Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 134

CHAPTER -5

BRICK WORK.
Note:- 1. The rates are to be reduced Proportionately if II or III Class Bricks are used.
2. Rates for all finsihed works include the removal of surplus debries, un-used material and by-Products..

3. For handling all types of materials or short lead including Carriage upto 3 Chains, nothing, is to be paid as
extra. Where handling and Carrige involves an extra lead beyond 3 chains, Carriage for whole of the distance should be
provided in the Estimate.

4. Masonry of boundary wall to be considered as masonry other than buildings for items 1, 4, 5, 15, 20, 21
and 23.
5. The rate of lime mortar also includes grinding of mortar.
6. The rates include the cost of scaffolding and its removal.
Rate (Rs)
S.NO Description Unit Specification Remarks.
Labour Composite
1 2 3 4 5 6 7
1 Pacca brick work in mud mortar in 21.1-21.4 (I) The rate is to
building. be reduced
Proportionately.
(a) In foundation and plinth. % Cft. 1762.06 9379.56 If II or III Class
brick are used
(b) In ground floor. Do 2336.81 9954.31 (II) See Note
No.4

2 Add extra labour in Item No. 1 for brick


work in

(I) First Floor % Cft. 226.90


(II) Second Floor Do 535.45
(III) Third Floor Do 844.00
(IV) 4th and subsequent Floor Do 1388.50
3 Pacca brick work in mud mortar other 21.1-21.4 (I) The rate is to
than building. be reduced
Proportionately.
(I) Upto 20 ft. height. % Cft. 2399.83 10017.33 If II or III Class
brick are used
(II) Extra labour to every 5 feet Do 226.90 (II) See Note
additional height. No.4

4 Pacca brick work in foundation and 21.1-21.4 Do


plinth in:
(I)
(a) Cement sand mortar 1:2 % Cft. 2324.21 13802.71

Page 23
Rate (Rs)
S.NO Description Unit Specification Remarks.
Labour Composite
1 2 3 4 5 6 7
(b) Cement sand mortar 1:3 Do 2324.21 4401.95
(c )Cement sand mortar 1:4 Do 2324.21 12501.41
(d) Cement sand mortar 1:5 Do 2324.21 12176.08
(e) Cement sand mortar 1:6 Do 2324.21 3865.15
(f) Cement sand mortar 1:7 Do 2324.21 3773.85
(g) Cement sand mortar 1:8 Do 2324.21 11631.03
(II) (a) lime cement sand mortar 1:1:6 % Cft. 2324.21 12457.41
(b) lime cement sand mortar 1:1:7 Do 2324.21 12249.96
(c ) lime cement sand mortar 1:1:8 Do 2324.21 3823.85
(d) lime cement sand mortar 1:1:9 Do 2324.21 3760.80
(e) lime cement sand mortar 1:1:10 Do 2324.21 3713.55
(III) Lime sand surkhi mortar 1:1:1 % Cft. 2324.21 3668.05
(IV)Lime sand mortar 1:2 Do 2324.21 3657.05
(V) (a) Lime surkhi mortar. 2:3 % Cft. 2324.21 12578.96
(b) Lime surkhi mortar. 1:2 Do 2324.21 3683.15
(c )Lime surkhi mortar. 1:3 Do 2324.21 3562.50
5 Pacca brick work in ground floor in: 21.1 I.the rate is to
be reduced
Proportionately
if Class bricks
are used.

(I) (a) Cement sand mortar. 1:2 % Cft. 3050.21 14528.71


(b) Cement sand mortar. 1:3 Do 3050.21 4783.10
(c ) Cement sand mortar. 1:4 Do 3050.21 13227.41 II. See Note
No.4.
(d) Cement sand mortar. 1:5 Do 3050.21 4363.70
(e) Cement sand mortar. 1:6 Do 3050.21 4246.30
(f) Cement sand mortar. 1:7 Do 3050.21 4155.00
(g) Cement sand mortar. 1:8 Do 3050.21 4082.70
(II) (a) Lime Cement sand mortar.1:1:6. % Cft. 3050.21 4373.05
(b) Lime Cement sand mortar 1: 1: 7 Do #VALUE! 4280.20
(c ) Lime Cement sand mortar 1: 1: 8 Do 3050.21 4204.95
(d) Lime Cement sand mortar 1: 1: 9 Do 3050.21 4141.95
(e) Lime Cement sand mortar 1: 1: 10 Do 3050.21 4094.75

Page 24
Rate (Rs)
S.NO Description Unit Specification Remarks.
Labour Composite
1 2 3 4 5 6 7
(III) Lime sand surki mortar. 1:1:1 % Cft. 3050.21 4029.30
(IV) Lime sand mortar. 1:2 Do 3050.21 4038.65
(V) (a) Lime Surhi mortar. 2:3 Do 3050.21 13304.96
(b) Lime surkhi mortar. 1:2 Do 3050.21 4064.30
(c) Lime surkhi mortar. 1:3 Do 3050.21 3943.65
6 Add extra labour in item No.5 for brick
work in:

First Floor % CFt. 226.90


Second Floor Do 535.45
3rd Floor Do 844.00
4th and subsequent Floor. Do 1388.50
7 pacca brick work other than building 21-1-21.5 The rate is to be
including striking of joints upto 20 feet reduced
height in: Proportionately
if II or III Class
bricks are used.

(I) (a) Cement sand mortar. 1:2 % CFt. 2722.50 5045.15


(b) Cement sand mortar. 1:3 Do 2722.50 4625.80
(c ) Cement sand mortar. 1:4 Do 2722.50 4374.15
(d) Cement sand mortar. 1:5 Do 2722.50 4206.40
(e) Cement sand mortar. 1:6 Do 2722.50 4089.00
(f) Cement sand mortar. 1:7 Do 2722.50 3997.70
(g) Cement sand mortar. 1:8 Do 2722.50 3925.40

(II) (a) Lime cement sand mortar. 1:1:6 % CFt. 2722.50 4215.75
(b) Lime cement sand mortar. 1:1:7 Do 2722.50 4122.90
(c ) Lime cement sand mortar. 1:1:8 Do 2722.50 4047.65
(d ) Lime cement sand mortar. 1:1:9 Do 2722.50 3984.65
(e) Lime cement sand mortar. 1:1:10 Do 2722.50 3937.40

(III) Lime sand Surkhi mortar 1:1:1 Do 2722.50 3859.20


(IV) Lime sand mortar 1:2 Do 2722.50 3881.35

Page 25
Rate (Rs)
S.NO Description Unit Specification Remarks.
Labour Composite
1 2 3 4 5 6 7
(IV) Lime sand mortar 1:2 Do 2722.50 4002.90
(V)(a) Lime Surkhi mortar. 2:3 Do 2722.50 3907.00
(b) Lime Surkhi mortar. 1:2 Do 2722.50 3907.00
(c) Lime Surkhi mortar. 1:3. Do 2722.50 3786.35
8 Add extra labour in item No.7 for every % Cft. 226.90
5 feet addl: height.

9 Extra labour for arch work in brick % Cft. 562.65 21.5


masonry including labour for centering
and decentering.

10 Extra for pacca brick in staining of % Cft. 680.63 516.60 21.1-21.4 The rate is to be
wells or any other circular masonry. reduced
Proportiontely
if II or III class
bricks are used.

11 Extra labour for profile and flared walls % Cft. 140.50

12 Extra labour for pacca brick work in


piers and abutments.

(I)from 10' to 20' height % Cft. 216.59


(II) Above 20' ft. height. Do 226.90
13 Reinforced brick work in Lintel of P.Cft. 76.63 214.16
openings laid in 1:3 cement mortar
including all labour, material, forms
moulds, lifting and shuttering etc, but
excluding cost and labour of steel
reinforcement which shall be paid for
separately.

14 Dressing of chamfering of bricks % Nos. #REF! Rate given


applies to brick
of special
architechtural
shape see re-
mark on P-25.

15 Perforated pacca brick walling 4 1/2" I The rate is to


thick in Ground floor in: be reduced
Proportionately
if II or III Class
bricks are used
II. See Note.4.
Page 26
Rate (Rs)
S.NO Description Unit Specification I The
Remarks.
rate is to
Labour Composite be reduced
1 2 3 4 5 6 7
Proportionately
(I) Mud mortar. % Sft. 1167.65 1082.55 if II or III Class
bricks are used
II. See Note.4.

(II) (a) Cement sand mortar 1:2 % Sft. 1527.63 1709.35


(b) Cement sand mortar 1:3 Do 1527.63 4196.01
(c ) Cement sand mortar 1:4 Do 1527.63 1541.60
(d) Cement sand mortar 1:5 Do 1527.63 1499.65
(e) Cement sand mortar 1:6 Do 1527.63 1470.20
(f) Cement sand mortar 1:7 Do 1527.63 1447.30
(g) Cement sand mortar 1:8 Do 1527.63 1430.50

(III) (a) Lime cement sand mortar 1:1:6 % Sft. 1527.63 1502.00
(b) Lime cement sand mortar 1:1:7 Do 1527.63 1478.55
(c ) Lime cement sand mortar 1:1:8 Do 1527.63 1461.15
(d) Lime cement sand mortar 1:1:9 Do 1527.63 1444.05
(e) Lime cement sand mortar 1:1:10 Do 1527.63 1433.90

(IV) Lime sand surkhi mortar 1: 1: 1 % Sft. 1527.63 1421.95


(V) Lime sand mortar 1:2 Do 1527.63 1417.70
(VI)(a) Lime surkhi mortar 2:3 Do 1527.63 1448.80
(b) Lime surkhi mortar 1:2 Do 1527.63 1425.10
(c ) Lime surkhi mortar 1:3 Do 1527.63 1394.65

16 Add extra labour in item No. 15 for


perforated pacca brick work in:

First Floor % Sft. 216.59


Second Floor Do 267.70
Third Floor Do 422.00
4th & Subsequent Floor. Do 694.25
17 Perforated pacca brick walling 9" thick 21.1-21.4 Rate is to be
in ground floor in: recduced
Proportionately if
II or III class
bricks are used.
Page 27
Rate (Rs)
S.NO Description Unit Specification Remarks.
Labour Composite
1 Perforated pacca brick
2 walling 9" thick 3 4 5 6 Rate is7 to be
in ground floor in: recduced
Proportionately if
II or III class
bricks are used.

