Professional Documents
Culture Documents
AAB 035416 Cement Base and Underlayment
AAB 035416 Cement Base and Underlayment
AAB 035416 Cement Base and Underlayment
1.1 GENERAL
This section covers specification of all plant, labor, equipment, appliances and
materials and in performing all works in connection with the installation of cement
screed floor finish including bases, skirting and wainscots, in strict accordance with
applicable drawings, reference to the Bills of Quantities and the contract documents
in general. Materials and methods not specifically described but required, for proper
fabrication and installation of floor screeding, is to be provided by the Contractor
subject to approval, at no claim for additional cost or time.
1.2 STANDARDS
1.3 PERFORMANCE
a. The Contractor is to deliver material to the job site in original packing with
labels intact and legible at time of use. If any material is delivered loose, it is
to be stored as directed.
c. Environmental Conditions:
ii. Only limited water is to be used for proper workability. Water cement
ratio is not to exceed 0.45. Mix is to be consumed within thirty
TS/A/SECTION 035416/1
minutes of mixing. Re-tempering is not to be permitted. Mix which
has begun to stiffen is to be discarded.
iv. Mix for 50mm or thicker cement screed finish is to be 1 part cement
and 4 parts sand.
e. The Contractor is to apply the mix over required areas in alternate strips or
bays not exceeding 25 Sq. M, to be laid to level or fall as shown or directed.
UPVC crack inducer to screed depth is to be inserted at panel control joints.
g. The Contractor is to protect materials of this section before, during, and after
installation and protect installed work and materials of other trades.
Screeded floor is to be kept free of traffic for 7 days.
2.0 MATERIALS
1. Cement Screed
b. 4 parts sand which is to be clean, sharp, angular, free from alkali, silt or
organic matter.
2. Skirting
3.0 EXECUTION
1. Surface conditions
TS/A/SECTION 035416/2
DIVISION 03: CONCRETE
SECTION 035416 CEMENT BASE
AND UNDERLAYMENT (SCREED)
Where possible, the screed is to be laid whilst the concrete is green i.e.
within 24 hours of casting. It is to be steel trowelled or using wooden float.
e. Wherever also possible, the surface is to be wet for the 7 days, and to wet
cut for any cracks; blisters or any other making good with same screed mix.
Prevent accumulation of scraps and debris arising from the work of this section.
Maintain premises in a neat and orderly condition at all times. In the event of spilling
or splashing material on to other surfaces immediately remove the same, and traces
of residue, to approval.
TS/A/SECTION 035416/3