SIte Daily Report 2018-10-11

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Sulut-3 Coal Fired Steam Power Plant (2x50MW)

SITE CONSTRUCTION DAILY REPORT (2018-10-11)


Weather :Clear  Cloudy □ Overcast□ Rainy□ Heavy Rain□ Temperature:26-34℃
Accumalative
Today Work Today Work Today Work Accumulative Tomorrow
No. Process Name Construction Area Total Quantity Compelete Remark
Items Planing Actual Completion Work Planning
Percentation
1 Site Construction
Continue
1.1 Excavation The whole plant 780,000 10,000 10,800 317,710 40.73% 10,000 m³
Excavation
Actual backfill Area 19,000
1.2 Backfill Coal Yard Continue Backfill 100,000 5,000 5,800 22,100 22.10% 5,000
m2
Drilling Holes Stopped
1.3 Drilling Holes SK 17 (Offshore) Drilling Holes 10 m 0m 45 m 0m Temporary because of
Changing Plan
2 Configure Equipment

Equipment Name Equipment Model Today Equip the Equipment Unit Tomorrow Equip the Equipment Remark
Excavator ACT 320 4 Set 4

1 Unit 330 Kobelco Excavator


Excavator 330 Kobelco 4 Set 4
is in Maintenance

Excavator 330 Hitachi 1 Set 1


Excavator Volvo 220 1 Set 1
2.1
Excavator Hitachi 210 2 Set 2
Excavator Sany SY365-H 1 Set 1
Excavator Komatsu PC200 2 Set 2
1 Unit Hitachi 200 Jack
Excavator Hitachi 200 Jack Hammer 1 Set 1 Hammer Excavator Arrived at
Site
2.2 Dump Truck 26 Set 26
Dozer D-85-SS 2 Set 2
2.3 2 Unit D-65-PX Dozer is in
Dozer D65PX 3 Set 3
Maintenance
2.4 Watering Truck 1 Set 1
2.5 Roller 2 Set 2
2.6 Drilling Machine 2 unit 2

3 Manpower

Company Name Position Today Total Person Unit Tomorrow Planning person Remark

Manager 49 Person 49 include local person


3.1 SINOHYDRO (Main Contractor)
labor 14 Person 14 local person

Manager 21 Person 21 include local person


3.2 CITY-KEY (Subcontractor)
labor 64 Person 64 local person

Manager 3 Person 3 local person


3.3 Soilens (Subcontractor)
labor 10 Person 10 local person

Total 161 Person 161 Chinese and local person

You might also like