Professional Documents
Culture Documents
Assignment Cons Econs 2
Assignment Cons Econs 2
AWARD OF MARKS
GROUP MEMBERS:
SECTION : 1
SEMESTER : SEM 1, 2020/2021
SUBJECT : CONSTRUCTION ECONOMICS 2
COURSE CODE : AQS 3130
To be filled by evaluator :
Score :
Remarks :
Introduction
Construction is a unique sector where each project has their own design, function,
administration and method of construction. It also an important industry for other industry
because they are linked and in need of each other. For example, the construction sector needs
materials from the manufacturing sector to build a building, while the manufacturing industry
players needs building to operate their business. Construction economic is a branch of
economic which concern to improve the quality of a product in term of efficiency,
effectiveness and economically (Ashworth, 2004). As mentioned, each construction project is
different and unique, which means the total cost would also be unique and different for each
project. Therefore, for each project there is a need for cost planning in order to make sure that
the funds provided are spend efficiently and accordingly. One of the outputs of cost planning
is a cost plan.
A cost plan is basically a plan where to allocate the money or funds according to the
needs of the construction project. For example, one of the ways a cost plan can be done is by
allocating sums of money by elements where the overall total would be the contract sum.
This cost plan is also known as an elemental cost plan. Consequently, for the purpose of this
assignment, we are to produce an elemental cost plan from a construction project that we
choose. The title of the project that we chose is Pembinaan Politeknik Besut, Terengganu
(Reka dan Bina) which is a two-storey bungalow construction project manage by the Public
Works Department (Jabatan Kerja Raya) and owned by the Ministry of Higher Education
(Kementerian Pengajian Tinggi). The architect and main contractor for this project is Arkitek
Aliran Cipta Sdn. Bhd. and Black Fox Engineering Sdn. Bhd. respectively.
PAGE 1
Cost Plan Bungalow Quarters Polytechnic Besut, Terengganu
PAGE 2
Specification of Element
ELEMENT SPECIFICATION
1 Substructure
1A Work Below Lowest Floor Finish Reinforced vibrated concrete bed, pile cap, column stump, ground beam, and
slab
2 Superstructure
2A Frame Reinforced vibrated concrete column and beams
2B Roof Reinforced concrete flat roofs with waterproofing membrane and corrugated
sheet roofing complete with all rainwater goods, lipped channel purlin
2C External Walls Generally 114mm thick concrete brick wall with brick reinforcement
2D External Windows & Doors Aluminium Multi Sliding Door 4 Panel and 2 Panel, Timber Solid Wood Door 6
Panel and 5 Panel and External Windows generally aluminum window; top
hung windows with multiple panel, fixed window with multiple panel
2E Internal Walls & Partitions Generally, 114mm thick concrete block with brick reinforcement
2F Internal Doors 5 Panel Timber Solid Wooden Door , PVC Folding Door, PVC Door
3 Finishes
3A Internal Wall Finishes Generally, 20mm thick plastered and painted on walls; Ceramic tiles on
bathroom walls
3B Internal Floor Finishes Generally ceramic tiles with 200mm skirting to floor level
3C Internal Ceiling Finishes Generally, skim coat and plain fibrous plaster, 600mm x 600mm x 9.5mm
suspended gypsum board for suspended ceilings
3D External Finishes Generally, 20mm thick plastered and painted on walls; skim coat and plain
fibrous plaster for ceilings, homogeneous tiles
4 Services
4A Sanitary Appliances Vanity basin, pedestal water closet, double bowl with double drainer sink,
floor trap, water tap and shower head
4B Plumbing Installation Authority approved 528 Gallon PE water storage tank and cold water
installation. uPVC pipes for internal soil pipes
PAGE 3
Calculation For Tender Price Index
PAGE 4
SUBSTRUCTURE
1) Proposed GIFA
Proposed Index
EUR = Existing Cost x =
Existing Index
570.42
= RM 93.87 x =
244.68
= RM 218.84
= RM 218.84 x 290.71 m2 =
= RM 63,618.45
PAGE 5
SUPERSTRUCTURE
2A Frame
Existing Project refer to ECA 4 (Page 41)
Element Cost = Proposed GIFA x cost per m2 existing project x price index 2020
price index 2012
= 290.71 x RM 120.43 x 570.42
420.49
= RM 47,493.29
2B Roof
Existing Project refer to ECA 5 (Page 47)
2C External Walls
Existing Project refer to ECA 4 (Page 41)
1) Proposed Area
Length Height
Ground Floor = 56.17m x 3.60m = 202.21 m2
First Floor = 55.69m x 3.00m = 167.07 m2
Total Area = 369.28
Proposed Index
EUR = Existing Cost x
Existing Index
570.42
= RM 30.26 x
420.49
= RM 41.05
PAGE 6
3) Total Elemental Cost
= RM 12,127.03
SD1 Aluminium Multi Sliding Door 4 Panel 3 nos xRM 6,048.00 = RM 18,144.00
SD2 Aluminium Multi Sliding Door 2 Panel 1 nos xRM 3,816.00 = RM 3,816.00
D1 6 Panel Timber Solid Wood Door 1 nos xRM 508.00 = RM 508.00
D3 5 Panel Timber Solid Wood Door 1 nos xRM 440.00 = RM 440.00
Build Up Rate
Note: Aluminium Multi Sliding Door 4 panel price (RM6048.00) includes delivery, installation and all necessary required.
