The document is a bill of quantities (BOQ) for a false ceiling project at the University of Kaolack. It details the contract for installing an Armstrong mineral tile ceiling system with a total area of 2,498.38 square meters. The payment structure allocates 70% for framing, 25% for gypsum board fixing, and the remaining 5% for final finishing. It then lists the areas and amounts for framing and gypsum board fixing for each building and level at the university.
The document is a bill of quantities (BOQ) for a false ceiling project at the University of Kaolack. It details the contract for installing an Armstrong mineral tile ceiling system with a total area of 2,498.38 square meters. The payment structure allocates 70% for framing, 25% for gypsum board fixing, and the remaining 5% for final finishing. It then lists the areas and amounts for framing and gypsum board fixing for each building and level at the university.
The document is a bill of quantities (BOQ) for a false ceiling project at the University of Kaolack. It details the contract for installing an Armstrong mineral tile ceiling system with a total area of 2,498.38 square meters. The payment structure allocates 70% for framing, 25% for gypsum board fixing, and the remaining 5% for final finishing. It then lists the areas and amounts for framing and gypsum board fixing for each building and level at the university.
Contract - Armstrong mineral tile ceiling 60x60 exposed grid system with acoustic insulation - white colour Date; 23/11/2022 Contract Value: Area 2 498,38 Value Per Area % Distribution of Payment For 1 no Apartment Sr No Description % Amount 1 Framing 70% 2 Gypsum Board Fixing 25%
Framing Gypsum Board Fixing Final Finishing Total Amount
BATIMENTS LEVEL Area Amount Area Amount Area Amount % Complete ADMIN UFR GROUND F 251,30 251,30 - GROUND F 74,88 74,88 - UFR ADMIN FIRST F 79,20 79,20 - GROUND F 21,60 21,60 - INSTITUT ARACHIDE FIRST F 30,24 30,24 - SECOND F 117,72 117,72 - SALE DE COURS NOS 6 GROUND F - - GROUND F 126,72 - - RECTORAT Nº 1 FIRST F 126,72 - - SECOND F 182,52 - - GROUND F 126,72 - - RECTORAT Nº 2 FIRST F 126,72 - - SECOND F 182,52 - - GROUND F 266,54 - - HT Nº1 FIRST F 167,90 - - GROUND F 28,98 28,98 - HT Nº2 FIRST F 249,00 249,00 - SALE DE COURS - 01 GROUND F 7,20 - - SALE DE COURS - 02 GROUND F 7,20 - - SALE DE COURS - 03 GROUND F 7,20 - - SALE DE COURS - 04 GROUND F - - RESTAURANT GROUND F 168,48 - - AMPHI 250 PLACES - 01 GROUND F 7,20 - - AMPHI 250 PLACES - 02 GROUND F 7,20 - - AMPHI 500 PLACES - 01 GROUND F 53,28 - - AMPHI 500 PLACES - 02 GROUND F 53,28 - - HALL TECHNOLOY - 01 GROUND F - - HALL TECHNOLOY - 02 GROUND F 28,06 - - - - - - Grand Total (XOF) Previous Invoice Amount Current Invoice Amount