox talks etc) /
P14 O37 ptw
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Excessive wear & tear of tools / equipment Poorly controlled contractors / external people
T17 O41
Ineffective fire / explosion / radiation / chemical / Insufficient / restricted access & exits
T22 electrical protection E46
Underlying CAUSES - Report the Underlying causes and describe more if needed
7. 7. ROOT CAUSES– Report the Root Causes selecting the basic categorization and detailing describing the root causes
identified during the investigation.
P People O Organization
T Technology E Environment
Root CAUSES - Report the Root causes and describe more if needed
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
8. 8. CORRECTIVE ACTIONS– Report identified actions to remove root causes and prevent recurrence – Use the following
guideline as needed. Report in sequence of priority. Assign a target time and person/company responsible to complete the
corrective action and give fee-back of completion. Try to be S.M.A.R.T (Specific, Measurable, Achievable, Realistic, Timed)
DUE-
CORRECTIVE ACTION PLAN TO BE EXECUTED BY
DATE
N
TITLE DOCUMENT NAME
O
2
3
10. APPROVAL
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
APPROVED
WRITTEN BY CHECKED BY
REV. DATE STATUS BY
(name) (name)
(name)
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Examining doctor will issue a medical fitness certificate to the candidate. If any abnormality is
observed, it shall be clearly mentioned in fitness certificate. The copy of medical fitness certificate
along with reports will be kept at the site.
N.B. In case of abnormal finding, in consultation with OHA, he will be referred to concerned specialist
for his opinion and / or further investigations like USG, TMT etc.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
B. Fitness Criteria
To declare the candidate fit/temporary unfit / unfit, in all groups, following guidelines will be adopted
for issuance fitness certificate.
1) He/She is advised to
undergo LASIK eye
procedure.
2) Post LASIK power of vision
should be less than -4.0D.
3) Post LASIK retinoscopy
report should be normal.
Severe Obesity (BMI > 35.0) Temp. Unfit Due to severe obesity he is
temporary unfit.
IMPACTS ON CONTROL
SR NO ACTIVITIES ASPECTS
ENVIRONMENT MEASURES
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
PUC / Fitness
Smoke / pollution Certificates / Regular
Maintenance.
Other Special
Vehicle Maintenance requirements based
TRANSPORTATI Noise Pollution on the Material /
3 Equipment being
ON
transported.
IMPACTS ON CONTROL
SR NO ACTIVITIES ASPECTS
ENVIRONMENT MEASURES
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Proper Segregation,
6 PILING Storage and Disposal at
Water & Land approved location
Pollution Periodic maintenance,
proper operation of
equipment
IMPACTS ON CONTROL
SR NO ACTIVITIES ASPECTS
ENVIRONMENT MEASURES
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Castables / Ceramic /
REFRACTORY / Mineral / Glass wool
material / etc. Disposal at authorised
8 INSULATION Land Pollution
location
WORKS
Scrap / Waste Material
Land
Leakage / Splash Proper Operation of
pollutiom/Air
during handling Equipment
pollution
9 PAINTING
Empty paint & thinner Water Pollution Disposal at authorised
Drums, Used brushes,
location
paint soaked dhotis
Land Pollution
Disposal at Authorised
Scrap and waste Water pollution location.
materials, Spillage of and Land
coolant pollution Secondary
10 GRINDING Containment.
Disposal at Authorised
location.
Scrap and waste Land Nuisance /
11 WELDING
materials Pollution
Secondary
Containment.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
IMPACTS ON CONTROL
SR NO ACTIVITIES ASPECTS
ENVIRONMENT MEASURES
Water
Drainage of Fluid used Drained to OWS &
& Pollution/Land
16 for testing then to ETP
pollution
SITE
Disposal of Hazardous Water Pollution Disposed to
CLEARANCE
Waste authorized location.
17 & Land pollution
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
1|P a g e
Guidelines on Personal Protective Equipment (PPE)
INDEX
e) Shuttering works
f) Brick masonry
g) Handling of Battery
2|P a g e
Guidelines on Personal Protective Equipment (PPE)
INDEX
1) Additional PPE to be provided for various activities as per requirement of Job Safety Analysis (JSA), OISD and
Statutory stipulations.
2) Training inputs as required to be given for proper usage, maintenance of PPE.
3) Various EN Standards / BIS codes mentioned are available on line on IOCL CO, HSE website.
This document is strictly for internal circulation of Indian Oil Corporation Limited. No part of this publication can be
reproduced or transmitted in any form or by any means, including electronic or mechanical, photocopying, recording, or any
information storage and retrieval system without permission in writing, from Corporate HSE Department, Indian Oil
Corporation Limited.
3|P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation of PPE Hazard of Not When to be
(Pictorial Display) Against hazard wearing of PPE discard
1 Work at Height ( height I) Safety Shoe (A) The safety shoe shall have Striking Not suitable Exceeding one
> 2 M) Contd... following marking as per IS against for hazards like year from the
15298 ( part -2) : stationary Chemical burns date of first
, electrical use of the
object.
a) size; flash, welding shoe .
Striking by spark and heat sign of crack /
b) manufacturer’s moving object
identification mark; radiation damage .
Stepping on Not suitable if
c) Year of manufacture and
at least quarter; hot object it is necessary Excessive wear
d) License No ( CM/L) Stepping on to minimise
e) IS Mark sharp object electrostatic
As per
charges in the
A Typical specimen of marking. Penetration Manufactures
shortest
Category of Safety Shoe (S3 category) recommendat
possible time .
Water ions.
Not suitable
Category of Safety shoe
penetration for work in
(S1,S2,S3 etc) as required as explosive work
and
per Table 16 of IS 15298 (part area.
absorption.
2) : 2011
(S2 & S3
category)
S1 : Closed seat region,
Antistatic properties , Energy
absorption of seat region
S2 : S1 plus
Water penetration and water
absorption.
S3 : S2 plus
Penetration resistance (S3)
Cleated outsole
4|P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation of PPE Hazard of Not wearing of When to be
(Pictorial Against hazard PPE discard
Display)
Work at Height ( II) Full body Safety 1. The full body harness shall Accidental fall Shall be of no use Sign of
height > 2 M) Harness with energy conform to EN 361 if anchor point / crack /
Contd... absorber : Direct the loads to life line / lanyard damage/
( Alternative -I) Marking on the full body harness shall legs. is not properly stitching
conform to 2.2 of EN 365:1992 and any designed. giving
Lanyard along with 5 text shall be in English. In addition to Keeping body way
Point ( 1 Dorsal + 2 conforming to 2.2 of EN 365:1992 the upright. There should be
Textile loops+ 2 marking shall include the following. proper Webbing
sternal D ring) harness Prevent the neck arrangement for and rope
On the full body harness, a damage for cuts,
to be used for rescue rescue
pictogram to indicate that users tears,
or tower climbing
shall read the information supplied slightly opens the excessive
After accidental
by the manufacturer. breathing way. wear and
fall & before
safety harness damages
Prevents from
becoming
colliding with the If in doubt
effective, the
ground or structure “Throw it
person should not
in case of a fall. Out”
strike ground /
A capital letter “A” at each fall object. (Prevent
Antistatic As per
arrest attachment element; risk of bottoming
characteristics Manufact
out)
The model/type identification mark ures
of the full body harness; recomme
The number of this European ndations
Standard, i.e. EN 361. SAFETY BELT NOT
2. Connector shall conform to EN TO BE USED
362 and Marking on the connector
shall conform to EN 365. The
marking shall include:
5|P a g e
Guidelines on Personal Protective Equipment (PPE)
Work at Height ( A Typical specimen of marking. Marking of major axis strength with gate closed &
height > 2 M) locked.
Contd...
6|P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation of PPE Hazard of Not When to be discard
(Pictorial Display) Against hazard wearing of PPE
Work at Height ( III) Full body Safety Full body harness conforming to IS 3521 may be Accidental fall Shall of no use Sign of crack /
height > 2 M) - Harness with engery allowed in "Green field project" where antistatic Direct the loads if anchor point damage/
Contd... absorber (Alternative safety harness are not required. to legs. / life line / stitching giving
-II) Following marking to be ensured in case of IS Keeping body way
lanyard is not
marked full body Harness.
upright. properly
Prevent the designed. Webbing and
The name, trade-mark or other means of
neck damage rope for cuts,
identification of the manufacturer or the There should be
slightly opens tears,
supplier who is responsible for acting on behalf proper
the breathing excessive wear
of the manufacturer for claiming compliance arrangement
way. and damages
with this standard; for rescue
Prevents from After
Manufacturer’s product identification If in doubt
colliding with accidental fall
information that shall include the “Throw it Out”
the ground or & before safety
manufacturer’s batch or serial number that
structure in case harness
enables the origin of the item to be traced; As per
of a fall. becoming
The year of manufacture; The identity of the Manufactures
effective, the
fibre used as the material of construction; recommendati
person should
Information that states by appropriate means ons
not strike
the intended purpose of each attachment
ground /
element
object.
and to identify specifically those attachment
(Prevent risk of
elements that are designed to be used as part of
bottoming out)
a complete fall arrest system; and
Warning for not to deviate from the
SAFETY BELT
manufacturer’s instructions.
NOT TO BE
A Typical specimen of
Name of marking USED
Manufacture and ISI marked
other details Other details such full body
year of harness are
manufactures , not antistatic
ISI Mark and number batch number etc hence not
recommended
Material used
in running
plants.
7|P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation of PPE Hazard of Not When to be
(Pictorial Display) Against wearing of PPE discard
hazard
Work at Height ( height Energy absorbing lanyard double Energy absorbing lanyard shall conform to Accidental Shall of no use Sign of cut
> 2 M) - Contd... 'Y' Type EN 355 and shall have the following Fall if anchor point / damage
marking : / life line is After every
To be attached to full body harness not properly fall.
at one end and life line at other a) On the energy absorber, a pictogram to As per
designed.
end indicate that users shall read the manufactur
Must if full body harness There should be
information supplied by the es
being used for protection manufacturer (see figure); proper recommend
against fall. arrangement ation.
The total length of a lanyard for rescue
connected to an energy After
absorber (including accidental fall
terminations and connectors)
shall not exceed 2 m. & before safety
harness
A Typical specimen of becoming
b) the maximum length allowed of the effective, the
marking
energy absorber including lanyard; person should
c) the model/type identification mark of
not strike
the energy absorber;
Model / Type and ground /
d) the number of this European Standard,
identification mark object.
i.e. EN 355.
(Prevent risk of
Year of manufacturing
The marking shall conform to EN 365 bottoming out)
and additionally shall include the
EN number following :
8|P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation of PPE Hazard of Not When to be discard
(Pictorial Display) wearing of PPE
Against
hazard
Work at Height ( height IV) Restraint lanyard Lanyard shall conform to EN 354 (latest Accidental Shall be of no Check metal fittings for
> 2 M) - Contd... edition). Connector incorporated in fall - Lets a use if life line sharp edges, excessive
To be secured to lanyard shall conform to EN 362. worker & anchor wear, correct operation and
properly designed travel just points are not distortion.
anchorage Marking on the lanyard shall conform to far enough properly
EN 365 and, in addition, shall include at to reach the designed.
least the following: If in doubt “Throw it Out”
The restraint edge but not To ensure
that fall
lanyards need not a) the maximum lanyard length, in far enough
restraint
have shock accordance with 4.1.6; to fall over lanyards are
absorption element b) the month and year of manufacture. never used
incorporated in for the
them As per EN 365 marking shall include : purpose of
fall arrest
Means of identification, e.g. As per Manufactures
manufacturer’s name, supplier’s recommendations
name, or trademark;
Manufacturer’s production batch or
serial number or other means of
traceability;
Model and type/identification;
Number and year of the document to
which the equipment conforms;
Pictogram or other method to
indicate the necessity for users to
read the instructions for use.
Name of manufacture A Typical specimen of marking
Pictogram
9|P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not wearing of When to be discard
of PPE PPE
(Pictorial Display) Against hazard
Work at Height ( V) Rope Grab (in Rope grab shall conform to EN 353-2 : Accidental fall Shall be of Check metal fittings for
height > 2 M) - case of vertical 2002 & Marking on the guided type no use if sharp edges, excessive
Contd... lifeline being used) fall arrester and the flexible anchor The anchorage life line & wear, correct operation
line shall conform to EN 365 . In line in anchor and distortion.
The rope grab addition shall include the following: points are
connection
immediately grabs on with the given not If in doubt “Throw it Out”
Means of identification, e.g.
the line in the event rope grab properly
manufacturer’s name, supplier’s
of a fall , there by provides designed. Coloured tracer strand
name, or trademark;
arresting the fall Manufacturer’s production batch necessary which loses its colour in
or serial number or other means shock due course of time to
of traceability; absorption. show that the rope is now
Model and type/identification; is unfit for future use
Number and year of the
document to which the As per Manufactures
equipment conforms;
recommendations
Pictogram or other method to
indicate the necessity for users to
read the instructions for use.
A Typical specimen of marking
CE Marking
EN Number
Name of
Manufacture
Pictogram
Pictogram
Note : PPE mentioned at III, IV & V above may not be required simultaneously while working at height. These use shall depend upon type of activity
10 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation of PPE Hazard of Not When to be discard
(Pictorial Display) Against hazard wearing of PPE
1 Work at Height VI) Helmet (A) The helmet shall Shock absorption The protection given by a helmet Sign of crack /
( height > 2 M) conform to EN 12492 depends on the circumstances of the damage .
and shall have Penetration accident and wearing a helmet De-colouration
following markings : cannot always prevent death or failing in lab test to
Impact long term disability. be done every 1-2
There may be a foreseeable risk years depending on
a) the number of this
Within limits that helmets could become condition
European Standard;
trapped and thereby cause a risk cradle to be
b) the name or stipulated in EN
of strangulation. changed after
trademark of the 12492
manufacturer and/or Cannot provide protection against every one year
his authorized hazard like splash of hot liquid, On sustaining a
representative; work in hot area, cryogenic or severe blow even if
c) the designation of corrosive liquid , flying hot damage is not
the model; particles like chipping, welding, apparent
d) the year and direct fire hazard, contact with bare As per
quarter of live electrical conductor . Manufactures
manufacture; recommendations.
e) the size or size For cleaning,
range (in cm). maintenance or
disinfection, use only
substances ( No
Solvent) that have no
adverse effect on the
helmet and are not
known to be likely to
have any adverse
effect upon the
wearer, when
applied in
accordance with the
manufacturer’s
instructions and
information).
11 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of When to be discard
(Pictorial Display) Not wearing
Against hazard of PPE of PPE
2 a) Excavation. I) Helmet (B) The helmet shall conform to either IS 2925 or Shock Absorption Resistance Not Sign of crack /
EN 397 Penetration Resistance suitable damage .
for hazards De-colouration
b) Fire pump Impact
a) The helmet conforming to IS 2925 shall like splash cradle to be
Operation. have following marking changed after
of hot
every one year
Protection as per EN 397 liquid,
c) Testing of Manufacturer’s name or trade-mark,
On sustaining a
work in hot severe blow
Pressure Shock absorption area, even if damage
Gauge Size of helmet. is not apparent
Penetration resistance cryogenic
or As per
The helmets may also be marked with Impact
corrosive Manufactures
the ISI Certification recommendati
Mark. The above protection shall be within the liquid ,
ons
limitations of various test as stipulated in flying hot
A Typical specimen of marking particles
IS 2925 /EN-397. For cleaning,
like
Marking for Optional test as per EN 397 as maintenance or
Name of chipping, disinfection, use
per clause no 7.2.2.
manufactures welding, only substances (
direct fire No Solvent) that
Each helmet shall carry moulded or hazard, have no adverse
impressed marking or shall carry a durable effect on the
contact
ISI Mark self-adhesive label stating the optional helmet and are
with bare not known to be
requirements complied with, as follows:
Optional requirement Marking/Label live likely to have any
electrical adverse effect
Very low temperature – 20 °C or – 30 upon the wearer,
conductor
Size °C as appropriate when applied in
Very high temperature + 150 °C accordance with
the
Electrical insulation 440 V a.c. manufacturer’s
Lateral deformation LD instructions and
Molten metal splash MM information).
12 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of When to be discard
(Pictorial Display) Not wearing
Against hazard of PPE of PPE
Name of
manufacture
Year of
EN Std Manufacture
CE Marking Size
13 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of When to be discard
(Pictorial Display) Not wearing
Against hazard of PPE of PPE
3 Excavation work
Involving
I) Helmet as
per IS and EN
Please refer (I) on page 12 &13 Please refer (I) on
page 12 &13.
dewatering (B)
works : Contd..
14 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of When to be discard
Against hazard of PPE Not wearing
(Pictorial Display) of PPE
3 Excavation work II) Gum Boot -Safety The gum shall Striking against Not suitable for hazards exceeding one
Involving dewatering conform to IS 12254 stationary like Chemical burns , year from the
works : Contd and have following object. electrical flash, welding date of first use of
marking : spark and heat radiation the shoe .
Striking by
Not suitable if it is
moving object necessary to minimise
Name of the Stepping on electrostatic charges in sign of crack /
manufacturer or sharp object the shortest possible time damage / cut
its recognised Water, alcohols, .
trade-mark, if acids and Not suitable for work in Excessive wear
any; alkalise explosive work area.
A Typical specimen of
Size No.; As per
marking
Batch No., and Manufactures
Month and year recommendatio
of manufacture. ns
Size
ISI Mark
15 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Typical Industrial Limitation Hazard of Not When to be discard
(Pictorial Display) Operation of PPE wearing of PPE
Excavation work III) Goggle : The goggles shall conform to • surround the Limitation exceeding one year from
Involving dewatering EN 166 and EN 170 & shall have eye area, : the date of first use of the
works : Contd.. following markings : give more Uncomfort goggles .
protection in able to
situations wear with sign of crack / damage .
Marking on the lens as
where one other head
Impact resistance (B)
encounters gear like Excessive wear
Optical Class (1) , anti
splashing helmet, As per Manufactures
fogging (N), Anti Scratch
liquids, ear muffs
resistance (K), no 2-1.2 recommendations
fumes, or
marked 2C
vapors, respirator
shade as per EN 170,
powders,
A Typical specimen of marking Manufacture's Name CE and
dusts, and
any other point as per
mists
discretion of IOCL in line
with EN 166 and 170
CE Marking
Optical Class
Scratch Resistance
Manufacture Name
16 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not wearing of When to be discard
Against hazard of PPE PPE
(Pictorial Display)
3 Excavation work IV) Gloves Gloves shall conform to EN Tear Not suitable
Involving dewatering 374 and 388 & gloves shall cut for hazards sign of crack / damage
works : Contd.. Alternative - I : Gloves as have the following markings Abrasion like electrical / cut
per EN stand 374 and 388. as per as per EN 420 Puncture flash, welding
spark and heat Excessive wear
a) Name, trade mark or radiation
other means of IMPORTANT All gloves
identification of must be thrown away
manufacturer or his (in the hazardous waste
authorized representative; bin if required) no more
b) Glove designation than 8 hours after
(commercial name or code initial contact with the
allowing the user to identify chemical.
clearly the product within the
manufacturer's/authorized Achieving date of
A Typical specimen of representative's range); obsolescence
marking c) Size designation;
As per Manufactures
d) Date of obsolescence a if recommendations
Name of Manufacture
applicable per clause 7.2.3
CE Marking
e) Pictogram (s) appropriate
Size to the standards WARNING If you work
accompanied by the with moving machine
EN Number and reference of the applicable parts, choosing a glove
pictograms standards and performance that is the right size and
levels which shall always be made from a less durable
EN Pictogram in the same fixed sequence as material is vital, since
defined in the corresponding the glove easily tears
standard apart if you get caught in
the machinery.
Cat -III Certificate to be
ensured.
17 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not wearing of When to be discard
Against hazard of PPE PPE
(Pictorial Display)
3 Excavation work Alternative - II Alternative -II Light Not suitable sign of crack / damage / cut
Involving dewatering handling for hazards
works : Contd.. Gloves as per IS Alternatively Gloves shall operation like electrical Excessive wear
6994. conform to IS : 6994 (Part I) - flash, welding
1973 & shall have the Tear spark and heat As per Manufactures
following marking . radiation recommendations
Puncture
a) The manufacturer’s name
or recognized trade-mark; Cut
IMPORTANT All gloves must be
b) The type and nominal size
thrown away (in the hazardous waste
of the gloves;
bin if required) no more than 8 hours
after initial contact with the chemical.
C) Year of manufacture; and
Recommended type of
Gloves. is 1, 2, 8, 14. 15. 16
As of May 2017 there is no party having BIS license. Use of this product is permitted assuming that in future some party
may get BIS license.
18 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality Typical Protection Limitation Hazard of Not wearing of PPE When to be
(Pictorial Display) assuran Industrial Against hazard of PPE discard
ce Operation
4 Blast cleaning
(confined space
-
/
I) Helmet (A)
Please refer (VI) on page 11 Please refer
(VI) on page
external)
11
III) Goggle
Please refer (III) on page 16 Please refer
(III) on page
16
19 | P a g e
Guidelines on Personal Protective Equipment (PPE)
Activity Required PPEs Quality assurance Protection Limitation Hazard of Not wearing of When to be discard
(Pictorial Display) Against hazard of PPE PPE
4 Blast cleaning - IV) Ear Muff of suitable Ear muff shall conform to EN 352 Extreme noise Over 8 hours Ear muff with
(confined space / size shall have following marking : Noise induced may be cracked, cut,
external) - Contd hearing losses uncomfortabl or missing
"Medium size range "fit a) the name, trade mark or other e in hot gaskets
satisfactorily in majority identification of the environments
Permissible Noise manufacturer or his authorised Note : . Excessive wear
of Industrial Application
exposure as per representative; In addition to hearing & tear
OSHA 29 CFR b) the model designation; loss, excessive noise Eyeglass
1910.95 c) the number of this EN exposure may wearers may Damage if any.
DB Hours Standard, i.e “EN 352” contribute to mental not get a As per
d) in the case of ear-muffs and physical stress, good seal Manufactures
90 8 intended by the manufacturer to certain illnesses, and Resonate
accidents recommendati
92 6 be worn in a particular (vibrate) at
orientation, an indication of the ons
95 4 lower sound
97 3 FRONT and/or TOP of the cups, frequencies
100 2 and/or an indication of LEFT and
102 1.5 RIGHT cup.
105 1
A Typical specimen of Check the NRR (Noise Reduction
110 0.30
marking Rating,) to ensure noise
115 0.15 or
less exposure within permissible
limits
CE Marking
EN Number
20 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not wearing of When to be discard
(Pictorial Display) Against hazard of PPE PPE
Hand gloves -
involving high
pressure as per EN
388 and 374.
21 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not When to be
(Pictorial Display) Against hazard of PPE wearing of PPE discard
4 Blast cleaning - VI) Apron The apron shall conform to EN 13892-1 and Protection to Not suitable Damage / infection exceeding
(confined space / shall have following markings : the full body for flame to skin etc six month
external) - Contd Alternative -I : Apron against airborne and Hot from the
as per EN 13982 -1 1. The marking shall be clearly visible and as solid material date of first
durable as adequate for the life of the particulates. use of the
clothing. apron .
22 | P a g e
Guidelines on Personal Protective Equipment (PPE)
Name of
Manufacture
Pictograms as per
EN
Year of manufactures
23 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not When to be
(Pictorial Display) Against hazard of PPE wearing of PPE discard
Blast cleaning - Alternative -II : Apron Alternative -II : Alternatively suit shall Protection to Not suitable for Damage / infection exceeding
(confined space / as per IS 4501 conform to IS : 4501 : 1981 shall have the full body flame and Hot to skin etc six month
external) Contd the following marking . against airborne material from the
solid date of first
The marking shall be particulates. use of the
clearly visible and as durable as apron .
adequate for the life of the clothing.
sign of
marked inside with manufacturer’s crack /
name or recognized trade mark, if damage .
any. The ink shall be non-irritating
to skin and shall not impair the Excessive
quality of aprons. wear
As per
The aprons may also be marked with Manufactur
the ISI Certification Mark. es
recommen
The finished material shall be white dations
or of a suitable colour on two sides
as agreed to between the purchaser
and the supplier. Do not use
As of May 2017 there compresse
d air to
is no party having BIS clean as
this will
license. Use of this create dust
product is permitted in the air.
assuming that in • Clean and
future some party decontamina
te tarps and
may get BIS license. other
equipment
on the
worksite.
24 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not When to be discard
(Pictorial Display) Against hazard of PPE wearing of PPE
Blast cleaning - Alternative -III : Boiler Alternative -III : Cloth and stitching Protection to Not suitable Damage / infection exceeding six
(confined space / suit / coverall should be of good quality on visual the full body for flame and to skin etc month from the
external) Contd inspection against airborne Hot material date of first use of
solid the apron .
particulates.
sign of crack /
damage .
Excessive wear
As per
Manufactures
recommendations
Do not use
compressed air
to clean as this
will create dust
in the air.
Avoid
blasting in
windy
conditions to
prevent the
spread of any
hazardous
materials.
25 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not When to be discard
(Pictorial Display) Against hazard of PPE wearing of PPE
Blast cleaning - confined VII) Half face mask 1. The half air mask shall conform to EN 140 Respiratory Not Silicosis Occupational Sign of crack /
space - Contd and shall have following : protection. suitable lung diseases. damage
A Typical specimen for heavy Excessive wear
of marking a) The manufacturer shall be identified by name, Protection gas Deposition of Damage of strap
trade mark or other means of identification. against inhaling concentrat particulate matter in After end of shelf life
b) All units of the same model shall be provided dust, etc. ion Lung. Change of filter /
with a type-identifying marking. cartridges at least
c) Size (if more than one size is available). every six month
d) The number and the year of this European Performance of the
Standard. ie EN 140 components may be
affected by aging
e) Where the reliable performance of As per Manufactures
components may be affected by ageing, means
recommendations
of identifying the date (at least the year) of
manufacture shall be given
26 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not When to be discard
(Pictorial Display) Against of PPE wearing of PPE
hazard
5 Painting - confined space /
external
I) Helmet (A)
Please refer (VI) on page 11 Please refer (VI) on
page 11
III) Goggles
Please refer (III) on page 16 Please refer (III) on
page 16
27 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not When to be discard
(Pictorial Display) Against hazard of PPE wearing of PPE
28 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not wearing of PPE When to be discard
(Pictorial Display) Against hazard of PPE
29 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not When to be discard
(Pictorial Display) Against hazard of PPE wearing of PPE
30 | P a g e
Guidelines on Personal Protective Equipment (PPE)
Activity Required PPEs Quality Protection Against Limitation of Hazard of Not wearing of When to be discard
(Pictorial Display) assurance hazard PPE PPE
6
a) Working in Confined I) Safety Helmet (B)
Please refer (I) on page 12 Please refer (I) on
page 12 &13
space
&13
b) Testing of Gas sensor
c) Tank Gauging
d) De Gassing of LPG
Cylinder
e) Shuttering works
f) Brick masonry
II) Safety Shoe (A)
Please refer (I) on page 4 Please refer (I) on
page 4
g) Handling of Battery
31 | P a g e
Guidelines on Personal Protective Equipment (PPE)
Activity Required PPEs Quality Protection Limitation of PPE Hazard of Not When to be discard
(Pictorial Display) assurance Against hazard wearing of PPE
c) Tank Gauging
d) De Gassing of LPG
Cylinder
e) Shuttering works
32 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation of Hazard of Not wearing When to be
(Pictorial Display) Against hazard PPE of PPE discard
III) Goggles
Please refer (III) on page 16 Please refer (III)
on page 16
33 | P a g e
Guidelines on Personal Protective Equipment (PPE)
Activity Required PPEs Quality assurance Protection Limitation of Hazard of Not wearing of When to be discard
(Pictorial Display) PPE PPE
Against hazard
34 | P a g e
Guidelines on Personal Protective Equipment (PPE)
N Activity Required PPEs Quality Protection Limitation Hazard of Not When to be discard
assurance Against hazard of PPE wearing of PPE
(Pictorial
Display)
b) Blinding
and de-
blinding
flange
work
35 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not When to be
(Pictorial Display) Against hazard of PPE wearing of discard
PPE
9 Electrical works II) Safety Shoe (B) The safety shoe shall have following Striking against Not Exceeding
marking as per IS 15298 ( part -2) : stationary object. suitabl one year
Electrical sub-station current Striking by moving e for from the
carrying equipment a) size; work date of first
object
b) manufacturer’s identification mark; in use of the
Electrical explos shoe .
c) Year of manufacture and at least
resistance ive Sign of
quarter;
d) License No ( CM/L) work crack /
e) IS Mark area. damage
Excessive
Or wear
As per
A Typical specimen of marki Work Manufactur
activit es
ies recommend
requiri ations
ng
antista
tic
Category of Safety shoe (,S3 etc) as work
required as per Table 16 of IS 15298 (part
2) : 2011
36 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not wearing of When to be discard
(Pictorial Display) Against hazard of PPE PPE
9 Electrical works : II) Electrical Hand gloves The gloves shall be marked Type 2—For 1) Type of the Frequently
Electrical sub-station Insulating Rubber Electrical indelibly at the use at voltage PPE restricts used Gloves to
current carrying Gloves back with the following information not exceeding the maximum be re-tested at
equipment Contd as per IS 4770 1 100 ac rms voltage at intervals of not
Type 3— For which it can more than 6
Size and type of glove; use at voltage be used months.
Maximum working potential in not exceeding Gloves issued
Volts, 7 500 ac rms 2) Other for occasional
followed by the word ‘working’ Type 4—For precautions to use shall be re-
in brackets; use at voltage be taken while tested after
Identification of the source of not exceeding working on use or in any
manufacture; and 17 000 ac rms. electrical case at
Month and year of installation intervals of not
manufacture more than 12
moisture absorption certificate to months.
be checked. Gloves
Showing any
A Typical specimen of marking defects
As per
Manufactures
Manufacture Name recommendati
ons
Test Potential
Size
37 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not wearing of PPE When to be
(Pictorial Display) discard
Against hazard of PPE
9 Electrical works :
Electrical sub-
Helmet as per
EN 397
Please refer (I) on page 12 & 13 Please refer
(I) on page 12
station current and 13
carrying equipment
Contd
38 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not wearing of PPE When to be
(Pictorial Display) discard
Against hazard of PPE
III) Goggles
Please refer (III) on page 16 Please refer
(III) on page
16
39 | P a g e
Guidelines on Personal Protective Equipment (PPE)
Required PPEs Quality assurance Protection Limitation Hazard of Not wearing of PPE When to be
Against hazard of PPE discard
Activity
(Pictorial Display)
10
Working with possibility of
IV) Gloves
Please refer (IV) on page 17 Please refer (IV)
on page 17
splashes of hot, cryogenic or Alternative -I : Hand
corrosive liquids. Contd gloves - involving high
pressure as per EN
388 and 374
Alternative - II
Please refer (IV) on page 18 Please refer (IV)
on page 18
Gloves as per IS 6994.
