PENGURUSAN ASET AIR BERHAD

CONTRACT NO. : PAAB/D007-P7/W/D/K/02/19

CLIENT : PENGURUSAN ASET AIR BERHAD

PROGRAM PENGGANTIAN PAIP LAMA/UZUR DENGAN


PROJECT NAME : PAIP BARU DI NEGERI KELANTAN TAHUN 2018,
PAKEJ 7 – KOTA BAHRU ZON D(KBU 12) (WORKS")

OVERALL REPORT ON MAKING


GOOD DEFECTS

EMPLOYER IMPLEMENTING AGENCY CONTRACTOR

RANHILL WATER SERVICES


PENGURUSAN ASET AIR AIR KELANTAN SDN BHD
SDN. BHD.
BERHAD Wisma Air Kelantan
Level 4, Matang Building,
19th Floor, Menara Felda, Lot 188 Jalan Tuan Guru Nik
83, Jalan Langkasuka, Larkin
Platinum Park, Abdul Aziz,
Industrial Area,
No.11 Persiaran KLCC, 15050 Kota Bharu
80350 Johor Bahru,
50088 Kuala Lumpur Kelantan Darul Naim
Johor Darul
PROGRAM PENGGANTIAN PAIP LAMA/UZUR DENGAN PAIP BARU DI NEGERI KELANTAN
2018,
PAKEJ 7 — KOTA BHARU ZON D (KBU12)("WORKS")
PAAB/D007-P7/W/D/K/02/19
REPORT ON MAKING GOOD DEFECTS

Table of Contents

SECTION 1: SUMMARY OF CONTRACT......................................................................................3

SECTION 2: PROJECT BRIEF....................................................................................................... 5

SECTION 3 : PROJECT COMPONENT......................................................................................... 5

3.1 Scope of Work.......................................................................................................................... 5

3.2 Scope of Variation Order Work................................................................................................. 5

SECTION 4: CERTIFICATE OF COMPLETION.............................................................................6

5.1 General..................................................................................................................................... 6

5.2 Letter of CPC............................................................................................................................ 6

5.3 Defect Liability Period............................................................................................................... 6

SECTION 5: DEFECT LIABILITY PERIOD.....................................................................................6

SECTION 6: CERTIFICATE OF MAKING GOOD DEFECT (CMGD).............................................7

SECTION 7: CONCLUSION AND RECOMMENDATION...............................................................7

LIST OF ATTACHMENTS

Attachment 1: Project Layout Plan


Attachment 2: Copy of CPC
Attachment 3: Copy of Letter Defect from RANHILL WATER SERVICES SDN BHD

2
PROGRAM PENGGANTIAN PAIP LAMA/UZUR DENGAN PAIP BARU DI NEGERI KELANTAN
2018,
PAKEJ 7 — KOTA BHARU ZON D (KBU12)("WORKS")
PAAB/D007-P7/W/D/K/02/19
REPORT ON MAKING GOOD DEFECTS

SECTION 1: SUMMARY OF CONTRACT

PROGRAM PENGGANTIAN PAIP LAMA/UZUR DENGAN


Project Name PAIP BARU DI NEGERI KELANTAN 2018,KOTA BAHRU
ZON D (KBU 12) ("WORK")

Pengurusan Aset Air Berhad


19th Floor, Menara Felda,
Platinum Park,
Employer No.11 Persiaran KLCC,
50088 Kuala Lumpur.

Air Kelantan Sdn Bhd


Wisma Air Kelantan
Lot 188 Jalan Tuan Guru Nik Abdul Aziz,
Implementing Agency 15050 Kota Bharu
Kelantan Darul Naim.

Ranhill Water Services Sdn. Bhd


Level 4, Matang Building,
83, Jalan Langkasuka, Larkin Industrial Area,
80350 Johor Bahru,
Johor Darul Takzim
Contractor
Site Office:.
Ranhill Water Services Sdn. Bhd
PT 718, Jalan Sultan Yahya Petra,
15200 Kota Bharu,
Kelantan.
Contract No. PAAB/D007-P7/W/D/K/02/19
Original Contract Sum RM18,588,219.00
Variation Order Contract Sum RM5,140,548.10

3
PROGRAM PENGGANTIAN PAIP LAMA/UZUR DENGAN PAIP BARU DI NEGERI KELANTAN
2018,
PAKEJ 7 — KOTA BHARU ZON D (KBU12)("WORKS")
PAAB/D007-P7/W/D/K/02/19
REPORT ON MAKING GOOD DEFECTS

Date of Commencement 10 March 2019


Date of Completion 09 March 2020
Extension of Time 13 May 2021
Contract Duration 12 months
12 months from date of Certificate of Practical Completion
Defect Liability Period
(CPC)
Liquidated and Ascertained
RM4,070.82 per day
Damages (LAD)
PAAB/CD/TE/D007/PAKEJ 7/LOA/19/0011 dated 20 Feb
Letter of Award Ref.
2019
Performance Guarantee Sum
Performance Bond Amount : RM 929,410.95 (5% of Contract Sum) in the form of
approved Bank Guarantee

