PENDING POINTS

AGENDA / MEETING
S.NO PHOTOGRAPH COMITEE DECISION RESPONSIBILITY TARGET DATE STATUS
POINTS

Fume extraction Dust fume extraction system is


1
system for CNC required Mr. Rajesh patil 30.10.2020 17.09.2020

1.Place identification for filled


cylinder with chain or belt
facility.
Use of Compressed 2.Arrangement of valve Mr. Abhishek Jain 07.09.2020
2 gas cylinder is in very protection cap, & 01.08.2020 (1st Point
unsafe manner 3.Arrangement of cylinder Mr.Abhineet done)
trolly.

Wire rope is not


3 To be anchored properly Mr.Abhineet 30.07.2020 07.09.2020
anchored properly

Socket to be provided where


Nacked wire used in needed, Mr.Abhineet
4
electrical supply board Users also have to take & Ongoing 09.09.2020
Mr. Nitin Upadhyay
initiative.
Mr Abhineet/ Mr
5 09.09.2020 Not Started
Uday

Electrical line to be
properly dress up & To be properly dress up & Mr Abhineet/ Mr
6 09.09.2020 Not Started
cover MCB in whole covered Uday
plant

Mr Abhineet/ Mr
7 09.09.2020 Not Started
Uday

Unwanted material Decision will be taken by Mr. Nitin Y/Mr


8 kept behind new GI
Plant Director Sir Hemraj
9
Unwanted material Decision will be taken by Mr. Nitin Y/Mr
kept in new GI plant Director Sir Hemraj

Unwanted material
10 kept behind new GI Decision will be taken by Mr. Nitin Y/Mr
Director Sir Hemraj
Plant

Unwanted material
11 kept near Fire hydrant Decision will be taken by Mr Abhishek
Director Sir Jain/Mr Hemraj
pump house

12 Mr Abhineet 15 Days

Electrical line to be
Electrical line to be
properly dress up & To be properly dress up &
13 Mr Abhineet 15 Days
cover MCB in whole covered
plant

14 Mr Abhineet 15 Days

15
Unused equipment Area identification required for Mr Abhineet/ Mr 07.09.2020
kept at shop floor spare equipments & parts Uday 17.09.2020

Electrical line to be
16
properly dress up & To be properly dress up Mr Abhineet
cover MCB in whole
plant
Electrical line to be
properly dress up &
17 To be properly dress up Mr Abhineet
cover MCB in whole
plant

Electrical line to be
18
properly dress up & To be properly dress up Mr Abhineet
cover MCB in whole
plant

19
Material segregation Decision will be taken by Mr. Gopal/Mr
required Director Sir Hemraj

Electrical line to be
20
properly dress up & To be dress up Mr. Nitin Y/Mr 15 days
fire extinguishers to Abhineet
be unobstructed
Electrcal lines to be
21
properly dress up To be dress up Mr Abhineet

Chemical storage area Decision will be taken by


22
to be saperate Director Sir Mr Dheeraj Gurbani

STP to be connected
23 with New plant overflow/
collection tank
Plan For October-2020

S.NO POINTS

1 Painting work required in both GI plant structure, EOT Cranes & stack platforms, due to
chemical fuems, it is get rusting.

2 All openings like earth pit chambers to be covered

3 Disposal or return of old/expired material (i.e. paint, hardner,chemicals etc.)

4 DG stack will be outside of building

5 Monkey ladder to be install in all areas of plant specially in new plant.

6 Safety rope line to be install in all bay for working at height ie. Maintanance work of EOT,
CCTV etc.

7 Installation of Fire alarm, Hand operated siren, Electrical siren & wind sock stand

8 Try to educate 100% Compney Employee & regular contaract labour on different topics
related to Safety.

9 Work Permit System to be impliment in the month

Equipment Identification no. to be displayed on each eq.


10 a) In first phase critical equipments like crane, pressure vessel, press m/c etc.
b) In second welding m/c, grinder, other power tools etc,
c) In third phase rest of all m/c.

Safety Committee Meeting:


11 1. On dated 10.10.2020
2. On dated 20.10.2020
Plant safety Inspection, Tool box talk, CRT :
12
Rendom, atleast twice in a month
13 Safety Audit:
Twice in a month cover different area