(I) Mud mortar. % Sft. 1754.50 1852.35


(II) (a) Cement sand mortar. 1:2 Do 2299.00 3015.15
(b) Cement sand mortar. 1:3 Do 2299.00 2805.50
(c )Cement sand mortar. 1:4 Do 2299.00 2679.65
(d) Cement sand mortar. 1:5 Do 2299.00 2595.80
(e) Cement sand mortar. 1:6 Do 2299.00 2536.90
(f) Cement sand mortar. 1:7 Do 2299.00 2490.95
(g) Cement sand mortar. 1:8 Do 2299.00 2455.30

(III) (a) Lime cement sand mortar 1:1:6 % Sft. 2299.00 2600.45
(b) Lime cement sand mortar 1:1:7 Do 2299.00 2552.95
(c ) Lime cement sand mortar 1:1:8 Do #VALUE! 2516.45
(d) Lime cement sand mortar 1:1:9 Do 2299.00 2484.90
(e) Lime cement sand mortar 1:1:10 Do 2299.00 2461.85
(IV) lime sand surkhi motar 1:1:1 % Sft. 2299.00 2439.10
(V) Lime sand mortar 1:2 % Sft. 2299.00 2432.70
(VI) (a) Lime surkhi mortar. 2:3 % Sft. 2299.00 2494.05
(b) Lime surkhi mortar. 1:2 % Sft. 2299.00 2446.70
(c ) Lime surkhi mortar. 1:3 % Sft. 2299.00 2385.75
18 Add extra labour in item No.17 for
Perforated Pacca brick work in:

First Floor % Sft. 170.15


Second Floor Do 401.55
Third Floor Do 633.00
4th & Subsequent Floor. Do 1041.35
19 Fire brick masonry in fire clay mortar 21.1-21.2

(I) Upto 20 feet height including all % Cft. 2994.75 6928.35


charges.

(II) Extra for every 5 ft.addl: height. Do 226.90


20 Pacca brick walling laid in 1:3 cement 21.19 I The rate is to be
sand mortar reinforced with 1" wide 18 reduced
gauge hoop iron:- Proporationately
if II or III Class
Page 28 bicks are used.
Rate (Rs)
S.NO Description Unit Specification Remarks.
Labour Composite
1 Pacca brick walling2 laid in 1:3 cement 3 4 5 6 I The rate
7 is to be
sand mortar reinforced with 1" wide 18 reduced
gauge hoop iron:- Proporationately
if II or III Class
bicks are used.

(I) 4 1/2" thick walling with hoop iron % Sft. 1104.13 6392.61
bounding 6" apart.

(II) 4 1/2" thick walling with hoop iron Do 1104.13 5840.16 II See Note 4
bonding 12" apart.

(III) 3" thick walling with hoop iron Do 853.05 4848.35


bonding 6" apart

(IV) 3" thick walling with hoop iron Do 825.83 4207.28


bonding 12" apart.

21 Ghilafi work 1" to 1- 1/2" (thick wall). % Cft. 2350.43 2563.50 21.18 I The rate is to
be reduceds
Proportionately
if II or III Class
bricks are used.

22 Dry brick Pitching % Cft. 1149.50 8574.50 21.1 See Note 4.


23 Sundried bricks in mud mortar. % Cft. 1951.13 1819.40 21.16 See Note 4.
24 Pise wall (Mud walling ) % Cft. 907.50 ___ 21.17

25 Eave brick moulded , weathered and


throated with back bricks or drip course
cornice in 1:3 cement mortar.

(I) 3" thick drip course cornice. Per Rft. 15.58 16.05
(II) 4 1/2" thick cave brick with back Do 17.70 19.80
brick.

(III) 4 1/2" thick cave brick with back Do 13.92 26.60


brick.

26 Laying dressed or moulded brick


cornices in 1:6 cement mortar, plastering
or pointing complete.

Page 29
Rate (Rs)
S.NO Description Unit Specification Remarks.
Labour Composite
1 2 3 4 5 6 7
(I) One brick. Per Rft. 17.70 14.25
(II) Two bricks Do 26.17 28.25
(III) Three bricks Do 34.88 41.15
(IV) four bricks Do 43.86 54.85
27 Cleaning bricks dismantled from kacha % Nos. 211.75 ___
pacca masonary.

28 Scraping bricks dismantled from pacca Do 998.25 ___


masonry.

29 Supplying and filling sand under floor % CFt. 151.25 203.50


and plugging in walls.

Note:- The rates for brick work have been calculated for the standard size of bricks 9" x 4 1/2" x 3" brick used are 8"
x 4" x4" the corresponding rate may be increased by 5%.

Page 30
BIRCK MASONARY.
FIRST FILL THIS SHEET.

MATERIAL. RATE UNITE

1 Pucca Brick.(9"x4-1/2"x3") 5000 % 0 Nos


(Ist Class)
2 Earth ,Stiffclay 500 % Cft

3 Cement. 400 P.bag

4 Sand 2425 % Cft.

5 Slaked Lime 375 P.Mand

6 Surkhi 2250 % Cft.

7 partal wood 1700 P.Cft.

8 Fire clay Brick. 5300 % 0 Nos.

9 Aluminia Cement. 650 P.bag

10 Crushed fire bricks. 2500 % Cft.

11 Hoop Iron. 2500 P.Cwt

12 Sundried Brick. 1200 % 0 Nos

13 Moulded Brick. 4800 % 0 Nos

14 Pit sand. 900 % Cft.

LABOUR RATE UNITE

1 MASSON (g-1) , Black Smith. 450 P.day

2 Coolies. 250 P.day

3 Bahishti, Skilled.Cooly. 250 P.day


CHAPTER -5
==================
B R I C K M A S O N A R Y.
============================
(1) The rates are to be reduced proportionately if II or III Class
Bricks are used.
(2) Rates for all finished works include the removal of surplus
debries, un-used material and by-products.
(3) For handling all types of materials for short lead including
carraige upto 3 chains, nothing is to be paid as extra. Where
rehandling and carraige involves an extra lead beyond 3 chains,
carraige for whole of the distance should be provided in the
estimate.
(4) Masonary of boundary wall to be considered as masonary other
than buildings for items 1, 4, 5, 15, 20, 21, 23.
(5) The rate of lime mortar also includes grinding of mortar.
(6) The rates includes the cost of scaffolding and its removal.
S/N D E S C R I P T I O N.
1. Pacca brick work in mud mortar in building.
(a) In foundation and plinth.
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs:
_____________________________ ______ _____ ______ _______ _________ Rs:
Pucca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00
Good earth or stiff clay 35.00 Cft. 500.00 % Cft. 175.00
for mud mortar.
_____________________________ ______ _____ ______ _______ _________
TOTAL
_____________________________ 6925.00
______ _____ ______ _______ _________
Contractor's profit 10.00 % 692.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 7617.50
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
For Masonary Work.
Masons. 1.50 Nos: 450.00 P.day. 675.00
Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00
Bahishti. 0.125 Nos: 250.00 P.day. 31.25
For Mud Mortar.
Skilled. Coolies. 0.667 Nos: P.day.
250.00 166.67
Bahishti.
_____________________________ 0.333 Nos:
______ _____ ______ P.day. _________
250.00 _______ 83.33
Rs: 1456.25
Sundries. 10.00 % 145.63
_____________________________ ______ _____ ______ _______ _________
TOTAL
_____________________________ 1601.88
______ _____ ______ _______ _________
Contractor's profit
_____________________________ ______ _____ ______ %
10.00 _______ 160.19
_________
TOTAL PART " B " 1762.06
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 9379.56
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 9379.56
S/N D E S C R I P T I O N.

1. Pacca brick work in mud mortar in building.


(b) In ground floor.

_____ _____________________________ ______ _____ ______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pucca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Good earth or stiff clay 35.00 Cft. 500.00 % Cft. 175.00


for mud mortar.
TOTAL 6925.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 692.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 7617.50
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

Bahishti. 0.125 Nos: 250.00 P.day. 31.25


For Mud Mortar.
Skilled Coolies. 0.667 Nos: 250.00 P.day. 166.67

Bahishti. 0.333 Nos: 250.00 P.day. 83.33

_____________________________ ______ _____ ______ _______ _________


Rs: 1931.25
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 193.13
_____________________________ ______ _____ ______ _______ _________
TOTAL 2124.38
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 212.44
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2336.81
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 9954.31
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 9954.31
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

2. Add extra labour in item No:1 for brick work.


(i) In First floor.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 0.25 Nos: 450.00 P.day. 112.50

Skilled Coolies. 1.00 Nos: 250.00 P.day. 250.00


_____________________________ ______ _____ ______ _______ _________
Rs: 362.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 36.25
_____________________________ ______ _____ ______ _______ _________
TOTAL
_____________________________ ______ _____ ______ _______ 398.75
_________
Contractor's profit 10.00 % 39.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 438.63
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 226.90
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

2. Add extra labour in item No:1 for brick work.


(ii) In Second floor.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.

Masons. 0.75 Nos: 450.00 P.day. 337.50

Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00


_____________________________ ______ _____ ______ _______ _________
Rs: 837.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 83.75
_____________________________ ______ _____ ______ _______ _________
TOTAL 921.25
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 92.13
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1013.38
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 535.45
S/N D E S C R I P T I O N.
2. Add extra labour in item No:1 for brick work.
(iii) In Third Floor.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.

Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled 'Coolies. 3.00 Nos: 250.00 P.day. 750.00


_____________________________ ______ _____ ______ _______ _________
Rs: 1312.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 131.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1443.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 144.38
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1588.13
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 844.00
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

2. Add extra labour in item No:1 for brick work.


(iv) In Fourth and subsequent Floor.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
For Masonary Work.

Masons. 2.25 Nos: 450.00 P.day. 1012.50

Skilled bCoolies. 4.50 Nos: 250.00 P.day. 1125.00


_____________________________ ______ _____ ______ _______ _________
Rs: 2137.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 213.75
_____________________________ ______ _____ ______ _______ _________
TOTAL 2351.25
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 235.13
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2586.38
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 1388.50
S/N D E S C R I P T I O N.
3. Pacca brick work in mud mortar other than building.
(i) Upto 20 feet hieght.
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pucca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00
Good earth or stiff clay 35.00 Cft. 500.00 % Cft. 175.00
for mud mortar.
_____________________________ ______ _____ ______ _______ _________
TOTAL 6925.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 692.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 7617.50
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00
Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00
For Mud Mortar.
Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00
Bahishti. 0.333 Nos: 250.00 P.day. 83.33
_____________________________ ______ _____ ______ _______ _________
Rs: 1983.33
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 198.33
_____________________________ ______ _____ ______ _______ ssssssssss
TOTAL 2181.67
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 218.17
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2399.83
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 10017.33
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 10017.33
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.
3. Pacca brick work in mud mortar other than building.
(ii) Extra labour for every 5 feet additional hieght.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 0.25 Nos: 450.00 P.day. 112.50
Skilled Coolies. 1.00 Nos: 250.00 P.day. 250.00
_____________________________ ______ _____ ______ _______ _________
TOTAL Rs: 362.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 36.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 398.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 39.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 438.63
_____________________________ ______ _____ ______ _______ _________
Labour rate for 100 Cft. Rs: 226.90
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________


S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(i) In cement sand mortar.
(a) 1:2
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 8.00 Cwt. 400.00 P.bag 3200.00

Sand. 20.00 Cft. 2425.00 % Cft. 485.00

TOTAL 10435.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 1043.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 11478.50
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 13802.71
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 13802.71
S/N D E S C R I P T I O N.

