LOAD TEST CERTIFICATE

File No.: LNGW/2022/LNGW/01/007 Testing Date: 16th Nov 2022


Manufacturer.: SAREN.
Fabricated at.: SAREN B.V., Registered Russian Branch «SAREN B.V.» in Murmansk Str. Shevchenko 36,
183052, Murmansk, Russian Federation. (NMP Yard, Murmansk, Russian Federation)
Intended for: GBS-1 LNG Pumps Installation

THIS IS TO CERTIFY that the ‘Bolted assembly of Gantry-2 on Monorails (133-HMB-901A & 133-HMB-901B) have been
load tested and found to be in compliance with the requirements of DNV GL ST-0378, Offshore and platform lifting
appliances. Gantry-2 assembly is load tested[1] at Tank-1 N7 (133-P-001C) location on GBS-1.

The calibration status and adequacy of the test measurements devices used have been satisfactorily verified.

Description of material:
LNG Pump installation System (Quantity: 01)
Gantry Frame-1 + Tension Load cell (for verifications).

Inspection and test carried out:


-Load Test:
Gross Functional Load = 8.72 T [1]
Load Test = 8.72*1.25 = 10.9T

- Visual checks are all acceptable.

Issued at: NMP Yard, Murmansk on: 16.11.2022


Lead Method Engineering Mechanical Superintendent HSE Representative

(Shaik Wahid) (Senol Kocakoyun) (HSE Representative)

[1] – GBS-100-ME-10045-Rev.00 GBS-1 LNG Pump Installation Frame Load Test Details.
[2] – GBS-100-ME-10036-Rev.01-GBS-1 LNG Pump Installation Gantry Frame Details.