This document discusses several important cases related to contractual damages:
1. Robinson v Harman established the principle of restitutio in integrum, which aims to restore the innocent party to the position they would have been in if the contract was performed.
2. Ruxley Electronics held that expectation damages refer to the benefits the innocent party would have received from proper performance, while reliance damages cover out-of-pocket expenses incurred in reliance on the contract.
3. Payzu Ltd v Saunders established that the innocent party must take reasonable steps to mitigate their losses, and cannot recover damages that could have been avoided through mitigation.
4. Hadley v Baxendale laid out the test
This document discusses several important cases related to contractual damages:
1. Robinson v Harman established the principle of restitutio in integrum, which aims to restore the innocent party to the position they would have been in if the contract was performed.
2. Ruxley Electronics held that expectation damages refer to the benefits the innocent party would have received from proper performance, while reliance damages cover out-of-pocket expenses incurred in reliance on the contract.
3. Payzu Ltd v Saunders established that the innocent party must take reasonable steps to mitigate their losses, and cannot recover damages that could have been avoided through mitigation.
4. Hadley v Baxendale laid out the test
This document discusses several important cases related to contractual damages:
1. Robinson v Harman established the principle of restitutio in integrum, which aims to restore the innocent party to the position they would have been in if the contract was performed.
2. Ruxley Electronics held that expectation damages refer to the benefits the innocent party would have received from proper performance, while reliance damages cover out-of-pocket expenses incurred in reliance on the contract.
3. Payzu Ltd v Saunders established that the innocent party must take reasonable steps to mitigate their losses, and cannot recover damages that could have been avoided through mitigation.
4. Hadley v Baxendale laid out the test
Pennant Hills Restaurants v Barrell Insurances The judicial approach to assessment of
(1981) damages is to a great extent a pragmatic one.
In many cases, the amount awarded is “no more than an approximation lacking in mathematical precision or economic accuracy or sufficiency” Robinson v Harman (1848) 1 Exch 850 The basic principle of contractual damages is that of restitutio in integrum, or full restitution, which involves putting the innocent party into the position it would have been in had the contract been performed. This principle can be traced back to Robinson v Harman. As a general rule, “[w]here a party sustains a loss by reason of a breach of contract, he is, so far as money can do it, to be placed in the same situation as if the contract had been performed” Ruxley Electronics and Construction Ltd v The category of expectation interest refers to Forsyth [1996] those benefits which the innocent party would have received, had the contract been performed properly. For example, in Ruxley Electronics and Construction Ltd v Forsyth [1996] AC 344, the House of Lords held that where a pool had not been built to agreed specifications, the cost of the cure, i.e. the cost of rebuilding the pool was too high and, thus, the injured party could only claim damages for loss of amenity. Reliance interest refers to those losses which an innocent party incurred in out-of-pocket expenses ‘in reliance’ on the contract. Expenses incurred both before and after the contract are recoverable. The defendant was an actor who are agreed to appear in a production staged by the plaintiffs. The actor cancelled his participation and the television company had to abandon the production. The television company sued for expenses incurred both before and after the contract was signed. The court held in favour of the plaintiffs and established that both pre- contractual and post-contractual costs are recoverable so long as they were reasonably in the contemplation of the parties as likely to be wasted if the contract was broken. However, the court also held that there was no ‘double recovery’. This means that a plaintiff can either recover for lost profits or for expenses incurred, not for both. Payzu Ltd v Saunders, doing nothing may have an impact on the amount of damages that may be recovered. An injured party who does not take steps to minimise its losses cannot claim damages for losses that could have been avoided, had mitigation taken place. In Payzu Ltd v Saunders, the plaintiffs had failed to make prompt payment for an instalment of goods. The defendants had, in breach of contract, then refused to deliver unless the plaintiffs agreed to pay cash with each order. It was held that the plaintiffs should have accepted this offer, which would have reduced their loss (since the market value of the goods in question was rising above the contract price). British Westinghouse Electric and In this case, two important