Professional Documents
Culture Documents
54-GENERAL Section - 1 - 57
54-GENERAL Section - 1 - 57
SECTION (1)
PROJECT DETAILS
CONTENT
1. General: .............................................................................. 55
1.1. Extent of Contract: ........................................................ 55
1.2. Program Of Work .......................................................... 57
1.3. SITE AMBIENT CONDITION CLIMATE .................. 57
1.4. STAFF TRAINING: ...................................................... 57
Project Details
1. General:
Tender in duplicate is required to cover the design, supply, shipping, Transport to site,
construction, erection, testing and commissioning of two diesel generator set on a
contract basis for extension to SADA power station. It includes 2x2.5 MW diesel
generating sets, medium speed (not exceeding 750 rpm) base load. Continues
operation diesel generating sets. Station transformer, switchgear, over head crane,
cabling, piping, all necessary civil works including site preparation design and
erection building services connection to all termination points, tests, commissioning
of the generator sets, 24,000 hrs spare parts. All material and services to operate to the
extended power plant in harmony with existing power system. Tenderer must submit
complete offer covering the whole project as set out in the specifications and should
consider that he can offer any advantage to the purchaser by a modification to the
specification he may draw attention to such by an attached document but should only
modify after approval of purchaser.
These generator sets should be capable to run in parallel with existing generator set,
“the existing power stations “.
The quoted tender price shall be for the supply of everything necessary whether it be
described or not, to leave the equipment complete and in working order at the
expiration of the guarantee period and in accordance with the provisions of the
contract. They shall include the cost of supervise staff and all other overhead charges.
The tenderer shall be deemed to have visited the site and to have collected all
information required for tendering purposes.
In the following speciation the engineer is the purchaser or an engineer appointed by
the purchaser.
Bidders should provide all details according tender documents any offers not
complain with tender document requirement will reject .
The purchaser is. Public Electricity corporation
Republic of Yemen P.O. Box 178 Sana’a
Tel. 1 -328141/2 Fax. 1 -328150/1
- 11 KV Switchgears as outgoing feeders and connection with existing system . bus coupler and
station transformers.
- 400 V Switchgear.
- Cabling and Earthling.
- Air Compressor system. .(starting & control compressed air system)
- Cooling water systems.
- Lub oil system .
- Fuel Oil system.
- Air intake system.
- exhaust system.
- Fuel transfer equipment, and all accessories.
- Water softening system .
- Power house building, control room switchgear, Mechanical& electrical work shop and store.
- Civil works.
- Foundations for all plant,
- Trenches and ducts as required,
- Site filling and leveling as necessary,
- Oil purifier system.
- Over head crane 5 tons for the power house.
- Connecting to the existing power stations ,coupling to old station, and extension in future to be
came 15MW
- Dc system. –
-Lighting
-fire fighting system (smoke detectors , fire extinguisher
- Air conditioning and ventilation.
- Station transformer 630KVA.
- Water Tanks, (Extension only)
- All material and equipments mechanical and electrical for installation and erection.
- Provision of spares, manuals, drawings, special tools... etc
- All spare parts consumed for operation, maintenance and repairing through periodic interval
to 24000 operating hour .
- Inspection and testing of all equipment,
This contract also provides for all parts of the works to be completed in every respect for
commercial operation to the agreed programme and to the requirements and satisfaction of the
engineer. Not withstanding that any details, accessories…… etc. required for the complete
installation and satisfactory operation of the plant are not specifically mentioned in the
specification nor indicated in specification drawings. such details are to be considered as being
included in the contract price.
Any material or works which not specified/included in bid specification but required for safe
and reliable operation of the plant shall be deemed to be included in work and contractor shall
be carry out such material or works at no extra cost to the PEC.
The civil works in the contract will comprise all civil works required on the site, for extension,
including power house, switch gear, control room and it is connection to existing system.