A] PREPARATORY WORK CIVIL WORK :


1 BAMBOO PRANCHI
TOTAL AREA -26,533/- SQ.FT
4 /- rs PER SQ.FT -----LOAD AND UNLOAD 1,06,532/-

2 NET JALI
TOTAL NET JALI AREA – 3000 SQ.FT
50 rs /- PER METER 15,000/-

3 BREAKING OF EXTERNAL PLASTER IN PATCHES


70 RS /- SQ.FT

4 R.C.C JOINTS WILL BE REPAIRED ,AND JOINTS THAT ARE FULLY DAMAGED WILL
BE REPAIRED BY DOING BOX PLY R.C.C.
350 RS/- SQ.FT

5 APPLYING DASH COAT PLASTER IN TWO COATS OVER EXTENSIVELY DAMAGED


WALLS WITH CEMENT SAND MORTAR 1: 4 LIQUID CHEMICALTO BE USED WILL BE
SUNNANDAR OR DR.FIXIT . 150 RS/- SQ.FT
[OR]
G.I GALONISED JALI OF 0.5 X 0.5 AND JALI WILL BE REDOXIDE

6 ALL THE DAMAGED BEAM AND COLUMNS OF HOUSES WILL BE REPAIRED .

ONLY DAMAGES WILL BE REPAIRED , THE COLOURING OF THE DAMAGE AREA WILL

BE DONE BY THE OWNER HIMSELF .


90 RS/- SQ.FT

7 FULL BUILDING CHAJJA PATCHES PLASTER


CRACKFIELDING PATCHES PLASTER WILL BE DONE BY DR. FIXIT PLASTER AND LIQUID URP
.
ALL BUILDING PATCHES REPAIRING INTERNAL AND EXTERNAL LUMPSUM :-
6000 /- PER SQ.FT 4,80,000/-
8 BUILDING CRACKFIELDING :
DR.FIXIT POWDER + LIQUID URP OR DR.FIXIT
25 KG BAG – 1350 /-RS
TOTAL BAGS NEEDED 20 BAGS
THESE 20 BAGS ARE NEEDED FOR CRACKFIELDING ,GROUND WATERPROOFING OF
2400 SQ.FT
URP LIQUID – 40 LITRE

WATERPROOFING WILL BE DONE FROM GR. LEVEL TO 4 FT OF EXTERIOR WALL OF THE


BUILDING WITH DR.FIXIT URP WITH TOTAL AREA OF 2400 SQ.FT

WITH MATERIAL ----- 70,000/-

9 FULL BUILDING WASH WITH PRESSURE MACHINE.

10 AFTER WASH IF ANY CRACKS ARE FOUND THEY WILL BE REPAIRED.

11 FULL SOCIETY TERRACE M.S : - REDOXIDE COLOUR 25,000/-

12 KITCHEN ,BATHROOM, TOILET DRAINAGE PIPELINE REPAIRING

TOTAL: 6,96,532/-
B] COLOURING :

1 ASIAN PAINT PRIMER


[OR] } --- SINGLE COAT
ASIAN PAINT DAMPROOF.

2 ASIAN PAINT REDOXIDE – JIN COLOUR }-– GRILL


AND THEN ASIAN PAINT APPOLIDE – BLACK COLOUR.

3 FULL BUILDING EXTERIOR WALL – ASIAN PAINT ULTIMA APEX COLOUR }---- 2 COAT
AFTER 1ST COAT OF COLOUR VERIFICATION WILL BE DONE BY SOCIETY COMMITY AND
LATER 2ND COAT WILL BE APPLIED.

4 COMPOUND WALL – PRIMER AND 2 COAT OF ULTIMA APEX COLOUR .

5 ASIAN PAINT WATERPROOF DAMPROOF PRIMER –4500/- rs –20 LITRE

6 ASIAN PAINT PRIMER –2500/-rs

7 ULTIMA APEX COLOUR – 7500/- rs

8 ASIAN PAINT COLOUR RATE STARTING FROM


1ST QUALITY ULTIMA APEX – 18/- rs 8,64,000/-
2ND QUALITY – 15/- rs 7,20,000/-
3RD QUALITY – 14/- rs 6,72,000/-
NOTE :
THIS WORK WILL BE COMPLETED WITHIN 2 MONTHS.
CHAJJA AND BUILDING COLOUR BY SOCIETY CHOICE
8 YEARS OF WARRANTY OF COLOUR
800 -1000 SQ.FT --- 20 LITRE LIMIT.
C] FLOORING
1 MAIN GATE TO C-03 BEDROOM END ---- 8 INCH RAVIT FILLUP. 45,000/-