Light Abrasion ix of table 2
40 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not When to be
(Pictorial Display) Against hazard of PPE wearing of PPE discard
Working with
possibility of
V) Apron
Please refer (VI) on page 22 &23 Please refer
(VI) on page
splashes of hot, Alternative -I Apron as 22 &23
cryogenic or per EN 13982
corrosive liquids
Contd
41 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not When to be
(Pictorial Display) Against hazard of PPE wearing of discard
PPE
11 Welding and cutting work I) Helmet attachable welding a) Helmet mountable welding shield. Protection Exceeding
shield (A) Conforms to EN 175 during To be used only one year
Protective lens made of clear high welding. in conjunction from the
with safety date of
impact resistant. polycarbonate
Liftable helmet & first use
conforming to EN 166 and ANSI Z 87.1
welding lens should not be of the
polypropylene Impact Resistance Shell used goggles .
allows clear
conform to EN 175 F independently. sign of
view while
The welding shield shall be CE marked restricting crack /
Marking on protective shall be fully harmful dust However damage
visible particles. welding helmets on lenses
can be used Excessive
Ocular marking shall be as per clause independently. wear
9.2 of EN 166
As per
b) Welding Helmet with welding Shield
Manufact
Protective lens made of clear high ures
II) Welding Helmet with welding
impact resistant. polycarbonate recomme
Shield (B)
conforming to EN 166 and ANSI Z 87.1 ndations
polypropylene Impact Resistance Shell
conform to EN 175 F
Marking on protective shall be fully
visible
Ocular marking shall be as per clause
9.2 of EN 166
Name of Manufacture
42 | P a g e
Guidelines on Personal Protective Equipment (PPE)
Activity Required PPEs Quality assurance Protection Limitation Hazard of Not When to be
(Pictorial Display) Against hazard of PPE wearing of discard
PPE
43 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not When to be discard
(Pictorial Display) Against hazard of PPE wearing of PPE
11 Welding and cutting work III) Apron Apron shall conform to EN minimize Additional electrical insulation On contaminated with
Contd. ISO 11611 & shall have skin burns layers will be required where flammable material.
the following markings : caused by there is an increased risk of
sparks, electric shock; garments Manufacturers shall
classification: :
spatter, or meeting the requirements of include the
Class 1: the number and
radiation clause of en ISO 11611 ( 6.10) information that
year of this International are welder’s protective
Standard (ISO 11611) designed to provide clothing be cleaned
followed by the graphical protection against short term, regularly in
symbol shown in below accidental contact with live accordance with the
and the indication “Class electric conductors at manufacturer’s
1” and the indication “A1” voltages up to approximately recommendations.
or “A1 + A2” as 100 V d.c. After cleaning, the
appropriate for Limited any identified hazards against clothing shall be
Flame Spread; which the clothing is visually inspected for
intended to protect (e.g. any sign of damage.
Class 2: the number and
flames, molten metal spatter, Similarly, users should
year of this International
radiant heat, and short term be advised that if they
Standard (ISO 11611) accidental electrical experience sunburn-
followed by the graphical contact); for protective like symptoms, UVB is
symbol shown in Figure 1 clothing, a warning that penetrating.
and the indication “Class additional partial body In either case, the
2” and the indication “A1” protection may be required, garment should be
or “A1 + A2” as e.g. for welding overhead; repaired (if
A Typical specimen appropriate; garments practicable) or
of marking conforming to Class 2 shall replaced and
meet Class 2 for all consideration given to
the use of additional,
performance
more resistant,
EN ISO Number requirements; protective layers in
instructions for cleaning future.
shall be marked (e.g. on a
label). As per Manufactures
Class marking recommendations
44 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not wearing of PPE When to be
(Pictorial Display) discard
Against hazard of PPE
45 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not When to be discard
Against hazard of PPE wearing of PPE
(Pictorial Display)
46 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not wearing of When to be discard
Against hazard of PPE PPE
(Pictorial Display)
47 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not wearing of PPE When to be
Against hazard of PPE discard
(Pictorial Display)
III) Goggles
Please refer (III) on page 16 Please
refer (III)
on page 16
48 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not wearing of PPE When to be
Against hazard of PPE discard
(Pictorial Display)
Alternative - II
Please refer (IV) on page
Gloves as per IS 6994. 18
Light Abrasion ix of table 2
49 | P a g e
Guidelines on Personal Protective Equipment (PPE)
SN Activity Required PPEs Quality assurance Protection Limitation Hazard of Not wearing When to be
(Pictorial Display) of PPE discard
Against hazard of PPE
50 | P a g e
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE A-VI
PROFORMA OF BANK
GUARANTEE (ADVANCE)
(i) The Owner shall have the fullest liberty without reference to the Bank and without affecting in any way
the liability of the Bank under this Guarantee/Undertaking, at any time and/or from time to time to
anywise vary the Contract and/or any of terms and conditions thereof or of or relative to the advance
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
and to extend time for the performance of the Contract and/or repayment of the advance or to postpone
for any time or from time to time the obligations of the SUPPLIER/CONTRACTOR and to waive or
postpone exercise of any of the rights available to the Owner against the SUPPLIER/CONTRACTOR
or to forebear from enforcing any of the terms or conditions of the Contract and/or the advance or any
security (ies) available to the Owner, AND the liability of the Bank shall remain in full force and effect
notwithstanding any exercise by the Owner of the liberty with reference to any or all the matters The
Owner shall have the fullest liberty without reference to the Bank and without affecting in any way the
liability of the Bank under this Guarantee/Undertaking, at any time and/or from time to time to anywise
vary the Contract and/or any of terms and conditions thereof or of or relative to the advance and to
extend time for the performance of the Contract and/or repayment of the advance or to postpone for
any time or from time to time the obligations of the SUPPLIER/CONTRACTOR and to waive or
postpone exercise of any of the rights available to the Owner against the SUPPLIER/CONTRACTOR
or to forebear from enforcing any of the terms or conditions of the Contract and/or the advance or any
security(ies) available to the Owner, AND the liability of the Bank shall remain in full force and effect
notwithstanding any exercise by the Owner of the liberty with reference to any or all the matters
aforesaid or by reason of time being given to the SUPPLIER/CONTRACTOR or any forbearance,
waiver, act or omission on the part of the Owner or any indulgence by the Owner to the
SUPPLIER/CONTRACTOR or any other act, matter or thing whatsoever which under the law relating
to sureties would have the effect of releasing the Bank from its liability hereunder or any part thereof,
AND the BANK DOTH HEREBY waive all rights at any time inconsistent with the terms of this
Guarantee/Undertaking.
(ii) It shall not be necessary for the Owner to proceed against the SUPPLIER/CONTRACTOR before
proceeding against the Bank and this guarantee/undertaking shall be enforceable against the
Bank as principal debtor notwithstanding the existence of any other security for any
indebtedness of the SUPPLIER/CONTRACTOR to the Owner (including relative to the
advance) and notwithstanding that any such security shall at the time when claim is made
against the Bank or proceedings taken against the Bank be outstanding or unrealized.
(iii) As between the Bank and the Owner for the purpose of this guarantee/undertaking the
amount claimed by the Owner from the Bank with reference to this guarantee/undertaking shall
be final and binding upon the bank as to the amount payable by the Bank to the Owner hereunder.
(iv) The liability of the Bank to the Owner under this guarantee/undertaking shall remain in full force
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
and effect notwithstanding the existence of any difference or dispute between the
SUPPLIER/CONTRACTOR and the Owner, the SUPPLIER/CONTRACTOR and the Bank
and/or the Bank and the Owner, or otherwise howsoever touching or affecting these presents
or the liability of the SUPPLIER/CONTRACTOR to the Owner, and notwithstanding the existence
of any instructions or purported instructions of the SUPPLIER/CONTRACTOR or any other
person(s) to the Bank not to pay or for any cause withhold or defer payment to the Owner under
these presents with the intent that notwithstanding the existence of such difference, dispute or
instruction, the Bank shall be and remain liable to make payment to the Owner.
(v) This guarantee/undertaking shall not be affected by any change in the constitution of the Bank
or that of the SUPPLIER/CONTRACTOR or the Owner, or any irregularity in the exercise of
borrowing powers by or on behalf of the SUPPLIER/CONTRACTOR.
(vi) This guarantee/undertaking shall be valid for all claims/demands made by the Owner to or upon
us up to midnight of provided always that if for any reason, the
SUPPLIER/CONTRACTOR is unable to complete supplies under the Contract, the Bank shall
at the request of the Owner and without recourse to the SUPPLIER/CONTRACTOR extend the
validity of this guarantee/undertaking for a further period of six months. For the purpose of this
clause, the Owner’s statement that the SUPPLIER/CONTRACTOR is unable to complete
supplies under the contract shall be conclusive and final binding on us.
a. The Bank’s liability under this Guarantee/Undertaking shall not exceed Currency. . . . . . .
. . . . . (Currency . . . . . . . . . . . . . . . . . . . . . . . . only),
b. This Guarantee/Undertaking shall remain in force up to . . ... and any extension(s) thereof;
and
c. The Bank shall be released and discharged from all liability under this
Guarantee/Undertaking unless a written claim or demand is issued to the Bank on or before
. . . . . . . . . . . . or the date of expiry of any extension(s) thereof if this Guarantee/Undertaking
has been extended.
(viii) The Bank DO HEREBY declare that Mr.__________ (name of the person signing on behalf
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Yours faithfully
For
Signature
Name &Designation
NOTE
1. This Guarantee/Undertaking is not to be witnessed.
2. This Guarantee is required to be stamped as an agreement according to the stamp duty act.
3. This Guarantee is required to be sent by SUPPLIER/CONTRACTOR’s Bankers directly to the Owner
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
ANNEXURE A-VII
1 MANAGER / RESIDENT
ENGINEER / SITE‐IN‐ CHARGE He should have successfully constructed &
commissioned multiple Process Units in Hydrocarbon /
Fertilizer/ LNG/Petrochemical/ On shore Oil & Gas
processing facilities.
Note:
1. For Mechanical, Composite, EPC or EPCC Contracts of value more than Rupees 20 crores,
the lead QA/QC Engineer shall be a qualified internal auditor of ISO 9001.
2. CVs of key construction personnel proposed to be deployed shall be submitted to
Owner/Engineer-in-Charge prior to their mobilization at Site. The mobilization of key
personnel shall be done at site subject to prior approval of their CVs by Owner/Engineer-
in-Charge.
1.0 PENALTY FOR NON - MOBILIZATION OF KEY CONSTRUCTION PERSONNEL
Penalty for non-mobilization per day per person after the contractual mobilisation period /
mobilisation schedule agreed during Kick off Meeting / jointly agreed between contractor
and PMC / owner based on front availability etc.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
o INR. 3000/- for Lead QA/QC Engineer, Lead Planning Engineer, Lead Safety
Officer, Warehouse In-charge, Lead Discipline Engineer, Lead Welding/ NDT
Engineer and the Quantity Surveyor
ANNEXURE TO SCC
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 1 of 3
ANNEXURE A-VIII
SR.
DESCRIPTION CONTRACTOR RESPONSE
NO.
1. Name of Main Contractor
2. Name of Work, Location
3. Name of Proposed Sub-Contractor
4. Scope of Work to be Sub-Contracted (Brief)
Estimated Value of the Proposed Work to be Sub-
5. Contracted (INR)
6. Qualifying Criteria for Sub-Contractor
Similar Work experience in Hydrocarbon Industry
Based on above information, we M/s. (Name of Main Contractor) propose M/s.(Name of Sub-
Contractor) as our sub-contractor for the above-mentioned works.
We understand that notwithstanding above approval, we shall remain fully responsible for the
9. performance of the said sub-contractor and any failure of the sub-contractor shall not absolve/relieve
us of our responsibility to complete the works as per the terms of conditions of the Contract.
Note: Bidders to fill all the details in the above proforma. Further, Bidder shall also fill- in the details at
Sr. No. 5 above based on the estimated value of the proposed work to be subcontracted.
ANNEXURE TO SCC
ANNEXURE A-IX
Page 2 of 2
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4
ANNEXURE A-X
FORMAT FOR GUARANTEES
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 1 of 12
ANNEXURE A-X
Page 1 of 12
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE A-X
FORMAT FOR GUARANTEES
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 2 of 12
A. GENERAL
1. GENERAL
1.1 This document describes the guarantee parameters, which the CONTRACTOR must fulfil to
meet his contractual obligations. The Cost of loading (during bidding) due to differential
guaranteed figures (if any) towards Technical parameter (Utility consumption etc.,), Price
reduction criteria for shortfall in the guarantee parameters and the Rejection criteria (during
project execution) of the various facilities being supplied by the CONTRACTOR under this
contract are outlined in this document.
CONTRACTOR to note that this document however, does not absolve the CONTRACTOR of
his responsibilities towards meeting the quality and performance linked guarantees outlined
extensively elsewhere in the bid document. Guarantee requirements as spelt out in this
document shall however; have to be demonstrated by the CONTRACTOR for acceptance of
the various facilities of the package by the Owner.
The guarantee parameters described herein are in addition to other warranties and guarantees
that are specified elsewhere in the scope of work and specifications that form part of the
Contract.
1.2 The guarantee parameters as outlined in this document shall be adjusted suitably in the event
of variation in the utility supply conditions, if any. CONTRACTOR shall furnish all calculations
as may be required for this purpose.
1.3 CONTRACTOR shall raise all necessary instruments and facilities as may be required to
establish the guarantee parameters during the performance tests. Owner's obligations in terms
of providing utilities etc. shall be limited to as outlined in the bid document. (Only at the B/L
without measuring instrument).
1.4 The total reduction in Price on all accounts as defined in the various clauses of this document
shall be limited to 10% of the total contract price. This ceiling does not include
repair/rectification/make-good guarantee covered in this document. The above reduction shall
be in addition to any other price reduction mentioned elsewhere in the tender document.
1.6 CONTRACTOR shall guarantee the equipment / complete system for the design, materials,
workmanship, size, capacity, performance, quality of utility & their consumptions, efficiency
and compliance with various technical requirements forming the part of the CONTRACTOR'S
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE A-X
FORMAT FOR GUARANTEES
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 3 of 12
scope and outlined variously in the bid document. This guarantee shall also include the sub
ordered/bought out items forming a part of the CONTRACTOR’s supplies.
1.7 CONTRACTOR shall repair / replace any part of equipment/component/sub system /complete
system free of cost and without loss of time if :
1.8 Contractor to submit sample calculation for guarantees along with their unpriced bids which
should include all constants / graphs and charts, as applicable.
1.9 Contractor to note that the data submitted vide point 1.8 will be utilized during guarantee test
run.
2.1 CONTRACTOR shall guarantee the equipment / complete system for the design, materials,
workmanship, size, capacity, performance, quality of utility & their consumptions, efficiency
and compliance with various technical requirements forming the part of the CONTRACTOR'S
scope and outlined variously in the bid document. This guarantee shall also include the sub
ordered/bought out items forming a part of the CONTRACTOR's supplies.
2.2.1 Design and Engineering is within the CONTRACTOR’s scope of work and the Plant shall be
executed based on the engineering performed, it shall be the prime responsibility of the
CONTRACTOR to carry out such design and engineering in accordance with good and sound
engineering practices using International Standards and Indian Codes & Regulations wherever
applicable to such design and/or engineering.
2.2.2 In case any error or omission in such design or engineering requires re-engineering which
results in any new requirements for equipment/ materials, the same shall be supplied and/or
re-engineering shall be carried by the CONTRACTOR within the scope of relative work and/or
supply and within the contractual period without extra cost to the OWNER or entitlement of
extension of time.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE A-X
FORMAT FOR GUARANTEES
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 4 of 12
2.2.3 The CONTRACTOR shall check and satisfy themselves with the Front End Engineering Design
Data provided in the tender for its accuracy, correctness and completeness and in case of
deficiency, CONTRACTOR shall inform the OWNER as well as CONSULTANT the
modifications proposed to be carried out to overcome the deficiency and rectify the same at no
extra cost. The CONTRACTOR, if required, shall carry out corrective technical studies and
engineering as may be required without any extra cost to the OWNER.
2.3.1 Workmanship for manufacture and construction shall be carried out in accordance with the
stipulations of the Bidding Documents. Any rectification of any defective material supply or
defective work done shall be made good in accordance with the instructions of Engineer-in-
Charge without any extra cost or entitlement of extension of time to the CONTRACTOR or
shall, if so considered by the OWNER, be replaced by new equipment within the relative scope
of Work and/or supply.
2.3.2 The CONTRACTOR guarantees and accepts full responsibility for all materials (including
equipment and all components / parts) and works within the CONTRACTOR’s scope and/or
work including but not limited to:
a) Selection of materials
b) Material specifications and metallurgy as per Bidding Documents
c) Work specifications as per Bidding Documents
d) Fabrication/manufacturing workmanship
e) Engagement of experienced, reliable and qualified suppliers, engineers and/or sub-
contractors.
2.4.1 CONTRACTOR is required to demonstrate that the Power Transformer losses are within the
guaranteed values furnished in the bid document.
ANNEXURE A-X
FORMAT FOR GUARANTEES
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 5 of 12
1. GUARANTEE PARAMETERS
Following guarantee parameter shall be considered for Price reduction (during Execution) or
Price Loading (during Bid evaluation) as mentioned in clause no. 2 & 3 below:
2.1 In addition and without prejudice to any other reduction, discount or adjustment in Price to
which the OWNER is entitled, if the actual losses of Power Transformers exceeds the
guaranteed figures furnished by the CONTRACTOR in its bid, the OWNER shall be
entitled to an adjustment in the lump sum price by way of Price Reduction / Price discount
as follows.
a) In case the actual Transformer losses exceed the limits shown in above table, the
equipment shall be rejected. The CONTRACTOR shall necessarily remedy/rectify
the transformer or make necessary replacements within such time as may be fixed
in this behalf by the Engineer-in-Charge after consulting the OWNER, so as to
ensure that the excess losses is brought within the guaranteed value. The
CONTRACTOR shall not be entitled to any extension of time and any additional cost
incurred thereof for undertaking any remedy /replacement / rectification as specified
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE A-X
FORMAT FOR GUARANTEES
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 6 of 12
above.
b) In case the actual losses exceed the guaranteed figures quoted by the bidder and
within the limit specified in the table above, the OWNER shall be entitled to an
adjustment in the lump sum price by way of PRICE REDUCTION to an amount
equivalent to the estimated cost of the excess losses for a period of 10 years
operations of the PLANT computed on the basis of 8,000 working hours per year at
the rate mentioned below, calculated in accordance with the formula mentioned in
this document in Clause no.2.2. (Refer clause 4 also)
c) However, the OWNER may, at their option, allow the Contractor to repair/ replace
the transformer in order to meet the guaranteed consumption figure, instead of
exercising the option of PRICE REDUCTION.
e) List of Equipment to be considered for Price Loading (during Bid Evaluation) or for Price
Reduction (during Project execution) for excess losses – Refer Attachment #1 to this
document.
The price reduction (INR) for excess loss shall be calculated as follows for each unit of
Transformers:
Price Reduction = (PRpower Total for Transformer A + PRpower Total for Transformer B)
ANNEXURE A-X
FORMAT FOR GUARANTEES
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 7 of 12
Where in,
PG_no / PG_fl / PG_ax = Guaranteed Transformer Power losses (KW) at No load / Full load /
Auxiliary losses respectively, quoted by the bidder in the Price bid (FORM SP-8) for the
identified equipment (specified in this document in Attachment # 1).
PA_no / PA_fl / PA_ax = Actual losses (KW) at No load / Full load / Auxiliary losses respectively,
by the identified equipment during Performance Guarantee Test Run (PGTR) during FAT.
CP = Cost of Power (INR per KWh) as specified in this document in Attachment # 2
DF = Discount Factor (as mentioned in clause no.4 of this document)
While computing the Price Reduction, negative values, if any, shall be ignored and no
credit shall be given to Contractor. It thus means that, if the actual losses of power
transformers is lower than the guaranteed losses quoted by the Contractor in its bid, no
credit will be given.
2.4 The total reduction in price as defined in this document for not meeting the guarantee
values as quoted by the bidder shall be limited to 10% of the total Contract price. The
above reduction in lumpsum price shall be in addition to any other price reduction
mentioned elsewhere in tender document. This ceiling does not include repair/ rectification
guarantee/make good covered in this document or elsewhere in tender document.
In case the shortfall in the guaranteed parameters is not beyond rejection limit, CONTRACTOR
may carry out necessary repair / rectification / modification / replacement at his own cost and
through his own agency on urgent basis and complete the repair/ rectification/modification/
replacement without any additional time. Should the equipment/transformer continue to
underperform, price reduction shall be levied as specified for shortfall in guaranteed
parameters above.
ANNEXURE A-X
FORMAT FOR GUARANTEES
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 8 of 12
During Bid Evaluation stage, Price Loading due to differential guaranteed values*^ if any
(*^difference between guaranteed figures quoted by bidder in Price bid (FORM SP-8) and
Datum figures specified in Attachment # 3) towards guarantee parameters for transformers shall
be carried out in accordance with the loading criteria / formula specified in this document.
Maximum Price Loading to be applied, however, shall not exceed 10% of the total Lumpsum Price
as quoted by Bidder in SP-0 Form.
Power Transformer losses shall be considered for Price loading (during Bid evaluation stage).
The price loading for excess loss shall be calculated as follows for each unit of Transformers:
Where in,
PG_no / PG_fl / PG_ax = Guaranteed Transformer Power losses (KW) at No load / Full load /
Auxiliary losses respectively, quoted by the bidder in the Price bid (FORM SP-8) for the
identified equipment (specified in this document in Attachment # 1).
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE A-X
FORMAT FOR GUARANTEES
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 9 of 12
PL_no / PL_fl / PL_ax = Transformer losses (KW) datum value at No load / Full load / Auxiliary
losses respectively, as specified in Attachment # 3.
CP = Cost of Power (INR per KWh) as specified in Attachment # 2
DF = Discount Factor (as mentioned in clause no.4 of this document)
• In case bidder quotes lesser net loss value than the Datum value specified in this
document, no negative loading value or NO CREDIT shall be considered for price
evaluation. However, the quoted value shall be taken as bidder guaranteed value and shall
be the revised guaranteed point for the bidder. Bidder will have to demonstrate the same
during FAT.
• Price loading calculated as specified above, shall be loaded on evaluated price based on
the other loading (if any) defined elsewhere in the document.
Discounting Factor (DF) to arrive at Net Present Value (NPV) is calculated as specified below.
To arrive at Net Present value (NPV) based on number of operating years, the discounting
factor (DF) is calculated as:
DF = Σ [1 / {1+ (IR%/100)}^N]
Where:
N = n +3 (Total number of operating years, including 3 years upto start-up operation)
n = Number of operating years for which loading is to be done as specified i.e. 10 years
IR% = Percentage rate of interest rate 12%
DF = 4.02
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE A-X
FORMAT FOR GUARANTEES
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 10 of 12
Attachment # - 1
Number
Considered in
Service operation
S. No Item No
for
Evaluation
220/33kV, 115/140 MVA (ONAN / ONAF) Power
1. 000-TR-101 A/B 2
Transformers
Notes:
a) The power guaranteed figures quoted by the bidder in SP form shall only be used for the purpose
of loading and reduction of price as defined in this document. However, bidder is required to ensure
that equipment are designed and shall meet the necessary technical requirement as spelt out in
the tender document for smooth operation of the unit in all operating conditions.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE A-X
FORMAT FOR GUARANTEES
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 11 of 12
Attachment # - 2
ANNEXURE A-X
FORMAT FOR GUARANTEES
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 12 of 12
Attachment # - 3
Datum figure
Guaranteed
220/33kV, 115/140MVA as mentioned
Figure (for
Sr. No (ONAN/ONAF) Power Unit in ITB (for
each
Transformer Losses: each
Transformer)
Transformer)
ANNEXURE TO SCC
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 1 of 1
ANNEXURE A-XI
ANNEXURE TO SCC
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 1 of 2
ANNEXURE A-XII
ITEM DESCRIPTION
SR. NO.
Building Fire Alarm Panel (BFAP), flame detectors, manual call points,
The delivery of Free issue Materials will be notified to the CONTRACTOR after award of Contract.
Annexure-………..of SCC (Part-A)
i) We meet the mandatory minimum Local Content (LC) requirement as per the Policy
ii) Percentage of LOCAL CONTENT calculated as per the Clause No.6.0 of the
above mentioned Policy is ……..………….%. (In Figures and Words)
* (Please see the NOTE below)
In case the above declared details are found wrong and/or in case the provisions of the said Policy
are violated by us at any stage during bidding stage or after award of the Work (in case awarded
to us), IOCL shall be free to initiate any action against us as per the provisions of the Tender
including the relevant provisions of the above said Policy.
Place :
Date :
*NOTE: 1) In case of procurement for a value in excess of Rs.10.00 Crores, the Undertaking submitted by
the Bidder shall be supported by a Certificate from the Statutory Auditor or Cost Auditor of the Company
(in case of Companies) or from a practising Cost Accountant or practising Chartered Accountant (in respect
of other than Companies) giving the percentage of Local Content.
2)However, in case of Foreign Bidder (wherever applicable as per the Notice Inviting Tender(NIT),
Certificate from the Statutory Auditor or Cost Auditor of their own Office or Subsidiary in India giving the
percentage of Local Content is also acceptable. In case Office or Subsidiary in India doesn’t exist or Indian
Office/Subsidiary is not required to appoint Statutory Auditor or Cost Auditor, Certificate from practising
Cost Accountant or practising Chartered Accountant giving the percentage of Local Content is also
acceptable.
Annexure-………..of SCC (Part-A)
i) We meet the mandatory minimum Local Content (LC) requirement as per the Policy
ii) Percentage of LOCAL CONTENT calculated as per the Clause No.6.0 of the
above mentioned Policy is ……..………….%. (In Figures and Words)
* (Please see the NOTE below)
In case the above declared details are found wrong and/or in case the provisions of the said Policy
are violated by us at any stage during bidding stage or after award of the Work (in case awarded
to us), IOCL shall be free to initiate any action against us as per the provisions of the Tender
including the relevant provisions of the above said Policy.
Place :
Date :
*NOTE: 1) In case of procurement for a value in excess of Rs.10.00 Crores, the Undertaking submitted by
the Bidder shall be supported by a Certificate from the Statutory Auditor or Cost Auditor of the Company
(in case of Companies) or from a practising Cost Accountant or practising Chartered Accountant (in respect
of other than Companies) giving the percentage of Local Content.
2)However, in case of Foreign Bidder (wherever applicable as per the Notice Inviting Tender(NIT),
Certificate from the Statutory Auditor or Cost Auditor of their own Office or Subsidiary in India giving the
percentage of Local Content is also acceptable. In case Office or Subsidiary in India doesn’t exist or Indian
Office/Subsidiary is not required to appoint Statutory Auditor or Cost Auditor, Certificate from practising
Cost Accountant or practising Chartered Accountant giving the percentage of Local Content is also
acceptable.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
ANNEXURE A-XIV
CALIBRATION REQUIREMENTS OF
MONITORING AND MEASURING DEVICES AT
CONSTRUCTION SITE
PETROCHEMICAL AND LUBE
INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
CALIBRATION REQUIREMENTS OF
MONITORING AND MEASURING DEVICES
AT CONSTRUCTION SITE
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 2 of 6
Abbreviations:
ABS : ABS Consultancy
BIS : Bureau of Indian Standards
BV : Bureau Veritas
CEIL : Certification Engineers International LTD.
DNV : Det Norske Veritas
IRS : Indian Registrar for Shipping
LRS : Lloyd’s Register Group Limited
NABL : National Accreditation Board for Testing and Calibration Laboratories
PMI : Positive Material Identification
PETROCHEMICAL AND LUBE
INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
CALIBRATION REQUIREMENTS OF
MONITORING AND MEASURING DEVICES
AT CONSTRUCTION SITE
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 3 of 6
To check by Backsight
Foresight readings, Record to
Every use
A.2. Levels the temporary be maintained (See note below)
adjustments of level
CALIBRATION REQUIREMENTS OF
MONITORING AND MEASURING DEVICES
AT CONSTRUCTION SITE
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 4 of 6
Weigh
Once in Six
Batcher/Batching Records to be maintained
B.2. Calibration of scales Months
Plant
As per
Calibration certificate manufacturer
Cube testing from manufacturers or specification or Records to be maintained
B.3. machine from reputed calibrating once a year
agency. whichever is
earlier
Calibration from
manufacturer or
Holiday tester reputed calibrating Once in 6 months Records to
C.5
agency or by calibrating be maintained
by zeep meter.
CALIBRATION REQUIREMENTS OF
MONITORING AND MEASURING DEVICES
AT CONSTRUCTION SITE
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 5 of 6
D. Welding /Inspection
CALIBRATION REQUIREMENTS OF
MONITORING AND MEASURING DEVICES
AT CONSTRUCTION SITE
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 6 of 6
Note: If Error is found, it has to be sent to manufacturers or their authorized agents for
rectification and certification. Reputed calibrating agency shall be NABL accredited for
relevant testing of the device.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 1 of 9
ANNEXURE A-XV
1.0 GENERAL
A system for evaluation of Contractors’ performance is a key process and important
to support an effective contracting function of an organization.
Performance of all contractors needs to be closely monitored to ensure complete
execution of project within scheduled completion period. For timely execution of project
and achieving the desired goals of the organization, it is necessary to monitor the
execution of project or contracts right from the award stage to completion stage and
take corrective measures in time.
2.0 OBJECTIVE
The objective of contractor performance evaluation is to ascertain the performance of
the contractor with respect to satisfactory execution of work while maintaining safety and
quality standards and to develop reliable contractors so that they consistently meet
or exceed expectations and requirements.
The purpose of this guideline is to put in place a system to monitor performance of
contractors associated with IOCL Refineries Division so as to ensure timely completion
of various projects.
Note:
1) Performance evaluation by Engineer-in-charge (EIC) for stages against SN (i), (ii) &
(iii) shall be carried out within a period of 01 (one) month after reaching at
designated schedule progress stage.
2) Performance evaluation by Engineer-in-charge (EIC) for SN (iv) shall be
carried out within a period of 06 (six) months after achieving Mechanical
Completion.
7.1 Following actions shall be taken at different evaluation stages depending upon the
performance rating:
SI Evaluation performance
Recommended Action
No stage rating
Very Good No further action
Letter to the contractor for improving the
Initial Stage Good
performance in future
1 Restrict Contractors' Pre-qualification in future jobs
(30% Schedule
Progress) Fair or
Additional bank Guarantee in future jobs (note)
SI Evaluation performance
Recommended Action
No stage rating
Very Good No further action
Note:
In case of Fair / unsatisfactory rating, indicated penal action shall be taken for future jobs for a
maximum period of 1 year across all Division, with a provision of revoking such penal action
in case of improvement in performance in the job under evaluation or any other concurrent
job (having contract value of minimum 80% of the job under evaluation) at similar or higher stage
of evaluation in the same division.
