Document Submittal Form

Project Name : Dammam Water Quality Improvement Project South Strategic Network & Reservoires Dammam-5
Project Code : 12828 Reference : WQIP-D5-AWP-T-0153
Consultant : ILF Consultant Engineers Revision : V0
Contractor : Alkhorayef Water & Power Technologies Date : 30-Oct-22

This section to be filled by contractor


Document Description
701220077-4-AWP-DAMAM5-GI-MST-000032-VIBRO Replacement (Stone Columns) for Central Reservoir Dammam-5
Mthod Statement of Ground Improvement

Document Type : Method Statement


Area of Application : Soil Improvement BoQ Item : N/A Discipline : Civil
Drawing Reference : N/A Specs. : N/A Standard :
Enclosure (No of Pages) : 63 No of Copies : 1

We certify that the document mentioned above is in accordance with the Contract Specification and Approved Drawings.

Name: M USMAN Position: QA/QC Signature: Date: 30-Oct-22

This Section to be filled by Consultant


Consultant's Comments :

Action

Approved As Submitted Approved Except As Noted Cancelled

Disapproved - Resubmit Receipt Acknowledge

Name: Position: Signature: Date:

Acceptance does not relieve the contractor from his responsibility and liability concerning compliance with the contract requirement.

All dates to be entered in format: dd/mm/yyyy


PMF-014-COM-005_02 Document Submittal Form 1 of 1
KINGDOM OF SAUDIA ARABIA

Project Name
Water Quality Improvement Project-South Distribution
Network & Reservoirs-Dammam Project 5

Main Contractor
Alkhorayef Water & Power Technologies

DOCUMENT TITLE:
VIBRO Replacement (Stone Columns) FOR Dammam Central RESERVOIR

0 30-10-2022 First Submission MAS MSN MSN AEN


Rev. Date Submission Prepared By Reviewed By QA/QC Approved By
CONTRACTOR CONSULTANT: Project No.: 701220077
701220077-4-AWP-DAMAM5-GI-MST-000032 Rev. 0
Ground Improvement for Central Reservoir, Al Khobar, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 1 of 80

VIBRO Replacement (Stone Columns) FOR Dammam Central RESERVOIR, Dammam


THE KINGDOM OF SAUDI ARABIA

Prepared For;

Project Client Project Contractor

This document is property of Geoharbour. Its total or partial reproduction is strictly forbidden by any means,
as well as its distribution to third parties without the express written consent. Any copy of this document in
digital or paper support will be considered a not control copy. The only valid copy is the last one approve
located in the document manager tool.

Oct 24, 2022

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Al Khobar, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 2 of 80

Revision control sheet

Description of the revision


Revision Date Elaborated by Revised by Approved by
and changes

Rev.00 27-10-2022 Issue for approval Qian Kun LJ Xuliang

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Al Khobar, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 3 of 80

CONTENTS
1. Purpose ....................................................................................................... 6

2. Scope .......................................................................................................... 6

3. Project Overview.......................................................................................... 8
3.1. Subsurface formation ....................................................................................... 9
3.2. Ground Water Condition .................................................................................10

4. Reference .................................................................................................. 10

5. Work Procedure ......................................................................................... 11


5.1. Site Survey and Temporary Bench Marks ...................................................... 11
5.2. Setting out of Column Locations ..................................................................... 11
5.3. Water Supply System ..................................................................................... 11
5.4. Vibro-Replacement Techniques-Wet Method .................................................12
5.5. Working Platform Layer (WPL) ....................................................................... 12
5.6. Load Transfer Platform (LTP) ......................................................................... 12

6. Operation Condition ................................................................................... 13


6.1. Construction Personnel ..................................................................................13
6.2. Machinery, Equipment and tools ....................................................................14
6.3. Material ..........................................................................................................14

7. Roles and Responsibilities ......................................................................... 14


7.1. The Project Manager ...................................................................................... 14
7.2. Project/Site Engineer...................................................................................... 15
7.3. The Site Surveyor ..........................................................................................15
7.4. The Supervisor ...............................................................................................15
7.5. The QA/QC Engineer ..................................................................................... 15
7.6. The Safety Officer ..........................................................................................16

8. Quality Control by Testing ......................................................................... 16

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Al Khobar, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 4 of 80

8.1. Post-Treatment Testing by Zone Load Test (ZLT) ..........................................16


8.2. Post-Treatment Testing by Plate Load Test (PLT) ..........................................16
8.3. Post-Treatment Testing by Cone penetration test (CPT) ................................16

9. Attachment ................................................................................................ 17

Appendix 1: Daily Report Form ...................................................................... 18

Appendix 2: Risk Assessment for Stone Column Works................................ 20

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Al Khobar, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 5 of 80

Abbreviations:

Owner NWC

Consultant ILF

Main Contractor Al Khorayef

Subcontractor GEOHARBOUR SAUDI ARABIA CO LTD

RFI Request for Inspection

ITP Inspection and Test Plan

MS Method Statement

NCR Non-conformity Report

GL Ground Level

PPE Personal Protection Equipment

CPT Cone Penetration Test

PLT Plate Load Test

ZLT Zone Load Test

SC Stone Column

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 6 of 80

1. Purpose
This method statement of construction of Stone Columns is proposed for Central Reservoir, Dammam, KSA. It
is prepared on the basis of data collected from the site as per soil condition of current site and gives an indication
of our general approach to the construction and management of the project.

