Professional Documents
Culture Documents
Chapter4 PlanningandScheduling
Chapter4 PlanningandScheduling
4th
Year
CHAPTER 4: PLANNING AND
SCHEDULING
A. GANTT CHART
C. PDM
(Precedence
Diagram Method)
Bansiloy, Leanne Amor M. Pateña, Brian M. Rengquijo, Kimberly Jade A.
OBJECTIVES
• Learn the difference
between planning and
scheduling
• Learn the different methods
in planning and scheduling
and how to use it
accordingly
TOPIC OUTLINE
#1| Planning and Scheduling
#4| PDM
BANSILOY, LA
INTRODUCTION
Every project is composed of works,
activities, tasks or functions.
INTRODUCTION
For management to function effectively, the
project planning system used must
consider all available alternatives.
The options could be a possibility of utilizing
its full resources such as money, manpower,
facilities and equipment.
Construction management considers time
as the controlling factor of all available
resources.
time versus number of manpower
time versus number of equipment
time versus peso
BANSILOY, LA
PLANNING AND
SCHEDULING
Project planning is the process of
identifying all the activities necessary to
successfully complete the project.
PLANNING AND
SCHEDULING
Project planning and scheduling are often
used synonymously because they are
performed interactively.
PLANNING
PLANNING OBJECTIVES
GANTT
CHART
Bansiloy, LA
GANTT CHART
• The Gantt chart is a popular tool for
planning and scheduling simple projects.
GANTT CHART
GANTT CHART
• Its simplicity
• Useful for simple projects
• On a more complex projects, Gantt chart
can be useful for initial project planning
13
Pateña, B
14
Pateña, B
15
Pateña, B
16
Pateña, B
EXAMPLE
18
Pateña, B
The Critical Path Method (CPM) offers the solution through systematic
approach.
• CPM pinpoints the particular work operations whose completion times are
responsible for controlling the complete date.
• It gives a time leeway or float available for each of the non-critical work
operations. The information on float time will give the project manager
that opportunity to maneuver in their planning and control of the
operations.
21
Pateña, B
22
Rengquijo, KJ
PRECEDENCE
DIAGRAM METHOD
Rengquijo, KJ
PRECEDENCE DIAGRAM
In project management,METHOD
the precedence diagram method (PDM) is
used to create diagrams of the progressive, interrelated steps in
project implementation. Explore the types of dependencies in
PDMs, the elements involved, and how to build and use PDMs for
different projects.
the precedence diagram method (PDM) is a technique used for
constructing a schedule in which activities are represented by
nodes and linked by one or more logical relationships to show the
sequence in which the activities are to be performed. This is also
known as activity on the node diagrams.
Rengquijo, KJ
CONTROLLING FACTOR
Time Time
Time
VS VS
John Doe VS
Number of Number of
Cost
Manpower Equipment
Rengquijo, KJ
4 Types of Dependencies
• Finish-to-Start (FS) dependency
If two activities are linked by a finish-to-start dependency, this means
that the predecessor activity must be completed before the successor
activity can start.
Rengquijo, KJ
4 Types of Dependencies
• Finish-to-Finish (FF) dependency
Under this type of logical relationship, a successor activity requires the
predecessor activity to be finished before it can be completed. This type
of dependency can also coincide with start-to-start relationships of the
same activities.
Rengquijo, KJ
4 Types of Dependencies
• Start-to-Start (SS) dependency
If two activities are connected through a start-to-start dependency,
this means that the predecessor activity must have started before the
successor activity can start
Rengquijo, KJ
4 Types of Dependencies
• Start-to-Finish (SF)
This logical relationship requires that a predecessor activity must have
started before the successor activity can be finished. In practice, this type
of dependency does not occur very often
Rengquijo, KJ
CRITICAL PATH
• Is the longest route in the network of activities representing a
project.
