MATERIALES PARA OBRA

1. CONCRETO Unidad Cantidad Precio unit. Parcial


Cemento Antialitre und. 465.0 28.50 13,252.50
Cemento Tipo I und. 800.0 26.50 21,200.00
Concreto premezclado [h=20cm] m3 63.0 350.00 22,050.00
S/ 56,502.50

2. LADRILLO Unidad Cantidad Precio unit. Parcial


Ladrillo KK 18 Huecos millar 18.0 750.00 13,500.00
Ladrillo de techo h=15cm und. 2000.0 2.50 5,000.00
S/ 18,500.00

3. AGREGADOS Unidad Cantidad Precio unit. Parcial


Piedra de 6" m3 20.0 54.00 1,080.00
Piedra de 1/2" m3 90.0 90.00 8,100.00
Arena Gruesa m3 85.0 53.00 4,505.00
Arena Fina m3 25.0 25.00 625.00
S/ 14,310.00

4. ACERO Unidad Cantidad Precio unit. Parcial


Fierro de 5/8" und. 160.0 70.00 11,200.00
Fierro de 1/2" und. 385.0 45.80 17,633.00
Fierro de 3/8" und. 465.0 26.80 12,462.00
Fierro de 8 mm und. 105.0 18.00 1,890.00
Fierro de 1/4" und. 200.0 12.30 2,460.00
Alambre # 16 kg 350.0 8.00 2,800.00
Alambre # 8 kg 200.0 8.00 1,600.00
Clavos de 2" kg 50.0 8.00 400.00
Clavos de 2 1/2" kg 50.0 8.00 400.00
S/ 50,845.00

TOTAL S/ 140,157.50