principles for Manufacturing Co Ltd v Underground Electric assessing damages were laid down, the Railways Co of London Ltd [1912] second of which speaks to mitigation: “The first is that, as far as possible, he who has proved a breach of a bargain to supply what he contracted to get is to be placed, as far as money can do it, in as good a situation as if the contract had been performed. The fundamental basis is thus compensation for pecuniary loss naturally flowing from the breach; but this first principle is qualified by a second, which imposes on a plaintiff the duty of taking all reasonable steps to mitigate the loss consequent on the breach, and debars him from claiming in respect of any part of the damage which is due to his neglect to take such steps.” The contract was for the sale of turbines. The defendants subsequently supplied turbines with less power than previously agreed. The plaintiffs accepted the deficient turbines but retained their right to claim for damages. They later replaced the deficient turbines with more powerful ones and claimed the cost of the replacement turbines as damages. However, the replacement turbines were more powerful than the turbines originally contracted for. The court held in favour of the defendants as the savings brought about by the replacement turbines exceeded their cost. The owners of a mill asked a common carrier to deliver a broken crankshaft to repairers by a certain date. The defendant carrier failed to deliver the crankshaft in time. In the meantime, the mill remained idle and the mill owners sued the carrier for all loss of profit during the period of delay caused by the carrier. The court found that a mill owner must be expected to have a spare crankshaft and therefore it was not necessarily the case that the mill had to remain idle. The court also found that the mill owner had not told the carrier that timing of was the essence as the mill would have to remain closed while the crankshaft was being repaired. The test of determining whether damage is too remote was laid down in the case of Hadley v Baxendale (1854) 156 ER 145. The applicable test is the test of foreseeability and contains two principles: (1) A party in breach of contract is liable for all loss which is likely to flow from the breach in the ordinary course of things. (In Hadley v Baxendale, no damages could be recovered under this principle, because a mill would usually have a spare shaft and would not usually have to be closed because a shaft was broken). (2) Where the loss is not an ordinary loss, as in the first principle, the party in
breach is liable for such a loss only if they
actually knew at the time of contracting what the consequences of a breach would be. (In Hadley v Baxendale, loss was not recoverable under the second principle because the carrier did not know that the mill did not have a spare shaft). Victoria Laundry v Newman Industries [1949] In Victoria Laundry v Newman Industries [1949], Victoria Laundry entered into a contract with Newman Industries to build two large boilers to replace the small boilers in the laundry. Newman Industries were delayed in delivering the replacement boilers. Victoria Laundry claimed damages under two heads. First, for the loss of profit the laundry would have made with the larger boilers, had they been delivered on time. This loss was recoverable under the first principle in Hadley v Baxendale. Secondly, the laundry had entered into a lucrative contract with a third party for dyeing, which could not be performed due to the delay. Thus, they also claimed for loss of profit owing to the lost contract. This is the kind of damage covered by the second principle in Hadley v Baxendale. However, since the Newman Industries did not know of the contract for the dyeing, they were not liable for the loss of contract. Dunlop Pneumatic Tyre Co Ltd v. New Garage In making its determination, the court looks at and Motor Co Ltd the particular circumstances of the case, whereby one of the defining tests is whether parties made a real, pre-breach attempt to estimate of the loss that could be suffered by the innocent party. However, if the clause in questions applies both to breaches with serious and minor consequences, it is assumed that it is a penalty clause. Flint v Brandon (1803) In Flint v Brandon (1803) the court established that specific performance is only available where the common law remedy of damages does not suffice: “This court does not profess to decree a specific performance of contracts of every description. It is only where the legal remedy is inadequate or defective that it becomes necessary for courts of equity to interfere”. Nutbrown v Thornton (1804) Nutbrown v Thornton (1804) concerned the sale of specialist machinery which was not available from other vendors. When the suppliers failed to deliver the machinery, the buyer tried to obtain them by way of specific performance. While the usual remedy for breach of contract is damages, this case demonstrates that where damages are not an adequate remedy, the courts may order specific performance.