4. Pacca brick work in foundation and plinth


(i) In cement sand mortar.
(b) 1:3
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 6.00 Cwt. 400.00 P.bag 2400.00

Sand. 22.50 Cft. 2425.00 % Cft. 545.63

TOTAL 9695.63
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 969.56
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 10665.19
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12989.40
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4401.95
S/N D E S C R I P T I O N.

4. Pacca brick work in foundation and plinth


(i) In cement sand mortar.
(c) 1:4
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 4.80 Cwt. 400.00 P.bag 1920.00

Sand. 24.00 Cft. 2425.00 % Cft. 582.00

TOTAL 9252.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 925.20
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 10177.20
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12501.41
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 12501.41
S/N D E S C R I P T I O N.

4. Pacca brick work in foundation and plinth


(i) In cement sand mortar.
(d) 1:5
_____ _____________________________ ______ _____ ______ _______ ssssssssss
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 4.00 Cwt. 400.00 P.bag 1600.00

Sand. 25.00 Cft. 2425.00 % Cft. 606.25


TOTAL 8956.25
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 895.63
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9851.88
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12176.08
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 12176.08
S/N D E S C R I P T I O N.

4. Pacca brick work in foundation and plinth


(i) In cement sand mortar.
(e) 1:6
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 3.44 Cwt. 400.00 P.bag 1376.00

Sand. 25.70 Cft. 2425.00 % Cft. 623.23


TOTAL 8749.23
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 874.92
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9624.15
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00% 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 11948.36
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3865.15
S/N D E S C R I P T I O N.

4. Pacca brick work in foundation and plinth


(i) In cement sand mortar.
(f) 1:7
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 3.00 Cwt. 400.00 P.bag 1200.00

Sand. 26.50 Cft. 2425.00 % Cft. 642.63


TOTAL 8592.63
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 859.26
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9451.89
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 11776.10
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3773.85
S/N D E S C R I P T I O N.

4. Pacca brick work in foundation and plinth


(i) In cement sand mortar.
(g) 1:8
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 2.66 Cwt. 400.00 P.bag 1064.00

Sand. 26.67 Cft. 2425.00 % Cft. 646.75


TOTAL 8460.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 846.07
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9306.82
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 11631.03
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 11631.03
S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(ii) In lime cement sand mortar.
(a) 1:1:6
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.60 Mand 375.00 P.Mand 600.00

Cement. 3.20 Cwt. 400.00 P.bag 1280.00

Sand. 24.00 Cft. 2425.00 % Cft. 582.00


TOTAL 9212.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 921.20
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 10133.20
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33
Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries.
_____________________________ ______ _____ ______ %
10.00 _______ 192.08
_________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12457.41
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 12457.41
S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(ii) In lime cement sand mortar.
(b) 1:1:7
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.42 Mand 375.00 P.Mand 532.50

Cement. 2.85 Cwt. 400.00 P.bag 1140.00

Sand. 24.78 Cft. 2425.00 % Cft. 600.92

_____________________________ ______ _____ ______ _______ _________


TOTAL 9023.42
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 902.34
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9925.76
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos:


_____________________________ ______ _____ ______ P.day.
250.00 _______ 125.00
_________
Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL
_____________________________ ______ _____ ______ _______ 2112.92
_________
Contractor's profit
_____________________________ 10.00
______ _____ ______ %
_______ 211.29
_________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12249.96
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3899.05
S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(ii) In lime cement sand mortar.
(c) 1:1:8
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.28 Mand 375.00 P.Mand 480.00

Cement. 2.56 Cwt. 400.00 P.bag 1024.00

Sand. 25.60 Cft. 2425.00 % Cft. 620.80


TOTAL 8874.80
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 887.48
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9762.28
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33
Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12086.49
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3823.85
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(ii) In lime cement sand mortar.
(d) 1:1:9
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.16 Mand 375.00 P.Mand 435.00

Cement. 2.32 Cwt. 400.00 P.bag 928.00

Sand. 26.20 Cft. 2425.00 % Cft. 635.35


TOTAL 8748.35
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 874.84
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9623.19
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: P.day.


250.00 125.00
Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 11947.39
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3760.80
S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(ii) In lime cement sand mortar.
(e) 1:1:10
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.07 Mand 375.00 P.Mand 401.25

Cement. 2.14 Cwt. 400.00 P.bag 856.00

Sand. 26.66 Cft. 2425.00 % Cft. 646.51


TOTAL 8653.76
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 865.38
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9519.13
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
Sundries. 10.00% 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 11843.34
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3713.55
S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(iii In lime sand surkhi mortar.
(a) 1:1:1
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.65 Mand 375.00 P.Mand 1743.75

Sand. 11.67 Cft. 2425.00 % Cft. 283.00

Surkhi. 11.67 Cft. 2250.00 % Cft. 262.58


TOTAL 9039.32
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 903.93
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9943.25
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00


Bahishti. 0.250 Nos: 250.00 P.day. 62.50
For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12267.46
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3668.05
S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(iv) In lime sand mortar.
1:2
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.67 Mand 375.00 P.Mand 1751.25

Sand. 23.33 Cft. 2425.00 % Cft. 565.75


TOTAL 9067.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 906.70
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9973.70
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12297.91
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3657.05
S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(v) In lime surkhi mortar.
(a) 2:3
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 5.60 Mand 375.00 P.Mand 2100.00

Surkhi. 21.00 Cft. % Cft.


2250.00 472.50
_____________________________ ______ _____ ______ _______ _________
TOTAL 9322.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 932.25
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 10254.75
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

SkilledCoolies. 2.50 Nos: 250.00 P.day. 625.00


Bahishti. 0.250 Nos: 250.00 P.day. 62.50
For Cement Mortar.
SkilledCoolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12578.96
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 12578.96
S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(v) In lime surkhi mortar.
(b) 1:2
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.67 Mand 375.00 P.Mand 1751.25

Surkhi. 23.33 Cft. 2250.00 % Cft. 524.93


_____________________________ ______ _____ ______ _______ _________
TOTAL 9026.18
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 902.62
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9928.79
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00
Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12253.00
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3683.15
S/N D E S C R I P T I O N.

4 Pacca brick work in foundation and plinth


(v) In lime surkhi mortar.
(c) 1:3
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 3.50 Mand 375.00 P.Mand 1312.50

Surkhi. 26.25 Cft. 2250.00 % Cft. 590.63


TOTAL 8653.13
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 865.31
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9518.44
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00
Skilled Coolies. 2.50 Nos: 250.00 P.day. 625.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 11842.65
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3562.50
S/N D E S C R I P T I O N.

5 Pacca brick work in ground floor (including striking of joints)


(i) In cement sand mortar.
(a) 1:2
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 8.00 Cwt. 400.00 P.bag 3200.00

Sand. 20.00 Cft. 2425.00 % Cft. 485.00

_____________________________ ______ _____ ______ _______ _________


TOTAL 10435.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 1043.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 11478.50
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2772.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 3050.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 14528.71
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 14528.71
S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(i) In cement sand mortar.
(b) 1:3
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 6.00 Cwt. 400.00 P.bag 2400.00

Sand. 22.50 Cft. 2425.00 % Cft. 545.63


TOTAL 9695.63
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 969.56
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 10665.19
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2772.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 3050.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 13715.40
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4783.10
S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(i) In cement sand mortar.
(c) 1:4
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 4.80 Cwt. 400.00 P.bag 1920.00

Sand. 24.00 Cft. 2425.00 % Cft. 582.00


TOTAL 9252.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 925.20
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 10177.20
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2772.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 3050.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 13227.41
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 13227.41
S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(i) In cement sand mortar.
(d) 1:5
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 4.00 Cwt. 400.00 P.bag 1600.00

Sand. 25.00 Cft. 2425.00 % Cft. 606.25


TOTAL 8956.25
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 895.63
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9851.88
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2772.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 3050.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12902.08
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4363.70
S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(i) In cement sand mortar.
(e) 1:6
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 3.44 Cwt. 400.00 P.bag 1376.00

Sand. 25.70 Cft. 2425.00 % Cft. 623.23


TOTAL 8749.23
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 874.92
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9624.15
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2772.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 3050.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12674.36
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4246.30
S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(i) In cement sand mortar.
(f) 1:7
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 3.00 Cwt. 400.00 P.bag 1200.00

Sand. 26.50 Cft. 2425.00 % Cft. 642.63


TOTAL 8592.63
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 859.26
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9451.89
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2772.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 3050.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12502.10
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4155.00
S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(i) In cement sand mortar.
(g) 1:8
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 2.66 Cwt. 400.00 P.bag 1064.00

Sand. 26.67 Cft. 2425.00 % Cft. 646.75


TOTAL 8460.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 846.07
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9306.82
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2772.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 3050.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12357.03
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4082.70
S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(ii) In lime cement sand mortar.
(a) 1:1:6
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.60 Mand 375.00 P.Mand 600.00

Cement. 3.20 Cwt. 400.00 P.bag 1280.00

Sand. 24.00 Cft. 2425.00 % Cft. 582.00


TOTAL 9212.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 921.20
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 10133.20
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL
_____________________________ 2772.92
______ _____ ______ _______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B "
_____________________________ 3050.21
______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 13183.41
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4373.05
S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(ii) In lime cement sand mortar.
(b) 1:1:7
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.42 Mand 375.00 P.Mand 532.50

Cement. 2.85 Cwt. 400.00 P.bag 1140.00

Sand. 24.78 Cft. 2425.00 % Cft. 600.92


TOTAL 9023.42
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 902.34
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9925.76
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Sundries. 10.00 % #VALUE!
_____________________________ ______ _____ ______ _______ _________
TOTAL #VALUE!
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % #VALUE!
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " #VALUE!
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) #VALUE!
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4280.20
S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(ii) In lime cement sand mortar.
(c) 1:1:8
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.28 Mand 375.00 P.Mand 480.00

Cement. 2.56 Cwt. 400.00 P.bag 1024.00


Sand. 25.60 Cft. 2425.00 % Cft. 620.80
TOTAL 8874.80
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 887.48
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9762.28
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos:


P.day. 250.00
125.00
Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2772.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 3050.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12812.49
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4204.95
S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(ii) In lime cement sand mortar.
(d) 1:1:9
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.16 Mand 375.00 P.Mand 435.00

Cement. 2.32 Cwt. 400.00 P.bag 928.00


Sand. 26.20 Cft. 2425.00 % Cft. 635.35
TOTAL 8748.35
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 874.84
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9623.19
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL
_____________________________ ______ _____ ______ 2772.92
_______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B "
_____________________________ ______ _____ ______ 3050.21
_______ _________
TOTAL (MATERIAL + LABOUR) 12673.39
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4141.95
S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(ii) In lime cement sand mortar.
(e) 1:1:10
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.07 Mand 375.00 P.Mand 401.25


Cement. 2.14 Cwt. 400.00 P.bag 856.00

Sand. 26.66 Cft. 2425.00 % Cft. 646.51


TOTAL 8653.76
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 865.38
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9519.13
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: P.day.


