Client:

Project: 

Project Manager:

Consultant:

Main Contractor: 

METHOD OF CONSTRUCTION & SCHEDULE PREMISIS 
1 SEPTEMPER 2021 

https://www.softedemy.com/
   

Contents 
1.  Introduction & Project Overview .................................................................................................. 3 
1.1.  Introduction ................................................................................................................................. 3 
1.2.  Project Overview: ......................................................................................................................... 3 
2.  Project Location & Package Layout ............................................................................................... 4 
2.1.  Project Location ........................................................................................................................... 4 
2.2.  Project Layout .............................................................................................................................. 5 
3.  Scope of Work .............................................................................................................................. 6 
3.1.  Work Description: ........................................................................................................................ 6 
3.2.  Total Project Buildings .................................................................................................................. 6 
4.  Project Description ....................................................................................................................... 6 
4.1.  Project Brief: ................................................................................................................................ 6 
4.1.1.  56 CHALETS: .......................................................................................................................... 6 
5.  Mobilization Plan ......................................................................................................................... 7 
6.  Coding & Key Plans ....................................................................................................................... 8 
6.1.  Activity Code ................................................................................................................................ 8 
7.  Construction Planning Methodology ............................................................................................ 9 
7.1.  Schedule Assumptions .................................................................................................................. 9 
7.2.  Structure Works ........................................................................................................................... 9 
7.3.  Ground to roof floor Internal Finishes Works ................................................................................ 9 
7.4.  External Finishes works .............................................................................................................. 10 
8.  Man Power Histogram & Schedule ............................................................................................. 11 
8.1.  Manpower Histogram ................................................................................................................ 11 
9.  KPI’s ........................................................................................................................................... 12 
10.  Cash Flow ................................................................................................................................... 15 
11.  Schedule Attachments ................................................................................................................ 15 
11.1.  Key Dates ............................................................................................................................ 15 
11.2.  Project Summary ................................................................................................................ 15 
11.3.  Construction Summary ....................................................................................................... 15 
11.4.  Longest Path ....................................................................................................................... 15 
11.5.  All Project Activities ............................................................................................................ 15 
 

2 | P a g e  
 

https://www.softedemy.com/
   

1. Introduction & Project Overview 
1.1.  Introduction 
The submitted time schedule methodology  based on the following: 
 
 Working days / week: 6 days 

 Holidays: Standard Egyptian Official Holidays (As Submitted – Narrative Report) 
 
 Planned number of shifts / days: 1 

 Working Hours: from 8:00 A.M. till 5:00 P.M. 

 Number of crews and its relative rotation (As Submitted – Narrative Report) 

 All material procurement dates are available on P6 for interior finishing.  

 Client to make decision for free issue and optional items as per schedule. 

1.2. Project Overview: 
 

Project Owner 

Project Location 

Contract Type 

Project Budget

Project Start 

Project Finish

Project Duration 

3 | P a g e  
 

https://www.softedemy.com/
   
 

2. Project Location & Package Layout 
2.1. Project Location  

 
   

4 | P a g e  
 

https://www.softedemy.com/
   
 

2.2. Project Layout 

   

5 | P a g e  
 

https://www.softedemy.com/
   
 

3. Scope of Work 
3.1. Work Description: 
1. Concrete Works for ground, two floors & roof 
2. Insulation Works 
3. Block Works 
4. Plaster Works for Internal and External Walls and Ceiling 
5. Internal & External Finishing (Painting, Marble, Aluminum, handrails, etc.) 
6. MEP Works for fully finish 

3.2. Total Project Buildings  
 ...... 

4. Project Description 
4.1. Project Brief: 
 
Whereas ....... for Construction & Projects Company has entered a Main Contract with 
................................. at ......................... Project and whereas the supervision consultant shall be a 
joint venture of ... for Design and Engineering and ... Project Management, ... teamed up with ..... to 
go through the Construction & the External Finishes ............. and structural fill & retaining wall 
within ........... duration that starts on ................ to be delivered .................... for their Clients. 
 
 
Buildings Brief: 
4.1.1. .....:  
 
 ground & 2 Floors  
 Built up Area   : ..... M² 
 Approximate R.C. Quantity  : ....... M³ 
 
 

6 | P a g e  
 

https://www.softedemy.com/
   
 

5. Mobilization Plan 
 

 
https://www.softedemy.com/
   
 

6. Coding & Key Plans 
6.1. Activity Code  

 
BOQ Summary 
Code Value  Description 
Gen  General 
ENG  Engineering Works
PRC  Procurement works 
STR  Structure Works 
ARC  Architecture Work
PLU  Plumping Work 
ELE  Electrical Work
 

BOQ Divisions 
Code Value  Description 
Gen  General 
ENG  Engineering Works
PRC  Procurement works 
EAR  Earth Work 
CON  Concrete works
MAS  Masonry Works 
INS  Moisture & Thermal Protection
MET  Metal works 
WAP  Wood And Plastic 
D&W  Doors & Windows
FIN  Finishes 
PLU  Plumbing works
ELE  Electric works 
 

https://www.softedemy.com/
   
 

7. Construction Planning Methodology  
7.1. Schedule Assumptions 

 
 Divide 56 Challets to 6 groups. 
 The first group will start is behind the street. 
 Link all groups sequential with 20 days lag approxmitly. 
 Start from earh work Excavation, Replacement and continues to concrete skeleton then 
finsh work with overlap between activities. 