In this method statement, we state our intentions for managing and supporting the project and the specific
approach that will be taken for certain key aspects. The main content includes the requirements, materials,
equipment and HSE regulations for works.

2. Scope
This document outlines the methods, required materials, equipment and quality control standards to be
performed in all operations during Stone Column construction works for Central Reservoir, specifically for two
water storage Tanks, KSA.

Stone Column extends the range of soils which can be improved by vibratory techniques, including cohesive soils.
Reinforcement of the soil with compacted granular columns or “stone columns” is accomplished by the top-feed
method. Stone columns are cylindrical columns made below ground level which is comprised of granular material
of large sizes varying from 20 to 100 mm and the small size (<20mm) content less than 10%. A hole is made in
the soft deposit by different techniques and then filled with stones in layers and compacted to form the complete
column. When a structure is placed over the area treated by stone columns, majority of the load could be borne
by stone columns. In this case, the diameter of stone column is 900 mm.

As a way forward, the testing method as indicated and is expected to demonstrate the following:

Settlement: over 25 years


Post-hydrotest
Maximum allowable settlement for Tank at center is 110mm
Maximum settlement for Tank edge is 50mm
Maximum differential settlement along ring beam is 13mm over 10m distance
Load is 260 kPa
A sketch of the vibro-replacement stone column is shown in Figure 1.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 7 of 80

Figure 1: Sketch description of Vibro-Replacement

This method suitable for vibratory techniques refer to Figure 2 as below.

Figure 2: Soils Suitable for Vibratory Techniques

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 8 of 80

Fig.3 SC Construction photos by Geoharbour

3. Project Overview
The project is located in Al Khobar, Eastern Province, Kingdom of Saudi Arabia and consists of two steel tank each
50m diameter, height 23.7m in addition to other facilities.

Figure 4: Location of project site

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 9 of 80

3.1. Subsurface formation


The subsurface soil information as provided by Al Khorayef consists of the following:

1) Fill layer consists of rubbish, silts, sands and gravel (this shall be cleaned by
MC)
2) Loose to medium Poorly graded SAND
3) Fractured limestone
4) Medium dense to dense poorly graded SAND
5) Hard Elastic Silt

Tanks 1 & 2

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 10 of 80


In addition to the boreholes, Pre-CPT testing will be performed to confirm soil conditions at each Tank. This pre-
CPT will be done using crawler CPT machine model 2021 as shown below.

Figure 5: CPT Machine

According to the soil condition and acceptance criteria, Stone Column would be the optimal improvement
technique in this area to enhance the soil stiffness thus to increase bearing capacity, reduce the post construction
settlement and reduce the potential of liquefaction (if any)

3.2. Ground Water Condition


As per the soil investigation report, the ground water condition is at around 5m below existing ground level.

4. Reference
 Layout Drawing provided by Al Khorayef
 Ground investigation report prepared by SAFCO of ref: KSM-4458

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 11 of 80

5. Work Procedure
The sequence for stone column works shall be found below.

5.1. Site Survey and Temporary Bench Marks


The main contractor shall establish the benchmarks at convenient locations well clear of the working area and
protected to allow for aggregate stockpile and movement of loader to and from the stockpile. Surveying will be
done by GPS.

5.2. Setting out of Column Locations


Locations for Stone columns shall be set out in accordance with shop drawings prepared by GH and approved by
consultant. Stone columns are arranged so as to accommodate varying combinations of load and foundation
configuration.

Steel pegs approx. 80 cm long shall be used to mark a Probe location and shall carry a tag identifying the Probe
number at enough intervals. Tolerance for coordinates will be not more than 200 mm.

5.3. Water Supply System


As water is required throughout the process of vibro replacement wet top feed method, a water source within
close distance to the working area is utilized. The establishment and operation of a temporary water supply to
service the vibro works shall be nearby water source or well point system or deep well system. The water is
pumped into a storage tank first then goes back to the ground through water jetting (tubes attached to the
vibrator). No foreign matter is added to the water thus ensuring “no contamination” of the water.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 12 of 80

5.4. Vibro-Replacement Techniques-Wet Method


For this project, GH will apply wet method

The essential equipment for this process is a vibrator – a long heavy tube enclosing eccentric weights driven by
an electric motor. The vibrator is connected to a source of electric power and a high-pressure pump with
following capacity Q=120 M3/hour. Extension tubes are added as necessary and the whole assembly is
suspended from a crane.

With the electric power and water supply switched on, the vibrator is lowered into the ground. The combination
of vibration and high-pressure water jetting causes liquefaction of the soils surrounding the vibrator that assists
in penetration.

Following penetration of the vibrator and its withdrawal after reaching the required depth the resulting cavity is
filled with coarse-grained materials (stone). This supply of material is itself in turn compacted. A stone column is
thus formed in which the stone is laterally pressed into the soil. The stone column and the in-situ soil form an
integrated system having low compressibility and high shear strength. The excess pore water can readily dissipate
through the stone columns that act simultaneously as drains. For this reason, settlement occurs faster than
normal in cohesive soils.

An indication of the effectiveness of the treatment is the quantity of backfill material used. Other control
procedures are available, such as load or penetration tests.

5.5. Working Platform Layer (WPL)


Working Platform layer will be provided by main contractor, safe and stable for work. WPL shall be above ground
water level: min. 1 m for the wet method. However, if ground water table is far from working platform level
and the ground is stable, then no need WPL.