Note: Aluminium Multi Sliding Door 2 panel price (RM3816.00) includes delivery, installation and all necessary required.
PAGE 7
Note: Solid Wood Door (6 panel) price (RM 350.00) includes all the necessary ironmongeries (exclude lock set) and
painting or finishings required.
Note: Solid Wood Door (5 panel) price (RM 282.00) includes all the necessary ironmongeries (exclude lock set) and
painting or finishings required.
EXTERNAL WINDOWS
W1 2 panel top hung with 1 panel fixed window 6 nos xRM 443.00 = RM 2,658.00
W2 2 panel top hung with 2 panel fixed window 5 nos xRM 501.00 = RM 2,505.00
W3 2 panel top hung window 6 nos xRM 364.00 = RM 2,184.00
W3a1 panel top hung window 1 nos xRM 246.00 = RM 246.00
W4 7 panel fixed corner window 2 nos xRM 5,170.00 = RM 10,340.00
W5 2 panel top hung with 1 panel narrow fixed window 2 nos xRM 465.00 = RM 930.00
W6 3 panel narrow fixed aluminium window 1 nos xRM 435.00 = RM 435.00
W7 Combination narrow fixed window with top hung panel 1 nos xRM 5,750.00 = RM 5,750.00
at center
W8 Combination fixed window with side top hung panel 1 nos xRM 5,420.00 = RM 5,420.00
Build Up Rate
Note: 2 panel top hung with 1 panel fixed window price (RM 368.00) includes all the necessary fixings or finishings
required.
PAGE 8
2) 2 panel top hung with 2 panel fixed window (W2)
2 panel top hung with 2 panel fixed window = RM 426.00
Transportation fee = RM 20.00
Installation Fee = RM 55.00
Note: 2 panel top hung with 2 panel fixed window price (RM 426.00) includes all the necessary fixings or finishings
required.
Note: Top hung window (2 panel) price (RM 296.00) includes all the necessary fixings or finishings required.
Note: Top hung window (1 panel) price (RM 178.00) includes all the necessary fixings or finishings required.
Note: 7 panel fixed corner window price (RM5170.00) includes delivery, installation and all necessary required.
PAGE 9
Note: 2 panel top hung with 1 panel narrow fixed window price (RM 390.00) includes all the necessary fixings or
finishings required.
Note: Narrow fixed aluminium window (3 panel) price (RM 360.00) includes all the necessary fixings or finishings
required.
8) Combination narrow fixed window with top hung panel at center (W7)
W7 = 1400mm (width) x 3855mm (height) (7 panel)
Combination narrow fixed window with top hung panel at center = RM 5,750.00
Note: Combination narrow fixed window with top hung panel at center price (RM5750.00) includes delivery, installation
and all necessary required.
Combination fixed window with side top hung panel (9 panel) = RM 5,420.00
Note: Combination fixed window with side top hung 9 panel price (RM5420.00) includes delivery, installation and all
necessary required.
