Professional Documents
Culture Documents
160 5E TR 002 3 PH Step Down Distribution 165
160 5E TR 002 3 PH Step Down Distribution 165
CONTENTS
DESCRIPTION ..................................................................................................... PAGE NO
1.0 SCOPE: ................................................................................................................. 161
2.0 STANDARDS: ...................................................................................................... 161
3.0 SERVICE CONDITIONS: .................................................................................. 161
4.0 DETAILED REQUIREMENTS: ........................................................................ 161
4.1 Type: ...................................................................................................................... 161
5.0 CONSTURACTION: ........................................................................................... 162
5.1 H.V. Termination: ................................................................................................ 162
5.2 L.V. Termination: ................................................................................................. 162
5.3 Transformer Tank:............................................................................................... 162
5.4 Cores: ..................................................................................................................... 162
5.5 Windings: .............................................................................................................. 163
5.6 Temperature Rise: ................................................................................................ 164
5.7 Fittings: .................................................................................................................. 164
5.8 Cleaning and Painting:......................................................................................... 164
6.0 TEST: ..................................................................................................................... 164
7.0 INFORMATION TO BE FURNISHED: ........................................................... 164
8.0 DRAWING AND OPERATION AND MAINTENANCE MANUAL: ........... 165
9.0 TEST CERTIFICATES:...................................................................................... 165
1.0 SCOPE:
This specification covers design, manufacture, factory testing and inspection, packing and
shipping of three phase outdoor distribution step down transformers complete with oil and
spare parts.
The transformer ratings and quantities as required by the project .
2.0 STANDARDS:
Unless otherwise specified herein, construction, performance and testing of all
equipment shall comply in all respects to requirements contained in the following latest
issue IEC, BS standards specification.
2.1 Power transformer (1-6 incl.)
2.2 Transformer oil
2.3 Painting
2.4 Insulation
Transformer shall be suitable to ensure satisfactory operation for the following altitude,
climatic and atmospheric site conditions:
a) Altitude: Sea Level and will be subjected to lightning strokes.
b) Ambient temperature: 50°C.
c) Wind pressure: (kg/m2) 80 – 130
d) Seismic acceleration: (g) 0.12 - 0.05
e) Isokeraunic level 10 – 18
f) Relative humidity: 90 -100%
g) Solar radiation: 1200 W/m²
h) Atmosphere: Heavy salt and dust laden pollution in coastal areas, moderate
sandstorm exposure and dust pollution in low to mid altitude and region and light to
heavy dust pollution at high altitudes.
5.0 CONSTURACTION:
The above shall be regarded as the basic information Specific data relating to any