5.6. Load Transfer Platform (LTP)


After installing the stone columns, cleaning for the top of columns and roller compaction shall be done for the
column’s heads, then, a minimum of 50 cm layer shall be provided on top of stone columns, filled with
engineering fill and compacted into two layers compacted up to 95% MDD (maximum dry density) before placing
the ring beam foundation. A Cross section for the LTP with the stone columns will be provided in design report.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 13 of 80

6. Operation Condition
6.1. Construction Personnel
Single or extended shift are considered for ground improvement works; the proposed manpower is listed in the
below table.

Table 1. Manpower Plan

Management

Item Personnel Quantity

Corporation Managers

1 Project Director 1

2 Technical Director 1

3 Corporate/Legal Director 1

4 Commercial Director 1

Project deportment managers

1 Project Manager 1

2 Site manager 1

3 HSE Manager 1

4 Document Controller 1

5 Safety Officer 1

6 Logistics 1

7 supervisor 1

Sub-total 11

Labor

1 Technician 2

2 Crawler Crane Driver 1

3 Loader Driver 1

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 14 of 80

4 Welder 1

5 Auxiliary Workers 3

6 Electrician 1

7 Maintenance 1

Sub-total 10

6.2. Machinery, Equipment and tools


The Main equipment:

 Vibrator with power 75 kw - 10 Nos


 50-ton Crawler Crane – 1 Nos
 Generator with power 250 - 300 kVA – 1 Nos
 Generator with power 50 kVA – 1 Nos
 Loader - 1
 Tower Light – 1 (if needed)
 Accessories like hoses.

6.3. Material
The material shall be suitable for the ground conditions for the ground conditions in which the stone columns
are formed and have no adverse effect on other work on the site. Grading shall be a nominal single-size material
within the range of 20mm-100mm and small size (<20mm) content less than 10%.

7. Roles and Responsibilities


7.1. The Project Manager
 Planning the activities
 Organizing a project team to perform work
 Delegating the teams
 Controlling time management
 Controlling project quantity management
 Monitor progress
 Establish Regular Meetings

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 15 of 80


 Communicate a vision with the team
 Managing reports and necessary documentation

7.2. Project/Site Engineer


 Provide the necessary information (Method Statement & Risk Assessment briefing), material, equipment,
and machinery to his team to carry out the job.
 Ensure all related approvals and NOCs are provided to the site supervisor.
 Preparation of cross section as per the existing site condition and providing a copy to site supervisor.
 Ensuring Work execution is being carried out as per project specifications and approved method of
statement.

7.3. The Site Surveyor


 Execute daily survey field tasks according to the procedures of the Survey Department.
 Perform setting-out tasks and as-built survey tasks as assigned by the Chief Surveyor.
 Prepare survey data and sketches in the proper format for transfer/ handover of information.
 Ensure that the workers under his command fully understand the procedures and hazards involved in the
job.

7.4. The Supervisor


 Ensure that the workers under his command fully understand the procedures and hazards involved in the
job.
 Making regular checkups ensuring all machinery and equipment related to the activity are working
properly.
 Regularly checking of the operation and ensure the work conditions are safe.
 Ensure adequate cool drinking water, toilets, rest areas are available for workers at site.

7.5. The QA/QC Engineer


 Conduct inspections and monitor the required tests as per the relevant Method Statement and ITP.
 Ensure that personnel are fully aware of the quality requirements relevant to their discipline and work.
 Regularly pay site visits to ensure that all the procedures in the Method Statement and ITP are
implemented.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 16 of 80


 Ensure that all necessary r190rds such as Inspection Requests and calibration records for survey
instruments are in-place prior to commencement of work.
 Ensure that properly documented quality records are maintained as per established Method Statement,
ITP.
 Determine and report any non-conformance to the QC Manager and the process owner.

7.6. The Safety Officer


 Ensure that all construction team members are aware of the requirements of PSSP & Risk Assessment for
the task.
 Provide the required HSE induction& Risk Assessment briefing.
 Regularly pay site visits to ensure that safety is being exercised at site as per requirement.
 Report to the Construction Manager or his designers any infraction of safety procedures.
 Promptly report accidents, incidents and near misses to HSE Manager.
 Ensure suitable provision of drinking water, toilets, rest areas and first aid.
 Stop all unsafe work activities

8. Quality Control by Testing


8.1. Post-Treatment Testing by Zone Load Test (ZLT)
Two (2) Zone Load Tests will be performed, one in each tank to reflect the overall effect of ground replacement
solutions. Zone Load Test may be performed on a group of stone columns to verify the bearing capacity of
composite of stone columns and its surrounding area. Zone load test requires a big set up and is performed on a
selected area of ground treated by stone columns. A reinforced concrete bearing plate of 3.0×3.0m shall be used
and loaded up to one time of the required bearing capacity.

8.2. Post-Treatment Testing by Plate Load Test (PLT)


Plate Load Tests shall be performed for quality control purposes on stone columns selected by the Client or his
representative. In this test a steel plate with 0.76m Dia. shall be loaded up to 3 times design bearing pressure.
For this ground improvement scope, total 12 PLT tests are proposed.