TOTAL COST ELEMENT = COST FOR EXTERNAL DOORS + COST FOR EXTERNAL WINDOWS
= RM 22,908.00 + RM30,468.00
= RM 53,376.00
PAGE 10
2) Wall between Wet Kitchen & Bath 1
Wall Area =( 1.15 x 1.51 )x 3.45 = 9.18 m2
Deduct = D4a
= 0.82 x 2.45 = 2.01 m2
Net wall area = 9.18 - 2.01 = 7.17 m2
PAGE 11
FIRST FLOOR
1) Wall between Bedroom 4, Bedroom 5 & Bath 4
Wall Area = (2.386 + 4.57 + 3.785 + 3.15 + 1.55) x 3.45
= 53.27 m2
Deduct =[( D4 + D3 )]x 2
= ((0.845 x 2.45) + (1.00 x 2.45)) x 2
= 9.04 m2
Net wall area = 53.27 - 9.04 = 44.23 m2
2. APPROXIMATE QUANTITIES
Cost of element = Total wall area x Element Unit Rate of Existing Project (year 2012) x (TPI 2020/ TPI 2012)
= 227.32 x RM 68.35 x( 570.418 / 420.490 )
= RM 21,077.24
2F Internal Doors
D3 5 Panel Timber Solid Wood Door 7 No. x RM440.00 = RM3,080.00
D4 PVC Folding Door 3 No. x RM209.90 = RM629.70
D4a PVC Door 5 No. x RM195.00 = RM975.00
Build Up Rate
Note: Solid Wood Door (5 panel) price (RM 282.00) includes all the necessary ironmongeries
(exclude lock set) and painting or finishings required.
PAGE 12
2) PVC Folding Door
Note: PVC Folding Door price (RM 99.90) includes all the necessary fittings required.
3) PVC Door
Note: PVC Door price (RM 85.00) includes all the necessary fittings required.
PAGE 13
FINISHES
3A Internal Wall Finishes
Existing project refer to ECA 2 (Page 33)
PAGE 14
Guest bath = 3.044 + 1.35 + 3.044 + 1.35 = 8.79
Deduct = Guest bath - D4a - W3
= 8.79 - 0.82 - 0.65 = 7.318
WALL AREA = 7.318 x 3.05 = 22.32 m2
WALL AREA FOR = 45.66 + 45.08 + 66.74 + 23.12 + 40.68 + 13.94 + 22.32
GROUNDFLOOR + 19.37 = 276.90 m2
FIRST FLOOR
Family = 3.15 + 3.7 + 3.954 + 1.877 + 1.546 + 1.877 + 1.306
1.35 + 1.306 + 2.305 = 22.371 m
Deduct = Family - SD1 - D3 - D3 - D3 - D4a
- D3
= 22.371 - 2.6 - 1.0 - 1.0 - 1.0 - 0.82
- 1.0 = 14.95
WALL AREA = 14.95 x 2.95 = 44.11 m2
PAGE 15
Bedroom 5 = 2.85 + 4.714 + 2.85 + 4.714 = 15.128
Deduct = Bed. 5 - D3 - D4 - W2
= 15.128 - 1.0 - 0.845 - 1.5 = 11.78
WALL AREA = 11.78 x 2.95 = 34.76 m2
WALL AREA FOR = 44.11 + 45.09 + 32.58 + 36.94 + 34.76 + 30.05 + 20.81
FIRST FLOOR + 20.24 = 264.57 m2
TOTAL WALL AREA = WALL AREA GROUND FLOOR + WALL AREA FIRST FLOOR
= 276.90 + 264.57 = 541.48 m2
2. APPROXIMATE QUANTITIES
Cost of element = Total wall area x Element Unit Rate of Existing Project (year 1997) x (TPI 2020/ TPI 1997)
= 237.86 x RM 20.18 x( 570.4180 / 217.207 )
= RM 12,605.55
1) Proposed Area
Tile
Ground Floor, GF = 143.8 m2
First Floor, FF = 146.91 m2
PAGE 16
Skirting
Ground Floor, GF
Living = 13.235
Dining = 13.067
Kitchen + Breakfast = 19.3
Utility = 6.7
Guest Room = 11.8
Powder Room = 4.57
Guest Bath = 7.318
Bath 1 = 6.352
First Floor, FF
Family Area = 14.95
Master Bedroom = 15.3
Bedroom 3 = 11.05
Bedroom 4 = 12.52
Bedroom 5 = 11.78
Master Bathroom = 10.185
Bath 3 = 7.055
Bath 4 = 6.86
Total = GF + FF + Skirting =
= 143.8 + 146.91 + 34.4084 =
= 325.12 m2
Proposed Index
EUR = Existing Cost x =
Existing Index
570.42
= RM 56.76 x =
217.21
= RM 149.06
PAGE 17
3C Internal Ceiling Finishes
Existing Project refer to ECA 3 (Page 37)
GROUND FLOOR
Living Hall = 27.98 m2
Dining = 21.75 m2
Wet Kitchen = 10.86 m2
Dry Kitchen = 10.10 m2
Utility Room = 6.00 m2
Bath 1 = 3.51 m2
Bath 2 = 4.75 m2
