Professional Documents
Culture Documents
Progress Nov 2022-R02
Progress Nov 2022-R02
RIVEA
TIME LAPSE OF
SITE
CONTRACTOR
Commencement Date: 11th October 2021
RIVEA
RIVEA Original Duration: 15 months
Progress Layout Original Completion Date: 03rd January 2023
New Completion Date: 01 May 2023
Building Works
Lot 3/4
Lot 5/6 Lot 1/2
Lot 7
First Floor
Lot 11/12 Beam
Lot 9/10 Lot 8
Loft First Floor
First Floor Beam
Beam
Rock Mattress First Floor
Ground Floor Beam
Beam
First Floor
First Floor Beam
Beam
CONTRACTOR
RIVEA
RIVEA Commencement Date: 11th October 2021
Original Duration: 15 months
Progress Layout Original Completion Date: 03rd January 2023
CONTRACTOR New Completion Date: 01 May 2023
Building Works
Lot 3/4
Lot 5/6 Lot 1/2
Lot 11/12 Lot 7
Lot 8
Loft
Lot 9/10
RIVEA
Excavation and Rock Mattress
Due to the river and soil conditions, the foundation of the
different units were excavated until firm soil was reached.
A rock mattress was proposed compared to a mass concrete
as value engineering.
This method enable safe transfer of loading to the ground. Excavation and
Compaction of Rock
compaction requirement
Rock Material used for Mattress
Proper Compaction