8.3. Post-Treatment Testing by Cone penetration test (CPT)


CPT shall be performed for quality control purposes on stone columns selected by the Client or his representative.
Five (5) post-CPT in each tank will be performed for liquefaction check.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 17 of 80

9. Attachment
 Appendix 1: Daily Report Form
 Appendix 2: Risk Assessment for Stone Column Works

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 18 of 80

Appendix 1: Daily Report Form

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 19 of 80

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 20 of 80

Appendix 2: Risk Assessment for Stone Column Works


Initial risk Residual risk
ALARP
…? ALARP…?
Expected Recommended If no ..? Responsible
Sr. Work Activities Hazard / (as low (as low

Likelihood
consequen remedial actions / ADDITIONAL department /

Risk rate
Severity

Likelihood
nor in sequence Hazardous event as as

Risk rate
ce/ risk control measures CONTROL MEASUREES person

Severity
possibl possible)
e)

1 Mobilization of Lack of Personnel 3 4 12 Must and should 2 4 8 NO Competent YES GEOHARBOUR


new personnel experience injuries, (H completed with the (M personnel’s should
to workplace. major ) induction prior to ) only be allowed to
Unawareness injuries. mobilize the enter/work at site .
of site personnel into
conditions workplace Provision of
suitable and
Unawareness Specific H.S.E sufficient personnel
of access egress training should be protective
conducted equipment to all the
Unawareness regarding site rules personnel’ prior to
of emergency and emergency enter into the site.
routes . protocols ( fire exits
, assembly points , All personnel’s to
first aid locations ) be issued with a
etc copy of the project
HSE instruction
sheet , risk

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 21 of 80


Pre planning of task assessment prior to
assigned based on project
experience commencement.

Constantly monitor
and frequent
consultation for
assign duty
including the
provision of
competent
supervision.

Avoid lonely
working for
new/young
appointed workers

Conducting Pre
start briefing , tool
box talks and H.S.E
training for
personnel to adopt
the necessary site
safe practices and
procedures

Awareness training
of access/egress,

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 22 of 80


pedestrian
walkways , welfare
facilities and
emergency routes.

2 Mobilization of Collision with Personnel 4 3 12 Safety induction , 2 3 6 NO Installation of radars YES GEOHARBOUR
tools and other vehicles minor equipment / tool and visible signage’s
equipment to or earth injuries , inspection prior to showing speed limit
the work place moving electrocuti enter any personnel of 20kmph .
machinery / on , , equipment or tools
equipment Major into the work place Installation of goal
injuries , posts if any
Hit by / struck Fatality , Supervisor/foreman overhead power
by moving Property to monitor the work lines .
pedestrians damage , force vigilantly for
moving vehicles and Segregation of
Trailing / pedestrians pedestrian
overhead walkways and
cables / wet Ensure that the area vehicle routes.
ground is clean and safe for
work with adequate Provision of well
Failure to lighting prior to compacted and
follow site safe mobilize the leveled ground for
access & egress equipment off loading materials
/ speed limits .
Machinery must be
Over speeding securely anchored
of loaded to the van / trailer
trucks.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 23 of 80


floor when in transit
.

The Crane hooks to


be fitted properly
and should be
clamped

Ground to be
securely plane and
compact to the
crane when the
machinery or tools
is being mobilizing.

Ensure / avoid the


over head cables
while mobilizing the
equipment.

Personnel’s are
trained regarding
the site safe access
and egress and
speed limits to
avoid accidents

The Area shall be


barricaded.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 24 of 80


proper sign boards
shall be installed to
indicate the hazard

3 Assembling Failure of Personnel 5 4 20 Moment and 2 4 8 NO Ensure safe working YES GEOHARBOUR
and loading and minor positioning of crane load must be
dissembling of unloading of injuries , (H must be sited in (M indicated on the
) )
cranes machinery/equi Major well compacted crawler crane .
pment or tools injuries , surface away from
Fatality , other structures and Crane shall be
Failure of lifting Property excavated areas . tested and
equipment and damage examined by a
accessories Assembling / competent 3rd party
dissembling area examiner in
Collision with must be barricaded accordance with the
other and installed statutory
equipments signage to requirements.
and nearby indication Before these tests
structures. and examinations
Crane must be are carried out,
Fall from height mounted /
, being struck dismounted and Inspect and color
by p plant / configured by code of all
machinery adequately trained accessories used to
and competent loading and
persons unloading of

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 25 of 80


equipment and
Prior to crane tools
operation it must be
with correct ballast Ladders and safety
and counter harness are
balanced as per the inspected and color
manufactures coded for safe use .
manual instruction

Crane must be
erected and jib set
up accordance with
the manufacturer's
Instructions, Care
should be taken to
ensure that the jib
sections are
assembled in their
correct order and
relative positions.

it is recommended
that a visual
inspection of the
crane be made by
the competent
person supervising
the erection.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 26 of 80


Proper conditioned
and inspected crane
should be used to
load or unload the
parts.

Ladders and fall


arresters (safety
harness), should be
used while working
at height

Lifting of boom Cuts, 3 3 9 Crane and all lifting 2 3 6 NO Provision of harness YES GEOHARBOUR
4 Boom sections Bruises, accessories belts and fall
Assembly Crushing ( inspected and (M arresters for the
M )
Falling pins, hands, certified by workers working at
hammer and Broken ) government- height.
Fixing pins and hand tools bones, accredited 3rd party
bolts for from height Personal inspector. Provide suitable
connecting injury, portable ladders to
boom at height Personnel Fall Property Crane operator with easy access to the
from height damage valid license and 3rd boom for fixing the
party assessment pins or bolts
Lifting roof Mechanical certificate.
beams, failure
Lifting angle Crane inspection
bracing. checklist filled up
Lifting purloins. (including crane

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 27 of 80


Failure of lifting suitability for the
equipment and lift, crane condition
accessories & lifting gear).