Guest Room = 17.19 m2
Breakfast = 9.13 m2
Powder Room = 2.64 m2
FIRST FLOOR
Family Area = 21.75 m2
Master Bedroom = 28.19 m2
Bedroom 3 = 17.19 m2
Bedroom 4 = 14.41 m2
Bedroom 5 = 14.14 m2
Bath 3 = 4.75 m2
Bath 4 = 6.00 m2
Master Bathroom = 7.27 m2
Staircase = 10.25 m2
TOTAL INTERNAL CEILING AREA = AREA FOR GROUND FLOOR + AREA FOR FIRST FLOOR
= 113.91 + 123.95
= 237.86 m2
2. APPROXIMATE QUANTITIES
Cost of element = Total ceiling area x Element Unit Rate of Existing Project (year 1997) x (TPI 2020/ TPI 1997)
= 237.86 x RM 16.53 x 570.42
217.21
= RM 10,325.56
PAGE 18
3D External Finishes
Existing Project refer to ECA 2 (Page 33)
1) Proposed Area
Length Height
Ground Floor = 56.17m x 3.60m = 202.21 m2
First Floor = 55.69m x 3.00m = 167.07 m2
Total Area = 369.28
First Floor
Balcony 1 = 2.34 m2
Balcony 2 = 5.19 m2
Passage = 6.18 m2
Total = 13.71 m2
Proposed Index
EUR = Existing Cost x
Existing Index
570.42
= RM 17.40 x
217.207
= RM 45.70
PAGE 19
3) Total Elemental Cost
Proposed External
TOS = EUR x
Finishes Area
= RM 45.70 x 382.63 =
= RM 17,484.14
PAGE 20
SERVICES
4A Sanitary Appliances
Existing project refer to ECA 2 (Page 33)
Cost of element = Existing Cost per m2 x Proposed GIFA x (Proposed TPI/Existing TPI)
= RM 12.74 x 290.71 x( 570.418 / 217.207 )
= RM 9,726.32
4B Plumbing Installation
Existing project refer to ECA 2 (Page 33)
1) Proposed GIFA
2) Proposed Cost
Proposed Index
PC = Existing Cost x =
Existing Index
570.42
= RM 3,413.20 x =
217.21
= RM 8,963.48
Proposed GIFA
TOS = PC x =
Existing GIFA
290.71
= RM 8,963.48 x =
159
= RM 16,388.51
PAGE 21
4C Air Conditioning & Ventilation System
Not Applicable
4D Electrical Installation
Existing Project refer to ECA 2 (Page 33)
Proposed
Updated Existing
x 5% increase in quality x Proposed GIFA / Existing GIFA Element
EC
= Cost
RM 4,160.61 x 105% x 290.71 / 109.00 = RM 11,651.44
Not Applicable
Not Applicable
PAGE 22
EXTERNAL WORKS
5A Site Work
Existing Project refer to ECA 4 (Page 41)
Element Cost = Proposed GIFA x cost per m2 existing project (2012) x price index 2020
price index 2012
= 290.71 x RM 315.02 x 570.42
420.49
= RM 124,233.06
5B Drainage
Existing Project refer to ECA 1 (Page 29)
5C External Services
Existing Project refer to ECA 1 (Page 29)
Cost element = Total cost of existing project x (proposed TPI / existing TPI)
= RM 2,928.95 x ( 570.418 / 203.469 ) = RM 8,211.189
5D Ancillary Building
Not Applicable
PAGE 23
Conclusion
As a conclusion, we have managed to study and discuss the preparation of the Elemental
Cost Plan which is part of construction economic. One of the importance of the cost planning
is to allow comparisons of cost data with other different projects. This Elemental Cost Planning
also can involve in examining the cost implications of various design solutions. In this
assignment, we managed to get a projects’ drawing which is Pembinaan Politeknik Besut,
Terengganu (Reka dan Bina) which is a two-storey bungalow construction project to produce
an Elemental Cost Plan. Since Elemental Cost Plan relies upon the Elemental Cost Analysis
(ECA) for buildings, we also collected a few ECA which allows costs to be compared on a
common format and forms the basis of the benchmarking analysis.
