Professional Documents
Culture Documents
2001 - 05 - 03 Draw Control at Koffiefontein Mine - Hannweg and Van Hout
2001 - 05 - 03 Draw Control at Koffiefontein Mine - Hannweg and Van Hout
2001 - 05 - 03 Draw Control at Koffiefontein Mine - Hannweg and Van Hout
* Geotechnical Officer
De Beers Consolidated Mines Limited
† Geotechnical Engineer
De Beers Corporate Headquarters
May 2001
2
ABSTRACT: In a first for the diamond industry, Koffiefontein Mine in the Free State, South Africa,
opted for the Front Cave Mining Method to extract a 90 metre high block of kimberlite ore. Block
caving, because of its high initial capital requirements, resulting in a negative internal rate of return
(IRR), was ruled out as a feasible mining method for Koffiefontein Mine.
Front Caving is essentially a combination of the traditional block cave and sub-level cave mining
methods, but uses two or more levels of retreating drawpoints. Two extraction levels, in the case of
Koffiefontein Mine, are spaced 12m apart vertically, with the upper 478m level (48 Level) acting as the
undercut/extraction level, and the lower 490m level (49 Level) as the extraction level. Caving is achieved
by undercutting a small column of ore, which is then drawn, on both the 48 and 49 Levels, until the
planned extraction percentage is achieved. The next column of ore is then mined by advancing the
undercut (48 Level), and the process is repeated until the entire ore block is depleted to the contact.
Caving-by-gravity techniques of mining rely on closely controlled draw of the caved ore to ensure proper
caving action and to minimise the dilution of ore with waste material from the open pit. This paper
discusses the need for, and implementation of, a draw control system at Koffiefontein Mine - a
computerised production management system, and a draw control system based on linear programming,
to allow control over the draw rate and mining sequence – a major factor in all production planning to
optimise production efficiency, ore recovery and cave management.
1. INTRODUCTION
The Koffiefontein Diamond Mine is located in the south-west portion of the Orange
Mining of the kimberlite pipe commenced in 1878, but ceased several times from 1892
to 1913 and from 1919 to 1931 due to World War I. It reopened in 1970 as an opencast
levels 27 to 60. Due to the downturn in the diamond market, the mine closed in 1982.
In 1987 the mine re-opened with a sub-level open-stope mining method, but the mining
method was immediately converted to the blast hole open stoping, compound-ring
method1.
Koffiefontein mine is a low grade, marginal mine and the forecasted ore dilution due to
pit sidewall failures when extracting the kimberlite pipe to lower levels resulted in an
investigation into an alternative mining method. Reducing the waste influx to the
underground drawpoints is vital to ensure a viable future when deepening the mining
operations. It was appreciated at the start of the blast hole open stoping that early waste
dilution would be a problem, but the method enabled the mine to get production, and
hence revenue, quickly. If a block cave or front cave was started instead, the build up
period would have delayed the production start-up and the required initial capital
investment was considered too high. Blast hole open stoping on the 37 level was later
replaced by sub-level caving in an attempt to cut off the increasing quantities of waste
The susceptibility to slope failures demanded a revision of the mining method at depths
below 37 level. Several miming methods were evaluated and front caving provided a
Front caving was selected above other methods for technical and financial merits. The
Front Cave layout constitutes two levels with 4m wide by 4.2m high tunnels spaced at
15m centres. The upper level, 48 Level, acts as the main undercut level. The lower
level, 49 Level, is the main extraction level and lags the upper level by 12 to 24m. The
vertical inter-level spacing is 12m. The extraction tunnels run north-south and are
Load-Haul-Dump (LHD) machines are used to transport the ore from loading points at
the end of the extraction drifts to ore passes located outside the orebody.
As the draw zone associated with the loading points has a limited reach and the
depletion of an ore column happens over a considerable time period, the loading points
must remain static both in space and time. However, due to the large volume of ore
fragments gravitating down through the small tunnel openings and the relatively weak
kimberlite rock mass, the brow at the loading points tend to wear away rapidly. This
brow erosion must be kept to a minimum to maintain the rock mass integrity and to
ensure safe loading from loading points which are fixed till the column has been
depleted. It is not within the scope of this paper to describe in detail the support for
these loading points, also called Semi Permanent Drawpoints (SPD), but its design is
very similar to the support type employed at Henderson Mine. The support installed at
the SPD’s has successfully managed to protect the brow of the loading points and recent
inspections of the brows at loading points that have ceased production showed very
little deterioration.
5
Once a column is depleted the associated SPD will be destroyed and a sequence of
drill/blast/load 2m wide blast hole ring’s around the extraction drift is repeated until the
undercut face has been retreated to the next SPD position in that drift.
The following Front Caving layout2 resulted from a number of planning sessions held at
the mine involving all affected disciplines, as well as input from Dr. D.H. Laubscher:
The Front Cave mining method would be ideal if three production levels were to be
developed – the bottom level being a scavenger level to recover any ore not
extracted on the upper two levels. Koffiefontein could not financially justify the
third level, and a compromise was made to develop only two production levels: 48
and 49 Levels were planned with 4m wide drawpoint drifts (see Figure 2).