In future jobs submit additional Bank Guarantee of an amount equivalent to 10% (ten
percent) of the contract value, over & above the other bank Guarantees specified in
the tender, if Contractor’ performance rating is Fair on the last date of submission of
Bid. This additional bank guarantee shall be submitted before signing of the contract and
shall be vaild up to completion of the work.
• Contractor shall have the option to choose between the above mentioned two options
i.e. at sr. no, 7.2 & 7.3 at the time of submission of bid for future jobs.
7.4 Banning
Not to consider the contractor in future jobs.
Annexure-1
INDIANOIL CORPORATION LIMITED
REFINERIES DIVISION
1. North
2. South
3. East
4. West
10.1 Allocation of marks for Initial, mid / Peak & Schedule Completion stage:
10.2 Allocation of marks for Actual Completion stage (i.e. Mechanical Completion):
10.2.1 In case there is NO DELAY solely attributable to contractor, marks obtained
by the Contractor =100
Note:
11.2 Part-Offloading
Note: The maximum deduction of marks on account of part of-loading in any work shall be
limited to 20 marks.
For calculation of marks towards deduction on safety violation, the following formula
shall be used:
MH
Where,
AFR - Accident Frequency Rate
D - Total Number of Fatalities and/ or Number of permanent
disabilities I - Number of loss time injury cases without
permanent disability
MH - Man Hours worked
Note:
1. Figure arrived after using the formula ‘{(AFR – 0.5)/ 0.05}”at SN 2 above shall
be rounded up to next whole number
2. The maximum deduction of marks on account of safety violation in any work shall
be limited to 25 marks.
3. Deductions on account of safety violation shall be applicable for the incidents
occurred from start to evaluation stage.
Note:
The maximum deduction of marks on account of part offloading in any work shall be limited
to 05 marks.
General Note:
The above-mentioned deduction towards 11.1 & 11.2 shall be applicable for incident(s)
occurred in between the successive evaluation stages only, but the deductions towards 11.3
&11.4 shall be applicable for the incidents occurred from start of work to respective evaluation
stage. For performance evaluation at 30% schedule progress stage, incident occurred
between start of work & 30% schedule progress stage shall be considered.
11.5 Total Deduction of Marks as calculated at 11.1, 11.2, 11.3, & 11.4 = ………….
ANNEXURE A-XV
GUIDELINES ON CONTRACTOR’S
PERFORMANCE EVALUATION
SN Description Marks
Name:……………………………………….
Designation: ……………………………………….
Date: ……………………………………….
PETROCHEMICAL AND LUBE
INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 1 of 3
ANNEXURE A-XVI
SPIR FORMAT
SAP
OWNER
OR
LEGEND
NO.
1
EQUIPMENT NO.
DATE
MANUFACTURER'S
MODEL OR TYPE.
MANUFACTURER
PART NUMBER
2
MATERIAL TYPE
SHELF LIFE IN WEEKS
NORMAL OPERATION
DESCRIPTION OF PARTS MATERIAL SPECIFICATION DRAWING NO. INCL. POS. NO SAP CODE
INSURENCE SPARES
ORIGINAL ITEM
UNIT OF MEASURE
MANUFACTURER'S
SERIAL NUMBER
MRP TYPE
MANUFACTURER
ITEM NUMBER
Min/Max
3 MANUFACTURER MANUFACTURER
CRITICAL
PLANT
S.LOC
NO OF
UNITS
4 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
N U M B E R O F P A R T S P E R U N I T
5
EQUIPMENT LOCATION
The SPIR form consist of a main sheet and extension sheet formatted A3 size. The completed forms shall be emailed to PMC/Owner. Hard copies in A3 format along will other supporting relevant documents shall also be
submitted. The consultant/manufacturer/supplier/vendor is required to complete all the columns in consultation with Owner. All information shall be clearly stated in English language.
COLUMN NO EXPLANATION COLUMN NO EXPLANATION
1 EQUIPMENT TAG NO. OR SAP EQUIPMENT NO.
Enter the equipment tag or SAP equipment number SHELF LIFE IN WEEKS
20
Enter length of time in weeks for which an item remains usable, fit for consumption
2 MANUFACTURER'S MODEL or TYPE 21 COMMISSIONING and CAPITAL INSURANCE SPARE PARTS RECOMMENDED BY
State model, type or other positive identification reference of the equipment/instrument MANUFACTURER
ordered
Enter the quantity of commissioning spares required to prepare the equipment ready for start up
3 MANUFACTURER'S SERIAL NO. 22 INITIAL (2 YEARLY) NORMAL OPERATION SPARE PARTS RECOMMENDED BY
State serial number or other unique identification of the reference of the equipment/instrument MANUFACTURER
ordered Enter the quantity of initial 2 yearly spare parts required to safeguard the operation of equipment
during the running-in and start-up periods and the first 2 year of operation
4 NO. OF UNITS SPARE PARTS FOR NORMAL OPERATIONS RECOMMENDED BY MANUFACTURER
Enter the total number of identical assemblies within equipment/instrument as stated in 23 Enter the quantity of spare parts may be required due to unforeseen failure during normal
columns 1, 2 and 3. operation not covered in 2 years operation spares.
5 NUMBER OF PARTS PER UNIT 24 CRITICAL SPARE PARTS
For each unit or group of identical units, enter in the appropriate space the number of parts Enter the functional criticality of the spare part i.e. V=vital E=essential & N=normal based on
fitted in each unit of equipment/instrument manufacturer's experience
34
15 SUPPLIER'S PART NUMBER SPIR APPROVAL DATE
Enter the supplier's unique identification number (Originate Part Manufacturer) of the items Final approval date for action by PMC
from third party manufacturers ("bought- out items") such as ball bearings, oil seals,
mechanicals, gaskets, instruments, electrical parts such as fuses, relays etc.
16 MESC OR SAP NUMBER 35 PLANNED COMMISSIONING DATE
Enter the IOCL SAP material code number Planned commission date to be entered by Project team
State delivery time of spare part to IOCL Gujarat Refinery (JR) Additional information not covered on previous columns may be filled in here.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE-4 Page 1 of 2
ANNEXURE A-XVII
Project :
Contractor:
W. O. No. :
Type of Reimbursable Taxes &
Invoice For the main item in the document
Supplier Date of Duties
date Name of GSTIN of Inward
Sr. Type of Inv LR (Manufacturer/ Goods Use of
the The register
No. Document No. No. Frist / Second received Assessable GST GST Material Sub-
DD/MM/YY Supplier Supplier Sr. No. Description UOM QTY.
Stage Dealer/ at Site. Value (%) Amount heading
YY
Importer)
Grand
0.00 0.00
Total
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
ANNEXURE A-XVIII
MSME
ANNEXURE A-XVIII
MSME
“As per GOI policy for Public Procurement Policy for Micro and Small Enterprises (MSEs) order
2012, the procurement of materials and services, purchased through MSEs are to be reported to
Ministry, which includes the sub contracts awarded by large enterprises.
As a part of compliance to the above order, bidders are required to submit the report of
procurements of materials and services taken from MSEs as per enclosed format”.
1.2 All efforts are to be made by LSTK vendors/contractors to encourage procurement from Micro and
Small Enterprises (MSEs) through their sub- contract work procurements. LSTK to ensure that the
MSEs are registered under Udyog Aadhar Memorandum by the Ministry of Micro, small and
Medium Enterprises MSME as per circular no F. No. 21(17)/2016-MA dtd 06.04.2018. Circular
attached as Attachment – B.”
1.3 Monthly report for purchase of material / services from MSE bidders in the enclosed format
(Attachment-A ) to be submitted by LSTK agency to IOCL.
1.4 The report shall be signed by Authorised person of LSTK Contractor.
1.5 IOCL will be at liberty to cross check / verify the details provided in the report as and when required.
1.6 In case no order / job is awarded to MSE’s the report shall be submitted as NIL.
ANNEXURE A-XVIII
MSME
MSME
Attachment-B
ANNEXURE A-XVIII
MSME
To,
All CPSEs
Subject: Amendment to Public Procurement Policy for Micro and Small Enterprises (MSEs)
Order, 2012 Implernentaion-reg
Sir,
As you may be aware that Ministry of Micro, Small and Medium Enterprise (MSME),
Government of India has notified Public Procurement Policy for Micro and Small Enterprises
(MSEs) Order, 2012 which mandates 20% of annual procurement by the Central Ministries/
Departments and CPSEs from MSEs including 4% from MSEs owned by SC/ST entrepreneurs.
This Policy has become mandatory w.e.f. 1st April, 2015.
It has been felt that an enhancement of benchmark preference from 20% to 25% and 3%
reservation for women would further help the MSEs immensely in the Government's 'Make in
India' initiative. Accordingly, a proposal to make amendment in the Public Procurement Policy
for MSEs Order, 2012 has been submitted to the Cabinet and Cabinet has approved the
following:-
It is therefore requested to kindy implement the above and also indicate the procurement
made from MSEs owned by women for which link has been already provided in the MSME
Sambandh Portal.
I~ y~~ faithfully,
~~~
PUBLISHED BY AUTHORITY
~. ~~l(!iq'lf~~
atmr
~~,9~,2018
2. ~ ~&'lf afR ~ ~ (~) ~ ~ fl14"1 f.l Cfi"SfTtlUT -;ftfcf 31R!iT, 2012 (fjffi ~ ~ l:fs:mT \rei
31Rf<T~ If<IT ~ if ~ ~ m~ afR!ir;<{ "20 mrmr" ~ ~ "25 m!ilCf" ~ ~ afR f<r;<{~
~fcl;1n-~1
3. ~ 3lR!iT~~ 4 ~~ f.'l<;j fBRl a 4uiT~;;rn:;rrr:-
"4 'P.$Tarr~ t41f?lt<!
crm~&'lf afR~~~~fufq-~1 ~ afR~~~~
~~~~ 25 m!ilcf~~~~ m~~ P-lII1l~~~ am:~~irmR~~
3 m!llCf CfiT~ f.tnh! mr ~I
[1llT. B". 21(22)/2018-~
(]l1 ~ fi:tm, 3f<R ~ afR fcrcrnr~
/
2 THE GAZETIE OF INDIA : EXTRAORDINARY [PART II-SEC. 3(ii)]
1. (i) This Order may be called the Public Procurement Policy for Micro and Small Enterprises
(MSEs) Amendment Order, 2018.
(ii) This shall come into force on the date of its publication in the Official Gazette.
2. Throughout the Public Procurement Policy for Micro and Small Enterprises (MSEs) Order, 2012,
(hereinafter referred to as the said Order), for the figures and word "20 'per cent", wherever they occur, the
figures and word "25 per cent" shall be substituted.
3. After paragraph 4 of the said Order, the following paragraph shall be inserted, namely:-
"4A. Special provision for Micro and Small Enterprise owned by women. Out of the total annual
procurement from Micro and Small Enterprises, 3 per cent from within the 25 per cent target shall be
earmarked for procurement from Micro and Small Enterprises owned by women.
[F. No. 21(22)-2018-MA]
RAM MOHAN MISHRA, Addl. Secy. & Development Commissioner
Uploaded by Dte. of Printing at Government of India Press. Ring Road, Mayapuri, New Delhi-l l 0064
and Published by the Controller of Publications, Delhi-l100S4.
MANOJ Digitally signed by
MANOJ KUMAR VERMA
KUMAR Date: 2018.11.10
VERMA 08:53:57 +05'30'
/
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
ANNEXURE A-XIX
ANNEXURE TO SCC
ANNEXURE A-XX
ANNEXURE TO SCC
ANNEXURE TO SCC
2.8 Semi-Finished Steel shall mean Ingots, billet, blooms and slabs, which can be subsequently
processed to finished steel.
2.9 Finished Steel shall mean Flat and Long products, which can be subsequently processed into
manufactured items.
2.10 L1 means the lowest tender or the lowest bid or the lowest quotation received in a tender,
bidding process or other procurement solicitation as adjudged in the evaluation process as per
the tender or other procurement solicitation.
2.11 Margin of purchase preference means the maximum extent to which the price quoted by a
domestic supplier may be above L1 for the purpose of purchase preference. In case of DMI&SP
policy, the margin of purchase preference shall be 20% for items in Appendix B.
2.12 Iron & Steel Product(s) shall mean such iron and steel product(s) which are mentioned in
Appendix A.
2.13 Domestic value addition shall be the net selling price (invoiced price excluding net domestic
taxes and duties) minus the landed cost of imported input materials at the manufacturing plant
in India (including all customs duties) as a proportion of the net selling price, in percent. The
‘domestic value addition’ definition shall be in line with the DPIIT(formerly DIPP) guidelines, and
shall be suitably amended in case of any changes by DPIIT in the future. For the purpose of this
policy document, domestic value addition and local content have been used interchangeably.
3 Exclusions
3.1 Waivers shall be granted by the Ministry of Steel to all such Government procurements subject
to the below conditions.
3.1.1 Where specific grades of steel are not manufactured in the country, or
3.1.2 Where the quantities as per the demand of the project cannot be met through domestic sources
The exclusion requests shall be submitted to the Standing Committee along with
sufficient proof of unavailability of domestically manufactured iron & steel products
4 Standing Committee
A Standing Committee under the Ministry of Steel (MoS) to be chaired by the Secretary
(Steel), shall be constituted to oversee the implementation of the policy. The Committee
shall comprise of experts drawn from Industry / Industry Association / Government
Institution or Body / Ministry of Steel (MoS). The said Committee in MoS shall have the
mandate for the following:
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
ANNEXURE TO SCC
5.4 Minimum domestic value addition requirement suggested for iron and steel products in Appendix
A, and for capital goods for manufacturing iron and steel products in Appendix B have been
decided on the basis of factors such as domestic supplier base, number of suppliers and import
to consumption ratio.
5.5 The domestic value addition requirement norm shall be so calibrated that it reflects the
average/above average manufacturing capability of the domestic industry for the iron & steel
products at a point of time. This shall be suitably reviewed by the Standing Committee from time
to time and amended, if required with the approval of Ministry of Steel.
6 Tender procedure for procurement by government and government agencies
6.1 The procuring/ Government agencies shall follow standard procurement procedures, in
accordance with instructions of Ministry of Finance and CVC while adhering to DMI&SP. The
policy shall come into effect from the date of its notification in all tenders where price bid have
not been opened.
6.2 The tender document, for procurement of both Goods as well as for EPC contracts, should
explicitly outline the qualification criteria for adherence to minimum prescribed domestic value
addition by the bidder for iron and steel products and capital goods for manufacturing iron &
steel products(as indicated in Appendix A and Appendix B)
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
ANNEXURE TO SCC
self-certification to the procuring Government agency declaring that the iron & steel
products are domestically manufactured in terms of the domestic value addition
prescribed. For capital goods in Appendix B, the bidder shall furnish the certification
issued by the statutory auditor to the domestic manufacturer declaring that the capital
goods are domestically manufactured in terms of the domestic value addition prescribed.
The bidders who are sole selling agents / authorized distributors / authorized dealers /
authorized supply houses of the domestic manufacturers of iron & steel products are
eligible to bid on behalf of domestic manufacturers under the policy. The bidder shall
furnish the Affidavits of self-certification issued by the domestic manufacturers and the
certifications issued by the statutory auditors, to the procuring agency declaring that the
iron & steel products are domestically manufactured in terms of the domestic value
addition prescribed. The Affidavit of self-certification shall be furnished in Form 1
attached to these guidelines.
8.2 It shall be the responsibility of the domestic manufacturer to ensure that the products so
claimed are domestically manufactured in terms of the domestic value addition
prescribed for the product. The bidder shall also be required to provide a domestic value
addition certificate on half-yearly basis (Sep 30 and Mar 31), duly certified by the
Statutory Auditors of the domestic manufacturer, that the claims of domestic value
addition made for the product during the preceding 6 months are in accordance with the
Policy. Such certificate shall be filed within 60 days of commencement of each half year,
to the concerned Government agencies and shall continue to be filed till the completion
of supply of the said products.
8.3 The procuring agency shall accept the Affidavit of self-certification regarding domestic
value addition in a steel product submitted by a bidder. It shall not normally be the
responsibility of procuring agency to verify the correctness of the claim. The onus of
demonstrating the correctness of the same shall be on the bidder when asked to do so.
8.4 In case a complaint is received by the procuring agency or the concerned Government
Agency against the claim of a bidder regarding domestic value addition in iron & steel
products, the procuring agency shall have full rights to inspect and examine all the related
documents and take a decision. In case any clarification is needed, matter may be
referred to MoS with a request for technical assistance.
8.5 Any complaint referred to the Government Agency shall be disposed off within 4 weeks
of the reference along with submission of all necessary documents. The bidder shall be
required to furnish the necessary documentation in support of the domestic value addition
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
claimed in iron & steel products to the Government Agency within 2 weeks of filing the
complaint.
8.6 In case, the matter is referred to the Ministry of Steel, the grievance redressal committee
setup under the MoS shall dispose of the complaint within 4 weeks of its reference and
receipt of all documents from the bidder after taking in consideration, the view of the
Government Agency. The bidder shall be required to furnish the necessary
documentation in support of domestic value addition claimed in iron & steel products to
the grievance redressal committee under MoS within 2 weeks of the reference of the
matter. If no information is furnished by the bidder, the grievance redressal committee
may take further necessary action, in consultation with Government Agency to establish
bonafides of claim.
8.7 The cost of assessing the prescribed extent of domestic value addition shall be borne by
the procuring agency if the domestic value addition is found to be correct as per the
certificate. However, if it is found that the domestic value addition as claimed is incorrect,
the cost of assessment will be payable by the bidder who has furnished an incorrect
certificate. The manner of enforcing the same shall be defined in the tender document.
9 Sanctions
9.1 Each Government Agency shall clearly define the penalties, in case of wrong declaration
by the bidder of the prescribed domestic value addition, in the tender document. The
penalties may include forfeiting of the EMD, other financial penalties and blacklisting of
such manufacturer/ service provider.
9.2 In case of reference of any complaint to MoS by the concerned bidder, there would be a
complaint fee of Rs. 10 Lakh or 0.2 % of the value of the DMI&SP being procured (subject
to a maximum of Rs. 20 Lakh), whichever is higher, to be paid by Demand Draft deposited
with the grievance redressal committee under MoS along with the complaint by the
complainant. In case, the complaint is found to be incorrect, the Government Agency
reserves the right to forfeit the said amount. In case, the complaint is found to be
substantially correct, deposited fee of the complainant would be refunded without any
interest.
10 Implementation monitoring by Ministry of Steel
10.1 The policy provisions shall be applicable for a period of 5 years from the date of
publication. The policy period may further be extended at the discretion of Ministry of
Steel.
10.2 MoS shall be the nodal ministry to monitor the implementation of the policy.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
10.3 All applicable agencies under DMI&SP policy shall ensure implementation of the policy
and shall annually, in the month of June, send a declaration indicating the extent of
compliance to the policy and reasons for noncompliance thereof, during the preceding
financial year.
Sl. Minimum
Indicative list of Iron & Steel Products Applicable
domestic value
No. HS code addition
requirement
Flat-rolled products of iron or non-alloy steel, of
1 7208 50%
a width of 600 mm or more, hot rolled, not clad, plated or
coated
Flat-rolled products of iron or non-alloy steel, of
2 7209 50%
a width of 600 mm or more, cold rolled (cold-reduced), not
clad, plated or coated
Flat-rolled products of iron or non-alloy steel, of
3 7210 50%
a width of 600 mm or more, clad, plated or coated
Flat-rolled products of iron or non-alloy steel, of a width of less
4 7211 35%
than 600 mm, not clad, plated or coated
Flat-rolled products of iron or non-alloy steel, of a width of less 35%
5 7212
than 600 mm, clad, plated or coated
Bars and rods, hot-rolled, in irregularly wound coils, of iron or 35%
6 7213
non-alloy steel
Other bars and rods of iron or non-alloy steel, not further 35%
7 worked than forged, hot rolled, hot-drawn or hot-extruded, but 7214
including those twisted after rolling
8 Other bars and rods of iron or non-alloy steel 7215 35%
9 Angles, shapes and sections of iron or non-alloy steel 7216 35%
10 Wire of iron or non-alloy steel 7217 50%
11 Flat-rolled products of stainless steel, of a width of 600 mm or 7219 50%
more
12 Flat-rolled products of stainless steel, of a width of less than 7220 50%
600 mm
Other bars and rods of stainless steel; angles, shapes and
13 7222 50%
sections of stainless steel
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
ANNEXURE TO SCC
Stranded wire, ropes, cables, plaited bands, slings and the 7312 15%
32
like, of iron or steel, not electrically insulated
Barbed wire of iron or steel; twisted hoop or single flat wire,
33 barbed or not, and loosely twisted double wire, of a kind used 7313 15%
for fencing, of iron or steel
Grill, netting and fencing, of iron or steel wire; expanded metal 7314 15%
34
of iron or steel
35 Chain and parts thereof, of iron or steel 7315 15%
36 Anchors, grapnels and parts thereof, of iron or steel 7316 15%
37 Articles of iron and steel 7317 15%
38 Articles of iron and steel 7318 15%
39 Articles of iron and steel 7319 15%
40 Springs and leaves for springs, of iron or steel 7320 15%
Stoves, ranges, grates, cookers (including those with
41 subsidiary boilers for central heating), barbecues, braziers, 7321 15%
gas-rings, plate warmers and similar non-electric domestic
appliances, and parts thereof, of iron or steel
Radiators for central heating, not electrically heated, and
parts thereof, of iron or steel; air heaters and hot air
42 7322 15%
distributors, not electrically heated, incorporating a motor-
driven fan or blower, and parts thereof, of iron or steel
43 Tables and similar household articles and parts thereof, of 7323 15%
iron or steel
44 Sanitary ware and parts thereof, of iron or steel 7324 15%
45 Other cast articles of iron or steel 7325 15%
46 Electrical steel and other articles of iron or steel 7326 15%
47 Railway or tramway passenger coaches, not self-propelled 8605 50%
48 Railway or tramway goods vans and wagons, not self- 8606 50%
propelled
Parts of railway or tramway locomotives or rolling-stock; such 8607 50%
49
as bogies, bissel-bogies, axles and forged wheels, and parts
thereof
Products included in descriptions are indicative; all products under the specified HS codes are
included as part of the appendix
Appendix B
Indicative list of capital goods(non-exhaustive) for manufacturing iron & steel products
Minimum
Sl. domestic
Plant shop Capital goods
value addition
No.
requirement
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
ANNEXURE TO SCC
ANNEXURE TO SCC
*Items in appendix B are an indicative list of capital goods for manufacturing steel, the list is not
exhaustive. All capital goods for steel manufacturing shall be considered for purchase
preference under the policy with a minimum domestic value addition requirement of 50%
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
Form-1
Format for Affidavit of Self Certification regarding Domestic Value Addition in Iron & Steel
Products/capital goods to be provided on Rs.100/- Stamp Paper Date:
I _ _ S/o, D/o, W/o, _ Resident of _
hereby solemnly affirm and declare as under:
That I will agree to abide by the terms and conditions of the policy of Government of India
issued vide Notification No: .
That the information furnished hereinafter is correct to the best of my knowledge and belief
and I undertake to produce relevant records before the procuring agency (ies) for the
purpose of assessing the domestic value addition.
That the domestic value addition for all inputs which constitute the said iron & steel
products has been verified by me and I am responsible for the correctness of the claims
made therein.
That in the event of the domestic value addition of the product mentioned herein is found
to be incorrect and not meeting the prescribed value-addition criteria, based on the
assessment of procuring agency (ies) for the purpose of assessing the domestic value-
addition, I will be disqualified from any Government tender for a period of 36 months. In
addition, I will bear all costs of such an assessment.
That I have complied with all conditions referred to in the Notification No. _
wherein preference to domestically manufactured iron & steel products in Government
procurement is provided and that the procuring agency (ies) is hereby authorized to forfeit
and my EMD. I also undertake to pay the assessment cost and pay all penalties as specified
in the tender document.
I agree to maintain the following information in the Company's record for a period of 8 years
and shall make this available for verification to any statutory authority.
i. Name and details of the Bidder (Registered Office, Manufacturing unit location, nature of
legal entity)
ii. Date on which this certificate is issued
iii. Iron & Steel Products for which the certificate is produced
iv. Procuring agency to whom the certificate is furnished
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
v. Percentage of domestic value addition claimed and whether it meets the threshold value
of domestic value addition prescribed
vi. Name and contact details of the unit of the manufacturer (s)
vii. Net Selling Price of the iron & steel products
viii. Freight, insurance and handling till plant
ix. List and total cost value of input steel (imported) used to manufacture the iron & steel
products
x. List and total cost of input steel which are domestically sourced.
xi. Please attach domestic value addition certificates from suppliers, if the input is not in
house.
xii. For imported input steel, landed cost at Indian port with break-up of CIF value, duties &
taxes, port handling charges and inland freight cost.
ANNEXURE TO SCC
ANNEXURE A-XXI
ANNEXURE TO SCC
Following Electronic Products are notified under the Public Procurement (Preference to
Make in India) Order 2017:
1. The Percentage of domestic value addition in terms of Bill of Material (BOM) required for the
(tendered DMEP item) to qualify as domestically manufactured electronic products (DMEP)
is (as mentioned in notification for the tendered DMEP item) %.
2. The local supplier at the time of bidding shall provide self-certification that the item offered
meets the minimum local content and shall give details of the location(s) at which the local
value addition is made.
3. In cases of procurement for a value in excess of Rs. 10 crores, the local supplier shall provide
a certificate from the statutory auditor or cost auditor of the company (in the case of
companies) or from a practicing cost accountant or practicing chartered accountant (in
respect of suppliers other than companies) giving the percentage of the local content.
4. All other terms & conditions including preference for procurement for DMEP item, criteria for
BOM of the DMEP item to be classified as Domestic, procedure for calculating local
content/domestic value addition, verification of local content/domestic value addition etc.
shall be as per Notification No. 33(1)/2017-IPHW dated 14.09.2017 of Ministry of Electronics
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
ANNEXURE TO SCC
For Purchase preference, Public Procurement Policy 2012 (PPP-2012 for MSEs)
benefits shall receive precedence over DMEP-2017 benefits as is being followed in
case of application of PPLC policy.
The bidder shall declare their preference for seeking Purchase Preference benefit as
MSE under PPP-2012 or as Local Supplier under DMEP-2017.
Abbreviation:
1) MSE- Micro and Small Enterprises
2) DM- Local Supplier
3) GN- Bidder(s) not falling in either category 1 or 2 above.
Here DM, MSE are those who are eligible for Purchase Preference as per the above mentioned
policies.
ANNEXURE TO SCC
3(b) When GN is L1 25% to MSE • If multiple MSE meet the condition, the
and MSE is within 37.5% to DM (i.e. preferential quantity shall be
15% and DM is 50% of proportionately distributed amongst them.
within 20% of L1 remaining 75%) • If all MSE fails to match L-1 rate, the
37.5% to GN quantity shall be awarded in the ratio of
50:50 to L1 GN and DM.
• If the lowest priced DM fails to match L-1
rate or accepts less than the offered qty.,
next DM shall be offered to match L1 rate
for the remaining qty. and so on. In case
qty. is still left uncovered on local
suppliers, then such balance qty. shall be
awarded to L-1 GN.
Notes:
• All splits & purchase preference will be subject to matching L1 rates.
• In case more than one DM (within 20% of L1) quote the same rate, the preferential
quantity shall be shared proportionately (to tendered quantity).
• Qty. during splitting shall be rounded to next higher whole number in order of
preference.
ANNEXURE TO SCC
ANNEXURE TO SCC
ANNEXURE A-XXII
FORM OF CONTRACT
FORM OF CONTRACT
WHEREAS
The OWNER desires to have executed the work of “……….. ……………. …………….
…………… ……………” (Tender No : ……………..) more specifically mentioned and
described in the contract documents (hereinafter called the ''work'' which expression
shall include all amendments therein and/or modifications thereof) and has accepted
the tender of the CONTRACTOR for the said work.
ARTICLE – 1
CONTRACT DOCUMENTS
1.1 The following documents shall constitute the ‘Contract documents’, namely:
2.1 The CONTRACTOR shall perform the said work upon the terms and conditions
and within the time specified in the Contract Documents.
ARTICLE -3
COMPENSATION
3.1 Subject to and upon the terms and conditions contained in the Contract
documents, the OWNER shall pay CONTRACTOR compensation as specified in the
Contract documents upon the satisfactory completion of the work and/or otherwise
as may be specified in the Contract documents.
ARTICLE -4
JURISDICTION
4.1 Notwithstanding any other court or courts having jurisdiction to decide the
question(s) forming the subject matter of the reference if the same had been the
subject matter of a suit, any and all actions and proceedings arising out of or relative
to the contract (including any arbitration in terms thereof) shall lie only in the court of
competent civil jurisdiction in this behalf at New Delhi (where this Contract has been
signed on behalf of the OWNER) and only the said Court(s) shall have jurisdiction to
entertain and try any such action(s) and/or proceeding(s) to the exclusion of all other
Courts.
ARTICLE -5
ENTIRE CONTRACT
ARTICLE -6
NOTICES
6.1 Subject to any provisions in the Contract documents to the contrary, any notice,
order or communication sought to be served by the CONTRACTOR on the OWNER
with reference to the Contract shall be deemed to have been sufficiently served upon
the OWNER (notwithstanding any enabling provisions under any law to the contrary)
only if delivered by hand or by Registered Acknowledgment Due Post to the
Engineer-in-Charge as defined in the General Conditions of Contract.
6.2 Without prejudice to any other mode of service provided for in the Contract
Documents or otherwise available to the OWNER, any notice, order or other
communication sought to be served by the OWNER on the CONTRACTOR with r
efer ence to the Contr ac ,t s hall be deemed to have been s uffic iently served if
delivered by hand or through Registered Post Acknowledgement Due to the principal
office of the CONTRACTOR ……….. ………… ………….. ……………… or to the
ARTICLE-7
WAIVER
7.1 No failure or delay by the OWNER in enforcing any right or remedy of the
OWNER in terms of the Contract or any obligation or liability of the CONTRACTOR
in terms thereof shall be deemed to be a waiver of such right, remedy, obligation or
liability, as the case may be, by the OWNER and notwithstanding such failure or
delay, the OWNER shall be entitled at any time to enforce such right, remedy,
obligation or liability, as the case may be.
ARTICLE-8
NON-ASSIGNABILITY
The Contract and benefits and obligations thereof shall be strictly personal to the
CONTRACTOR and shall not on any account be assignable or transferable by the
CONTRACTOR.
IN WITNESS WHEREOF the parties hereto have executed this Contract in duplicate
the place, day and year first above written.
1. 1.