7.2. Structure Works  
 
1. Shuttering for P.C. Foundation. 
2. R.C. Footings & GB Shuttering/steel fix will start after replacement work. 
3. Shuttering for R.C. Columns Shall Start after finishing RC footings & GB 
activity. 
4. Waterproofing insulation & Back filling will start after finish masonry of 
2 n d  floor.  
5. Shuttering for R.C. Slab Shall Start after finishing RC Columns activity. 
 

R.C. Columns 
P.C. Footings R.C. Footings For Ground 
Floor 
 
 
 

7.3. Ground to roof floor Internal Finishes Works 
1. Finishing Works will start with Masonry activity that shall start once the 
scaffolding dismantling of each floor starts. 
2. Plastering works for ducts, plaster preparation for internal wills will start after 
Masonry works finish 
3. Finishing & MEP Activities will start after plaster prep. /Fill  
 

Plaster for  ceramic  Painting 


Masonary
walls for floor for walls
 

 
https://www.softedemy.com/
   
 
 

7.4. External Finishes works  
1. External Elevation finishes works will start after finishing the block work of three 
floor for elevation. 
2. External Plaster Fill will start after Block Works  
3. Main Activities sequence is illustrated Below 

External  External  Doors &  Scaffolding 


Scaffolding
Plaster Paint Windows dismantle

 
 

10 | P a g e  
 
https://www.softedemy.com/
   
 

8. Man Power Histogram & Schedule 
8.1. Manpower Histogram 

MANPOWER HISTOGRAM
30000

24780
25000

20829
20000 18143
16970

15000 13999
12833

10000
7648
6389

5000 3769 3714


2150
209
0
Sep 21 Oct 21 Nov 21 Dec 21 Jan 22 Feb 22 Mar 22 Apr 22 May 22 Jun 22 Jul 22 Aug 22
 
 

 
   

11 | P a g e  
 
https://www.softedemy.com/
   
 

9. KPI’s 
 

Concrete KPI
3000 2854.4
2702 2715.35

2500

1899
2000
1648.35
1500
1183
955.5
1000
659.05
437 485 514.8
500 388
67 37.3 37.3 70.8 67.5
0
Sep Oct Nov Dec Jan Feb Mar Apr May
Sep Oct Nov Dec Jan Feb Mar Apr May
PC Concrete Poured Per Month 388 437 485 514.8 955.5 37.3 37.3 70.8
RC Concrete Poured Per Month 67 1183 1899 2702 2854.4 2715.35 1648.35 659.05 67.5
 

Masonary KPI
6000 5544

5000

4024
4000 3736
3344
2904
3000

2000
1376

1000 576

0
Nov‐21 Dec‐21 Jan‐22 Feb‐22 Mar‐22 Apr‐22 May‐22

Nov‐21 Dec‐21 Jan‐22 Feb‐22 Mar‐22 Apr‐22 May‐22


Masonary M3 / Month 576 1376 3736 4024 5544 3344 2904

Masonary M3 / Month
 

12 | P a g e  
 
https://www.softedemy.com/
   
 

Plaster / Month
45000
38305
40000 36204
35000 30982
30000 27461
25000 20834
19054
20000
15000
10000 6024
5000
0
Dec‐21 Jan‐22 Feb‐22 Mar‐22 Apr‐22 May‐22 Jun‐22

Dec‐21 Jan‐22 Feb‐22 Mar‐22 Apr‐22 May‐22 Jun‐22


Plaster / Month 6024 20834 30982 38305 36204 27461 19054
 
 

Paint / Month
80000 73276
67347 66765 65121
70000
60000
50000 43970
40000
30000 25522 22759
20000
6632
10000
0
Jan‐22 Feb‐22 Mar‐22 Apr‐22 May‐22 Jun‐22 Jul‐22 Aug‐22

Jan‐22 Feb‐22 Mar‐22 Apr‐22 May‐22 Jun‐22 Jul‐22 Aug‐22


Paint / Month 6632 25522 73276 67347 66765 65121 43970 22759
 
 

13 | P a g e  
 
https://www.softedemy.com/
   
 

Cement Render / Month
18000
15369
16000
14000 12644
12000 10900
9810
10000 8720
8000
6000
3597
4000
2000
0
Feb‐22 Mar‐22 Apr‐22 May‐22 Jun‐22 Jul‐22
Feb‐22 Mar‐22 Apr‐22 May‐22 Jun‐22 Jul‐22
Cement Render / Month 8720 9810 10900 12644 15369 3597
 
 

14 | P a g e  
 
https://www.softedemy.com/
   
 

10. Cash Flow  
MONTHLY CASH FLOW FOR 56 CHALETS 
40,000,000
37,125,150

35,000,000
31,046,428 31,561,872
30,000,000
26,150,222
25,000,000 23,441,820

19,472,894
20,000,000 18,474,568

15,000,000 13,029,840
9,455,296 9,672,804
10,000,000

5,000,000 2,442,712 2,881,629

 
 

11. Schedule Attachments  
11.1. Key Dates 

11.2. Project Summary 

11.3. Construction Summary 

11.4. Longest Path 

11.5. All Project Activities 
 

15 | P a g e  
 