The undercutting should start against the north contact of the mudstone and retreat
northwards. By starting at the mudstone, the mining sequence will be from poor to
better rock mass and caving is expected to progress more rapidly. There will be no
to the long axis of the pipe. This will ensure maximal tunnel stability in the
kimberlite zone close to the contact. Figure 3 illustrates the Front Cave mining
sequence.
It was recognised that there is a need to control the extraction process, to gain maximum
ore recovery with minimum waste dilution, particularly at the time of near exhaustion.
Careful control of the production will ensure that the secondary fragmentation process3
6
within the cave takes place, resulting in acceptable fragmentation size blocks reporting
The need for a very strict draw control system at the mine became more crucial due to
the reduction in extraction levels from three to two. This reduced the flexibility of
”draw”, as the production section would not be able to return if ground was left behind.
Other benefits for a draw control system can be highlighted by listing the following:
Ensure the draw horizon is strictly maintained and that the ore is drawn from the
The following operating parameters affecting draw control were established for the
Side dilution entry will commence at 20 per cent draw and will amount to
approximately 10 per cent of the ore column volume. Side dilution is sourced from
the previously mined area and occurs as a result of the ground left behind from the
previous block. Its appearance is rapid due to its close proximity to the drawpoints
Top dilution entry will commence at 52 per cent draw and the waste content will
gradually increase as the column is drawn down. The dilution entry and rate of
influx are determined from the ore recovery chart based on the following parameters
(after Laubscher3); ore column height, height of interaction, swell factor and draw
control factor.
7
From the ore recovery chart the draw cut off percentage can also be determined. The
maximum tolerable instantaneous waste in the head feed is 20 per cent, resulting in
a draw cut off percentage equal to 81 per cent of the column reserves.
Draw control must be strictly controlled on the upper level, as waste drawn into the
drawpoints on the 48 Level will cut off the 49 Level resources. Currently it is
planned to extract 40 per cent of the mineable resource from the upper level and 60
per cent from the lower level. Limiting the extraction on the upper level is due to
the fact that the associated draw ellipsoid does not fully develop as a result of the
adjacent unmined block. Also 48 Level draws ore from columns that are less
The undercut is mined in a breast fashion – when drawpoints on the eastern side are
reaching maturity, drawpoints at the West Side will only be commencing extraction.
This allows for a blending of diluted ore from the East Side with undiluted ore from
the West Side. As the West Side starts to mature, so the East Side will be reaching
draw cut off and the undercutting of the next block commences. This sequence will
also ensure that, at all times, there are enough drawpoints available to achieve call
while other drawpoints are being prepared to come into production when the most
The ore columns should be drawn down uniformly across the cave to ensure the ore-
waste interface is maintained. Poor draw control practices lead to premature waste
dilution with the possibility of waste either cutting off payable ore or diluting payable
If draw control is mismanaged and premature dilution occurs on the 48 and 49 Levels,
higher dilution will continually be drawn as the undercutting blast hole ring’s are
retreated toward the next series of semi-permanent drawpoints. In that case, the
Progress with the flat undercut, drawing only a limited tonnage to ensure a
successful undercut between the contaminated area and the next semi-permanent
drawpoints. This would ensure that the undercut is maintained, preventing cave
inhibition.
drawn onto the lower level and not carried on the undercut face contaminating the
The interface between waste, from the expected pit sidewall failures, and the top of
would have to be retreated simultaneously once the first strip is depleted. This
would result in a loss of production for a long period as undercutting and SPD
An angle less than 25 degrees would have the same, but less severe effect, on
production loss.
increase the probability of the overlying waste mixing with the ore material through
Maintaining a constant angle in the cave is essential and can sometimes overrule other
constraints. As a drawpoint matures to the end of its life, it will begin to draw more and
more waste until it becomes uneconomic to continue mining. If adjacent drawpoints are
still mining at low waste contents, there may be a necessity to continue to extract ore
from the high waste drawpoints to maintain the correct shape to maximise extraction
Investigations are currently been carried out to replace the concept of a constant angle
with a constraint that controls the depletion difference between columns. It is easier to
of the swell factor and density of the material within each column.
The draw cut-off percentage is a crucial parameter for the Front Cave at Koffiefontein
Mine as extra recovery of a few per cent has a huge financial benefit. The development
of the draw control programme was necessary to ensure maximum extraction of the ore
resource. Two main factors determine the allowable draw cut-off percentage:
Treatment plant’s inability to treat diluted ore. The plant can only manage a
maximum of 20 per cent instantaneous waste in the head feed after which diamond
If good draw control practices are adhered to, at least 81 per cent of the resource can be
approaching 100 per cent. An extra recovery (above 81%) of only a few per cent easily
pays back the cost of installing a state of the art draw control system.
A draw control programme capable of the following was thus required to control the
Allocate dynamic calls on a shift by shift basis ensuring that the long-term draw
Different quantities (tonnages) of vertical virgin, vertical wedge and other sources
Base ore resource tonnages can be adjusted throughout the life of the mine. This
Automatic optimal call distribution facility throughout the block so that high and
extraction data.