250.00 125.00
Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2772.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 3050.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12569.34
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4094.75
S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(iii In lime sand surkhi mortar.
1:1:1
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.65 Mand 375.00 P.Mand 1743.75


Sand. 11.67 Cft. 400.00 % Cft. 46.68

Surkhi. 11.67 Cft. 2250.00 % Cft. 262.58


TOTAL 8803.01
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 880.30
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9683.31
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2772.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit
_____________________________ 10.00
______ _____ ______ %
_______ 277.29
_________
TOTAL PART " B "
_____________________________ 3050.21
______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) ______ _____ ______ _______ _________
_____________________________ 12733.51
Total material & labour for 100 Cft. Rs: 4029.30
S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(iv) In lime sand mortar.
1:2
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00
Slaked lime. 4.67 Mand 375.00 P.Mand 1751.25

Sand. 23.33 Cft. 2425.00 % Cft. 565.75


TOTAL 9067.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 906.70
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9973.70
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2772.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 3050.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 13023.91
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4038.65
S/N D E S C R I P T I O N.

5. Pacca brick work in grund floor (including striking of joints)


(v) In lime surkhi mortar.
(a) 2:3
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00
Slaked lime. 5.60 Mand 375.00 P.Mand 2100.00

Surkhi. 21.00 Cft. 2250.00 % Cft. 472.50


TOTAL 9322.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 932.25
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 10254.75
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2772.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 3050.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 13304.96
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 13304.96
S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor including striking of joints)


(v) In lime surkhi mortar.
(b) 1:2
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.67 Mand 375.00 P.Mand 1751.25

Surkhi. 23.33 Cft. 2250.00 % Cft. 524.93


TOTAL 9026.18
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 902.62
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9928.79
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2772.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 3050.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12979.00
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4064.30
S/N D E S C R I P T I O N.

5. Pacca brick work in ground floor (including striking of joints)


(v) In lime surkhi mortar.
(c) 1:3
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 3.50 Mand 375.00 P.Mand 1312.50

Surkhi. 26.25 Cft. 2250.00 % Cft. 590.63


TOTAL 8653.13
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 865.31
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9518.44
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Cement Mortar.
Skilled Coolies. 0.833 Nos: 250.00 P.day. 208.33

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2772.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 3050.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12568.65
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3943.65
S/N D E S C R I P T I O N.

6. Add extra labour in item No:5 for brick work.


(i) In First floor.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 0.25 Nos: 450.00 P.day. 112.50

Skilled Coolies. 1.00 Nos: 250.00 P.day. 250.00


_____________________________ ______ _____ ______ _______ _________
Rs: 362.50
_____________________________ ______ _____ ______ _______ _________
Sundries.
_____________________________ ______ _____ ______ %
10.00 _______ 36.25
_________
TOTAL 398.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 39.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 438.63
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 226.90
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

6. Add extra labour in item No:5 for brick work.


(ii) In Second floor.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.

Masons. 0.75 Nos: 450.00 P.day. 337.50

Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00


_____________________________ ______ _____ ______ _______ _________
Rs: 837.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 83.75
_____________________________ ______ _____ ______ _______ _________
TOTAL 921.25
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 92.13
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1013.38
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 535.45
S/N D E S C R I P T I O N.

6. Add extra labour in item No:5 for brick work.


(iii) In Third Floor.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.

Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00


_____________________________ ______ _____ ______ _______ _________
Rs: 1312.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 131.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1443.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 144.38
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1588.13
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 844.00
S/N D E S C R I P T I O N.

6. Add extra labour in item No:5 for brick work.


(iv) In Fourth and subsequent Floor.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.25 Nos: 450.00 P.day. 1012.50

Skilled Coolies. 4.50 Nos: 250.00 P.day. 1125.00


_____________________________ ______ _____ ______ _______ _________
Rs: 2137.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 213.75
_____________________________ ______ _____ ______ _______ _________
TOTAL 2351.25
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 235.13
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2586.38
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 1388.50
S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(i) In cement sand mortar.
(a) 1:2
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 8.00 Cwt. 400.00 P.bag 3200.00

Sand. 20.00 Cft. 2425.00 % Cft. 485.00


TOTAL 10435.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 1043.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 11478.50
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 14201.00
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 5045.15
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(i) In cement sand mortar.
(b) 1:3
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 6.00 Cwt. 400.00 P.bag 2400.00

Sand. 22.50 Cft. 2425.00 % Cft. 545.63


TOTAL 9695.63
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 969.56
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 10665.19
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 13387.69
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4625.80
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(i) In cement sand mortar.
(c) 1:4
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 4.80 Cwt. 400.00 P.bag 1920.00

Sand. 24.00 Cft. 2425.00 % Cft. 582.00


TOTAL 9252.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 925.20
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 10177.20
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12899.70
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4374.15
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.
7 Pacca brick work other than buildings (i/c striking of joints)
(i) In cement sand mortar.
(d) 1:5
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 4.00 Cwt. 400.00 P.bag 1600.00

Sand. 25.00 Cft. 2425.00 % Cft. 606.25


TOTAL 8956.25
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 895.63
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9851.88
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12574.38
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4206.40
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.
7 Pacca brick work other than buildings (i/c striking of joints)
(i) In cement sand mortar.
(e) 1:6
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 3.44 Cwt. 400.00 P.bag 1376.00

Sand. 25.70 Cft. 2425.00 % Cft. 623.23


TOTAL 8749.23
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 874.92
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9624.15
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12346.65
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4089.00
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(i) In cement sand mortar.
(f) 1:7
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 3.00 Cwt. 400.00 P.bag 1200.00

Sand. 26.50 Cft. 2425.00 % Cft. 642.63


TOTAL 8592.63
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 859.26
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9451.89
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12174.39
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3997.70
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(i) In cement sand mortar.
(g) 1:8
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Cement. 2.66 Cwt. 400.00 P.bag 1064.00

Sand. 26.67 Cft. 2425.00 % Cft. 646.75


TOTAL 8460.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 846.07
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9306.82
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12029.32
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3925.40
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(ii) In lime cement sand mortar.
(a) 1:1:6
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.60 Mand 375.00 P.Mand 600.00

Cement. 3.20 Cwt. 400.00 P.bag 1280.00

Sand. 24.00 Cft. 2425.00 % Cft. 582.00


TOTAL 9212.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 921.20
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 10133.20
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00


_____________________________ ______ _____ ______ _______ _________
Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12855.70
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4215.75
S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(ii) In lime cement sand mortar.
(b) 1:1:7
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.42 Mand 375.00 P.Mand 532.50

Cement. 2.85 Cwt. 400.00 P.bag 1140.00

Sand. 24.78 Cft. 2425.00 % Cft. 600.92


TOTAL 9023.42
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 902.34
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9925.76
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12648.26
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4122.90
S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(ii) In lime cement sand mortar.
(c) 1:1:8
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.28 Mand 375.00 P.Mand 480.00

Cement. 2.56 Cwt. 400.00 P.bag 1024.00

Sand. 25.60 Cft. 2425.00 % Cft. 620.80


TOTAL 8874.80
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 887.48
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9762.28
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12484.78
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4047.65
S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(ii) In lime cement sand mortar.
(d) 1:1:9
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.16 Mand 375.00 P.Mand 435.00

Cement. 2.32 Cwt. 400.00 P.bag 928.00

Sand. 26.20 Cft. % Cft.


2425.00 635.35
_____________________________ ______ _____ ______ _______ _________
TOTAL 8748.35
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 874.84
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9623.19
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00


_____________________________ ______ _____ ______ _______ _________
Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12345.69
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3984.65
S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(ii) In lime cement sand mortar.
(e) 1:1:10
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 1.07 Mand 375.00 P.Mand 401.25

Cement. 2.14 Cwt. 400.00 P.bag 856.00

Sand. 26.66 Cft. 2425.00 % Cft. 646.51

TOTAL 8653.76
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 865.38
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9519.13
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 2250.00
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12241.63
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3937.40
S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(iii In lime sand surkhi mortar.
(a) 1:1:1
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.65 Mand 375.00 P.Mand 1743.75

Sand. 11.67 Cft. 400.00 % Cft. 46.68

Surkhi. 11.67 Cft. 2425.00 % Cft. 283.00


TOTAL 8823.43
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 882.34
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9705.77
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12428.27
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3859.20
S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(iv) In lime sand mortar.
1:2
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.67 Mand 375.00 P.Mand 1751.25

Sand. 23.33 Cft. 2425.00 % Cft. 565.75


TOTAL 9067.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 906.70
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9973.70
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12696.20
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3881.35
S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(v) In lime surkhi mortar.
(a) 2:3
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 5.60 Mand 375.00 P.Mand 2100.00

Surkhi. 21.00 Cft. 2250.00 % Cft. 472.50


TOTAL 9322.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 932.25
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 10254.75
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12977.25
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4002.90
S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(v) In lime surkhi mortar.
(b) 1:2
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 4.67 Mand 375.00 P.Mand 1751.25

Surkhi. 23.33 Cft. 2250.00 % Cft. 524.93


TOTAL 9026.18
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 902.62
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9928.79
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. %
10.00 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12651.29
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3907.00
S/N D E S C R I P T I O N.