2. 2.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18) IOCL
GUJARAT REFINERY
ANNEXURE TO SCC
ANNEXURE A-XXIII
BG FORMAT FOR SECURITY DEPOSIT
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18) IOCL
GUJARAT REFINERY
ANNEXURE TO SCC
APPENDIX-VII
Dear sir,
In consideration of Indian Oil Corporation Limited (Refineries Division) (hereinafter called the
Corporation which expression shall include its successors and assigns) having awarded certain Work
for and relative to the installation of a (Name of Project) at ……………… of the Corporation to (Name
& address of Contractor) (hereinafter called the “CONTRACTOR”) upon certain terms and conditions
mentioned in the Corporation’s Letter of Acceptance No. ……….. Dated …………… read with the
CONTRACTOR’s bid and the relative Bid Documents (hereinafter collectively called the “Contract”
which expression shall include any formal Contract entered into between the Corporation and the
CONTRACTOR in supersession of the said Letter of Acceptance and all amendments and/or
modifications in the Contract) inclusive of the condition that the Contractor shall cause to be furnished
a Bank Guarantee from a Scheduled Bank in India (which includes the Indian Branch of a foreign
Bank acceptable to the Corporation) as hereinafter appearing in lieu of cash Security deposit.
We ………………. (Name of the Bank) a body corporate registered/constituted under the laws
of………………….. (hereinafter called the “BANK” which expression shall include its successors and
assigns) with the intent to bind the Bank and its successors and assigns, do hereby unconditionally
and irrevocably undertake to pay the Corporation at the project office of the Indian Oil Corporation at
New Delhi on first demand in writing without protest or demur or proof of condition any and all
amounts from time to time demanded by the Corporation from the Bank with reference to this
Guarantee/Undertaking upto an aggregate limit of US $ ……………………. (United States Dollars
…………………………….. only) and Indian Rupees ……………………….. (Rupees
…………………………….. only).
i) The Guarantee/Undertaking herein contained shall remain in full force and effect during
the entire period that would be taken for the performance for the Contract and until the
claims of the Corporation relative thereto are satisfied and/or discharged and the
Corporation accordingly discharges this Guarantee/Undertaking subject, however, that
the Corporation shall have no claim under this Guarantee/Undertaking after midnight of
…….. 20__ , unless a notice of the claim under this Guarantee/ Undertaking has been
served on the Bank before the expiry of the said date, in which event the same shall be
valid notwithstanding that the same is enforced after the expiry of the said date, provided
that the Bank shall upon the written request of the Corporation made at any time within 6
(six) months after the expiry of the said date extend this Guarantee/Undertaking for a
further 6 (Six) months from the said date within which the Corporation may make a
demand
ii) The Corporation shall have the fullest liberty without reference to the Bank and without
affecting in any way the liability of the Bank under this Guarantee/ Undertaking, at any
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18) IOCL
GUJARAT REFINERY
ANNEXURE TO SCC
time and/or from time to time anywise to vary the Contract and/or any of the terms and
conditions thereof or relative to the Security deposit or to extend time of performance of
the Contract in whole or part or to postpone for any time and/or from time to time any of
the obligations of the CONTRACTOR and/or the power(s) exercisable by the Corporation
against the CONTRACTOR and either to enforce or forbear from enforcing any of the
terms and conditions of or governing the Contract or the Security deposit or the securities
available to the Corporation or any of them and the Bank shall not be released from its
liability under these presents and the liability of the Bank shall remain in full force and
effect notwithstanding any exercise by the Corporation of the liberty with reference to any
or all the matters aforesaid or by reason of time being given to the CONTRACTOR or any
or all the matters aforesaid or by reason of time being given to the CONTRACTOR or any
other forbearance, act or omission on the part of the Corporation or any indulgence by the
Corporation to the CONTRACTOR or of any other act, matter or thing whatsoever which
under the law relating to sureties could but for this provision, have the effect of releasing
the Bank from its liability hereunder or any part thereof and the Bank doth hereby
specifically waive any and all contrary rights.
iii) It shall not be necessary for the Corporation to proceed against the CONTRACTOR
before proceeding against the Bank and the Guarantee/Undertaking herein contained
shall be enforceable against the Bank notwithstanding the existence of any other security
for any indebtedness of the CONTRACTOR to the Corporation (including relative to the
security deposit) and notwithstanding that any such security shall at the time when claim
is made against the Bank or proceeding taken against the Bank hereunder, be
outstanding or unrealised.
iv) The amount stated by the Corporation in any demand, claim or notice as due to the
Corporation from the CONTRACTOR shall as between the Bank and the Corporation for
the purpose of these presents be conclusive of the amount payable by the Bank to the
Corporation hereunder.
v) The liability of the Bank to the Corporation under this Guarantee/Undertaking shall remain
in full force and effect notwithstanding the existence of any difference or dispute between
the CONTRACTOR and the Corporation, the CONTRACTOR and the Bank and/or the
Bank and the Corporation, or otherwise howsoever touching or affecting these presents
or the liability of the CONTRACTOR to the Corporation, and notwithstanding the
existence of any instructions or purported instructions by the CONTRACTOR or any other
person to the Bank not to pay or for any cause withhold or defer payment to the
Corporation, under these presents, with the intent that notwithstanding the existence of
such difference, dispute or instructions, the Bank shall be and remain liable to make
payment to the Corporation in terms hereof.
vi) The Bank shall not revoke this Guarantee/Undertaking during its currency except with the
previous consent of the Corporation in writing and also agrees that any change in the
constitution of the CONTRACTOR or of the Bank or of the Corporation shall not
discharge the Bank’s liability hereunder.
vii) Without prejudice to any other mode of service, a demand or claim or other
communication may be transmitted by the Corporation to the Bank either by post or by
fax. If transmitted by fax, the transmission shall be complete as soon as acknowledged by
the Bank.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18) IOCL
GUJARAT REFINERY
ANNEXURE TO SCC
c) The Bank shall be released and discharged from all liability under this
Guarantee/undertaking unless a written claim or demand is issued to the Bank
on or before _____________ (at least 6 months from the said expiry date in S.N.
(viii) b)) or the date of expiry of any extension(s) thereof if this
guarantee/undertaking has been extended.”.
ix) The Bank doth hereby declare that Shri …………………………….. (Name and
Designation of the person) is authorised to sign this Guarantee/Undertaking on behalf of
the Bank and to bind the Bank thereby.
Yours faithfully,
For ___________________________
Signature
*******************************
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Table of Contents
1. GENERAL ...................................................................................................................... 6
1.1 Purpose .......................................................................................................................... 6
1.2 Project Overview............................................................................................................. 6
2. PROJECT PROCEDURES ............................................................................................. 7
2.1 General .......................................................................................................................... 7
2.2 Project Procedures to be issued by Contractor ............................................................... 7
3. ORGANISATION ............................................................................................................ 9
3.1 PMC / OWNER’s Organization........................................................................................ 9
3.2 CONTRACTOR's Organization ....................................................................................... 9
4. COMMUNICATION ....................................................................................................... 10
4.1 General......................................................................................................................... 10
4.2 Correspondence Requirement ...................................................................................... 10
4.3 Type of Correspondence............................................................................................... 11
4.4 Documents Register ..................................................................................................... 12
4.5 Relations with Authorities, Certifying Agencies etc. ....................................................... 12
4.6 Public Relations ............................................................................................................ 12
4.7 Teleconference / Video Conference/ Meetings through Internet based platforms .......... 12
4.8 Communication with OWNER's Other CONTRACTORS ............................................... 12
5. COORDINATION .......................................................................................................... 13
5.1 Purpose ........................................................................................................................ 13
5.2 Scope ........................................................................................................................... 13
5.3 Addresses of Owner/Parties and Their Representatives ............................................... 14
5.4 Communication and General Correspondence.............................................................. 15
5.5 Project Coordination Meetings ...................................................................................... 16
5.6 Drawing/Documents to be reviewed by PMC / OWNER ................................................ 16
6. MEETINGS ................................................................................................................... 16
6.1 Kick-Off Meeting ........................................................................................................... 16
6.2 Weekly Meeting ............................................................................................................ 17
6.3 Monthly Meeting ........................................................................................................... 17
6.4 Special Meeting ............................................................................................................ 18
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
1. GENERAL
1.1 Purpose
The purpose of this document is to define the PMC / OWNER (Indian Oil Corporation
Limited) and various Contractors/ Agencies baseline strategy for execution of the scope of
works for IOCL Gujarat Refinery LuPech project.
This Project Execution Plan (PEP) defines the Gujarat Refinery LuPech project and
describes baseline planning, assumptions, constraints, roles, responsibilities, authorities,
management interactions and interface management necessary to successfully execute
this project.
This PEP provides necessary guidance to Project Manager and the project team members.
This document will be reviewed and modified in line with the level of project realization
during the Project execution period.
Gujarat Refinery (Vadodara) has a capacity to process 13.7 MMTPA of crude oil, with crude
basket comprising of 55% high Sulphur crude (7.6 MMTPA) and 45% low Sulphur
indigenous crude (6.1 MMTPA). In addition to BS-III/BS-IV fuel products, the refinery has
also the capacity to produce a wide range of specialty products such as benzene, toluene,
Food Grade Hexane & LAB. Currently refinery is executing projects to upgrade the entire
gasoline and diesel to BS-IV specification by revamp of existing DHDT, DHDS and VGO
hydrotreater units.
Further, with objective of meeting the guidelines established in Auto Fuel policy 2025,
wherein refinery would be required to manufacture 100% BS-VI fuels, IOCL is also
executing BS VI project under which a new DHDT unit, a FCC Gasoline Desulphurization
Unit and new HGU are envisaged.
IOCL has started the process of value addition by implementation of petrochemical and
lube integration project (LuPech). The project envisages raising the capacity of the
Vadodara refinery in Gujarat from 13.7 MMTPA to 18 MMTPA and building a 500KTPA
Polypropylene (PP) plant and a 235 KTPA Lube Oil Base Stock (LOBS) unit.
This Package-4 Contract has been developed for realizing the following unit as part of
LuPech Project:
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Sl No. Description
Buildings:
Sl No. Description
1 Electrical Substation for LuPech Power Distribution Facility for LuPech Project
2. PROJECT PROCEDURES
2.1 General
CONTRACTOR shall prepare and submit to PMC / OWNER upon the dates stated
hereafter, of the various sections of the PROJECT PROCEDURES. The Project
Procedures shall comprise planning, organization, control and other documents
necessary for efficient co-ordination, management and execution of the work.
Within twenty-one (21) days of the receipt of each such section the PMC / OWNER will
respond with comments, if any.
Within twenty-one (21) days of receipt of the PMC / OWNER comments, CONTRACTOR
shall revise and re-issue the project procedure for approval upon which it shall be put
into effect.
The contractor shall prepare and submit to PMC/ OWNER, the following procedures as
minimum level of documents to demonstrate their ability and strategy for execution of the
project:
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
The above procedure should provide sufficient details to enable PMC / OWNER
exercise Project , schedule , Cost and QHSE Control during the entire duration of the
Project.
3. ORGANISATION
PMC / OWNER shall appoint their representative who shall administer and co-ordinate
PMC / OWNER’s obligation during the contract execution including the issuance
instruction, order and certificate as necessary.
3.2.1 CONTRACTOR shall prepare and submit the relevant documents as stated in Sl. No. 2.2
for approval of PMC / OWNER.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
CONTRACTOR shall provide detailed structure of its project team, the personnel for
each functions / roles/ responsibility (i.e. Project Management, Electrical, Civil etc.),
showing the positions, inter relationship, names and locations from where it intends to
execute the work. CONTRACTOR shall perform design and engineering at same location
only. The structure of the team could vary in its terms of numbers / field of expertise /
location of work for different phases of the work. An organization chart for the overall
project structure shall be provided and a separate organization chart showing Home
Office structure and any other organization that may assist the CONTRACTOR for
execution of the project. Organization chart shall indicate names, key personnel / show
their line of responsibility & reporting positions.
CONTRACTOR's ORGANISATION Chart shall be updated as and when there are changes
in CONTRACTOR's personnel. Any such changes in personnel shall be notified in
writing to PMC / OWNER for approval prior to the change.
3.2.2 CONTRACTOR shall upon effective date, or in no event later than one week after effective
date, appoint a representative who shall have full authority to act on behalf of
CONTRACTOR in receiving instructions and in the administration of the contract.
3.2.3 CONTRACTOR shall upon PMC / OWNER's request furnish all information concerning
CONTRACTOR, his Sub-CONTRACTORS and their representative assigned personnel
and agents as may be required for submission to any applicable government agency,
authority or regulatory body.
4. COMMUNICATION
4.1 General
This communication procedure shall be applied for all correspondence among OWNER,
PMC and CONTRACTOR. All communications shall clearly indicate the unit involved in
the Subject and shall be mutually discussed and agreed.
4.3.1 Letter
All letters from CONTRACTOR’s office shall adhere to the requirements given in Project
Coordination & communication procedure of the CONTRACTOR which shall be reviewed
and approved by PMC/OWNER after award of contract
Scanned copy of Letters shall be sent by email and hard copy by courier. Each letter shall
be limited to one subject in-principle.
E-mail address of all responsible persons authorized to correspond for this project should
be available with all the parties for effective and fastest mode of communication, over
and above letter.
4.3.3 Transmittals
Documents/drawings shall be sent with a transmittal, listing all the documents covered
under the transmittal in duplicate. The list of document shall include document title,
document number, revision number, number of sheets, type of document, purpose such
as for Review/information/Approval etc.
Contractor shall provide necessary details of their Electronic Data Management System
to be used for the execution of the project and how the various types of documents are
stored, transmitted, controlled and safeguarded against loss of information.
submission of hard copy for contractual purposes as and when required by PMC/OWNER.
Minutes of meeting shall be issued for confirmation of discussion made in all official
meetings.
All contacts with the Authorities, Certifying Agencies etc. shall be organized by the
CONTRACTOR in co-operation with PMC / OWNER. Scheduling of meetings with
such bodies shall be arranged by the CONTRACTOR in consultation with PMC /
OWNER, and CONTRACTOR shall give written notice to PMC / OWNER at least two
weeks in advance of the required meeting date. Minutes of meetings shall be prepared
and distributed according to OWNER's instruction.
All draft press releases, information hand outs and photographs for publication relating
to the contract shall be submitted for review and approval of PMC / OWNER prior to
release.
5. COORDINATION
5.1 Purpose
5.1.1 This co-ordination procedure has been prepared in order to give guidance to the
CONTRACTOR to develop and submit a detailed procedure to be used for a smooth
and orderly administrative relationship among related parties for the “LuPech” (J18)
PROJECT” for Indian Oil Corporation Limited’s, Gujarat Refinery, INDIA.
5.1.2 The procedure hereunder neither abrogates nor modifies the provisions of the Contract,
but rather stipulates the methods and procedures by which the administrative relationship
shall be executed for efficient and effective implementation.
5.1.3 The procedure submitted by the contractor which is reviewed and approved by PMC/
OWNER shall be binding for all the parties and it may be modified by the contractor in
agreement with PMC/OWNER as the job progresses, for convenience for efficient /
effective implementation among the parties concerned.
5.2 Scope
Unless otherwise agreed, the normal communication routes among the related
parties are established as shown in the schematic hereunder:
IOCL
PMC
Project Manager
Vendors (LLI/Critical) /
LSTK CONTRACTORS
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
5.3.1 OWNER
5.3.2 PMC
5.3.3 CONTRACTOR
CONTRACTOR securing the award of contract from OWNER shall provide details of their
offices involved in performing Engineering, Procurement, Construction management and
Site Management with responsible persons for correspondence.
i) Deputy Project Director of PMC is the sole contact point with OWNER as well as other
parties for all activities of the Project. All correspondence between PMC and
OWNER / other parties ( other contractors etc.,) shall be directly done by him or by his
authorized representative. Contractor shall address the communication to
Deputy Project Director of PMC or his authorized representative for any information
required from or to be passed on to OWNER / other parties.
ii) For signatory for communication, Deputy Director would authorize the Project
Manager to sign the letters. Deputy Director will correspond for important issues
regarding t h e contract, schedules etc. as deemed necessary.
Project Organization:
- CONTRACTOR organization chart with OWNER/PMC interfaces
- Work locations
Communication:
- Abbreviations
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
PMC or OWNER may take lead to organize the Project Coordination and/or progress
review meeting between OWNER/ CONTRACTOR and PMC for the purpose of the
smooth project execution. Agenda, place and time of the meetings shall be
communicated in advance and agreed to between the parties.
6. MEETINGS
Within two weeks of the EFFECTIVE DATE, a kick-off meeting will be held between
OWNER, PMC and CONTRACTOR at a venue decided by PMC / OWNER. The
meeting will cover following broad aspects:
PMC / OWNER may hold weekly progress review meetings at the work site and during
the initial phase of the work at CONTRACTOR's engineering or other work center
with CONTRACTOR in order to evaluate progress, i d e n t i f y problems and discuss
other matters relevant to the work and to review CONTRACTOR's weekly report.
PMC / OWNER shall hold monthly meetings with CONTRACTOR to review and
evaluate the overall status and progress of the work and other matters relating to the work
and to review CONTRACTOR's monthly report.
The agenda for the monthly meeting as far as possible shall be settled by agreement
five (5) working days before the meeting. Indicative agenda items for the meeting
are as below:
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
PMC / OWNER or CONTRACTOR may from time to time request a meeting to be held
in order to discuss a matter of an urgent nature and which cannot be left until the
weekly or monthly meeting, covering a specific matter, requiring a dedicated meeting.
In such circumstances, the party requesting the meeting shall contact the other party
and agree upon the agenda, attendees and timing of such meeting. Such
arrangements are subject to approval.
CONTRACTOR shall hold a Pre-Award Meeting with the selected Vendor or Sub-
CONTRACTOR (for major / critical equipment and package items) prior to
CONTRACTOR's award of a purchase order or sub-contract to ensure conformance
to all P M C / OWNER technical and commercial requirements.
Brief daily meeting shall be held during the mechanical completion and Pre-
commissioning/Commissioning period with an agenda covering:
CONTRACTOR shall give prior notice with reasonable time period (shall be 3 days in
case of Meetings where participants are in same location and at least 7 Days in case of
Meetings where participants are in different locations) to PMC / OWNER, for all meetings
identified above. PMC / OWNER shall attend any such meetings as deemed
necessary.
PMC / OWNER shall have the right, at its own discretion, to attend/not to attend any
such meeting.
Unless otherwise instructed by OWNER, meetings shall be held in PMC office and
shall be organized by PMC and chaired by PMC / OWNER.
CONTRACTOR shall prepare the minutes of all meetings between PMC / OWNER and
CONTRACTOR.
For ease of reference, minutes of meetings shall be divided into paragraphs with
sub-headings indicating the various topics discussed.
CONTRACTOR shall submit the MOM for all meetings to PMC / OWNER for REVIEW
and APPROVAL prior to formal issue.
The MOM shall be prepared and distributed to the participants and other designated
on the same day or at least within two (2) working days for all meetings except for the
daily meetings, for which MOM will be issued at the end of the meeting.
Any meeting may be convened at any other place, e.g. PMC / OWNER offices,
Sub-CONTRACTOR's offices, Government offices etc. when PMC / OWNER Consider
it to be useful to the progress of the project
7. ENGINEERING
Other specialists who are required shall also be deputed. The field engineering cell
shall be equipped with all their design Aids and effective communication network
facilities with their Home design center.
CONTRACTOR shall also transfer to WORK SITE all the required hardware and
software (including 3D system and workstations) for carrying out balance works at site,
as applicable. CONTRACTOR shall make available their Lead discipline engineers with
adequate experience for technical discussions and clarification at PMC / OWNER
office as and when required.
Drawings / documents listed therein are not exhaustive. Based upon MDR prepared by
CONTRACTOR, PMC / OWNER may revise the list of documents for Review/Approval.
CONTRACTOR shall prepare and update the MDR for each unit. The MDR shall
comprise a register of all Engineering documentation to be prepared by CONTRACTOR
and Sub-CONTRACTOR and shall provide the following details in respect of each
document, as minimum.
Deviations from schedule dates shall be clearly marked so that these can be easily
recognized. Exception reporting shall be provided to identify drawings overdue, drawings
to be issued.
A copy of the MDR, updated to show status, shall be provided weekly / Fortnightly but also
included in the Monthly Report.
7.4.2 All dimensions and other units of measurement shall be in SI or SI recognized units except:
- Pipe sizes and stud bolt diameter in inches
- Where specified otherwise in the Technical specifications.
7.4.3 Drawing sizes shall be ISO standard. When submitted, copies of all documents larger than
A4 shall be folded to size A4.
CONTRACTOR shall prepare A3 size edge bound sets of key drawings and documents
normally produced in A1 format, i.e. P&ID's, PFD's, area plot plans and the like.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
7.5.1 Each document shall have a title block providing as a minimum the following information.
The title block layout is to be approved by the PMC / OWNER.
• OWNER’s Contract Number (Fax of Award/ Letter of Award till FOA/LOA Number
• CONTRACTOR’s Project code reference
• Project Title
• Name of Equipment / Package
• Equipment / Package Tag No.
• OWNER’s Name & Logo
• PMC’s Name & Logo
• Main CONTRACTOR (if work is sub-contracted)
• Drawing / Document Title
• Drawing / Document No.
• Drawing / Document Revision No. and Date
• Unit No.
• Format Size
• Scale
7.5.2 Any revision to a document after first issue to PMC / OWNER shall be clearly detailed as
such on the document and in the revision box.
7.6.1 All deliverable drawings and documents will be given a unique number to identify each item
for inclusion in the Master Document Index.
7.6.2 CONTRACTOR shall submit document numbering procedure to PMC for APPROVAL
CONTRACTOR shall indicate how PMC / OWNER, Vendor or third-party drawings
will be incorporated into the system.
7.6.3 Document number must contain at least EPCC Code (CONTRACTOR to propose),
Unit No. & Document type code. Further document number shall have provision to include
OWNER code either as Prefix or Suffix. Requirement for this OWNER code shall be decided
after award of contract.
7.6.4 CONTRACTOR shall also submit his Document control procedure for review and Approval.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Such procedure shall cover the classification of drawings, their distribution, internal
approval, APPROVAL, control of revisions, identification of deliverables, control of
cancellations, storage and retrieval, etc. CONTRACTOR shall indicate how PMC /
OWNER, Vendor or third party drawings including "as-built" will be incorporated into the
system.
CONTRACTOR shall develop in liaison with PMC / OWNER a distribution chart for all
documents issued by CONTRACTOR to PMC / OWNER and their parties based upon
the Master Deliverable Register (refer item 7.3).
PMC / OWNER may require documents to be forwarded to Statutory Authorities, from time
to time. In such case, PMC / OWNER will inform CONTRACTOR of the number of
required copies and address.
Review/approvals (As per category) of all important design documents and drawing of
CONTRACTOR to ensure consistency and adherence to contractual engineering
specifications and adherence to Quality Assurance/ Quality Control plans during the
Engineering phase, are as follows.
PMC / OWNER will not accept any deviation from the DRAWINGS and
SPECIFICATIONS, however if CONTRACTOR wishes to propose a modification to the
DRAWINGS and / or SPECIFICATIONS under exceptional circumstances,
CONTRACTOR shall initiate and obtain APPROVAL prior to effecting any such
modification.
The Deviation Report shall be circulated to each of the parties which reviewed the
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
The Deviation Request shall describe the proposed modifications/deviations in detail and
shall be accompanied by marked up documents as necessary. It shall also state any
cost and / or schedule implication arising from the proposed modifications/deviation.
Upon receipt, PMC / OWNER shall proceed with its review of the DEVIATION REQUEST
and on completion of the review sign the form for APPROVAL or non-recommendation,
as appropriate, and forward it to CONTRACTOR.
During the performance of the Work, PMC / OWNER shall have right to perform, any
safety and technical Inspection & audits. CONTRACTOR shall provide, at
CONTRACTOR's cost, its full co-operation to the PMC / OWNER and shall make
available all necessary documents, services and facilities to enable the proper
performance of such audits. CONTRACTOR to perform modifications to correct
deficiencies as identified in such reports, if any, without cost and time impact to OWNER.
8.1 General
8.1.1 All materials and equipment to be supplied by CONTRACTOR under this contract shall
be procured from Vendors specified in the master supplier list (MSL) and manufactured
in the manner set out in the Contract including the Technical Specifications/Documents.
Where the procedure of manufacture, specification or any other detail is not set out in
the contract, the work shall be executed in a proper, work man like and careful manner
with properly equipped facilities and in accordance with good industry practice.
8.1.2 Within twenty-one (21) days following effective date, CONTRACTOR shall submit his
proposed project specific Procurement Procedure relating to purchase enquiry, bid
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
8.1.3 Procurement Plan – CONTRACTOR shall prepare and submit to PMC / OWNER a
Procurement Plan which will outline organization, methodologies and procedure to be
implemented by CONTRACTOR for carrying out all procurement and related activities
required by the contract. The plan shall include a sample of each standard form to be used
for such activities.
8.1.4 CONTRACTOR shall prepare and issue a Procurement and Material status Report on a
monthly basis, incorporating critical data and information from each detailed purchasing
report. The exact format and content of this summary report shall subject to approval.
8.1.5 PMC / OWNER reserves the right, on a case by case basis and upon notice to
CONTRACTOR, to deviate from the review procedure specified herein.
8.1.6 PMC / OWNER reserves the right to attend any CONTRACTOR meetings with
CONTRACTOR/Sub-CONTRACTORs or Vendors. CONTRACTOR shall give PMC /
OWNER sufficient notice to allow PMC / OWNER to attend such meeting. Upon
PMC's / OWNER's request at any stage of design, fabrication or installation,
CONTRACTOR shall organize and attend meetings with Sub-CONTRACTORs or
Vendors.
8.1.7 Within one month of the effective date, CONTRACTOR shall produce a list of items to be
imported with their estimated value. Each month, or at any other time PMC / OWNER
requires, this list shall be updated with latest quantities and estimated actual or forecast
costs.
8.2.1 General
All Purchase Orders shall be strictly administered in accordance with the CONTRACT and
the Project Procedures. The Purchase Order format shall be submitted for approval.
Purchase orders shall include, when appropriate, a statement that the Material
concerned is subject to the requirement of applicable law or statutory regulation
and shall include the relevant procedure to be followed by the Vendor.
Purchase Orders shall include, when appropriate, a statement that the Material
concerned is subject to inspection by CONTRACTOR, Third Party and PMC /
OWNER and that CONTRACTOR and PMC / OWNER shall have access to the Vendor's
works during all stages of manufacturing and testing.
CONTRACTOR shall consider the need for standardization to restrict the number of
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
types and sizes of items in the complex to simplify maintenance and reduce spare
requirements.
CONTRACTOR shall specify the same oil and grease for all equipment lubrication to
the extent possible.
CONTRACTOR shall ensure that all required documentation for final importation of
Materials and Work to the facilities is prepared and submitted to PMC / OWNER
or the appropriate authority in a timely manner prior to the intended date of importation.
Purchase Orders shall include, when appropriate, a statement that Vendors shall ensure
the availability of spare parts in accordance with the provision of Technical
specification/Contract.
CONTRACTOR shall ensure that Vendors furnish for review and for final
documentation, all drawings, bills of materials, manuals, certificates and other
information necessary to define the equipment and the performance of the equipment
as required by contract
This information shall be incorporated, where relevant, in the equipment dossiers, and
the current status of receipt of such information shall be given in the Materials Status
Reports.
CONTRACTOR to report immediately to PMC / OWNER all changes which will affect
material quality and recommend any necessary corrective actions to be taken.
Ensure that Vendors/ Sub-CONTRACTORs are aware of procedure and rules regarding
taxes and duties as applicable for goods/equipment supplied/WORK executed and
furnish proper documentation to PMC / OWNER to enable them to avail benefit of
“Input Tax Credit” and other tax/duties benefit.
The purchase order placed by CONTRACTOR shall include, but not limited to, the
following.
8.3.1 CONTRACTOR and its Sub-CONTRACTORs shall prepare all requisitions and requests
for Quotation for all equipment, materials and sub-contracts in accordance with the
project specifications and procurement schedule.
8.3.2 Requisitions and Requests for Quotation shall cover requirements for items including, but
not limited to
• Scope of work, transportation and installation, and training for OWNER's personnel
as required.
• Rates for services, such as Commissioning services, Vendor/Manufacturer
representative supervision services at site, priced recommendations for two years’
operation and maintenance spare parts as applicable.
• Equipment and ancillary system specifications, data sheets and drawings, battery
limits of the supply.
• Design basis, environmental conditions and applicable general specifications.
• Delivery schedule and milestones, including shop tests;
• Schedules, sub-orders, fabrication, shop testing, packing, transportation, and
delivery to CONTRACTOR
• Vendor Documentation Requirement Schedule as per requirements of the
CONTRACT, including
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
8.4.1 CONTRACTOR shall forward Purchase Orders together with attached documentation,
without pricing details (except in cases where the items are being imported under
EPCG License provided by OWNER, where priced copies of WO / Purchase Order are
required by statutory / custom authorities), to OWNER for information. Purchase
Order shall contain Supplier and Sub-CONTRACTOR acceptance of all essential
technical and schedule requirements. Any inaccuracy, omission or inconsistency
observed and brought to the notice of CONTRACTOR at any stage during the pendency
of the contract shall be appropriately rectified, remedied by the CONTRACTOR at no
additional cost to OWNER.
8.5.1 List of approved Vendors and other stipulation on Vendor list is included in contract
document. CONTRACTOR is required to strictly adhere to these requirements.
8.5.2 OWNER may, at its discretion, delete or add any Vendor or Sub-CONTRACTOR from the
list of approved Vendors and Sub-CONTRACTORs at any time during the performance
of the work.
After receipt of bids, CONTRACTOR shall review and check the bids for conformity with
technical, contractual terms and conditions and Project requirements.
CONTRACTOR shall then prepare and submit its Unpriced preliminary bid evaluation
summary of all technical, contractual and Project requirements for OWNER's review
and comments, indicating CONTRACTOR's recommended short list of bidders with
reasons for such recommendation. The list of such items which require PMC / OWNER
representative review is indicated in the contract documents. Also, deviations to tender
specifications sought by Vendors to be clearly indicated in the bid evaluation summary
by CONTRACTOR.
After receipt of the approved short-listed clarified bids, CONTRACTOR shall carry out
its complete Priced evaluations of the short-listed bidders. CONTRACTOR shall submit
its complete un- priced final Bid Evaluation to PMC / OWNER for review, indicating
its recommendation for the selection of the Vendor or Sub-CONTRACTOR.
CONTRACTOR shall establish and maintain a Purchase Order Control Register. This
Register shall include all Purchase orders issued for all items of material and equipment
to be incorporated in the work. CONTRACTOR shall be capable of generating reports
from the Register for Indian and imported items separately.
The Purchase Order Control Register shall show for each Purchase Order and for
each item the following information.
• Purchase order number
• Material Requisition/Purchase Requisition number
• Unit Name / Number
• Date of invitation of Bid
• Date of Bid Receipt
• Bid Opening Date
• Date of unpriced final bid evaluation to OWNER
• Date of Purchase Order.
• Date of Order Confirmation
• Name/Address of Vendor
• Brief Description of materials and equipment purchased, together with
specific identification reference
• Ex shop delivery date
• Expected delivery at worksite
• Shipping details
• Latest purchase order amendment No.
• Expediting details
• Status of Purchase order
• Inspection Status
This Register shall be updated and issued monthly in hard copy along with Monthly
progress report.
