ea PRECAST DURAWALL CONSTRUCTION


Enter Company Name in cell B2.
Mon, 11/28/2022
Enter the name of the Project Lead in cell B3. Enter the Project Start
Project
dateStart:
in cell E3. Project Start: label is in cell C3.
Th
1 Nov 28, 2022 Dec 5, 2022 Dec 12, 2022 Dec 19, 2022 Dec 26, 2022
e Display Week:
Ce 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1
ASSIGNED
TASK PROGRESS START END M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
ITEM TO

1 SCHEDULE OF WORKS
Ce
1 ll Site Establishment Palmer Construction 0% 11/28/22 11/30/22

2 Site Clearance Palmer Construction 0% 12/1/22 12/2/22


R
3 Excavation Palmer Construction 0% 12/3/22 12/7/22
o

4 Pillars Palmer Construction 0% 12/8/22 12/15/22

5 Durawall panels Palmer Construction 0% 12/16/22 12/26/22

6 Site handover Palmer Construction 0% 12/27/22 12/28/22