Insurer : Takaful Ikhlas General Berhad


Ranhill Water Services Sdn Sum insured : RM 18,588,219.00 (paid)
Bhd’s All Risks Insurance Policy Policy No. : JBB301EN19100248
Period : Contract duration + 12 months + 3 months + 14 days

Insurer : Takaful Ikhlas General Berhad


Workmen’s Compensation Sum insured : RM 1,858,821.90 (paid)
Insurance Policy Policy No.: JBB341WC19100249
Period : Contract duration + 12 months + 3 months + 14 days
Conditions of Contract PWD FORM 203A (Rev.1 /2010)
CIDB Levy RM23,235.25 (paid 29.03.2019)
Lithography Charges RM1,500.00 (paid 19.03.2019)
DOSH/JKKP Registration KN/19/03/136566
SOCSO Registration E1100040766V
Cert No. : 0120051223-JH107552
CIDB Registration Class : G7
Validity : 16.07.2017 to 15.06.2020

Cert No. : 0120051223-JH107552


BPKU Registration Class : Bumiputera
Validity : 16.10.2017 to 15.06.2020

Permit No. : SPAN/EKS/(PT)/800-2C/1/09/412


SPAN Registration Type : IPA JENIS C1 (BEKALAN AIR)
Validity : 18.06.2019 to 17.06.2020

4
PROGRAM PENGGANTIAN PAIP LAMA/UZUR DENGAN PAIP BARU DI NEGERI KELANTAN
2018,
PAKEJ 7 — KOTA BHARU ZON D (KBU12)("WORKS")
PAAB/D007-P7/W/D/K/02/19
REPORT ON MAKING GOOD DEFECTS

SECTION 2: PROJECT BRIEF

Ranhill Water Services Sdn Bhd (RWS) was awarded a contract by Pengurusan Aset Air Berhad
(PAAB) for Program Penggantian Paip Lama/Uzur Dengan Paip Baru Di Negeri Kelantan 2018,
Kota Bahru Zon D commencement on 10th March 2019.

RWS has set up a Project Management Team headed by the Project Manager with the overall
responsibility for the management, execution, monitoring and quality control of the project.

There would be six (6) management and supervisory personnel directly involved in the works with
additional support by other professionals at the professionals at the Head Office.

SECTION 3 : PROJECT COMPONENT

3.1 Scope of Work

i. Supply and Lay PVC-O and Mild Steel pipelines and specials at size 160mm to 630mm
nominal diameter to replace existing file.
ii. Supply and Install valves, construction of valves chambers, washout pipe works, typical and
specific overground pipe crossing, concrete support, anchor and thrust block etc. in
connection of the pipelines.
iii. Supply and Install new tapping saddle on PVC-O and Polyethylene Aluminium Composite
(PA) communication pipe to replace existing tapping to all affected consumer connections.
iv. Any related ancillary works not detailed in this section but necessary for the completion of the
works as may be ordered by the S.O. or this representative in accordance with the terms of
the contract.

3.2 Scope of Variation Order Work

i. Mill and Pave Road Reinstatement


ii. Supply, delivery and lay PVC-O and Mild Steel Pipe
iii. Laying pipe for HDPE 225mm through HDD method

The project layout plan is attached in Attachment 1.

5
PROGRAM PENGGANTIAN PAIP LAMA/UZUR DENGAN PAIP BARU DI NEGERI KELANTAN
2018,
PAKEJ 7 — KOTA BHARU ZON D (KBU12)("WORKS")
PAAB/D007-P7/W/D/K/02/19
REPORT ON MAKING GOOD DEFECTS

SECTION 4: CERTIFICATE OF COMPLETION

5.1 General

The overall works were completed on 31 May 2021. The defect inspection has been conducted
and attended by PENGURUSAN ASET AIR BERHAD, AIR KELANTAN SDN BHD and RANHILL
WATER SERVICES SDN BHD.

5.2 Letter of CPC

A CPC for overall works was issued by PENGURUSAN ASET AIR BERHAD to the RANHILL
WATER SERVICES SDN BHD on 06 August 2021.

The copy of letter CPC is attached in Attachment 2.

5.3 Defect Liability Period

Defect liability period for overall works commenced on 14 May 2021 and ended on 13 May 2022.

SECTION 5: DEFECT LIABILITY PERIOD

Defect inspection has been carried out prior to the issuance of a certificate of Making Good
Defects (CMGD). Total of 89 defects have been identified and rectified on site. Letter on
rectification of defects has been issued to AKSB on 14 th July 2022.

The copy of letter is attached in Attachment 3.

6
PROGRAM PENGGANTIAN PAIP LAMA/UZUR DENGAN PAIP BARU DI NEGERI KELANTAN
2018,
PAKEJ 7 — KOTA BHARU ZON D (KBU12)("WORKS")
PAAB/D007-P7/W/D/K/02/19
REPORT ON MAKING GOOD DEFECTS

SECTION 6: CERTIFICATE OF MAKING GOOD DEFECT (CMGD)

The Certificate of Making Good Defects (CMGD) for Works has yet to be issued to the RANHILL
WATER SERVICES SDN BHD.

SECTION 7: CONCLUSION AND RECOMMENDATION

As the defects has been rectified accordingly, we hereby request for the issuance of the
Certificate of Making Good Defect (CMGD) effective on 15 July 2022.