8.8 Traffic
CONTRACTOR shall organize and co-ordinate the traffic of all materials and
equipment by unit and maintain records of such.
Prior to transportation to worksite of any and all parts or components of the facilities, by
sea, special means or any other mode of transportation, CONTRACTOR shall obtain
all necessary approvals from marine or insurance surveyors or any other statutory
body with respect to the means and procedures to be used during packing, weighing,
load out, sea fastening, transportation, off-loading and the like.
At all stages of the work, CONTRACTOR shall ensure the proper identification of all
bulk material equipment and supplies.
CONTRACTOR shall provide PMC / OWNER with all applicable certificates and
documentation upon delivery of such items at worksite.
Bulk material equipment and supplies shall be properly packed and secured so as to
satisfactorily reach their destination.
Packing cases, boxes, tins, wrappings and other packaging materials supplied by
CONTRACTOR shall be non-returnable.
CONTRACTOR shall on a timely basis dispatch and deliver any and all bulk material
equipment and supplies to the locations required for the performance of the work and
maintenance of the contract master schedule.
CONTRACTOR shall arrange and carry out its responsibility and supervision of the
transportation of all bulk material, equipment and supplies from the point of fabrication
to worksite.
CONTRACTOR to undertake to properly store and maintain any and a bulk material,
equipment and supplies in accordance with the contract and the best professional
practices and shall protect such bulk material, equipment and supplies against weather
hazards, water, humidity, sand, fire, theft, vandalism and the like.
CONTRACTOR shall always use every means to prevent any damage or loss
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
All purchase items shall be properly boxed and shipped to worksite to meet the
Project Schedule. CONTRACTOR shall expedite all forwarding of bulk material,
equipment and supplies
CONTRACTOR shall be responsible for all customs handling and payment of customs
dues and port dues and shall maintain a register of customs entry references for the
material received at site.
CONTRACTOR to carry out detailed study to establish firm transportation mode and route
and all cost for such study is to the CONTRACTOR's account.
CONTRACTOR shall comply with statutory regulations for storage of any material
covered under Explosives Rules
CONTRACTOR field supervision staff shall supervise and coordinate material arrival at
site, inspect it to check the compliance with the purchase orders and related
specifications classify, store, maintain and finally release them to the Sub-
CONTRACTORs at the proper time of installation.
CONTRACTOR shall submit for Approval his proposed Site Warehousing procedure
which is based upon the following:
a) Receive the materials which arrive at jobsite and issue the "Daily Receipt report(DRR)".
b) Check adherence in quantity and in characteristics of each item with the
indications specified in the relative packing list or bill of material.
c) Control that no damage has occurred during transportation.
d) After inspection, store materials arrived in good conditions and in accordance with
the purchase order issuing the "Material Receipt Report(MRR)".
e) Periodically control materials, parts, components and equipment to be installed, in
order to guarantee proper maintenance during storage, and to minimize the risk of
damage during withdrawal and handling.
In accordance with the criteria outlined above, CONTRACTOR to prepare & finalise
forms to be used in performing the field warehousing activity.
Final forms and detailed Procedures shall be agreed upon between the OWNER and
the CONTRACTOR before the starting of the Site construction activities.
As necessary, CONTRACTOR shall ensure co-ordination and shall work with Customs
Authorities and any Vendor or Sub-CONTRACTORS in order to implement the
importation procedures in the most efficient manner.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
9.1 General
9.1.2 For this purpose, the CONTRACTOR shall deploy a construction management team
headed by a Site Manager at site. The Construction Management team shall include
engineers/specialists in QA/QC, Project Control, (Planning, scheduling, monitoring)
contracts, construction supervision, progress measurement / billing, safety, first-aid,
warehousing, purchasing etc. Key personnel including Site Manager should have
sufficient experience and should not be changed without concurrence from PMC /
OWNER. Resumes of key personnel shall be submitted for approval of PMC / OWNER
prior to deployment.
9.1.3 The construction supervision, co-ordination and management activities shall be carried
out by the CONTRACTOR in accordance with the construction procedures developed
and submitted by the CONTRACTOR and approved by PMC / OWNER. CONTRACTOR
will prepare construction schedules within the framework of overall contract schedule and
submit to PMC /OWNER for approval. CONTRACTOR shall plan, execute, monitor and
control construction activities as per the approved construction schedule.
9.1.4 CONTRACTOR will deploy a construction management team headed by a Site Manager
for each unit and off-site & Utilities (O&U) at site for construction management of their
contractual scope of work. CONTRACTOR shall extend all necessary assistance and
provide all necessary data / documents as required by PMC / OWNER for review and
monitoring of the jobs performed by the CONTRACTOR.
The CONTRACTOR shall ensure delegation of adequate and sufficient authority and
controlling power (including inimical) to his Site Manager for effective and smooth
functioning of the construction management. CONTRACTOR’s home office support shall
be provided to the Site Manager at site during construction on all matters of Project
execution including the following:
• Field engineering
• Vendor specialists required during construction.
• Rectification/ replacement of defective supplies, if any, noticed during
construction and commissioning.
• Inspection / expediting of replacement orders / field purchase orders for items
ordered by Field Purchase Team
• Expediting replacement of imported items found short / damaged.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
CONTRACTOR will depute a project team at site during construction phase under a
project coordinator for providing above-mentioned support to Site Manager.
All reference procedures and detail work plans referred to in this document must be
submitted for review and approval by PMC / OWNER at least four (4) weeks in
advance of actual commencement of the activity concerned.
9.2.1 CONTRACTOR’s manpower and man-hour histogram by major section and discipline and
their manpower deployment schedule on monthly basis with distribution of Foreign /
Indian/ Local personnel.
9.2.2 Major equipment mobilization plan on monthly basis with short description.
• Temporary facilities etc. – Like construction power, water, site office space,
Warehouse, Fencing, canteen, fabrication yard in location allocated by OWNER if
any.
• Soil testing and Piling plan
• Scaffolding plan
• Excavation and underground work plan
• Heavy transport and heavy lifting plan (Rigging Plan)
• Pre-fabrication plan
• Hydrotest plan
• Other activity plans e.g. equipment and steel structure erection plan etc. indicating
sequence of erection as per material received at site.
• Instrument loop check plan.
• Monsoon counter measures and preparation
• Emergency evacuation procedure
• Storm management plan
9.2.3 Sub-Contracting
The list and major scope of each Sub-contract shall not be changed from those
of the CONTRACTOR’s plan unless specially approved by OWNER.
9.2.4.1 Exact location of temporary work area, access and general layout inside the area.
CONTRACTOR will develop the temporary facilities layout for approval of PMC /
OWNER.
• Industrial water
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
• Drinking water
• Electricity
• Telephone/Fax
All inspections and QA/QC Test records are to be kept up to date and in first rate condition
by the CONTRACTOR and shall be made available to PMC / OWNER whenever
requested. These documents shall be handed over to OWNER within one (1) month
after completion of Mechanical Completion of the Project as per Final Documentation
Procedures.
All work/ services to be performed by the CONTRACTOR under this contract shall
be of specified/ approved quality and the CONTRACTOR shall have a Quality
assurance / Quality Control (QA/QC) system during the performance of various
activities such as engineering, procurement, tendering, construction commissioning etc.
PMC shall carry out a Construction Quality Audit of the Project Facility every three (3)
months during construction phase of the project by an independent group of PMC
personnel not reporting to the site in–charge. The audit shall employ special tools such
as include positive material identification through alloy analyzers etc.
Review approval of the activities by PMC / OWNER shall not however dilute the
responsibility of the CONTRACTOR for maintaining quality.
The CONTRACTOR will be responsible for carrying out the Warehouse Management
and Material Control in accordance with the approved warehousing procedure and
material control procedure, which is to be submitted by the CONTRACTOR during kick-
off meeting. A computerized stores management and material control system shall be
developed. The activities will include but not limited to:
• Transport liaison, both for imported materials as well as materials procured in India
from the time of dispatch up to receipt at Site.
• Transportation Plan (i) from source to site (ii) site to erection location.
• Receipt, handling, identification, inspection (including confirmation by an alloy
analyzer for alloy steel, stainless steel and other exotic materials) and acceptance,
storage and preservation of materials, codification of all materials including free
issue materials to be supplied by OWNER.
• Chemicals/Catalyst/Column internals loading, unloading and transportation, storage
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
and handling
• Filing of insurance claims and follow up
• Documentation for control and accounting of materials
• Generation and upkeep of traceability records for materials
• Materials control and issue
• Inventory checks
• Field requisition and purchase
• Spare & tools including handing over of mandatory spares/ tools to the Client as
per the terms of the contract
• Material Appropriation and Handing over as per the terms of contract.
• Taking up with suppliers on short supplied items and placing replacement
orders for lost/damaged items
• Intimating to CONTRACTOR’s Home office regarding short/lost/damaged items and
taking up with suppliers and taking replacement action wherever applicable.
• CONTRACTOR shall codify all items of permanent nature which are to be
supplied to OWNER as part of this contractual obligation such as Mandatory
spares. This codification shall confirm to OWNER’s own codes allotted to each
item and which shall be given by OWNER in advance.
Field Engineering team will consist of mainly engineers who have worked at the design
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
CONTRACTOR will be responsible for carrying out field tendering activities as required.
CONTRACTOR will be responsible for carrying out field purchase activities as required.
The bulk of procurement action will be done from CONTRACTOR’s H.O. Field Purchase
items are restricted to those required for running and maintenance of the field offices,
items required to expedite construction work and items found short, missing or
damaged against the main order when received at the site. Any material purchased
from field for usage in the Plant should have proper inspection certificate and should
be purchased only from PMC / OWNER approved Vendors.
Safety Practices during Construction by Oil Industry Safety Directorate (OISD guideline
OISD-GDN-192 and OISD-GDN-207] which is supplementary requirements to be
followed by the CONTRACTOR at site.
Both these documents though are separately written, shall be considered as mutually
complementary to one another. In case of ambiguities in the descriptions of safety
requirements stringent one shall be considered as applicable.
9.9.2 CONTRACTOR shall have a documented HSE policy to cover commitment of their
organization to ensure health, safety, environment & Security aspect in their line
operation. Specifications required to be followed by CONTRACTOR are given as per
9.9.3 It is the responsibility of the CONTRACTOR to ensure that safe construction procedures
are complied with. CONTRACTOR will also ensure that adequate First Aid medical
facilities with trained nurse and ambulance are available for emergency purpose and
that safety practices as per the approved safety procedure are followed by his Sub-
CONTRACTOR(s).
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
• The use of safety gadgets like safety goggles, helmets, safety shoes, safety
earplug, safety belts, provision of safety net for construction at higher elevations
and provision of toe boards in scaffolding platforms.
• All hot works must be performed by ensuring compliance to the requirements
specified by OWNER.
• Barricading of crane movement areas
• Proper earthing of equipment
• Proper shoring / strutting of excavated areas
• All gas cylinders to be stacked upright, regarding Nitrogen, Oxygen, acetylene,
Argon and other gas cylinders separately.
To assist in the development of an effective safety program, a HSE Manual including safety
checklist for various jobs shall be developed by the CONTRACTOR and the same
shall be submitted to PMC / OWNER for approval and shall adhered to by
CONTRACTOR’s Site-in-charge.
CONTRACTOR shall maintain proper liaison with Statutory Authorities and local bodies
and will be responsible to implement and observe all statutory laws at site.
CONTRACTOR must have on his staff, a well experienced Labour Relation Officer,
preferably from local area.
CONTRACTOR must submit a Labour Relations Plan prior to the start of the work/within
one month of award of the contract, whichever is earlier.
1. A detailed estimate of the number of foreign labour/local labour / labour from other
States of India, both indirect and direct, sorted by craft. This estimate shall specifically
include the months and durations that potential foreign labour will be required.
2. Outline of training plan for local semi-skilled labour and respective crafts.
3. Outline how the respective Government Agencies will be educated on
maximization of local workers.
4. Outline recruiting plans for all manpower requirements.
5. Identify personnel involved with labour relations and outline procedures to
mitigate disputes, problems should they occur with the labour force.
6. Labour welfare plan.
CONTRACTOR shall hold labour relations meeting twice a month with their work
force as well as a separate meeting with PMC / OWNER.
The CONTRACTOR shall without prejudice to his responsibility to execute and complete
the work, strictly as per the specifications and other laid down procedures, execute all the
work by mechanizing the construction activities to the maximum extent by deploying
all necessary construction equipment / machinery of adequate capacities and numbers.
▪ Batching plants
▪ Concrete pump cars
▪ Transit mixers
▪ Excavators
▪ Bar bending machines
▪ Automatic welding machines
▪ Tower crane
▪ Cranes of different capacities
▪ X-ray and radiography sources
▪ Stress relieving equipment with recording facility
▪ All weather fabrication sheds
▪ Sand/Shot blast cleaning and painting shop
CONTRACTOR shall deploy portable alloy analyzer with print out facility and carryout
“Positive Material Identification (PMI)” of materials and welds after erection/ installation
but prior to hydro-testing. Any non-conformance detected shall be removed and replaced
prior to final testing.
CONTRACTOR shall be responsible for arranging all facilities for torque tightening /
tensioning of bolts/ fasteners as specified. CONTRACTOR shall ensure that stud bolts
are ordered extra-long by one diameter to facilitate tensioning. Guidelines for torque
tightening / tensioning are specified in specifications for boxing up of flanged joints.
cost. Construction of hard stands for the positioning of crane in the fabrication yard
and at erection site/ locations including approach roads to the hard stands from the
plant roads shall be CONTRACTOR’s responsibility. The hard stands shall be suitable
for the crane loads provided by the crane manufacturer.
For equipment erection, the CONTRACTOR shall deploy a rigging team headed by
a Rigging Foreman / Engineer reporting to concerned Area Engineer. Area Engineer
should be well conversant with various erection techniques and shall be responsible for
preparing erection schemes in accordance with the approved procedures and based
on crane manuals and suiting to plant layout. Area engineer shall have to foresee
various other construction activities in the surrounding areas while planning erection
schemes including safety aspects of man and machinery also.
CONTRACTOR shall prepare erection schedule in line with the overall project schedule
of the Plant in phased manner with erection schemes of various equipment, vessels
and submit to PMC / OWNER for approval. Monitoring and control of erection schedule
and erection activities shall be carried out by the CONTRACTOR as per the approved
construction procedures.
CONTRACTOR shall ensure the timely augmentation of the men, equipment and
machinery depending upon the exigencies of the work to meet the overall project
schedule and as per instructions of Engineer-In-Charge.
During the execution of the work, CONTRACTOR must ensure that structures, materials
and Equipment are adequately braced with Guys, Struts or any other means as
deemed fit and approved by Engineer-In-Charge. Such means shall be supplied and
installed by the CONTRACTOR as required till the erection works is satisfactorily
completed. Such guys shoring, bracing, strutting, planking supports etc., shall not
interfere with the work of other agencies and shall not damage or cause distortion to
works executed by other agencies. All lifting tools, tackles and cranes shall be tested
periodically by Statutory / Competent authorities for their load carrying capacity. Such
relevant valid/ test certificates shall be submitted to PMC / OWNER for review before
actual use of tools, tackles and cranes.
For this purpose, the CONTRACTOR shall clearly indicate in his construction
methodology whether work shall be done departmentally or by engaging Sub-
CONTRACTOR or the combination of both. CONTRACTOR will prepare detailed
methodology for the work to be carried out departmentally as well as through Sub-
CONTRACTOR’s clearly defining the scope and responsibility of CONTRACTOR and his
Sub-CONTRACTOR’s.
The works of all Sub-CONTRACTOR’s will be managed by the construction staff of the
main CONTRACTOR who will perform the duties of construction management and will
administer, coordinate, and inspect the works of the Sub-CONTRACTOR(s) and be
responsible for the quality and timely completion of the respective works. The
CONTRACTOR will establish the pre-requisites for successful completion of Sub-
CONTRACTOR(s) work. However, by deploying the Sub-CONTRACTOR(s), as
approved by PMC / OWNER for any discipline, does not absolve the CONTRACTOR
from his total responsibility under the subject contract.
CONTRACTOR must submit the construction manpower deployment schedule along with
the bid. Construction manpower deployment schedule shall clearly indicate deployment
of national and international (foreigner) manpower with specific man-hour /man months
for foreign nationals who will be deployed at site along with details of their qualification/
experience and nationality. Daily construction manpower deployment report will also be
submitted by the CONTRACTOR to PMC / OWNER on approved format. Any additional
manpower of any category required to be deployed during the actual execution of the
work to meet the Project time schedule and as instructed by PMC / OWNER, shall be
mobilized by the CONTRACTOR within a reasonable time. Mobilization of such
additional manpower by the CONTRACTOR will not entitle him for any additional
compensation at all.
CONTRACTOR shall prepare Construction manual / methods statements for all major
Construction activities.
Standard procedures for boxing up of interface joints not subjected to hydrostatic test
at site shall be strictly followed as per the BOLT TENSIONING & TORQUING procedure.
10.1 Introduction
To ensure timely completion, the CONTRACTOR shall establish and maintain an effective
Planning, Scheduling, Monitoring and Control system, including mobilization of required
number of professionally qualified and experienced Planning Engineers for design office
and construction site. The system shall be capable of accurate and timely prediction of
trend, evaluation of adequate preventive actions for likely slippages and formulation of
suitable catch-up schedule for delays, if any have occurred.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
This procedure covers Schedule, Control and Progress Measurement aspects through all
the phases of the Project i.e. Engineering, Procurement, Construction, Mechanical
Completion & Pre-commissioning and Commissioning. In order to ensure the completion
of the Project as scheduled, every person and / or party concerned shall observe and
execute the work according to this procedure.
During the course of execution of the Project, if this document requires modifications to
facilitate smoother operation of the project (contract), the same can be done with mutual
consent of all the concerned parties.
The EPCC bidder shall submit following documents along with bid:
a) Overall Project Schedule in network form showing all the details unit wise in line
with time schedule indicated in Appendix A-II of SCC.
b) Write up on proposed Project Planning, Scheduling, Monitoring and Control
system (in line with requirement of this Procedure).
c) Organizational set up for Planning, Scheduling, Monitoring & Control at
CONTRACTOR’s design & site office.
d) Progress Measurement System with details such as Weightages, Milestones,
frequency, etc.
e) Project execution methodology
f) Details of Software’s to be used for planning and material control
g) Phase wise Resource Deployment Schedule (HO & Site manpower and
construction equipment).
h) Statement confirming compliance to the “Planning, Scheduling, and Monitoring
and Control System” requirements regarding contents of the documents to be
submitted to PMC / OWNER.
Kick Off Meeting shall be organized within 1 week from award of contract. The meeting
shall be attended by OWNER's and PMC's representatives. During the meeting, the
following with respect to Planning, Scheduling, Monitoring and Control system shall be
discussed, schedule for submission formats, details shall be finalized
The CONTRACTOR shall prepare and submit a detailed Look Ahead Schedule
covering all initial activities (Front end activities) including Residual Basic Engineering
(if any), Detailed Engineering, Procurement and Construction pertaining to first 90 days
of the project duration.
It is derived from the scope and schedule agreed as per contract. It forms the basis of
project execution and monitoring till Overall Project Schedule is finalized. A draft look
ahead schedule shall be submitted at the time of kick-off meeting. The schedule shall
be reviewed in the kick-off meeting. Revised look Ahead Schedule is submitted within
2 weeks (or 14 calendar days) from KOM. If Kick off meeting is delayed, draft look
ahead schedule shall be submitted within 2 weeks from award.
• Functional Schedules
o Engineering Schedule
o Procurement Schedule
o Sub-Contracting Schedule
o Construction Schedule
o Pre-commissioning & Commissioning schedule
• Supporting Schedule and Control Document
• Progress Measurement Methodology
• Schedule Performance Curves (‘S’ Curves)
• Catch-up Schedule (In case of delays as required)
• List of Project Milestones (in addition to the milestones listed in Tender) with
dates
• Manpower and Machinery Deployment Histograms
• Agreed Reporting Formats
CONTRACTOR shall submit reports, updated schedules and program(forecast) as
described herein till the completion of all work in the scope of the contract. No chapter
/ annexure of any report shall be deleted without prior written approval of PMC /
OWNER.
Work Breakdown Structure is a diagram depicting subdivision of project works into smaller
items like units, project phases, disciplines for ease of managing projects. WBS reflects
natural hierarchy of summarization, top level reflecting total project and lower level reflect
successively increasing details which shall illustrate the way work shall be divided up.
The WBS shall be used as the basis for Planning, Scheduling, Progress Monitoring and
Progress Reporting, and it shall be applied to all Project Control documents.
To identify and to evaluate the work progress of the project, weightage shall be added to
the Work Breakdown Structure (WBS) elements, based on work volume. Then weightages
will be further divided up to lowest levels to deliverables. WBS for Planning, Scheduling,
Progress Monitoring and Progress Reporting is to be developed by CONTRACTORS for
their scope of work and same to be submitted to PMC / OWNER for approval.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
The CONTRACTOR shall prepare resource based detailed unit wise functional schedules
for all activities and deliverables in tabular form in line with overall project schedules for
monitoring and control.
For each activity and deliverables maturity level shall be depicted in the form of applicable
milestone till final issue and these milestones will be discussed during kick-off meeting.
CONTRACTOR shall ensure preparation, submission and updation of all functional
schedules as described herein for all subcontracted packages. Supporting Schedules to
ensure timely completion from CONTRACTOR shall be established and maintained for an
effective planning, scheduling and control system, including mobilization of number of
professionally qualified and experience planning engineers for design office and
construction site. The system shall be capable of accurate and timely prediction of trend,
evolution of adequate preventive actions by CONTRACTOR for review of PMC at various
stages. Control Documents shall be prepared, updated and issued in accordance to the
requirements and compatible with the Overall Project / Detailed Project Schedule.
The updated functional schedule shall have submitted to PMC / OWNER on monthly basis.
While updating activities / deliverables, the following aspects shall be considered:
• Actual date of completion of each milestone
• Forecast date of balance milestone to be completed
Detailed Engineering Schedule: CONTRACTOR shall submit a Unit wise schedule for
all engineering deliverables/ documents such as AFC drawings, Isometrics,
Specifications, Tender inputs / Tender drawings, material requisition, purchase
requisition, purchase requisition, design calculations etc. Interface and logical sequence
with other activities also shall be considered while establishing the schedule.
Procurement activities of all disciplines (Enquiry to Receipt of item at site) for equipment
/ bulk shall be reflected in Detailed Schedule.
Ordering Schedule: CONTRACTOR shall submit a unit wise schedule within 60 days from
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
FOA. This shall include all MRs listed in Engineering schedule (DCI/MDR).
All the tagged items shall be covered in MRs listed. Bulk material ordering shall reflect
Procurement philosophy for the project.
.
Manufacturing & Delivery Schedule: The CONTRACTOR shall submit a unit wise
schedule within 60 days from FOA for all Manufacturing & Delivery activities. These shall
include all orders listed in ordering schedule. The progress at function / unit level shall be
summarized considering weightage values of equipment & bulk items material report to
overall manufacturing and delivery progress.
CONTRACTOR shall also submit along with weekly progress report, status of drawings
and documents for all Vendors on whom orders have been placed. In addition to the
above, for critical items, long delivery items and packages as mutually agreed between
CONTRACTOR and PMC / OWNER, CONTRACTOR shall ensure Vendors prepare and
update logical network/schedule, status reports for manufacturing & delivery and submit
the same on weekly / monthly basis to PMC / OWNER.
Subcontracting Schedule: The CONTRACTOR shall submit a Unit wise schedule for all
Sub-contracting activities. This shall include all tenders envisaged for the Project. This
schedule shall cover all subcontracts and milestones for Tender preparation till award.
In case of Construction the monthly programs shall be finalized in consultation with PMC
/ OWNER’s site representative and submitted within two calendar days of monthly
progress report cut-off date. In all matters concerning the extent of targets set out in
monthly program, the decision of PMC / OWNER shall be final and binding.
The monthly forecasts (programs) shall be further broken down into weekly forecasts
(programs) and indicated in weekly reports for closer monitoring of progress.
The following schedules shall be prepared and updated on a weekly basis and submitted
to PMC / OWNER before the weekly review meeting at site in bar chart format. The
updated schedule trend shall be compared with original schedule.
1. Loop wise piping completion schedule
2. System wise completion schedule
The description of the system and the number of the loop mentioned in the schedule
above shall be as agreed with PMC / OWNER (Construction / Commissioning group).
The schedule shall be resource based and shall indicate total and remaining workload
for each activity.
The CONTRACTOR shall submit the detail methodology of progress Measurement as per
WBS.
General weightage allocation for different discipline shall be on following basis
Weighted values for the following along with basis of their derivation shall be submitted
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
• Units
• Phases / Functions
• Deliverable level
The above-mentioned weightage shall be discussed during kick-off meeting.
WBS for weightages shall be filled up for all levels and submit for review to PMC / OWNER
Progress figures shall be summarized from deliverable level and indicated in the function
schedules.
The progress basis shall be physical realization of work on earned value measurement for
deliverables and construction quantity/volume accomplished. The amalgamation of such
output across the project to compute overall progress shall be suitably established with
proper rational and norms and Maintained throughout the project. PMC / OWNER reserve
the right to modify the methodology in part or in full.
The “S” -curves shall show planned, actual and forecasted progress values.
Progress shall be reported against the Current Baseline Schedule and Current Forecast
Schedule.
Initial progress curves shall be prepared by CONTRACTOR and submitted to PMC for
approval along with detailed schedules & Planning package within 10 weeks from LOA.
Progress curves shall be included in the monthly progress report showing the original
Baseline Plan, Current Plan, actual earned to date and forecast to completion for each
WBS level.
Progress curves for construction WORK are to be updated weekly by CONTRACTOR and
shall be issued PMC and owner.
Based on the forecast progress, contractor shall revise the resource deployment schedule
in line with forecast schedules.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Through the monthly progress report CONTRACTOR shall report to PMC the trends, areas
of concern, opportunities and recommendations for corrective actions necessary to recover
or improve schedule.
The CONTRACTOR shall generate and submit catch-up schedule for completion of all
balance activities without change in contractual completion date with detailed resource
reinforcement as and when asked by OWNER/PMC. Whenever the progress lag crosses
more than a month schedule progress, contractor shall submit a catch-up schedule to
arrest further delay. The catch-up schedules shall be submitted to OWNER/PMC for
review. Accordingly, the "S" curves for catch-up schedules shall be made and shown along
with the original schedules and actual "S" curves.
During updation of overall project schedule and construction schedule, the catch-up
schedules shall be shown in bar charts along with the original schedule.
10.12 Reporting
CONTRACTOR shall submit daily, weekly as well as monthly progress Report to keep
PMC / OWNER updated on the status of the PROJECT as described below:
This shall cover for both CONTRACTORS design office and construction activities at site.
Monthly Progress report along with Progress Figures up to 20th of every calendar month
shall be sent by CONTRACTOR to OWNER/PMC to reach by 25th of each month in the
agreed format.
The above is indicative, the same will be finalized after award of contract.
CONTRACTOR shall submit (daily before 10 AM) for status of previous working day a
daily report including the following:
• The physical quantities of activities expressed in the relevant applicable units (such
as m, m2, m3, kg, tons) (For example concrete: in m3)
a. TOTAL quantities
b. SCHEDULED quantities to be released to site
c. RELEASED quantitates by CONTRACTOR in the form of IFC drawings;
d. AVAILABLE quantities to CONTRACTOR in the form of CONTRACTOR’s
equipment and materials.
e. PERFORMED quantities by CONTRACTOR
f. NETWORK FRONT that is calculated by deducting points d, e from point
c.
• Build-up progress, overall and by discipline achievable by CONTRACTOR,
calculated in accordance with the progress weighing system, based on quantity of
activities by CONTRACTOR in from of IFC drawings and equipment and materials
including LLIs as per points a. to f. above, considering the information deriving from
Detailed Construction Schedule Level IV prepared by CONTRACTOR.
During the performance of the work, CONTRACTOR shall continuously monitor the actual
progress and productivity of the WORK and CONTRACTOR shall issue on a weekly basis
the "Productivity Report", providing, as a minimum, the following information:
a. the comparison between the planned overall progress and productivity versus the
actual achieved ones (cumulative and weekly);
b. the comparison between the planned progress and productivity by discipline,
detailed for specific work classes, as agreed
c. the comparison between the planned production quantities (m, m2, m3, kg) versus
the actual achieved ones (cumulative arid weekly);
d. CONTRACTOR analysis of the deviation (if any) between the planned data and the
actual ones.
When the planned progress or productivity values are not achieved, the CONTRACTOR will
promptly submit its relevant Recovery Plan, identifying the corrective actions which it needs
to implement to comply with all the planned values and to keep the CONTRACT Schedule,
and will submit it to OWNER/ PMC for evaluation.
The productivity data used for construction progress measurement shall directly lead to
manpower to be deployed for performing activity.
CONTRACTOR shall submit fortnightly expediting report of all orders placed by him.
Following additional report shall be prepared and submitted at regular intervals
The CONTRACTOR shall present project status, project highlights and action plans as
applicable at various review meetings as described below. The presentation materials
shall be submitted by CONTRACTOR to PMC / OWNER at least two days before the date
of meeting for management level review meetings and Monthly/ Fortnightly review
meetings. The meetings will be attended by senior management of OWNER, PMC &
CONTRACTORS. Venue and timings of meetings shall be decided by PMC / OWNER
based on the criticality of the project.
The CONTRACTOR shall have conference room at site to display charts featuring salient
static information of the project, schedules, status of progress, resource deployment,
block flow diagram, plot plan, work break down structure, etc. The status shall be updated
at least on monthly basis. The objectives of the control room are to provide information at
a glance to project personnel including the management of OWNER and PMC.
For schedule preparation and updation, the CONTRACTOR shall use Primavera Project
Enterprise of latest Version. The other package used shall be compatible with software’s
used by PMC / OWNER and submit the backup of the schedules in electronic compressed
files along with hard copy / soft copy whenever submissions of the schedules are called
for. The electronic files for all other deliverables shall be Microsoft compatible.
Contractor shall submit the schedule, forecast and actual data of entire project
deliverables in electronic form in addition to the PDF reports. The structure and format
shall be shared during the kick-off meeting
CONTRACTOR shall provide the following facilities for use by PMC / OWNER at
CONTRACTORS Design office:
i. PC with latest hardware, A3 size colour laser jet printer and internet connection
ii. Softwares :
a. Primavera Project Planner (P6 latest version)
b. E-mail Facilities & Internet explorer / Netscape
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Format for Monthly Progress Report shall be provided by the PMC/ OWNER to the
CONTRACTOR on commencement of the job.
CONTRACTOR to furnish the Billing Schedule within one month of award for
PMC / OWNER approval.
Project Cost Control and Monitoring activities for the Project are required to be performed
by PMC / OWNER during execution of contract. CONTRACTOR is required to furnish
relevant information on cost status, change orders, if any, deviation permits and
master cash flow schedule and cash flow on monthly basis.
