Professional Documents
Culture Documents
(F) .II 1 (1) Method Statement - Earthworks Rev.A1
(F) .II 1 (1) Method Statement - Earthworks Rev.A1
(f).ii.1 (1)
Table of Contents
1. General...........................................................................................................................................1
1.1 Purpose..................................................................................................................................1
1.2 Scope of Method Statement...................................................................................................1
2. Detailed method statement...........................................................................................................1
2.1 Sub-point 1 (Level 1)...............................................................................................................1
2.2 Sub-point 2.............................................................................................................................1
3. Appendix – 1...................................................................................................................................2
4. Appendix – 2...................................................................................................................................3
Contents Page
TOKYU-STA. CLARA JOINT VENTURE
Davao City Bypass Construction Project (f).ii.1 (1)
Package I-3, Sta. 23+500 to Sta.29+700 Method Statement: Earthworks
1. General
1.1 Purpose
2.2 Sub-point 2
2.2.1 Level 2 points
2.2.1.1 Level 3 points
Generally, Tokyu add following into the Method Statements. STA. Clara can use the same or
revise as per other DPWH projects.
Work Sequence
Equipment to be used (Please mention number of equipment, its specifications, placement
requirement, etc.)
Manpower to be used (Please mention about number of personnel, type of skill,
Organization structure, etc.)
Materials to be used
628606364.docx
TOKYU-STA. CLARA JOINT VENTURE
Davao City Bypass Construction Project (f).ii.1 (1)
Package I-3, Sta. 23+500 to Sta.29+700 Method Statement: Earthworks
3. Appendix – 1
628606364.docx
TOKYU-STA. CLARA JOINT VENTURE
Davao City Bypass Construction Project (f).ii.1 (1)
Package I-3, Sta. 23+500 to Sta.29+700 Method Statement: Earthworks
4. Appendix – 2