Be able to accept daily data from a standard vehicle management system. This will
As there was no package available on the market to satisfy the above-mentioned criteria,
Linear Programme (LP) based application. This draw control package meets the criteria
set out above and has many other benefits over other existing applications considered to
be draw control programs. The system has been described by Guest et al4. As the
As good Draw Control practice requires correct and ‘real time’ production data, a
integral component of the Draw Control System. The VMS, a productivity monitoring
and vehicle dispatching system, was set up to provide continuous real-time data to the
control room computers. The draw control linear programme needs to communicate the
shift production calls for each drawpoint to the VMS, and also capture from VMS the
Both systems independently maintain their shift calendars. The VMS has an internal
real-time shift calendar for all mini-shifts (night, morning and afternoon shifts). The
Draw Control system will be based on whole day shifts and also be able to report using
the mine’s production calendar. Exceptional shifts (extended weekend shifts) will be
12
manually added by system operators for both systems. Interfacing between the VMS
Planned production and actual production tonnage are stored in specifically named files.
The planned and actual files contain an entire shift day’s tonnages. The files reside in
one location on a central fileserver. The draw control system manages the import of
actual data files. The two programmes interface with each other and update the draw
control tally information on a continuous basis. The vehicle monitoring system is the
Implementing the combined LP Draw Control System and vehicle monitoring system at
Koffiefontein, has enabled better control and management of the ore resource resulting
system. Figure 5 shows a graph drawn during the implementation of the vehicle
monitoring system. Manual reports were compared to VMS results and plotted per
shift. Major variances were seen during the implementation phase, however vast
improvements can be seen since the systems have been fully up-and-running. A graph
(as in Figure 5) drawn for March 2001, would show a single line – no difference
between what the miners report and what the VMS records.
The ‘theoretical’ cave profile is checked every two weeks by plotting a graph of the
tonnages drawn from the cave. This is done in an attempt to ensure that the 25 degree
angle of broken ore in the cave is maintained. Figure 6 shows an example of this graph.
13
7. CONCLUSION
The need for a strict draw control system at Koffiefontein Mine resulted from the need
to maximise ore recovery and limit the waste dilution from pit sidewall failures but
became crucial after the decision to develop only two extraction levels. The flexibility
of draw was reduced and the production section would not be able to return to the level
Draw Control at Koffiefontein centres around optimising tonnage rather than carats, as
financially more attractive scenario’s unless a full risk assessment exercise has been
conducted. In the planning stage, decisions should not be made based on NPV
attractive scenario’s that overlook the risks and associated costs by violating the
The implementation of the integrated Draw Control System and Vehicle Management
System has improved the recording of tons loaded from underground drawpoints.
Production efficiency, ore recovery and cave management have been optimised, and are
ACKNOWLEDGEMENTS
and all other persons who made valuable contributions and expressed constructive
criticism.
REFERENCES
Massive Mining Methods, Randburg, The South African Institute of Mining and
Metallurgy, 1996
for the extraction of the 370m to 490m ore reserve. Massive Mining Methods,
3. Laubscher, D H, 1994. Cave mining, the state of the art, JS Afr Inst Min Metall,
October, pp 279-293
4. Guest et al, 2000. An application of Linear Programming for Block Cave Draw
SUB LEVEL
SUB LEVEL CAVING
SOUTH CAVING NORTH
FRONT CAVE
NORTH
25
LEGEND
KIMBERLITE CONTACT
MUDSTONE CONTACT
UNDERCUT
SOUTH
37 LEVEL
37 LEVEL
48 LEVEL
48 LEVEL
49 LEVEL
49 LEVEL
A B
37 LEVEL 37 LEVEL
48 LEVEL 48 LEVEL
49 LEVEL 49 LEVEL
C D
37 LEVEL
SOUTH NORTH
48 LEVEL
49 LEVEL
52 HAULAGE LEVEL
E
Figure 3: Front Cave mining sequence A - Slot cutting B - Undercutting C – Caving progress
D – Holing into the pit floor E – Retreating the Undercut (Koffiefontein is currently at this stage)
17
DRAW CONTROL
OFFICER
GATEWAY PC PLANT
GATEWAY PC
PRODUCTION
GEOTECH DRAW CONTROL once a week
PLANNING SYSTEM DRAW CONTROL once a week
DEVELOPMENT XLS LP SYSTEM
once a week once a week XLS LP
once a day
ORIGIN
S/BOSS PRODUCTION
CALL SHEET GEOTECH
ORIGIN
PLANNING
Figure 4: Flow charts showing the original (left) and improved (right) draw control systems.
400
350
300
scoops loaded
250
200
150
100
50
0
N01
N02
N03
N04
N05
N06
N07
N08
N09
N10
N11
N12
N13
N14
N15
N16
N17
N18
N19
N20
N21
Figure 5: Graph showing comparison between PRODMAN and Miners’ reports during August
2000. The same graph drawn for March 2001 is one line.
18
Figure 6: Graph showing broken ground profile, as well as profile of waste rock in the pit.