CONTRACTOR to include a chapter of cost control in the Monthly Progress Report and
shall highlight the cost, change order, deviation permit and cash flow status. The contents
of each of section are as follows:
• COST STATUS
Cost status of the Contract shall be projected suitably in a tabular form with a break-
up of costs under the heads of (original contract value, approved change orders,
approved deviation permits, pending change orders, pending deviation negative
permits, current forecast, invoice to-date and payment to-date. Format in this regard
shall be issued after the award of the contract.
For Change Order / Deviation Permit, the CONTRACTOR shall prepare and
submit necessary document containing reason for change/deviation, estimated
cost along with rate analysis and quotation/documentary support, sketches and
drawings and impact on schedule.
The CONTRACTOR will maintain Change Order and Deviation Permit registers that
will form part of their monthly progress report. The registers will list all the change
orders/deviation permits and indicate their approval, cancellation or rejection
status. Formats in this regard shall be issued after the award of the contract.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
• CASH FLOW
The CONTRACTOR shall submit a, Master Cash Flow Schedule within a month of
award of the Contract. The cash flow projections from zero date shall be made on
the basis of billing schedule. CONTRACTOR shall use separate sheets for Rupee
and Foreign Currency components.
12.1 Intent
This Mechanical Completion Procedure (hereinafter referred to as “PROCEDURE”) has
been prepared to achieve an expeditious MECHANICAL COMPLETION by identifying
discipline work responsibilities of CONTRACTOR and the OWNER. This Procedure
shall be made “Job Specific” based on Definition of MECHANICAL COMPLETION in
the Contract as well as “Scope of Work” as per Contract.
b) Final inspection
All field inspection shall be conducted in accordance with “FIELD QUALITY
CONTROL PROCEDURE”.
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
The request letter for final inspection shall include the following information:
c) Punch list
Where the PMC/OWNER considers MECHANICAL COMPLETION is not satisfied,
they shall issue a punch list to CONTRACTOR, within 7 – 10 days from the date
of receiving the inspection request.
Each punch item satisfactorily completed and inspected shall be dated and initialed
by the PMC/OWNER and CONTRACTOR jointly. Upon completion of the punch
list, it shall be signed by PMC/OWNER with Mechanical date of completion.
CONTENTS
1. GENERAL 3
1. GENERAL
1.1 This procedure defines the type of drawings and documents to be generated by
CONTRACTOR for all project deliverables/ documents against the Tender/ Contract,
which shall be developed and submitted to PMC/OWNER by the CONTRACTOR for
review/ records for the LuPech Project at Indian Oil Corporation Limited’s, Gujarat Refinery,
Gujarat, INDIA.
1.2 The CONTRACTOR must recognize that efficient handling of drawings and documents
prepared by him under the contract is the key to the timely completion of the plant.
1.3 The CONTRACTOR shall ensure that all drawings and documents to be submitted by them
to the OWNER and/or PMC shall be of professional quality and conforming to the
contractual requirements.
1.4 The CONTRACTOR shall introduce a formal drawing control system, which will be
documented and submitted to the PMC/OWNER for review or approval.
1.5 CONTRACTOR shall form a Documentation Control Team. This team shall be responsible
for all incoming and outgoing technical documents related to the project. These documents
will be compiled as per agreed procedure, kept updated to the latest revision and delivered
to the designated agency(ies).
1.6 Compliance to the requirements as indicated in this document on drawings and documents
is mandatory and is non-negotiable.
1.7 The drawings/ documents as generated by the CONTRACTOR at various stages of the
Project will be in the category of Approval / review / information / records as defined
elsewhere in the bid document.
1.8 Computer aided design and drafting only shall be used, manual drafting is not permitted.
Bidders shall commit in their Offer the extent (discipline-wise) to which Computer Aided
Design (CAD) shall be used.
1.9 CONTRACTOR shall prepare the drawing numbering procedure and submit to
PMC/OWNER for APPROVAL.
1.10 CONTRACTOR to note that the numbers corresponding to Process Units, Utility Systems,
Offsite Facilities & Infrastructure along with Sub-Units will be prefixed to all related
documents / deliverables.
1.11 PMC/OWNER comments on Approval / Review category documents shall be duly taken
care while submitting deliverables under Information category.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
1.12 The prerequisite documents must have Code-A or Code-B before submitting the
downstream documents,
1.14 The CONTRACTOR/Sub-vendors etc. shall only use standard, approved and well-
established PC based computer programs/ software packages available in the market.
CONTRACTOR shall bring out the list of all such packages in the Offer, for each
discipline, Minimum requirements of the software to be used for engineering and
documentations are specified in the tender document needs to be complied by the
CONTRACTOR. Additional software if required to be utilized by the CONTRACTOR
during execution of the project shall be indicated by the Bidders along with the offer.
CONTRACTOR is required to execute complete project in the software as specified
or suggested by the CONTRACTOR in the offer and deviation against that will not be
entertained by PMC/OWNER during project execution. In case it is felt that there is a
requirement of any change with respect to software during execution, same shall be
permitted only after approval of PMC/OWNER.
1.17 The CONTRACTOR shall check all documents, including documents of his sub-vendors
before submission to the PMC/OWNER for review. CONTRACTOR shall duly stamp &
sign the hardcopies of documents submitted by him as proof of his vetting. Document
received without CONTRACTOR’s vetting will be returned without review / approval.
Also, the CONTRACTOR will not only rectify any inaccuracies / mistakes found during
review but the CONTRACTOR shall remain liable for bearing charges towards efforts
spent by PMC/OWNER for discussing the same. Delay owing to these shall be to the
account of CONTRACTOR.
1.18 Review of the CONTRACTOR drawings by PMC would be only to review the compatibility
with basic designs and concepts and in no way absolve the CONTRACTOR of his
responsibility/ contractual obligation to comply with Tender/Contract requirements,
applicable codes, specifications and statutory rules/ regulations. Any error/ deficiency
noticed during any stage of manufacturing/ execution/ installation shall be promptly
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
corrected by the CONTRACTOR without any extra cost or time, whether or not comments
on the same were received from PMC during the drawing review stage.
1.19 Only AUTOCAD release 2011 or later versions shall be used for drawings, data sheets
and all graphic works. For all text related documents, MS Word 2011 or later versions
only shall be used.
1.20 CONTRACTOR shall furnish 3D modeling of plant with dynamic walk-through facility to
check any interference, requirement of safety, operation and maintenance for getting
approval from PMC/OWNER. CONTRACTOR shall demonstrate their capability through
walk-through of one of such 3D models developed by them. CONTRACTOR shall carry
out the 3D Modelling in accordance to the specification provided in the tender document.
Such modelling could be done by CONTRACTOR or through an agency approved, which
has proven track record for 3D modelling of packages of similar complexities.
1.21 Drawings shall be prepared on the DRAWING FORMAT as provided to successful bidder.
1.23 The schedule of submission of Drawings / Documents shall be in accordance with Project
plans only. The detailed list of documents/ documents proposed to be submitted for the
PMC/OWNER review (for different categories) shall be prepared by the CONTRACTOR
for review of PMC/OWNER. This activity is to be completed within one month of placement
of the order.
1.24 Sequence of submission of all drawings and documents is essential for proper review of
documents and timely completion of the Project and is to be strictly adhered to. In case
sequence is not maintained, PMC/OWNER will not review the documents submitted and
responsibility of timely execution of Package shall be to CONTRACTOR’s accounts.
1.25 CONTRACTOR shall clearly indicate the sequence of submission of all the drawings/
documents after award of CONTRACT. This sequence shall be adhered during entire
execution period. CONTRACTOR shall also ensure that drawing documents which are
based on other drawings/documents are submitted only after the basis
drawings/documents has been reviewed/approved without any major comment.
Submission not following this sequence will be treated as redundant and may not be
reviewed / approved by PMC/ OWNER.
1.26 PMC/OWNER reserves the right to change the category of documents from review to
records and vice versa.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
1.27 The CONTRACTOR shall maintain latest record of drawings & document status and
make regular issue of drawing/ documents index (discipline wise), on fortnightly/
monthly/weekly basis, as agreed, with copies to PMC Site, HO and OWNER
indicating schedule date of submission, submission date of various revisions and date
of review with code.
1.28 All drawings and documents for each UNIT shall be submitted separately.
1.30 All Documents shall be in ENGLISH language and in M.K.S System of units.
1.31 Before submitting the drawings and documents, CONTRACTOR shall ensure that the
following information is properly entered in each drawing:
A detailed document list clearly identifying the class of review to be performed against
each document shall be developed. Following Codes of review shall be followed for all the
documents prepared by the CONTRACTOR:
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Review
The documents shall be reviewed by PMC/OWNER with respect to specifications,
guidelines and details provided in the Tender package. Upon review of the documents,
approval review codes will be indicated in the documents based on the compliance to
tender requirements.
Information/Records
The CONTRACTOR shall submit documents for OWNER’s/ PMC information/ records
and proceed with the work. Inadequacies/ inaccuracies noticed at any stage of the Project
on such documents/ drawings shall be brought to the attention/ notice of the
CONTRACTOR for corrections and incorporation in works. These corrections, as made
by the CONTRACTOR, shall be to the CONTRACTOR’s account and would not have
any cost or time impact to the OWNER.
Documents falling under review category shall in general, except for drawings
requiring multi-disciplinary review, be returned with comments within 10 working days.
The period of ten working days shall be calculated from the date of receiving the Hard
copy documents at PMC/OWNER Review center. Receiving date shall be considered as
date entered by PMC.
The following cycle time shall be adopted for the incorporation of comments by
CONTRACTOR
CONTRACTOR shall revert on unacceptable comment, if any, within 10 days from the
date of release of documents by PMC/OWNER. In absence of any rebuttal by
CONTRACTOR all comments will be deemed as acceptable to CONTRACTOR.
3.1 The CONTRACTOR shall ensure that all equipment are ordered on vendors who are
capable of supplying the equipment and meet all specifications.
All subsequent changes to purchase requisition following review of the original shall be
subject to prior APPROVAL. Where requisitions specify a particular make or brand of
equipment to be used followed by the statement “or PURCHASER approved equal”, any
such “equal” proposed by the suppliers shall be submitted for APPROVAL of
PMC/OWNER.
A document logging system shall be established within PMC through Web Portal
(Electronics Data Management System) to monitor the review cycle. This log shall be
updated on real time basis.
In case review requires more than stipulated cycle time for any document, CONTRACTOR
shall be informed for the same.
Submissions
• PMC is using electronic document management system for document workflows
and storage.
• All vendor documents shall be submitted and reviewed through web portal. To
facilitate document exchange with the vendors a separate vendor portal for the
successful bidder will be provided at the time of award.
• Discipline wise Document Control Index (DCI) based on VDR in Purchase
Requisitions / Material Requisitions will be created by vendor through the vendor
portal in the format available in the portal.
• DCI shall be submitted and will be approved by PMC. All document submission
on the vendor portal shall be against the approved DCI only.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
5.1. The Drawing Index (discipline wise) shall include description of drawings/ documents,
category of drawings, scheduled date of submission, actual date of submission, review
code received with dates. This shall be updated regularly and copies issued to PMC
site and HO as well as OWNER. Drawings submitted before finalization of drawing index
shall be rejected.
5.2. CONTRACTOR shall plan submission progressively so that no bunching takes place in
any discipline.
5.3. Documents/ drawings received prior to holiday/ week end shall be accounted as received
on the following working day and the review period committed shall include only working
days.
5.4. Quality of drawings / documents is essence for a timely review. If major comments /
deviations to the agreed design basis are noticed, the drawing shall be rejected in Code-
C. (CONTRACTOR cannot proceed with construction with Code-C document).
5.5. Civil/ Instrument & other engineering drawings/ documents shall be issued only after the
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
corresponding Electrical documents coming under approval/ review category are first
approved/ reviewed by the concerned department in Code-B as a minimum.
5.6. For 3D model, review files along with database shall be provided
5.8. Deviation permit, submitted for seeking deviation, shall be separately identified and shall
not be considered as a document for timely approval/ review.
5.9. When PMC deploys engineers at the CONTRACTOR’s work center, following shall be
satisfied:
- Reviews limited to identify long delivery/ schedule critical items only.
- Readiness of documents/ drawings shall be ensured by the CONTRACTOR.
- Presence of lead engineers of all disciplines of the CONTRACTOR.
5.10. If PMC/OWNER highlights any necessary rectifications required in the construction at the
time of Technical Review/ Audit, construction executed based on Reviewed drawings not
complying with Bid requirement, CONTRACTOR shall rectify without any impact of time
and cost to OWNER.
5.11. CONTRACTOR (outside India) shall open an engineering office in India for speedy
document submission and to help faster review of the drawings & documents.
Drawings approved / reviewed under Code-B & Code-A required for execution at site
shall be arranged by CONTRACTOR to PMC (RCM), CONTRACTOR’s RCM and IOCL-
JR (site).
- Copies of only reviewed or final documents like design calculations, design basis etc.
shall be sent to PMC site for records.
- Copy of such transmittal shall be sent to PMC (HO) & IOCL for records.
The drawings requiring PMC/OWNER’s review shall be uploaded on Web Portal of PMC
and E- mail intimation, regarding uploading to be forwarded to PMC/OWNER.
CONTRACTOR shall establish a local office having facility of telephone, fax and electronic
mail system for receiving documents and drawings from outstation.
On uploading the drawings/ documents through Web Portal, CONTRACTOR shall send an
Email Intimation for the same to PMC/OWNER. However, hard copies in numbers as
mentioned in above section of this document shall be sent by CONTRACTOR to
PMC/OWNER by courier or by hand delivery.
After review, PMC/OWNER shall send back the drawings/ documents through Web Portal
with Email intimation to CONTRACTORS.
CONTRACTOR shall also establish electronic system at site to receive all drawings and
documents with all printing and scanning facilities.
templates if required shall be provided to the successful bidders. For the requirement
of Final Documentation in the integrated & smart platform PMC/OWNER shall be
engaging an agency and Project document integration shall be carried out the other.
However, for carrying out the activities related to document integrations by others certain
activities are required to be performed by the CONTRACTOR during execution of the
project is covered in this part of the document.
Sr.
Deliverable List Software
No.
1 Project Scheduling Primavera
2 3D Design E3D/SP3D/Equivalent
3 Electrical System Configuration ETAP Version 20.0.0
In house tools with compatible output
4 Datasheets
in PDF/ Excel
EDMS or Equivalent (For centralization
5 Documentation Handling of documents with vendor, client and
consultant interface)
6 Al Text Data MS Word in Words
7 All Spread Sheet work MS Excel in Windows
8 Final Drawings In PDF as well as in Original Format
For ensuring Integration & smart Document handover CONTRACTOR to ensure following
during execution of the project till final document handover.
conflicts. Any such deviations will be recorded for the documentation clearance at
the time of stage review (30%, 60%, 90% and 100% of engineering completion).
3. Quality assurance will be a part of completion for the stage review (30%, 60%, 90%
and 100%). Non-adherence to data quality standards may impact the milestone
completion and further to the release of the milestone payments of the
CONTRACTOR.
5. During Execution of the Project it is expected that the detailed engineering documents
shall be submitted as generated using following software as minimum.
As built drawings and documents will have to be generated within one month of
completion of activities on respective items of work.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
CONTRACTOR shall furnish electronic files of all the documents under their scope to
PMC/OWNER certified as "As Built Issue". These documents also need to be submitted
through PMC web Portal.
iii. As Built drawings generated specifically for this job in electronic media (AutoCAD
2011 or above) – 2 sets.
iv. All vendor drawings & documents either in AutoCAD or in scanned images stored in
electronic media – 2 sets.
vi. 4 complete sets in hard binders of the Manufacturer’s Data Book including certified
prints and data for all items including test reports. Data Book shall be complete with
index as tag numbers associated with Manufacturer’s data shown. Equipment data
shall include as a minimum requirement the principal and description of operation,
drawings and dimensions, spare parts lists and un- priced purchase orders and bill of
materials.
vii. 4 bound copies each of the Spare Parts data book and the Lubricants inventory
schedule.
viii. The CONTRACTOR’s and OWNER’s representatives at the site shall sign 4 complete
sets of field records.
ix. Original approvals and related drawings and documents from the statutory authority.
9.3 CONTRACTOR shall get the completeness of final documentation verified by PMC/TPIA
and attach the Completeness certificate of Final Documentation duly signed by PMC
or TPIA as applicable to the document folder.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Final Documents shall be legible photocopies in A4, A3 size only. Drawings will be
inserted in plastic pockets (both sides transparent, sheet thickness minimum 0.1 mm) with
an extra strip of 12 mm wide for punching so that drawings are well placed.
Final Documentation shall be bound in hard board plastic folder(s) of size 265 mm x 315
mm and shall not be more that 75 mm thick. It may be of several volumes and each
volume shall have a volume number, index of volumes and index of contents of that
particular volume. Where numbers of volumes are more, 90mm thickness can be used.
Each volume shall have top PVC sheet of minimum 0.15 mm thick duly fixed and
pressed on folder cover and will have 2 lever clips. In case of imported items documents,
4 lever clips shall also be accepted. All four corners of folders shall be properly metal
clamped. Indexing of contents with page numbering must be incorporated by
CONTRACTOR. Spiral/ Spico bound documents shall not be acceptable. As mentioned
above, books should be in hard board plastic folders with sheets punched and having
2/4 lever clips arrangement.
Each volume shall contain on cover a title block indicating Tender No., name of project,
name of customer, package equipment tag no. & name (if applicable). Each volume will
have hard front cover and a reinforced spine to fit thickness of book. These spines will
also have the title printed on them. Title shall include also volume number (say 11 of 15)
etc.
10.3 CONTRACTOR shall also develop supervisory operating manual including concise SOP
(pocket booklets) for the assigned units
Refer Attachment- 1 for discipline wise list of documents identified for review by PMC /
OWNER.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Attachment-1
DOCUMENTS REQUIRED FOR PMC/OWNER REVIEW
LIST OF DOCUMENTS
1. ELECTRICAL 077154C-1825-NM-1600-002_A
5. INSTRUMENTATION 077154C-1825-NM-1500-002_A
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
POST ORDER
FOR FOR FOR
S.NO DOCUMENT DESCRIPTION WITH BID
REVIEW APPROVAL INFORMATION
Design calculations
CT Sizing calculations
Design calculations
8 X
Transformer Sizing calculations
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
POST ORDER
FOR FOR FOR
S.NO DOCUMENT DESCRIPTION WITH BID
REVIEW APPROVAL INFORMATION
Design calculations
10 Lighting X
Cable tray/ trench sizing
12 Insulation co-ordination X
POST ORDER
FOR FOR FOR
S.NO DOCUMENT DESCRIPTION WITH BID
REVIEW APPROVAL INFORMATION
HV Cables, AC and DC UPS system
etc.
POST ORDER
FOR FOR FOR
S.NO DOCUMENT DESCRIPTION WITH BID
REVIEW APPROVAL INFORMATION
Cable schedule / drum schedule and
interconnection and terminal
25 X
diagrams – Power, control cables
including ECS interfacing cables
POST ORDER
FOR FOR FOR
S.NO DOCUMENT DESCRIPTION WITH BID
REVIEW APPROVAL INFORMATION
Material take-off for electrical items
including bulk materials for power,
31 X
lighting, earthing, lightning protection
system etc.
40 Training Manuals X
POST ORDER
FOR FOR FOR
S.NO DOCUMENT DESCRIPTION WITH BID
REVIEW APPROVAL INFORMATION
POST ORDER
WITH
S.NO DESCRIPTION FOR FOR REVIEW FOR REMARKS
BID
APPROVAL INFORMATION
A Duly filled-in Technical
compliance checklist – Civil X
(077154C-1825-NM-1800-002)
B Document control Index (DCI) X
C ARCHITECTURAL
POST ORDER
WITH
S.NO DESCRIPTION FOR FOR REVIEW FOR REMARKS
BID
APPROVAL INFORMATION
authorized applicators to be
engaged for execution of various
specialized items (like Aluminium
Doors and Windows,
Waterproofing/ Insulation, False
ceiling/ Flooring, Partitioning etc.
1 Geotechnical investigation
Report / Foundation X
recommendations
2 Fire proofing philosophy X
3 Structural Design calculation and
Structural drawing of
X
substructure and superstructure
for 33 kV Substation Building
4 Structural Design calculation and
Structural drawing of
substructure and superstructure X X (Note 1)
for Pipe Rack/Cable racks
support
5 Structural Design calculation and
Structural drawing of
substructure and superstructure X (Note 1)
for Transformer foundation and
fire walls
6 Structural Design calculation and
Structural drawing of
X (Note 1)
substructure and superstructure
for Deluge Valve house
7 Structural Design calculation and
Structural drawing for Oil pits and X (Note 1)
cable trenches
8 Structural Design calculation and
Structural drawings for all other
balance works including all
Foundation and Superstructure
for Pipe supports, cable X (Note 1)
supports, operating /
maintenance platforms,
walkways, cross-over, monorails
etc.
9 Fabrication Drawings for main
X
pipe rack & structure
10 Design calculation document &
drawings of Structural steel X
connection details.
11 Monthly updated status of BOQs
of major items (i.e. Pile,
X
Concrete, Rebar & Structural
Steel).
12 All other structural drawings for X
PMC/ EPCM Services for
PROJECT PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
POST ORDER
WITH
S.NO DESCRIPTION FOR FOR REVIEW FOR REMARKS
BID
APPROVAL INFORMATION
miscellaneous platform / support
etc.
E GENERAL CIVIL
NOTES
1) One typical structure / pipe rack / Equipment foundation will be reviewed by PMC and balance shall be issued
for information and as built as part of final documentation.
2) Apart from above, any other document identified during detailed Engineering shall be decided for its category
after award of the Job.
3) "X" denotes Applicability.
4) Computer software input and output also to be included with these documents.
PMC/EPCM SERVICES FOR PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LUPECH” (J-18)
IOCL GUJARAT REFINERY
DOCUMENTS FOR PMC/OWNER’s REVIEW / REFERENCE /
RECORDS – PACKAGED EQUIPMENT
POST ORDER
Sr No DRAWING / DOCUMENT WITH BID
Approval Review Information
PROCESS SAFETY
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
POST ORDER
INFORMATION
FOR REVIEW
APPROVAL
S.No. DESCRIPTION WITH BID REMARKS
FOR
FOR
1. Layout - Firefighting & Safety, Fire and X
Gas detection, Hazardous area
classification-Lupech Power Distribution
Facilities Packages and Buildings
2. Fire water demand calculation X
3. Datasheet for Firefighting & Safety X
Equipment including
specification/datasheet for Nitrogen
Injection system
4. Firefighting & Safety Equipment, Fire & X
Gas Detectors MTO- Lupech Power
Distribution Facility Packages and
Buildings
5. MR for IFI – Firefighting & Safety X
Equipment
6. TBT - Firefighting & Safety Equipment X
7. MR for IFP - Firefighting & Safety X
Equipment
8. Vendor Drawings - Firefighting & Safety X
Equipment
9. Fire and Gas- Cause & Effect Matrix X
10. Operation & Maintenance Manual X
including Vendor manuals
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
POST ORDER
INFORMATION
FOR REVIEW
APPROVAL
S.No. DESCRIPTION WITH BID REMARKS
FOR
FOR
11. Inspection Test Plan (ITP) and Quality X
Assurance Plan (QAP)
12. FINAL DOCUMENTATION containing
the following:
i. All certified as built documents
ii. All inspection & test
records/certificates
iii. All Statutory certificates (IBR, PESO
etc.) X
iv. Operation and maintenance
manuals
v. Spare parts manual
vi. List of Tools & Tackles
Manufacturers Catalogue for various
firefighting equipment and accessories
13. Technical Compliance List – Process X
Safety duly filled by the bidder
Notes:
1. "X" denotes Applicability.
2. Post order, Document/Drawing review shall commence only after approval of Document Control Index
(DCI).
3. All post order documents shall be submitted/Approved through Electronic Document Management
system.
4. Final documentation shall be submitted in hard copies and soft (in DVDs & CD's) as per copies mentioned
elsewhere in tender package in addition to submission through Electronic Document Management
system.
5. The Documents and Drawings listed in the above table indicates the minimum requirements.
CONTRACTOR shall submit drawings / documents (other than the one listed in the above table) which
shall be required to submit as per tender documents / to be submitted as requested by CONSULTANT /
OWNER during the course of execution of the work without any price and schedule implication to
CONSULTANT / OWNER.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
The following drawings/documents marked as “X“ shall be furnished by the bidder/LSTK contractor as part of bid and after
award of contract for Owner / PMC’s Approval / Review / Record. LSTK contractor shall follow the Documentation procedure
attached elsewhere in the ITB.
POST ORDER
Sr. WITH
Description FOR FOR Remarks
No. BID FOR APPROVAL
REVIEW INFORMATION
Duly filled-in Technical
compliance checklist
1 X
(077154C-1825-NM-1500-
001)
2 Document Control Index (DCI) X
X
3 Purchase Requisition Note-2, 3
X
4 Vendor Drawings Note-1
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
POST ORDER
Sr. WITH
Description FOR FOR Remarks
No. BID FOR APPROVAL
REVIEW INFORMATION
14c Commissioning Spares X
14d Special Tools and tackles X
Inspection and test plan and
15 X
procedures
Material Take-off for
Instrument Installation, JBs,
16 X
cables, cable gland, tracing,
etc.,
17 MCT Layout X
Loop Checking/Calibration
18 X
Reports
Certificates (statutory / CCOE/
SIL certificate
19 X
(Exida/TUV/Eqn) and test
calibration / inspection/)
Catalogues including technical
information, Programming
20 manuals & Installation, X
operation and maintenance
manuals
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Notes:
(1) This list indicates the minimum drawings and documents requirements. However, LSTK CONTRACTOR shall submit
below listed documents as minimum and not limited to complete schedule of Documents and Drawings listing all
Documents and Drawings to be prepared by them along with their number and expected date of submission, during
the course of execution of the work.
a) GA/IA drawings
b) Legal Compliance such as PESO/CCOE, etc.,
c) SIL Certification
d) Data Sheet
(2) Material Requisition shall contain instrument data sheets independent of quantity duly filled with selected
manufacturer data along with compliance statement stating either no deviation or deviation with reason with backup
paper shall be included.
(3) a) The following items are identified as critical and under OWNER/PMC approval/Review category.
b) Apart from above identified (a) critical documents, the documents identified by OWNER/PMC from
CONTRACTOR’s drawing schedule shall also submitted for approval.
c) Documents other than those identified for approval / review by OWNER/PMC shall be submitted for Record.
(4) Drawing/Documents related to Gas Detection System/Fire alarm system such as, Wiring drawings, controller loading,
system architecture, FAT procedure, etc., shall be reviewed and approved by the CONTRACTOR
(5) As built drawings shall be submitted for all the documents listed.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
1. CATEGORY OF SPARES
Parts of equipment / systems/items that will be required f or replacement where f ailure of which will be
critical for continuous safe operation of the plant. The ITB / Material Requisitions shall include all Mandatory
Spare Parts and clearly indicate the quantity required. These mandatory spares shall be procured along
with main equipment/ systems/ items. Above-mentioned mandatory spares list defines the minimum
requirement. Additional items as recommended by manufacturer if any shall also be considered.
These will be selected and ordered by OWNER separately. Broad Guidelines f or selection of the same
PETROCHEMICAL AND LUBE
PROJECT INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
CLIENT INDIAN OIL CORPORATION LIMITED
include:
• Current delivery time and transportation time to site of items not stocked.
2. SCOPE OF SUPPLY
The CONTRACTOR shall procure and supply all spare parts required during pre-commissioning and
commissioning of the UNIT and various systems. The price of supply shall be deemed to be inclusive of
the provision of all such commissioning spares required till successful commissioning of the UNIT. The
CONTRACTOR shall make available all the commissioning spares required at site at least 4 (four) weeks
prior to commissioning. Any un-used commissioning spares shall be handed over to OWNER.
The CONTRACTOR shall, within the Lumpsum Price, supply all the mandatory spares as specified in ITB.
The handing over of the spares will be followed through SAP system and the templates against individual
category of items shall be duly filled in by the CONTRACTOR including price for each item before handing
over the mandatory spares to OWNER. Methodology / Modalities to be followed f or handing over of spares
as per SAP system shall be provided by OWNER during Kick of Meeting.
PETROCHEMICAL AND LUBE
PROJECT INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
CLIENT INDIAN OIL CORPORATION LIMITED
b) O & M Spares required for the uninterrupted operation of the Plant during the Defect Liability period shall
be considered by CONTRACTOR. The cost of the spares shall be included in the scope of
CONTRACTOR.
c) Price lists of these spares are intended for information purpose only and shall not be included in
quoted Lumpsum Price.
PETROCHEMICAL AND LUBE
PROJECT INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
CLIENT INDIAN OIL CORPORATION LIMITED
TABLE OF CONTENTS
PAGE
SL.NO DESCRIPTION
NUMBER
3.2 PIPING 7
3.4 ELECTRICAL 10
3.5 INSTRUMENTATION 13
PETROCHEMICAL AND LUBE
PROJECT INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
CLIENT INDIAN OIL CORPORATION LIMITED
3.1.1 HVAC
3.2 PIPING
Spare Quantity
S. No. Part Description Remarks
(%) of As-built
1a Pipes and Fittings (0.5” to 1.5”) 2 Note-2
1b Pipes and Fittings (2” to 8”) 2 Note-2
1c Pipes and Fittings (10” to 36”) 2 Note-2
1d Pipes and Fittings (Above 36”) Nil
2a Valves and Flanges (0.5” to 1.5”) 2 Note-2,3
2b Valves and Flanges (2” to 4”) 2 Note-2,3
2c Valves and Flanges (6” to 8”) 2 Note-2,3
2d Flanges (10” and above) 2
3 Gaskets, Bolts & Nuts (All Sizes) 10 Note-5
4 Steam Traps (All Sizes) 2 Note-8
5 Expansion Bellows (All Sizes) 100
Notes:
1. % of quantity required to be left as mandatory spare is for each and every item consumed in as-built
including for packaged items. No substitution is allowed.
2. As a minimum one piece (/one pipe length) per item spare shall be supplied. No substitution in size
and material allowed.
3. As a minimum one piece per Type per size for valves quantity above 10nos.
4. One actuator of each type is required for motor operated valves as spare.
5. As a minimum one set of bolts/nuts.
6. The above listed spares do not include installed spares/commissioning spares.
7. Wherever “% quantity” is specified, CONTRACTOR to provide in next higher rounded figure.
8. As a Minimum one piece per Type per size as spare for steam trap shall be supplied except process
Traps.
9. Out of % spares and minimum quantity specified against each item, higher of the two shall be
supplied.
PETROCHEMICAL AND LUBE
PROJECT INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
CLIENT INDIAN OIL CORPORATION LIMITED
Notes:
1. The above table does not include any mandatory spares for piping items (such as pipes, fittings,
valves, flanges, blind flanges, gaskets, bolt & nuts etc.
