Professional Documents
Culture Documents
24-31 Brickwork Chapter-5
24-31 Brickwork Chapter-5
BRICK WORK.
Note:- 1. The rates are to be reduced Proportionately if II or III Class Bricks are used.
2. Rates for all finsihed works include the removal of surplus debries, un-used material and by-Products..
3. For handling all types of materials or short lead including Carriage upto 3 Chains, nothing, is to be paid as
extra. Where handling and Carrige involves an extra lead beyond 3 chains, Carriage for whole of the distance should be
provided in the Estimate.
4. Masonry of boundary wall to be considered as masonry other than buildings for items 1, 4, 5, 15, 20, 21
and 23.
5. The rate of lime mortar also includes grinding of mortar.
6. The rates include the cost of scaffolding and its removal.
Rate (Rs)
S.NO Description Unit Specification Remarks.
Labour Composite
1 2 3 4 5 6 7
1 Pacca brick work in mud mortar in 21.1-21.4 (I) The rate is to
building. be reduced
Proportionately.
(a) In foundation and plinth. % Cft. 1762.06 9379.56 If II or III Class
brick are used
(b) In ground floor. Do 2336.81 9954.31 (II) See Note
No.4
Page 23
Rate (Rs)
S.NO Description Unit Specification Remarks.
Labour Composite
1 2 3 4 5 6 7
(b) Cement sand mortar 1:3 Do 2324.21 4401.95
(c )Cement sand mortar 1:4 Do 2324.21 12501.41
(d) Cement sand mortar 1:5 Do 2324.21 12176.08
(e) Cement sand mortar 1:6 Do 2324.21 3865.15
(f) Cement sand mortar 1:7 Do 2324.21 3773.85
(g) Cement sand mortar 1:8 Do 2324.21 11631.03
(II) (a) lime cement sand mortar 1:1:6 % Cft. 2324.21 12457.41
(b) lime cement sand mortar 1:1:7 Do 2324.21 12249.96
(c ) lime cement sand mortar 1:1:8 Do 2324.21 3823.85
(d) lime cement sand mortar 1:1:9 Do 2324.21 3760.80
(e) lime cement sand mortar 1:1:10 Do 2324.21 3713.55
(III) Lime sand surkhi mortar 1:1:1 % Cft. 2324.21 3668.05
(IV)Lime sand mortar 1:2 Do 2324.21 3657.05
(V) (a) Lime surkhi mortar. 2:3 % Cft. 2324.21 12578.96
(b) Lime surkhi mortar. 1:2 Do 2324.21 3683.15
(c )Lime surkhi mortar. 1:3 Do 2324.21 3562.50
5 Pacca brick work in ground floor in: 21.1 I.the rate is to
be reduced
Proportionately
if Class bricks
are used.
Page 24
Rate (Rs)
S.NO Description Unit Specification Remarks.
Labour Composite
1 2 3 4 5 6 7
(III) Lime sand surki mortar. 1:1:1 % Cft. 3050.21 4029.30
(IV) Lime sand mortar. 1:2 Do 3050.21 4038.65
(V) (a) Lime Surhi mortar. 2:3 Do 3050.21 13304.96
(b) Lime surkhi mortar. 1:2 Do 3050.21 4064.30
(c) Lime surkhi mortar. 1:3 Do 3050.21 3943.65
6 Add extra labour in item No.5 for brick
work in:
(II) (a) Lime cement sand mortar. 1:1:6 % CFt. 2722.50 4215.75
(b) Lime cement sand mortar. 1:1:7 Do 2722.50 4122.90
(c ) Lime cement sand mortar. 1:1:8 Do 2722.50 4047.65
(d ) Lime cement sand mortar. 1:1:9 Do 2722.50 3984.65
(e) Lime cement sand mortar. 1:1:10 Do 2722.50 3937.40
Page 25
Rate (Rs)
S.NO Description Unit Specification Remarks.
Labour Composite
1 2 3 4 5 6 7
(IV) Lime sand mortar 1:2 Do 2722.50 4002.90
(V)(a) Lime Surkhi mortar. 2:3 Do 2722.50 3907.00
(b) Lime Surkhi mortar. 1:2 Do 2722.50 3907.00
(c) Lime Surkhi mortar. 1:3. Do 2722.50 3786.35
8 Add extra labour in item No.7 for every % Cft. 226.90
5 feet addl: height.