Slinging of loads
only by certified
rigger/slinger and
tag lines available.

Ensure temporary
guys/bracings are
securely anchored.

Supervisor to
monitor and
supervise lifting
activity.

Only trained and


experienced rigger
on the job.

Exclusion zone and


warning signs
around working
area.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 28 of 80


Activity to stop if
wind speed reaches
35 kmph.

Job rotation and


provision of
hydrating liquids.

Collapse of 6
5 Assembling 3 3 9 Tagline should be 2 3 NO A supporting mobile YES GEOHARBOUR
materials due
vibro cat Personnel used to handling the crane should be
to lack of un (M
equipment to injury, ( ( vibro cat while provided while
stable ground )
the crane minor / M fixing , assembling the
level ,
major ) ) No personnel’s are vibrators to support
Fall of vibro cat Electrocuti allowed n the radius lifting the vibrator .
while lifting on , of crane .
Over turning of property Provide a suitable
equipment due damage. All work to be rope or belt for
unstable completed under tagline to control
ground or the guidance and the handling of load
improper control of the Crane .
signaling Lifting supervisor.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 29 of 80


Under any Trained and
Fall of persons
circumstances “NO certified technicians
or materials
MOBILE PHONE” are allocated for
while fixing
during fixing the vibrators.
vibro cat
operation.

Ground conditions
to be assessed by
crane driver and
Crane

Lifting supervisor
and signed off by
Crane Lifting
supervisor prior to
set up

Crane to be checked
in accordance with
legal requirements

Driver to check
safety system daily
using checklist.

Trained and skilled


technicians are only
allowed to work to
fix the vibrators .

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 30 of 80

Workers personnel
protective
equipment should
be ensured prior to
work ( hand gloves
hard hat , high
visible west , safety
shoes and if nay
required rubber
gloves )

Vibrocat cables
should be secured
and handled
properly while
installation process

6 Lifting of cat Hit persons Severe 4 2 8 Technicians are 2 2 4 YES YES GEOHARBOUR
vibrator near by personnel advised to securely
injuries , ( fix the cat vibrator
Hit equipment Fatality , M to the crane hook
or structures Property ) and lock properly .
around. damage.
A supporting tagline
should be used to
control the load to
avoid hitting men

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 31 of 80


material or
structures.

Operators are
advised to lift the
vibrators slow and
move smoothly
without jerking to
avoid collisions .

Surrounding areas
to be barricaded ad
installed with
warning signs to
prior to lifting.

Certified operators
and riggers only
should be allowed
to the workplace ,
all others are
restricted to come
around the working
radius of crane.

7 Installation of Electrical Electrocuti 3 4 12 Ensuring proper 1 4 4 YES YES GEOHARBOUR


Generators , hazards on , earthling is given to
water pumps , and manual electric all the generators ,
electrical handling burns ,

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 32 of 80


panel boards skin burns electrical DBs ,
,and , fatality , panel boards .
Electrical DBs fire and
property Ensuring the Fire
damage. extinguishers are
placed at the work
place and available
closer to workers.

Workers are asked


to use gum boots
and dry rubber
gloves to avoid
electric shocks

Experiences
electrician /
technicians are
appointed to carry
out the activities .

Avoid storage of
water for long time

All the cables are


secures and
protected from the
water and sunlight

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 33 of 80


to avoid property
damage.

8 Delivery of Collision with 2 4 8 Pre task tool box 1 4 4 YES GEOHARBOUR


stones by other vehicles , Minor / ( talk with the truck
heavy trucks major m operators .
Overturning of personnel )
vehicles . injuries Implementation of
Property site traffic rules
Non damage properly .
compliance by
speeding truck Installation of speed
reducing signage .

Implementation of
one way routes to
avoid collisions

Allow well
maintained trucks
and competent
operators for safe
delivery.

9 Setting survey Slip /trip & falls Minor 2 3 6 Work procedure 1 3 3 YES YES GEOHARBOUR
point & on uneven personnel and safety
installation of ground. injuries measures to be
communicated with

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 34 of 80


rebar for Damage to Property the surveyors and
markings. survey damage others personnel
equipment. working for survey.

Rebar caps /
reflecting caps
should be installed
on rebar to warn
others falling on
that.

Advising for proper


implementation of
Personnel
protective
equipment.

Placing all the


survey material
properly in a good
arrangement to
avoid property
damage

10 Crane Rigging Fatality 4 4 16 All work to be 2 4 8 NO Riggers , operators , YES GEOHARBOUR


operation failure – lifting completed under supervisors and

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 35 of 80


tools and Serious the guidance and people working with
tackles / body control of the Crane crane should be
crane injuries Lifting supervisor. certified by the third
collapse Fractures/ party prior to start
amputatio Under any the work .
ns circumstances “NO
MOBILE PHONE” Crane , cat vibrator
during and all other
Operation. equipment used for
stone column
Crane to be checked should be inspected
in accordance with and certified by
legal requirements third-party prior to
work .
Driver to check
safety system daily
using checklist .

Load charts MUST


be in cab of crane.

Lifting slings/gears
to be inspected
daily by user and
thoroughly
examined 6-
monthly by
competent person
including the use of

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 36 of 80


Spreader bars.

No unauthorized
person should come
around / beneath of
the crane radius .

Should not lift any


load which is
exceeding the safe
working load.

Check for the firm


ground to park /
place the crawler
crane prior to start
work .