Stickney v. Keeble [1915] As it is an equitable remedy, specific performance will only be
ordered in accordance with the rules of equity; it was held in Stickney v. Keeble [1915] that ‘equity will only grant specific performance if, under all the circumstances, it is just and equitable to do so’. Blackett v Bates (1865) "The court does not grant specific performance unless it can give full relief to both parties" per Lord Cranworth LC Patel v Ali [1984] Specific performance is not available where it would cause hardship to the defendant The plaintiff had contracted to sell her house to the defendant. Before the transaction could be completed, Mrs Patel, who was healthy at the time the contract was signed, was diagnosed with bone cancer and lost her leg. She became reliant on others and no longer wanted to move house. Mr Ali sought specific performance but failed as the court held that it would cause hardship on Mrs Patel if she was required to move. Co-operative Insurance Society Ltd v Argyll Specific performance is not awarded in Stores (Holdings) Ltd (1998)188 relation to contracts for personal service and those in which performance cannot be enforced without constant superintendence of the court. Facts: The plaintiffs were seeking specific performance of a covenant in a lease of retail premises to keep them open for business during particular hours. The defendants had closed the supermarket which had been run at the premises. The trial judge refused specific performance, but this ruling was overturned by the Court of Appeal. Held specific performance would not be ordered. In all but exceptional cases, an injunction would not be granted requiring a defendant to carry on a loss making business. Lumley v Wagner (1852) In Lumley v Wagner (1852), the defendant was engaged by the plaintiff to sing exclusively at a particular event. When she was offered more money by another party, the defendant broke the contract. The court issued an injunction prohibiting her from performing for other parties. Note that injunctions are usually not issued to compel personal performance (Page One Records v Britton [1968]). That is why Mrs Wagner was not compelled to perform for Mr Lumley, but merely prevented from performing for anyone else. Union Eagle Ltd v Golden Achievement Ltd The case of Union Eagle Ltd v Golden [1997] Achievement Ltd [1997] demonstrates that the courts will not exercise their equitable jurisdiction where the common law already provides for the outcome. Barclays Bank Plc v O’Brien [1993] A contract can be rescinded if agreement was reached under duress or undue influence Leaf v International Galleries [1950] Lapse of time may prevent rescission: The contract was for the sale and purchase of an oil painting of Salisbury Cathedral that was innocently represented as being a Constable. The buyer discovered that it was not a Constable when he tried to sell it five years later. His claim for rescission failed and he appealed. The Court of Appeal rejected his claim, holding that an action for damages would have been the appropriate action, and also that he had delayed too long for rescission. Cutter v Powell (1795) In Cutter v Powell (1795), a seaman’s wife was not able to recover part-payment of his wages after he died during a voyage. One particular aspect considered by the court was that the seaman had agreed to receive a higher sum than he might ordinarily have expected to be paid, on condition that the higher sum was payable at the end of the contract. From the employer’s perspective, it could be said that the employer agreed to pay a higher sum in order to guarantee that the contract is performed fully. Had there not been such an agreement on higher pay, the seaman’s wife could have recovered on a quanatum meruit of the voyage. Sumpter v Hedges [1898] In Sumpter v Hedges [1898], the plaintiff builder was unable to complete a contract to build two houses as he had run out of money. The defendant was able to complete the project with the help of another builder. In the event, materials which had been supplied by the plaintiff were later used by the replacement builder. It was held that Mr Sumpter was entitled to a refund of the cost of the materials, although he was not entitled to reclaim the cost of his labour Planche v Colburn (1831) A publisher hired an author to write one of a series of books on a theme.When the publisher decided to abandon the whole series, the author was prevented from completing the work through no fault of his own. He was entitled to recover a fee for his wasted work