10 Extra for pacca brick in staining of % Cft. 680.63 516.60 21.1-21.4 The rate is to be
wells or any other circular masonry. reduced
Proportiontely
if II or III class
bricks are used.
(III) (a) Lime cement sand mortar 1:1:6 % Sft. 1527.63 1502.00
(b) Lime cement sand mortar 1:1:7 Do 1527.63 1478.55
(c ) Lime cement sand mortar 1:1:8 Do 1527.63 1461.15
(d) Lime cement sand mortar 1:1:9 Do 1527.63 1444.05
(e) Lime cement sand mortar 1:1:10 Do 1527.63 1433.90
(III) (a) Lime cement sand mortar 1:1:6 % Sft. 2299.00 2600.45
(b) Lime cement sand mortar 1:1:7 Do 2299.00 2552.95
(c ) Lime cement sand mortar 1:1:8 Do #VALUE! 2516.45
(d) Lime cement sand mortar 1:1:9 Do 2299.00 2484.90
(e) Lime cement sand mortar 1:1:10 Do 2299.00 2461.85
(IV) lime sand surkhi motar 1:1:1 % Sft. 2299.00 2439.10
(V) Lime sand mortar 1:2 % Sft. 2299.00 2432.70
(VI) (a) Lime surkhi mortar. 2:3 % Sft. 2299.00 2494.05
(b) Lime surkhi mortar. 1:2 % Sft. 2299.00 2446.70
(c ) Lime surkhi mortar. 1:3 % Sft. 2299.00 2385.75
18 Add extra labour in item No.17 for
Perforated Pacca brick work in:
(I) 4 1/2" thick walling with hoop iron % Sft. 1104.13 6392.61
bounding 6" apart.
(II) 4 1/2" thick walling with hoop iron Do 1104.13 5840.16 II See Note 4
bonding 12" apart.
21 Ghilafi work 1" to 1- 1/2" (thick wall). % Cft. 2350.43 2563.50 21.18 I The rate is to
be reduceds
Proportionately
if II or III Class
bricks are used.
(I) 3" thick drip course cornice. Per Rft. 15.58 16.05
(II) 4 1/2" thick cave brick with back Do 17.70 19.80
brick.
Page 29
Rate (Rs)
S.NO Description Unit Specification Remarks.
Labour Composite
1 2 3 4 5 6 7
(I) One brick. Per Rft. 17.70 14.25
(II) Two bricks Do 26.17 28.25
(III) Three bricks Do 34.88 41.15
(IV) four bricks Do 43.86 54.85
27 Cleaning bricks dismantled from kacha % Nos. 211.75 ___
pacca masonary.
Note:- The rates for brick work have been calculated for the standard size of bricks 9" x 4 1/2" x 3" brick used are 8"
x 4" x4" the corresponding rate may be increased by 5%.
Page 30
BIRCK MASONARY.
FIRST FILL THIS SHEET.
TOTAL 10435.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 1043.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 11478.50
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00
Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 13802.71
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 13802.71
S/N D E S C R I P T I O N.
TOTAL 9695.63
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 969.56
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 10665.19
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00
Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12989.40
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4401.95
S/N D E S C R I P T I O N.
TOTAL 9252.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 925.20
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 10177.20
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.00 Nos: 450.00 P.day. 900.00
Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12501.41
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 12501.41
S/N D E S C R I P T I O N.
Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries.
_____________________________ ______ _____ ______ %
10.00 _______ 192.08
_________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12457.41
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 12457.41
S/N D E S C R I P T I O N.
Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12086.49
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3823.85
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.
Rs: 1920.83
Sundries. 10.00% 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 11843.34
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3713.55
S/N D E S C R I P T I O N.
Rs: 1920.83
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12267.46
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3668.05
S/N D E S C R I P T I O N.
Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12578.96
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 12578.96
S/N D E S C R I P T I O N.
Rs: 1920.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 192.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2112.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 211.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2324.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12253.00
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3683.15
S/N D E S C R I P T I O N.
Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL 2772.92
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 3050.21
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 14528.71
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 14528.71
S/N D E S C R I P T I O N.
Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL
_____________________________ 2772.92
______ _____ ______ _______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B "
_____________________________ 3050.21
______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 13183.41
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4373.05
S/N D E S C R I P T I O N.
Rs: 2520.83
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 252.08
_____________________________ ______ _____ ______ _______ _________
TOTAL
_____________________________ ______ _____ ______ 2772.92
_______ _________
Contractor's profit 10.00 % 277.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B "
_____________________________ ______ _____ ______ 3050.21
_______ _________
TOTAL (MATERIAL + LABOUR) 12673.39
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4141.95
S/N D E S C R I P T I O N.
Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12648.26
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4122.90
S/N D E S C R I P T I O N.
Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12484.78
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 4047.65
S/N D E S C R I P T I O N.
TOTAL 8653.76
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 865.38
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 9519.13
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 2.50 Nos: 450.00 P.day. 1125.00
Rs: 2250.00
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12241.63
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3937.40
S/N D E S C R I P T I O N.
Rs: 2250.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 225.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2475.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2722.50
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12428.27
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 3859.20
S/N D E S C R I P T I O N.
S/N D E S C R I P T I O N.
10. Extra for pacca brick in staining of wells or any circular
masonary.
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 82 Nos: 5000.00 %0 Nos: 410.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 410.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 41.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 451.00
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 1.25 Nos:
P.day. 450.00 562.50
_____________________________ ______ _____ _______ _________
Rs: 562.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 56.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 618.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 61.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 680.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 1131.63
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 516.60
_____ _____________________________ ______ _____ ______ _______ _________
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.
11. Extra labour for profile and flared walls.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 0.43 Nos: 450.00 P.day. 193.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 19.35
_____________________________ ______ _____ ______ _______ _________
TOTAL 212.85
Contractor's profit 10.00 % 21.29
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 234.14
_____________________________ ______ _____ ______ _______ _________
Labour rate for 100 Cft. Rs: 140.50
_____ _____________________________ ______ _____ ______ _______ _________
12 Extra labour for pacca brick work in piers & abutments.
(i) From 10' to 20' Hieght.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 0.12 Nos: 450.00 P.day. 54.00
Skilled Coolies. 0.50 250.00 P.day. 125.00
_____________________________ ______ _____ ______ _______ _________
Rs: 179.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 17.90
_____________________________ ______ _____ ______ _______ _________
TOTAL 196.90
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 19.69
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 216.59
_____________________________ ______ _____ ______ _______ _________
Labour rate for 100 Cft. Rs: 216.59
_____ _____________________________ ______ _____ ______ _______ _________
12 Extra labour for pacca brick work in piers & abutments.
(ii) Above 20' Hieght.
_____ _____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 0.25 Nos: 450.00 P.day. 112.50
Skilled Coolies. 1.00 250.00 P.day. 250.00
_____________________________ ______ _____ ______ _______ _________
TOTAL Rs: 362.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 36.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 398.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 39.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 438.63
_____________________________ ______ _____ ______ _______ _________
Labour rate for 100 Cft. Rs: 226.90
_____ _____________________________ ______ _____ ______ _______ _________
Rs: 1262.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 126.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1388.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 138.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 1527.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 3975.07
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 1461.15
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.
TOTAL 4847.81
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 484.78
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 5332.59
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00
TOTAL 4373.40
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 437.34
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4810.74
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00
TOTAL 4230.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 423.05
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4653.54
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00
S/N D E S C R I P T I O N.
17. Perforated pacca brick walling 9" thick in ground floor.
(iii In lime cement sand mortar.
(a) 1:1:6
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Pacca brick 9" * 4-1/2"* 3" 675 Nos: 5000.00 %0 Nos: 3375.00
TOTAL 4437.40
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 443.74
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4881.14
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00
Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7110.59
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2484.90
S/N D E S C R I P T I O N.
TOTAL 4328.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 432.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4761.63
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00
TOTAL 4531.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 453.17
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 4984.92
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.90 Nos: 450.00 P.day. 855.00
S/N D E S C R I P T I O N.
Rs: 1900.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 190.00
_____________________________ ______ _____ ______ _______ _________
TOTAL 2090.00
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 209.00
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2299.00
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 7058.10
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 2385.75
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.
Rs: 2475.00
_____________________________ ______ _____ ______ _______ _________
Sundries. %
10.00 247.50
_____________________________ ______ _____ ______ _______ _________
TOTAL 2722.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 272.25
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 2994.75
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 17762.25
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Cft. Rs: 6928.35
S/N D E S C R I P T I O N.
19. Fire brick masonary in fire clay mortar.
(ii) Extra for every 5 feet additional hieght.
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 0.25 Nos: 450.00 P.day. 112.50
Skilled Coolies.
_____________________________ 1.00 Nos:
______ 250.00 P.day.
_____ ______ 250.00
_______ _________
Rs: 362.50
_____________________________ ______ _____ ______ _______ _________
Sundries.
