BR. CAT INTERNATIONAL CO. LTD. METHOD STATEMENT FOR CONSTRUCTION OF CELLAR
Table of Contents
2
BR. CAT INTERNATIONAL CO. LTD. METHOD STATEMENT FOR CONSTRUCTION OF CELLAR
1. Scope
This CMS define requirements for construction of cellar base and walls.
2. Reference
3. Responsibilities
Quality Supervisor – is responsible to make sure that execution of work is implemented with
approved procedure & specification.
Site Engineer – is responsible to ensure that concerned work force is familiar with the activity,
hazards and mitigated effects of the situation and are responsible to ensure that the works
are carried out as per approved IFCs and applicable project standards.
Surveyor – is responsible to ensure that all Surveying Work is in accordance to approved data
and recorded well.
Site Foreman – is responsible to ensure that the work crew is familiar with the safety
requirement of the activity.
The safety of all personnel, equipment and plant operations will be the responsibility of the
Construction Manager in coordination with the Site Engineer.
3
BR. CAT INTERNATIONAL CO. LTD. METHOD STATEMENT FOR CONSTRUCTION OF CELLAR
4. Methodology
4.1 Levelling & Compacting of Cellar base
Tools shall be inspected before and after use, as well as before storage
Personnel shall not operate any tools unless they are appropriately trained in their
selection, use, inspection, and storage
Tools constructed of good quality materials shall be used. Use of “homemade”
tools is prohibited.
The correct type, size and weight of tool shall be used for each task.
Ensure that sharp edged objects are properly capped/covered with visible warning
signs
Execute proper manual handling/lifting technique
Ensure that walkway and working area is free from any obstruction
Proper racks and boxes shall be provided and used for storage of tools.
Personnel shall not operate any tools unless they are appropriately trained in their
selection, use, inspection, and storage
Proper tools shall be used.
Tools shall be inspected before and after use, as well as before storage
Excessively worn, defective or deformed tools shall not be used. If excessive wear,
defect, or damage is observed, the tool shall be immediately tagged and
withdrawn from use for repair or disposal.
Proper racks and boxes shall be provided and used for storage of tools.
Protruding rebar shall be protected with rebar caps/cover
Materials and tools shall be set back at least 2ft from the edge of the excavation
The correct type, size and weight of tool shall be used for each task.
Provide and use proper platform on elevated installation.
Adequate, proper, and secured access shall be installed
Personnel shall not operate any tools unless they are appropriately trained in their
selection, use, inspection, and storage
Tools constructed of good quality materials shall be used. Use of “homemade”
tools is prohibited.
Tools shall be always kept clean.
Tools shall be inspected before and after use, as well as before storage
Excessively worn, defective or deformed tools shall not be used. If excessive wear,
defect, or damage is observed, the tool shall be immediately tagged and
withdrawn from use for repair or disposal.
Proper racks and boxes shall be provided and used for storage of tools.
4
BR. CAT INTERNATIONAL CO. LTD. METHOD STATEMENT FOR CONSTRUCTION OF CELLAR
The correct type, size and weight of tool shall be used for each task
Proper manual handling and lifting technique shall be done
Provide and use proper platform on elevated installation. Use full body harness
when required
Proper and secured access shall be installed
Walkway and working area shall be free from any loose materials and obstructions
Materials and tools shall be set back at least 2ft from the edge of the excavation
4.4 Concrete pouring using concrete mixer and concrete pump, vibrator
Excessively worn, defective or deformed tools shall not be used. If excessive wear,
defect, or damage is observed, the tool shall be immediately tagged and
withdrawn from use for repair or disposal.
Proper racks and boxes shall be provided and used for storage of tools.
The correct type, size and weight of tool shall be used for each task
Execute proper manual handling/lifting technique
Walkway and working area shall be free from any loose materials and obstructions
Provide and use proper platform on elevated installation. Use full body harness
when required
Materials and tools shall be set back at least 2ft from the edge of the excavation
Adequate, proper, and secured access shall be installed
Install highly visible barricades and warning signs
Proper manual handling and lifting technique shall be done
5. Safety
The health and safety will perform a splendid role in all construction activities to ensure
that all the works are being carried out in a safe manner and creating a healthy
environment at site. All works performed by individuals will comply with the Client
health and Safety Standards.
Ensured that all site personnel involved use their PPE. Housekeeping and safe access
properly maintained all the time. All the signs install prior to start the job.
Site Supervisor will conduct daily toolbox meetings and explain the requirements of the
Client and other special needs to make and maintain a safe working environment.
If there is any unsafe condition, Workers/ Equipment shall not be allowed to enter the
area.
All activities will be carried out safely in accordance with Contractor’s HS plan approved
by the Client.
6. Reporting
6
BR. CAT INTERNATIONAL CO. LTD. METHOD STATEMENT FOR CONSTRUCTION OF CELLAR
Contractor will document all necessary record and will represent to Aramco Inspection
team for review and approval.
7. Attachments
None