• The sum of the activities duration along this route is the
duration of the project
• Activities on the Critical Path are called “Critical Activities”
• Activities not on the Critical Path are called “Non Critical
Activities
• Critical activities have no float or slack
Rengquijo, KJ
LF – EF = Total Float
LS + D – (ES + D)
LS - ES = Total Float
Rengquijo, KJ
ES – EF = FF
ES – (ES + D) = FF
Rengquijo, KJ
ES – ( LF -D ) = IF
Rengquijo, KJ
PDM
Example
Rengquijo, KJ
A 2 days Start
B 6 days A
ACTIVITY C 6 days B
D 1 day B
E 3 days A
F 3 days D, E
G 2 days C(+2), F
Rengquijo, KJ
Example:
A 2 days Start
B 6 days A
C 6 days B
D 1 day B
E 3 days A
F 3 days D, E
G 2 days C(+2), F
Rengquijo, KJ
Example:
A B
A 2 days Start
B 6 days A
C 6 days B
D 1 day B
E 3 days A
F 3 days D, E
G 2 days C(+2), F
Rengquijo, KJ
Example:
A B C
A 2 days Start
B 6 days A D
C 6 days B
D 1 day B
E 3 days A
F 3 days D, E
G 2 days C(+2), F
Rengquijo, KJ
Example:
A B C
A 2 days Start
B 6 days A D
C 6 days B
D 1 day B
E 3 days A
F 3 days D, E
E
G 2 days C(+2), F
Rengquijo, KJ
Example:
A B C
A 2 days Start
B 6 days A D
C 6 days B
D 1 day B
F
E 3 days A
F 3 days D, E
E
G 2 days C(+2), F
Rengquijo, KJ
Example:
A B C (+2)
B 6 days A D
C 6 days B
D 1 day B
F
E 3 days A
F 3 days D, E
E
G 2 days C(+2), F
Rengquijo, KJ
Example: E D E
S F
2 6 6
ACTIVITY
A B C (+2) L T2 L
ACTIVITY DURATION PREDECESSOR
1
S FG F
A 2 days Start
B 6 days A D 3
C 6 days B
F
D 1 day B 3
E 3 days A
F 3 days D, E
E
G 2 days C(+2), F
Rengquijo, KJ
Example: E D E
+ + S F
0 2 2 2 6 8 6
ACTIVITY
A B
C (+2) L T2 L
ACTIVITY DURATION PREDECESSOR
1
S FG F
A 2 days Start
B 6 days A D 3
C 6 days B
+
F
D 1 day B 2 3 5
E 3 days A
E
F 3 days D, E
G 2 days C(+2), F
Rengquijo, KJ
Example: E D E
+ + + S F
0 2 2 2 6 8 8 6 14
ACTIVITY
A B C 14+2 =16
(+2) L T2 L
+
ACTIVITY DURATION PREDECESSOR
8 1 9
S FG F
9,5
A 2 days Start bigger +
B 6 days A D 9 3 12
C 6 days B
+
F
D 1 day B 2 3 5
E 3 days A
E
F 3 days D, E
G 2 days C(+2), F
Rengquijo, KJ
Example: E D E
+ + + S F
0 2 2 2 6 8 8 6 14 16 , 12
ACTIVITY
bigger
A B C 14+2 =16 +
(+2) L 16T 2 18
L
+
ACTIVITY DURATION PREDECESSOR
8 1 9
S FG F
9,5
A 2 days Start bigger +
B 6 days A D 9 3 12
C 6 days B
+
F
D 1 day B 2 3 5
E 3 days A
E
F 3 days D, E
G 2 days C(+2), F
Rengquijo, KJ
Example: E D E
S F
0 2 2 2 6 8 8 6 14
- ACTIVITY
16-2 =14
A B C
8 14
(-2) L 16T2 18L
-
ACTIVITY DURATION PREDECESSOR
8 1 9
S FG F
A 2 days Start - 16 18
B 6 days A D 9 3 12
12 13
C 6 days B -
F
D 1 day B 2 3 5 13 16
E 3 days A -
E
F 3 days D, E
10 13
G 2 days C(+2), F
Rengquijo, KJ
Example: E D E
S F
0 2 2 2 6 8 8 6 14
- - - ACTIVITY
16-2 =14
A B C
0 2 2 8 8 14
(-2) L 16T 2 18
L
-
ACTIVITY DURATION PREDECESSOR 8 , 12
smaller 8 1 9
S FG F
A 2 days Start - 16 18
2 , 10
B 6 days A
smaller D 9 3 12
12 13
C 6 days B -
F
D 1 day B 2 3 5 13 16
E 3 days A
E -
F 3 days D, E
10 13
G 2 days C(+2), F
Rengquijo, KJ
TF = LF - EF
Example: or = LS - ES E D E
S F
0 2 2 2 6 8 8 6 14
ACTIVITY
A B C
0 0 2 2 0 8 8 0 14
L 16T 2 18
L
ACTIVITY DURATION PREDECESSOR
8 1 9
S FG F
A 2 days Start 16 0 18
B 6 days A D 9 3 12
12 4 13
C 6 days B
F
D 1 day B 2 3 5 13 4 16
E 3 days A
E
F 3 days D, E
10 8 13
G 2 days C(+2), F
Rengquijo, KJ
Critical Path = (TF = 0)
Example: E D E
S F
0 2 2 2 6 8 8 6 14
ACTIVITY
A B C
0 0 2 2 0 8 8 0 14
L 16T 2 18
L
ACTIVITY DURATION PREDECESSOR S FG F
A 2 days Start 16 0 18
B 6 days A
C 6 days B
D 1 day B
E 3 days A
F 3 days D, E
G 2 days C(+2), F
THANK YOU
Bansiloy, Leanne Amor M.
Pateña, Brian M.
Rengquijo, Kimberly Jade A.