2. The word “Set” means the quantity required for full replacement of that part in one equipment.
3. The spare quantities where specified in terms of percentage, shall be rounded off to the next higher
number.
4. Spare parts shall be identical in all respects to the parts f itted on the main equipment, including
dimensions, material of construction and heat treatment.
5. Mandatory spares shall be supplied to OWNER for the applicable firefighting and safety equipment
in the package. These spares shall not be used during construction, erection or commissioning.
6. Prices of mandatory spares shall be included in the quoted price of the CONTRACTOR.
PETROCHEMICAL AND LUBE
PROJECT INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
CLIENT INDIAN OIL CORPORATION LIMITED
3.4 ELECTRICAL
System
4.1 Thyristors/ Transistors / IGBT / Diode 1 no. of each type and rating
4.2 Control cards 1 no. of each type
4.3 Power supply cards 1 no. of each type and rating
20% or 1 no. (min) of each type and
4.4 Control fuses / MCB
rating - whichever is more
20% or 1 no. (min) of each type and
4.5 Power f uses / MCB
rating - whichever is more
4.6 Indication lamp covers 3 nos. of each colour
10% or 3 nos. (min) - whichever is
4.7 Indication lamps
more
4.8 Panel cooling fans 1 no. each rating
5 One set of spares for each DC
DC system
system
5.1 Thyristors / transistors / IGBT/ Diode 1 no. of each type and rating
5.2 Control cards 1 no. of each type
5.3 Power supply cards 1 no. of each type and rating
20% or 1 no. (min) of each type and
5.4 Control fuses / MCB
rating - whichever is more
20% or 1 no. (min) of each type and
5.5 Power f uses / MCB
rating - whichever is more
5.6 Indication lamp covers 3 nos. of each colour
10% or 3 nos. (min) - whichever is
5.7 Indication lamps
more
6 Battery
6.1 Complete cell assembly 3 nos. of each type and rating
NOTES:
1. Type-means the make, model no., type, size/length, rating, material as applicable.
2. Wherever % is identified, contractor shall supply next rounded figure
PETROCHEMICAL AND LUBE
PROJECT INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
CLIENT INDIAN OIL CORPORATION LIMITED
3.5 INSTRUMENTATION
NOTES:
1. Above-mentioned mandatory spares list defines the minimum requirement for each type. Contractor
to select applicable to his scope of supply f or this unit. Additional items as recommended by
manuf acturer if any shall also be considered.
2. Next rounded f igure to be considered wherever % is specified. Example: For total 11 Nos.
Instruments with 10%> spares basis, 2 Nos. spares shall be provided.
3. The word ‘TYPE’ means the Make, model no., type, range, size/length, rating, material as applicable.
4. The terminology used under ‘Part Description’ is the commonly used name of the part and may vary
f rom manufacturer to manufacturer.
5. Wherever complete instrument/set is considered as spare, spare quantity shall never exceed
PETROCHEMICAL AND LUBE
PROJECT INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
CLIENT INDIAN OIL CORPORATION LIMITED
TABLE OF CONTENTS
2. PLANNING .................................................................................................. 3
3. INSTRUMENTATION ................................................................................... 4
4. CONSTRUCTION ........................................................................................ 4
5. ELECTRICAL .............................................................................................. 4
7. DEVIATIONS ............................................................................................... 5
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
The Bidder shall submit the following documents along with their bid in general. However,
any additional information / technical details also have to be submitted along with the bid, if so
specifically mentioned elsewhere in the tender document.
1.1 Duly filled in technical compliance checklists shall be furnished by the bidder confirming all
points without any deviation.
1.2 List of software for the project including design, engineering, planning, stores
management, etc.
1.7 Proposed organization chart for project engineering, construction and commissioning and
safety along with CVs of key personnel.
2. PLANNING
2.1 Proposed Overall Project Schedule in network form showing details of all units.
2.2 Write up on Project Planning, Scheduling, Monitoring and Control system (proposed).
2.3 Organizational set up for Planning, Scheduling, Monitoring and Control at Package
Contractor’s Design Office and Site Office.
2.6 Function wise Resource Deployment Schedule (manpower and construction equipment)
for this project. Also, concurrent commitments should be given.
3. INSTRUMENTATION
4. CONSTRUCTION
4.2 Transportation plan for Heavy equipment movement from works to erection point.
4.3 Procedure and work method statement for Heavy lift erection.
5. ELECTRICAL
6. QUALITY ASSURANCE
6.2 Project Quality Plan (A brief description of the BIDDER’s quality assurance system and
statement detailing how quality assurance will be implemented for the Project).
6.6 List of other relevant procedures, practices and work instructions which will be used to
control the Project.
7. DEVIATIONS
CONTENTS
1 ELECTRICAL 077154C-1825-NM-1600-001_A
4 INSTRUMENTATION 077154C-1825-NM-1500-001_A
5 PLANNING 077154C-1825-PLG-304-001_A
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
The Compliance Statements / Queries are required to be categorically confirmed / answered by the
Package CONTRACTOR and the completely filled in Technical compliance sheet shall be
submitted along with the bid.
Notes: -
1. The Bidder shall indicate his reply in the space provided in the Technical confirmation. In case space
provided is not adequate, the reply may be furnished separately under suitably numbered annexure/
attachments duly referred against the comment / query.
1. TECHNICAL COMPLIANCE
Following queries are to be categorically answered, Signed, Stamped and included with the Bid
by the Bidder.
8 Bidder to confirm that the final micro grading after completion of works to the
final desired levels is in Bidder’s scope of work.
12 Bidder to confirm that he has checked availability of land for fabrication yard
and considered the same outside the plant boundary if land available within
the plant is not adequate.
13 Bidder to note and confirm that all statutory approvals, from local municipal or
Development authorities and any other concerned local/national/state bodies
as applicable, is in the Bidder’s scope with no extra cost to the OWNER / PMC.
This shall include preparation of documents, carrying out all necessary liaison
works, all payments and fees. Any modifications, alterations/ additions in
scope of work required to meet statutory regulations are included in Bidder’s
scope of work and no extra amount shall be paid on this account.
14 Bidder to confirm that, required earth for filling / micro-grading to achieve the
desired levels as per OWNER / PMC shall be arranged by the Bidder and
borrow areas shall be got approved by OWNER / PMC. Bidder shall also
dispose surplus earth/ debris etc. outside Plant Complex compound wall. For
borrowed earth or disposal outside plant boundary, location for borrow area /
disposal of surplus earth, debris shall be identified by the Bidder. Bidder shall
obtain relevant statutory approval from all statutory authorities (like municipal
etc.) including payment of charges for the same. Bidder shall keep the client
indemnified of any liability and / or complaint from local authorities / municipal
bodies / local public.
15 Bidder shall identify the exact locations at site where connections, tie-ins /
hook-ups are required for various services and facilities during pre-bid site visit.
Confirm compliance.
16 Bidder to note that rerouting & remaking, strengthening, widening, dismantling
as directed, of any permanent structure / roads / culverts / drains / other
structures or any other services as per detailed engineering necessary for the
completion of job are in Bidder scope. Confirm compliance.
17 Bidder to note and confirm that providing sleeves / culverts for storm water
drains etc. at all road crossings, ERC (culvert), IRC (culvert), SCRC on all
roads within scope limit, laying / crossing work of process pipe line, water pipe,
electric cable and instrument cables, etc. are in Bidder’s scope.
18 Bidder to note and confirm that for RCC pipes, wherever required as per
Design Basis, socket and spigot type joint shall only be used. No collar type
jointed pipes are acceptable.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18) IOCL GUJARAT
PROJECT
REFINERY
20 Bidder to confirm that, the seismic zone is considered as per the design basis
- 077154C-000-JSD-1700-001.
21 Bidder shall provide all structure/ hard stands (shall be designed and provided
by Bidder depending upon the type of crane and erection sequence) / approach
roads etc. required for erection of equipment & dismantling the same after
completion of work if required (as per direction of Engineer-in-charge). Confirm
compliance.
22 Note and confirm that Bidder has understood the subsoil profile as given in
Geotechnical recommendation, which shall also be followed for earth work,
subgrade preparation of trenches, bedding & backfilling under / around for
underground pipes in all types of soil within his scope limit.
23 Bidder shall go through the design basis, specifications and soil report and
design the foundation accordingly. Bidder to confirm the above will be followed.
24 Bidder to confirm that piling has been considered as per the foundation
recommendation given in geotechnical report.
34 Bidder to confirm that painting for building will be done as per applicable codes
and standards.
35 Bidder to confirm that all temporary barricading, water curtain, fencing required
during construction activities shall be provided and maintained by the bidder
during execution of the works and same shall be removed, if required, after
completion of works including remaking/finishing of the surface.
Notes: -
1. The Bidder shall indicate his reply in the space provided in the Technical confirmation. In case space
provided is not adequate, the reply may be furnished separately under suitably numbered annexure/
attachments duly referred against the comment / query.
2. The confirmation statements / Queries are required to be categorically confirmed/answered by the Bidder
and the completely filled in Technical confirmation shall be submitted together with the Bid.
TECHNICAL COMPLIANCE
Project No. Document No. Rev. No.
CHECKLIST 077154C001 077154C-1825-NM 1900-002 A
Page 1 of 2
PROCESS SAFETY
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE4
S.
COMPLIANCE STATEMENT / QUERY BIDDER’S REPLY
No.
1. Please confirm that, the site area has been physically surveyed by bidder and well
acquainted with the site area and collected relevant existing system information
from site.
2. Please note and confirm that, all statutory approvals within scope limit are in the
Bidder’s scope of work. Any modifications, alterations/ additions required to meet
statutory regulations are in the Bidder’s scope of work and no extra amount shall
be paid on this account.
3. Please confirm that entire Fire protection system, Fire & Gas Detection System,
Personal Protection System shall comply to Design Basis/OISD / Statutory
Requirements. In case of conflicts, most stringent requirement will govern.
4. Please note and ensure that, entire fire water system including associated
requirements within unit and battery limit conditions specified as per scope of work.
5. Bidder must ensure the Fire water system requirements including fixed water
spray system for cable cellar and Nitrogen Injection System for transformers as
per the scope of work.
6. All firefighting equipment shall be as per attached data sheet / standard
specifications. Confirm compliance.
7. Please confirm that all approaches for construction, erection, maintenance,
emergency evacuation, firefighting etc. have been included in bidder’s scope of
work.
8. First aid appliances, extinguishers, all firefighting equipment like hydrants, portable
monitors, hoses, hose reels, nozzles, hose boxes, spray system equipment, etc.,
shall be provided as per practices & codes/standards inside the Lupech Power
Distribution facility package scope area as applicable.
9. Confirm that the entire work shall be executed as per contract document.
10. Confirm that the equipment and components supplied shall be from one of the
approved vendors given in the in the bid document.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
TECHNICAL COMPLIANCE
Project No. Document No. Rev. No.
CHECKLIST 077154C001 077154C-1825-NM 1900-002 A
Page 2 of 2
PROCESS SAFETY
Bidding Document Reference: 077154C/T/LuPech(J18)/PACKAGE4
S.
COMPLIANCE STATEMENT / QUERY BIDDER’S REPLY
No.
11. Confirm that pre-commissioning, commissioning spares, consumables, first fill,
standby fill etc. as required for each equipment has been included in the proposal
as per ITB.
12. Confirm that Special Tools and Tackles, as required for each equipment, have
been included in the proposal as per ITB.
13. Confirm that all consumables such as lubricants etc. as applicable for initial charge
and for pre-commissioning, commissioning and site performance guarantee run
have been included.
14. Please confirm compliance on Mandatory spare part requirements as per ITB.
15. Confirm that the Inspection & Testing requirements including third party
inspections as required shall be complied and included in the proposal with its
necessary cost.
16. Bidder to confirm that no cast iron valves are used for fire water services. Only
cast steel valves as per OISD/ PMS shall be provided.
17. Please note and confirm that all required structures, Civil supports, RCC
Trench/covers, Culverts for road crossing, etc. as required as per specification are
included in the offer.
18. Bidder shall comply with all necessary approvals for the fire protection system in
the scope including the local authority any & PESO/OISD etc.
19. Please note and confirm that the Lupech Power Distribution Facility package shall
be adequately protected by firefighting system. as per specifications, OISD and
NFPA’s requirements.
- Complete fire detection and protection in the bidder’s scope work.
- First aid appliances, extinguishers etc. shall be provided as per OISD/ NFPA.
20. Confirm that the entire fire protection system work shall be executed and
commissioned as per contract document.
21. Please note and confirm that, fire water network and system dismantling within
battery limit including associated requirements specified shall be in the Bidder’s
scope of work including rerouting with nearest existing fire water network or
blinding off, hydro-testing, commissioning complete in all respect.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
INSTRUMENTATION
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It
shall not be used for any purpose other than that for which it is supplied.
Please note that it is mandatory to furnish replies to the technical queries listed below, without which bidder’s
offer will be considered as incomplete and is liable for rejection.
Notes: -
1. The Bidder shall indicate his reply in the space provided in the Technical confirmation. In case space provided is not
adequate, the reply may be furnished separately under suitably numbered annexure/ attachments duly referred against
the comment / query.
2. The confirmation statements / Queries are required to be categorically confirmed/answered by the Bidder and the
completely filled in Technical confirmation shall be submitted together with the Bid.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J‐18)
IOCL GUJARAT REFINERY
TECHNICAL COMPLIANCE
CHECKLIST – PLANNING
Doc. No: 077154C-1825-PLG-304-001 Rev: A Page 1 of 1
Bidders to give specific confirmation that following documents have been submitted along with bid.
(please refer project execution plan” “enclosed with the bidding document)
Notes: -
1. The Bidder shall indicate his reply in the space provided in the Technical confirmation. In case
space provided is not adequate, the reply may be furnished separately under suitably numbered
annexure/ attachments duly referred against the comment / query.
2. The confirmation statements / Queries are required to be categorically confirmed/answered by the
Bidder and the completely filled in Technical confirmation shall be submitted together with the Bid.
PROJECT PMC/ EPCM Services for
PETROCHEMICAL AND LUBE
INTEGRATION PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
Sub Supplier List for LuPech Project No. Document No. Rev. No.
Page 1 of 62
Power Distribution Facility 077154C001 077154C-1825-SL-1650-004 A
Digitally signed by
Govindarajan DN:
Govindarajan Ramakrishanan
o=Technip Energies
Anand Kandasamy Ramakrishana Employee, cn=Govindarajan Venkataraman Krishnamoorthy
2021.06.03 14:40:38 Ramakrishanan 2021.06.03 16:49:20 +05'30'
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
1. PACKAGE SUPPLIER / CONTRACTOR shall necessarily procure all the material / equipment forming
permanent part of the WORK from Vendor’s / Suppliers listed in applicable categories in the MSL only. This
shall include sub-ordered items / components also. The Approved Vendors shall be item specific.
2. Any and all additions /deletions in the MSL shall be subject to OWNER/PMC approval.
3. New Vendors/Suppliers added to the existing category in the MSL shall be considered by PACKAGE
SUPPLIER / CONTRACTOR for all the new enquiries issued for that category after such additions.
4. PACKAGE SUPPLIER / CONTRACTOR may request additions to MSL. In such cases, it is PACKAGE
SUPPLIER / CONTRACTOR’s responsibility to ensure any vendor proposed for addition to the list is
technically qualified to carry out the required work , operates a quality system in accordance with latest ISO
norms or equivalent, is financially stable, can demonstrate past satisfactory experience of similar work, has
the availability of technical support and resources , satisfactory after sales and complies with necessary
Secrecy Declarations, and shop loading / Capacity to complete the required scope of work. PACKAGE
SUPPLIER / CONTRACTOR shall be required to demonstrate to OWNER /PMC’s satisfaction compliance
with this requirement. Consideration of proposed alternate vendors is at the sole discretion of the OWNER
/ PMC and OWNER /PMC may decline to evaluate those vendors based on prior knowledge or resource
limitations.
6. The deletion of Vendor(s) from MSL may be proposed by PACKAGE SUPPLIER / CONTRACTOR provided
detailed and qualified reasons are provided for OWNER/PMC’s review and approval.
7. PACKAGE SUPPLIER / CONTRACTOR shall verify with the Vendor regarding current validity, holiday
status and range of approval, workload, stability and solvency before placement of order. PACKAGE
SUPPLIER / CONTRACTOR is also required to ensure that equipment qualification criteria, specified
elsewhere in the bid document are also simultaneously met.
8. Vendors on OWNER / PMC holiday list shall not be considered for ordering. PACKAGE SUPPLIER /
CONTRACTOR shall comply with this requirement without any time or cost implication to the OWNER. If a
vendor is put on OWNER/PMC’s holiday list subsequent to PACKAGE SUPPLIER / CONTRACTOR placing
an order, it shall be PACKAGE SUPPLIER / CONTRACTOR’s responsibility to ensure quality work and
timely supply from the vendor.
9. PACKAGE SUPPLIER / CONTRACTOR shall make an independent assessment of capability of all the
vendors for timely deliveries of material / equipment. Any delays in deliveries by vendor(s) shall not be a
cause of schedule and cost implication.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
10. For Vendors included in each category , it will be PACKAGE SUPPLIER / CONTRACTOR’s responsibility
to ensure that the item being ordered on approved vendor has been manufactured and supplied by them (
range , thickness, size, Capacity, MOC, etc.) on past projects of IOCL/PMC or any reputed Refinery
/Hydrocarbon Sector.
11. At any stage of the project, if it comes to the notice of OWNER / PMC that PACKAGE SUPPLIER /
CONTRACTOR has procured material / equipment, intentionally or unintentionally whatsoever, from an
unapproved vendor and/or items not falling in approved range of vendor(s), the same shall be rejected
forthwith and PACKAGE SUPPLIER / CONTRACTOR shall be liable to replace such material / plant /
machinery without any schedule and cost implication to the OWNER.
12. Wherever Licensor recommended Vendor list is provided, it shall overrule the vendor list enclosed
herewith. Whenever, Vendors list is given by Process Licensor, for specific items, PACKAGE SUPPLIER /
CONTRACTOR shall follow the same.
13. It is understood that should the name of Vendor be changed due to change in their Company or Corporate
shareholding, OWNER may accept such Vendors under its new name with prior approval. Any such
approval shall, however, not absolve the PACKAGE SUPPLIER / CONTRACTOR from any of his
obligations under the contract, neither shall any such approval signify nominations or instruction to use
such a vendor. All approved vendors are deemed to have been freely chosen by the PACKAGE SUPPLIER
/ CONTRACTOR at his own risk.
14. The approved vendors list for fabricated equipment (Vessels, Column, Heat Exchangers, Ejectors etc.) is
for fabrication alone. Where mechanical design of the equipment is included in PACKAGE SUPPLIER /
CONTRACTOR’S scope, PACKAGE SUPPLIER / CONTRACTOR shall either himself or through his
Detailed Engineering sub- sub-contractor be responsible for designing and obtaining approval / review of
Mechanical design calculations as per codes/specifications specified elsewhere in the Bid/ Supplier
document from OWNER / PMC.
15. PACKAGE SUPPLIER / CONTRACTOR can use any Suppliers/Vendors from a country which shares a
land border with India provided if the said Supplier is registered with the Competent Authority in line with
requirements specified by Government of India. Broad Guidelines in this regard is specified in the Tender.
The PACKAGE SUPPLIER / CONTRACTOR shall ensure to complete the registration process by such
Suppliers/Vendors before the placement of Order and provide proof of the same to OWNER/PMC.
16. Any item /material/ equipment value less than INR 200 crores shall be inquired only to Indian Vendors.
17. If any item is not listed in this document, PACKAGE SUPPLIER / CONTRACTOR shall contact PMC /
OWNER for the Approved Supplier list.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
MASTER INDEX
SECTION-A : EQUIPMENTS
S.No Category Page No
3 FIRE FIGHTING EQUIPMENT 5-6
4 HVAC & MISCELLANEOUS 6-8
SECTION-B : BULK PIPING ITEMS
1 PIPING & FITTINGS 9-29
SECTION-C : ELECTRICAL
5 ELECTRICAL EQUIPMENTS 29-48
SECTION-D : INSTRUMENTATION ITEMS
6 INSTRUMENTS 48-57
SECTION-E : CIVIL & STRUCTURAL ITEMS
7 CIVIL & STRUCTURAL ITEMS 57-62
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-A : EQUIPMENTS
S.No SUPPLIER NAME COUNTRY
3 FIRE FIGHTING EQUIPMENT
3.1 FIRE EXTINGUISHERS (PORTABLE)
A INDIAN BIDDERS
3.1.1 ASCO STRUMECH PVT LTD INDIA
3.1.2 BHARAT ENGG. WORKS INDIA
3.1.3 BRIJBASI HI-TECH UDYOG INDIA
3.1.4 FIRE SAFETY DEVICES PVT. LIMITED INDIA
3.1.5 GUNNEBO INDIA LIMITED INDIA
3.1.6 INTEGRATED FIRE PROTECTION PVT. LTD. INDIA
3.1.7 INTIME FIRE APPLIANCES PVT LTD INDIA
3.1.8 KANADIA FYR FYTER PVT. LTD. INDIA
3.1.9 KIDDE INDIA LTD. INDIA
3.1.10 NEWAGE INDUSTRIES INDIA
3.1.11 NITIN FIRE PROTECTION INDUSTRIES LTD INDIA
3.1.12 SAFEX FIRE SERVICES LTD. INDIA
3.1.13 SUPREMEX EQUIPMENTS INDIA
3.1.14 UNITED FIRE EQUIPMENTS PVT. LTD. INDIA
3.1.15 VIMAL FIRE CONTROLS PVT LTD INDIA
3.1.16 ZENITH FIRE SERVICES (INDIA) PVT. LTD. INDIA
3.1.17 MINIMAX INDIA
B FOREIGN BIDDERS ( FOR GLOBAL TENDERING AS APPLICABLE)
3.1.18 MINIMAX GmbH & Co.KG GERMANY
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-A : EQUIPMENTS
S.No SUPPLIER NAME COUNTRY
B FOREIGN BIDDERS ( FOR GLOBAL TENDERING AS APPLICABLE)
3.2.7 EMERGENCY SHOWER COMPANY LTD UK
3.2.8 KNOWSLEY S.K. LIMITED UK
3.2.9 SHOWERS & EYEBATHS LIMITED UK
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-A : EQUIPMENTS
S.No SUPPLIER NAME COUNTRY
4.30.1 GE POWER INDIA LIMITED INDIA
4.30.2 CROMPTON GREAVES LTD. INDIA
4.30.3 PATEL AIRFLOW LTD INDIA
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-A : EQUIPMENTS
S.No SUPPLIER NAME COUNTRY
4.36.2 CARRYAIRE INDIA
4.36.3 DYNACRAFT INDIA
4.36.4 RAVISTAR INDIA
4.36.5 TITUS INDIA
4.36.6 TROX INDIA
4.36.7 METAL AIRE INDIA
4.36.8 WATERLOO INDIA
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
1.74 FASTENERS
A INDIAN BIDDERS
1.74.1 AEPCOM FASTENERS PRIVATE LIMITED INDIA
1.74.2 DEEPAK FASTENERS LIMITED (DORAHA UNIT) INDIA
1.74.3 FASTENERS & ALLIED PRODUCTS PVT LTD. INDIA
1.74.4 FIX FIT FASTENERS MFG. PVT.LTD. INDIA
1.74.5 HARDWIN FASTENERS PVT LTD. INDIA
1.74.6 HEM INDUSTRIES INDIA
1.74.7 INDUSTRIAL ENGINEERING CORP. INDIA
1.74.8 KUNDAN INDUSTRIES LTD. INDIA
1.74.9 LAKSHMI PRECISION SCREWS LTD INDIA
1.74.10 MEGA ENGINEERING PVT. LTD. INDIA
1.74.11 MULTI FASTENERS PVT LTD INDIA
1.74.12 NITIN FASTNERS PVT LTD INDIA
1.74.13 PANKAJ INTERNATIONAL INDIA
1.74.14 PIONEER NUTS & BOLTS PVT LTD INDIA
1.74.15 PRECISION AUTO ENGINEERS INDIA
1.74.16 PRECISION ENGG. INDUSTRIES INDIA
1.74.17 PRESIDENT ENGINEERING WORKS INDIA
1.74.18 PROCYON TCHNOLOGY INDIA
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
5 ELECTRICAL EQUIPMENT
5.2 SWITCHBOARD-MV: MCC/ASB/LDB-FIXED TYP
A Indian Bidders
5.2.1 ABB INDIA LIMITED INDIA
5.2.2 C & S Electric Ltd INDIA
5.2.3 Controls & Schematics Ltd INDIA
5.2.4 LARSEN & TOUBRO LIMITED INDIA
5.2.5 M.K. Engineers & Controls Pvt. Ltd. INDIA
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
5.2.6 Schneider Electric India Private Limited INDIA
5.2.7 Siemens Ltd INDIA
5.2.8 BCH ELECTRIC LIMITED INDIA
B Foreign Bidders (wherever applicable) Nil
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
5.6.4 Schneider Electric Infrastructure Limited (SEIL) INDIA
5.6.5 Siemens India INDIA
5.6.6 Toshiba Transmission & Distribution Systems (India) Private Limited INDIA
B Foreign Bidders (wherever applicable) Nil
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
5.9.5 Jyoti Ltd INDIA
5.9.6 LARSEN & TOUBRO LIMITED INDIA
5.9.7 OMRON INDIA
5.9.8 Schneider Electric India Private Limited INDIA
5.9.9 Siemens Ltd INDIA
B Foreign Bidders (wherever applicable) Nil
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
5.13.5 Schneider Electric India Private Limited INDIA
5.13.6 Narayan Powertech Pvt. Ltd. INDIA
5.13.7 Pragati Electricals Pvt. Ltd. INDIA
5.13.8 Precise Electricals INDIA
5.13.9 Silkaans Electricals Pvt. Ltd. INDIA
B Foreign Bidders (wherever applicable) Nil
5.18 CONTACTOR
A Indian Bidders
5.18.1 ABB INDIA LIMITED INDIA
5.18.2 BCH Electric Ltd INDIA
5.18.3 C&S Electric Ltd INDIA
5.18.4 GE T&D India Limited INDIA
5.18.5 LARSEN & TOUBRO LIMITED INDIA
5.18.6 Schneider Electric India Private Limited INDIA
5.18.7 Siemens Ltd INDIA
B Foreign Bidders (wherever applicable) Nil
5.19 MCCB
A Indian Bidders
5.19.1 ABB INDIA LIMITED INDIA
5.19.2 GE T&D India Limited INDIA
5.19.3 Havells India Ltd INDIA
5.19.4 LARSEN & TOUBRO LIMITED INDIA
5.19.5 Schneider Electric India Private Limited INDIA
5.19.6 Siemens Ltd INDIA
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
B Foreign Bidders (wherever applicable) Nil
5.2 TIMERS
A Indian Bidders
5.20.1 Electronic Automation Pvt Ltd INDIA
5.20.2 Honeywell Automation India Limited INDIA
5.20.3 ICA Pvt. Limited (Omron) INDIA
5.20.4 Schneider Electric India Private Limited INDIA
5.20.5 OEN INDIA
5.20.6 Siemens Limited INDIA
5.20.7 GE T&D India Limited INDIA
B Foreign Bidders (wherever applicable) Nil
5.21 PUSH BUTTON & INDICATING LAMPS (Independent supply / Retrofitting /
Alteration / Modification work)
A Indian Bidders
5.21.1 C & S Electric Ltd INDIA
5.21.2 Essen Deinki INDIA
5.21.3 Hotline Switchgear & Controls INDIA
5.21.4 LARSEN & TOUBRO LIMITED INDIA
5.21.5 Precifine Products Pvt. Ltd. INDIA
5.21.6 Schneider Electric India Private Limited INDIA
5.21.7 Shri Tulsi Switchgears Pvt Ltd INDIA
5.21.8 Siemens Limited INDIA
5.21.9 Teknic Electric (I) Pvt. Ltd. INDIA
B Foreign Bidders (wherever applicable) Nil
5.22 MCB (Independent supply / Retrofitting / Alteration / Modification work)
A Indian Bidders
5.22.1 ABB INDIA LIMITED INDIA
5.22.2 C & S Electric Ltd INDIA
5.22.3 Havells India Ltd INDIA
5.22.4 Novateur Electrical & Digital Systems P INDIA
5.22.5 Indiana Current Control Ltd INDIA
5.22.6 Legrand (India) Pvt. Ltd INDIA
5.22.7 Siemens Limited INDIA
5.22.8 Standard Electricals Ltd INDIA
5.22.9 Schneider Electric India Private Limited INDIA
5.22.10 Polycab India Limited (MCB upto current range 63A) INDIA
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
B Foreign Bidders (wherever applicable) Nil
5.23 HEAVY DUTY SWITCHES (Independent supply / Retrofitting / Alteration /
Modification work)
A Indian Bidders
5.23.1 C & S Electric Ltd INDIA
5.23.2 Schneider Electric India Private Limited INDIA
5.23.3 Novateur Electrical & Digital Systems P INDIA
5.23.4 Siemens Ltd INDIA
B Foreign Bidders (wherever applicable) Nil
5.24 CONTROL SWITCHES FOR BREAKER (Independent supply / Retrofitting / Alteration /
Modification work)
A Indian Bidders
5.24.1 GE T&D India Limited INDIA
5.24.2 Reliable Electronic Components Pvt Ltd INDIA
5.24.3 Switron Devices INDIA
B Foreign Bidders (wherever applicable) Nil
INDIA
5.25 CONTROL SWITCHES / SELECTOR SWITCHES (Independent supply / Retrofitting / INDIA
Alteration / Modification work)
A Indian Bidders
5.25.1 GE T&D India Limited INDIA
5.25.2 Hotline Switchgear & Controls INDIA
5.25.3 Kaycee Industries Ltd. INDIA
5.25.4 Schneider Electric India Private Limited INDIA
5.25.5 Reliable Electronic Components Pvt Ltd INDIA
5.25.6 Siemens Limited INDIA
5.25.7 Switron Devices INDIA
B Foreign Bidders (wherever applicable) Nil
A Indian Bidders
5.26.1 ABB INDIA LIMITED INDIA
5.26.2 GE T&D India Limited INDIA
5.26.3 Havells India Ltd INDIA
5.26.4 Legrand (India) Pvt. Ltd INDIA
5.26.5 Novateur Electrical & Digital Systems P INDIA
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
5.26.6 Schneider Electric India Private Limited INDIA
5.26.7 Siemens Ltd INDIA
B Foreign Bidders (wherever applicable) Nil
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
5.31.9 Kappa Electricals INDIA
5.31.10 Kirloskar Electric Co. Ltd India INDIA
5.31.11 Raychem Rpg India INDIA
5.31.12 Sudhir Power Limited INDIA
5.31.13 Transtron Electricals Pvt Ltd India INDIA
5.31.14 Voltamp Transfomers INDIA
B Foreign Bidders (wherever applicable) Nil
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
B Foreign Bidders (wherever applicable) Nil
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
A Indian Bidders
5.57.1 Bajaj Electricals Ltd INDIA
5.57.2 Baliga Lighting Equipments (P) Limited INDIA
5.57.3 Cooper Crouse-Hinds INDIA
5.57.4 CG Power and Industrial Solutions Ltd INDIA
5.57.5 FCG Flamproof Control Gears P. Ltd INDIA
5.57.6 FCG Power Industries Pvt Ltd INDIA
5.57.7 Flameproof Equipments Pvt.Ltd INDIA
5.57.8 Flexpro Electricals Pvt Ltd INDIA
5.57.9 Kaysons Techno Equipment P Ltd. INDIA
5.57.10 PEPPERL & FUCHS MANUFACTURING (INDIA) PRIVATE LIMITED / INDIA
OEM Authorised bidder: M/s. Pepperl & Fuchs (India) Pvt Ltd. – INDIA
5.57.11 Prompt Engineering Works INDIA
5.57.12 R Stahl INDIA
5.57.13 Sudhir Switchgears Pvt Ltd INDIA
5.57.14 Victor Product PLC INDIA
B Foreign Bidders (wherever applicable)
5.57.16 A.T.X SA FRANCE
5.57.17 R Stahl Schaltgerate Gmbh INTERNATIONAL
5.57.18 Victor Products PLC UK
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
A Indian Bidders
5.60.1 Bajaj Electricals Ltd INDIA
5.60.2 CG Power and Industrial Solutions Ltd INDIA
5.60.3 Philips Electronics India Limited INDIA
B Foreign Bidders (wherever applicable) Nil
5.62 LIGHTING PANEL / POWER PANELS & DISTRIBUTION BOARDS (SAFE AREA)
A Indian Bidders
5.62.1 ABB INDIA LIMITED INDIA
5.62.2 Advance Panels & Switchgear (P) Ltd INDIA
5.62.3 C & S Electric INDIA
5.62.4 Havells India Ltd INDIA
5.62.5 Indo Asian Fusegear INDIA
5.62.6 Indo Chem INDIA
5.62.7 Industrial Switchgear & Controls (Bombay) Pvt. Ltd INDIA
5.62.8 Intrelec INDIA
5.62.9 Legrand INDIA
5.62.10 M.K Engineers & Controls Pvt. Ltd INDIA
5.62.11 Md Switchgear Ltd INDIA
5.62.12 Novateur Electrical & Digital Systems Pvt Ltd INDIA
5.62.13 Standard Electricals INDIA
5.62.14 Zenith Engineering Corporation INDIA
B Foreign Bidders (wherever applicable) Nil
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
A Indian Bidders
5.63.1 Cable Corporation of India Limited INDIA
5.63.2 Finolex Cables Ltd. INDIA
5.63.3 KEC International Ltd INDIA
5.63.4 KEI Industries Limited INDIA
5.63.5 POLYCAB INDIA LIMITED INDIA
5.63.6 Sterlite Power Transmission Limited (under Sterlite Technologies Limited) INDIA
5.63.7 Torrent Cables Ltd INDIA
5.63.8 Universal Cables Limited INDIA
B Foreign Bidders (wherever applicable) Nil
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
5.65.6 Insucon Cable And Cond Pvt Ltd INDIA
5.65.7 KEI Industries Limited INDIA
5.65.8 POLYCAB INDIA LIMITED INDIA
5.65.9 Suraj Cables INDIA
5.65.10 SUYOG ELECTRICALS LIMITED INDIA
B Foreign Bidders (wherever applicable) Nil
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
5.67.2 Associated Cables Pvt Ltd INDIA
5.67.3 Associated Flexibles & Wires [P] Ltd INDIA
5.67.4 Cables Corporation of India INDIA
5.67.5 CMI Limited INDIA
5.67.6 Cords Cable Industries Ltd INDIA
5.67.7 Delton Cables Limited INDIA
5.67.8 Ecko Cables Pvt. Ltd. INDIA
5.67.9 Elkay Telelinks Ltd. INDIA
5.67.10 Finolex Cables Ltd. INDIA
5.67.11 Gemscab Industries Ltd INDIA
5.67.12 Havells India Ltd INDIA
5.67.13 Icon Cable Ltd. INDIA
5.67.14 Insucon Cables And Cond Pvt Ltd INDIA
5.67.15 KEC International Ltd INDIA
5.67.16 KEI Industries Limited INDIA
5.67.17 North Eastern Cables Pvt. Ltd. INDIA
5.67.18 POLYCAB INDIA LIMITED INDIA
5.67.19 Rallison Electricals Pvt. Ltd. INDIA
5.67.20 Ravin Cables Limited INDIA
5.67.21 Reliance Engineers Ltd. INDIA
5.67.22 Scot Innovation Wires & Cables Pvt. Ltd. INDIA
5.67.23 Special Cables Pvt. Ltd. INDIA
5.67.24 Sriram Cables Pvt Ltd INDIA
5.67.25 Suraj Cables INDIA
5.67.26 SUYOG ELECTRICALS LIMITED INDIA
5.67.27 Thermo Cables Ltd. INDIA
5.67.28 Torrent Cables Ltd INDIA
5.67.29 Universal Cables Ltd INDIA
B Foreign Bidders (wherever applicable) Nil
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
5.68.5 KEI Industries Limited INDIA
5.68.6 Reliance Engineers Ltd INDIA
5.68.7 Vindhya Telelinks Ltd INDIA
5.66.8 SUYOG ELECTRICALS LIMITED INDIA
B Foreign Bidders (wherever applicable) Nil
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
5.71.2 Siemens Enterprise Communications INDIA
B Foreign Bidders (wherever applicable)
5.71.3 Armtel LLC Russia
5.71.4 Comtrol PTE Ltd Singapore
5.71.5 Industronic Ind.-Elec. Gmbh & Co. Kg Germany
5.71.6 Neuman Elektronik Gmbh & Co Germany
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
5.74.4 Honeywell Automation India Ltd. INDIA
5.74.5 Mather & Platt India Ltd INDIA
5.74.6 New Fire Engineers (P) Ltd INDIA
5.74.7 Tyco Fire & Security India Pvt. Ltd INDIA
5.74.8 Vijay Fire Protection Sytem Ltd INDIA
B Foreign Bidders (wherever applicable)
5.74.9 Honeywell INC USA
5.74.10 Siemens Building Technologies INTERNATIONAL
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
SECTION-C : ELECTRICAL
S.No SUPPLIER NAME COUNTRY
B Foreign Bidders (wherever applicable) Nil
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
7.1 CEMENT
A INDIAN BIDDERS
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
A INDIAN BIDDERS
7.3 RE-BARS
A INDIAN BIDDERS
7.4 PAINTS
A INDIAN BIDDERS
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
A INDIAN BIDDERS
A INDIAN BIDDERS
A INDIAN BIDDERS
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
A INDIAN BIDDERS
A INDIAN BIDDERS
A INDIAN BIDDERS
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
A INDIAN BIDDERS
A INDIAN BIDDERS
A INDIAN BIDDERS
A INDIAN BIDDERS
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
A INDIAN BIDDERS
This document is developed by TECHNIP India Limited and the information it contains is property of Indian Oil Corporation Ltd. It shall
not be used for any purpose other than that for which it is supplied.