7 Pacca brick work other than buildings (i/c striking of joints)


(v) In lime surkhi mortar.
(c) 1:3
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 1350 Nos: 5000.00 %0 Nos: 6750.00

Slaked lime. 3.50 Mand 375.00 P.Mand 1312.50

Surkhi. 26.25 Cft. 2250.00 % Cft. 590.63


TOTAL 8653.13
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 865.31
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9518.44
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

For Cement Mortar.


Skilled Coolies. 1.000 Nos: 250.00 P.day. 250.00

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12240.94
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3786.35
S/N D E S C R I P T I O N.
8. Pacca brick work in mud mortar other than building.
Extra labour for every 5 feet additional hieght.

_____ _____________________________ ______ _____ ______ _______ _________


(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 0.25 Nos: 450.00 P.day. 112.50

Skilled Coolies. 1.00 Nos: P.day.250.00


250.00
Rs: 362.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 36.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 398.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 39.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 438.63
_____________________________ ______ _____ ______ _______ _________
Labour rate for 100 Cft. Rs: 226.90
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________


S/N D E S C R I P T I O N.
9. Extra labour for arch work in brick masonary including labour
for centering and decentering.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 1.50 Nos: 450.00 P.day. 675.00
Skilled Coolies. 0.50 Nos: 250.00 P.day. 125.00
_____________________________ ______ _____ ______ _______ _________
Rs: 800.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 80.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 880.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 88.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 968.00
_____________________________ ______ _____ ______ _______ _________
Labour rate for 100 Cft. Rs: 562.65
_____ _____________________________ ______ _____ ______ _______ _________

S/N D E S C R I P T I O N.
10. Extra for pacca brick in staining of wells or any circular
masonary.
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 82 Nos: 5000.00 %0 Nos: 410.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 410.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 41.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 451.00
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 1.25 Nos:
P.day. 450.00 562.50
_____________________________ ______ _____ _______ _________
Rs: 562.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 56.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 618.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 61.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 680.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 1131.63
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 516.60
_____ _____________________________ ______ _____ ______ _______ _________
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.
11. Extra labour for profile and flared walls.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 0.43 Nos: 450.00 P.day. 193.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 19.35
_____________________________ ______ _____ ______ _______ _________
TOTAL 212.85
Contractor's profit 10.00 % 21.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 234.14
_____________________________ ______ _____ ______ _______ _________
Labour rate for 100 Cft. Rs: 140.50
_____ _____________________________ ______ _____ ______ _______ _________
12 Extra labour for pacca brick work in piers & abutments.
(i) From 10' to 20' Hieght.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 0.12 Nos: 450.00 P.day. 54.00
Skilled Coolies. 0.50 250.00 P.day. 125.00
_____________________________ ______ _____ ______ _______ _________
Rs: 179.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 17.90
_____________________________ ______ _____ ______ _______ _________
TOTAL 196.90
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 19.69
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 216.59
_____________________________ ______ _____ ______ _______ _________
Labour rate for 100 Cft. Rs: 216.59
_____ _____________________________ ______ _____ ______ _______ _________
12 Extra labour for pacca brick work in piers & abutments.
(ii) Above 20' Hieght.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 0.25 Nos: 450.00 P.day. 112.50
Skilled Coolies. 1.00 250.00 P.day. 250.00
_____________________________ ______ _____ ______ _______ _________
TOTAL Rs: 362.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 36.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 398.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 39.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 438.63
_____________________________ ______ _____ ______ _______ _________
Labour rate for 100 Cft. Rs: 226.90
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________


S/N D E S C R I P T I O N.

13. Reinforced brick work in lintels of openings laid in 1:3 cement


mortar including all labour, material, forms, moulds, lifting
and shuttering etc, but excluding cost and labour of steel
reinforcement which shall be paid for separately.
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
Considering lintel over
verandah opening say 1.5 ft
* 10' * 0.75 =11.75 Cft.
Pacca bricks. 113 Nos: 5000.00 %0 Nos: 565.00
Cement. 1.23 Cwt. 400.00 P.bag 492.00
Sand. 4.60 Cft. 2425.00 % Cft. 111.55
Centering & shuttering 0.14 Cft. 1700.00 P.Cft 238.00
(Partal woood for
centering & shuttering
10'*15'*0.2' can be used
for 20 times)
TOTAL 1406.55
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 140.66
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 1547.21
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 0.75 Nos: 450.00 P.day. 337.50

Skilled Coolies. 1.25 Nos: 250.00 P.day. 312.50


Bahishti. 0.250 Nos: P.day.
250.00 62.50
Rs: 712.50
_____________________________ ______ _____ ______ _______ _________
Sundries.
_____________________________ ______ _____ ______ %
10.00 _______ 71.25
_________
TOTAL 783.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 78.38
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 76.63 862.13
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 2409.33
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 11.25 Cft. Rs: 2409.33
Total material & labour for one Cft. Rs: 214.16
Total material & labour for one Cft. Say Rs: 214.16
S/N D E S C R I P T I O N.
14 Dressing of chamfering of bricks.
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 3.00 Nos: 450.00 P.day. 1350.00
Cooly. 0.34 _____
_____________________________ ______ P.day. _________
250.00 _______
______ 85.00
TOTAL Rs: 1435.00
_____________________________ ______ _____ ______ _______ _________
Sundries.
_____________________________ ______ _____ ______ %
10.00 _______ 143.50
_________
TOTAL 1578.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 157.85
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B "
_____________________________ 1736.35
______ _____ ______ _______ _________
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(i) In Mud Mortar.
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00
Earth. 8.75 Cwt. 500.00 % Cft. 43.75
_____________________________ ______ _____ ______ _______ _________
TOTAL 1733.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 173.38
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 1907.13
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.00 Nos: 450.00 P.day. 450.00
Skilled Coolies. 1.83 Nos: 250.00 P.day. 457.50
Bahishti. 0.230 Nos: 250.00 P.day. 57.50
_____________________________ ______ _____ ______ _______ _________
Rs: 965.00
_____________________________ ______ _____ ______ _______ _________
Sundries.
_____________________________ 10.00
______ _____ ______ %
_______ 96.50
_________
TOTAL 1061.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 106.15
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1167.65
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 3074.78
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1082.55
S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(ii) In cement sand mortar.
(a) 1:2
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Cement. 2.00 Cwt. 400.00 P.bag 800.00

Sand. 5.00 Cft. 2425.00 % Cft. 121.25


TOTAL 2611.25
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 261.13
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2872.38
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00


_____________________________ ______ _____ ______ _______ _________
Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 4400.00
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1709.35
S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(ii) In cement sand mortar.
(b) 1:3
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Cement. 1.50 Cwt. 400.00 P.bag 600.00

Sand. 5.60 Cft. % Cft.


2425.00 135.80
_____________________________ ______ _____ ______ _______ _________
TOTAL 2425.80
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 242.58
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2668.38
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00


Bahishti. 0.380 Nos: 250.00 P.day. 95.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 4196.01
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 4196.01
S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(ii) In cement sand mortar.
(c) 1:4
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Cement. 1.20 Cwt. 400.00 P.bag 480.00

Sand. 6.00 Cft. 2425.00 % Cft. 145.50


TOTAL 2315.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 231.55
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2547.05
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00


Bahishti. 0.380 Nos: 250.00 P.day. 95.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 4074.68
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1541.60
S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(ii) In cement sand mortar.
(d) 1:5
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Cement. 1.00 Cwt. 400.00 P.bag 400.00

Sand. 6.25 Cft. 2425.00 % Cft. 151.56


TOTAL 2241.56
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 224.16
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2465.72
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00


Bahishti. 0.380 Nos: 250.00 P.day. 95.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 3993.34
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1499.65
S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(ii) In cement sand mortar.
(e) 1:6
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Cement. 0.86 Cwt. 400.00 P.bag 344.00

Sand. 6.40 Cft. 2425.00 % Cft. 155.20


TOTAL 2189.20
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 218.92
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2408.12
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50
Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 3935.75
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1470.20
S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(ii) In cement sand mortar.
(f) 1:7
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Cement. 0.75 Cwt. 400.00 P.bag 300.00

Sand. 6.58 Cft. 2425.00 % Cft. 159.57


TOTAL 2149.57
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 214.96
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2364.52
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50
Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 3892.15
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1447.30
S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(ii) In cement sand mortar.
(g) 1:8
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Cement. 0.67 Cwt. 400.00 P.bag 268.00

Sand. 6.67 Cft. 2425.00 % Cft. 161.75


TOTAL 2119.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.97
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2331.72
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 3859.35
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1430.50
S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(iii In lime cement sand mortar.
(a) 1:1:6
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 0.40 Mand 375.00 P.Mand 150.00

Cement. 0.80 Cwt. 400.00 P.bag 320.00

Sand. 6.00 Cft. 2425.00 % Cft. 145.50


TOTAL 2305.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 230.55
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2536.05
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 4063.68
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1502.00
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(iii In lime cement sand mortar.
(b) 1:1:7
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 0.36 Mand 375.00 P.Mand 135.00

Cement. 0.71 Cwt. 400.00 P.bag 284.00

Sand. 6.13 Cft. 2425.00 % Cft. 148.65


TOTAL 2257.65
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 225.77
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2483.42
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 4011.04
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1478.55
S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(iii In lime cement sand mortar.
(c) 1:1:8
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 0.33 Mand 375.00 P.Mand 123.75

Cement. 0.64 Cwt. 400.00 P.bag 256.00

Sand. 6.40 Cft. 2425.00 % Cft. 155.20


TOTAL 2224.95
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 222.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2447.45
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 3975.07
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1461.15
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________


S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(iii In lime cement sand mortar.
(d) 1:1:9
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 0.29 Mand 375.00 P.Mand 108.75

Cement. 0.58 Cwt. 400.00 P.bag 232.00

Sand. 6.50 Cft. 2425.00 % Cft. 157.63

_____________________________ ______ _____ ______ _______ _________


TOTAL 2188.38
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 218.84
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2407.21
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00


_____________________________ ______ _____ ______ _______ _________
Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 3934.84
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1444.05
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(iii In lime cement sand mortar.
(e) 1:1:10
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 0.27 Mand 375.00 P.Mand 101.25

Cement. 0.54 Cwt. 400.00 P.bag 216.00

Sand. 6.70 Cft. 2425.00 % Cft. 162.48


TOTAL 2169.73
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 216.97
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2386.70
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00


_____________________________ ______ _____ ______ _______ _________
Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 3914.32
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1433.90
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________


S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(iv) In lime sand surkhi mortar.
1:1:1
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 1.17 Mand 375.00 P.Mand 438.75

Sand. 2.92 Cft. 2425.00 % Cft. 70.81

Surkhi. 2.92 Cft. 2250.00 % Cft. 65.70


TOTAL 2265.26
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 226.53
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2491.79
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: P.day.


