KROTUS GROUP LIMITED UMA PROJECT

UMA MATERIAL SCHEDULE 04 Nov. 18, 2022


No MATERIAL UNIT QTTY COMMENT RATE TOTAL
SLAUGHTER HOUSE (+0 - +6,000)
1 Rebar T8 BS 500 Tonnes 6 SUPPLIED 2,915,000 17,490,001
2 Rebar T12 BS 500 Tonnes 8 SUPPLIED 2,860,000 22,880,000
3 Rebar T16 BS 500 Tonnes 9 SUPPLIED 2,860,000 25,740,000
4 Ballast m3 200 60,876 12,175,240
5 Marine boards Pcs 100 70,598 7,059,822
6 Sand m3 1,200 22,500 27,000,000
7 Cement Bags 5,400 PROVISIONAL 15,033 81,179,280
8 High speed doors 3,270 mm NO 8 REFER TO SCHEDULE
9 Steel Doors 1,500mm NO 3 REFER TO SCHEDULE
10 Steel Doors 2500mm NO 4 REFER TO SCHEDULE
11 Door frames 850mm NO 8 REFER TO SCHEDULE
12 Door frames 900mm NO 20 REFER TO SCHEDULE
13 Door frames 1,500mm NO 3 REFER TO SCHEDULE
14 Normal Windows NO 21 REFER TO SCHEDULE
15 Windows 600x600 mm NO 6 REFER TO SCHEDULE
16 Concrete blocks Pcs 60,000 2,242 134,520,000
17 Murram m3 2,000 SUPPLIED 37,595 75,190,000
18 Expansion Joint filler(bitumen ASED) LITRES 2,160 3,600 7,776,000
411,010,343
Total
OFFICE BUILDING (ROOF, TRUSS, PLASTER)
1 Timber 2x2 18ft treated PC 200
Timber 2x4 18ft treated PC 150
2 Wood Preservative LITRES 200 TO TREAT TIMBER ON SITE
3 Timber 2x6 18ft treated PC 200 24,480 4,896,056
4 Timber 1x10 18ft treated PC 20 FASCIA BOARD 18,626 372,526
5 Roofing sheet IT5/covermax 26G 4.8m PC 125 PROVISIONAL 33,010 4,126,238
6 Roofing Redge(cape 26G 3m) PC 55 PROVISIONAL 34,060 1,873,274
7 Roofing Valley 26G 3m PC 25 PROVISIONAL 34,060 851,488
8 Roofing nails KG 50 129,800 6,490,000
9 Normal nails 5" KG 100 225,540 22,554,048
10 Normal nails 6" KG 50 321,281 16,064,048
11 Steel Doors 1,500mm NO 2 REFER TO SCHEDULE
12 Steel Doors 900mm NO 1 REFER TO SCHEDULE
13 Door frames 850mm NO 4 REFER TO SCHEDULE
14 Door frames 900mm NO 11 REFER TO SCHEDULE
15 Door frames 1,500mm NO 2 REFER TO SCHEDULE
17 Normal Windows NO 21 REFER TO SCHEDULE
17 Windows 600x600 mm NO 6 REFER TO SCHEDULE
18 Cement Bags 200 15,033 3,006,640
19 Sand m3 60 22,500 1,350,000
61,584,318
Total
PLUMBING SLAUGHTER
1 PVC pipe 6" LESSO CLASS C PC 53 192,104 10,181,512
2 PVC pipe 4" LESSO CLASS C PC 25 CHANGES MADE ACCORDING TO 88,264 2,206,600
3 PVC pipe 3" LESSO CLASS C PC 20 UPDATED SERVICE DRAWINGS
4 PVC pipe 2" LESSO CLASS C PC 22 36,344 799,568
5 PVC TEE 6" PC 30 45,430 1,362,900
6 PVC ELBOW 6" 45* PC 20 32,450 649,000
7 PVC ELBOW 6" 90* PC 30 36,344 1,090,320
8 PVC TEE 4" PC 25 11,033 275,825
9 PVC ELBOW 4" 45* PC 30 8,437 253,110
10 PVC ELBOW 4" 90* PC 30 9,735 292,050
11 PVC TEE 2" PC 30 6,490 194,700
12 PVC ELBOW 2" 45* PC 20 5,841 116,820
13 PVC GLUE (TANGITE) kG 3 19,470 58,410
14 PVC ELBOW 2" 90* PC 30 5,841 175,230
15 Gate valve; 1/2' PC 1 12,980 12,980
16 Gate valve; 3/4' PC 1 19,470 19,470
17 IPS Elbow 1/2' PC 12 1,298 15,576
18 IPS TEE 1/2' PC 4 1,298 5,192
19 IPS Union1/2' PC 1 2,596 2,596
20 IPS R- SOCKET 1/2 -3/4' PC 2 1,947 3,894
21 Hand wash basin (40cm) NO 1 194,700 194,700
22 Nipple IPS 1/2' PC 10 1,298 12,980
23 PVC Reducing Bush 3' to 2' PC 10

17,923,433
Total
1 139.7X5mm CHS Grade S535 (@ 7,500mm) PC 340 PROVISIONAL
2 60.5X5 mm CHS Grade S535 (@ 7,500mm) PC 220 PROVISIONAL
3 Roofing sheet IT5/covermax 26G 3.0 m PC 750 PROVISIONAL 33,010 24,757,429
4 Welding Rods PC 3000
5 150X75X18 U-Channels (@ 7,500mm) PC 10,500
6 Tapping Screws kg 1,500

Total
Sum Total 515,275,522