_____________________________ 10.00
______ _____ ______ %
_______ 36.25
_________
TOTAL
_____________________________ ______ _____ ______ _______ _________398.75
Contractor's profit 10.00 % 39.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 438.63
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 226.90
_____ _____________________________ ______ _____ ______ _______ _________
20. Pacca brick walling laid in 1:3 cement sand mortar reinforced
with 1" wide 18 gauge hoop iron:-
(i) 4-1/2" thick walling with hoop iron bonding 6" apart.
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
For Masonary Work.
Masons. 1.00 Nos: 450.00 P.day. 450.00
20. Pacca brick walling laid in 1:3 cement sand mortar reinforced
with 1" wide 18 gauge hoop iron:-
(ii) 4-1/2" thick walling with hoop iron bonding 12" apart.
Rs: 912.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 91.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 1003.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit
_____________________________ 10.00
______ _____ ______ %
_______ 100.38
_________
TOTAL PART " B " 1104.13
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 5840.16
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 5840.16
S/N D E S C R I P T I O N.
20. Pacca brick walling laid in 1:3 cement sand mortar reinforced
with 1" wide 18 gauge hoop iron:-
(iii) 3" thick walling with hoop iron bonding 6" apart.
Rs: 705.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 70.50
_____________________________ ______ _____ ______ _______ _________
TOTAL 775.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 77.55
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 853.05
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 4848.35
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Sft. Rs: 4848.35
S/N D E S C R I P T I O N.
20. Pacca brick walling laid in 1:3 cement sand mortar reinforced
with 1" wide 18 gauge hoop iron:-
(iv) 3" thick walling with hoop iron bonding 12" apart.
S/N D E S C R I P T I O N.
25. Eave brick moulded, weathered and throated with back bricks or
drip course cornice in 1:3 cement mortar.
(i) 3" thick drip coarse cornice.
_____ _____________________________ ______ _____ ______ _______ _________
(A) MATERIAL QUANTITY RATE UNIT AMOUNT
Rs: Rs:
_____________________________ ______ _____ ______ _______ _________
Assume for 100 Rft.
Moulded bricks. 280 Nos: 4800.0 %0 Nos: 1344.00
(100*12*2/9 + 13)
Cement for laying and 1.50 Cwt. 400.00 P.bag 600.00
plastering.
Sand. 5.00 Cft. 2425.00 % Cft. 121.25
Deduct cost of ordinary 140.0 Nos: 5000.00 %0 Nos: -700.00
bricks. 280/2 =140 Nos:
25. Eave brick moulded, weathered and throated with back bricks or
drip course cornice in 1:3 cement mortar.
(ii) 4-1/2" thick drip coarse cornice.
TOTAL 1811.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 181.15
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 1992.65
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Masons. 2.00 Nos: 450.00 P.day. 900.00
25. Eave brick moulded, weathered and throated with back bricks or
drip course cornice in 1:3 cement mortar.
(iii 4-1/2" thick eave brick with back brick.
TOTAL 3311.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 331.15
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " A " 3642.65
_____________________________ ______ _____ ______ _______ _________
(B) LABOUR
_____________________________ ______ _____ ______ _______ _________
Rs: 2162.50
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 216.25
_____________________________ ______ _____ ______ _______ _________
TOTAL 2378.75
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 237.88
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 26.17 2616.63
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 6259.28
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Rft. Rs: 6259.28
Total material & labour for one Rft. Rs: 62.59
Total material & labour for one Rft. say Rs: 28.25
S/N D E S C R I P T I O N.
Rs: 3625.00
_____________________________ ______ _____ ______ _______ _________
Sundries. 10.00 % 362.50
_____________________________ ______ _____ ______ _______ _________
TOTAL 3987.50
_____________________________ ______ _____ ______ _______ _________
Contractor's profit 10.00 % 398.75
_____________________________ ______ _____ ______ _______ _________
TOTAL PART " B " 43.86 4386.25
_____________________________ ______ _____ ______ _______ _________
TOTAL (MATERIAL + LABOUR) 12963.23
_____________________________ ______ _____ ______ _______ _________
Total material & labour for 100 Rft. Rs: 12963.23
Total material & labour for one Rft. Rs: 129.63
Total material & labour for one Rft. say Rs: 54.85
_____ _____________________________ ______ _____ ______ _______ _________
S/N D E S C R I P T I O N.
27 Cleaning bricks dismantled from katcha pacca masonary.