2 ALL R.C.C CHAMBER – 18 X 36


- 24 X 18
-1X1 80,000/-
ALL CHAMBER KADAPPA LADI ------ 60,000/-

3 DRAINAGE LINE OPPOSITE TO SOCIETY OFFICE --- 40 FT


PRINCE PIPE ISI – 8 INCH 22,000/-

BUILDING GARDEN WALL BREAK AND THEN 1 FT DIGGING FROM GROUND LEVEL AND
4 LATER FILL IT BY KHADI RETI AND 4 INCH KOVA . 1,20,000/-

A,B,C WING GATE ----2 INCH CUTTING AND THEN MAT FINISH LADI IN WING BY YOUR
5 CHOICE. 4,000/-
CUTTING AND THEN SHOULDER

6 BAND KAAM OF A WING OPPOSITE GATE AND DUSTBIN AREA . ----- 14,000/-

7 FULL BUILDING FLOORING – RED OR YELLOW PATTI COLOUR.

8 PARKING SPACE – RED AND YELLOW PATI COLOUR BLOCK -2.5 FT SPACING.

MACHING GRIP POWDER WILL BE APPLIED IN LABEL AND THEN 4 INCH BLOCK WILL BE
9 FIXED BY CEMENT PANI.

BLOCK WILL BE BY SOCIETY CHOICE EITHER OF 60 MM OR 30 MM.


TOTAL FLOORING AREA INCLUDING METER BOX AREA – 8500 SQ.FT .
WITH MATERIAL ------ PER SQ.FT . 60 MM –70/-rs 6,95,000/-
10 BMC WATER CONNECTION - 4 LINE .

TOTAL : 9,80,000/-
D] EXTRA WORK
1 FRONTSIDE 100 X 3 FT .
GRILL – 8MM M.S AND THEN REDOXIDE AND COLOUR WILL BE APPLIED.--- 120 /SQ.FT
36,000/-
DISTANCE BETWEEN 2 POLES WILL BE 10 FT.

2 BACKSIDE COMPOUND WALL – FANCY TAR ---3.5 FT X 220 FT . 60/SQ.FT 46,200/-

3 PARKING SHED – BACKSIDE --- 50 X 8 --- TOTAL 400 SQ.FT


KHUMAN PROFILE SHEET 0.5 --- GST INC.. 130/SQ.FT
10 YEARS WARRANTY OF COLOUR. 52,000/-

4 DUSTBIN WILL BE SHIFT TO CORNOR AND NEW ENTRANCE GATE WILL BE


FORMED IN DUSTBIN AREA. 7000/-

5 GATE AREA ----15 X 6 .--- THIS GATE PILLAR WILL BE OF I BEAM. 27,000/-

6 NEW MAIN ENTRANCE GATE WILL BE FORMED – 6 X 14 27,000/-

7 SAFETY TANK :
RCC SLAB 8 AND 10 MM SALIA --- DOUBLE JALI WITH THICKNESS OF 6 INCH SLAB.
OUTLIGHT CHAMBER – RCC

WITH MATERIAL 40,000/-

8 BREAK THE SLAB OF SAFETY TANK AND DECREASE THE HEIGHT OF SAFETY TANK
TO FLOORING LEVEL.
I BEAM CHANNEL
KOTA LADI
4 INCH KOVA
RCC --- 8MM AND 10MM SALIA
6 INCH RCC SLAB OF DOUBLE JALI
CHEMICAL WILL BE SURRANDA OR DR.FIXIT.

WITH MATERIAL 85,000/-

9 SAFETY TANK CLEANING


FULL TANK WILL BE CLEANED ONLY THE LAST 6 INCH WILL BE UNCLEAN. 25,000/-

TOTAL : 3,45,200/-

GENERAL NOTE :
15% MONEY TO BE PAID AFTER COMPLETION OF WORK
5 % MONEY TO BE PAID AFTER 1 YEAR OF WORK

TOTAL COST OF COMPLETE WORK : 28,85,732/-