Palmer Construction Zimbabwe

Civil, Electrical & Electronic Engineers

Cell: +263784928928 Email: start@palmer.co.zw


+263712042555 Website: www.palmer.co.zw
Tel: +263242755904 Address: 14 Enterprise Block, Harare Showgrounds

"Permanent solution to all your construction concernS"


Architectural Drawings * Engineering Designs * Construction Services * Electrical Installations & Maintanance * Projects Management
Water Reservoirs * Solar Power * Power Backup Systems * Consultations * Roads * Driveways * Pools & Ponds * Estimates etc

Client/Project Details: 11/14/2022


Att: Tilco Industrials Zengeza 3 Chitungwiza
Address: 10472
Cell:
Email:

ESTIMATED SCHEDULE OF MATERIALS/BILL OF QUANTITIES + LABOR

Price List:

Materials USD$ Price/Unit


Solid Common Bricks $0.17 per brick
PC15 Cement $12.00 per 50kg bag
Washed Riversand $15.00 per cubic
Pitsand $12.00 per cubic
Concrete stones $38.00 per cubic
Brickforce/Reinforce wire $3.00 per 15m roll
Damp proof course/DPC $4.00 per 20m roll
50cm Hoop Iron $0.50 per piece
16mm Deformed Reinforcement steel $1.10 per meter
Links/Ringforce $3.00 per piece
Tying wire $50.00 per sheet
Termite poison $4.00 per kg
Coal rubble/ Gravel $1.00 per litre
$15.00 per cubic

TYPE OF STRUCTURE:
Mainhouse
Structure Measurements:
W230:
TOT: 22 W115: 7.5 L & B: 6
Estimated floor area:29.5 CONC-MIX:
Single bag of Cement mixing ratios 52 10.96 Courses below DPC 8
Concrete Ratio: 47.95 Courses above DPC: 35
log1: concre 6 Mortar ratio: 6
log2: brickw 5.94 1.575
log3: reinfo 176 30
1.222222222 0.416666667

Brick Type:
Cement Type: Common Brick OR any brick above 8 MPa
Grade 22.5 & above

SITE PREPARATIONS: Cost


Site clearance and preparation $147.50
Gravel $200.00
Termicide $300.00
Total $647.50

GROUND FLOOR Cost + Trans


Quantities Measure
1. BRICKWORK TO BOTTOM WINDOW (Shell) Cost + Trans
Solid Common Bricks $441.90
Pitsand 2599.3947 Bricks $56.15
PC15 Cement 4.6789105 Cubic $93.58
Brickforce/ Reinforce wire 7.7981842 Bags $29.47
Damp proof course (DPC) 9.8230903 Rolls $6.56
Total 1.6388889 Rolls $627.65
Labor $251.06
Supply & Fix $878.71

2. BRICKWORK TO TOP WINDOW Cost + Trans


Solid Common Bricks $419.80
Pitsand 2469.425 Bricks $53.34
PC15 Cement 4.444965 Cubic $88.90
Brickforce/ Reinforce wire 7.408275 Bags $19.54
Total 6.5117284 Rolls $581.58
Labor $232.63
Supply & Fix $814.21

3. LINTELS & BEAMS Cost +Trans


Concrete stones $28.50
Washed Riversand 0.75 Cubic $11.25
PC15 Cement 0.75 Cubic $36.00
16mm deformed bars 3 Bags $26.40
12 mm Ringforce/Links 24 Meters $72.00
Tying wire 24 Links $8.00
Total 2 Kgs $182.15
Labor $72.86
Supply & Fix $255.01

4. BRICKWORK TO WALLPLATE Cost + Trans


Solid Common Bricks $335.84
Pitsand 1975.54 Bricks $42.67
PC15 Cement 3.555972 Cubic $71.12
Brickforce/ Reinforce wire 5.92662 Bags $19.65
50cm Hoop Irons 6.5487269 Rolls $7.38
Total 14.75 Strips $476.65
Labor $190.66
Supply & Fix $667.32

5. PLASTERING Cost + Trans


Pitsand $95.58
PC15 Cement 7.965 Cubic $191.16
Total 15.93 Bags $286.74
Labor $114.70
Supply & Fix $401.44

TOTAL QUANTITIES FOR CONSTRUCTION


Solid Common Bricks $755.64
PC15 Cement #REF! Bricks $480.76
Washed Riversand #REF! Bags $11.25
Pitsand #REF! Cubic $247.74
Concrete stones #REF! Cubic $28.50
Brickforce/Reinforce wire #REF! Cubic $68.66
Damp proof course/DPC #REF! Rolls $6.56
50cm Hoop Iron 1.6388889 Rolls $7.38
16mm Deformed Reinforcement steel 14.75 Strips $26.40
12mm Links/Ringforce 24 Meters $72.00
Tying wire 24 Links $8.00
Termite poison #REF! Kgs $300.00
Coal rubble/ Gravel #REF! Liters $200.00
Total for Materials #REF! Cubic $2,212.88

Total for Labor $1,451.29

Total for Supply and Fix $3,664.17

Upcoming Quotations
Doors & Windows Status
Doors & Window frames Pending
Pillars Pending
Wall & Floor Tiling Pending
Glazing Pending
Roofing Materials Pending
Ceiling Pending
Skimming Pending
Painting Pending
Electricals Pending
Plumbing Pending
Septic & Soakaway Pending
Equipment Hire Pending
Material Transport Pending
Durawall Pending
Paving Pending
Security Systems Pending
Garage Roller Shutter Pending
Council Stage Inspections Pending
Swimming Pool Pending
Gym Customization Pending
Pending
NOTES:
While we endeavour to provide accurate and correct quantities, we make no warranties of any
kind about the completeness and accuracy of the the information provided.
Our estimates are mainly for budgetting and knowledge of estimated costs of projects.
As the title states estimates, we advise you do your budget with an allowance for +/- overall cost if cash jobs
The accuracy of this bill of quantities may be affected due to various reasons:
* Ground slope may seriously affect the quanties to either become an overquote or underquote
* The way materials are used may also affect the quanties if used wastefully without care.
* If cement ratios are altered from those used when preparing this B.O.Q, there is a probabity
of change in quantities
* Quantities provided are solely based on the provided plan drawings, alterations on the ground
may also affect the quantities.