Regular
maintenance should
be done to the
crane for safe work .

11 Moment of Collide with Minor / 3 4 12 Daily maintenance 2 4 8 NO Third party YES GEOHARBOUR
shovel / wheel workers , other major of pre use checklist certification for the
injuries for the equipment. operator and flag

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 37 of 80


loader for equipment and and man should be
leveling structures. property Certified / ensured by the
damage competent engineer prior to
Overturning of operator should be start the work.
equipment by allowed to work
uneven surface with the equipment. Maintenance of
or harsh equipment should
operating. A flagman should be be arranged
appointed to signal regularly for safe
the operator to movement of
avoid collisions. vehicles.

Check for the


reverse alarm ,
beacon lights ,
warning lights and
horn prior to start
the work.

Tool box talk , pre


task briefing should
be done for the
workers working
with the moving
machinery to avoid
accidents.

Barricading and
signage should be

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 38 of 80


installed to warn
the unauthorized
persons entering
into the site .

12 Stone column Collapse of Minor / 3 4 12 Safe distance shall 1 4 4 YES Ensure that auxiliary YES GEOHARBOUR
works ground major be maintained to safety devices are in
personnel avoid contact with place and in good
Damage to injuries vibro Probe. order.
hearing Property
damage Water barriers shall Load charts MUST
Loss of stability be provided to be in cab of crane.
avoid contact with
Bursting of vibro at least 5 Loads must not be
water pipes meter near the suspended by the
and electrical center of crane. crane if unattended.
wires
Ear plugs shall be Crane
Noise and provided to must be
vibration decrease the effect immobilized when
of noise. left unattended.

Noise survey shall


be provided.
Conduct safety Lifting slings/gears
communication and to be inspected
TBT before starting daily by user and
the activity, Ensure thoroughly
examined 6-monthly

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 39 of 80


stable ground for by competent
the crane. person including the
use of
A tagline should be spreader bars.
installed to control
the vibrators to
avoid collision with
another structures

13 Manual Loading Minor / 3 3 9 Where appropriate 2 3 6 NO Provide manual YES GEOHARBOUR


handling unloading of major ( rotation and breaks handling aids for
materials Slips personnel m of repetitive work. lifting heavier loads
,trips & fall injuries ) Correct manual that cannot lift by
Property handling themselves
damage techniques.
Manual handling Provision of suitable
assessment and sufficient
completed for high personnel
risk tasks protective
equipment for the
Communicate safe persons involved in
manual handling manual handling
procedures through works
Tool box talk to all
workers who is
involved in the job.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 40 of 80


Encourage team
lifting where
appropriate
Provide training in
safe manual
handling techniques

Personnel shall not


exceed their own
lifting capacity
Avoid awkward
postures or
repetitive tasks, or
take
frequent breaks.

Keep the load close


to your body.

Check the load for


stability and look
out for sharp edges.

Don’t twist your


body, use your feet
to change direction.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 41 of 80


Hot works Flying particles 3 4 12 Safety Goggles / Full 2 4 8 NO Inspection of YES GEOHARBOUR
14 Cutting and Electrocuti face visor shall be grinding machine
removal Fire on worn while at work. before the job
Personnel started as per
Maintenance Overexposure injury Safety glass shall project check list
works to Fumes Skin burns also be worn
Property underneath a face Periodic inspection
Inadequately damage visor. of grinding machine
mounted and recording.
grinding disc. Provide Fire
blanket/Fire Grinding area shall
Electric shock retardant tarpaulin. free from any
combustible
Grinding machine material
must be available
with the dead man RPM of grinding
switch. wheel should be
more than the RPM
Cable shall be tied / of grinding machine.
secured /overhead Only certified and
if possible to valid grinding wheel
remove the tripping shall be used.
hazard.
Ensure proper
cable management Only trained /
to be implemented. certified personnel
shall be permitted
to change discs.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 42 of 80


Fire extinguisher
kept nearby hot
work area.
Fire watcher shall
be present during
the Hot work time.

Grinding/cutting
machine operators
shall ensure that
they wear suitable
respiratory
equipment’s.

Personnel shall
ensure that all discs
are adequately
fitted to grinders.

All electrical
connections should
be routed through'
ELCB of 30 mA.

Use low voltage


(110V) operated
portable power
tools

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 43 of 80

15 Work at height Slip 3 3 9 2 3 6 NO All ladders should Yes GEOHARBOUR


Will use full body
Trip Injury and be inspected and
harness and will
Falling from fatality color coded
attached to stable
height due to due to according to the
hooking points.
non-availability falling project HSE
of hooking from regulations
points and height, All full body harness
inadequate will be inspected by Certified and
edge 3rd party to ensure competent persons
protection it is safe to use should only allow to
work at height.
Unsafe Ladder Life line to be tied
Access or to hook the harness
Scaffolding in case of non- All aspect will be
access availability of strong checked including
points. the stability of the
Material falling ground and as per
from height the work activity.
All working platform
Non availability will be inspected
of strong point regularly by a
for harness competent person.
hooking
Unsafe access Inspection tag will
and egress be in place.
TBT and task
specific briefing will
be given daily

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 44 of 80


before the works
starts

Adequate
supervision at all
times

All tools will be tied


up with lanyard to
avoid from falling.
No storing of
unwanted materials
in the working plat
form and area of
work will be
excluded to ensure
no one will work or
closer to the area.

