Client: Safaricom

Contractor:- Broadcom Network Consultancy Service Plc.


Address :- Addis Ababa.
ID Task Name Duration Start Finish Predecessors
Dec 25, '22 Jan 1, '23 Jan 8, '23 Jan 15, '23 Jan 22, '23 Jan 29, '23 Feb 5, '23
Dec 25, '22 Jan 1, '23 Jan 8, '23 Jan 15, '23 Jan 22, '23 Jan 29, '23 Feb 5, '23
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
0 Tentative Schedule for 50m and 60m Tower Green Field Site36 days Mon 1/2/23 Mon 2/6/23
1 1 Surveying and Setting out 1 day Mon 1/2/23 Mon 1/2/23
2 1.1 Kickoff & Overall site setting out 1 day Mon 1/2/23 Mon 1/2/23
3 2 Tower Raft Foundation 16 days Tue 1/3/23 Wed 1/18/23 1
12 3 Concrete Test 1 day Tue 1/24/23 Tue 1/24/23 3
13 3.1 Hammer Test and Closing QC 1 day Tue 1/24/23 Tue 1/24/23
14 4 Backfilling and Compaction 4 days Wed 1/25/23 Sat 1/28/23
15 4.1 Backfilling and Compaction 4 days Wed 1/25/23 Sat 1/28/23 13
16 5 Tower Erection 7 days Sun 1/29/23 Sat 2/4/23 14
17 5.1 Assembling and Erection 5 days Sun 1/29/23 Thu 2/2/23 15
18 5.2 Telecom accessories 2 days Fri 2/3/23 Sat 2/4/23 17
19 6 Cabinet Foundation 3 days Thu 1/19/23 Sat 1/21/23
20 6.1 Leveling and Lean concrete 1 day Thu 1/19/23 Thu 1/19/23
21 6.2 Reinforcement work and formwork 1 day Fri 1/20/23 Fri 1/20/23 20
22 6.3 Casting concrete C-25 1 day Sat 1/21/23 Sat 1/21/23 21
23 7 Cable tray foundation 2 days Thu 1/19/23 Fri 1/20/23 19
24 7.1 Preparing formwork 1 day Thu 1/19/23 Thu 1/19/23
25 7.2 Casting Plain concrete without bar C-20 1 day Fri 1/20/23 Fri 1/20/23 24
26 8 Cable ladder Foundation 2 days Thu 2/2/23 Fri 2/3/23 16
27 8.1 Excavation 0.5 days Thu 2/2/23 Thu 2/2/23
28 8.2 Leveling and lean concrete 0.5 days Thu 2/2/23 Thu 2/2/23 27
29 8.3 Formwork and Reinforcement foundation 0.5 days Fri 2/3/23 Fri 2/3/23 28
30 8.4 Casting concrete C-20 0.5 days Fri 2/3/23 Fri 2/3/23 29
31 9 Hand hole 1.5 days Sun 1/22/23 Mon 1/23/23
32 9.1 Excavation 1 day Sun 1/22/23 Sun 1/22/23
33 9.2 Brick wall 0.5 days Mon 1/23/23 Mon 1/23/23 32
34 10 Installation of Earting system 3 days Sun 1/22/23 Tue 1/24/23 31SS
35 10.1 Excavation 1 day Sun 1/22/23 Sun 1/22/23
36 10.2 Installation of earting 1 day Mon 1/23/23 Mon 1/23/23 35
37 10.3 Backfilling and Compaction 1 day Tue 1/24/23 Tue 1/24/23 36
38 11 Fence Foundation (50x50)cm 4 days Tue 1/24/23 Fri 1/27/23
39 11.1 Excavation for Post Foundation 2 days Tue 1/24/23 Wed 1/25/23
40 11.2 Masonry wall 1 day Thu 1/26/23 Thu 1/26/23 39
41 11.3 R bar and formwork 1 day Thu 1/26/23 Thu 1/26/23
42 11.4 Vertical Steel Post 1 day Thu 1/26/23 Thu 1/26/23 41SS

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: Tentative Schedule for
Milestone Inactive Summary Start-only Late Slack
Date: Thu 11/24/22
Summary Manual Task Finish-only Critical

Project Summary Duration-only External Tasks Critical Split

Page 1
Client: Safaricom
Contractor:- Broadcom Network Consultancy Service Plc.
Address :- Addis Ababa.
ID Task Name Duration Start Finish Predecessors
Dec 25, '22 Jan 1, '23 Jan 8, '23 Jan 15, '23 Jan 22, '23 Jan 29, '23 Feb 5, '23
Dec 25, '22 Jan 1, '23 Jan 8, '23 Jan 15, '23 Jan 22, '23 Jan 29, '23 Feb 5, '23
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
43 11.5 Casting concrete C-25 1 day Fri 1/27/23 Fri 1/27/23 42
44 12 Fence beam (20x30)cm 2 days Sat 1/28/23 Sun 1/29/23 38
45 12.1 Formwork and Reinforcement 1 day Sat 1/28/23 Sat 1/28/23
46 12.2 Concrete Casting C-25 1 day Sun 1/29/23 Sun 1/29/23 45
47 13 Mesh Fence 2 days Fri 2/3/23 Sat 2/4/23
48 13.1 Fixing Mesh 2 days Fri 2/3/23 Sat 2/4/23
49 14 Site Gravel 1 day Sat 2/4/23 Sat 2/4/23 47
50 14.1 Leveling Gravel 1 day Sat 2/4/23 Sat 2/4/23
51 15 Fixing main Gate 1 day Sun 2/5/23 Sun 2/5/23
52 15.1 Main Gate 1 day Sun 2/5/23 Sun 2/5/23
53 16 Site handing over 1 day Mon 2/6/23 Mon 2/6/23
54 16.1 Site handover 1 day Mon 2/6/23 Mon 2/6/23

Task Inactive Task Manual Summary Rollup External Milestone Progress

Split Inactive Milestone Manual Summary Deadline Manual Progress


Project: Tentative Schedule for
Milestone Inactive Summary Start-only Late Slack
Date: Thu 11/24/22
Summary Manual Task Finish-only Critical

Project Summary Duration-only External Tasks Critical Split