250.00 95.00
Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 4019.41
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1421.95
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________


S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(v) In lime sand mortar.
1:2
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 1.17 Mand 375.00 P.Mand 438.75

Sand. 5.58 Cft. 2425.00 % Cft. 135.32


TOTAL 2264.07
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 226.41
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2490.47
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 4018.10
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1417.70
S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(vi) In lime surkhi mortar.
(a) 2:3
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 1.40 Mand 375.00 P.Mand 525.00

Surkhi. 5.25 Cft. 2250.00 % Cft. 118.13


TOTAL 2333.13
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 233.31
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2566.44
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 4094.06
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1448.80
S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(vi) In lime surkhi mortar.
(b) 1:2
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 1.17 Mand 375.00 P.Mand 438.75

Surkhi. 5.83 Cft. 2250.00 % Cft. 131.18


TOTAL 2259.93
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 225.99
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2485.92
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: 250.00 P.day. 95.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 4013.54
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1425.10
S/N D E S C R I P T I O N.

15 Perforated pacca brick walling 4-1/2" thick in ground floor.


(vi) In lime surkhi mortar.
(c) 1:3
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 338 Nos: 5000.00 %0 Nos: 1690.00

Slaked lime. 0.875 Mand 375.00 P.Mand 328.13


Surkhi. 6.56 Cft. 2250.00 % Cft. 147.60
TOTAL 2165.73
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 216.57
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 2382.30
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.25 Nos: 450.00 P.day. 562.50

Skilled Coolies. 2.42 Nos: 250.00 P.day. 605.00

Bahishti. 0.380 Nos: P.day.


250.00 95.00
Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 3909.92
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1394.65

_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________


S/N D E S C R I P T I O N.

16. Add extra labour in item No:5 for brick work.


(i)
_____ In First floor.
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 0.12 Nos: 450.00 P.day. 54.00

Skilled Coolies. 0.50 Nos: 250.00 P.day. 125.00


_____________________________ ______ _____ ______ _______ _________
Rs: 179.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 17.90
_____________________________ ______ _____ ______ _______ _________
TOTAL 196.90
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 19.69
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 216.59
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 216.59
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

16. Add extra labour in item No:5 for brick work.


(ii) In Second floor.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.

Masons. 0.38 Nos: 450.00 P.day. 168.75

Skilled Coolies. 1.00 Nos: 250.00 P.day. 250.00


_____________________________ ______ _____ ______ _______ _________
Rs: 418.75
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 41.88
_____________________________ ______ _____ ______ _______ _________
TOTAL 460.63
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 46.06
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 506.69
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 267.70
S/N D E S C R I P T I O N.

16. Add extra labour in item No:5 for brick work.


(iii) In Third Floor.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.

Masons. 0.625 Nos: 450.00 P.day. 281.25


Skilled Coolies. 1.50 Nos: 250.00 P.day. 375.00
_____________________________ ______ _____ ______ _______ _________
Rs: 656.25
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 65.63
_____________________________ ______ _____ ______ _______ _________
TOTAL 721.88
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 72.19
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 794.06
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 422.00
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

16. Add extra labour in item No:5 for brick work.


(iv) In Fourth and subsequent Floor.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.

Masons. 1.125 Nos: 450.00 P.day. 506.25

Skilled Coolies. 2.25 Nos: 250.00 P.day. 562.50


_____________________________ ______ _____ ______ _______ _________
Rs: 1068.75
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 106.88
_____________________________ ______ _____ ______ _______ _________
TOTAL 1175.63
_____________________________ ______ _____ ______ _______ _________
Contractor's profit
_____________________________ ______ _____ ______ %
10.00 _______ 117.56
_________
TOTAL PART " B " 1293.19
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 694.25
S/N D E S C R I P T I O N.

17 Perforated pacca brick walling 9" thick in ground floor.


(i) In Mud Mortar.

_____ _____________________________ ______ _____ ______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00
Earth. 17.50 Cwt. 500.00 % Cft. 87.50
TOTAL 3462.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 346.25
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 3808.75
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.50 Nos: 450.00 P.day. 675.00

Skilled Coolies. 2.75 Nos: 250.00 P.day. 687.50

Bahishti. 0.350 Nos: 250.00 P.day. 87.50

_____________________________ ______ _____ ______ _______ _________


Rs: 1450.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 145.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 1595.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 159.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1754.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 5563.25
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1852.35
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________

S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(ii) In cement sand mortar.
(a) 1:2
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Cement. 4.00 Cwt. 400.00 P.bag 1600.00

Sand. 10.00 Cft. 2425.00 % Cft. 242.50


TOTAL 5217.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 521.75
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 5739.25
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

_____________________________ ______ _____ ______ _______ _________


Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 8038.25
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 3015.15
S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(ii) In cement sand mortar.
(b) 1:3
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Cement. 3.00 Cwt. 400.00 P.bag 1200.00

Sand. 11.25 Cft. 2425.00 % Cft. 272.81

TOTAL 4847.81
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 484.78
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 5332.59
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

_____________________________ ______ _____ ______ _______ _________


Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7631.59
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2805.50
S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(ii) In cement sand mortar.
(c) 1:4
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Cement. 2.40 Cwt. 400.00 P.bag 960.00

Sand. 12.00 Cft. 2425.00 % Cft. 291.00


TOTAL 4626.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 462.60
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 5088.60
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

_____________________________ ______ _____ ______ _______ _________


Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7387.60
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2679.65
S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(ii) In cement sand mortar.
(d) 1:5
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY
RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Cement. 2.00 Cwt. 400.00 P.bag 800.00

Sand. 12.50 Cft. % Cft.


2425.00 303.13
_____________________________ ______ _____ ______ _______ _________
TOTAL 4478.13
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 447.81
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4925.94
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

_____________________________ ______ _____ ______ _______ _________


Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7224.94
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2595.80
S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(ii) In cement sand mortar.
(e) 1:6
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Cement. 1.72 Cwt. 400.00 P.bag 688.00

Sand. 12.80 Cft. 2425.00 % Cft. 310.40

TOTAL 4373.40
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 437.34
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4810.74
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

_____________________________ ______ _____ ______ _______ _________


Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7109.74
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2536.90
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________


S/N D E S C R I P T I O N.

17 Perforated pacca brick walling 9" thick in ground floor.


(ii) In cement sand mortar.
(f) 1:7
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Cement. 1.50 Cwt. 400.00 P.bag 600.00

Sand. 13.13 Cft. % Cft.


2425.00 318.40
_____________________________ ______ _____ ______ _______ _________
TOTAL 4293.40
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 429.34
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4722.74
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

_____________________________ ______ _____ ______ _______ _________


Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7021.74
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2490.95
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________


S/N D E S C R I P T I O N.
17 Perforated pacca brick walling 9" thick in ground floor.
(ii) In cement sand mortar.
(g) 1:8
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Cement. 1.33 Cwt. 400.00 P.bag 532.00

Sand. 13.34 Cft. 2425.00 % Cft. 323.50

TOTAL 4230.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 423.05
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4653.54
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

_____________________________ ______ _____ ______ _______ _________


Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 6952.54
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2455.30
_____ _____________________________ ______ _____ ______ _______ _________

S/N D E S C R I P T I O N.
17. Perforated pacca brick walling 9" thick in ground floor.
(iii In lime cement sand mortar.
(a) 1:1:6
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 0.80 Mand 375.00 P.Mand 300.00

Cement. 1.60 Cwt. 400.00 P.bag 640.00

Sand. 12.00 Cft. 2425.00 % Cft. 291.00


TOTAL 4606.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 460.60
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 5066.60
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

_____________________________ ______ _____ ______ _______ _________


Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7365.60
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2600.45
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.
17 Perforated pacca brick walling 9" thick in ground floor.
(iii In lime cement sand mortar.
(b) 1:1:7
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 0.71 Mand 375.00 P.Mand 266.25

Cement. 1.42 Cwt. 400.00 P.bag 568.00

Sand. 12.39 Cft. 2425.00 % Cft. 300.46

_____________________________ ______ _____ ______ _______ _________


TOTAL 4509.71
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 450.97
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4960.68
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: P.day.


250.00137.50
Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7259.68
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2552.95
_____ _____________________________ ______ _____ ______ _______ _________
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(iii In lime cement sand mortar.
(c) 1:1:8
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 0.64 Mand 375.00 P.Mand 240.00

Cement. 1.28 Cwt. 400.00 P.bag 512.00

Sand. 12.80 Cft. 2425.00 % Cft. 310.40

TOTAL 4437.40
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 443.74
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4881.14
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

_____________________________ ______ _____ ______ _______ _________


_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % #VALUE!
_____________________________ ______ _____ ______ _______ _________
TOTAL #VALUE!
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % #VALUE!
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " #VALUE!
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) #VALUE!
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2516.45
S/N D E S C R I P T I O N.

17 Perforated pacca brick walling 9" thick in ground floor.


(iii In lime cement sand mortar.
(d) 1:1:9
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 0.58 Mand 375.00 P.Mand 217.50

Cement. 1.16 Cwt. 400.00 P.bag 464.00

Sand. 13.10 Cft. 2425.00 % Cft. 317.68

_____________________________ ______ _____ ______ _______ _________


TOTAL 4374.18
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 437.42
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4811.59
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7110.59
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2484.90
S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(iii In lime cement sand mortar.
(e) 1:1:10
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 0.54 Mand 375.00 P.Mand 202.50

Cement. 1.07 Cwt. 400.00 P.bag 428.00

Sand. 13.33 Cft. 2425.00 % Cft. 323.25

TOTAL 4328.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 432.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4761.63
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

_____________________________ ______ _____ ______ _______ _________


Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7060.63
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2461.85
S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(iv) In lime sand surkhi mortar.
1:1:1
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 2.33 Mand 375.00 P.Mand 873.75

Sand. 5.84 Cft. 2425.00 % Cft. 141.62

Surkhi. 5.83 Cft. % Cft.


2250.00 131.18
_____________________________ ______ _____ ______ _______ _________
TOTAL 4521.55
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 452.15
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4973.70
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

_____________________________ ______ _____ ______ _______ _________


Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7272.70
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2439.10
S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(v) In lime sand mortar.
1:2
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 2.33 Mand 375.00 P.Mand 873.75

Sand. 11.67 Cft. 2425.00 % Cft. 283.00

TOTAL 4531.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 453.17
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4984.92
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

_____________________________ ______ _____ ______ _______ _________


Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7283.92
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2432.70
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________


S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(vi) In lime surkhi mortar.
(a) 2:3
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 2.80 Mand 375.00 P.Mand 1050.00

Surkhi. 10.50 Cft. 2250.00 % Cft. 236.25


TOTAL 4661.25
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 466.13
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 5127.38
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: P.day.


