Baseline Narrative Report Template
Baseline Narrative Report Template
Project:
Project Manager:
Consultant:
Main Contractor:
METHOD OF CONSTRUCTION & SCHEDULE PREMISIS
1 SEPTEMPER 2021
https://www.softedemy.com/
Contents
1. Introduction & Project Overview .................................................................................................. 3
1.1. Introduction ................................................................................................................................. 3
1.2. Project Overview: ......................................................................................................................... 3
2. Project Location & Package Layout ............................................................................................... 4
2.1. Project Location ........................................................................................................................... 4
2.2. Project Layout .............................................................................................................................. 5
3. Scope of Work .............................................................................................................................. 6
3.1. Work Description: ........................................................................................................................ 6
3.2. Total Project Buildings .................................................................................................................. 6
4. Project Description ....................................................................................................................... 6
4.1. Project Brief: ................................................................................................................................ 6
4.1.1. 56 CHALETS: .......................................................................................................................... 6
5. Mobilization Plan ......................................................................................................................... 7
6. Coding & Key Plans ....................................................................................................................... 8
6.1. Activity Code ................................................................................................................................ 8
7. Construction Planning Methodology ............................................................................................ 9
7.1. Schedule Assumptions .................................................................................................................. 9
7.2. Structure Works ........................................................................................................................... 9
7.3. Ground to roof floor Internal Finishes Works ................................................................................ 9
7.4. External Finishes works .............................................................................................................. 10
8. Man Power Histogram & Schedule ............................................................................................. 11
8.1. Manpower Histogram ................................................................................................................ 11
9. KPI’s ........................................................................................................................................... 12
10. Cash Flow ................................................................................................................................... 15
11. Schedule Attachments ................................................................................................................ 15
11.1. Key Dates ............................................................................................................................ 15
11.2. Project Summary ................................................................................................................ 15
11.3. Construction Summary ....................................................................................................... 15
11.4. Longest Path ....................................................................................................................... 15
11.5. All Project Activities ............................................................................................................ 15
2 | P a g e
https://www.softedemy.com/
1. Introduction & Project Overview
1.1. Introduction
The submitted time schedule methodology based on the following:
Working days / week: 6 days
Holidays: Standard Egyptian Official Holidays (As Submitted – Narrative Report)
Planned number of shifts / days: 1
Working Hours: from 8:00 A.M. till 5:00 P.M.
Number of crews and its relative rotation (As Submitted – Narrative Report)
All material procurement dates are available on P6 for interior finishing.
Client to make decision for free issue and optional items as per schedule.
1.2. Project Overview:
Project Owner
Project Location
Contract Type
Project Budget
Project Start
Project Finish
Project Duration
3 | P a g e
https://www.softedemy.com/
2. Project Location & Package Layout
2.1. Project Location
4 | P a g e
https://www.softedemy.com/
2.2. Project Layout
5 | P a g e
https://www.softedemy.com/
3. Scope of Work
3.1. Work Description:
1. Concrete Works for ground, two floors & roof
2. Insulation Works
3. Block Works
4. Plaster Works for Internal and External Walls and Ceiling
5. Internal & External Finishing (Painting, Marble, Aluminum, handrails, etc.)
6. MEP Works for fully finish
3.2. Total Project Buildings
......
4. Project Description
4.1. Project Brief:
Whereas ....... for Construction & Projects Company has entered a Main Contract with
................................. at ......................... Project and whereas the supervision consultant shall be a
joint venture of ... for Design and Engineering and ... Project Management, ... teamed up with ..... to
go through the Construction & the External Finishes ............. and structural fill & retaining wall
within ........... duration that starts on ................ to be delivered .................... for their Clients.
Buildings Brief:
4.1.1. .....:
ground & 2 Floors
Built up Area : ..... M²
Approximate R.C. Quantity : ....... M³
6 | P a g e
https://www.softedemy.com/
5. Mobilization Plan
https://www.softedemy.com/
6. Coding & Key Plans
6.1. Activity Code
BOQ Summary
Code Value Description
Gen General
ENG Engineering Works
PRC Procurement works
STR Structure Works
ARC Architecture Work
PLU Plumping Work
ELE Electrical Work
BOQ Divisions
Code Value Description
Gen General
ENG Engineering Works
PRC Procurement works
EAR Earth Work
CON Concrete works
MAS Masonry Works
INS Moisture & Thermal Protection
MET Metal works
WAP Wood And Plastic
D&W Doors & Windows
FIN Finishes
PLU Plumbing works
ELE Electric works
https://www.softedemy.com/
7. Construction Planning Methodology
7.1. Schedule Assumptions
Divide 56 Challets to 6 groups.
