Gama for Trading & Contracting Co.

Risk Assessment
Unilever Project
Gama For Trading and Contracting Co.
‫شــــــركــــــــــــة جــــــــــــامـــــا للتــجارة والمقــــــــاوالت‬
RISK ASSESSMENT

Initial Risk
Activity

(With existing Residual Risk


Job Steps Health and Safety Hazards Effect controls) Control Measures
Risk Risk
S P R S P R
Level Level
Ensure all
necessary permits Miscommunication resulting in Asset /  Supervisor/ Foreman to discuss with discipline
are approved incorrect work type and duty equipment / 2 2 4 L supervisor(s) what works requirements are needed 2 1 2 L
prior to starting being built personal for the tasks to be performed
work.
Survey works

 Safe access and egress will be provided and an


established safe route will be designated by the
foreman.
Survey works in  Employees must maintain alertness at all times
Slipping and tripping hazards Personal 3 3 9 M 3 2 6 L
ground level  Maintain job cleanliness on a daily basis in order to
prevent tripping,
 Hard hat and other appropriate PPE must be worn
and used.
 Safety harnesses and lanyards to be worn and
Survey works in Personnel/
Falling from Height 3 3 9 M lanyards tied off to an adequate anchorage at all 3 2 6 L
heights equipment
times.

Severity (S) Values: 1-5 Probability (P) Values: 1-5 Note: Use the RAM when determining the values of S and P
Risk (R) = S x P Risk Ranking: 1 – 6 = Low (L) 8 – 12 = Medium (M) 15 – 25: High (H) Page 2 of 2