250.00 137.50
Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7426.38
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2494.05
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________

S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 4-1/2" thick in ground floor.


(vi) In lime surkhi mortar.
(b) 1:2
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 2.34 Mand 375.00 P.Mand 877.50

Surkhi. 11.67 Cft. 2250.00 % Cft. 262.58

_____________________________ ______ _____ ______ _______ _________


TOTAL 4515.08
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 451.51
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4966.58
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

_____________________________ ______ _____ ______ _______ _________


Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7265.58
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2446.70
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________


S/N D E S C R I P T I O N.

17. Perforated pacca brick walling 9" thick in ground floor.


(vi) In lime surkhi mortar.
(c) 1:3
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00

Slaked lime. 1.750 Mand 375.00 P.Mand 656.25

Surkhi. 13.12 Cft. 2250.00 % Cft. 295.20


TOTAL 4326.45
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 432.65
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4759.10
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00

Skilled Coolies. 3.63 Nos: 250.00 P.day. 907.50

Bahishti. 0.550 Nos: 250.00 P.day. 137.50

Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7058.10
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2385.75
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________

S/N D E S C R I P T I O N.

18. Add extra labour in item No:17 for brick work.


(i) In First floor.
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.

Masons. 0.188 Nos: 450.00 P.day. 84.38

Skilled Coolies. 0.75 Nos: 250.00 P.day. 187.50


_____________________________ ______ _____ ______ _______ _________
Rs: 271.88
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 27.19
_____________________________ ______ _____ ______ _______ _________
TOTAL 299.06
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 29.91
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 328.97
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 170.15
S/N D E S C R I P T I O N.

18. Add extra labour in item No:5 for brick work.


(ii) In Second floor.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.

Masons. 0.563 Nos: 450.00 P.day. 253.13

Skilled Coolies. 1.50 Nos: 250.00 P.day. 375.00


_____________________________ ______ _____ ______ _______ _________
Rs: 628.13
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 62.81
_____________________________ ______ _____ ______ _______ _________
TOTAL 690.94
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 69.09
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 760.03
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 401.55
S/N D E S C R I P T I O N.

18. Add extra labour in item No:17 for brick work.


(iii) In Third Floor.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.

Masons. 0.938 Nos: 450.00 P.day. 421.88

Skilled Coolies. 2.25 Nos: 250.00 P.day. 562.50


_____________________________ ______ _____ ______ _______ _________
Rs: 984.38
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 98.44
_____________________________ ______ _____ ______ _______ _________
TOTAL 1082.81
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 108.28
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1191.09
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 633.00
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

18. Add extra labour in item No:17 for brick work.


(iv) In Fourth and subsequent Floor.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.688 Nos: 450.00 P.day. 759.38

Skilled Coolies. 3.38 Nos: 250.00 P.day. 843.75


_____________________________ ______ _____ ______ _______ _________
Rs: 1603.13
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 160.31
_____________________________ ______ _____ ______ _______ _________
TOTAL 1763.44
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 176.34
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1939.78
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1041.35
S/N D E S C R I P T I O N.

19. Fire brick masonary in fire clay mortar.


(i) Upto 20 feet hieght including all charges.

_____ _____________________________ ______ _____ ______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Fire clay bricks 9" * 1350 Nos: 5300.0 %0 Nos: 7155.00
4-1/2"* 3"
Aluminia Cement. 8.800 Cwt. 650.00 P.bag 5720.00

Crushed fire bricks graded 22.00 Cft. 2500.00 % Cft. 550.00


as sand.
TOTAL 13425.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 1342.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 14767.50
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 3.00 Nos: 450.00 P.day. 1350.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


For Mortar.
Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50

Rs: 2475.00
_____________________________ ______ _____ ______ _______ _________
Sundries. %
10.00 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL 2722.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 272.25
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2994.75
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 17762.25
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 6928.35
S/N D E S C R I P T I O N.
19. Fire brick masonary in fire clay mortar.
(ii) Extra for every 5 feet additional hieght.

(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 0.25 Nos: 450.00 P.day. 112.50

Skilled Coolies.
_____________________________ 1.00 Nos:
______ 250.00 P.day.
_____ ______ 250.00
_______ _________
Rs: 362.50
_____________________________ ______ _____ ______ _______ _________
Sundries.
_____________________________ 10.00
______ _____ ______ %
_______ 36.25
_________
TOTAL
_____________________________ ______ _____ ______ _______ _________398.75
Contractor's profit 10.00 % 39.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 438.63
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 226.90
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________


S/N D E S C R I P T I O N.

20. Pacca brick walling laid in 1:3 cement sand mortar reinforced
with 1" wide 18 gauge hoop iron:-
(i) 4-1/2" thick walling with hoop iron bonding 6" apart.

_____ _____________________________ ______ _____ ______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca bricks 9" * 4-1/2"*3" 525 Nos: 5000.00 %0 Nos: 2625.00

Cement. 2.400 Cwt. 400.00 P.bag 960.00

Sand. 9.00 Cft. 2425.00 % Cft. 218.25


Hoop Iron. 45.00 Lbs: 2500.00 P.Cwt 1004.46

_____________________________ ______ _____ ______ _______ _________


TOTAL 4807.71
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 480.77
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 5288.49
_____________________________ ______ _____ ______ _______ _________

(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.00 Nos: 450.00 P.day. 450.00

Skilled Coolies. 1.42 Nos: 250.00 P.day. 355.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50

Blacksmith. 0.10 Nos: 450.00 P.day. 45.00

_____________________________ ______ _____ ______ _______ _________


Rs: 912.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 91.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1003.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 100.38
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1104.13
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 6392.61
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 6392.61
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________


S/N D E S C R I P T I O N.

20. Pacca brick walling laid in 1:3 cement sand mortar reinforced
with 1" wide 18 gauge hoop iron:-
(ii) 4-1/2" thick walling with hoop iron bonding 12" apart.

(A) MATERIAL QUANTITY


RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca bricks 9" * 4-1/2"*3" 525 Nos: 5000.00 %0 Nos: 2625.00

Cement. 2.400 Cwt. 400.00 P.bag 960.00

Sand. 9.00 Cft. 2425.00 % Cft. 218.25

Hoop Iron. 22.50 Lbs: 2500.00 P.Cwt 502.23

_____________________________ ______ _____ ______ _______ _________


TOTAL 4305.48
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 430.55
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4736.03
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.00 Nos: 450.00 P.day. 450.00

Skilled Coolies. 1.42 Nos: 250.00 P.day. 355.00

Bahishti. 0.250 Nos: 250.00 P.day. 62.50


Blacksmith. 0.10 Nos: 450.00 P.day. 45.00

Rs: 912.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 91.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1003.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit
_____________________________ 10.00
______ _____ ______ %
_______ 100.38
_________
TOTAL PART " B " 1104.13
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 5840.16
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 5840.16
S/N D E S C R I P T I O N.

20. Pacca brick walling laid in 1:3 cement sand mortar reinforced
with 1" wide 18 gauge hoop iron:-
(iii) 3" thick walling with hoop iron bonding 6" apart.

_____ _____________________________ ______ _____ ______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca bricks 9" * 4-1/2"*3" 350 Nos: 5000.00 %0 Nos: 1750.00

Cement. 1.800 Cwt. 400.00 P.bag 720.00

Sand. 6.50 Cft. 2425.00 % Cft. 157.63

Hoop Iron. 45.00 Lbs: 2500.00 P.Cwt 1004.46


TOTAL 3632.09
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 363.21
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 3995.30
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 0.75 Nos: 450.00 P.day. 337.50

Skilled Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.200 Nos: 250.00 P.day. 50.00


Blacksmith. 0.15 Nos: 450.00 P.day. 67.50

Rs: 705.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 70.50
_____________________________ ______ _____ ______ _______ _________
TOTAL 775.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 77.55
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 853.05
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 4848.35
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 4848.35
S/N D E S C R I P T I O N.

20. Pacca brick walling laid in 1:3 cement sand mortar reinforced
with 1" wide 18 gauge hoop iron:-
(iv) 3" thick walling with hoop iron bonding 12" apart.

_____ _____________________________ ______ _____ ______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca bricks 9" * 4-1/2"*3" 350 Nos: 5000.00 %0 Nos: 1750.00

Cement. 1.800 Cwt. 400.00 P.bag 720.00

Sand. 6.50 Cft. 2425.00 % Cft. 157.63

Hoop Iron. 20.00 Lbs: 2500.00 P.Cwt 446.43


TOTAL 3074.05
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 307.41
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 3381.46
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 0.75 Nos: 450.00 P.day. 337.50

Skilled Coolies. 1.00 Nos: 250.00 P.day. 250.00

Bahishti. 0.200 Nos: 250.00 P.day. 50.00


Blacksmith. 0.10 Nos: 450.00 P.day. 45.00
_____________________________ ______ _____ ______ _______ _________
Rs: 682.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 68.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 750.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 75.08
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 825.83
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 4207.28
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 4207.28
S/N D E S C R I P T I O N.

21. Ghilafi work 1' - 1-1/2" thick wall.

_____ _____________________________ ______ _____ ______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
(i) Material same as per Item
No:1(i)-(A)/2 3808.75

(ii) Material same as per Item


No:23-(A)/2 987.25
TOTAL PART " A " 4796.00
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 3.67 Nos: 250.00 P.day. 917.50

Bahishti. 0.500 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 1942.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 194.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 2136.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 213.68
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2350.43
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7146.43
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2563.50
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________

S/N D E S C R I P T I O N.

22. Dry brick pitching.

_____ _____________________________ ______ _____ ______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
First class burnt bricks. 1350 Nos: 5000.00 %0 Nos: 6750.00

_____________________________ ______ _____ ______ _______ _________


TOTAL 6750.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 675.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 7425.00
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________

Masons. 1.00 Nos: 450.00 P.day. 450.00

Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00


_____________________________ ______ _____ ______ _______ _________
Rs: 950.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 95.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 1045.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 104.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1149.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 8574.50
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 8574.50
_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________


S/N D E S C R I P T I O N.