The first group will start is behind the street.
Link all groups sequential with 20 days lag approxmitly.
Start from earh work Excavation, Replacement and continues to concrete skeleton then
finsh work with overlap between activities.
7.2. Structure Works
1. Shuttering for P.C. Foundation.
2. R.C. Footings & GB Shuttering/steel fix will start after replacement work.
3. Shuttering for R.C. Columns Shall Start after finishing RC footings & GB
activity.
4. Waterproofing insulation & Back filling will start after finish masonry of
2 n d floor.
5. Shuttering for R.C. Slab Shall Start after finishing RC Columns activity.
R.C. Columns
P.C. Footings R.C. Footings For Ground
Floor
7.3. Ground to roof floor Internal Finishes Works
1. Finishing Works will start with Masonry activity that shall start once the
scaffolding dismantling of each floor starts.
2. Plastering works for ducts, plaster preparation for internal wills will start after
Masonry works finish
3. Finishing & MEP Activities will start after plaster prep. /Fill
https://www.softedemy.com/
7.4. External Finishes works
1. External Elevation finishes works will start after finishing the block work of three
floor for elevation.
2. External Plaster Fill will start after Block Works
3. Main Activities sequence is illustrated Below
10 | P a g e
https://www.softedemy.com/
8. Man Power Histogram & Schedule
8.1. Manpower Histogram
MANPOWER HISTOGRAM
30000
24780
25000
20829
20000 18143
16970
15000 13999
12833
10000
7648
6389
11 | P a g e
https://www.softedemy.com/
9. KPI’s
Concrete KPI
3000 2854.4
2702 2715.35
2500
1899
2000
1648.35
1500
1183
955.5
1000
659.05
437 485 514.8
500 388
67 37.3 37.3 70.8 67.5
0
Sep Oct Nov Dec Jan Feb Mar Apr May
Sep Oct Nov Dec Jan Feb Mar Apr May
PC Concrete Poured Per Month 388 437 485 514.8 955.5 37.3 37.3 70.8
RC Concrete Poured Per Month 67 1183 1899 2702 2854.4 2715.35 1648.35 659.05 67.5
Masonary KPI
6000 5544
5000
4024
4000 3736
3344
2904
3000
2000
1376
1000 576
0
Nov‐21 Dec‐21 Jan‐22 Feb‐22 Mar‐22 Apr‐22 May‐22
Masonary M3 / Month
12 | P a g e
https://www.softedemy.com/
Plaster / Month
45000
38305
40000 36204
35000 30982
30000 27461
25000 20834
19054
20000
15000
10000 6024
5000
0
Dec‐21 Jan‐22 Feb‐22 Mar‐22 Apr‐22 May‐22 Jun‐22
Paint / Month
80000 73276
67347 66765 65121
70000
60000
50000 43970
40000
30000 25522 22759
20000
6632
10000
0
Jan‐22 Feb‐22 Mar‐22 Apr‐22 May‐22 Jun‐22 Jul‐22 Aug‐22
13 | P a g e
https://www.softedemy.com/
Cement Render / Month
18000
15369
16000
14000 12644
12000 10900
9810
10000 8720
8000
6000
3597
4000
2000
0
Feb‐22 Mar‐22 Apr‐22 May‐22 Jun‐22 Jul‐22
Feb‐22 Mar‐22 Apr‐22 May‐22 Jun‐22 Jul‐22
Cement Render / Month 8720 9810 10900 12644 15369 3597
14 | P a g e
https://www.softedemy.com/
10. Cash Flow
MONTHLY CASH FLOW FOR 56 CHALETS
40,000,000
37,125,150
35,000,000
31,046,428 31,561,872
30,000,000
26,150,222
25,000,000 23,441,820
19,472,894
20,000,000 18,474,568
15,000,000 13,029,840
9,455,296 9,672,804
10,000,000
11. Schedule Attachments
11.1. Key Dates
11.2. Project Summary
11.3. Construction Summary
11.4. Longest Path
11.5. All Project Activities
15 | P a g e