STRUCTURE COMPLETED BEFORE MONTH OF MAY 2017

BOX CULVERT
CHANAIGE COMPONENT STATUS SIDE REMARK
1+026 Completed B/S
5+525 Completed B/S
6+980 Completed B/S
9+409 Completed L/S
13+459 Completed B/S

17+636 Raft & side Wall final lift completed B/S

20+125 Completed B/S


21+037 Raft Completed B/S
21+470 Raft Completed B/S
22+572 Raft Completed B/S
22+971 Completed B/S
23+235 Completed B/S
27+002 Raft & side Wall final lift completed B/S
27+625 Completed B/S COS
28+432 Raft Completed B/S

HPC
9+944 Completed R/S
10+798 Completed B/S
12+225 Completed B/S
13+079 Completed B/S
14+107 Completed B/S
20+722 Completed B/S
22+491 Completed B/S
27+981 Completed B/S COS

VUP

Raft & side Wall final lift completed L/S


4+882
Raft & side Wall final lift completed R/S

MNB
11+905 Upto Slab Completed L/S
8+023 A2 Pile no. 7 R/S Collapsed
MJB
P4 6 nos. Completed
17+900
P5 6 nos. Completed
AS PER GOVERNMENT OF INDIA MINISTRY OF SURFACE TRANSPORT STANDARD
DRAWING OF BOX CELL STRUCTURES AS PER SADBHAV ENGINEERING LIMITED WORKING DRAWING

(DIMENSIONS DETAILS) (DIMENSIONS DETAILS)

Chanaige Box Cell a b c d e f g a b c d e f g

15+525 2x2x2 2.0 2.0 0.300 0.400 0.400 0.370 0.300 2.0 2.0 0 0.250 0.300 0.250 0.150

29+710 1x2x2 2.0 2.0 0.500 0.350 0.380 0.300 - 2.0 2.0 0 0.250 0.300 0.250 -

32+279 1x2x2 2.0 2.0 0.500 0.350 0.380 0.300 - 2.0 2.0 0 0.250 0.300 0.250 -

35+410 1x3x3 3.0 3.0 0.900 0.420 0.420 0.420 - 3.0 3.0 0 0.350 0.375 0.360 -

39+850 1x2x2 2.0 2.0 0.500 0.350 0.380 0.300 - 2.0 2.0 0 0.250 0.300 0.250 -

40+875 1x2x2 2.0 2.0 0.500 0.350 0.380 0.300 - 2.0 2.0 0 0.250 0.300 0.250 -