Cost analysis are often used in the preparation of cost planning. The costs will need to
be adjusted to take into account and the various design factors such as size, shape and height
also need to be taken into considerations. The principle of analysis also needs to be applied for
the whole process in preparing the Elemental Cost Plan where the historic data that being used
need to be updated. Besides, it will be necessary to ensure that the elemental costs are realistic
and achievable in the construction industry.
PAGE 24
References
Ashworth, A. (2004). Cost Studies of Buildings 4th Edition. England: Pearson Education
Limited.
PAGE 25
APPENDICES
PAGE 26
ELEMENTAL COST ANALYSIS 1 :
PAGE 27 - 30
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
ELEMENTAL COST ANALYSIS 2 :
PAGE 31 – 34
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
ELEMENTAL COST ANALYSIS 3 :
PAGE 35 - 38
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
ELEMENTAL COST ANALYSIS 4 :
BUNGALOW 2012
PAGE 39 – 44
ELEMENTAL COST ANALYSIS - Form 1
Submitted by Muhammad Faauwaz bin Idris SBEQ 2009/2010
8-Residential Buildings
A - 2- 858
JOB TITLE : Rumah banglo CLIENT : Private
LOCATION : No 8, Jalan 14/3, Taman Tun Abdul Razak Mukim Ulu Kelang TENDER DATE : 20 March 2012
Daerah Gombak, Selangor Darul Ehsan
INFORMATION TOTAL PROJECT
Project and Contract Information
Type of Contract : PAM Contract 2006 with quantities Cost Fluctuation : Yes RM Int (Jv)/L
No
Basis of Tender Open/Selected L
Bills of Quantities Competition Government
L
Bills of Appr. Quant. Negotiated Private
L
Sched. of Rates/ Serials Provisional Sum RM 320,000.00
Spec. & Drawings L
Prime Cost Sum RM 1,046,535.00
Contract Period Stip. by Client : 12 Weeks L
Preliminaries RM 298,310.00
Contract Period Offered by Buliders : 12 Weeks L
Contingencies RM 100,000.00
Number of Tenders Issued : 5
Contract Sum RM 4,358,000.00
Number of Tenders Received : 5 1,306,101.96 L
3 Finishes
3A Internal Wall Finishes 126,168.00 126,168.00 147.05 2,320 M2 54.38 2.704
3B Internal Floor Finishes 233,612.00 233,612.00 272.28 1,114 M2 209.71 1.298
3C Internal Ceiling Finishes 123,216.00 123,216.00 143.61 481 M2 256.17 0.561
3D External Finishes 168,381.00 168,381.00 196.25 516 M2 326.32 0.601
22,653 535.00
15,021 514
52,147 1,056
5,814 413
367 42
1,052 121
400 40
4,846 14
575 35
4358 191
ELEMENTAL COST ANALYSIS - Form 2
3 Finishes
3A Internal Wall Finishes 123,139.97 126,168.00 147.05 2,320 M2
3B Internal Floor Finishes 228,005.31 233,612.00 272.28 1,114 M2
3C Internal Ceiling Finishes 120,258.82 123,216.00 143.61 481 M2
3D External Finishes 164,339.86 168,381.00 196.25 516 M2
OFFICE 1999
PAGE 45 - 48
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
