SB 01 Target Finished : 07-Nov

TANGGAL PEKERJAAN JML


ITEM PEKERJAAN VENDOR SPV PJ
04-Nov 05-Nov 06-Nov 07-Nov PEKERJA

I FINISHING
1 Repair Semua Dinding (acian) 2 Sodik Irwan Yudi
2 Pasang Batu Sumba (area sanitary) 2 Sodik Irwan Yudi
3 Repair & Pasang Batu Tulungagung 1 Sodik Irwan Yudi
4 Finishing Area Geberit 2 Sodik Irwan Yudi

II MEP
1 Pasang Sanitary LD Broto Yudi
2 Pasang Lampu LD Broto Yudi
3 Pasang Socket / Outlet LD Broto Yudi
4 Pasang AC + Fan LD Broto Yudi
5 Panel Electrical LD Broto Yudi

III JAYAGIRI
1 Repair Terrazo JG Irwan Yudi
2 Repair Carrara JG Irwan Yudi
3 Finishing Acid + Coating Final JG Irwan Yudi

IV OTHERS
1 Kalpataru TBC Widodo Yudi
2 Finishing Kayu Galam Other Widodo Yudi
3 Kaca Tempered Pergola TBC Irwan Yudi

JOINT CHECKLIST : 08-Nov Catatan :

Periode Repair Defect diberi waktu 2 hari sejak Checklist