PACKAGE-4
LUPECH POWER DISTRIBUTION FACILITY FOR PETROCHEMICAL
AND LUBE INTEGRATION PROJECT “LUPECH” (J-18) PROJECT AT
IOCL GUJARAT REFINERY, INDIA
(BIDDING DOCUMENT NO.: 077154C/T/LuPech(J-18)/PACKAGE-4)
SCHEDULE OF PRICES
SCHEDULE OF PRICES
1. Price must be filled strictly in the format enclosed. If price quoted, in separate typed sheets and
any variation noticed, the bid is liable to be rejected. In case any contradiction is noticed between
price formats attached with bidding document and price format used in price bid submitted,
description/ contents of price format attached with bidding document shall prevail.
2. Bidder shall specify name of company and sign & affix seal on all pages of price bid.
3. Bidder shall quote Two prices – SUPPLY PRICE (SP-1) and SERVICE PRICE (SP- 2).
(a) SUPPLY PRICE (SP-1) shall include price of all Materials required for completion of the
Works in all respects including construction material.
(b) SERVICE PRICE (SP-2) shall comprise of Residual Process Design, Detailed Design and
Engineering, Prices for Construction services and other allied services required as per
bidding document.
4. Prices quoted in SP-1 and SP-2 shall be considered as separate prices and the entire contract
shall be considered to be fully and conclusively covered under these prices.
5. Total Lump Sum Price means aggregate of Lump Sum prices quoted in FORM SP-1, FORM SP-
2. However, for convenience of all, bidder is required to summarize above price in FORM SP-0.
6. Break-up of Lump Sum price indicated in FORM SP-4 and FORM SP-5 is for further break down
of Supply Price and Service Price. However, total price payable under the Contract shall be
restricted to Lump Sum price quoted in FORM SP-1 and SP-2 respectively.
7. In case of any contradiction between lumpsum price mentioned in FORM SP-0 and breakup of
lumpsum price mentioned in FORM SP-1 and FORM SP-2, following precedence shall apply:
(a) FORM SP-0;
(b) FORM SP-1, FORM SP-2
In case of this contradiction, Prices of SP1 & SP2 shall be modified on Prorata based on Price
quoted in FORM SP-0, limited to lumpsum prices quoted in FORM SP-0.
8. In case of any contradiction between Lump Sum Prices indicated in SP-1 & SP-2, and their break
down in SP-4, SP-5 respectively; the prices in SP-1, SP-2 shall prevail respectively.
9. The Engineering Price quoted in FORM SP-2 shall not exceed 7% (Seven percent) of Total Lump
Sum Price (in FORM SP-0).
10. The total of prices quoted for Engineering portion in FORM SP-2 (in FORM SP-2) and Supply
component (in FORM SP-1) taken together shall not exceed 70% (Seventy percent) of Total
Lump Sum Price (in FORM SP-0).
11. In case the prices are beyond the above limits mentioned under 9 and 10, then such additional
amount shall be payable to the Contractor in the final bill.
12. FORM SP-8 is enclosed to indicate Guaranteed Power, Steam Consumption Values. Refer
Loading Criteria attached as Annexure A-X to SCC of the Bidding Document.
13. Deleted.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
SCHEDULE OF PRICES
SUPPLY PRICE shall include price of all Materials required for completion of the Works in all
respects including construction material. The guidelines for covering the materials and associated
activities under Supply Price are specified here below:
14.1 SUPPLY PRICE (SP-1) shall include supply of all materials as mentioned under SP- 4.
14.2 SUPPLY PRICE (SP-1) shall include supply of any other Materials, not mentioned under SP-4,
but required as per provisions of the Bidding or Contract Documents, and as per the guidelines
mentioned under this Para 14.0.
14.3 SUPPLY PRICE (SP-1) shall include the price of mandatory spare parts but exclude the price of
2 years recommended Operation & Maintenance spare parts.
14.4 SUPPLY PRICE (SP-1) shall include the price of spare parts for pre-commissioning,
commissioning, defect liability period and the price for such spares shall be included in the
individual equipment.
14.5 SUPPLY PRICE (SP-1) shall include price for special tools and tackles, if any.
14.6 SUPPLY PRICE (SP-1) shall include first fill of lubricants, chemicals, catalyst etc.
14.7 SUPPLY PRICE (SP-1) shall include Procurement services of the Materials and shall include other
services including but not limited to: clearance of the goods through custom and port authorities
including filling and/or filling of all custom manifests, bill of entry, and custom declarations and
other documents as may be required for the clearance of the goods from custom or port authorities,
for which purpose the Owner shall from time to time grant to Contractor or the Contractor’s
designates, such authority as may be reasonably required by the Contractor ; stevedoring,
clearing, forwarding, and handling services as required for clearing, forwarding, and handling
imported and indigenous materials and consignments including payment at Contractor’s cost of
any demurrage, wharf age, port charges, siding charges, retention charges, detention charges or
other charges whatsoever and howsoever designated or levied by any railway, airport, ship and/
or other authorities for or in connection with the loading, unloading or deletion of any materials or
vessels or other means of transport beyond the free period or unloading, clearance, retention or
detention of loading, as the case may be, provided by the relevant authorities in this connection.
14.8 SUPPLY PRICE (SP-1) shall include supply of all construction materials as required for completion
of the Work in all respects. Construction Materials, in general, shall include cement, reinforcement
bar, sand, aggregates, stones, bricks, earth and clay, nuts and bolts, screws and nails and other
fasteners of all kinds, all type of structural steel materials, woods and boards of all kinds, sanitary
pipes and fittings, sewage pipes and fittings, drainage pipes and associated fixtures and fittings,
cisterns, toilets, toilet seats and other sanitary fittings of any kind whatsoever, water proofing
compounds, chemicals, paints, varnishes, white- washes, distempers, plaster of paris and other
finishing materials whatsoever, barricading materials of all kinds and welding and other electrodes,
lead and other alloys and compounds and consumables whatsoever involved for and / or
incorporated in the permanent Works.
14.9 SUPPLY PRICE (SP-1) shall include the cost of all inspections including Third Party Inspection,
as applicable as per provisions of the Bidding Document.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
SCHEDULE OF PRICES
14.10 SUPPLY PRICE (SP-1) shall include cost of transportation; taking delivery of the Materials from
the port of delivery in India in respect of imported materials and from the factory or ware house or
other places of delivery in respect of indigenous materials and to transport these to the Contractor’s
stockpiles, godowns or other places of storage approved by the Owner, and to transport the same
from said godowns or places of storage to the work site for incorporation in the permanent work.
14.11 SUPPLY PRICE (SP-1) shall also include any incidental or auxiliary supplies which are not
specified in the Bidding Document specifically but which are required for completion of Works in
all respects which could be reasonably implied from the contents of the Bidding Document.
14.12 SUPPLY PRICE (SP-1) shall include all applicable taxes & duties except the taxes & duties quoted
in FORM SP-3. Supply prices in FORM SP-1 & SP-4 and taxes & duties in FORM SP-3 shall be
quoted in line with the Provisions for taxes & duties in clause no. 3 of Special Conditions of
Contract - Part-B.
14.13 DELETED
14.14 All materials under SP-1 shall be the property of OWNER and Contractor shall act as a trustee of
OWNER for custody of these materials and any surplus material left at Site shall be OWNER’s
property.
15.1 Service Price (SP-2) SHALL COMPRISE OF ENGINEERING, CONSTRUCTION AND OTHER
ALLIED SERVICES, REQUIRED AS PER BIDDING DOCUMENT
15.2 SP-2 Price shall include all type of taxes and duties (except GST). Service Price (SP-2) shall not
include GST; the same shall be reimbursed to the Contractor subject to the provisions mentioned
in the Special Conditions of Contract.
15.3 SP-2 Price shall include prices of all type of construction services required for completing the
Works in all respects including construction, testing, pre- commissioning, commissioning and
handing over to Owner. This shall include all type of Services required for completing the works in
all respects as per the scope of work specified in the Bidding Document. The major services are
specified here below, without being limited to:
15.3.1 SP-2 Price shall include - Supply, procurement, mobilization and deployment of all labour,
construction plant/ equipment/ machinery necessary for lifting, loading, handling, removing,
transporting, unloading or securing the materials.
15.3.2 SP-2 Price shall include - The cost of mobilization including but not limited to mobilization of
vehicles, movements, machinery, equipment, gear, tools, tackles, and other items and goods and
personnel necessary for or to perform the works contemplated under the Contract.
15.3.3 SP-2 Price shall include - The cost of all construction plants and equipment, vehicles, movements,
supply of water and power, construction of temporary roads and access, temporary works, pumps,
wiring, pipes, scaffolding, piling, shuttering and other materials, supervision, labour, fuel, stores,
geo technical investigation etc.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
SCHEDULE OF PRICES
15.3.4 SP-2 Price shall include- All supervision charges, establishment charges, overheads,
contingencies, site organization, charges etc.
15.3.5 SP-2 Price shall include- The cost of all indemnities under the Contract, and insurance premia on
insurance required in terms of the Contract documents. “Insurance” here shall include Insurance
other than those specified under Owner’s scope.
15.3.6 SP-2 Price shall include- The cost of all rents, royalties, licenses, permits, permission and any
other fee, duty, penalty, levy payable on the excavation, transportation of any material or
acquisition or use of any right of way or other right, licenses, permit, privilege, permission or uses
required for the performance of work.
15.3.7 SP-2 Price shall include - Assembly of sub-assemblies, installation, alignment, welding, and
completion up to Erection Completion and of all the disciplines – civil and structural, Static & Fired
Equipment, pressure vessels, rotary equipment, package equipment, piping, electrical,
instrumentation, insulation, fire proofing, refractory, painting, etc. as required according to the
specifications and drawings.
15.3.8 SP-2 Price shall include - Testing, Hydraulic testing/pneumatic testing at Site.
15.3.11 SP-2 Price shall include - Performance Guarantee Test runs of the plant
15.3.12 SP-2 Price shall include - The incidental cost arising out of Punch list/ check list issued by
commissioning team of licensor or owner or operation group of Owners during pre-commissioning
/ commissioning for smooth and trouble free operation of the system/ units.
15.3.13 SP-2 prices shall include training charges.
15.4 CONSTRUCTION PRICE shall also include any incidental or auxiliary works which are not
specified above or in the specifications or in the Conditions of Contract or in the Bidding Document
specifically but which are required for completion of Works in all respects and which could be
reasonably inferred from the contents of the Contract Document.
16. SP-0 are considered as the Prices which Owner agrees to pay and the Contractor agrees to accept
as full compensation for the Contractor’s full performance of the Work (i.e. Engineering, Supply
and Construction & other services) in accordance with the provisions of the Contract Documents.
These Prices shall be shall remain firm, fixed and valid till the completion of the Works and will not
be subject to variation on any account except as otherwise specifically provided in the Bidding
Documents and Change Orders, if any subject to the provisions of the Contract.
17. Obligation of the Contractor is not limited to the quantities that the Contractor may either indicate
in the Schedule of Breakup of Prices along with his bid or in the billing schedules after award of
work. Contractor shall carry entire scope of Work as detailed in various sections/volumes of the
Bidding Document within the quoted Price of SP-0.
18. It will be the duty of the Contractor to duly observe and perform all laws, rules, regulations, orders
and formalities applicable to GST (CGST, SGST, IGST) and Custom Duty on the manufacture,
sale, import and/ or supply of any material to OWNER and/ or applicable to GST on the services
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
SCHEDULE OF PRICES
performed by the Contractor pursuant hereto. The Contractor shall keep OWNER indemnified for
and against any and all claims, demands, prosecutions, penalties, damages, demurrages, and/ or
other levies whatsoever made or levied by the court or Custom Authorities with respect to any
alleged breach, evasion, or infraction of such duties, taxes, charges, or levies or any breach or
infraction of such laws, rules, regulations, orders, or formalities concerning the same and from the
consequences thereof.
19. Bidder shall furnish the details of taxes & duties in FORM SP-3 of Schedule of Prices, which would
be applicable with respect to Supply Price and Service Price.
20. The Bidder shall indicate in FORM SP-6 the list of recommended Operation & Maintenance spares
for two (2) years normal operation of the Unit/Plant as recommended by the manufacturers of
various Systems (other than startup/commissioning, Mandatory spares required during the defect
liability period). This Price shall have a validity of 12 months after mechanical completion of
plant/unit. This Price shall not be considered for Price Evaluation.
21. Bidder shall quote the year wise charges for CPWAMC for 05 years as per technical portion of
bidding document in the FORM SP-7 of Price schedule.
The CPWAMC charges quoted by the bidder shall be exclusive of all output taxes and duties. The
output taxes & duties shall be paid as per prevailing rate against tax invoice and related documents
of the Contractor. (Only basic cost to be quoted by the bidder & applicable output taxes/GST shall
be paid extra at that time prevailing rate). The price shall be quoted by the Contractor shall take
into account the input tax credit available to them.
The quotation by the bidder for Annual maintenance charges as specified above for the
period of 5 (five) years is mandatory and shall be considered in the evaluation of the bid.
For the purpose of comparison of bids, no loading of output tax on CPWAMC charges shall be
done. i.e. prices quoted by bidder shall only be considered for comparison of bids.
The Prices for Comprehensive Post Warranty Annual Maintenance Contract (CPWAMC) quoted
in FORM SP-7 shall not be included in the total Lump Sum Price.
The Prices for CPWAMC shall remain valid up to the defect liability period. In case of award, the
price for CPWAMC shall remain FIRM till the completion of scope of CPWAMC. The OWNER will
place separate Purchase Order for CPWAMC as defined elsewhere in the tender and this price
shall not be included in the Lump sum price.
22. Foreign Bidders may quote prices for materials and services to be imported into India either in
Indian Rupees or in Foreign Currency or in a combination of Indian Rupees and a Foreign
Currency.
23. Indian Bidders shall quote the price for materials and services to be procured from India and for
expenses to be incurred in India only in Indian Rupees.
Indian bidders may quote the prices for materials and services to be imported into India in Foreign
Currency. Such bidders quoting in foreign currency shall separately indicate in a list of the
materials and services to be imported into India and the Foreign Currency price payable for such
materials and services.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
SCHEDULE OF PRICES
For the purpose of this clause and any other relevant provisions in these documents, Foreign
Currency (FC) shall mean and be limited to US DOLLARS, EURO, JAPANESE YEN.
However, maximum no. of currencies of quote shall be limited to Indian Rupees and any one of
the allowed Foreign Currencies mentioned above.
If the Foreign bidder has not mentioned any currency in their Price bid/ Unpriced bid, US Dollar
shall be considered as their currency of quote.
24. Bidder confirms that he has noted the contents of the Preamble to Schedule of Price, Price
Schedule, Bidding document and quoted his prices accordingly without any deviation and without
changing format of Price Schedule including this BOQ.
25. Bidder shall submit unpriced Price schedule (all Forms) indicating 'QUOTED' in all columns in their
unpriced bid.
Bidder shall submit their Priced Bid duly filled in with prices, stamped & signed by Bidder on each
page and scanned & uploaded in the respective “PRICE BID” folders only on the e-procurement
Portal as mentioned in the ITB.
26. The Liability of payment of excess of Custom duty, on account of change in DDP value referred to
in FORM SP-4 shall be to Contractor’s account.
27. Lump sum prices quoted by the Contractor shall include cost of any other supplies/work(s)/
services not specifically mentioned in the Bidding document but necessary for the efficient, trouble
free operation of the plant and to make this package job complete.
NOTE: Bidder must indicate “QUOTED”, “NOT QUOTED” or “NOT APPLICABLE” as applicable
against the respective Item(s) in all the SP FORMS of Schedule of Prices while submitting unpriced
part of Schedule of Prices in Techno-Commercial Bid along with this PREAMBLE signed &
stamped.
PETROCHEMICAL AND LUBE INTEGRATION
PROJECT “LuPech” (J-18)
IOCL GUJARAT REFINERY
SCHEDULE OF PRICES
FORM SP-4
Notes:
1. Bidder to furnish break up of FORM SP-1 price in this FORM SP-4 in terms of % of total supply portion
quoted in FORM SP-1.
2. Bidder to ensure that total of percentage indicated against all the items below respectively for foreign
currency and Indian Currency shall be total 100% each for foreign currency and Indian Currency quoted
in FORM SP-1.
3. This duly filled in FORM SP-4 with % is required to be submitted in unpriced bid only
SCHEDULE OF PRICES
SCHEDULE OF PRICES
FORM SP-5
Bidder Name:
Notes:
1. Bidder to furnish break up of FORM SP-2 price in this FORM SP-5 in terms of % of total service portion
quoted in FORM SP-2.
2. Bidder to ensure that total of percentage indicated against all the items below respectively for foreign
currency and Indian Currency shall be total 100% each for Foreign currency and Indian Currency quoted
in FORM SP-2.
3. This duly filled in FORM SP-5 with % is required to be submitted in unpriced bid only.
SCHEDULE OF PRICES
Notes:
1. The price quoted shall be Lump sum Price on Turnkey basis. Total payments to be made to the Contractor shall be limited to Lump sum price indicated at FORM SP-0 in the Price Bid and Taxes and
duties calculated as per the rates quoted in Form SP-3, irrespective of the progressive payments made during execution based on the split up of price.
2. Refer the PREAMBLE TO SCHEDULE OF PRICES enclsoed elsewhere in the Bidding Document.
Name of the
Bidder/
Bidding Firm /
Company :
Quoted
Total Lumpsum Price in Figures To be entered by
Sl. Currency in
Item Description Units the Bidder (except Custom duty, SWS and
No. INR / Other
IGST/CGST&SGST and its related cess, if any)
Currency
1 2 5 12 13
Project Management, Consistency Checks, Power System Studies as mentioned in Bidding Documents, Site development and
enabling jobs, Topography Survey, Soil Investigation and underground scanning mentioned in the bid and co-ordination for the
same with Owner/PMC, Total Procurement (including first fill of consumables, special tools and tackles, Pre-Commissioning
Spares, Commissioning Spares, Start-up spares & Mandatory spares), Fabrication, Manufacturing, Quality Assurance,
Inspection & Expediting, Third Party Inspection, Supplies, Transportation, Insurance, Handling & Storage of all Equipment,
1 Materials, items and other Construction Materials at yard/site, Fabrication, Assembly, Construction, Erection, Installation of all
equipment pertaining to LuPech Power Distribution facility including civil, Structural, HVAC, Piping, Electrical and
Instrumentation including tie-ins, Testing, Insulation and Painting, Obtaining all Statutory Approvals Pre-commissioning &
Mechanical Completion, Preparation of operating manuals, Training of Owner’s O&M personnel, consumables for 6 (six)
months operation, Contract closure activities ,Final invoice/billing and handing over of the facilities with Final and “As Built”
drawing/documentation, supply of spares with necessary support and services during defect liability period.
Notes:
1. All supplies for the completion of the work shall be included in the FORM SP-1 only.
2. Bidder to furnish further break-up of FORM SP-1 in FORM SP-4 in terms of % of total supply price quoted in FORM SP-1, in unpriced part of their Bid,
which is enclosed in the Bidding document as PDF.
3. No supplies shall be included under FORM SP-2.
Name of the
Bidder/
Bidding Firm /
Company :
1 2 5 12 13
Name of Work: LUPECH POWER DISTRIBUTION FACILITY FOR PETROCHEMICAL AND LUBE INTEGRATION PROJECT “LUPECH” (J-18) PROJECT AT IOCL GUJARAT
REFINERY, INDIA
BREAKUP OF TOTAL LUMPSUM PRICE - Detailed Design & Engineering, Construction/Installation, Start-up, Pre-commissioning, Commissioning, Performance Guarantee Test
Run (PGTR) , Training
Notes:
1. All services for the completion of the work shall be included in the Form SP-2 only.
2. Bidder to furnish further breakup of Form SP-2 in Form SP-5 in terms of % of total service price quoted in Form SP-2, in unpriced part of their Bid, which is enclosed in the
Bidding document in PDF.
3. No services shall be included under Form SP-1.
Name of the
Bidder/
Bidding Firm /
Company :
1 2 5 12 13
ENGINEERING PRICE (DETAILED DESIGN AND ENGINEERING AS PER
1 REQUIREMENTS DETAILED OUT IN VARIOUS SECTIONS OF BIDDING
DOCUMENT
Name of Work: POWER DISTRIBUTION FACILITY FOR PETROCHEMICAL AND LUBE INTEGRATION PROJECT “LUPECH” (J-18) PROJECT AT IOCL
GUJARAT REFINERY, INDIA
TAXES AND DUTIES ON REIMBURSEMENT BASIS (Not included in quoted Price in SP-0)
Notes:
1. Bidder are advised to consider prevailing rates of taxes & duties for quoting the below percentage. The reimbursement shall be paid against submission
of original tax invoices with related documents. All related and relevant documents, but not limited to Original tax invoice, bill of entry, importer invoice,
endorsed copy of consignment note or bill of lading etc, shall be submitted by the contractor as per prevailing rules and regulations and as per Clause 3 of
SCC-Part B.
2. No other taxes and duties except mentioned in this form shall be eligible for reimbursement
3. Bidder to note that breakup of lump sum price in SP forms are for interim progressive payment purpose only. The total price Payable under the contract
shall be restricted to the quoted lump sum price and rate of taxes & duties quoted below. If any mismatch in actual progressive invoice value and rate of
taxes & duties quoted below, bidder will adjust the same in lump sum Price quoted in SP forms, so that there should not be any additional liability to the
OWNER.
4. Bidder to note evaluation shall be done as per BID DATA SHEET Sl.no.14. II.e after loading the IGST/GST (at prevailing rate on the last price bid
submission date) to be paid by OWNER on FOREIGN CURRENCY part of Services (calculated based on the percentage quoted by bidder in SP-5) to be
offered by Foreign Bidder (in case of direct bidding)/ Foreign Member of the consortium/JV.
Name of the
Bidder/ Bidding
Firm / Company :
1 2 5 13
Basic Customs Duty & other import duties on Supply of Imported Goods other
2.1 %age
than those mentioned below (Foreign Component of SP-1)
Name of Work: LUPECH POWER DISTRIBUTION FACILITY FOR PETROCHEMICAL AND LUBE INTEGRATION PROJECT “LUPECH” (J-18) PROJECT AT IOCL GUJARAT REFINERY, INDIA
PRICE SCHEDULE OF RECOMMENDED SPARES FOR TWO YEARS OPERATION AND MAINTENANCE
Notes:
1.Contractor shall provide itemized priced list of two years operation and maintenance (O&M) spares along with the bid. Prices of O&M spares shall be kept valid for a period of 12 months after contractual
mechanical completion. Owner reserves the right to place the order for such O & M spares.
2. 2 years operation & maintenance spares shall be furnished as per this format and shall not be included in the quoted supply prices. Quoted 2 years operation & maintenance spares shall not be
considered for evaluation.
3. Bidder shall indicate Zero (0) in the row where bidder does not recommend spares and the same shall be considered as "Not Quoted"
4. Currency of bid shall be as per Preamble to Schedule of Rates
Name of the
Bidder/
Bidding Firm /
Company :
1 2 5 12 13 19 24 26
1 AMOUNT OF FOREIGN COMPONENT
Name of Work: LUPECH POWER DISTRIBUTION FACILITY FOR PETROCHEMICAL AND LUBE INTEGRATION PROJECT “LUPECH” (J-18) PROJECT AT IOCL GUJARAT REFINERY,
INDIA
Name of the
Bidder/ Bidding
Firm / Company :
1 2 5 12 13
6 of 7
Validate Print Help
Name of Work: LUPECH POWER DISTRIBUTION FACILITY FOR PETROCHEMICAL AND LUBE INTEGRATION PROJECT “LUPECH” (J-18) PROJECT AT IOCL
GUJARAT REFINERY, INDIA
Name of the
Bidder/ Bidding
Firm / Company :
1 2 5 13
GUARANTEED UTILITIES FOR PACKAGE-04 AS PER BIDDING
1
DOCUMENT
1.02 Full load losses (Copper + stray loss) at 75˚C and at ONAN Rating (PL_fl) KW