TENDER PRICE INDEX
PAGE 49 - 50
ANGKATUNJUK HARGA TENDER DAN FAKTOR LOKALITI BAGI KOS BINAAN BANGUNAN PROJEK JKR DI MALAYSIA
FAKTOR LOKALITI
ANGKATUNJUK KAWASAN
BIL TEMPOH A B C D E F
HARGA TENDER
(Perlis, Kedah, (Perak) (Selangor, W.P.KL, (Johor) (Pahang) (Terengganu, Kelantan)
P.Pinang) N.Sembilan, Melaka)
1 1/2000 258.42 1.1167 1.0672 1.0000 1.0918 1.0575 1.0477
2 2/2000 258.28 1.1167 1.0672 1.0000 1.0918 1.0575 1.0477
3 1/2001 258.65 1.1114 1.0671 1.0000 1.0908 1.0570 1.0469
4 2/2001 261.25 1.1114 1.0671 1.0000 1.0908 1.0570 1.0469
5 1/2002 252.72 1.1129 1.0701 1.0000 1.0842 1.0559 1.0480
6 2/2002 250.65 1.1129 1.0701 1.0000 1.0842 1.0559 1.0480
7 1/2003 249.97 1.1134 1.0652 1.0000 1.0811 1.0582 1.0580
8 2/2003 246.81 1.1134 1.0652 1.0000 1.0811 1.0582 1.0580
9 1/2004 243.69 1.1127 1.0693 1.0000 1.0796 1.0491 1.0574
10 2/2004 288.59 1.1127 1.0693 1.0000 1.0796 1.0491 1.0574
11 1/2005 312.09 1.1038 1.0603 1.0000 1.0793 1.0569 1.0552
12 2/2005 312.56 1.1038 1.0603 1.0000 1.0793 1.0569 1.0552
13 1/2006 393.64 1.1010 1.0489 1.0000 1.0637 1.0450 1.0412
14 2/2006 412.62 1.1010 1.0489 1.0000 1.0637 1.0450 1.0412
15 1/2007 415.44 1.1101 1.0529 1.0000 1.0589 1.0462 1.0373
16 2/2007 426.13 1.1101 1.0529 1.0000 1.0589 1.0462 1.0373
17 1/2008 441.68 1.1078 1.0610 1.0000 1.0517 1.0442 1.0384
18 2/2008 458.76 1.1078 1.0610 1.0000 1.0517 1.0442 1.0384
19 1/2009 427.14 1.0816 1.0466 1.0000 1.0567 1.0438 1.0417
20 2/2009 491.96 1.0823 1.0466 1.0000 1.0567 1.0438 1.0433
21 1/2010 410.18 1.0823 1.0309 1.0000 1.0547 1.0444 1.0507
22 2/2010 398.59 1.0820 1.0302 1.0000 1.0545 1.0441 1.0502
23 1/2011 408.49 1.0818 1.0302 1.0000 1.0545 1.0441 1.0502
24 2/2011 411.36 1.0818 1.0255 1.0000 1.0545 1.0441 1.0502
25 1/2012 420.49 1.1302 1.0249 1.0000 0.9105 0.9555 0.9484
26 2/2012 429.32 1.1307 1.0249 1.0000 0.9105 0.9554 0.9484
27 1/2013 415.24 1.1307 1.0249 1.0000 0.9105 0.9558 0.9484
28 2/2013 437.35 1.1307 1.0249 1.0000 0.9105 0.9566 0.9484
29 1/2014 446.03 1.1307 1.0249 1.0000 0.9105 0.9566 0.9484
30 2/2014 453.99 1.1307 1.0249 1.0000 0.9080 0.9566 0.9484
31 1/2015 461.82 1.1307 1.0249 1.0000 0.9080 0.9566 0.9484
32 2/2015 469.54 1.1307 1.0249 1.0000 0.9080 0.9566 0.9484
33 1/2016 477.15 1.1305 1.0284 1.0000 0.9068 0.9554 0.9439
34 2/2016 484.69 1.1305 1.0284 1.0000 0.9068 0.9544 0.9439
35 1/2017 491.96 1.0841 1.0452 1.0000 1.0403 1.0482 1.0324
Penafian : Kerajaan Malaysia dan JKR tidak bertanggungjawab terhadap sebarang kehilangan atau kerosakan yang dialami kerana menggunakan maklumat di atas. Mana-mana
pihak tidak boleh menggunakan maklumat di atas untuk menyimpang daripada terma-terma kontrak apabila membuat tuntutan terhadap pihak Kerajaan maupun terhadap mana-
mana pihak.