Life line to be tied


to hook the harness
in case of non-
availability of strong
points.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 45 of 80

Noise/vibration 8
16 Using Power 3 4 12 roper guards must 2 4 NO Cable management YES
/dust/ electrical injury,
tools be in place should be
hazards breathing
maintained while
problem, Competent persons
cuts/tears working with power
exposure for the job role.
sprains etc tools.
to high Adequate
Electrical organic supervision.
shocks and Power tools
vapors,
burns checklist to be
fire,
Adequate provided at
dermatitis
Illuminating source. workplace and
Induction and maintain it everyday
training
Special training for
the fresher
Appropriate
working platform
Remove all trailing
cables from access.
Proper PPE
All power tools
should be inspected
by competent
person and color
coded prior to work
Damaged and not in
use equipments
should be

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 46 of 80


immediately
removed from the
site

Dehydrati 3 3 9 Individuals that may 2 3 6 NO Shaded rest area YES GEOHARBOUR


17 Heat stress Injury due to on, be affected are will be provided. .
the fall sunburn, educated about
heat recognizing the Workmen will be
stroke, early signs of heat trained to identify
faints stress. symptoms of heat
stroke/ heat stress.
Consider
rescheduling Job rotation shall be
activities to cooler considered.
times of the day. Check urine color
(The sun is at its frequently
strongest around
midday) individuals
to keep themselves
hydrated – drink
plenty of water.

Free access to cool


drinking water is
available.
More frequent rest
breaks and shaded
rest areas are
provided.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 47 of 80

individuals to wear
a hat and
appropriate clothing
to help protect from
UV rays

18 Weather Unstable Injury 2 3 6 Stop work during 1 3 3 YES GEOHARBOUR


conditions climate from foul weather- wind
falling exceed 25kmph
from Where possible,
height, external work is
flying postponed to be
debris undertaken at a
later date when
safety will not be
compromised.

No working at
heights externally
takes place
Consider
rescheduling
activities.

More frequent rest


breaks are provided
in order to relax
tired muscles.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 48 of 80

Appropriate
clothing is worn
Means of services
back up are
considered in case
of power failure.

Weather forecasts
are checked and the
Environment
Agency
If premises are
located within an
identified flood
zone.

An emergency plan
is in place.
Provisions are in
place to protect
services to
premises.

Weather should be
checked and
reported every time
and should not
allow any activities

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 49 of 80


in bad weather
conditions

Environmental Hearing 2 2 4 Appropriate hearing 1 2 4 YES YES GEOHARBOUR


19
compliance Noise exposure loss protection to be
Oil spill Ground worn ex. Ear plug
Loss control contamina and ear muff
Dust tion
Injury Ground protection
from the by drip trip trays or
fall plastics covering
Respirator sheet
y
Drink plenty of
water at least one
bottle of water at
each hours

Rest room to be
provided

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 50 of 80


Appropriate rest to
be taken as per the
requirements

Supervisor/foreman
to be monitors the
team accordingly

Appropriate dust
mask to be worn as
per the task
requirements

Dust Respirator 2 3 6 All waste shall be 1 3 6 YES YES GEOHARBOUR


Noise y issues kept and disposed
Sharp solid Hearing safely.
waste materials issues
Vehicle Injuries All waste shall be
Housekeeping movement Body pain removed each day.
and carting Property Provide sufficient
20 away damage people for house
unwanted keeping.
waste
Portable garbage
SKIPS should be
provided to collect
the workplace
waste

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 51 of 80


Skips should be
separate and
segregated for good
housekeeping

All should adequate


Personal Protective
Equipment.

Equipment Skin burns 2 4 8 Maintain diesel 1 4 4 YES YES GEOHARBOUR


failure. Fatality supply vehicle
Property regularly
Oil spills damage
Environme Competent and
Fire explosions ntal authorized persons
impact are allowed to
Diesel refueling activities
transportation
21
and handling Follow the local
government
regulations for
handling the fuel

Smoking should be
strictly prohibited in
areas of refueling

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 52 of 80

Fire explosion Fire burns 3 5 15 A double mounted 2 5 10 NO Should follow safety YES GEOHARBOUR
and oil spillage , diesel tanks should Rules and
Fire be installed for regulations of
explosions storing the oil and government
, fuel. regarding storage of
Fatality highly flamed fuels.
Environme Dip trays should be
ntal provided for the Third party certified
impact storage tanks to fuel containers are
Fuel and oil
22 control the spillage only to be used at
storage
which effects soil the workplace.
contamination.

A spill kit should be


provided to cleans
in the spill event .

Sufficient fire
extinguishers to be
provided

Vehicles Collide Minor / 3 4 12 Daily maintenance 2 4 8 NO Third party YES GEOHARBOUR


with workers , major of pre use checklist certification for the
Leveling the
other injuries for the equipment. operator and flag
23 ground
equipment and and man should be
structures. property Certified / ensured by the
damage competent engineer prior to
operator should be start the work.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 53 of 80


Overturning of allowed to work
equipment by with the equipment. Maintenance of
uneven surface equipment should
or harsh A flagman should be be arranged
operating. appointed to signal regularly for safe
the operator to movement of
avoid collisions. vehicles.

Check for the


reverse alarm ,
beacon lights ,
warning lights and
horn prior to start
the work.

Tool box talk , pre


task briefing should
be done for the
workers working
with the moving
machinery to avoid
accidents.

Barricading and
signage should be
installed to warn
the unauthorized
persons entering
into the site .

