Structure Work On 19.06.2017 (BE SIR)
Structure Work On 19.06.2017 (BE SIR)
2017
Box Culvert HPC
S. No. Chainage Status Side S. No. Chainage Status Side Belance
1 1+026 Complete B/S 1 9+944 in Prog. R/S Pipe laying
2 1+925 Raft B/S 2 10+798 Head wall B/S Pipe laying
3 4+692 PCC B/S 3 12+225 Head wall B/S Pipe laying
4 5+525 Complete B/S 4 13+079 Head wall B/S Pipe laying
5 6+980 Complete B/S 5 20+722 Head wall B/S Pipe laying
6 9+409 slab Complete L/S 6 22+491 Head wall B/S Pipe laying
7 9+653 PCC L/S
8 13+459 Complete B/S
9 17+116 Raft L/S Structure work on 19.06.2017
10 17+634 Complete B/S VUP
11 20+125 Complete B/S S. No. Chainage Status Side
12 21+037 Complete B/S 1 3+251 Raft B/S
13 21+407 Complete B/S final lift L/S
2 4+882
14 21+665 Complete B/S 2nd lift R/S
15 22+572 Complete B/S 3 28+922 Raft B/S
16 22+971 Complete B/S
17 23+235 Complete B/S Structure work on 19.06.2017
18 24+664 Complete L/S Minor Bridge
19 24+564 Complete L/S S.No Chainage Status Side
20 25+516 1st lift B/S
A2 side Pile no.
21 25+972 Raft B/S 1 8+023 R/s
7, Collapsed
22 27+002 Complete B/S
23 28+432 1st lift R/S
24 29+710 PCC B/S
25 36+564 Raft L/S Structure work on 19.06.2017
26 40+875 Raft R/S Major Bridge
27 41+784 Raft L/S S. No Chainage Status Side
Pile P4-6nos.
L/S
Completed