NOTA : Data bagi Sabah dan Sarawak akan dimasukkan setelah diperolehi.
Source: https://www.data.gov.my/data/ms_MY/dataset/angka-tunjuk-harga-tender-dan-faktor-lokaliti-bagi-kos-binaan-bangunan-projek-jkr-di-malaysia/resource/65ee39d2-
b00a-4ad2-af7f-1b4701d33025
A/1
DRAWING 1 :
PAGE 51 – 52
HAK CIPTA TERPELIHARA
B B
RWDP RWDP
DRY RWDP
RWDP RWDP
YARD RWDP
1.28 SQM
W1 F2 A/C
C1
W1 F2
LEDGE BEDROOM 4
C1 14.41 SQM
BATH 4
\\Prodanaserver\drawings\PWCE - DWG - 2017\1710 - POLITEKNIK BESUT\3. MECHANICAL\REV04\XREF\Logo KPT - Font Putih.jpg
6.00 SQM
WET UTILITY W1 F2
BATH 1 C2
RWDP RWDP 3.51 SQM
W4 F2
KITCHEN 6.00 SQM
RWDP RWDP W4 F2
10.86 SQM
W1 F2 W1 F2
C1 C1
GUEST ROOM BEDROOM 3
17.19 SQM DRY KITCHEN BREAKFAST
17.19 SQM
BEDROOM 5
10.10 SQM W1 F2
9.13 SQM 14.14 SQM
C2
W1 F2 W1 F2
C1 C2
A
4.75 SQM C2
4.75 SQM ARKITEK ALIRANCIPTA SDN. BHD.
A W4 F2
C1
A A
W1 F2 FAMILY BALCONY 1
C1 21.75 SQM 2.34 SQM
DINING W1 F2
21.75 SQM TERRACE 1 C2
2.19 SQM
MASTER BEDROOM
TERRACE 2
LIVING UP 28.19 SQM DN
27.98 SQM W1 F2
1.57 SQM POWDER ROOM C2
2.64 SQM
W1 F2 MASTER BATHROOM
7.27 SQM
C1 W4 F2
C1 W4 F2
C2
STORE
shoes planter
box
wardrobe
PERUNDING IKATAN
ENTRANCE 20.50 SQM
FOYER
6.99 SQM
LAID TO FALL
BALCONY 2
5.19 SQM
B B
PROJEK :
QUARTERS - BANGLO
QUARTERS - BANGLO
FIRST FLOOR PLAN
GROUND FLOOR PLAN
PINDAAN
DRAWING 2 :
PAGE 53 - 54
HAK CIPTA TERPELIHARA
RWDP RWDP
RWDP
RWDP RWDP
DINING GUEST BATH
ARKITEK ALIRANCIPTA SDN. BHD.
FALL 3° FALL 3°
A A PERUNDING IKATAN
SECTION A-A
PRODANA WAWASAN CONSULTING ENGINEERS SDN BHD
(734708-W)
No 12-2 Jalan Opera C U2/C, Taman TTDI Jaya,
40150 Shah Alam, Selangor Darul Ehsan
Tel : 03-78457845 Fax : 03-78457847
R.C. FLAT ROOF YONG DAN MOHAMAD FAIZ SDN BHD (13239-K)
QUANTITY SURVEYORS AND CONSTRUCTION COST
CONSULTANT
LAID TO FALL
No 18,-1, Jalan pjs 8/12, Dataran Mentari, 46150 Petaling Jaya,
FALL 3° Selangor Darul Ehsan.
Tel ; 03 5632 9999 Fax : 03 5636 3723 / 03 5636 7723
RWDP
RWDP
LAID TO FALL
RWDP RWDP
PROJEK :
B
DINING GUEST BATH
QUARTERS - BANGLO
ROOF PLAN
SECTION A-A
PINDAAN
DRAWING 3 :
PAGE 55 - 56
HAK CIPTA TERPELIHARA
FRONT ELEVATION
RIGHT ELEVATION
PERUNDING IKATAN
PROJEK :