Professional Documents
Culture Documents
Chapter 2
Chapter 2
CHAPTER 2
Introduction to Construction Cost
Construction costs form part of the overall costs incurred during
the development of a built asset such as a building. Very broadly, construction costs will
be those costs incurred by the actual construction works themselves, and on
some projects may be determined by the value of the contract with the main
contractor.
However, the construction contract may include costs that might not in
themselves be considered literal construction costs (hard costs), such
as fees, profits, overheads, and so on.
Many projects will also include costs that it is not possible to determine when
the construction contract is awarded (such as prime cost sums and provisional sums),
and there may be construction works that are awarded by the client outside of the main
contract (such as fitting out the interior, minor alterations to
the completed works, installation of equipment, and so on).
In addition, the contract is likely to allow for the contract sum to be adjusted as a
result, for example, of variations to the works, claims for loss and expense,
or fluctuations (a way of dealing with inflation on large projects that may last for several
years). It is because of these unknowns that clients are advised to hold a contingency.
The ability to quantify precise construction cost estimates is vital to projects of all
sizes. Construction costs constitute a significant portion of any project budget, and it is
only through close, ongoing collaboration with a contractor and cost estimator that
investors can receive a reliable initial cost estimate as well as revised estimates
throughout the various stages of project development.
Cost estimates are broken down into three categories that serve one of three
basic functions: design, bid, and control. To establish a project’s financing, you must start
with a design estimate or a bid estimate.
Romblon State University
COLLEGE OF ENGINEERING AND TECHNOLOGY
Department of Civil Engineering
Design Estimates
Bid Estimates
For the contractor, a bid estimate submitted to the owner either for
competitive bidding or negotiation consists of direct construction cost
including field supervision, plus a markup to cover general overhead and
profits. The direct cost of construction for bid estimates is usually derived
from a combination of the following approaches.
Subcontractor quotations
Quantity takeoffs
Construction procedures
Control Estimates
Cost estimation is vital to the success of any construction project, but if you fail to
utilize the correct type of cost estimates, your project could result in failure.
Preliminary Estimates
Depending upon the type of infrastructure, the estimation technique and units
may change.
For buildings: The rate per square foot/per cubic foot/per room/per
occupant is given
For Roads and Highways: The rate per Km is provided depending upon the
thickness of layers and the type of construction material.
For Irrigation channels: The cost per Km is given. It can also be based on a
per hectare basis (area irrigation by the canal/water channel).
This is followed by a detailed estimate that includes a list of all the construction
materials along with the specifications. The detailed BOQ (Bill of Quantities) can be
priced based on the cost of each line item including masonry estimate, concrete
estimate, etc. and the total budget amount for the construction can be estimated
precisely in this way. The quantity takeoff sheet can be priced easily by putting the unit
cost and most of the clients require such cost filled BOQ’s from contractors.
Before you create a work breakdown structure, it's essential to first assess the
project scope by talking to all stakeholders and key team members involved.
As the project manager, you want to ensure that all critical input and deliverables
are gathered and transparently prioritized. You may use Gantt charts, flow charts,
spreadsheets, or lists to show the hierarchical outline of importance and connectivity
between the tasks needed to complete the project.
After outlining the deliverables and tasks in order of completion, you can then
assign each task to a project team member. Ensure no team member carries the majority
of the project's weight by spreading duties and responsibilities across the team.
Each WBS level represents a new and increasingly detailed definition of work
needed to complete the project.
PMI's definition adds that a WBS structure must be constructed in a way that each
new level in the hierarchy includes all the work needed to complete its parent task. This
means that every parent task element must have more than one child task within it to
consider the parent task element complete.
Romblon State University
COLLEGE OF ENGINEERING AND TECHNOLOGY
Department of Civil Engineering
Work breakdown structure Gantt chart. You can structure your WBS as a Gantt
chart that represents both a spreadsheet and a timeline. With a Gantt chart-structured
WBS, you can link task dependencies and show project milestones.
As a project manager, you may have to experiment to see which WBS works best
for you and your team. The goal is to show the hierarchy of your projects and make
progress clear to everyone involved — whether they are a team member or an external
stakeholder.
CSI MasterFormat
This enables construction companies to know what to expect and how to prepare
a scene for purchased items.
Here’s an easy example of how this works. A builder knows when fitting a toilet
when making a bathroom from scratch, the water and drainage pipes need to be
distanced properly from the wall and from each other. Because of the MasterFormat,
toilet manufacturers have pre-built the toilet to accommodate the plumbing- where and
how the builders have prepared.
This coding system works as a middleman, helping one industry make things clear
for the other. The end result is faster and more error-free manufacturing, easier
engineering, and quicker building times for construction companies.
Romblon State University
COLLEGE OF ENGINEERING AND TECHNOLOGY
Department of Civil Engineering
Over the years, people within the building and construction manufacturing
industries have dubbed MasterFormat as “the Dewey Decimal System” of building and
construction. The CSI MasterFormat is a series of coding systems, broken down and
categorized by sections referred to as Divisions. More specifically, 50 Divisions in all to
date. Up until 2004, there were only 16 Divisions (more about the divisions below).
As aforementioned, several Divisions are not yet populated with any information.
They have been reserved for further expansion as different categories may arise. This is
CSI’s solution for preparing for the next wave of technological and material leaps.
Each Division contains a host of subgroups that fall under the Division’s subject. For
the sake of expedience, we’ll just stick to the overall coverage by only displaying top-
level Division titles.
widely used within the design and construction industry when estimating for Construction
Document design phases, as it aligns well with MasterFormat specification sections. On
the other hand, Uniformat-based estimating is often used in providing planning stage and
early design phase estimating, where take-off measurements do not readily allow
MasterFormat databases to be applied. In either case, the key to successful estimating is
whether accurate cost data is available (through databases or other sources) that
enable WBS quantities to be applied. Key also is whether WBS categories enable
effective cost management, associated with the ability to compare current estimate
breakdowns to previous estimate components—having lineage back to the project's
programmed budget.
Cost Planning
Cost planning is an imperative part of any construction project. During this process
we take into account current market rates and previously completed jobs and allows us
to calculate an accurate and realistic plan that is in line with your goals and budget. We
take a multi-disciplined approach to set lifecycle budgets and cost controls to manage
the quality and delivery of the project’s outcomes over a set timeframe. As a commercial
builder, we tender for many projects and this provides us with a mass of current market
data and knowledge, applicable to a wide range of projects.
Activity:
ESSAY.
1. How does construction cost estimate important in the start of the project?
Romblon State University
COLLEGE OF ENGINEERING AND TECHNOLOGY
Department of Civil Engineering