23. Sundried bricks in mud mortar.

_____ _____________________________ ______ _____ ______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Sun dried bricks. 1350 Nos: 1200.00 %0 Nos: 1620.00

Stiff clay. 35.00 Cft. 500.00 % Cft. 175.00

_____________________________ ______ _____ ______ _______ _________


TOTAL 1795.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 179.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 1974.50
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________

Masons. 1.50 Nos: 450.00 P.day. 675.00

Skilled Coolies. 3.50 Nos: 250.00 P.day. 875.00


Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ ______ _____ ______ _______ _________


Rs: 1612.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 161.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1773.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 177.38
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1951.13
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 3925.63
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 1819.40
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.

24. Pise wall. (Mud Wall)


(B) LABOUR
_____________________________ ______ _____ ______ _______ _________

Cooly skilled. 1.00 Nos: 250.00 P.day. 250.00

Coolies. 1.50 Nos: 250.00 P.day. 375.00

Bahishti. 0.50 Nos: P.day.


250.00 125.00
Rs: 750.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 75.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 825.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 82.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 907.50
_____________________________ ______ _____ ______ _______ _________
Labour rate for 100 Cft. Rs: 907.50
S/N D E S C R I P T I O N.

25. Eave brick moulded, weathered and throated with back bricks or
drip course cornice in 1:3 cement mortar.
(i) 3" thick drip coarse cornice.
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Assume for 100 Rft.
Moulded bricks. 280 Nos: 4800.0 %0 Nos: 1344.00
(100*12*2/9 + 13)
Cement for laying and 1.50 Cwt. 400.00 P.bag 600.00
plastering.
Sand. 5.00 Cft. 2425.00 % Cft. 121.25
Deduct cost of ordinary 140.0 Nos: 5000.00 %0 Nos: -700.00
bricks. 280/2 =140 Nos:

_____________________________ ______ _____ ______ _______ _________


TOTAL 1365.25
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 136.53
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 1501.78
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________

Masons. 1.75 Nos: 450.00 P.day. 787.50

Skilled Coolies. 1.75 Nos: 250.00 P.day. 437.50

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

_____________________________ ______ _____ ______ _______ _________


Rs: 1287.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 128.75
_____________________________ ______ _____ ______ _______ _________
TOTAL 1416.25
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 141.63
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 15.58 1557.88
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 3059.65
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Rft. Rs: 3059.65
Total material & labour for one Rft. Rs: 30.60
Total material & labour for one Rft. say Rs: 16.05

_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________


S/N D E S C R I P T I O N.

25. Eave brick moulded, weathered and throated with back bricks or
drip course cornice in 1:3 cement mortar.
(ii) 4-1/2" thick drip coarse cornice.

_____ _____________________________ ______ _____ ______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Assume for 100 Rft.
Moulded bricks. 420 Nos: 4800.0 %0 Nos: 2016.00
(100*12/3 + 20)
Cement for laying and 1.75 Cwt. 400.00 P.bag 700.00
plastering.
Sand. 6.00 Cft. 2425.00 % Cft. 145.50
Deduct cost of ordinary 210.0 Nos: 5000.00 %0 Nos: -1050.00
bricks. 420/2 =140 Nos:

TOTAL 1811.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 181.15
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 1992.65
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.25 Nos: P.day.


250.00 62.50
Rs: 1462.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 146.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1608.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 160.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 17.70 1769.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 3762.28
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Rft. Rs: 3762.28
Total material & labour for one Rft. Rs: 37.62
Total material & labour for one Rft. say Rs: 19.8
S/N D E S C R I P T I O N.

25. Eave brick moulded, weathered and throated with back bricks or
drip course cornice in 1:3 cement mortar.
(iii 4-1/2" thick eave brick with back brick.

_____ _____________________________ ______ _____ ______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Assume for 100 Rft.
Moulded bricks i/c wastage. 465 Nos: 4800.0 %0 Nos: 2232.00
Ordinary bricks. 465 Nos: 5000.00 %0 Nos: 2325.00
Cement for laying and 1.20 Cwt. 400.00 P.bag 480.00
plastering.
Sand. 5.00 Cft. 2425.00 % Cft. 121.25

_____________________________ ______ _____ ______ _______ _________


TOTAL 5158.25
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 515.83
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 5674.08
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________

Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 1.00 Nos:


P.day. 250.00
250.00
Rs: 1150.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 115.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 1265.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 126.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 13.92 1391.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7065.58
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Rft. Rs: 7065.58
Total material & labour for one Rft. Rs: 70.66
Total material & labour for one Rft. say Rs: 26.60
S/N D E S C R I P T I O N.

26. Laying dressed or moulded brick cornices in 1:6 cement mortar,


plastering or pointing complete.
(i) One brick.

_____ _____________________________ ______ _____ ______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Assume for 100 Rft. Moulded bricks:- Bricks = 268 Nos:
Wastage 10% = 27 Nos: Total = 300 Nos: The rate is only for
projected portion so that the bricks will be=300*1/5 = 60 Nos:
_____________________________ ______ _____ ______ _______ _________
Bricks. 60 Nos: 5000.00 %0 Nos: 300.00
Cement for laying and 1.60 Cwt. 400.00 P.bag 640.00
plastring.
Sand. 6.00 Cft. 2425.00 % Cft. 145.50

_____________________________ ______ _____ ______ _______ _________


TOTAL 1085.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 108.55
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 1194.05
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________

Masons. 2.00 Nos: 450.00 P.day. 900.00

Skilled Coolies. 2.00 Nos: 250.00 P.day. 500.00

Bahishti. 0.25 Nos: P.day.


250.00 62.50
Rs: 1462.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 146.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1608.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 160.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 17.70 1769.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 2963.68
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Rft. Rs: 2963.68
Total material & labour for one Rft. Rs: 29.64
Total material & labour for one Rft. say Rs: 14.25
S/N D E S C R I P T I O N.

26. Laying dressed or moulded brick cornices in 1:6 cement mortar,


plastering or pointing complete.
(ii) Two bricks.

_____ _____________________________ ______ _____ ______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Bricks. 175 Nos: 5000.00 %0 Nos: 875.00

Cement for laying and 5.00 Cwt. 400.00 P.bag 2000.00


plastring.

Sand. 18.00 Cft. 2425.00 % Cft. 436.50

TOTAL 3311.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 331.15
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 3642.65
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________

Masons. 3.00 Nos: 450.00 P.day. 1350.00

Skilled Coolies. 3.00 Nos: 250.00 P.day. 750.00

Bahishti. 0.25 Nos: 250.00 P.day. 62.50

Rs: 2162.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 216.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 2378.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 237.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 26.17 2616.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 6259.28
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Rft. Rs: 6259.28
Total material & labour for one Rft. Rs: 62.59
Total material & labour for one Rft. say Rs: 28.25
S/N D E S C R I P T I O N.

26. Laying dressed or moulded brick cornices in 1:6 cement mortar,


plastering or pointing complete.
(iii Three bricks.

_____ _____________________________ ______ _____ ______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Bricks. 270 Nos: 5000.00 %0 Nos: 1350.00

Cement for laying and 8.00 Cwt. 400.00 P.bag 3200.00


plastring.

Sand. 28.00 Cft. 2425.00 % Cft. 679.00

_____________________________ ______ _____ ______ _______ _________


TOTAL 5229.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 522.90
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 5751.90
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________

Masons. 4.00 Nos: 450.00 P.day. 1800.00

Skilled Coolies. 4.00 Nos: 250.00 P.day. 1000.00

Bahishti. 0.33 Nos:P.day.250.0082.50


Rs: 2882.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 288.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 3170.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 317.08
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 34.88 3487.83
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 9239.73
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Rft. Rs: 9239.73
Total material & labour for one Rft. Rs: 92.40
Total material & labour for one Rft. say Rs: 41.15
S/N D E S C R I P T I O N.

26 Laying dressed or moulded brick cornices in 1:6 cement mortar,


plastering or pointing complete.
(iv) Four bricks.

_____ _____________________________ ______ _____ ______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Bricks. 580 Nos: 5000.00 %0 Nos: 2900.00

Cement for laying and 10.00 Cwt. 400.00 P.bag 4000.00


plastring.

Sand. 37.00 Cft. 2425.00 % Cft. 897.25


TOTAL 7797.25
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 779.73
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 8576.98
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________

Masons. 5.00 Nos: 450.00 P.day. 2250.00

Skilled Coolies. 5.00 Nos: 250.00 P.day. 1250.00

Bahishti. 0.50 Nos: 250.00 P.day. 125.00

Rs: 3625.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 362.50
_____________________________ ______ _____ ______ _______ _________
TOTAL 3987.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 398.75
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 43.86 4386.25
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12963.23
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Rft. Rs: 12963.23
Total material & labour for one Rft. Rs: 129.63
Total material & labour for one Rft. say Rs: 54.85
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.
27 Cleaning bricks dismantled from katcha pacca masonary.

_____ _____________________________ ______ _____ ______ _______ _________


(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Coolis. 1.75 Nos: 250.00 P.day. 437.50
_____________________________ ______ _____ ______ _______ _________
TOTAL Rs: 437.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 43.75
_____________________________ ______ _____ ______ _______ _________
TOTAL 481.25
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 48.13
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 529.38
_____________________________ ______ _____ ______ _______ _________
Labour rate for 1000 Nos: Rs: 211.75
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.
28. Scraping bricks dismantled from pacca masonary.

_____ _____________________________ ______ _____ ______ _______ _________


(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Coolis. 3.30 Nos: 250.00 P.day. 825.00
_____________________________ ______ _____ ______ _______ _________
TOTAL Rs: 825.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 82.50
_____________________________ ______ _____ ______ _______ _________
TOTAL 907.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 90.75
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 998.25
_____________________________ ______ _____ ______ _______ _________
Labour rate for 1000 Nos: Rs: 998.25

_____ _____________________________ ______ _____ ______ _______ _________

_____ _____________________________ ______ _____ ______ _______ _________


S/N D E S C R I P T I O N.

29 Supplying and filling sand under floor and plugging in walls.

_____ _____________________________ ______ _____ ______ _______ _________


(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pit Sand. 100 Cft. 900.00 % Cft. 900.00

_____________________________ ______ _____ ______ _______ _________


TOTAL 900.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 90.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 990.00
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________

Coolies. 0.50 Nos: 250.00 P.day. 125.00

_____________________________ ______ _____ ______ _______ _________


Rs: 125.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 12.50
_____________________________ ______ _____ ______ _______ _________
TOTAL 137.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 13.75
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 151.25
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 1141.25
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 203.50
_____ _____________________________ ______ _____ ______ _______ _________

You might also like