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 54 of 80

Collapse of 6
3 3 9 Tagline should be 2 3 NO A supporting mobile YES GEOHARBOUR
materials due
Personnel used to handling the crane should be
to lack of un (M
injury, ( ( vibro cat while provided while
stable ground )
minor / M fixing , assembling the
level ,
major ) ) No personnel’s are vibrators to support
Fall of vibro cat Electrocuti allowed n the radius lifting the vibrator .
while putting on , of crane .
down property Provide a suitable
Over turning of damage. All work to be rope or belt for
equipment due completed under tagline to control
unstable the guidance and the handling of load
ground or control of the Crane .
dissembling
improper Lifting supervisor.
vibro cat
24 signaling Trained and
equipment to
Under any certified technicians
the crane Fall of persons circumstances “NO are allocated for
or materials MOBILE PHONE” fixing the vibrators.
while fixing during
vibro cat operation.

Ground conditions
to be assessed by
crane driver and
Crane

Lifting supervisor
and signed off by
Crane Lifting

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 55 of 80


supervisor prior to
set up

Crane to be checked
in accordance with
legal requirements

Driver to check
safety system daily
using checklist.

Trained and skilled


technicians are only
allowed to work to
fix the vibrators .

Workers personnel
protective
equipment should
be ensured prior to
work ( hand gloves
hard hat , high
visible west , safety
shoes and if nay
required rubber
gloves )

Vibrocat cables
should be secured

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 56 of 80


and handled
properly while
installation process

Dissembling of Failure of Personnel 5 4 20 Moment and 2 4 8 NO Ensure safe working YES GEOHARBOUR
cranes loading and minor positioning of crane load must be
unloading of injuries , (H must be sited in (M indicated on the
)
machinery/equi Major ) well compacted crawler crane .
pment or tools injuries , surface away from
Fatality , other structures and Crane shall be
Failure of lifting Property excavated areas . tested and
equipment and damage examined by a
accessories Assembling / competent 3rd party
dissembling area examiner in
Collision with must be barricaded accordance with the
other and installed statutory
25
equipments signage to requirements.
and nearby indication Before these tests
structures. and examinations
Crane must be are carried out,
Fall from height mounted /
, being struck dismounted and Inspect and color
by p plant / configured by code of all
machinery adequately trained accessories used to
and competent loading and
persons unloading of
equipment and
Prior to crane tools
operation it must be

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 57 of 80


with correct ballast Ladders and safety
and counter harness are
balanced as per the inspected and color
manufactures coded for safe use .
manual instruction

Crane must be
erected and jib set
up accordance with
the manufacturer's
Instructions, Care
should be taken to
ensure that the jib
sections are
assembled in their
correct order and
relative positions.

it is recommended
that a visual
inspection of the
crane be made by
the competent
person supervising
the erection.

Proper conditioned
and inspected crane
should be used to

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 58 of 80


load or unload the
parts.

Ladders and fall


arresters ( safety
harness ) , should be
used while working
at height

Collision with Personnel 4 3 12 Safety induction , 2 3 6 NO Installation of radars YES GEOHARBOUR


other vehicles minor equipment / tool and visible signage’s
or earth injuries , inspection prior to showing speed limit
moving electrocuti enter any personnel of 20kmph .
machinery / on , , equipment or tools
equipment Major into the work place Installation of goal
injuries , posts if any
26
Hit by / struck Fatality , Supervisor/foreman overhead power
Demobilizing
by moving Property to monitor the work lines .
the equipment
pedestrians damage , force vigilantly for
moving vehicles and Segregation of
Trailing / pedestrians pedestrian
overhead walkways and
cables / wet Ensure that the area vehicle routes.
ground is clean and safe for
work with adequate Provision of well
Failure to lighting prior to compacted and
follow site safe leveled ground for

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 59 of 80


access & egress mobilize the off loading materials
/ speed limits equipment .

Over speeding Machinery must be


of loaded securely anchored
trucks to the van / trailer
floor when in transit
.

The Crane hooks to


be fitted properly
and should be
clamped

Ground to be
securely plane and
compact to the
crane when the
machinery or tools
is being mobilizing.

Ensure / avoid the


over head cables
while mobilizing the
equipment.

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 60 of 80


Severity Risk Rating
Moderate – Catastrophic - Very Activity or industry should not proceed in
Likelihood Insignificant - 1 Minor - 2 Major - 4 15 – 25
3 5 High current form.
Highly Unlikely - 1 1 2 3 4 5 Activity should be subject to detailed OHS
8 – 12 High assessment and relevant corrective
Unlikely - 2 2 4 6 8 10
measures should be taken to reduce risk.
Possible - 3 3 6 9 12 15 Moderat Activity operates subject to management
4-6
Likely - 4 4 8 12 16 20 e approval and/or modification.
Highly Likely - 5 5 10 15 20 25 No immediate action required, unless
1-3 Low
escalation of risk is possible.

Title Full Name, ID # Signature Date


Contractor Project Manager
Contractor Construction Representative

Contractor EHS Representative

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group
Ground Improvement for Central Reservoir, Dammam, KSA

GH-MS-SC-R0-Central Reservoir Method Statement for Ground Improvement Page 61 of 80

P. O. Box: 391662, Dubai – U.A.E. | Tel: +971 4 447 0945 | Fax: +971 4 447 2190 | P.O.Box:5100648 |Tel:+9712 510 2400|Fax:+9712 558 9961
E-mail: dubai@geoharbour.com | www.geoharbour.ae
Member of Shanghai Geoharbour Group