CONTRACTOR

RIVEA

TIME LAPSE OF
SITE

CONTRACTOR
Commencement Date: 11th October 2021
RIVEA
RIVEA Original Duration: 15 months
Progress Layout Original Completion Date: 03rd January 2023
New Completion Date: 01 May 2023
Building Works

Lot 3/4
Lot 5/6 Lot 1/2
Lot 7

First Floor
Lot 11/12 Beam
Lot 9/10 Lot 8
Loft First Floor
First Floor Beam
Beam
Rock Mattress First Floor
Ground Floor Beam
Beam
First Floor
First Floor Beam
Beam

CONTRACTOR
RIVEA
RIVEA Commencement Date: 11th October 2021
Original Duration: 15 months
Progress Layout Original Completion Date: 03rd January 2023
CONTRACTOR New Completion Date: 01 May 2023
Building Works

Lot 3/4
Lot 5/6 Lot 1/2
Lot 11/12 Lot 7

Lot 8
Loft

Lot 9/10
RIVEA
Excavation and Rock Mattress
Due to the river and soil conditions, the foundation of the
different units were excavated until firm soil was reached.
A rock mattress was proposed compared to a mass concrete
as value engineering.
This method enable safe transfer of loading to the ground. Excavation and
Compaction of Rock
compaction requirement
Rock Material used for Mattress
Proper Compaction

This method prevented for future users to have flooding and


unsuitable foundation such as photos taken below:
Testing of Rock Mattress Rockfill